Dowel-Bar Retrofit Using Polyester Polymer Concrete



Similar documents
September 1, 2003 CONCRETE MANUAL CONCRETE PAVEMENT REHABILITATION

Joint Rehabilitation. Driving Forces for Concrete Pavement Joint Repairs

Concrete Repair. Applications and Procedures

Construction Materials Testing. Classes of Test

Bonding Agents: The Good, the Bad, and What Works. Bond with Your Concrete

APE T CFRP Aslan 500

Rehabilitation Strategies for Bonded Concrete Overlays of Asphalt Pavements

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

PROPERTIES AND MIX DESIGNATIONS

CONCRETE REPAIR GUIDELINES. Concrete repairs can be broken down into four basic types, plus special repairs and planing.

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted )

SECTION 18 - CAST IN PLACE HIGH PERFORMANCE CONCRETE (HPC)

La Nueva AASHTO Guia de Diseno de Pavimentos Hormigon

Construction. 3-part thixotropic epoxy patching mortar. Product Description. Tests

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Pavement Patching Repair for AC and PCC Pavement Surfaces. Vern Thompson

SPECIAL COMPOUND FOR RHEOPLASTIC AND ANTI-CORROSION SUPERCONCRETE WITH VERY HIGH DURABILITY

Construction Specifications for Keyhole Pavement Coring and Reinstatement

The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

PC-Concrete Injectable Concrete Anchoring and Repair System

SECTION III-06 Surfacing Page 1 Revised 3/2/10. See the DESIGN GUIDELINES in Section I-06 for requirements for cross slope of the roadway.

Concrete Pavement Rehabilitation Techniques and Canadian Based Case Studies

Ironwork in Highways -Whole Life Cost Perspective. Reducing cost through collaboration

beams columns blast walls slabs pipes protective coatings polymer concrete Solutions Looking for Problems...

Portland Cement Concrete Pavement Best Practices Summary Report

BRIDGE REHABILITATION TECHNIQUES

Testing and appraisal of Lucobit polymer effect as an additive on asphalt mixture performance

ICS: Strengthening retrofitting of reinforced concrete structures by gluing of fibre reinforced polymeric fabrics (FRP fabrics)

Concrete Pavement Rehabilitation

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES

SECTION STORM DRAINAGE SYSTEM

Standards for Specifying Construction Of Airports

BRIDGE REHABILITATION. Maintaining and Repairing Existing Structures

Jointed Plain Concrete Pavement (JPCP) Preservation and Rehabilitation Design Guide

CA-48 TECHNICAL SPECIFICATION

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

The Concrete Life Cycle: Maintain to Sustain. Fred Goodwin BASF Construction Chemicals (EB-N) Beachwood OH

Condition assessment and repair of antenna towers concrete foundations

Fosroc Construction Grouting Solutions. constructive solutions

Rapid Chloride Permeability Testing

Pavement Thickness. esign and RCC-Pave Software. Roller-Compacted Concrete Pavement: Design and Construction. October 24, 2006 Atlanta, Georgia

The First Commandment for floor slabs:

Improving Rehabilitation Selection for Pavement Life Cycle Cost Analysis

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Causes and Repair Method

Epoxy Crack Injection (the basics)

INTRODUCTION TO CONCRETE PAVEMENTS

CRACK and JOINT REPAIRS on INDUSTRIAL CONCRETE FLOORS, PAVEMENTS and SECONDARY CONTAINMENT AREAS

INTERIM ADVICE NOTE 96 /07 Revision 1 GUIDANCE ON IMPLEMENTING RESULTS OF RESEARCH ON BRIDGE DECK WATERPROOFING

1.5 Concrete (Part I)

A Professional s Handbook on Grouting and Concrete Repair

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

The AQUAFIN Approach to Concrete Repair

How To Fix A Cracked Road Surface

OHIO ASPHALT PAVING CONFERENCE

NEGATIVE SIDE WATERPROOFING SYSTEMS FOR MASONRY AND CONCRETE

SECTION PLAYGROUND SURFACING TILES

Concrete Repair. Solutions that Challenge Corrosion

RHOPLEX MC-1834P Cement Mortar Modifier

Preservation, Repair and Rehabilitation of Concrete Bridges, Pavements and Tunnels in Virginia

THORO. Waterproofing Systems

TECHNICAL PROPOSAL FOR WATERPROOFING TREATMENTS SYSTEM RECOMMENDATION

Hardened Concrete. Lecture No. 14

Fire-Damage or Freeze-Thaw of Strengthening Concrete Using Ultra High Performance Concrete

The Original Carbon Fiber Reinforced Polymer System

Polyester Polymer Concrete Overlay

Chapter - 3 Design of Rectangular Beams and One-way Slabs

LEGACY REPORT. (800) (562) A Subsidiary of the International Code Council. *Corrected March 2014

A. This Section includes rubberized asphalt sheet membrane waterproofing systems.

AGREGADOS RECICLADOS MITOS Y REALIDADES

ENGINEERING SPECIFICATION PULTRUDED DYNAFORM FIBERGLASS STRUCTURAL SHAPES. July 1, 2008 Revision 2

Concrete Pavement Rehabilitation: Repairing Florida One Slab At A Time

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Construction and Preliminary HVS Tests of Pre-Cast Concrete Pavement Slabs

Formwork Direct International Ltd Phone No +44 (0151) Fax no +44 (0151)

(T indicates a Tropicalised version with extended workability. No change has been made to the formulation)

Chemical-Resistant Epoxies for Secondary Containment by Christine Stanley Ameron Inc., Protective Coatings Group

NATURAL STONE LABORATORY

Condition Evaluation of Bridge Deck Surface Structure by Using State of the Art NDT- Techniques

Pavement Rehabilitation Selection Rehabilitation Techniques

Common Perils of Ceramic Floor Tile Systems. Parkway, Suite 220, Plano, Texas 75093; PH (469) ;

Chapter 7: Pavement Rehabilitation 7-1 Asphalt Pavement Overlays 7-1 Surface Preparation Methods 7-2 Concrete Pavement Preparation 7-3 Recycling

Resurfacing Concrete. Page 1 of 5

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION CONCRETE BONDING COMPOUND.

ElastoFlake & ElastoTec

CURRENT PRACTICE SHEET

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

HIGHWAYS DEPARTMENT GUIDANCE NOTES ON THE USE OF WATERPROOFING MEMBRANES ON CONCRETE BRIDGE DECKS

CONCRETE BRIDGE DECK CONDITION ASSESSMENT GUIDELINES

The Recognized Leader for WATERSTOPS FOR CONCRETE

Advancements in GPR for a Sustainable Tomorrow

RESEARCH PROJECT NO EVALUATION OF TUF-STRAND FIBER CONCRETE ADDITIVE

Transcription:

PPETG May 3-4, 2011, Oklahoma City Dowel-Bar Retrofit Using Polyester Polymer Concrete Shakir Shatnawi, Ph.D., P.E. President, SHATEC ENGINEERING CONSULTANTS, LLC sshatnawi@sbcglobal.net 916-990-6488

2 Presentation Outline Description Project Selection Nationwide Usage Typical Distress California Experience Key Parameters Cementitious Grouts Polyester Polymer Concrete Comparisons State Route 50 Final Remarks

Description 3

Description -DBR Assembly Schematic View 4

5 Description Core showing grout and dowel Improving load transfer

6 Project Selection Low Load Transfer: <70% Faulting: <0.1 inch Cracking: <10% Structurally Adequate

Nationwide Usage >5 Million 7

8 Typical Distress Studded Tire Wear Backfill Cracking

9 Typical Distress Backfill Spalling Backfill Debonding

10 Typical Distress Poor Consolidation Foam Board Misalignment

11 Typical Distress Excessive Voids around Dowel US59-Computerized X-Ray Tomography -above and below dowel-chen (2008)

12 California Experience Between 1950 and 2000 California did not require dowel bars in JPCP. 1998-Colfax, CA was the First DBR Pilot Project. Avg. LTE increased from 30% to 82%. Backfill is still in good condition.

13 California Experience 2001 SR 101-Ukiah DBR Test Sections. LTE increased from 49.2% to 85.3% or higher after 10 months in service 2001 SR 14-Palmdale. LTB increased to above 80%. several locations experienced failure of the bond between the backfill and the existing concrete.

California Experience -2005 Investigation 14 Overall, DBR is an effective method for improving joint load transfer efficiency across transverse joints and cracks. Distress on various statewide projects was noticed. Debonding and deleterious material were found between backfill and existing pavement, and poor consolidation.

California Experience 15-2005 Investigation Considerable variation in the performance of the backfill material. In the same project, and sometime at the same transverse joint, not all slots exhibited backfill material distress. Improper construction techniques.

California Experience Summary of Issues 16 Poor consolidation is the most common problem. Under-vibration results in honeycombing. No requirement for proper consolidation. Difficulty of backfill to flow below the dowel. Excessive vibration-misalignment and non-uniform strength. Inadequate Adhesion to existing pavement.

17 Key Parameters Proper consolidation to prevent honeycombing and non-uniform strength Adequate compressive strength to sustain Dowel bearing Adequate tensile strength to resist cracking Adequate Bond strength to ensure a durable slot and monolithic behavior

Key Parameters -Effect of Strength & Consolidation MN Minne-ALF Experiment (2001) 9000 Single Load Cycles Slabs 2&3: 4000 PSI C. Strength Slabs 4&7: 5000 PSI C. Strength Slab 4 is poorly Consolidated 18 LTE=70%: Slab 7---Nf=100,000,000,000 Cycles Slabs 2&3----Nf=10,000,000 Cycles (<1000 times )

Key Parameters -Effect of Strength and Consolidation Minne-ALF Experiment-Embacher et al. (2001) 9000 Single Load Cycles Slabs 2&3: 4000 PSI C. Strength Slabs 4&7:5000 PSI C. Strength Slab 4 is poorly Consolidated 19 Slab 7---------DD=53 micro-m Slabs 2&3----DD=325 and 331 Micro-m

Key Parameters -Effect of Strength and Consolidation 20 Minnesota Test Sections-Trunk Highway TH 23 near Mora, Minnesota built 1998 1999 Investigation-Majority of the slots using lower strength backfill material had shrinkage cracks along one of the slot edges at the interface indicating debonding. However, the higher strength backfill material showed very little cracking along the edges of the slots.

Cementitious Grouts 21 -Specifications Property Test Method Requirements Compressive Strength at 3 hours, psi California Test 551 3,000 min. at 24 hours, psi California Test 551 5,000 min. Flexure Strength at 24 hours, psi California Test 551 500 min. Bond Strength: at 24 hours SSD Concrete, psi California Test 551 300 min. Dry Concrete, psi California Test 551 400 min. Water Absorption,% California Test 551 10 max. Abrasion Resistance at 24 hours, ounces California Test 550 1 max. Drying Shrinkage at 4 days, % Soluble Chlorides by weight, % Water Soluble Sulfates by weight,% ASTM Designation: C596 California Test 422 California Test 417 0.13 max. 0.05 max. 0.25 max.

Polyester Polymer Concrete -Characteristics 22 Successfully used in repairing spalls, rut fills and bridge deck overlays High strength Strong bond characteristics High flowability High toughness Fast curing Impact and abrasion resistance High resiliency Age hardening resistance Water impermeability and de-icing salts Forgiving Creep characteristics-less shrinkage cracking

Polyester Polymer Concrete 23 -Pertinent Specifications Test Property Value ASTM D38 CT 551 Grout Tensile Strength Bond Strength (SSD) 2500 PSI 500 PSI ASTM D2196 Viscosity 75-300 cp Styrene Content 40-50%

Comparisons 24 -Properties Property PCC PPC Compressive Strength (MPa) 13.0-35.0 50.0-150.0 Tensile Strength (MPa) Flexural Strength (MPa) Modulus of Elasticity (GPa) Abrasion-CT 550 Ball Bearing T. Coefficient of Expansion (106 C-1) 1.5-3.5 8.0-25.0 2.0-8.0 15.0-45.0 20.0-30.0 20.0-40.0 40 grams 2-4 grams 10.0-12.0 10.0-30.0

Comparisons 25 -Bond Strength CT-551 PPC: 1200-1800 psi Min 500 PSI (SSD) PCC: 400-500 psi Min 300 psi (SSD) & 400 PSI (Dry)

26 SR-50 DBR Project 8 inch thick PCC 2004 ADT: 149,000-184,000 2030 ADT: Forecasted at 246,000-299,000. Polyester Polymer Grout (KwikBond) in 2010 61,200 dowels Diamond Grinding

27 SR-50 DBR Construction Cutting the Slots

28

29 SR-50 DBR Construction Cutting the Slots

30

31

32 SR-50 DBR Construction Ready to Pour PPC Grout

33 SR-50 DBR Construction Low Viscosity PPC Grout

34

35 SR-50 DBR Construction Minimum Vibration

36 SR-50 DBR Construction Making Sure Slots are Filled Completely

37

38 SR-50 DBR Construction Completed DBR Installation

39 SR-50 DBR Construction Extracted Core

40 SR-50 DBR Construction Before Grinding

41 SR-50 DBR Construction After Grinding

42 Final Remarks DBR is an effective pavement preservation strategy Distress mainly due to failure of cementitious backfill (cracking, debonding & spalling) Improper consolidation & low strength are major culprits DBR with polymer polyester gout reduces risk of failure due to superior properties US 50 DBR project have been placed successfully. Recommend more projects with polyester polymer concrete grouts.

43 Thank You Questions?