Concepts for Transfer of Personnel in Offshore Wind Skibsteknisk Selskab / Maritimt Selskab / Transportens Innovationsselskab 21 October 2013 in Copenhagen Niels Agner Jensen, Lead Maritime Project Manager, DONG Energy Wind Power, O&M Offshore Logistics
DONG Energy Wind Power Key Logistic Parameters Personnel Transfer Large Access Systems Sophisticated CTVs and Transfer Systems Verification of Performance 2
DONG Energy Wind Power Core activities Development, construction and operation of offshore wind farms Market position Market leader in offshore wind, has built 38% of European capacity Strong pipeline of projects in lead-up to 2020 Business drivers Wind conditions Availability Electricity prices and subsidies Industrialisation and maturing of value chain Securing supplies via framework agreements and partnerships Partnerships with industrial and financial investors ROCE targets 2016: 6-8% 2020: 12-14% Strategic targets for 2020 Installed offshore wind capacity (before divestments): 6.5 GW Reducing offshore wind Cost of Energy to below EUR 100/MWh 3 1 The percentages indicate the proportion of the Group that each business unit represented in 2012. 2 Intragroup revenue means that the business units combined revenue exceeds consolidated revenue. 3 Cost to society based on projects in the UK where investment decisions will be made in 2020.
DONG Energy has a significant portfolio and a strong pipeline of future offshore wind projects IN OPERATION UNDER CONSTRUCTION UNDER DEVELOPMENT Our offshore wind projects are centred around North western Europe UK, Germany and Denmark 4
DONG Energy Wind Power Key Logistic Parameters Personnel Transfer Large Access Systems Sophisticated CTVs and Transfer Systems Verification of Performance 5
Key Logistic Parameters? 6 6
Example of a Far Shore Site: Borkum Riffgrund Borkum Riffgrund I Offshore Wind Farm (BKR01) is situated approx. 40km north of the island Borkum Route partly in channel Speed limit Shallow water / tidal restrictions Long distance in open water 7 7
Breakdown of a Working Day for Technicians Technician working day when travelling from harbour in Norden-Norddeich to BKR01&02 Hours per activity, based on crew boats travelling with a speed of 17 knots 12.0 0.3 3.5 Only approx. 6 hours with a traditional setup 1.3 0.5 0.5 5.9 Working day Preparation Travel time WTG transfer Lunch break Acclimatisation Effective working time Consequences of long boat travel 8
DONG Energy Wind Power Key Logistic Parameters Personnel Transfer Large Access Systems Sophisticated CTVs and Transfer Systems Verification of Performance 9
Traditional logistic is based on Crew Transfer Vessels 10
11
12
13
14
Our Own Dedicated CTV's 15
DONG Energy Wind Power Key Logistic Parameters Personnel Transfer Large Access Systems Sophisticated CTVs and Transfer Systems Verification of Performance 16
Access from Large Vessels Ampelmann More than 390,000 transfers Long experience Oil & gas and offshore wind Typically 22m Heave compensation A-type typical 2.5m, E-type typ. 3.5-4.0m Capability depends on vessel size Requires dedicated operators DP2 vessel required Source: http://www.ampelmann.nl/products/ 17
Access from Large Vessels OAS More than 190,000 transfers / more than 10,000 connections Oil & gas Typically 21m Typical connection time 5-30 min. (possible up to 60h) Operation in up to 2.5 3.0m Hs Capability depends on vessel size Can be operated by vessel crew after training DP2 vessel required Next Gen Unit under development 18 Source: http://www.offshore-solutions.nl/en/ + Lindsay Young, Man. Dir.
Access from Large Vessels Uptime More than 60 systems delivered Oil & gas (mainly) and offshore wind Typically 19.4m for large vessels Typically long connection times (days, weeks or months) Capability depends on vessel size Can be operated by vessel crew after training DP2 vessel required Has developed smaller version for CTVs Source: http://www.uptime.no/?cat=9 + Bjørnar Huse, Man. Dir. 19
DONG Energy Wind Power Key Logistic Parameters Personnel Transfer Large Access Systems Sophisticated CTVs and Transfer Systems Verification of Performance 20
Carbon Trust Offshore Wind Accelerator The Offshore Wind Accelerator (OWA) is Carbon Trust's flagship collaborative RD&D programme. Set up in 2008, the OWA is a joint industry project, involving nine offshore wind developers with 77% (36GW) of the UK's licensed capacity, that aims to reduce the cost of offshore wind by 10% by 2015. Source: Carbon Trust 21
CT OWA TWG on Access Access Competition Autumn 2011 450 entries from 30 countries 13 selected Source: Carbon Trust 22
Source: Umoe Mandal, Trygve.Halvorsen.Espeland@um.no CTV - Umoe Mandal "Wave Craft" 23
CTV - Umoe Mandal "Wave Craft" Source: Umoe Mandal Trygve.Halvorsen.Espeland@um.no http://www.youtube.com/watch?v=e6nadnw15vs 24 Based on navy experience High speed / long range, yet acceptable fuel consumption Improved PAX comfort Shallow draft Tests show good performance at turbine foundation Breaking news: Prototype under construction, January 2015 delivery Source: Umoe Mandal, Trygve.Halvorsen.Espeland@um.no
CTV - Fjellstrand "WindServer" 25m / 30m Advanced trimaran hull form Contract for six vessels early in the CT process http://www.carbontrust.com/news/2012/06/offshore-wind-accelerator-news-update 25
CTV - Fjellstrand "WindServer" 25m 'Soft bow' to minimize impact on boatlanding Comfortable 'business class' type of seats 4 th vessel to be tested at HR2 in October / November 2013 Source: World Marine Offshore 26
Access System - Momac "MOTS 500" Source: MOMAC, NOS, Carbon Trust and DONG Energy 27
Access System - OSBIT Power "MaXccess" on BAYARD 7 The BAYARD 7 from F.O. Windcarrier fitted with MaXccess T18 at Walney Offshore Wind Farm 28
Access System - OSBIT Power "MaXccess" on BAYARD 7 Access system that grips one of the vertical boatlanding pipes Allows the vessel to roll, pitch and sway Allows an angled approach/berthing at the boatlanding Traffic light system shows when the system is safe to use Source: MOMAC, NOS, Carbon Trust and DONG Energy 29
DONG Energy Wind Power Key Logistic Parameters Personnel Transfer Large Access Systems Sophisticated CTVs and Transfer Systems Verification of Performance 30
Verification of Performance Source: Carbon Trust 31
Horns Reef 2 Offshore Wind Farm Thank you for your attention. Questions? Niels Agner Jensen niaje@dongenergy.dk 32