SAVANNAH-CHATHAM COUNTY BOARD OF EDUCATION Internal Audit Department 208 Bull Street, Room 310 Savannah, GA 31401



Similar documents
Peralta Energy Oakland, CA

Overview. PG&E and Energy Efficiency. CA Energy Efficiency Regulatory & Policy Roadmap. Financing Options for Efficiency & Demand Response

FMXcellence Update: Gilbert Public Schools. Energy Management Plan

Fountain Hills Unified School District #98

Tompkins-Seneca-Tioga Board of Cooperative Educational Services

Conservation Demand Management Plan London Health Sciences Centre Made for Ontario Regulation 397/11 Green Energy Act, 2009

Program Overview. Free intelligent thermostat and gateway device ($150 - $200 value)

Delaware Community Schools

Section 1 Bills Bills Bills All copies of bills and information obtained from company websites

HVAC System Optimization

SEVEN REASONS FOR ENERGY ACCOUNTING

GREEN BAY AREA PUBLIC SCHOOL DISTRICT Board Policy Manual ENERGY MANAGEMENT

7.1 Conservation Programs for Industrial, Commercial, and Institutional Accounts

ENERGY USAGE GUIDELINES

Tracer Summit Energy Services

Queensbury Union Free School District

Air Conditioning. The opportunity for energy efficiency. Low cost actions to reduce energy usage now

PENNSYLVANIA GREEN ENERGY LOAN FUND

Proposed Annual Operating Budget Fiscal Year July 13, 2015

Energy Efficiency and Automated Demand Response Program Integration: Time for a Paradigm Shift

Feasibility Study Proposal & Report Guide. Industrial Optimization Program

EnerSmart Programs. enercase. Performance Contracting. contracting. Tired of. chasing capital for infrastructure upgrades?

Report for Fiscal Year 2014

Energy Audits. Good energy management begins with an energy audit

Design Guide. Retrofitting Options For HVAC Systems In Live Performance Venues

CHAPTER 8 HVAC (Heating, Ventilation, and Air-Conditioning)

PROFESSIONAL AND INSTITUTIONAL DEVELOPMENT PROGRAM: PROGRAM GUIDELINES

Difference (Remaining Funds) $0 $0 $0 $0 $0 $0

Energy Conservation Plan 4rd Quarter FY2014 Texas Facilities Commission COVERING THE PERIOD JUNE 1, 2014 THROUGH AUGUST 31, 2014

ENERGY AUDITS FOR EXISTING BUILDINGS: It s like (nearly) free money! FSi consulting engineers

County of Santa Clara Finance Agency Controller-Treasurer Department

QUESTAR III BOARD POLICY NO CELL PHONE POLICY

PPS Energy Management Program. Report to Board of Education June 4, 2012

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

Exxon Chemical Company's Linden Technology Center Site Map

FINANCIAL SERVICES DIVISION DIVISION INFORMATION AND KEY PERFORMANCE INDICATORS (K P I) DATA

Energy Management Performance Contract

Florida Power & Light Company. Business Heating Ventilation & Air Conditioning ( HVAC ) Program Standards. Effective: November 9, 2015

Energy Savings Contract

Sustain GRANT. accepted.***

Process and Impact Evaluation of Roseville Electric s Residential New Construction, HVAC Retrofit and Commercial Custom Rebate Programs: FY2007/08

Use of External Consulting Services Fiscal Years 2007/08 through 2010/11 April 2012

SCHOOL BOARD OF BROWARD COUNTY, FL INTERNAL FUNDS ACCOUNTING FUNDRAISING ACTIVITIES

Review of. Freedom Shores Elementary Parent-Teacher Association's Bank Accounts

Energy Savings Contract

Date: April 17, Enclosures: 2

NEW COMMERCIAL Rates. Understanding the. Commercial Customers

SEDAC Energy Efficiency Workshop Jacksonville March 9, 2012

ENERGY SOLUTIONS FOR BUSINESS CUSTOMERS

Energy Efficiency Building Retrofit Case Study: City of Houston Retrofit Program, Tranche 2 Results

Audit Report Employee Expense Reimbursements Fiscal Year 2013 February 20, 2015

Exceptional Educational Facilities Management

OFFICE OF AUDITOR OF STATE

General Fund Expenditures

STATE OF NEW YORK OFFICE OF THE STATE COMPTROLLER 110 STATE STREET ALBANY, NEW YORK February 25, 2011

BUSINESS PLAN Florida High School for Accelerated Learning. 14. Facilities If the site is not secured.

Esperanza Cyber CS Charter Annual Report 07/01/ /30/2015

Chapter 5. Program Cost Accounting and Reporting. 1. Identification of direct program costs and aggregation of these costs by program

Energy Savings Performance Contracting. Guidelines for State Agencies. Part 2

How To Improve School Guidance And Counseling In Gorgonia

ESPC Life of Contract (LOC) Plan:

Q Utility Rebate Report. Houston, TX

1.1. "Applicant" means an entity that submits an Application for Financial Assistance to the Board, including:

AEP Ohio Business Incentives for Energy Efficiency. Topics. Why Energy Efficiency? 11/24/2014. Economic Development 101 November 21, 2014

The sample report format is applicable to many different building types and systems and the examples provided cover a variety of applications.

ENERGY STAR Data Verification Checklist

Upper Occoquan Service Authority Centreville, Virginia A Case Study

Energy. Management. BTU Meter Installation BTU Meter Commissioning Maintenance Billing and Collection ISO Management.

Standard Operating Procedures

COMMONWEALTH OF VIRGINIA STANDARD CONTRACT ENERGY SAVINGS CONTRACT

PUBLIC SCHOOL DISTRICT BUDGET AND TAX LEVY - CERTIFICATE OF LEVY NORTH DAKOTA DEPARTMENT OF PUBLIC INSTRUCTION OFFICE OF SCHOOL FINANCE

Using Time-of-Day Scheduling To Save Energy

AGENDA. Benchmarking Methods. How to use the B3 Program to Identify Buildings to Save Energy New B3 Features Funded in 2010

Eldred Central School District

The District Energy Manager and Classroom Heating

Total Cost of Ownership. ChromeBooks vs. Laptops for Downey Unified School District. Author: Chris Nezzer

A U D I T R E P O R T. Audit of Child Support Contract CD336

Making the Most of Property

Appendix A Contractor Quality Control Plan The Contractor Quality Control Plan is the Contractor s management plan for executing the contract.

REQUEST FOR PROPOSAL GUARANTEED ENERGY SAVINGS CONTRACT. Dallas School District 2000 Conyngham Avenue Dallas, PA Addendum 2

FEDERAL COMMUNICATIONS COMMISSION

Company name Date submitted. Building address City State ZIP. * Building Sq. Ft.

School District Gives Andover Infinity TM High Marks

Deep Fork Community Action Foundation, Inc. REQUEST FOR PROPOSAL FOR ACCOUNTING SERVICES

Product Catalog. Trane eview Energy Reporting Software BAS-PRC054-EN. November 2010

Leveraging the Power of Intelligent Motor Control to Maximize HVAC System Efficiency

INTRODUCTION. Summary of revenue/expenditures available for new construction and remodeling projects only. CERTIFICATION

Table of Contents. Transmittal Letter Executive Summary Background Objectives and Approach Issues Matrix...

PROTOCOL FOR BUILDING ENERGY ANALYSIS SOFTWARE For Class 3, 5, 6, 7, 8 and 9 buildings

Energy Action Plan 2015

Bond Funds Compliance Monitoring Internal Audit

Energy Dashboard Activity

APPLICABILITY/ACCOUNTABILITY

Performance Audit Report. Department of Human Resources The Maryland Energy Assistance Program and the Electric Universal Service Program

Office of Public Affairs Business Process Audit Final Report

Business Office Department Improvement Plan

Georgian Bay General Hospital Strategic Energy Management Plan 2014

We help municipalities do more with less.

Detailed Assessment Report Plant Operations. Objectives, with Any Associations and Related Measures, Targets, Findings, and Action Plans

Summer (FY11 &12) $255,418 Article III - Summer Undergrad. Cost of Ed. $255,418 Total Summer Funding

Transcription:

SAVANNAH-CHATHAM COUNTY BOARD OF EDUCATION Internal Audit Department 208 Bull Street, Room 310 Savannah, GA 31401 To: Through: From: Board of Education Dr. Thomas B. Lockamy, Jr., Superintendent Vanessa Miller-Kaigler, Executive Director of Facilities Management Rebecca McClain, Chief Financial Officer Kelly Crosby, Senior Director, Internal Audit Date: February 27, 2014 Subject: M&O Contract Audit Trane U.S. Inc PACT Agreement We have completed our Audit of the Trane U.S. Inc PACT Agreement. Our audit report is presented in the sections listed below: I. AUDIT OBJECTIVES II. SCOPE III. BACKGROUND IV. AUDIT FINDINGS Management s response to our report is attached in its entirety. In addition, the specific action that management has agreed to take in response to each recommendation is included in the Management Action Plan, along with who is responsible for the action and when it will be completed. I. OBJECTIVES Our audit was designed to meet specific objectives. Within those objectives, we focused on areas where we identified opportunities for improvement. The objectives of our audit were as follows: Verify compliance with SCCPSS Policies and Administrative Regulations. Validate SCCPSS compliance with all customer responsibilities in the PACT Agreement between SCCPSS and Trane U.S. Inc, dated June 21, 2010. Validate Trane compliance with all contract responsibilities in the PACT Agreement between SCCPSS and Trane U.S. Inc, dated June 21, 2010. 1

Verify Total Energy Savings calculated by Trane to ensure that guaranteed savings goals were met. II. SCOPE Internal Audit conducted an audit of the contract between the Savannah/Chatham County Public School System (SCCPSS) and Trane U.S. Inc. This is part of Internal Audit s continuing focus on the District s larger contracts. The focuses of this audit were the deliverables and savings guaranteed by the contract. In order to accomplish our objectives, we conducted the following steps during the course of our review: Held discussions with District management and staff within the Facilities Construction and Maintenance and Operations Departments; Reviewed the PACT Agreement (contract) between SCCPSS and Trane U.S. Inc, dated June 21, 2010. This includes additional exhibits that provide more detail and clarity of the contract requirements; Reviewed utility bills and District expenditures to validate the cost savings provided by Trane U.S. Inc.; and Reviewed the District purchasing procedures for the request for proposal process. We conducted our fieldwork during the period of August 2013 and January 2014. We conducted this performance audit in accordance with generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. III. BACKGROUND On June 21, 2010, SCCPSS entered into a contract with Trane U.S. Inc. (Trane) for energy management consulting services, equipment and installation fees at a total cost of $10,693,640. This contract was paid using both ESPLOST I ($3,429,344) and General funds ($7,264,296). The initial phase of the contract consisted of an Energy Audit; Trane reviewed the energy usage of selected schools, based on the energy invoices paid by the District in FY 2009 (the year prior to signing the contract). This established the baseline of SCCPSS energy costs. The Energy Audit also reviewed equipment used in schools for age and efficiency. This process identified schools with the potential for energy savings, using updated equipment and automated temperature controls. Trane s Energy Audit made recommendations for reducing energy consumption and costs District-wide. These recommendations were put in place during the next phase of the contract, called the Installation Period (May 2011 July 2012). During this phase, schools were outfitted with new lighting fixtures (24 schools and maintenance area), water economizing pedal valves (42 schools), hardware and software upgrades to air 2

control systems (25 schools), and replacement of outdated air conditioning units (21 schools, 947 units). The contract includes both guaranteed and non-guaranteed (or stipulated) savings to the District. The guaranteed savings over 10 years are based on anticipated annual savings at six identified schools (Haven Elementary, Hesse K-8, Myers Middle School, Jenkins High School, Savannah High School, and Savannah Arts Academy). These savings are based on recommendations made by Trane to ensure the maximum cost savings. The stipulated savings are those savings that were agreed upon at the onset of the project based on retrofitting existing kitchen sinks with water economizing pedal valves, updating lighting fixtures, and changes to the gas rates. The projected total savings over 10 years are $14,453,304. IV. AUDIT FINDINGS Savings Trane presented The First Year Performance Results for the Performance Agreement for Comfort to District staff on October 29, 2013. This report showed the following savings for the period of May 2011 through July 2013: Electrical Energy Natural Gas Total Year 1 Actual Savings 10,070,076 kwh 268,812 Therms Year 1 Guaranteed Savings 11,701,080 kwh 250,405 Therms Savings in Excess of Guarantee (1,631,004 kwh) 18,407 Therms Installation Period Savings 5,729,804 kwh 192,011 Therms Total Savings in Excess of Guarantee through July 2013 4,098,800 kwh 210,418 Therms To determine these savings, Trane developed a baseline year of utility usage/cost for the District. They used the year prior to the contract (FY 2009) for the baseline. The next fifteen months were identified by Trane as the installation period. The installation period ran from May 2011 July 2012. By reviewing the utility bills during this period, they determined the District saved $814,117 in electrical and gas utilities. Water utilities were not included in this calculation. While Trane did not meet the guaranteed kilowatt hour savings (see table above), the dollar amount saved exceeded the estimated (calculated) savings, as shown below. Total Year 1 Actual Savings (Cost Avoidance) $1,284,737 Year 1 Calculated Value of Energy Savings in Contract 1,260,769 Savings in Excess of Calculated Value $ 23,968 Calculated Savings during Installation Period 814,117 Total Estimated Savings $ 838,085 The contract allows for the Installation Period Savings to serve as a reserve for any shortfalls during the 10 year time period. Unapplied savings from the Installation Period carry over into the following year(s). Industry standard methodologies were used to determine energy consumption and utility bills were used to determine energy costs. 3

Calculation methods can be located in the exhibits of the PACT Agreement. The report presented to SCCPSS on October 29, 2013 included possible explanations for the deviation between the actual and guaranteed savings. The recurring issues were the scheduled hours of operations and chiller operations. The Trane contract used the following operational parameters: Elementary Schools: Weekdays 7:00 AM 4:00 PM (Class schedule), 7:00 AM 5:00 PM (Office Schedule). No weekend or summer occupancy. Middle Schools: 6:00 AM 4:00 PM (Class schedule), 6:00 AM 5:00 PM (Office Schedule). No weekend or summer occupancy. High Schools: 5:00 AM 6:00 PM (Class schedule), 5:00 AM 6:00 PM (Office Schedule). No weekend or summer occupancy. Summer periods for the classroom were July August and for the office July. Equipment failures were also a problem at two schools. Savannah High School had issues with their condenser tubes, resulting in the chiller running harder and longer to pre-cool the building. Savannah Arts Academy had a chiller issue that resulted in the unit running 24 hours a day. Those issues were addressed, and the chillers are now functioning appropriately. These adjustments should provide additional future energy savings. Trane reserves the right to adjust the Utility Baseline used to calculate energy savings. Any costs incurred to adjust the Utility Baseline will be at the District s expense. The baseline may be changed using standard and sound engineering principles based on the following conditions: Changes to the building utilization the total number of building occupants, Changes to building occupancy hours the total number of hours the building is occupied or changes to the use of equipment, Changes in weather conditions yearly average highs and lows, and/or Changes to the building structures additional portables or new structures. For Year 1, no baseline adjustment was made. In Year 2, Trane will make a baseline adjustment based on the operations schedules and the chiller plant. Trane will work with the District to optimize schedules and other operational strategies prior to making baseline adjustments. Management is currently reviewing the recommended changes. No formal decision has been made to adjust the utility baseline. Conclusion: Trane U.S. Inc. and SCCPSS have adhered to the requirements in the June 21, 2010 PACT Agreement. The guaranteed savings in the first year were met using the Installation Period savings. The main cause of the reduced savings was the difference between the baseline operational schedules and each school s actual operations. The District should review the baseline adjustments proposed by Trane and continue to track the guaranteed savings each year. Management s Response: 4

Management agrees with the findings as outlined in the referenced document. In addition to the original program savings, the District also received a rebate of $192,000 for utilizing energy efficient products. Facilities Management staff will implement an annual energy management awareness program geared towards all school sites and departments, with our first campaign presented before the end of this fiscal year. We will actively monitor usage and identify opportunities for improvement. District staff will work collaboratively to determine if adjusting the utility baseline is in the best interest of the district. In addition, staff will consult with Trane prior to making a final decision relative to the proposed adjustments. 5

Signature Page for Audit of M&O Contract Audit Trane U.S. Inc PACT Agreement Dr. Thomas B. Lockamy, Jr. Superintendent Rebecca McClain Chief Financial Officer Vanessa Miller-Kaigler Executive Director of Facilities Management Kelly Crosby Senior Director, Internal Audit Leah Underwood Senior Internal Auditor 6