Hydroelectric Power Plant - Los Cóndores. Santiago, April 2014



Similar documents
Endesa Chile YE14 Results

National Electric Power Regulatory Authority

AES GENER HIGHLIGHTS

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

INTRODUCING PUMPED STORAGE IN LEBANON: TOWARDS A PROSPECTIVE NATIONAL MASTER PLAN

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

Introduction to the Chilean power sector

Economics Training Series Introductory Course. Cost Estimation

COMPANY PRESENTATION 1Q 2013

ELECTRICITY DISTRIBUTION TARIFFS The Chilean Experience. Hugh Rudnick Pontifícia Universidad Católica de Chile

During 2013, we had special advances in the main civil works, and the execution of the social and environmental commitments related to the license.

AES Gener 2013 Year-End Results

How To Profit From Power Production

USAID ENERGY POLICY PROGRAM SITE VISIT REPORT STATUS OF 4 RUN OF RIVER HYDROPOWER PROJECTS. October 2013

enersis 1H 2012 results

The Brazilian Electricity Model: An Overview of the Current Structure and Market Design

Technology Fact Sheet for Mitigation B. Small Hydropower Technology i 1. Introduction 1.1. Historical - All over the World, hydropower sector is

Frequently Asked Questions (FAQs) on Hydropower

Analytical Approach for Cost Estimation of Low Head Small Hydro Power Schemes

Guidelines for Monthly Statistics Data Collection

Sample Micro Hydro Initial Report

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

ENERGY NETWORKS ASSOCIATION. Electricity Industry EMF Measurement Protocol for High Field Areas

Flat-land large-scale electricity storage (FLES) Lecture at the European Energy Conference 2012, Maastricht

Tufts Consulting Group: Macedonian Energy

Financing hydropower Introduction to the Specifics of Small Hydro Power Plants

Why solar is a good fit for mines: Pampa Elvira Solar project - Codelco

The 10th Chile Taiwan Joint Business Council Meeting

CHAPTER VII CONSTRUCTION QUALITY CONTROL INSPECTION PROGRAM 1

City of Vernon Request for Expressions of Interest and Information (RFI)

BTG Pactual& CelfinSouthern Cone Andean Conference Santiago, June 5 and 6, 2013

Methodology for Merit Order Dispatch. Version 1.0

HYDROPOWER POTENTIAL OF NEUQUÉN PROVINCE

Results of Electricity Sector Restructuring in Chile

CALIFORNIA ISO. Pre-dispatch and Scheduling of RMR Energy in the Day Ahead Market

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

: Promoters Contribution : Term Loan Total Profitability at optimum level. : Optimum Utilization(3 rd Year)

Tanzania: Lower Kihansi Hydropower Station / Hydropower plants

How To Work For Stellar

Pump Storage Technology

Búrfell. hydropower station

THE POWER MARKET IN CHILE WHAT IS GOING ON?

The River Devoll Project

Hydropower in Rwanda: Ongoing Initiatives & New Investment Opportunities. Yves Muyange Director General Energy Water & Sanitation Authority

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P Turbidity Monitoring Plan

Hydropower Projects Portfolio

U.S. Army Corps of Engineers Tulsa District

*This view is a sample image of electricity consumption.

HYDROMETEOROLOGICAL AND MONITORING SERVICE

J. Gaspar: Adapted from Jeff Madura, International Financial Management

Project Layout & Design Features of the Project

ESTIMATION OF PROJECT COSTS AND BENEFITS

Solar PV panels fitted to roofs. Solar PV panels produce electricity from energy provided by sunlight. 3.5 MWh per system

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Welcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community.

Line 2 and Av. Faucett Av. Gambetta branch line concession of the Lima and Callao Basic Metro Network

(NYSE-MKT:XRA, TSX:XRC,

Overview on SEA output

Electricity Market in Kazakhstan

Flood Risk Management

Flood Risk Management

COMPANY PRESENTATION. BTG Pactual & Celfin Southern Cone / Andean Conference. Santiago, June 5 th -6 th 2013

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project

Design Criteria & Service Goals

ELECTRICAL ENGINEERING ASSOCIATE, 7525

XAYABURI HYDRO POWER PLANT, LAO PDR

Challenges to integrate Renewables In the French and European Power System. Michel Béna, SmartGrids Director

Manage water resources for on site hydro-electricity generation

POWER NETWORKS Electricity Network Tariffs and Charges and Future Price Trends

The Status of the Wind Power Market in Egypt. Dr. Walid El-Khattam Ain Shams University (Cairo, Egypt) The Egyptian Electricity Regulator (EgyptERA)

SCHEDULE 1-2 CONSTRUCTION AGREEMENT. between KEEYASK HYDROPOWER LIMITED PARTNERSHIP, - and - THE MANITOBA HYDRO-ELECTRIC BOARD. DATED, 2009.

Disclaimer. This presentation does not constitute financial advice.

2015 Third Quarter Results Webcast October 29, 2015

Managing Foreign Exchange Risk

State of Renewables. US and state-level renewable energy adoption rates:

Transcription:

Hydroelectric Power Plant - Los Cóndores Santiago, April 2014

Introduction Los Cóndores, a large hydro project of 150 MW with water flow regulation using the existing water reservoir of the Embalse Laguna El Maule, located in VII Region. With expected Commercial Operation in December 2018, will strengthen our leadership and growth strategy in the Chilean market with a profitable and sustainable project. Los Cóndores project is 100% owned by Endesa Chile. 2

Strategic view Los Cóndores project will be key for Endesa Chile in order to fulfill current and future contract commitments and support margins, with an optimal generation mix (maximizing margin and decreasing market risk). Los Cóndores project will start operations at the end of 2018, just at the highest expected spot price point for the next years. The project is expected to lower the average energy price of the SIC market in 5 US$/MWh aprox. Efficient and sustainable large hydro project with low generation cost will consolidate competitiveness of Endesa Chile and remark a strong message of commitment with Chile (Los Cóndores is the unique new large hydro project foreseen in the next 5 years). Average long term generation Attractive generation profile to profit with high average energy prices in summer and spring seasons by means of the water regulation capacity ( Embalse Laguna El Maule ). Capture operating synergies due to its proximity to current Endesa Chile assets. Low social and environmental involvement due to the absence of communities in the area and optimal engineering solution with underground civil works. Principal permits approved. Agreement signed with DOH relative to Convenio Regulación del Río Maule (1947) and JVRM about the optimization of water use in the basin of the river Maule. 3

Project key features and status The water-intake facilities are located at Embalse Laguna del Maule at 2,500 m.a.s.l. Expected average annual energy of 642 GWh (48% load factor). Design flow rate of 25 m³/s with a verified maximum operational flow rate of 28 m³ /s and Overall Height of 765 m. 2x220 kv H-V transmission line of 87 km to connect the power plant to the SIC market in the Ancoa substation facility. Adduction consist on intake, adduction tunnel (with a total length of 12,000m which will be excavated using a tunnel-boring machine (TBM)), head zone, lower tunnel and turbine cavern. Water rights: granted by DGA (Res. No 434 in 11/1988). Environmental Impact Assessment Gx: 150 MW approved in 04/2008 and DIA of the optimized project approved in 11/2011. Environmental Impact Assessment Tx: approved in 05/2012. Hydraulic Work Permit (POH): approved in November 28th 2013 with the agreement about a Operation Protocol. Definitive Electrical Concession Gx: not required by signing of rental contracts in 10/2013 (temporary works) and signing of surface easement agreement (permanent works) with the Goverment. Expected to sign in April 2014. Definitive Electrical Concession CED Tx: currently in process. Notice to proceed for Civil Works Contractor on March 31th, 2014. Running contract for rescue and relocation of the flora and wild animals. Laguna del Maule Bocatoma existente Obra de aducción subterránea Zona de descarga 4

Los Cóndores Project Budget and risk Investment cost of the project amounts to US$662 million 84% of total project budget is supported by firm commitments 25% of total budget allocates contingencies and risks. The amount included with high certainty considers a firm value. Focus on risks The budget of Los Cóndores project for contingencies includes: Risk Matrix: 16% Includes all potential risks not covered under the insurance program for the construction period. Social Geological Weather Contractual Land and easements Other minors and not identified risk Consolidation of learned lessons to lower financial deviation during the construction @Risk: 6% Includes all uncertainty in quantities of civil work made by the level of project field studies It measures quantity variations with expected fixed prices of contracts Currency and Contract Indexation Risks: 3% Mitigation of 100% FX volatility and partial hedging for indexed variables in main contracts for domestic currency tranches 5

Mitigation measures included for the project Agreements signed with JVRM and DOH. The agreement with JVRM, about the optimization of water use in the basin of the Maule river, is part of a long term solution. Cost of forced stoppages was negotiated and agreed with bidders during the bidding process. Large scale field studies, geological survey, two Board of Consultants during design process (Gx), expert advice for TBM, transmission line layout modifications (Tx). Advanced negotiation in progress for transmission easements (49% of required easements are agreed with the owners and Endesa Chile owns additional 8,5%). Main contracts includes clauses to transfer relevant risks during construction to contractors. Insurance program negotiated by Endesa Chile which was adhered by the contractors. 6