INTRODUCTION. Prakash Chandar. S¹, Dhivya Shree. G² ABSTRACT



Similar documents
Automated Micro-Planning and Real-time Tracking of Precast Building Components

General Comparison between 4D Software

Certified Instructors & Curriculum

Application of MS Project Software for Time and Cost Management in Real Estate Construction

Efficient Planning Scheduling And Delay Analysis Of Residential Project

Cash Flow of High Rise Residential Building

MASTER CLASS INTEGRATED PROJECT MANAGEMENT SOFTWARE REPORT Timo Hartmann

Building Information Modelling (BIM); How it Improves Building Performance. R.P. Kumanayake Lecturer, Department of Civil Engineering

Building Information Modeling (BIM) Requirements for PT Projects Today s Capabilities for a BIM based Design

A WORKFLOW ANALYSIS FOR BIM SOFTWARE: ARCHITECTURAL AND MECHANICAL ENGINEERING DEPARTMENT OF ARUP TURKEY

Resource Scheduling of Construction Project: Case Study

Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects

Project Cost & Schedule Monitoring Process Using MS Excel & MS Project

PS.12. 4D Scheduling A Case Study

Tesla Outsourcing Services An Architectural & Engineering Company

Olilo's AEC Design Services. SrinSoft Inc, Partners of

MULTI-RESIDENTIAL BUILDING SOLUTIONS

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

BIM: FOR PROJECT MANAGERS CSI Southwest Region Conference Program 1B 8:45am 11:00am

AC : IMPLEMENTING BUILDING INFORMATION MODELING IN CONSTRUCTION ENGINEERING CURRICULA

Synergy: Building Information Modeling and

Mortenson Construction Virtual Mockups A Collaborative Solution

ENGINEERING AND TECHNOLOGY DEPARTMENT

C-2 Construction, Inc. - NAICS Codes

Abstract: BIM: A Technological Advancement in the Field of Architecture. Introduction:

ESSENTIAL CURRICULUM ARCHITECTURAL DESIGN ACADEMY

Prof. A. Ray Chaudhuri Department of Civil Engineering Adama Science and Technology University (ASTU), Adama, Ethiopia. I.D:

An Automatic Scheduling Approach: Building Information Modeling-Based Onsite Scheduling for Panelized Construction

CAREER LYNX Constructing Careers in Architecture

ESTIMATION AND PLANNING TOOL FOR INDUSTRIAL CONSTRUCTION SCAFFOLDING. *C. Kumar, S. M. AbouRizk, and Y. Mohamed

Autodesk Revit LEARNING PATH BUILDING DESIGN SUITE

Coordinating and Sharing Information with Revit Architecture and Revit Structure Best Practices!

Get to know your Autodesk Design and Creation Suites 2014

PREPLANNING METHOD FOR MULTI-STORY BUILDING CONSTRUCTION USING LINE OF BALANCE

Virtual Reality Applications in Project Management Scheduling

IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online):

Revit MEP. Autodesk Navisworks

NSW Payroll Tax Information for Contractors and Employment Agents

Streamline your design-to-cost processes with Autodesk Navisworks

Canterbury Skill Shortage List

LECTURE 10. Resource Allocation and Resource Leveling

AUTOMATED PROJECT SCHEDULE AND INVENTORY MONITORING USING RFID

Fame Design Ltd (10295) Plot # A-115/116,BSCIC Hosiery I/A, Narayangonj, Bangladesh ( , ) 18.June.2014

SRISHTI TECHNICAL SERVICES L.L.C

NATIONAL FLOOD INSURANCE PROGRAM (NFIP) SUBSTANTIAL DAMAGE/ SUBSTANTIAL IMPROVEMENT (50% RULE)

A BIM Case Study: SELCEN Mimarlik

Building Information Modeling Based Time And Cost Planning In Construction Projects

APPLICATIONS OF GIS IN INFRASTRUCTURE PROJECT MANAGEMENT

WESTERN MICHIGAN UNIVERSITY

Technique (LOBST) for a Real estate sector

Technical Assignment 2

Collaborating Across Disciplines with Revit Architecture, MEP, and Structure

Canterbury Skill Shortage List

BIM and API Extensions

Scope of Building Information Modeling (BIM) in India

CME 405 Building Information Modeling for Construction Management 3 Credits (3 Lecture Hours)

BIM Extension into Later Stages of Project Life Cycle

HOW TO LINK AND PRESENT A 4D MODEL USING NAVISWORKS. Timo Hartmann t.hartmann@ctw.utwente.nl

reality Revit check Autodesk have long Identify possible Utilize structural Tool Works Building bcg.com

Notice to Property Owners

CHECKLIST FOR SUBMISSION Construction Productivity Awards - Projects 2015

D Sample Notices to Property Owners, Sample Affidavits, and Other Material

Professional CAD System

SCHEDULING AND PROJECT MANAGEMENT

Planning & Scheduling CSTM 462. Managing a project through time and resources. The need for proper planning and scheduling.

BECKHAM Bending the Curve

ARCHITECTURAL TECHNICIAN PROGRAM (T132)

NEW APPLICATIONS OF LINE OF BALANCE ON SCHEDULING OF MULTI-STOREY BUILDINGS

BIM and Project Planning

How To Understand The Design Process

SUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER

PLUMBING MAINTENANCE WORK FOR TOILETS IN HEAD OFFICE, SUPPLYCO ESTIMATE

L_All_Vocatinal_Ed_Construction. Sector: Construction. Sr. No Specialisation Page No 1 Construction and Building Technology 02.

Analysis II Façade Redesign: Architectural Precast Panels

Outlook for the construction industry. Part One: BETA monitoring report Joinery ITO August 2013

Revit and BIM for Facilities Management

A Guide to... Home Renovation Incentive (HRI)

Performance by design. Autodesk Revit MEP

INTRODUCTION OF CONSTRUCTION MANAGEMENT INTEGRATED SYSTEM USING BIM IN THE HONAM HIGH-SPEED RAILWAY LOT NO. 4-2

APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE

EMPLOYMENT APPLICATION

Construction Technology COURSE OUTLINE

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

Historic Preservation Tax Incentive Program General information and instructions for applying for a historic tax exemption

A. O. Odior Department of Production Engineering University of Benin, Edo State.

Chapter. Restoration of Damaged Structures

Proceedings of Meetings on Acoustics

STATE OF MINNESOTA DEPARTMENT OF LABOR AND INDUSTRY 443 Lafayette Road North St. Paul, Minnesota (651) or DIAL-DLI

Ontology-Based Semantic Modeling of Safety Management Knowledge

ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY

PROJECT COST ESTIMATES & FEASIBILITIES

Estimator: Miami Estimates Business: (305) Date Entered: 04/30/2008

Automated construction schedule creation using project information model

Building Information Modeling for Masonry (BIM-M)

Exploring Ferrocement

C I T Y O F P E A R S A L L

Design. Design. Certificates. Contact Information. Full-Time Faculty. Associate Degrees. Associate in Arts Degrees. Certificate of Achievement

Transcription:

International Journal of Emerging Engineering Research and Technology Volume 3, Issue 4, April 2015, PP 67-74 ISSN 2349-4395 (Print) & ISSN 2349-4409 (Online) Integrating Building Information Modelling (BIM) and Construction Project Scheduling to Result in 4D Planning for a Construction Project with Relevant Illustrations Prakash Chandar. S¹, Dhivya Shree. G² 1 Asst. Professor, Department of Civil Engineering, S.R.M University, Chennai, India 2 Department of Civil Engineering, S.R.M University, Chennai, India ABSTRACT The present study is to understand about the benefits of 4D Planning to Construction project managers and the Construction industry. Integrating the construction schedule time with 3D modelling components and its parameters will result in 4D planning methodology. Earlier studies on 4D planning have proved to be useful for On-time delivery of the project. In turn the Construction manager is exempted from loses caused due to delay in project delivery. Here, the study involves the reanalysis of a project completed in traditional planning method and the same project is demonstrated in 4D planning method. All discrepancies of the executed project are determined and the same can be avoided while following 4D planning technique. Keywords: 4D Planning, 3D Modelling, Construction Manager, On-time delivery, Project Delivery. INTRODUCTION Indian Construction sector is yet to understand the advantages and benefits of 4D planning techniques. Only 10% of the construction projects are planned according to 4D planning methods and techniques. Rest 90% of the projects is still visualized based on 2D design documents with the additional aid of 3D modelling. This is interpreted as Building Information Modelling (BIM) which is primarily a three dimensional digital representation of a building and its intrinsic characteristics. Since the time schedule defines sequences of activities and allocates resources such as material and labor, it plays an important role in optimizing and managing a construction project. A 4D model is presented to define the order in which the segments should be constructed or demolished. The result of this step is a sequence which will be used as the process chain for simulation techniques. Then, a probabilistic 4D model is introduced by linking the 3D model of the project with generated probabilistic schedules from suitable scheduling software. Then a 4D simulation is created in suitable software which lists the sequence of works to be carried out in a date wise manner. The simulation model determines the idleness of resources and locates any potential bottlenecks. To achieve this, the developed simulation model should reflect the real world system. Live Project Details Builder: Sri Jyothi Builders Location: Urappakkam, Chennai, Tamil Nadu, India Plot Area: 1860 ft² (172.7 m²) Total Built-up Area: 4600 ft² (427 m²) *Address for correspondence: adcbaa@gmail.com International Journal of Emerging Engineering Research and Technology V3 I4 April 2015 67

Project Status: Completed Total Project Value: 1.1 Cr Planned Project Duration: 1 year Planned Start: Sept 2012 Planned Finish: Sept 2013 Actual Finish: Dec 2013 Planned Construction cost: 60 Lakhs Actual Construction cost: 68 Lakhs 4D PLANNING AND SIMULATION PROCESS Based on the fundamental attributes required by 4D models the software selection may vary depending on construction project planning practice. As per the requirements of the research on 4D planning, the conventional 2D drawings are prepared in Autocad 2010. The 2D drawings are converted into 3D model in Revit Architecture 2014 and the Time Scheduling is done in Microsoft Office project 2007. Both the 3D model and the scheduling are integrated in Naviswork Manage 2014 for creating the 4D simulation. Further the features in Naviswork Manage 2014 enable us to do Material Management and Elemental Clash Detection of the project effectively. The figure1 shows the process of 4D simulation in a schematic representation. 2D Drawings in Autocad Figure1. Schematic representation of 4D Simulation process The Figure 2 shows the typical floor plan of the Ground, First and Second floor of the project. The areas respectively are Ground Floor -1664 ft² (154.59 m²), First & Second Floor - 1666 ft² (154.77 m²) each. The 2D drawings form the basis for the development of the 3D model in Revit Architecture. The 2D drawings from Autocad can be exported to any desired 3D modelling software which supports Dwg. Format. The estimated quantities are based on the 2D drawings provided by the builder. 68 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015

Scheduling in MS Project Office Figure2. Typical Floor Plan of Ground, First & Second Floor On the basis of the information and details provided by the Construction Manager of the building, a MS Schedule is created according to the duration planned by the Builder which is shown in the figure 3. Figure3. As planned MS Project Schedule for the project Due to improper planning and scheduling the project was delayed by 3 months beyond the planned finish date. International Journal of Emerging Engineering Research and Technology V3 I4 April 2015 69

A few of the issues faced during the execution which led to delay are described below: Conflict 1: Shortage of labor at Ground Floor roof slab. Conflict 2: Procurement of Material delayed during First floor. Conflict 3: Shortage of labor during First Floor roof slab. Conflict 4: Shortage of labor at Second floor wall plastering. Conflict 5: Procurement of flooring tiles delayed at First floor. Conflict 6: Delay in connection from Electricity Board. Conflict 7: Accidental collapse of scaffolding of Exterior Wall. Conflict 8: Delay due to lack of uniformity in Bathroom wall tiles. Table1. Shortage of Labour Conflict 1, 3 & 4 Work Description Laying Rebar for GF roof slab & beam Pouring concrete and Compacting for FF roof slab & beam Plastering SF walls Work Area 923 ft² (85.7 m²) 1666 ft² (154.7 m²) 5812 ft² (540 m²) No. of Labors 2 Bar benders 4 Masons 5 Masons required/day Total Working Days 2 2 10 No. of Labors 1 Bar bender 2 Masons 3 Masons employed/ day No. of days Extended 2 2 6 Planned Start 28/02/13 09/04/13 06/08/13 Planned finish 01/03/13 10/04/13 19/08/13 Actual Start 08/04/13 20/05/13 18/09/13 Actual Finish 11/04/13 23/05/13 09/10/13 Table2. Delay in Material Procurement- Conflict 2 & 5 Material Description(First Floor) Cement Fine Aggregate Coarse Aggregate MS Rod Vitrified Tiles- Flooring Quantity 330 1272 659 2 1730 Units Bags ft³ ft³ Tons ft² Material Planned Order 06/05/13 06/05/13 06/05/13 06/05/13 20/08/13 Date Material Planned Delivery 14/05/13 14/05/13 14/05/13 14/05/13 09/09/13 Date Material Actual Order Date 14/06/13 14/06/13 14/06/13 14/06/13 10/10/13 Material Actual Delivery 04/07/13 04/07/13 04/07/13 04/07/13 13/11/13 Date No. of Days Delayed 8 8 8 8 10 Table3. Delay Due to External Agent Conflict 6 Description Electricity Board Connection Planned Start 07/06/13 Planned Finish 17/06/13 Actual Start 22/07/13 Actual Finish 20/08/13 No. of Days Delayed 15 Days Table4. Accidental Delay Conflict 7 Work Description Exterior Wall Painting Planned Start 01/08/13 Planned Finish 28/08/13 Actual Start 13/09/13 Actual Finish 24/10/13 No. of Days Delayed 10 Days Cause of Delay Mishap of Scaffolding 70 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015

Table5. Delay Due to Material Replacement Conflict 8 Material Description Ceramic Bathroom Tiles Quantity 2000 ft² (186 m²) Quantity to be replaced 600 ft² (55.7 m²) Duration for Replacement 14 Days Cause of Replacement Non-Uniformity in colour of tiles Planned Start 19/06/13 Planned Finish 27/06/13 Actual Start 30/07/13 Actual finish 27/08/13 Due to the above conflicts the Project was delivered on December 2013 instead of September 2013.The Actual Schedule of the project is re-scheduled according to the delays occurred during the execution of the project as shown in the Figure 4. These problems could have been avoided by the using the 4D Planning Technique. 3D Modelling in Revit Architecture Figure4. Actual MS Project Schedule for the project The modelling process in Revit involves a sequence of stages in which each are going to be linked to the corresponding task in the MS Schedule by Naviswork Manage. The figure 5 shows the stage wise 3D modelling of the project. Figure5. Showing the Sequential Development of 3D Model in Revit Architecture International Journal of Emerging Engineering Research and Technology V3 I4 April 2015 71

4D Simulation 4D simulation involves the step by step construction animation of the building tasks. Here, the work task from MS project office is linked to its corresponding building components. For example, the task of Laying Ground floor slab in schedule is linked or attached to its corresponding 3D slab element in the model. This integrating work of schedule and the 3D model is carried out in Naviswork Manage 2013. Figure6. 4D Simulation on day - 14/04/2013 Once all the tasks from the schedule are linked to their corresponding 3D elements, the 4D simulation can be viewed. The simulation shows the progress of tasks taking place on a Day-to-Day basis. Planning of the labor and resources can be done for any particular element of the building by simply scrolling down to a particular date in the course of construction in the simulation. The figure 6 shows the building elements which are planned to be executed as on date in green color which is differentiated from rest of the building. A video of the simulation from the start to the finish date can be exported to give a demo of the project to the client. Labor Management by Naviswork Manage The Timeliner feature of the Naviswork Manage software enables you to view the work tasks of the schedule along with the visual of the 3D model. Before executing any particular work task the required amount of Labor and Resources associated with the task is determined from the schedule. This feature of Naviswork enables to visualize the task and pre-plan the requirements without any error. This feature appears in Naviswork as shown in the figure 7. Figure7. Showing the Timeliner Bar along with the 3D model of the Building 72 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015

Material Management by Naviswork Manage Naviswork helps to manage procurement of materials efficiently at the start of every level of the building without any delay. During the 3D modelling process in Revit Architecture, extra parameters can be added to the 3D elements such as Material Order Date, Material Order status, Material Delivery Date, Material Delivery Status & Material Location under desired property section. As the construction progresses, the dates or values can be manually entered in the above parameters. Revit enables to create a schedule automatically as the values or dates are entered in the property section. The figure 8 shows the schedule created by Revit with property box showing the values entered for the parameters under construction sub-division. The schedule can be exported to excel if desired. Figure8. Showing the dates in Revit property section and its Schedule Naviswork Manage synchronizes with Revit at every stage of construction as the dates and values are entered in Revit to manage the material procurement. Naviswork creates a separate selection set for the parameters like Material Order Date, Material Order status, Material Delivery Date, Material Delivery Status & Material Location and its corresponding dates and values such as Material Order status- Not Ordered, Material Delivery status Not Delivered. And on selecting a particular selection set, Naviswork high lightens the selection in the 3D visual screen. The figure 9 shows the Material Order Date for First Floor which is to be ordered on 24/04/13. Figure9. Showing the Selction set Material Order Date 24/04/13 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015 73

RESULTS AND ANALYSIS The completed project is demonstrated in 4D technique and each stage of construction is considered for investigation. Primarily, a MS project schedule was created according to the planned duration of the builder. The delay of schedule in each work task is computed with area, quantity and is shown in the tables above. Another MS project schedule is created to show the actual work schedule with the delay. The reason for the delay is found to be Lack of planning and communication between the designing and execution team. By the use of 4D technique, the changes in documentation can be updated in simulation from time-totime. This keeps the site personal informed of the changes done in the schedule and take appropriate action for the work task. Further, the simulation helps to visualize the construction tasks in a better way. CONCLUSION This research proposed a simulation-based 4D modelling approach for planning and scheduling of Residential projects by integrating simulation and 4D modelling techniques. This research investigated the applications of 4D modelling for sequence assessment in the planning stage of Residential projects. This research investigated a new approach integrating simulation with 4D modelling to create a probabilistic 4D model. This approach can be a useful system to avoid delay in project delivery and hence can also avoid loses incurring due to the delay. REFERENCES [1] Jan Tulke and Jochen Hanff, 4D Construction sequence planning New process and data model, Bauhuas University, Germany. [2] Anamika Sharma, An Interactive Visual Approach to Construction Project Scheduling, Marquette University, 2009. [3] Lingyun Wang, Using 4D Modeling To Advance Construction Visualization In Engineering Education, CIC, Pennstate, May 2007. [4] Peter Smith, BIM & Project Cost Manager, ICEC, University of Technology Sydney, Australia, 2007. [5] Mohamad Kassem, Trevor Brogden, and Nashwan Dawood, BIM and 4D planning: a holistic study of the barriers and drivers to widespread adoption, JCEPM, November 14, 2012. [6] Satish A. Pitake and Prof. Dhananjay S. Patil, Visualization of Construction Progress by 4D Modeling Application, IJETT, Volume 4 Issue 7, july 2013. [7] Ahmad Doriani, Simulation-Based 4D Modeling for Planning and Scheduling of Elevated Urban Highway Reconstruction Projects, Concordia University, Canada, 2012. 74 International Journal of Emerging Engineering Research and Technology V3 I4 April 2015