The ACR : Advanced Design Features for a Short Construction Schedule



Similar documents
Advanced Construction Methods for New Nuclear Power Plants

Chapter 3 Pre-Installation, Foundations and Piers

CONSTRUCTION EXPERIENCE FROM MODULAR NUCLEAR POWER PLANTS

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Hanson Building Products. precast basement solutions

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION

SikaProof A Technology

Hitachi s Involvement in Nuclear Power Plant Construction in Japan

SECTION 1 GENERAL REQUIREMENTS

Building New Generation Nuclear Plants Worldwide : AREVA's Experience

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

The minimum reinforcement for the stem wall is the placement of:

6 RETROFITTING POST & PIER HOUSES

MULTI-RESIDENTIAL BUILDING SOLUTIONS

Excerpts from the Canadian National Building Code (NBC)

Ecoflex Wall Penetration Systems: An efficient, sustainable solution for penetrating concrete or block walls

10 Nuclear Power Reactors Figure 10.1

Buildings Construction Procurement Strategy

Machine Foundation Design

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC October 27, 2015 Session 26

Residential Deck Safety, Construction, and Repair

Air-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association

WATERPROOFING SikaProof -A TECHNOLOGY

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

Structural Assessment Report

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Electrical. This section applies to the design and installation of building power distribution systems.

Embedded Parts Introduction - Anchors

High Capacity Helical Piles Limited Access Projects

Chaudière Crossing Bridge Rehabilitation

University of Missouri Hospitals and Clinics. Structural Repair and Protection of Post-tensioned Parking Garage

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

Requirements for Building Application Submission

TABLE OF CONTENTS. INTRODUCTION... 5 Advance Concrete... 5 Where to find information?... 6 INSTALLATION... 7 STARTING ADVANCE CONCRETE...

Mark Cramer Inspection Services, Inc.

STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM

Page & Turnbull imagining change in historic environments through design, research, and technology

necessary for years of satisfactory service. SmartBlock insulating form concrete walls share the

Whitepaper. Modular Substation Cable Termination Design. Author: Allan Bozek P.Eng, MBA, EngWorks Inc, Calgary, Canada

Engineers at Liftech designed the structure of the first container crane and have designed and reviewed thousands of container cranes since.

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Built to Last. Built for Beauty. Good. Solid. Logix. TM

Scope of EN Clarification Document

How To Build A Luxury Apartment Complex In London

Lighthouse Engineering, L.L.C.

Safe & Sound Bridge Terminology

1.2 Advantages and Types of Prestressing

Construction Technologies Career Field Pathways and Course Structure

FORM DESIGN. easy to work with, and generally available.

INSTALLING SEISMIC RESTRAINTS FOR MECHANICAL EQUIPMENT

3Dcities INDIA. Architecture and Engineering Outsourcing Company since 1999

Since it was established in 1989, with a small manufacturing base in Qwa Qwa and a hire yard in Botswana, Uni-Span

Technologies & Management Systems that Work: Current Best Practice in Nuclear New Build

Olilo's AEC Design Services. SrinSoft Inc, Partners of

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

Wall Thinning Trend Analyses for Secondary Side Piping of Korean NPPs

Structural Failures Cost Lives and Time

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Installation PowerPoint for Grasscrete Formers

AREVA: supply chain network principles and company s vision

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

Moving Small Mountains Vesuvius Dam Rehab

HOW DOES A NUCLEAR POWER PLANT WORK?

LOADING DOCK EQUIPMENT. A. Section Concrete Forms and Accessories: Placement of anchors into concrete.

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

STRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA

NAPCS Product List for NAICS 54134: Drafting Services

Westinghouse AP1000 PWR and the Growing Market for New Nuclear Power Plants

ModuSec. Secure and efficient IT room solutions. Turnkey Modular Construction Fast clean build to any size or shape

SnoTrace KSR Surface Snow and Ice Melting INSTALLATION PROCEDURES

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

Stormwater/Wetland Pond Construction Inspection Checklist

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

Cody Park One of Ark s high integrity data centre campus sites

SECTION VIBRATION AND SEISMIC CONTROLS FOR ELECTRICAL SYSTEMS

If stepping is required, step at 180mm as seen in this picture.

Miller Engineered Solutions Customized Fall Protection Solutions. NEW! Now featuring Rigid Rail Systems

INSPECTION FINDINGS. for. Paragon Condominiums 2102 W 31 st Avenue Denver, Colorado. Inspection Date: August 8, Perfonned By: Drew Schneider

REHABILITATION PACKAGE 1-a

Issue of the Guidelines on Prevention of Water Seepage in New Buildings

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Residential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center

PRODUCT AND ENGINEERING MANUAL

Group TRAFFIC MANAGEMENT SPECIALIST ACCESS WAY SOLUTIONS CREATIVE SOLUTIONS TO COMMON CHALLENGES. Products

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

The Impact of Market Demands on Residential Post-Tensioned Foundation Design: An Ethical Dilemma

Slip-Form Application to Concrete Structures

Transcription:

Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for a Short Construction Schedule Medhat Elgohary and Neville Fairclough Atomic Energy of Canada Limited Sheridan Park Research Community Mississauga, Ontario, Canada ABSTRACT Through their worldwide operating records, CANDU Nuclear Power Plants have repeatedly demonstrated safe, reliable and competitive performance. Atomic Energy of Canada Limited s (AECL) Advanced CANDU Reactor - the ACR - is the genesis of a new generation of technologically advanced reactors founded on the CANDU reactor concept. The ACR is the next step in the evolution of the CANDU product line. The ACR products (ACR-700 and ACR-1000) are based on the proven CANDU technology and incorporate advanced design features and technologies. Currently there are fourteen single unit CANDU 6 reactors operating or under construction worldwide. The first CANDU 6 reactors went into service in Canada and overseas in the early 1980s. The latest two units are at the Qinshan site in China. Prior to the Chinese units, construction had been relatively conventional. The project schedule for the first Chinese unit was 72 months with a 47 month construction period duration from First Concrete to Fuel Load. The first unit was completed 38 days ahead of schedule. Building on the successful CANDU construction at Qinshan, the ACR-700 is designed with constructability considerations as a major requirement during all project phases from the concept design stage to the detail design stage. A project schedule of 48 months has been developed for the nth ACR unit with a 36 months construction period from First Concrete to Fuel Load. This paper describes some of the advanced design features implemented in the reactor building design in order to achieve this short construction period. These features include large volume concrete pours, prefabricated rebar, composite structures, prefabricated permanent formwork and significant modularization and prefabrication. KEY WORDS: AECL, CANDU, ACR, nuclear, module, construction, constructability, parallel, prefabricate, construction, strategy, schedule, optimize, modularize, modularization. INTRODUCTION CANDU 6 reactors went into service in Canada and overseas in the early 1980s. Currently there are fourteen single unit CANDU 6 reactors operating or under construction worldwide. The latest two units are at the Qinshan (Phase III) site in China. Prior to the Chinese units, construction had been relatively conventional. For the Qinshan plant, advanced construction methods were implemented with minimum changes to the reference design. This resulted in a 72 month project schedule for the first Chinese unit with a 47 month construction period duration from First Concrete to Fuel Load. The first unit was completed 38 days ahead of schedule. For the nuclear option to be competitive in the future, even shorter construction schedules are essential. Considering the construction method during the conceptual design stage of the project makes this possible. The ACR nuclear power plant is designed with constructability considerations as a major requirement during all project phases from the concept design stage to the detail design stage. An ACR construction strategy that utilizes advanced construction techniques has been developed based on the successful implementation of these methods in the Qinshan CANDU 6 plant in China (Reference 1). Continuing to develop these advanced construction techniques and applying them to the ACR design enables the construction schedule to be further reduced. This paper reviews the ACR construction strategy and schedule and presents some of the advanced design features implemented in the reactor building design that will ensure achieving the ACR short construction schedule. CANDU and ACR are registered trademarks of Atomic Energy of Canada Limited (AECL) 1

PROJECT SCHEDULE The major milestones considered in the project schedule are: Contract Effective Date (CED) refers to the date the contract is in place. First Concrete (FC) refers to the start of construction of the Reactor Building base slab. This requires a construction license from the regulatory body. Fuel Load (FL) refers to the activity of the first loading the fuel in the reactor. In-Service (I/S) refers to the in-service date for the unit. Figure 1 illustrates the project schedule evolution for CANDU 6 plants and the schedule for the ACR-700 plant. As mentioned before, for Qinshan CANDU Unit 1, the construction period, FC to FL is 47 months with total project duration of 72 months. For an optimized CANDU 6 plant with more modularization and prefabrication, this construction period (FC to FL) can be further reduced to 42 months. Building on the Qinshan experience and further utilization of advanced construction methods, the ACR 1 st unit construction period is 40 months, which can be further reduced to 36 months for the nth unit. CED FC FL IS 17 47 8 CANDU 6 Qinshan 72m CANDU 6 Optimized ACR 1/2 ACR 3/4 ACR n th CONSTRUCTION STRATEGY CED FC FL IS 12 42 6 60m CED FC FL IS 12 40 8 60m CED FC FL IS 12 38 8 58m CED FC FL IS 6 36 6 48m Figure 1 Simplified Schedule Comparison The reactor building consists of a steel-lined, pre-stressed concrete containment structure and a reinforced concrete internal structure supported on a reinforced concrete base slab. The containment structure provides an environmental boundary, biological shielding, and a pressure boundary in the event of a loss-of-coolant accident. It is the principal component of the containment system. A reactor building plan view and section view are shown in Figures 2 and 3, respectively. The containment structure perimeter wall is separate from the internal structures. This provides flexibility in construction and eliminates any interdependence between the containment wall and the internal structures. The internal concrete structures include the reactor vault walls, the fuelling machine vault walls, the moderator enclosure walls, the steam generator enclosure walls, the heat transport pump support walls and floors, the reactivity mechanism floor, and intermediate floors. The internal structures also include some steel floors to provide equipment support, pipe restraints, walkways and stairs. The construction strategy developed for the ACR reactor building comprises the following: Open Top construction technique using a Very Heavy Lift crane, Paralleling of construction activities, Extensive modularization and prefabrication, and Implementation of advanced construction technologies. This construction strategy was successfully implemented in the CANDU 6 Qinshan project. The same strategy is adopted for the ACR-700. However, in order to meet a shorter schedule, it is necessary to increase the paralleling of construction activities, the level of modularization and prefabrication and the utilization of advanced construction technologies. 2

Figure 3 Section View of Reactor Building Figure 2 Plan View of Reactor Building MODULARIZATION In order to achieve maximum utilization of paralleling of construction activities, the systems inside the reactor building are designed and built as modules. In this case, a large volume of mechanical/electrical work that is traditionally done on site is shifted out of the reactor building for fabrication into modules. Therefore, the mechanical/electrical work can be done in parallel with the civil program. To realize the maximum gain from modularization, as much equipment, piping, and interfacing systems are included in the modules prior to installation into the building. Generally, each room consists of a complete module. In most cases, the room floor is the main base for the module allowing inclusion of everything in the room as part of the module before installation into the building. ADVANCED CONSTRUCTION TECHNOLOGIES One of the major elements of the construction strategy is the use of advanced construction technologies in the design and construction of the ACR-700 (References 2, 3 and 4). These advanced construction technologies include: Large Volume Pours - With the development of low-heat concretes, large volume pours are practical and have major benefits. Pours up to 6 m deep will be utilized and vertical bulkheads minimized on areas such as base slab and the concrete internal structure major walls. Prefabricated Rebar - Rebar installation by individual bar placement is very time-consuming and produces long durations for critical path activities. For such areas as the base slab, containment walls and internal structural walls, rebar assemblies are designed for maximum prefabrication. Use of Climbing Forms - For improved schedule and precision of poured concrete, climbing forms will be used for both the reactor building containment and internal structure walls. Use of Composite Structures - The composite structures being considered are essentially large steel fabricated box sections that are later filled with concrete for compressive strength, shielding and seismic qualification. These structures, when combined into modules have the advantage of eliminating formwork and rebar. 3

Use of Prefabricated Permanent Formwork - In conventional construction, equipment is installed after the completion of the floor above. This method is time consuming as no work at all, including installation of equipment can be done until all the shoring has been removed. In the case of heavy slabs, removal of shoring cannot be done before 7 days, preferably 14 days. In addition to the concrete curing duration, installation and removal of conventional shoring further impedes work in the room. In these areas it is more practical to design a bridging system (usually steel containing prefabricated rebar) that will span over the top of the room and will act as the formwork. Use of Automatic Welding - Greater use of automatic welding will lead to reduced durations for welding, improved weld quality and reduced weld repair. This will be applied to the steel containment liner and all piping systems particularly large size heavy wall piping. 3D CADDs - (Computer Aided Design and Drafting) provides consistent, high quality output with minimal field interferences due to clash checking capabilities and therefore reduction/elimination of rework. In addition, 3D CADD has been developed to prepare construction sequences to match the schedule through links with scheduling software packages (4D visual models). REACTOR BUILDING CONSTRUCTION METHOD The construction method for the reactor building was established by evaluation of various options against the project requirements. Based on the evaluation, the vertical installation approach was chosen as the method of construction for the reactor building. This vertical installation approach is summarized below. A simplified construction sequence is shown in Appendix A. Reactor vault & internal structure walls all rise together using standardized climbing formwork, forming a honeycomb structure conventional concrete & rebar construction. Initially no floors so jump forming proceeds quickly. The vault walls, a rectangular portion of the internal structure contains the reactor assembly at base slab elevation, are key to the center of the internal structure. Walls continuous from base slab to top of the internal structure. Remaining internal structure around vault divided into 12 vertical, roughly rectangular compartments with one curved side, which is the containment wall contour. Both containment and internal structure walls jump formed with reinforcing steel suitable for prefabrication. See Figure 4 shows the 12 major vertical installation compartments. All compartments filled with modules or equipment installed through the open top using heavy lift crane. Modules, which include floors, are attached to the internal structure walls but not the containment wall. Floors are part of the module and generally of steel beam construction. These floor modules will rest on brackets welded to embedments. In most cases the steel floor will directly become the skid base and it would be delivered to site as a unit. In other cases the skids and equipment can be delivered to site and installed on the steel floor prior to installation. Floors requiring concrete for shielding will be filled with concrete after installation of the module. Where monolithic floors are required to stiffen the overall internal structure, these will be added after the walls. Typical methods of connections to the internal structure walls are shown in the next section. Normally two to four levels of modules/equipment in each vertical installation compartment. During layout, standardized floor elevations developed for ease of movement between vertical installation compartments. Wiring and service connections are routed vertically to service each particular vertical installation compartment. Wiring will travel vertically up or down the vertical compartment and be connected to wall containment penetrations designed to serve the vertical compartment. Temporary weather covers will be installed on a compartment basis during the open top construction phase to provide dry working conditions. 4

MODULE CONNECTIONS Figure 4 Plan View of Reactor Building Vertical Installation Compartments From a structural point of view, there are several types of module connections to the internal structure. An example of a module located on the base slab (the lowest level of the reactor building) is illustrated in Figure 5, and it s installation sequence is provided in Figure 8. A typical example of modules supported from the building internal structure walls, not requiring concrete in the module base, is illustrated in Figure 6 and it s installation sequence is provided in Figure 9. A typical example of modules supported from the building internal structure walls, requiring concrete in the module base, is illustrated in Figure 7 and it s installation sequence is provided in Figure 10. Figure 5 Example of a Module on the Base Slab (see Figure 8 for installation sequence) Figure 6 Example of a Module Supported from Internal Structure (Not Requiring Concrete in Base) (see Figure 9 for installation sequence) Figure 7 Example of a Module Supported from Internal Structure (Requiring Concrete in Base) (see Figure 10 for installation sequence) 5

Step A: The base slab fill pour is not initially poured to the finished elevation in the areas where modules are located. Embedments are provided in the fill pour for connection to the module base. Step A Step B: The module is lowered vertically and placed on embedments in the recessed area of the base slab fill pour. The module base is shimmed to ensure the floor is flush with the adjacent floor. The module base is then welded to the embedment. Step B Step C: If required additional reinforcing is provided and then the recessed area in the fill pour is filled with concrete to be flush with the top of the module base. Additional anchors are provided to embedments in the walls for seismic bracing near the top of the module. Step C Figure 8 Sequence for Installation of Module onto Base Slab (Lowest Level of Vertical Installation Compartment) 6

Step A: When the internal structure walls are jump formed, embedded parts are provided for angle support brackets. Step A Step B: Angle support brackets are attached into the embedded parts. Step B Step C: The module is set in place in the vertical installation compartment to the required elevation using shimming on the angle brackets. Step C Figure 9 Sequence for Installation of a Steel Frame Floor Module into a Vertical Installation Compartment (Concrete not required in the floor) 7

Step A: When the internal structure walls are jump formed, embedded parts are provided for angle support brackets and recesses are provided in the concrete for access to rebar connections. Step A Step B: Angle support brackets are locked into the embedded parts ready to accept the prefabricated permanent formwork floor (PPF). Step B Step C: The PPF is installed vertically and placed on beams, supported by the angle support brackets. The beams distribute the load to the brackets and seal the PPF to the wall for later concreting. Reinforcing in the PPF is connected to the exposed reinforcing in the walls. Step C Step D: The module is lowered onto the PPF and set to elevation, spacers are provided to ensure the module floor is flush with the adjacent floors. Step D Step E: Concrete is poured to fill the PPF, recesses in wall and up to the top of the module base, flush with the adjacent floors. Additional anchors are provided to embedments in the walls for seismic bracing near the top of the module. Step E Figure 10 Sequence for Installation of a Floor/Module into a Vertical Installation Compartment (Concrete required in floor for shielding or structural purposes) 8

CONCLUSIONS The ACR-700 is designed using the latest construction methods to achieve a 36 month construction period for the nth replicated unit. A strategy has been developed based on the proven successful implementation in the Qinshan project. This strategy is further extended for implementation in the ACR project to achieve the shorter schedule and reduce project costs and improve quality. One of the key construction strategies that assist in achieving the short construction schedule is prefabrication and modularization. Using the vertical installation method, the modules are installed into the reactor building using the very heavy lift crane. Various connection details for attaching the modules to the internal structure walls were developed to illustrate the feasibility of the construction concept. REFERENCES 1 Petrunik, K., Construction of CANDU in China, A China-Canada Success Story, Proceedings of the 13th Pacific Basin Nuclear Conference, Shenzhen, Guangdong, China, October 2002. 2 Elgohary, M., Choy, E., Yu, S.K.W., Advanced Construction Methods in ACR, Proceedings of the 13th Pacific Basin Nuclear Conference, Shenzhen, Guangdong, China, October 2002. 3 Choy, E., Elgohary, M., Fairclough, N., Yu, S.K.W, Impact of Modules on the ACR Construction Schedule, Proceedings of the 11th International Conference on Nuclear Engineering, Tokyo, Japan, April 2003. 4 Hopwood, J.M., Love, I., Elgohary, M., Fairclough, N., Next Generation CANDU: Conceptual Design for a Short Construction Schedule, Proceedings of the 10th International Conference on Nuclear Engineering, Arlington, VA, USA, April 2002. 9

Appendix A TYPICAL VERTICAL INSTALLATION COMPARTMENT CONSTRUCTION (Reactor Building containment sectioned on all views and internal structure sectioned on last four views) Construction sequence from month 4 to month 36 of the nth unit construction period. Month 4 Month 36 10