RECENT FAILURES OF LARGE CORRUGATED METAL PIPE SPILLWAYS



Similar documents
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

Stormwater/Wetland Pond Construction Inspection Checklist

Wastewater Capital Projects Management Standard Construction Specification

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

REHABILITATION OF FAILED CORRUGATED METAL PIPE SPILLWAYS PRESENTED AT JUNE 1996 REGIONAL CONFERENCE MID-ATLANTIC COUNCIL FOR SAFE DAMS

Section 2100-Trenching and Tunneling

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

DIVISION 4300 STORM DRAINAGE

Moving Small Mountains Vesuvius Dam Rehab

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

DIVISION 2 - SEWERAGE AND DRAINAGE SECTION STORM DRAIN SYSTEMS PART 1 - GENERAL

SECTION NONREINFORCED CONCRETE SEWER PIPE

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

SECTION STORM DRAINAGE TABLE OF CONTENTS

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

Section SEWER PIPE INSTALLATION AND TESTING

Protecting Your Pools Crack Treatments

SECTION STORM DRAINAGE SYSTEM

Meeting the Challenge of Pipeline Emergency Repair

Emergency Spillways (Sediment basins)

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SECTION STORM DRAIN SYSTEM

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Appendix B.1. NRCS-MD Code No. 378 Pond Standards/Specifications

SECTION 724 PIPE CULVERTS

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

STANDARD SPECIFICATIONS & CONSTRUCTION DETAILS MANUAL SECTION 5 - STORM DRAINAGE Design

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

SECTION ABANDONMENT OF SEWER MAINS

C. Section TESTING LABORATORY SERVICE.

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

Baton Rouge Foundation Repair

Installation of Large Diameter Buried Pipes

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA (7300 Short Road, Serene Lakes)

STORMWATER MANAGEMENT CHECKLIST

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

CHAPTER 6 - SANITARY SEWER

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

NRCS Overview. National Dam Safety Program Technical Workshop #19 February 22-23, 2012

SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Minimum Design Criteria for the permitting of Gravity Sewers

PVC PIPE PERFORMANCE FACTORS

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

SECTION PRECAST CONCRETE UTILITY STRUCTURES

Specifications for Residential Property Owners Connection to New Public Sewer

Foundation Water Problems. An Overview and Discussion of some Causes and Cures for Water Infiltration into Basements and Foundation Structures

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

SECTION 3 SANITARY SEWER DESIGN

817 - PIPE CULVERTS, EROSION PIPE, STORM SEWERS, SANITARY SEWERS & END SECTIONS SECTION 817

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SECTION PRECAST CONCRETE STRUCTURES

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

NAPCA BULLETIN APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

X Planning X Quality X Maintenance & Operations

SECTION 7- STORM SEWER

CCU Engineering Specifications. Section PRECAST CONCRETE PRODUCTS

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

FY08 SEWER POINT REPAIRS BID TABULATION

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

February 4, Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth

Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control

BEST MANAGEMENT STANDARDS FOR FOUNDATION REPAIR MARCH 2003 REVISED JUNE 13, 2012

SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

ENGINEERED SOLUTIONS. A2 Liner Pipe for Trenchless Technology

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

PIPE INSPECTION AND REPAIR. Larry Ritchie

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

Local Road Assessment and Improvement Drainage Manual

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Section 402. STORM SEWERS

SECTION 9. All sewer laterals shall tie into the sewer main lines unless approved by the City Engineer.

Safe & Sound Bridge Terminology

CLIFTY CREEK PLANT MADISON, INDIANA

Waste Collection Systems

Transcription:

RECENT FAILURES OF LARGE CORRUGATED METAL PIPE SPILLWAYS Harald W. Van Aller,P.E. Geotechnical Engineer Maryland Dam Safety Division ABSTRACT Many new stormwater management dams in Maryland have been constructed with large diameter corrugated metal pipe (CMP) spillways. Several of these dams, all dry ponds that impound water only during storms, have recently failed by piping of embankment soils along the outside of the conduit or through leaky joints. Random inspections have revealed serious deficiencies in many of the structures. Inadequate construction inspection of critical items has contributed to the failures. Several case histories are discussed. INTRODUCTION During the lastten years,more than 400 stormwater management ponds have been designed and built in Maryland with large (48-inches and larger in diameter) pipe conduits. In general, these ponds are low hazard structures less than 30 feet high. As such, they are exempt from Maryland s waterway construction permit requirements if the design is approved by a local Soil Conservation District. Although such local approval requires adherence to minimum design and construction standards that were developed by the USDA Soil Conservation Service, detailed construction inspection by a qualified engineer is often neglected, Approximately 200 of these ponds have spillways constructed of large diameter corrugated metal (steel) pipe, with some more than eight feet in diameter. In the last two years, the Dam Safety Division has investigated more than a dozen failures of these structures. The failures range in severity from complete failure of the dam and loss of the pool to leaking joints and indications that piping of embankment soils has been initiated. During the same period of time, about 170 ponds were designed with large diameter reinforced concrete pipe spillways. Only two failures of RCP spillways have been investigated by the Dam Safety Division. One of these had leaking joints that were repaired by injection of hydrophilic grout. The other structure required complete removal and replacement of the spillway conduit. INSPECTION PROGRAM The Dam Safety Division recently inspected more than a dozen small dams constructed with CMP spillway conduits. Some of these inspections were conducted with a local CMP manufacturer in order to determine if there are inherent problems with CMP spillways or whether the problems are construction related. In addition, after numerous deficiencies were noted, we enlisted the help of local publics works officials to perform inspections of 341

additional dams. In all, more than 40 new dams with large CMP spillways have been inspected, and more inspections are in progress. Two complete dam failures were investigated. These resulted in loss of impounded stormwater and severe environmental damage below the dams. Both structures were apparently constructed by installation of the conduits into near vertical trenches cut into the partially completed embankment fill and/or foundation soils. Both failures resulted from loss of embankment soil from along the outside of the conduit by seepage flow, a process termed piping. We found that very few installations of large CMP conduits are in accordance with generally accepted criteria for pipes through dams, Many of the problems we observed are most likely due to poor installation, such as: 1, Poor compaction of fill under the haunches of the pipe. Unlike rigid (concrete) pipes which are designed to support external loads with minimal deformation, CMP conduits are flexible, and are designed to deform slightly which allows the surrounding soil to provide most of the support for the embankment fill above the conduit. In practice, it is very difficult to obtain adequate compaction under the haunches of the pipe to provide the necessary support, especially with large diameter pipes. If the contractor is overzealous in his efforts to compact the soil in this zone, there is a possibility that the relatively lightweight pipe will be lifted from the subgrade soils, leaving an open void under the conduit, Inadequate support under the haunches of the pipe will likely result in eventual failure of the conduit. In addition, voids in the fill under the pipe are avenues for seepage flow, increasing the possibility of a piping failure. 2, Pipe was installed in trench with near-vertical sides cut through partially completed embankment fill. Some contractors contend that it is more cost effective to place the majority of embankment fill with large equipment and to cut a trench through the fill and install the pipe. However this can result in poor compaction of the pipe backfill because much of the work is hand labor in a confined area, especially in the haunch area as described above, and thin fill layers are necessitated by the use of lightweight compaction equipment. In addition, there is a potential for transverse cracking of the dam embankment due to differential settlement between the hand placed backfill and embankment fill placed with heavy equipment, increasing the possibility of a piping failure. Also, pipe backfill placed in a trench tends to reduce loads on the pipe by a process known as arching. While desireable from a structural standpoint for design of the pipe, this phenomenon may result in low soil pressures near the pipe. If the soil pressures are less than the anticipated hydrostatic loading, there is a potential for the pond water to cause serious cracking of the embankment by a process termed hydraulic fracturing. 3. Watertight joints were not obtained. Our experience indicates that watertight joints are difficult to obtain in the field. This can result from: Damaged pipe ends which prevent proper alignment of pipe sections. 342

Gaskets notinstalled joints, wrong type of gaskets used, or gaskets not lubricated properly which causes uneven gasket contact. Helically corrugated pipe ends not re-rolled to provide concentric channels for proper gasket contact. Incorrect joint connecting bands installed. Dimple or narrow hugger bands do not provide the desired level of joint integrity. Construction inspection was performed on some, but not all, of these structures while they were being built. However, the inspector was often a soils technician, with limited dam construction experience, retained by the contractor to simply test the fill for compliance with the project specifications. The inspector was usually not on site full-time, so that certain critical items, such as joint construction, gasket details, compaction of the fill under the haunches of the pipe, etc. were not observed, Interviews with construction and inspection personnel for some of the projects indicates that there is sometimes a lack of communication between the inspectors and the engineers, often because the inspector worked for another company and was not under the direct supervision of the design engineer, Also, since most of the inspectors were on site to simply observe and document construction techniques, the inspector had no control over the project, In one instance, the inspector duly noted in his report that the contractor was installing incorrect gasket materials into the joints. However, this problem was not corrected at the time of construction and several years later the pipe is in the process of failure due to loss of fill material by piping into the leaky joints. RECOMMENDATIONS Sowers (1974) observed that the most common failures of dams are those of small reservoirs, in part because the owners of these structures are /rj/ed into complacency by the very insignificance of their structures. /t is difficu/t for them to realize the damaging effects of the fai/ure of sma// reservoirs. He further states that those responsible for design... of such reservoirs are interested primari/y in the [function) of the reservoir rather than with the structure (itse/f]. They... are rarely dam designers and builders. Therefore, the smaller dams often are not given the benefit of experienced design, adequate construction supervision... The consequences are disastrous. Itis obvious that detailed construction inspection by qualified geotechnical engineers is essential for proper construction of small dams. The construction industry needs to have better trained, full-time construction inspection under the direction of the design engineer. The designer should be a geotechnical engineer experienced in dam design and construction. In addition to soil compaction specifications, the inspector should be familiar with pipe specifications and should be able to reject deficient installations on the spot. Too often, inspector is under contract only to observe and document installation and problems that are documented in daily reports are not forwarded to the engineer until too late to remedy. 343

Use fly-ash based controlled low strength material or flowable fill to backfill under the haunches and sides of the pipe. Flowable fill is a low strength material that can be delivered to the job site in a standard ready-mix concrete truck. It can be formulated to have compressive strengths in the range of 30 to 1200 psi. Flowable fill in the range of 30 to 150 psi has characteristics similar to that of compacted fill, and can easily be removed by common excavation techniques at a later date if needed. The material is self-levelling, and is simply poured into an excavation, where it fills the voids under the pipe with no compactive effort.itisrecommended thatitbe placedtoa leveltoatleasthalfwayup the sides of the pipe, Due to the potential for significant shrinkage, it is recommended that the flowable fill be placed in two pours, with sufficient time between then to allow the first pour to cure. The pipe conduit must be anchored to prevent flotation. Compact the fill that will be under the haunches of the pipe before installing the pipe, and use a special excavator bucket to conform the bottom of the trench to the contour of the conduit. This may reduce the possibility voids under the pipe. Better inspection during construction to ensure that joints are watertight, from the time the joints are made through completion of filling operations. Since watertight joints are essential for a safe conduit through a dam embankment or its foundation, pressure testing of each joint before continuing with installation may be warranted. This is commonly done for sewer installations. Improve joint design. Soil Conservation Service pond construction standards in Maryland now requires that pipes with a diameter of 24-inches or more be connected by a 24 long annular corrugated band using rods and lugs. A 12 wide by 3/8 thick closed cell circular neoprene gasket is to be installed on the end of each pipe for a total of 24. Perhaps the use flanged joints instead of connector bands and o-ring gaskets should be considered. Have pipe manufacturers match mark pipe sections. CMP manufacturers in Maryland typically custom fabricate pipe for pond projects in one continuous section which is then cut into lengths that can be shipped to the job site. Since the cuts are not always perpendicular to the pipe axis, misalignment of the joints is inevitable if the same two pieces are not installed adjacent to each other. This is more of a problem with large diameters, since a small cutting error translates to a sizeable alignment error. Match marks will help with alignment of joints in field and result in a greater likelihood of watertight joints. Eliminate anti-seep collars and use filter diaphragms to control seepage and piping along the conduit. It is interesting to note that the two structures that failed completely were built with anti-seep collars which did not prevent loss of soil by piping. It is a common misconception that the collars will prevent seepage along the conduit. Thus, there is a temptation to skimp on compaction of backfill material and to rely on the collars to prevent failure. Properly designed filter diaphragms, on the other hand, will control seepage that may occur along the outside of the conduit. A filter diaphragm is a zone of filter material (sand and gravel) that completely surrounds the pipe. It is generally located near the downstream end of the conduit. (SCS 1985) The filter must be designed in accordance with standard soil mechanics filter criteria. (Talbot 1985, 1990) 344

CONCLUSIONS A large number of pond and dam failures can be attributed to problems with the conduit. Since all of the failures that we observed were located along the spillway pipe, consideration should also be given to eliminating conduits through dam embankments and foundations wherever possible, perhaps by utilizing weir structures instead of conduits, If large CMP spillways are to continue to be used in dam construction, new standards need to be developed. These could include: elimination of anti-seep collars and use of filter diaphragms to control seepage that may develop along the outside of the conduits; better joint design to ensure watertightness; shaping the bottom of the trench to precisely fit the circumference of pipe to improve the support of the pipe haunches; and the use of flowable fill material for pipe backfill. In addition, installation of pipes in vertical trenches excavated through partially completed dam embankments contribute toward failure potential and the technique should be avoided, REFERENCES American Concrete Pipe Association, (1992) Design Stormwater Pipelines, Greenbelt, Maryland Genstar Stone Products Company, (1990) Ready Mixed Life Seminar, Buried Wastewater and Flowable Fill, Hunt Valley, Maryland. Manzi, Joseph E,, (1984) Construction Inspection: Improvin the Benefits Received, Professional Inspection of Construction, edited by Stephen 6, Quinn, AS 8 E, New York, p, 11-19 Martin, Ray E., (1989), Seepage Control Along Conduits Penetrating Embankment Dams, presented at the 1989 Southeastern Association of State Dam Safety Officials Conference National Ready Mixed Concrete Association (1989), CIP 17: Flowable Fill Materials, Silver Spring, Maryland Shields, David R,, (1985) Geotechnical Inspection for Small Dams: How Small is Too Small?, Hvdro Review Maqazine, Fall issue. Sowers, George F., (1974) Dam Safety Legislation: A Solution or a Problem, Proceedings of Engineering Foundation Conference at New England College, ASCE, New York, p.65-100 Talbot, J. R. and Ralston, D. C. (1985), Earth Dam Seepage Control, SCS Experience, SeeDaGe and Leakaqe from Darns and Impoundments, ASCE Geotechnical Engineering Symposium, edited by R.L. Volpe and W.E, Kelly, New York, p. 44-65. Talbot, James R., (1990) SCS Filter Studies, Design Procedures and Experiences with Filter Diaphragmsn, Association of State Dam Safety Officials Mid-Atlantic Regional Technical Seminar on Seepacre in Dam Safetv: Evaluation and Remediation, Baltimore, Maryland USDA Soil Consewation Service, (1992) MD-378, Standards and Specifications for Ponds, Annapolis, Maryland USDA Soil Conservation Service, (1985), Technical Release No. 60 (TR-60), Earth Dams and Reservoirs, Washington, DC, p. 6-7 through 6-9 USDA Soil Conservation Service, South National Technical Center, (1985), Technical Note 7091 Dimensioning of Filter Drainaqe Diaphragms for Conduits Accordina to TR-60, Fort Worth, Texas Van Aller, Harald W., (1990) Filter Diaphragm Design Considerations, Association of State Dam Safety Officials Mid-Atlantic Regional Technical Seminar on Seepaue in Dam Safetv: Evaluation and Remediation, Baltimore, Maryland 345

PARTIAL SUMMARY OF CMP PIPE INVESTIGATIONS Insp. Dam Site Dam Pipe ~~e ~ ~ Comments 4/93 <1 yr AML 25 54 Complete failure and severe environmental damage to creek below dam. Poor compaction; leaky jointsj installed m trench cut through partially completed fill. Conduit to be replaced with concrete pipe. 5/89 4yr LFM 25 72 Complete failure and severe environmental damage to trout stream. Poor compaction; installed in trench cut through partially completed fill. 10/90 5yr SSS 25 84 Leaky joints; sinkholes; extensive piping in regress. Breach excavated through dam to alleviate pubhc sa fety hazard, 2/91 5yr VHL 15 72 Leaky joints; sinkholes in fill due to piping, 10/92 2yr CST 25 48 Deformation of conduit noted to be about 7-inches; leaky joints; missing o-ring gaskets. Embankment was removed, joints were repaired with concrete collars and dam was rebuilt, 4/91 4yr MRN 15 66 Wet pond with 6 foot normal pool depth. Leaking joints; pi ing in progress. Ongoing investigation for repair alternatives. Eam is only access to a housing subdivision, and major utilities (electric, water: sewer, telephone) in the embankment make pipe replacement dtficult. 4/91 2yr BWC 20 72 Leaking joints; piping. Sinkhole at upstream end. Pipe replaced. 5/93 3yr CGY 30 48 No askets installed during construction. Internal joint rings instaf led after the fact do not appear watertight. 11/92 6yr TMR 15 72 Leaking joints; wrong connecting bands; pipe ends not re-rolled; pig;:fationin progress; pipe damaged by utility contractors after 3/93 3yr HSM 20 60 Leaking joints;repairattempted with mastic but jointsnot watertight. 2/92 2yr CVY 20 54 Leakage along outsides of five parallel spillway pipe conduits. Repaired by injection of cement grout into voids in embankment. 4/92 3yr RTP 20 48 Leaking joints; excessive deformation. Pipe replaced. 7/93 2yr MKS 12 48 Open joints; large voids under pipe; piping in progress. 5/91 2yr UP4 20 72 Voids and see a e along pipe; settlement profile indicates that l % pipe was insta Ie in trench through dam. 5/91 <1 yr FOX 15 66 Joints separated up to 2. Exposed flat, neoprene gasket leaking. Voids under haunches. 5/93 2yr SRP 30 90 Excellent alignment; nearly all joints appear watertight. 4/91 e2yr HBC 25 66 Voids under haunches; more flow under the pipe than through it; infiltration noted at all joints; deflection of pipe noted at center of dam. 346

Complete failure of 25 foot high dam for dry end, viewed from the pool area. The structure does not normally impound water. f he 72-inch barrel pipe was apparently installed in a vertical trench cut through nearly completed embankment fill. Failure occurred during a storm that filled pool to just below enlarged top of riser. Detail of above, looking downstream along pipe from riser. Note collapse of 14-foot square anti-seep collar and the near vertical trench wall parallel to pipe in center of picture. 347

Complete failure of 25 foot hi h dam as viewed from downstream end of 54-inch pipe, TI his pipe was ap arently instal f ed in a vertical trench cut through partially complet ed embankment fill, Loss of soil support due to piping of surrounding backfill resulted in collapse of pipe and catastrophic release of flood waters. Man emb joint 3W ch 348