Update on Heap Leach potential of the Murchison gold project



Similar documents
ALCYONE REPORTS JORC SILVER RESOURCES

Positioned for Production: Exploring for Growth

Resources Rising Stars

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT

Developing the Tanlouka Gold Project. AGM Presentation 18th November 2015

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value

Press Release 29 th January 2016

C o r p o r a t e P r e s e n t a t i o n A u g u s t

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District

For personal use only

Cannon Big Pit Given the Green Light

INVESTOR PRESENTATION JULY 2013

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME

For personal use only

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

ENCOURAGING PRELIMINARY METALLURGICAL TESTWORK FOR OXIDE HEAP LEACHING AT THE SOUTH HOUNDÉ PROJECT

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016

Press Release 30 th October 2015

Interim Financial Report for the half-year ended 31 December 2011

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS).

ANNUAL GENERAL MEETING November 2015

How To Mine And Treat Ore From Castle Hill Stage 1

For personal use only

Cummins Range Rare Earths Project

GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER

Sorby Hills Silver Lead Project

For personal use only

Quarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia

QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2015

September 2015 Quarterly Activities Report

UPDATE ON SRIG - ALTONA TRANSACTION AGREED WORK AND DRILLING PROGRAMME COMMENCES

Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb TORONTO

FOCUS MINERALS LIMITED

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015

Exploration and Development Activity

AIM: KEFI 6 March KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE

For personal use only

Fast Tracking to Production

For personal use only

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW

Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q at Grants Patch Gold Tribute Project, Australia

Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back

For personal use only

For personal use only

Armadale Capital Plc Armadale or the Company Robust Project Demonstrated by Mpokoto Feasibility Study HIGHLIGHTS

For personal use only

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015

RED 5 Limited The next gold producer

Shaw River Manganese Ltd January 2012 Update. Vincent Algar - Managing Director

For personal use only

Ruby Joint Venture commenced to explore Montepuez East Ruby Project in Mozambique Kroussou Zinc-Lead Project in Gabon advancing

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE:

AngloGold Ashanti La Colosa Site Visit November, 2011

Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review

Pathway to Production

RC drilling identifies high grade gold in bedrock at Pacific Dunes Corkwood Camp Scale Target

Mako Project, Eastern Senegal Completion of Scoping Study

For personal use only

Quarterly Activities Report

PNG Mining & Petroleum Investment Conference December Geoff Day Executive General Manager PNG and Indonesia

Merlin Diamonds Limited

Pacifico set to commence drilling at Borroloola West Project and co-funding secured from NT Government

Mar Qtr Ore Mined t 79,000 68, , ,000 Mine Grade g/t Contained Gold oz 21,511 13,252 18,262 19,759

Investing in an Underground Coal Mine in Indonesia

CHALICE GOLD MINES AND SUB SAHARA RESOURCES ANNOUNCE PROPOSED MERGER TO CONSOLIDATE AND FUND ERITREAN GOLD PROJECT

Savannah North Scoping Study Looking into the future 3 February 2016

HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT

September 2010 Quarterly Report

BAUXITE RESOURCES LIMITED

C R A D L E / T R E M O N T J V A C Q U I R E S % O F P A N D A H I L L L I C E N C E S

Mines and Money Presentation

JACQUES GOLD PROSPECT RETURNS 37.7g/t. Re-assay of 1m samples from initial drilling program at Jacques returns gold grades of up to 37.

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project

Q4 & FY2015 OPERATING HIGHLIGHTS. January 29, 2016

MAJOR NEW COPPER EXPLORATION PROGRAM UNDERWAY IN NORTH QUEENSLAND

Krasny license: Operational update September 2015

For personal use only

Annual Financial Report

Aspire Mining Limited

Punching Above Its Weight

Paladin Energy. Development & Expansion of the Langer Heinrich Operation in Namibia. June 2009

QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDED 31 st December 2015

ACQUISITION OF SIGNIFICANT COAL ASSETS IN INDONESIA AND STRENGTHENING OF INDO MINES BOARD

DECEMBER 2015 QUARTERLY REPORT HIGHLIGHTS

HALF-YEAR REPORT TO 30 JUNE 2003

Core : CXO. and. Uranium Session SAREIC Conference Adelaide 13th April 2015

Dragon Mining A Growing Nordic Gold Producer. RMG Helsinki Mining Summit October 2012

WARWICK AND ATLAS IRON ANNOUNCE MERGER TO CONSOLIDATE PILBARA IRON PROJECTS

Highlights. Quarterly Report For the quarter ended 30 June Horizon Healthcare Solutions Pty Ltd

Developing Power Projects in Southern Africa. Annual General Meeting Presentation 20 th November 2015

Transcription:

3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and the Kyrgyz Republic. The Murchison Gold Project in Western Australia -scheduled to commence high grade gold mining at the Burnakura plant in mid-2012, with the potential to add goldcopper production from the neighbouring Gabanintha deposit. The high grade, very low cost Andash Gold-Copper Project in the Kyrgyz Republic development-ready, awaiting site access and targeting 2013 to commence production at 70,000 oz gold and 7,400 tonnes copper pa for an initial six years, with high potential for expansion. The Jervois Copper-Silver-Gold Project in the Northern Territory targeting 2014 startup following current studies into developing the high grade copper-silver resource with potential for gold, magnetite and other base metals. Issued capital: 106.2 million ordinary shares 5.8 million unlisted options Update on Heap Leach potential of the Murchison gold project As part of the ongoing evaluation of Kentor s established resources at Burnakura (see Table 1), large tonnages of low grade material, adjacent to high grade resources that are being targeted as potential ore for Kentor s Burnakura CIL Gold Plant, have been identified. Table 1 Burnakura Inferred Resource estimates May 2011 0.5 g/t Au cut off 1.0 g/t Au cut off 1.5 g/t Au cut off Mt Au Au Au Au Au Mt Mt Au g/t g/t koz g/t koz koz NOA 5.3 1.8 307 3.4 2.4 262 2.2 3.0 212 Alliance 1.9 1.3 79 0.8 2.0 51 0.4 2.7 35 Lewis Reward 1.2 1.1 42 0.4 1.8 23 0.2 2.3 15 Authaal 1.2 1.2 46 0.4 2.0 26 0.2 2.8 18 Federal City 0.4 1.7 22 0.2 2.7 17 0.1 3.7 12 Banderol 0.6 1.0 19 0.2 1.5 10 0.1 2.1 7 Total 10.6 1.5 516 5.4 2.2 390 3.2 2.9 298 Table from ASX announcement of 30 th May 2011 The large Alliance (New Alliance) and Authaal resources were not included in the Stage 1 mining schedule that is focussed on feeding Kentor s existing CIL plant, currently being commissioned. Historical drilling at Alliance included 586 RC and diamond holes and at Authaal it included 405 RC and diamond holes. These formed the basis for the current resource estimate. Kentor has this year drilled a further 52 RC and 6 diamond holes at Alliance and is planning further validation drilling at Authaal to upgrade the resource. Exploration potential also exists to the north of Authaal and south of Alliance. Preliminary pit designs have been created to assess the mineable potential of the two resources. (Figure 1) Market Capitalisation 2 July 2012: $71 million

Kentor Gold Limited Figure 1 Preliminary Mine designs for Authaal and Alliance pits Mining at both the Lewis and Reward pits is well advanced with the Reward pit anticipated to be completed this week. In the process of mining high grade ore from these two pits, substantial stockpiles of low grade ore are being established. This low grade material has been tested in the metallurgical test work program. Heap Leach column and coarse bottle roll test work has been completed at Ammtec s Perth laboratory on samples from the NOA, Lewis, Reward, Authaal and Alliance pits. The results showed that most ore would benefit from being crushed to minus 12.7 mm with the exception of Alliance that is achieving good recoveries at a much coarser minus 50mm. Many more tests are planned to analyse the variability within the resource but these initial results offer the potential for direct tipping of the ore. Test work is also suggesting that Lewis and Reward ore could benefit from further crushing and this will be optimised as part of the current test work program. Natural percolation results were good to very good for all samples except Authaal that benefitted from cement agglomeration. Testing at several cement addition rates suggests that 6 kg/t of ore is required to achieve good percolation. All column test work results also showed good correlation with Intermittent Bottle Roll (IBR) tests hence going forward, greater advantage can be taken in future test work using more IBR and percolation tests which are faster and cheaper than running leaching columns. Recoveries predicted for the various pits for both oxide and transitional ore types ranged from 44% through to 91% gold recovery. The primary ore tested gives poor recoveries as expected. The poorest performing low grade material from the Reward pit totals only 40kt. Importantly, samples from deposits where the bulk of the low grade resources are contained are achieving recoveries of 60% or better (Figure 2). 3 July 2012 Page 2 of 7

Figure 2 IBR Extraction v s Time curves The designed heap leach pad has a footprint of 400m x 200m and consists of eight cells each eight metres high on the lower lift and a further five, eight metre high cells on the second lift. The current design prepared by Knight Piesold will accommodate approximately 2 million tonnes of ore (Figure 3). The planned production rate when crushing and agglomerating ore is being targeted at 150 tph and the annual material anticipated to be stacked is 450-500ktpa. It is further proposed that the crushing circuit will have sufficient additional capacity to meet the anticipated future requirements for the phase 3 expansion of the Burnakura CIL plant, doubling its capacity to 500ktpa. Kentor Gold purchased a complete heap leaching circuit from the Indee gold project last year for $1.1m. This equipment has been dismantled and transported to the Murchison Gold Project site in preparation for construction of a heap leach operation. The gold room, stripping plant and RO plant from Indee have already been installed in the Burnakura CIL gold plant. This installation has more than enough excess capacity to strip additional loaded carbon from the heap leach operation. The capital cost to complete the heap leach project is estimated to be $7.5m which is broken down in Table 2. Table 2 Capital Cost Estimate Heap Leach Capital Cost $ Refurbishment and New Equipment $ 2,300,000 Installation of Equipment $ 2,400,000 EPCM $ 450,000 Other Directs $ 100,000 Indirects $ 50,000 Initial Pad and Pond Construction $ 2,000,000 Contingency $ 200,000 Total Estimate $ 7,500,000 A further $1.1m is required to complete resource drilling, geotechnical drilling, metallurgical drilling, resource and reserve estimation, metallurgical analysis and detailed plant design. 3 July 2012 Page 3 of 7

Processing costs for the heap leach is estimated to average $11.27/t of ore treated (see Table 3). This cost will vary depending on whether the ore needs to be agglomerated. The cost of agglomerating Authaal ore (which is factored into the cost estimated above) including the cement addition of 6kg/t is approximately $2/t of ore. Heap Leach processing costs are targeted to be in the range $500-550/oz. Table 3. Heap Leach Operating Costs Heap Leach Pad Operating Costs $/t ore Workforce $ 1.32 Crushing and Agglomeration $ 5.85 Stacking and Irrigation $ 2.03 Adsorption and Stripping $ 2.07 Total $ 11.27 All of the test work to date is indicating that the oxide gold resources and some of the transitional gold resources are performing well, achieving good percolation and recoveries. The benefits of leveraging off established administrative and maintenance support, power station, gold room and camp help keep the operating costs low. With the existing heap leach plant ideally suited for this operation requiring only refurbishment and installation Kentor will be able to keep the capital cost contained. Further Work Environmental surveys are underway and it is anticipated that the permitting process can commence next month. Further drilling for metallurgical-geotechnical test work and to further define additional heap leach resources will continue in parallel with the permitting process. It is anticipated that construction of the heap leach can commence later in 2012 with first production of gold from the heap leach currently expected in mid-2013. The addition of a heap leaching circuit to the Murchison gold project will increase the annual gold production. A lot of the low grade ore to be treated by the heap leach circuit needs to be mined anyway to access the high grade ore feed to the CIL plant, hence the additional production from the heap leach will substantially reduce the cash costs for the site. Resource updates for a number of the pits at the Murchison Gold project are currently underway following completion of the 20,000m drilling program. Pit optimisation and design work will then be completed to come up with a revised mining schedule for the operation. This work is expected to be completed in October. For further information contact: Mr Simon Milroy Managing Director Phone: (07) 3071 9003 Email: info@kentorgold.com.au Mr. David Waterhouse Investor Relations Phone (03) 9670 5008 Email: dwaterhouse@waterhouseir.com.au 3 July 2012 Page 4 of 7

Competent Person Statement Figure 3 Heap Leach Pad Layout The information in this report that relates to metallurgical testwork is based on information compiled by Phil Hunt who is a full time employee of PR Hunt and Associates Pty Ltd. Mr Hunt is a member of the Australasian Institute of Mining and Metallurgy. Mr Hunt has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Hunt consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. The information in this report that relates to mineral resource estimation for Burnakura is based on work completed by Mr Jonathon Abbott. Mr Abbott is a full-time employee of MPR Geological Consultants Pty Ltd and a member of the Australian Institute of Geoscientists. Mr Abbott has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr Abbott consents to the inclusion in the report of the matters based on his information in the form and context in which it appears. 3 July 2012 Page 5 of 7

Kentor Gold Limited 3 July 2012 Page 6 of 7

Note: Photographs of equipment on site at the Indee mine site 3 July 2012 Page 7 of 7