CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE



Similar documents
Safe & Sound Bridge Terminology

Dynamic Load Testing of Helical Piles

High Strain Dynamic Load Testing of Drilled Shafts

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

KWANG SING ENGINEERING PTE LTD

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

The unit costs are based on the trend line of the 3 low bids for the average quantity.

Technical Notes 3B - Brick Masonry Section Properties May 1993

System. Stability. Security. Integrity. 150 Helical Anchor

Numerical Analysis of the Moving Formwork Bracket Stress during Construction of a Curved Continuous Box Girder Bridge with Variable Width

The advantages and disadvantages of dynamic load testing and statnamic load testing

Chapter 5 Bridge Deck Slabs. Bridge Engineering 1

Stability. Security. Integrity.

PROVA DINAMICA SU PALI IN ALTERNATIVA ALLA PROVA STATICA. Pile Dynamic Load test as alternative to Static Load test

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

PDCA Driven-Pile Terms and Definitions

Detailing of Reinforcment in Concrete Structures

Strengthening of Large Storage Tank Foundation Walls in an Aggressive Environment by External Post-tensioning. May 7th 2013: Dominique Deschamps

Instrumentations, Pile Group Load Testing, and Data Analysis Part II: Design & Analysis of Lateral Load Test. Murad Abu-Farsakh, Ph.D., P.E.

SECTION 700 STRUCTURES SECTION 701 DRIVEN PILING MATERIALS Materials Materials shall be in accordance with the following:

REHABILITATION OF THE FIGUEIRA DA FOZ BRIDGE

MILMAN & ASSOCIATES STRUCTURAL CONSULTING ENGINEERS/ PROJECT MANAGERS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

Designed and Engineered to Perform

SECTION 1 GENERAL REQUIREMENTS

ENCE 4610 Foundation Analysis and Design

Chapter 2 Basis of design and materials

SECTION 5 ANALYSIS OF CONTINUOUS SPANS DEVELOPED BY THE PTI EDC-130 EDUCATION COMMITTEE LEAD AUTHOR: BRYAN ALLRED

LEGACY REPORT ER ICC Evaluation Service, Inc. Reissued November 1, Legacy report on the 1997 Uniform Building Code

Driven Concrete Pile Foundation Monitoring With Embedded Data Collector System

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI

Field Damage Inspection and Static Load Test Analysis of Jiamusi Highway Prestressed Concrete Bridge in China

Chapter 3 Pre-Installation, Foundations and Piers

Numerical modelling of shear connection between concrete slab and sheeting deck

Report on. Wind Resistance of Signs supported by. Glass Fiber Reinforced Concrete (GFRC) Pillars

METHOD OF STATEMENT FOR STATIC LOADING TEST

The following sketches show the plans of the two cases of one-way slabs. The spanning direction in each case is shown by the double headed arrow.

load on the soil. For this article s examples, load bearing values given by the following table will be assumed.

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

PRESENTATION ON REPAIR AND REHABILITATION OF BUILDINGS DAMAGED IN EARTHQUAKE. By H P Gupta & D K Gupta

MECHANICS OF SOLIDS - BEAMS TUTORIAL 1 STRESSES IN BEAMS DUE TO BENDING. On completion of this tutorial you should be able to do the following.

A transverse strip of the deck is assumed to support the truck axle loads. Shear and fatigue of the reinforcement need not be investigated.

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

GLOSSARY OF TERMINOLOGY

Reinforced Concrete Slab Design Using the Empirical Method

APE T CFRP Aslan 500

Step 11 Static Load Testing

US 51 Ohio River Bridge Engineering and Environmental Study

Calibration and Use of a Strain-Gage-Instrumented Beam: Density Determination and Weight-Flow-Rate Measurement

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

Mersin, TURKEY. Port extension project

EFFECTS ON NUMBER OF CABLES FOR MODAL ANALYSIS OF CABLE-STAYED BRIDGES

The AASHO Road Test site (which eventually became part of I-80) at Ottawa, Illinois, was typical of northern climates (see Table 1).

External Wrapping of Steel Riser Pipe. Case Study HJ3 CS200902

Instrumented Becker Penetration Test for Liquefaction Assessment in Gravelly Soils

After reading this lesson you will be able to: 12.3 IMPORTANCE OF ROOF 12.4 TYPES OF ROOF IN A HOUSE

METHOD STATEMENT HIGH STRIAN DYNAMIC TESTING OF PILE. Prepared by

Proceedings of the ASME 28 TH International Conference on Ocean, Offshore and Arctic Engineering OMAE2009 May 31 June 5, 2009, Honolulu, Hawaii, USA

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

Index Series Prestressed Florida-I Beams (Rev. 07/12)

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

6 RETROFITTING POST & PIER HOUSES

ASSESSMENT AND PROPOSED STRUCTURAL REPAIR STRATEGIES FOR BRIDGE PIERS IN TAIWAN DAMAGED BY THE JI-JI EARTHQUAKE ABSTRACT

Structural Failures Cost Lives and Time

Seismic Retrofit of Reinforced Concrete Beam- Column T-Joints in Bridge Piers with FRP Composite Jackets

Bridge Structural Rehabilitation Using FRP Laminates

Durability, Versatility

CH. 2 LOADS ON BUILDINGS

INDIRECT METHODS SOUNDING OR PENETRATION TESTS. Dr. K. M. Kouzer, Associate Professor in Civil Engineering, GEC Kozhikode

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

High Capacity Helical Piles Limited Access Projects

The entire document shall be read and understood before proceeding with a test. ISTA 3B Page 1 of 35

PILE FOUNDATIONS FM 5-134

Kentucky Lake Bridge Pile Load Testing Overview Ohio Transportation Engineering Conference Columbus, Ohio 10/28/2015

PC-Concrete Injectable Concrete Anchoring and Repair System

REPAIR AND STRENGTHENING OF HISTORICAL CONCRETE BRIDGE OVER VENTA RIVER IN LATVIA

vulcanhammer.net This document downloaded from

Compression load testing straw bale walls. Peter Walker Dept. Architecture & Civil Engineering University of Bath Bath BA2 7AY.

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA

CEEN Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

STATNAMIC : Pile Load Testing Equipment

Precision Miniature Load Cell. Models 8431, 8432 with Overload Protection

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design

Simulation for the Collapse of WTC after Aeroplane Impact

IN-SERVICE PERFORMANCE AND BEHAVIOR CHARACTERIZATION OF THE HYBRID COMPOSITE BRIDGE SYSTEM A CASE STUDY

Diameter. Swift Lift Round Recess Plug. Note: The diameter of the narrow recess plug is the same as the diameter of the round recess plug.

Measuring the Condition of Prestressed Concrete Cylinder Pipe

Optimum proportions for the design of suspension bridge

CHAPTER 2 QUANTITY TAKE-OFF

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

Miss S. S. Nibhorkar 1 1 M. E (Structure) Scholar,

PRESTRESSED CONCRETE. Introduction REINFORCED CONCRETE CHAPTER SPRING Reinforced Concrete Design. Fifth Edition. By Dr. Ibrahim.

Transcription:

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long track record of performance. To help fill this void, a long term monitoring program was implemented at the Route 351 bridge project. The initial plan was to compare the performance of three adjacent bridge piers each supported by different pile types. The three pile types initially considered for this study were: Lancaster composite piles, Hardcore composite piles, and VDOT standard prestressed concrete piles. Unfortunately, the scope of the monitoring program was reduced due to withdrawal from the project by Lancaster Composites Inc., and a request from Hardcore Composites Inc. to reduce the quantity of their piles installed in the pier from seven piles, i.e., full pier support, to just one pile installed at the pier centerline. Hardcore s request was partly due to their concern of lack of precedent for using FRP piles to support bridge piers. Therefore, the long term monitoring program was modified to a reduced version consisting of monitoring two instrumented piles installed at the center of two adjacent piers. The instrumented production piles will be monitored for several years. This reduced program is not the most ideal, particularly because the bent with the FRP composite pile will have two types of piles with stiffness differences that may affect load distribution among the piles in the pier. In addition, the pile arrangements in the two piers are not the same. The pier with the FRP pile has the five central piles installed vertically, and the two outer piles installed with 4 to 1 batter in the direction perpendicular to the bridge axis. The pier with the instrumented prestressed concrete pile has the three central piles installed vertically and the two outer piles on each end of the pier installed at 4 to 1 batter oriented in the direction of the bridge axis. Nevertheless this program is expected to provide some insight on the long term durability 295

and performance of the FRP composite pile. This chapter describes the instrumented production piles, the instrumentation used, the soil conditions at the locations of the instrumented piles, the installation information including driving records, PDA, CAPWAP, and PIT tests, and the monitoring data gathered to date. 9.2 INSTRUMENTED PRODUCTION PILES Long term instrumentation was installed in a Hardcore FRP composite pile and a prestressed concrete pile, which were installed as the center piles of Piers 11 and 10, respectively. The location of the instrumented production piles are shown in Figure 9.1. Steel plate girder spans Prestressed concrete beam spans West Instrumented Prestressed concrete pile East Instrumented FRP pile 15.2 m 26.6 m 25.4 m 21.29 m 9 spans @ 15.49 m Abutment A Abutment B 1 2 3 4 5 6 7 8 9 10 11 12 Notes: : indicates 1:4 pile batter in the direction shown : prestressed concrete pile : instrumented prestressed concrete pile : instrumented FRP composite pile Figure 9.1 Location of instrumented production piles at the Route 351 Bridge 296

9.2.1 Prestressed Concrete Production Pile The instrumented prestressed concrete production pile has characteristics similar to the test pile described in Chapter 6. However, the production pile is longer, with a length of 22 m (72.2 ft). The 28-day strength of the concrete used in this pile is 61 MPa (8,870 psi). The prestressed concrete pile was instrumented with eighteen vibrating wire sister bar strain gages located at seven levels, as shown in Figure 9.2. These gages will be used to assess the load transfer from pile to soil. As shown in Figure 9.2, a pair of gages was located at each level to provide gages on opposite sides of the pile. Two extra gages were installed at the uppermost and lowermost levels for redundancy. The gages are Geokon Model 4911 rebar strain meter gages manufactured and calibrated by Geokon Inc. These gages consist of two lengths of No. 12M, grade 420 steel bar (No. 4 steel bar, grade 60) welded onto each end of a miniature vibrating wire strain gage element. The entire assemblage is 1.3 m long. The instrumentation for the prestressed concrete production pile was installed on November 6, 2001. The pile was cast on November 7, 2001. The vibrating wire sister bar strain gage survival rate, after pile manufacturing, driving, and restrike, was 100%. 297

Top of pile 2.31 m 4 sister bars (SB-1) 3.69 m LEGEND Vibrating wire sister bar strain gage SB-#: Level of sister bars 2 sister bars (SB-2) 3.00 m 2 sister bars (SB-3) 610 mm 2.99 m 22 m 2 sister bars (SB-4) 3.01 m 95 mm 95 mm Cross section of prestressed pile 2 sister bars (SB-5) 3.00 m 2 sister bars (SB-6) 2.68 m 4 sister bars (SB-7) 1.32 m Bottom of pile Figure 9.2 Load transfer instrumentation layout for prestressed concrete production pile 298

9.2.2 FRP Composite Production Pile The instrumented FRP composite production pile has the same characteristics as the FRP composite test pile described in Chapter 6, but the length of this pile is 21.2 m (69.6 ft). Similar to the prestressed concrete pile, the FRP composite production pile was instrumented with eighteen vibrating wire sister bar strain gages located at seven levels, as shown in Figure 9.3. These gages will be used to assess the load transfer from pile to soil. The FRP pile was also instrumented with gages installed to study the performance and durability of the FRP tube. The following durability instrumentation was installed to monitor strains in the FRP tube: - Two foil gages at each of six levels, labeled IG-1 through IG-6, as shown in Figure 9.3, for a total of twelve gages bonded to the internal wall of the FRP tube. The foil gages are type CEA-13-500UW-350, temperature compensating, underwater, resistance strain gages manufactured by the Micro-Measurements Division of Vishay Measurements Group, Inc. The gages are configured in a onequarter active bridge. A protective coating system was used to cover these gages to protect them from possible moisture and chemical attack during filling of the tubes with concrete. The protective coating consisted of a Teflon film, overlain by a layer of polymer compound, overlain by aluminum foil, overlain by another layer of polymer compound, overlain by aluminum foil with the edges sealed with a rubber coating. - Four vibrating wire strain gages were installed on the outside surface of the FRP pile at the locations shown in Figure 9.4. These gages are Geokon Model VK- 4100 vibrating wire strain gages manufactured and calibrated by Geokon Inc. These gages have a 50 mm (2 in.) gage length. The gages were installed by epoxy bonding their mounting tabs to the pile exterior. In addition to providing strain, 299

these gages can measure temperature since they come with a thermistor incorporated. The vibrating wire sister bars and the internal foil resistance strain gages for the FRP composite production pile were installed between January 24 and February 1, 2002. The concrete was poured for this pile on February 6, 2002. The vibrating wire sister bar strain gage survival rate, after pile manufacturing, driving, and restrike, was 100%. The survival rate of the internal foil gages was 30%. The majority of the internal foil gages started to drift after the concrete was poured. This could be due to moisture from the concrete. The external vibrating wire strain gages were installed after pile installation on November 7, 2002. As of December 30, 2002, all external gages are functioning. 300

2.30 m 4 sister bars (SB-1) 3.70 m 2 sister bars (SB-2) IG-1 IG-2 IG-3 IG-4 IG-5 IG-6 1.14 m 0.44 m 0.33 m 0.42 m 0.47 m 0.60 m LEGEND Vibrating wire sister bar strain gage Strain gage bonded to inside of FRP tube in the axial direction Strain gage bonded to inside of FRP tube in the hoop direction SB-#: Level of sister bars 3.00 m 2 sister bars (SB-3) IG-#: Level of strain gages bonded to the FRP inside 3.00 m 21.2 m 2 sister bars (SB-4) 3.00 m 2 sister bars (SB-5) 58 mm 58 mm Cross section of FRP composite pile 3.00 m 2 sister bars (SB-6) 2.70 m 4 sister bars (SB-7) Bottom of pile Note: Layout of external durability instrumentation shown in Figure 9.4. Figure 9.3 Instrumentation layout for FRP composite production pile 301

Centerline Route 351 A 1.22 m 0.64 m 0.23 m FRP pile 0.72 m 0.35 m EG-1 0.15 m EG-2 EG-3 EG-4 0.14 m 0.62 m View looking East A Centerline Pier 11 1.27 m Pile cap Pier 11 LEGEND External vibrating wire strain gage EG-#: Vibrating wire strain gage bonded to the outside of FRP tube 1.22 m Pile cap Pier 11 0.64 m 0.23 m 0.72 m EG-2 EG-1 EG-3 EG-4 FRP pile Section A-A (looking North) Figure 9.4 Layout of external durability instrumentation used in the FRP composite production pile 302

9.3 SOIL CONDITIONS AT THE INSTRUMENTED PRODUCTION PILES VDOT investigated the soil conditions along the bridge alignment. The general soil stratigraphy found along the Route 351 bridge alignment is shown in Figure 9.5. The uppermost layer of river sediments consist of very soft to soft silty clay of varying thicknesses, as shown in Figure 9.5. The soft river sediments are underlain by loose to medium dense silty fine sand extending to variable depths depending on the location along the alignment. In general, the silty fine sand was found to increases in density with increasing depth, becoming dense to very dense at a depth of about 30 m. The specific soil conditions found at the Piers 10 and 11 are shown in Figures 9.6 and 9.7, respectively. As shown, a sandy, silty, clay interbed was found at Piers 10 and 11, between elevations -18.7 and -20 m, and -11.6 to -20 m, respectively. For reference, the elevations of the installed piles are also shown in these figures. Station (m) (m) Figure 9.5 Simplified stratigraphy along the Route 351 bridge alignment 303

5 Top of cap elevation +3.69 m 0 Mudline elevation -1.41 m -5 CLAY, silty, very soft, gray, with shell fragments SAND, silty, loose to medium dense, green Elevation (m) -10-15 -20-25 SAND, silty, loose to medium dense, gray, with shell fragments CLAY, sandy, stiff, gray SAND, silty, medium dense to dense, gray, with shell fragments Tip elevation -18.4 m 32 31 60-30 78 35 End of borehole at EL. -31.89 m -35 0 5 10 15 20 25 30 Measured SPT N (field values) Figure 9.6 Simplified stratigraphy in the vicinity of the instrumented prestressed concrete pile installed at Pier 10 304

5 Top of cap elevation +3.265 0-5 CLAY, silty, sandy, soft, gray, with shell fragments SAND, silty, loose to medium dense, brown, with shell fragments Mudline elevation -0.09 m Elevation (m) -10-15 SAND, silty, medium dense, gray, with shell fragments CLAY, silty, sandy, low plastic, stiff, gray, with shell fragments -20 SAND, silty, clayey, medium dense, gray, with shell fragments Tip elevation -18.8 m 55-25 -30 SAND, silty, medium dense 0 5 10 15 20 25 30 Measured SPT N (field values) Figure 9.7 Simplified stratigraphy in the vicinity of the instrumented FRP composite pile installed at Pier 11 305

9.4 PILE INSTALLATION AND DYNAMIC TESTING 9.4.1 Pile Driving The instrumented production piles were driven with an ICE model 80S single-acting diesel hammer. The maximum rated energy of the hammer is 108.6 kn-m (80,000 ftlbs). Both instrumented production piles were driven with 230 mm (9 in.) thick plywood pile cushions. The pile driving records are shown in Figure 9.8. The prestressed concrete pile and FRP pile were driven on June 13, 2002 and June 14, 2002, respectively. 5 0 Mudline at FRP pile Prestressed pile FRP pile Elevation (m) -5-10 Mudline at prestressed pile -15-20 0 20 40 60 80 100 Pile blows per 305 mm Figure 9.8 Driving records for instrumented production piles 306

9.4.2 Dynamic Testing Dynamic monitoring was performed using a Pile Driving Analyzer (PDA) manufactured by Pile Dynamics, Inc. The PDA monitoring and data processing was carried out by GSI, Inc. from Norfolk, Virginia. Monitoring was performed during initial driving and during restrike. Restrike occurred on June 18, 2002, which represents a setup period of 4 and 5 days after initial driving, for the FRP composite pile and prestressed concrete pile, respectively. PDA records for the two instrumented production piles at restrike are shown in Figure 9.9. The PDA records show a force peak at about time 0, measured with respect to the horizontal bars that are shown in Figure 9.9 and that represent the wave travel time for two pile lengths for each pile. The prestressed concrete and FRP composite piles show similar dynamic behavior. Both piles show a large increase in the velocity record and a corresponding low force at about 2L/c (where L is the pile length, and c is the wave speed). This type of PDA record shape is characteristic of piles with a small toe resistance. Very little separation between the force and velocity traces is noticed between time 0 and about 0.5L/c. This corresponds to the zone of zero to minimal shaft resistance, i.e., the portion of the pile above the ground surface and the portion through the very soft river sediments where the shaft resistance is small. Table 9.1 provides some of the measurements obtained during pile driving. It can be seen that the wave speed (c) and impedance values (EA/c) recorded in the FRP composite pile were about 5.3% and 6.1% lower, respectively, than the prestressed pile. The maximum compressive and tensile stresses in the prestressed concrete pile were lower than the allowable stresses recommended for prestressed piles (Hannigan et al. 1996). The highest driving stresses were recorded in the FRP composite pile; however, no standards are currently available for allowable driving stresses of FRP composite piles. 307

8000 6000 Force Velocity x (EA/c) 4000 (kn) 2000 0-2000 -4000 (a) Prestressed concrete pile 8000 6000 4000 pile 10.196 ms 0 2L/c 0 10 20 (ms) 30 40 50 Force Velocity x (EA/c) (kn) 2000 0-2000 -4000 (b) FRP composite pile Table 9.1 Summary of pile driving measurements for the prestressed and FRP production piles (after Spiro and Pais 2002b) Pile Type Measurement Prestressed FRP Wave speed (c) 4054 m/s 3840 m/s Impedance (EA/c) 3589 kn/m/s 3370 kn/m/s Maximum compression stress measured during driving Maximum tensile stress measured during driving Allowable Stresses pile 9.714 ms 0 2L/c 0 10 20 (ms) 30 40 50 Figure 9.9 PDA recordings during restrike (Spiro and Pais 2002b) 11.7 MPa 13 MPa 7 MPa 8.8 MPa Comp. < 24.3 MPa Tension < 7 MPa No standards available 308

Estimates of pile capacity from the dynamic strain and acceleration measurements were obtained using the Case Method and CAPWAP analyses (Spiro and Pais 2002b). Both the Case Method and CAPWAP capacities are listed in Table 9.2. The FRP composite production pile showed an increase in the Case Method capacity of about 125% between the end of initial driving and restrike 4 days later. According to the CAPWAP analyses, the prestressed concrete and FRP composite piles have capacities of 1980 and 2046 kn (445 and 460 kips), respectively. These CAPWAP capacities are over two times larger than the design axial design load for the piles in the piers of 890 kn. The CAPWAP analyses also indicate that the shaft capacities, as percentages of the total capacities, are 82%, and 71% for the prestressed concrete, and FRP piles, respectively. These high shaft capacity percentage values agree with the observations made earlier regarding the shape of the PDA records being characteristic of piles with low toe resistance. Table 9.2 Summary of CASE and CAPWAP analyses results (Spiro and Pais 2002b) Capacity Prestressed Method FRP pile component concrete pile Case (1) (End-of-Driving) Total Not available (2) 890 kn Case (1) (Restrike (3) ) Total 2091 kn 2002 kn CAPWAP (Restrike (3) ) Shaft 1624 kn 1459 kn Toe 356 kn 587 kn Total 1980 kn 2046 kn Notes: (1): Case method using a Case damping coefficient of 0.60. (2): Not available due to signal acquisition problems. (3): Restrike of piles performed 4 and 5 days after initial driving, for the FRP and prestressed concrete piles. 9.5 PILE INTEGRITY TESTING OF TEST PILES Pile integrity tests (PIT) were performed on the instrumented production piles before and after pile installation. These tests were carried out using the same procedure used for the test piles described in Chapter 6. PIT results for the prestressed concrete production pile installed at Pier 10, performed before and after pile driving, are shown in Figures 9.10 and 9.11, respectively. No discernable damage was noted based on comparison of the pre- and post-driving PIT 309

soundings. The soil resistance in the pile after installation results in a smaller toe reflection, as shown in Figure 9.11. Velocity (in/s) 1.0 0.8 0.6 0.4 0.2 0.0 Recorded June 13, 2002 Wave speed = 13,065 ft/s Pile length = 72.18 ft -0.2-0.4 0 10 20 30 40 50 60 70 Distance (ft) Figure 9.10 PIT sounding on the prestressed concrete production pile before installation Velocity (in/s) 1.0 0.8 0.6 0.4 0.2 0.0 Recorded June 18, 2002 Wave speed = 13,200 ft/s Pile length = 72.18 ft -0.2-0.4 0 10 20 30 40 50 60 70 Distance (ft) Figure 9.11 PIT sounding on the prestressed concrete production pile after installation and restrike 310

PIT results for the FRP composite pile installed at Pier 11 are shown in Figures 9.12 and 9.13. No significant difference between the pre- and post-drive PIT traces was observed for the FRP pile. Toe reflection in the post-drive PIT is almost not discernible, probably due to high soil resistance. No discernable damage could be detected based on comparison of the pre- and post- driving PIT soundings. Velocity (in/s) 1.0 0.8 0.6 0.4 0.2 0.0 Recorded March 5, 2002 Wave speed = 13,335 ft/s Pile length = 69.6 ft -0.2-0.4 0 10 20 30 40 50 60 70 Distance (ft) Figure 9.12 PIT sounding on the FRP composite production pile before installation Velocity (in/s) 1.0 0.8 0.6 0.4 0.2 0.0 Recorded June 18, 2002 Wave speed = 13,335 ft/s Pile length = 69.6 ft -0.2-0.4 0 10 20 30 40 50 60 70 Distance (ft) Figure 9.13 PIT sounding on the FRP composite production pile before installation 311

9.5 MONITORING DATA GATHERED TO DATE Important date information for these two piles is summarized in Table 9.3. Table 9.3 Test dates for the instrumented production pile program at the Route 351 bridge project Length Fabrication Driving Restrike Pile Type Cross section (m) date date Date Prestressed 610 mm square 22 11/7/01 6/13/02 6/18/02 concrete FRP 622 mm circular 21.2 2/6/02 6/14/02 6/18/02 Due to delays in the construction schedule of the bridge, only a few readings have been made on the instrumented production piles. The instrumentation for the prestressed and FRP composite piles have been read on the dates summarized in Tables 9.4 and 9.5, respectively. On December 30, 2002 the estimated loads acting on the prestressed concrete and FRP composite piles were 24.1% and 30.9% of the axial design load, respectively. Table 9.4 Monitoring dates for prestressed concrete pile at the Route 351 bridge Date Description of pile loading condition Estimated load on pile 6/18/02 After pile installation and restrike. 0 kn 11/7/02 Pile cap and girders from east span installed. 110 kn 12/30/02 Pile cap and girders from adjacent spans installed. Deck slab for east span in place. 227 kn Table 9.5 Monitoring dates for FRP composite pile at the Route 351 bridge Date Description of pile loading condition Estimated load on pile 6/18/02 After pile installation and restrike. 0 kn 11/7/02 12/30/02 Pile cap and girders from east and west spans installed. Pile cap, girders, and deck slab from adjacent spans in place. 155 kn 290 kn 312

The loads acting on each pile were estimated based on the information reported in the bridge design drawings. The weight of the pile cap is based on unit weight for the reinforced concrete of 23.6 kn/m 3 (150 lbf/ft 3 ) and the pile cap dimensions of 1.22 x 1.27 x 12.5 m. The load from the AASHTO Type II girders (7 girders per each span), are based on a span length of 15.5 m and a girder weight per unit length of about 5.6 kn/m (384 lbf/ft) (Nilson 1987). The load due to the reinforced concrete bridge deck is based on a slab thickness of 0.2 m and a deck width of 12.8 m. As a first approximation the loads acting on the pile was estimated by dividing the total pier load by the number of piles in the pier. A photo of the bridge on December 30, 2002, is shown in Figure 9.14. This photo shows that Piers 7 through 12 have been installed and the bridge deck has been poured up to Pier 10. The photo also shows the formwork for the deck between Piers 9 and 10. Slab of bridge deck poured up to Pier 10 Instrumented prestressed concrete pile at Pier 10 Instrumented FRP pile at Pier 11 Figure 9.14 Photo of Route 351 bridge under construction on December 30, 2002 313

The load distributions estimated for the prestressed concrete and FRP composite piles are shown in Figures 9.15 and 9.16, respectively. These load distributions were estimated by multiplying the average strain at each level of vibrating wire sister bars by the values of axial stiffness, EA, of each pile reported in Chapter 6. The load distributions were calculated considering the residual stresses after driving using the procedure described by Fellenius (2002). Future monitoring of the piles will include readings at the end of bridge construction, which is expected near the end of spring 2003, and periodic readings taken for the next few years with the bridge under normal operation. The long term monitoring and data collection responsibility will be transferred to VTRC/VDOT. Load (kn) 0 0 50 100 150 200 250 5 November 7, 2002 Mudline Depth (m) 10 15 December 30, 2002 20 25 Figure 9.15 Load distributions on November 7, 2002 and December 30, 2002 for the prestressed concrete production pile at Pier 10 314

0 Load (kn) 0 50 100 150 200 250 300 350 Mudline 5 Depth (m) 10 15 November 7, 2002 December 30, 2002 20 25 Figure 9.16 Load distributions on November 7, 2002 and December 30, 2002 for the FRP composite production pile at Pier 11 315

6.8 SUMMARY A long term monitoring program has been implemented at the Route 351 bridge project to compare the long-term performance, load transfer, and durability characteristics of an FRP composite pile and a standard prestressed concrete pile. The two production piles selected for monitoring were installed at the centers of Piers 10 and 11. The piles consist of: 1) a conventional, 610 mm square, prestressed concrete pile installed at Pier 10, and 2) a 622 mm diameter composite pile formed of an FRP shell and filled with concrete and steel reinforcing bars installed at Pier 11. The instrumented production piles are about 22 m long. Load transfer instrumentation consisting of 18 vibrating wire sister bars was installed at seven levels in both piles. Durability instrumentation consisting of resistance foil gages and vibrating wire gages was installed on the FRP composite pile to monitor the inside and outside of the FRP tube, respectively. The soils at the production pile locations were investigated by VDOT, and consisted of very soft to soft silty clay underlain by loose to medium dense silty sand. A sandy, silty, clay interbed was found at Pier 10 between elevations -18.7 and -20 m, and at Pier 11 between elevations -11.6 to -20 m. The field testing of the instrumented production piles included PDA, CAPWAP, and PIT tests. The following conclusions can be drawn from this test program: - The FRP composite pile and prestressed concrete pile performed similarly during pile driving, as demonstrated by the driving records, PDA traces, measured wave speed generated by the driving hammer, and measured compressive and tensile stresses. - Both instrumented production piles showed similar estimated pile capacities using the Case Method on pile restrike blows. 316

- CAPWAP analyses at pile restrike showed similar estimated pile capacities, and high shaft capacity components. The shaft capacities were estimated as being 82% and 71% of the total capacity, for the prestressed concrete and FRP composite piles, respectively. Based on the CAPWAP analyses the pile capacities were estimated to be more than twice the axial design load of the pier piles of 890 kn. - No discernable damage was detected in the piles after installation, based on PIT testing performed on the piles before and after pile driving. - Monitoring data of the piles is limited to date. The bridge is still under construction, and on December 30, 2002, the loads acting on the piles were estimated as 215 kn and 275 kn for the prestressed concrete pile and FRP composite pile, respectively. Durability instrumentation was installed on the FRP composite pile to monitor the inside and outside strains of the FRP tube. The durability instrumentation had to be installed once the construction activities near Pier 11 were completed. Hence, monitoring data for the durability instrumentation is not yet available at the time of this report. In addition to providing the strain for the FRP shells, the durability strain gages will also provide records of temperature because vibrating wire strain gages incorporate thermocouples to provide information necessary for reducing the strain gage data. The strain and temperature data will be used to interpret the performance of the FRP shells, as follows: Knowledge of the exposure time and temperature can be used to estimate the FRP properties of modulus and strength from the laboratory durability study described in Chapter 4. Knowledge of the strain in the production piles can be combined with the modulus to give the stress in the FRP shell. Comparing the stress with the strength of the FRP shell indicates how close the shell is to failure. 317