GOWANUS EXPRESSWAY TUNNEL PRIMER



Similar documents
BUTE Department of Construction Management and Technology

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

Safe & Sound Bridge Terminology

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

TBM CROSSING OF STATIONS

Types of Mining - Expert Table

Milan M5 metro extension the construction of Lotto station

The Manitoba Water Services Board SECTION Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

Appendix E Construction Methods

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

STRUCTURES Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Soils, Foundations & Moisture Control

Söderströmtunnel: immersion in downtown Stockholm, Sweden

Member Nation Report 2010 from Denmark.

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

SECTION STORM DRAIN SYSTEM

SECTION SUPPORT OF EXCAVATION

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

METHOD OF STATEMENT FOR STATIC LOADING TEST

BRIDGES ARE relatively expensive but often are

San Antonio Water System Standard Specifications for Construction ITEM NO POINT REPAIRS AND OBSTRUCTION REMOVALS

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

Introduction to Minimal Excavation Foundations

TRENCHLESS TECHNOLOGY RESOURCE CENTRE TRENCHLESS TECHNOLOGY GUIDELINES

SECTION ABANDONMENT OF SEWER MAINS

Chapter 3 Pre-Installation, Foundations and Piers

Construction Technology 3

EXCAVATION and BASEMENT CONSTRUCTION. Introduction

SECTION 1 GENERAL REQUIREMENTS

Section 2100-Trenching and Tunneling

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

KOSCIUSZKO BRIDGE PROJECT BRIDGE PRIMER

How To Repair A House

9.00 THE USE OF HUNTER LAND DRAINAGE PERFORATED PIPES. Hunter Underground Systems

ources of Drinking Water

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

Excavation Procedure. MIDGA Reviewed: 07/29/14 Effective: 06/20/09 Supersedes: Original Preparer: Owner: Approver: Safety Safety Safety

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SOME EXPERIENCE FROM THE SOFT GROUND TUNNELLING IN URBAN AREA

Trenching and Excavation Safety

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Stormwater/Wetland Pond Construction Inspection Checklist

Section Installation of pipe and casing for sanitary sewer by methods of augering.

SECTION EARTH MOVING

ITEM # OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

SECTION GRAVITY SANITARY SEWERS

STEPS TO CONSTRUCTING A MOISTURE-RESISTANT FOUNDATION SOURCES OF MOISTURE IN NEW CONSTRUCTION. Natural ground slope

Chapter 9 Remedial Measures

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM

symptoms of a faulty foundation

State Route 640 Itinerary Agrigento-Caltanissetta-A19. Description of work

Outlet stabilization structure

Elevating Your House. Introduction CHAPTER 5

Storm Drain Inlet Protection

SE-10 STORM DRAIN INLET PROTECTION. Objectives

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

Settlement of Foundations on Expansive Clays Due to Moisture Demand of Trees CIGMAT 2008

Transmission Foundations Case History : Helical piles Hydro One Networks Inc.

Geotechnical Building Works (GBW) Submission Requirements

Texas Building Pros Foundation Repair Services

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

Note: All dimensions are nominal. All weights are for shipping purposes only. Availability is subject to change.

GEORGE J. CAMBOURAKIS, P.E., C. ENG. PRESIDENT & CHIEF STRUCTURAL ENGINEER

ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R Lecturer: Jim Cahill

The minimum reinforcement for the stem wall is the placement of:

Wastewater Capital Projects Management Standard Construction Specification

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

R E S I D E N T I A L H O U S I N G

hs2 Ground A non-technical guide

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

C-2 Construction, Inc. - NAICS Codes

ENGINEERED FOUNDATIONS. Department of Public Works Jeff Hill, PE

Index. protection. excavated drop inlet protection (Temporary) Block and gravel inlet Protection (Temporary)

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

50AI01oe 02/15. Labko GRP cesspools. Instructions for installation, operation and maintenance

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

How To Check For Scour At A Bridge

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

-SQA-SCOTTISH QUALIFICATIONS AUTHORITY HIGHER NATIONAL UNIT SPECIFICATION GENERAL INFORMATION

March 19, Ms. Jean McDonald CAP Management th Street, Suite 1010 Denver, Colorado 80202

Storm Drain Inlet Protection

EXCAVATION AND PILING NEAR SEWERS, STORMWATER DRAINS AND WATER MAINS

Table 4.9 Storm Drain Inlet Protetion Applicable for

SECTION CEMENT-MORTAR LINED AND COATED STEEL PIPE

Lighthouse Engineering, L.L.C.

Storm Drain Inlet Protection - IP

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Cardok Sàrl CP37 CH-1295 Tannay Switzerland Phone:

Transcription:

GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a number of potential alignments, or routes, for the tunnel and identifying which ones best meet transportation needs and address project goals and community concerns. As this investigation proceeds, it will require increasing levels of engineering and technical analysis. In discussing these analyses, certain terms and concepts specific to tunnel design, construction, and operations will be employed. This booklet is meant to help you understand some of these terms and to briefly explain several of the construction methods that may be used to build a tunnel. BUILDING THE HOLLAND TUNNEL, 1920S: Sandhogs take a break to pose within the tunnel shield. New York State Department of Transportation Joseph H. Boardman, Commissioner Douglas A. Currey, P.E., Regional Director TUNNELING UNDER CAIRO, EGYPT, 2000: Cairo s new subway line, scheduled to open in 2000, is being built beneath its downtown and under the Nile River. Above, sections of a tunnel-boring machine waiting to be lowered underground, where they will be assembled.

ENGINEERING DRAWINGS Before construction of a tunnel can occur, a variety of tunnel routes, or ALIGNMENTS, must be investigated. To see how the alignment fits in with existing conditions, engineering drawings called plans, profiles and cross-sections are created, showing different views of the tunnel. A PLAN shows the top of the tunnel, a PROFILE shows the sides, and a CROSS-SECTION shows a cut through the tunnel. Original New Jersey portal to the Lincoln Tunnel, 1957 THE ANATOMY OF A TUNNEL These are some of the terms used to describe the individual parts of a tunnel: CROWN: the top of a tunnel. INVERT: the bottom of a tunnel. PORTAL: the entrance to a tunnel. SHIELD: a structure used in soft ground to provide support at the face of the tunnel for the soil above the tunnel, to provide space for erecting supports, and to protect the workers excavating and erecting supports. 1991 David Sailors Access shaft to a water tunnel, Chicago, Illinois Tunnel workers preparing a section of the shield used to construct the Third Tube of the Lincoln Tunnel, early 1950s

HOW A TUNNEL IS BUILT Tunnels are constructed using many methods, depending upon the kind of soil and/or rock through which they will pass, how deep they need to be, and the obstructions that may be encountered along the route. These methods include tunnel boring with machines (TBMs), cut-and-cover construction, immersion of prefabricated tunnels, and sequential excavation method (SEM). BORED TUNNEL This type of tunnel is circular and may be constructed with a tunnel-boring machine (TBM), which mechanically excavates soil or rock. A large-diameter, reinforced steel cylinder, a TBM contains drive motors for a rotating cutter, which is mounted on one end, and hydraulic machinery for the thrusting jacks mounted along the perimeter of the cylinder on the other end. A TBM moves forward by pushing with the jacks against the tunnel lining or against the surrounding rock. The tunnel is lined with rings, usually made of concrete or steel, bolted together to provide integrity and watertightness to the lining. Each time there is space for another ring of lining, the TBM stops, the jacks are retracted, and the ring is installed. In a rock tunnel, the TBM body moves forward until the jacks reach the end of their stroke. The jacks are then retracted into the body of the machine before gripping the rock again and repeating the boring cycle. These are some of the technical terms associated with tunnel boring: ADVANCE RATE: the amount of progress the tunnel-boring machine makes the distance it covers in a day, usually measured in feet or meters. FACE: the soil being excavated directly in front of the tunnelboring machine. A MIXED FACE is a condition with more than one type of material, such as clay, sand, gravel, cobbles, or rock. LINING: a temporary or permanent structure, made of concrete or other materials, to secure and finish the tunnel interior or to support an excavation. A 46-foot-diameter tunnel-boring machine used under the Elbe River, Germany, is the largest in the world. Muck removal by conveyor belt, Bangkok, Thailand Courtesy of Herrenknecht AG Tunneling Systems The front of the TBM is made up of a CUTTER HEAD, which uses rotating cutting tools to break up rock and/or other materials. Immediately behind the head is the machine BODY, which remains stationary while the cutters rotate. The MUCK (excavated material) from the excavation is either dropped onto a conveyor belt (above right) or removed by a screw conveyor, which carries it to the back of the machine. As the material is cut by the cutter head, thruster JACKS maintain forward pressure, and the machine is advanced until the jacks reach the end of their stroke. Face TBM BODY Tunnel Lining Rings All TBMs contain these essential components, but designs differ according to the type of ground to be encountered (for example, soft soil, a mixture of soils, rock). Rotating Cutter Head Muck Conveyor System

1996 David Sailors 1997 David Sailors Cut-and-cover construction of the extension of the 63rd Street Tunnel, Queens, New York: Tiebacks (steel bars or cables) are angled into the completed slurry walls and anchored into rock to support the walls. CUT-AND-COVER TUNNEL In this method of tunnel construction, a deep trench is excavated, the tunnel is constructed within the trench, and then covered by soil. Sometimes a temporary deck is placed over the excavation at an early stage so that vehicular and pedestrian movements can be reinstated while construction continues below. The following are some of the technical terms that apply to cut-and-cover tunneling: BENTONITE: a clay mineral that can absorb large amounts of water. When mixed with water, it forms a SLURRY used to support deep trenches or bore holes against collapse until they can be filled with concrete. DECKING: a plank cover over a work area that serves as a temporary surface for pedestrian and vehicular traffic (including construction equipment); usually made of wood, concrete, or steel. OPEN CUT: a method of construction in which the excavated trench is left uncovered while the tunnel is constructed. BOTTOM UP: a method of construction in which a tunnel is built within an excavated trench in a conventional way or sequence: base slab first, then the walls and, finally, the roof. The completed structure is then backfilled and the ground surface reinstated. In TOP DOWN construction, the tunnel walls are built first, using special machinery, within a narrow trench. Next, the roof is built in a shallow excavation, and the ground surface is reinstated. The rest of the tunnel is then excavated and constructed underneath the roof. A clamshell excavator, left, digs a slurry wall panel in downtown Boston. The plastic sheeting protects the building from splashes of soil and bentonite slurry. One method of supporting the sides of a cut-andcover tunnel is SLURRY WALL CONSTRUCTION, in which a wall is constructed within a narrow trench. During excavation (A), the trench is kept filled with a heavy clay and water mixture (bentonite slurry), which supports the sides of the trench. When excavation is complete, prefabricated cages (B) of reinforcing steel, and sometimes also steel beams, are lowered into the slurry. Concrete, which is heavier than slurry, is piped to the bottom of the hole, displacing the slurry upward (C). Excess slurry is pumped away and cleaned, stored, and reused. A B C Slurry Unexcavated Material Rebar Cage Slurry Slurry Slurry Pumped Out and Recycled Concrete Displacing Slurry

IMMERSED TUNNEL A tunnel below a body of water may be built using this method. First, the individual elements of the tunnel, made of steel or concrete and designed to be buoyant, are constructed on land, usually in a shipyard or dry dock. The ends of the elements are closed with temporary bulkheads, making them watertight. Each element, which may be as large as a football field, is then floated to the tunnel site, sometimes on a barge. The tunnel element is readied for immersion, then lowered into a trench that has been dredged under water. Each successive element is aligned with the previously placed element and joined underwater using a watertight seal. After the elements are joined, the bulkheads are removed from the inside. The completed tunnel is covered with fill material and topped with a layer of heavy stones or precast concrete castings. These are some of the technical terms commonly used to discuss this method of tunnel construction: BALLAST: a stabilizing weight (stones or concrete), either temporary or permanent, often added to the tunnel elements while floating, being immersed, or in their final position. COFFERDAM: a temporary structure, constructed in water and pumped dry; used to keep water out so that work can be performed in dry conditions. QUAY (pronounced key ): A wharf or reinforced bank where ships are loaded or unloaded, built parallel to the bank of a waterway. A tunnel west of Third Avenue in Brooklyn may encounter buried quays built along earlier shorelines. Tunnel elements are lowered underwater, where they are placed in a trench dredged in the sea bottom. 1991 David Sailors This cofferdam, used to build immersed tunnel elements under dry conditions, was then flooded so the completed sections could be floated out. A steel-shell segment, used to construct an immersed tunnel as part of the Boston Central Artery project

Sandvik 4 Roadheader A roadheader may be used to excavate tunnels through soft rocks and soils. A waterproofing membrane is installed between the ground and the tunnel s concrete lining. SEQUENTIAL EXCAVATION METHOD (SEM) TUNNEL SEM, also known as New Austrian Tunneling Method (NATM), was developed in Austria but is now used worldwide. This underground method of excavation divides the space (cross-section) to be excavated into segments, then mines the segments sequentially, one portion at a time. Whereas TBMs can only excavate a fixed (generally circular) shape, SEM permits a tunnel of any shape or size to be excavated. This makes it useful in areas where the tunnel shape or size needs to change, such as highway ramps and subway stations. The excavation can be carried out with common mining methods and equipment (often a backhoe), chosen according to the soil conditions; tunnel-boring machines are not used. Ground conditions are assessed at the face of the tunnel or from the side of a small tunnel, which helps to decide how to proceed in the best way and determines the choice of equipment and lining. SEM involves careful sequencing of the excavation as well as installation of supports. SHOTCRETE (a kind of concrete sprayed from high-powered hoses) may be used to line the tunnel or support the face, and GROUTING (the injection of a cementing or chemical agent into the soil) may be used to increase the soil s strength and reduce its permeability. SEM requires extremely dry conditions; dewatering is often necessary before the excavation can proceed. Because of the requirements of this method, the rate of excavation is slow. These are some of the technical terms associated with this type of tunnel construction: DEWATERING: the removal of ground water from the area to be excavated. DRAWDOWN: a lowering of the normal ground-water level (water table) as the result of dewatering. HEADING: A smaller tunnel used when a larger tunnel is excavated in several stages. Smaller headings are used when full tunnel excavation at once would not be prudent. Sometimes multiple headings are used simultaneously to increase the number of excavation faces and compensate for SEM s slower excavation rate. Shotcrete, a pneumatically sprayed concrete, will be applied on these tunnel walls, which have been lined with waterproofing and a cage of wire-mesh fabric.

OTHER TUNNELING TERMS CROSS-PASSAGE: a short passage or tunnel connecting two adjacent tunnels, often used to allow people to escape from one tunnel to another in an emergency. CUT-OFF WALL: an underground wall, either temporary or permanent, used in tunnel excavations to prevent the passage of ground water. GRADE: a measure of the inclination of a road or slope. MOLE: slang term for a tunnel engineer. PILE: a long, slender, below-ground column, usually of steel, timber or reinforced concrete, serving as a foundation for a structure by transferring the structure s weight to bedrock or other subsurface materials more capable of withstanding the loads. PILOT TUNNEL: an exploratory tunnel, usually smaller and driven ahead of the main tunnel. SANDHOG: slang term for a tunnel worker. SHAFT: a vertical excavation, often used to provide access to a tunnel from the surface. UNDERPINNING: the installation of new supports beneath the foundation of a building or other structure to protect it from settlement caused by adjacent tunneling or other construction; sometimes used in place of an old foundation that was removed. VENTILATION BUILDING: a building that houses ventilation fans and other mechanical and electrical equipment necessary to ventilate, power, and light a tunnel. GEOTECHNICAL TERMS BACKFILL: material such as sand, gravel or crushed stone used to fill the remainder of an excavation after a tunnel or other underground structure has been constructed within the excavation. GLACIAL DEPOSITS: a mixture of geological debris (such as rocks, stones, gravels, silts and clays) carried, plowed and mixed by glacial ice and meltwater. ORGANIC SILT: a silt, highly compressible and with a low bearing capacity (strength), containing plant and occasionally animal remains. OVERBURDEN: the soil between the ground surface and the roof of a tunnel. SETTLEMENT: the movement or settling of soils. SILT: soil whose grains are finer than sand but coarser than clay. SOFT GROUND: soils and weak rock that can be easily removed. TERMINAL MORAINE: an area where glaciers melted during their southward advance, leaving behind an accumulation of boulders, stones and other debris. Underpinning the IND tunnel, Northern Boulevard, with transfer beams and new supports Brooklyn-Battery Tunnel ventilation building, Governor s Island, New York Muck in the Lincoln Tunnel awaiting removal, 1935

HOW TO CONTACT US We welcome your comments. To contact us or for more information, please write or call: New York State Department of Transportation Gowanus Expressway Project Community Office 920 Third Avenue (34th Street) Brooklyn, New York 11232 Phone: (718) 832-5060 Fax: (718) 832-5097 Visit our project website at: http://www.gowanusproject.com 1986 David Sailors New York State Department of Transportation Joseph H. Boardman, Commissioner Douglas A. Currey, P.E., Regional Director Trial assembly of the castiron ring segments used to line the Lincoln Tunnel Fort McHenry Tunnel portal, Maryland