LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD



Similar documents
WHY MORE PUBLIC SECTOR OWNERS ARE CONSIDERING LEAN PROJECT DELIVERY BASED ON DATA-DRIVEN METRICS. Presented to LCI San Diego CoP January 15, 2015

Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at

APPLICATION OF LEAN PRINCIPLES & PRACTICES IN CONSTRUCTION MANAGEMENT

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.

LEAN CONSTRUCTION: THE NEW STANDARD, AND THE

The Last Planner System of Production Planning & Control. Glenn Ballard Trondheim, Norway May 21, 2014

ResearcH JournaL 2014 / VOL

LCI Lean Project Delivery Glossary

Lean Enablers for Managing Engineering Programs Presentation at the NDIA Program Management Systems Committee August

Lean Principles by Jerry Kilpatrick

Manufacturing Flow Management

Lean Construction Opportunities Ideas Practices

Rules to Consider. All work shall be highly specified as to content, timing, sequence, and outcome.

IMPLEMENTING LEAN CONSTRUCTION: UNDERSTANDING AND ACTION

Getting Started with Lean Process Management

Ensuring Reliability in Lean New Product Development. John J. Paschkewitz, P.E., CRE

Lean Manufacturing Essential Principles

The Combination of Last Planner System and Location-Based Management System

SAN DIEGO COMMUNITY COLLEGE DISTRICT FACILITIES SERVICES LEAN ENTERPRISE JOURNEY

IPD, Lean and BIM: Hype or the Real Deal?

Developing a Formidable Business / Continuous Improvement Methodology in Africa. By: Frederick O Popoola

Business Challenges. Customer retention and new customer acquisition (customer relationship management)

Sigma (σ) is a Greek letter used to represent the statistical term standard deviation

Terrigal Burn MD Lean Physician Champion Palo Alto Medical Foundation

Lean Silver Certification Blueprint

Thank you for joining: The Bottom Line of Green is Black: Sustainability Practices for Every Business to Profit The webinar will begin shortly.

Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at

Greening The Data Center

WHITE PAPER. Lean Construction. Technology Advances in Lean Construction

Chapter 11. Lean synchronization

Lean Software Development

Lean Manufacturing and Six Sigma

Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at

Executive Guide to SAFe 24 July An Executive s Guide to the Scaled Agile Framework.

Turner Innovation Series BIM Conference Istanbul May Brian Krause, Dan Gramer, Turner Construction Company

times, lower costs, improved quality, and increased customer satisfaction. ABSTRACT

CFIRE. Applying Lean Techniques in the Delivery of Transportation Infrastructure Construction Projects. CFIRE July 2011

PLAYING GAMES: EVALUATING THE IMPACT OF LEAN PRODUCTION STRATEGIES ON PROJECT COST AND SCHEDULE

Improving NPI Effectiveness using Lean Thinking. Webinar 6 th October 2015

The Lego Lean Game. Danilo Sato, Francisco Trindade XP 2009 Sardinia - Italy. 25 th May 2009

Breaking Down Silos Asset Management, Predictive Maintenance and Space Utilization Identify Collective Interests Across District and Colleges

AEC Supply Chain Optimization

Investigation on the Effects of Elimination of Waste Levels in Managing Cost Levels In the Pharmaceutical Industry in Kenya

Operations Management and Lean Six Sigma. Presented by: David Muncaster Manager, CI and CSAT Staples Advantage Canada

Waterloo Agile Lean P2P Group

THE MARRIAGE OF CPM AND LEAN CONSTRUCTION

The Economics of LEED for Existing Buildings. Michael Arny President, Leonardo Academy

REDUCING ENERGY CONSUMPTION IN SCHOOLS: 12 Tips for Tackling an Energy Management Program K-12 WHITE PAPER

Using the Lean Model for Performance Improvement

Leading Continuous Improvement in Established Agile Organizations

White Paper. Process Improvement

CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?

VALUE STREAM MAPPING FOR SOFTWARE DEVELOPMENT PROCESS. Ganesh S Thummala. A Research Paper. Submitted in Partial Fulfillment of the

WORKPLAN: DATABASE FOR WORK PACKAGE PRODUCTION SCHEDULING

LEED PRESENTATION OUTLINE

How Lean Services Lead to Lower Costs and Happier Customers

Online Orientation. San Diego Community College District WorkAbility III

Global Packaging Solutions Driving world class supply chain solutions

KANBAN IN CONSTRUCTION

Creating the Lean and Efficient Medical Practice

UTILIZAÇÃO DA LEAN METODOLOGIA. Desmistificando Aplicações Reais Para CME. Apresentado por John Kimsey

EXHIBIT 2-2-C PROGRESS SCHEDULES

Maximizing Our CMMS Effectiveness

Adopting Lean Methodology In A Behavioral Healthcare Setting

The California State University Office of Audit and Advisory Services CSU CONSTRUCTION. San José State University. Student Wellness Center

Lean Training Ideas for TECOM. The Marine Corps needs more training time. Industry best practices can improve our training pipeline.

PROJECT MANAGEMENT BASICS

Srikanth (Sri) Poranki, Ph.D., CSS-Black-Belt Director, Performance Improvement Dept. Quality & Patient Safety UHSH

Making Improvement Work in Pharmaceutical Manufacturing Some Case Studies. Ronald D. Snee

Value Stream Mapping

Total Productive Maintenance. Implementing TPM in Baxter Aibonito

Design Build Institute of America (DBIA)

Lean Manufacturing: Part 1. Charles Theisen, CPIM, CIRM. Lean Manufacturing Part 1

LEAN 101 CRASH COURSE. Presented by Jacob McKenna and Seaver Woolfok

Brant Community Healthcare System STRATEGIC ENERGY MANAGEMENT PLAN (SEMP) FOR

PARADIGMS THAT DRIVE COSTS IN MANUFACTURING. The whole purpose of a business enterprise is pretty simple to make a profit by selling

Lean Thinking Part I

GE Capital. Driving change and continuous process improvement. how-to

Getting Started with Kanban Paul Klipp

Concord Hospital ASQ Meeting May

Lean manufacturing in the age of the Industrial Internet

Improving Healthcare at. Lean Six Sigma

for Information Technology

Lean in Product Development

Lean Manufacturing for the Wood Products Industry. Brian Brashaw University of Minnesota Duluth Natural Resources Research Institute

Live Learning Center. Solution-Driven Integrated Learning Paths. Make the Most of Your Educational Experience

Implementation of Lean Six Sigma Principles: Making Data Cleansing Lean

Lean Supply Chain and Logistics Management

Learning to see True Cost

Greening Our Future By Educating Tomorrow s Workforce. Module 2: Lean Manufacturing and the Environment

TRAINING SESSION SUMMARIES FOR MANUFACTURING

VALUE STREAM MAPPING & VM

Board of Regents Meeting August 14-15, 2008 Item # 20 EXECUTIVE SUMMARY Page 1 of 7

Case study background Intensive Big Room

The paper should take you around 60 minutes to read and complete any directed tasks.

NORTHUMBERLAND HILLS HOSPITAL STRATEGIC ENERGY MANAGEMENT PLAN FOR 2014 TO 2019

Purchasing Success for the Service Sector: Using Lean & Six Sigma.

CHAPTER 9 SUPPLY CHAIN DESIGN DAVID A. COLLIER AND JAMES R. EVANS. OM, Ch. 9 Supply Chain Design 2009 South-Western, a part of Cengage Learning

The Need for Lean Training

TALKING POINTS SUPPORTING BACHELORS IN SCIENCE IN NURSING FROM CALIFORNIA COMMUNITY COLLEGES

Transcription:

LEAN PROJECT DELIVERY THROUGH DESIGN-BUILD Presented to Arizona State University DBIA Student Chapter Co-sponsored by DBIA Arizona Chapter and LCI Arizona CoP February 24, 2015

In the Beginning

+ 80 percent Why Did San Diego Community College District Start Its Lean Journey? Built Environment (+1.6M square feet) Operating Budgets (-US$46M) -16 percent

What our team heard? You want us to do what???

Let s Think!!!

Current State

Current State Future State

Current State

Desired State Design Team Owner Builder Building Users Specialty Trades Energy Management Project Suppliers FF&E Prefabrication IT Maintenance & Operations

How to Get a Better Project BIM LEAN LEED & LCCA

Use Design-Build to Foster Lean Behaviors

Lean Fundamentals

Constant $ of Contracts/Labor Hours per Hourly Worker Non-Farm Construction From: Teicholz (2013) 2015 Umstot Project and Facilities Solutions, LLC

Construction Labor Waste in the U.S. Current Manufacturing Current Construction Support Activity 12% Waste 26% Support Activity 33% Waste 57% Value Added 62% Value Added 10% Source: Construction Industry Institute 2015 Umstot Project and Facilities Solutions, LLC

What is Lean Construction? Lean Construction is a production management-based approach to project delivery to maximize value and minimize waste. - Lean Construction Institute 2015 Umstot Project and Facilities Solutions, LLC

Lean Philosophies Define customer value Identify and remove waste Innovate and perfect Value Value is defined by the owner Value is not cost Courtesy: Southland Industries

The Eight Wastes as Defined by Toyota (and Liker) 1. Overproduction 2. Waiting 3. Unnecessary transport 4. Over-processing 5. Excess inventory 6. Unnecessary movement 7. Defects 8. Unused employee creativity 2015 Umstot Project & Facilities Solutions, 18LLC

Cartoon By: JC Gatlin

Cartoon By: JC Gatlin

Typical Types of Design Waste: Iterative Design Rework Lack of Coordination Between Disciplines Inefficient work flow Over design of systems (diversity and factors of safety) Poor design that generates waste during construction Designing over allowable budget 2015 Umstot Project & Facilities Solutions, LLC 26

Typical Types of Construction Waste: Rework Requests for Information Change orders Inadequate Resources Inefficient work flow Workarounds Multiple handling of material Excess material Waiting on supplies Waiting on another trade Safety losses Improper sequencing of work 2015 Umstot Project and Facilities Solutions, LLC

UK Construction 2025 Goals https://www.gov.uk/government/uploads/ system/uploads/attachment_data/file/210 099/bis-13-955-construction-2025- industrial-strategy.pdf

UK Construction 2025 Goals

UK BIM Goals 2015 Umstot Project and Facilities Solutions, LLC

Perceptions of Efficiency in Our Industry Source: McGraw-Hill SmartMarket Report (2013)

2-Second Lean (A Guide) Fix What Bugs You Paul Akers

Who is Going Lean? 2015 Umstot Project and Facilities Solutions, LLC

http://www.leanconstruction.org/training/lean-project-delivery-guide/ 2015 Umstot Project and Facilities Solutions, LLC

San Diego CCD Lean Practices

San Diego Community College District (SDCCD) Overview The Second Largest Community College District in California Serving 130,000 students Sixth Largest in Nation Three Colleges - City, Mesa and Miramar Six Continuing Education Campuses $1.555 B Locally Approved Capital Bonds City College Mesa College Miramar College Continuing Education

Total Cost of Ownership 50-year design life 100,000 square foot classroom building Design and construction cost - $30 million Capital Renewal: 2% of current replacement value (APPA benchmark) O&M Budget $5.69/square foot Inflation: 3%

Total Cost of Ownership Save 5% in Cap. Renewal Total Cost of Ownership 11% 36% 53% Savings D&C: $30M Total NPV Cap. R.: $101M $ 5M $1.1M O&M: $149M $15M $3.4M Total: $280M $20M $4.4M Save 10% in O&M 2015 Umstot Project & Facilities Solutions, 39 LLC

Early (and continued) Attitudes Toward Lean We ve tried that. We already do that. We don t need it. It won t work here. We don t build cars. We re different. The other guy needs it, not me. We re doing well, so why change? Credit: Lean Construction Institute 40

Use of Lean Tools in Capital Project Delivery 1. Target Value Design 2. A3 Problem Solving and Reporting 3. Set-Based Design 4. Value Stream Mapping 5. Building Information Modeling (BIM) 6. The Last Planner System

Defining Values for SDCCD Enhance the student experience Flexibility in design to accommodate future changes in pedagogy Lower total cost of ownership Highly energy efficient buildings Reduce maintenance and operations costs Meet or exceed sustainability objectives

Value-Waste Nexus How to create value within fixed monetary constraints? Eliminate waste Enhance value with the savings from waste reduction 2015 Umstot Project & Facilities Solutions, LLC 43

Public Owner Benefits Reduced Waste in Project Delivery Sustainable Buildings Reduced Total Cost of Ownership Enhanced Value 44

How to get there?

Design-Build Using Target Costing

Target Costing - Project Budget Development Space Programming Space Efficiency Targeted Cost Per Sq. Ft.

Keys to Target Value Value Definition Concurrent Estimating BIM Target Value LCCA Lean Set-Based Design

A3 Problem Solving HVAC Design

A3 Problem Solving Structural System Design

http://public.sdccdprops-n.com/design/sdccd%20- %20Building%20Design%20Standards/SDCCD%20BIM%20Standards%20Version%202.pdf

Which Design Would You Want?

Is Critical Path Method Scheduling Obsolete?

Schedule Performance SDCCD Experience: 34 Major Projects with CPM Scheduling 4 (12%) finished on time UC System Experience in past 10 years: More than 30% of projects delayed by more than 90 days Research by Glenn Ballard and Greg Howell indicated only 54% of planned weekly activities get completed on average. Last Planner pull system a better way (typically 80-90% percent promises kept)

Last Planner System Who are the Last Planners? The foremen and superintendents 5 Major Elements of System 1. Master Scheduling setting milestones 2. Phase (Pull) Planning specifying handoffs 3. Make Work Ready Planning 6 week look-ahead 4. Weekly Work Planning 5. Learning - Measure Percent Promises Complete, conduct root cause analysis and act on reasons for failure to keep promises 2015 Umstot Project and Facilities Solutions, LLC

Last Planner System Principles 1.All plans are forecasts and all forecasts are wrong. The longer the forecast the more wrong it is. The more detailed the forecast, the more wrong it is. 2.Plan in greater detail as you get closer to doing the work. 3.Produce plans collaboratively with those who will do the work. 4.Reveal and remove constraints on planned tasks as a team. 5.Make reliable promises. 6.Learn from breakdowns. 2015 Umstot Project and Facilities Solutions, LLC

Source: Adrian Smith (2011) 2015 Umstot Project and Facilities Solutions, LLC

2015 Umstot Project and Facilities Solutions, LLC Pull Planning Start with the end in mind. Steven Covey

Pull Planning Activities 2015 Umstot Project and Facilities Solutions, LLC

Milestone Planning Design Phase 2015 Umstot Project and Facilities Solutions, LLC

Pull Planning 6 Week Lookahead 2015 Umstot Project and Facilities Solutions, LLC

Pull Planning 6 Week Lookahead 2015 Umstot Project and Facilities Solutions, LLC

Pull Planning 6 Week Lookahead 2015 Umstot Project and Facilities Solutions, LLC

Pull Planning 6 Week Lookahead Source: LCI (2009) 2015 Umstot Project and Facilities Solutions, LLC

https://www.youtube.com/watch?v=i4vaykjmmyg 2015 Umstot Project and Facilities Solutions, LLC

San Diego CCD Metrics Discussion

Wouldn't It Be Nice If You Could... Average Savings of $900,000 on each of 15 projects Reduce Average Schedule Delay by 56 days Enhance Sustainability Objectives by 44% Reduce Facilities Maintenance Costs by 53% 72

By the Numbers The Database 35 COMPLETED PROJECTS US$584M CONTRACT VALUE 8000 CHANGE ORDERS 73

Change Order Analysis Pre-Lean 7.73% Total COs 2.99% E&O COs Post-Lean 4.43% Total COs 1.88% E&O COs 74

Interesting Finding Without Lean: E&O 33% of COs With Lean: E&O 36% of COs 75

Who is on Time? Pre- Lean 1/19 (5%) Post- Lean 3/15 (20%) 76

San Diego CCD Schedule Impacts Lean (with BIM) vs. No Lean or BIM (20 projects) Average Delay (All Contract Types) Lean w/ BIM: 25 days (n=8) Pre-Lean w/o BIM: 80 days (n=12)

Target Costing 11 Projects Avg. Value: US$21.8M 83% Met Target Cost; Avg. 7% Below Target Cost 78

Target Value Design Six projects evaluated Range of GMP: $4,707,408 to $50,423,353 Average: $21,768,648 5/6 (83%) met target budget Averaged 7% under target budget

Target Value Design Root Cause Analysis Lack of contemporaneous estimating and exclusion of specialty trades from early participation in project resulted in project exceeding target budget Counter measure: All subsequent projects required presentation of budget first

Potential Sustainability Features Higher building energy efficiency Extensive use of daylighting Use of natural ventilation tied to EMS Reduced water consumption Use of reclaimed water for irrigation, flushing Solid flooring without need for stripping and waxing

Sustainability as a Core Value LEED Gold Projects Direct Contract with Architect Post-Lean Target Value Design 82

Value as Reduced Maintenance Costs $3.93/sq.ft. Over 4 Years $1.91 $1.73 $1.46 83

US$34.6 Million of Waste Eliminated US$13.6M Total Savings in Reduced COs US$7.7M Total Savings To Date with TVD US$13.3M Total Savings over 3 Years in Maintenance Costs 84

Questions? David Umstot, PE, CEM Umstot Project & Facilities Solutions, LLC 2015 President, DBIA Western Pacific Region david.umstot@umstotsolutions.com 619.201.8483 (O) www.umstotsolutions.com www.realignment.solutions