San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS



Similar documents
SECTION POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.

San Antonio Water System Standard Specifications for Construction ITEM NO SLIP-LINING SANITARY SEWERS

SECTION GRAVITY SANITARY SEWERS

53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:

SECTION 21 REHABILITATION OF SANITARY SEWER MAINS BY THE PIPE BURSTING AND TRENCHLESS PIPE REPLACEMENT METHOD

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation

San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

INSTALLATION OF INSITUFORM LINER

FY08 SEWER POINT REPAIRS BID TABULATION

SECTION CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

Section 2100-Trenching and Tunneling

CLEANING, INSPECTION, AND TESTING OF SEWERS

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

SECTION SITE PREPARATION

LS 2540 SEWER LATERALS AND INSPECTION TEES

SECTION 810 SEWER LINE CLEANING

Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority

Section 402. STORM SEWERS

Special Specification 7021 Water Main and Sewer Line Replacements

C. Section TESTING LABORATORY SERVICE.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

Sewer Water Pipeline Replacement with CERTA LOK RESTRAINED JOINT PVC PIPE

SECTION REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.

STANDARD SPECIFICATIONS SECTION CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

STANDARD SPECIFICATIONS SECTION CLOSED CIRCUIT TELEVISION INSPECTION OF SEWER MAINS, MANHOLES AND LATERALS

CCTV INSPECTION OF SEWER LINES. A. Section Sanitary Gravity Sewer Lines. B. Section Sanitary Gravity Sewer Line Testing

MDWASD 8/1999 SECTION TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

FY15 Gravity Sewer and Manhole Rehabilitation

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

SECTION ABANDONMENT OF SEWER MAINS

March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS

DIVISION 4300 STORM DRAINAGE

SERVICE LINE EXTENSION AND SERVICE LINE CONNECTION CONDENSED SANITARY SEWER SYSTEM INSTALLATION SPECIFICATIONS

Sewer Line Rehabilitation

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

San Antonio Water System Standard Specifications for Construction ITEM NO. 854 SANITARY SEWER LATERALS

SECTION EARTH MOVING

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

ARLINGTON HEIGHTS MUNICIPAL CODE CHAPTER 22 SEWERS

SECTION STORM DRAIN SYSTEM

SEWER BACKUPS & BASEMENT FLOODING PREVENTATIVE SOLUTIONS FOR THE BUILDING OWNER

SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

Beacon Hill Sewer District Standard Specifications

SECTION STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

REHABILITATION OF UNDERGROUND SEWER LATERAL PIPES WITH CURED-IN-PLACE-PIPE LINER SECTION 02542

STANDARD SPECIFICATIONS SECTION CLEANING AND LINING WATER MAINS

ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

SECTION SELECTIVE DEMOLITION

SECTION STORM DRAINAGE TABLE OF CONTENTS

Wastewater Capital Projects Management Standard Construction Specification

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH Purpose and Application.

SANITARY SEWER SERVICE CONNECTION INSTRUCTIONS

1.3.2 Method of construction and restoration of existing water service connections. This shall include:

SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING

812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.

City of Virginia Beach Public Utilities HRPDC Regional Construction Standards, 5 TH Edition Amendments May 19, 2014

CONSTRUCTION PERMIT REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS

Sewer Rehabilitation Design Requirements

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

City of Regina Standard Construction Specification SECTION 1320 SEWERMAIN TESTING

STANDARD SPECIFICATIONS SECTION PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

Town House Center Highway North Huntingdon, PA 15642

SECTION IX SLIP LINING PIPELINES

SECTION PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION BUILDING SEWERS. B. Connection of building sanitary drainage system to municipal sewers.

Section SEWER PIPE INSTALLATION AND TESTING

SEWER SERVICE LINE REPLACEMENT PROGRAM PROCEDURE Revision No. 1 - Effective January 4, 2016

SECTION 802 GRAVITY SEWER PIPE

CHAPTER 6 - SANITARY SEWER

DESCRIPTION OF WORK:

SEWER CLEANING, INSPECTION AND ASSESSMENT

CHAPTER 17: STORM SEWER STANDARDS Introduction Administration Standards 17.1

CW GRAVITY SEWERS TABLE OF CONTENTS

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

SECTION FACILITY STORM DRAINAGE PIPING

CHAPTER 5. Storm Sewer

Waste Collection Systems

THE CORPORATION OF THE CITY OF GUELPH. THEREFORE the council of the Corporation of the City of Guelph enacts as follows:

STORM DRAIN PIPE MAINTENANCE. a. Develop standard operating procedures for maintaining storm drain pipes.

Storm Drain Inlet Protection - IP

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

STANDARD SPECIFICATIONS SECTION INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223

Close-Out Documents... 9

Minimum Design Criteria for the permitting of Gravity Sewers

SECTION ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section Submittals.

Stormwater/Wetland Pond Construction Inspection Checklist

Transcription:

ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located within the utility easement or street right-of-way, when replacing short lengths of failed pipe with new pipe. 3. Obstruction removal by remote device or excavation. 1103.2 MATERIALS: 1. Material of sanitary sewer pipe and lateral: Materials for sanitary sewer pipe and laterals shall conform to Item No. 848, Sanitary Sewers and Item No. 854, Sanitary Sewer Laterals. If point repair is located at a service connection, use a full-bodied fitting for the service connection. No field fabrications of fittings are allowed. 2. Jointing Material: Use flexible adapters secured with ½ inch stainless steel bands, as manufactured by Fernco, or approved equal. All flexible adapters shall be concrete encased to prevent movement or breakage of the steel bands. 1103.3 CONSTRUCTION: 1. Point Repair: a. Locate and replace small lengths of one or more pipe sections where isolated line failure has occurred due to settlement, corrosion, crushing, or separation of joints. b. The Inspector may identify potential locations for point repair, but the Contractor is responsible for verifying all point repair locations. c. Determine the location of service line repairs by smoke testing the sewer line between the manhole sections where the failed pipe is 1103-1 April 2014

located. The Inspector will authorize the Contractor to make additional point repairs based on results of smoke testing. d. Smoke testing shall not be performed within 24 hours of a rainfall event, or if ponding/ standing water is present on the ground or in the drainage channels in the area planned for smoke testing e. Smoke testing shall be accomplished utilizing two minimum 1,750 CFM blowers designed specifically for smoke testing of sewers. Place blower on the upstream and downstream manhole of the line section to be tested. Place sandbags in the upstream and downstream manholes to isolate the section being tested and prevent the migration of smoke into sections not being tested. Utilize smoke bombs as necessary to ensure a continuous supply of smoke is provided for the entire duration of the test period. f. Determine the location of point repairs by smoke testing or video inspection of the sewer line between the manhole sections where the failed pipe is located. The Inspector will authorize the Contractor to make additional point repairs. g. The Inspector will authorize each point repair after failure points are located. Do not make point repairs without prior authorization of the Inspector. Perform point repairs only on those portions of service lines which are located in an easement or right-of-way; perform no repairs to service lines on private property. h. Replace all identified damaged pipe for point repairs unless otherwise directed by the Inspector. 2. Obstruction Removal: Remove obstructions by one of the following methods: a. Obstruction removal by remote device: (1) Protruding taps: Service laterals that protrude more than one inch into the sewer main. (2) Other obstructions: Hanging gaskets, fixed debris, stabilized sand, hardened mineral deposits, roots, rust scale, tuberculation, etc. 1103-2 April 2014

b. Obstruction removal by excavation: Obstructions encountered during liner insertion that are removed by digging and exposing the damaged section of main. 3. Submittals: Submit product data for each pipe product, fitting and jointing material. 4. Sequencing: a. Before rehabilitating a section of sewer main between adjacent manholes, complete point repair and obstruction removal of that section. b. Clean line and perform post-installation video inspection for each point repair on sewer mains not scheduled for rehabilitation. c. Post-installation video inspection of service laterals having point repairs performed are required. d. All approved post installation video shall be performed in conformance to Item No. 866, Sewer Main Television Inspection. 5. Protection: a. Provide barricades, warning lights and signs for excavations created by point repairs. Comply with Item No. 805; Temporary Facilities and Controls. b. Do not allow soil, sand, debris or runoff to enter sewer system. 6. Bypass Pumping: Install and operate bypass pumping equipment as required to maintain sewage flow and to prevent backup or overflow. Comply with Item No. 864, Bypass pumping. 7. Excavation: a. Excavate and backfill trenches in accordance with Item No. 804, Excavation, Trenching and Backfill. 1103-3 April 2014

b. Perform work in accordance with OSHA standards. Employ a trench safety system as required in Item No. 550, Trench Excavation Safety Protection. c. Remove and lawfully dispose of excess excavated material and debris from the work site daily. 8. Typical Sequence of Point Repair: a. Perform pre-installation video inspection, if required, to verify location of sewer main point repair locations. Perform service testing between manholes to verify location of service lateral point repair locations. b. After the location of a point repair is determined, excavate the required length for the point repair. c. Prior to replacing a damaged section(s) of pipe, determine condition of the existing line on both sides of the point repair by lamping the main at least 10 feet in each direction. Determine whether additional lengths of main (beyond "minimum length" criteria) need replacement. Report need for additional replacement to Inspector and obtain authorization before proceeding. d. Remove the damaged section(s) pipe and replace with new pipe, shaping the bottom of the trench and placing the required pipe bedding so that the grade of the replaced pipe matches the grade of the existing main. Establish proper grade for the section(s) of pipe being replaced using methods acceptable to the Inspector. e. Connect the new pipe to existing main using flexible adapters. If joints cannot be made watertight using flexible adapters, place waterstop gaskets on each joint and encase in a reinforced concrete collar. Reconnect affected service connections or stacks using fullbodied fittings. No field fabrication of fittings is allowed. f. After completion of point repair, and prior to backfill, perform a smoke test to demonstrate satisfactory integrity of the repair, in the presence of the Inspector. Test as specified in Item No. 849, Air Deflection Testing for Sanitary Sewers. Repair and retest sections that fail until repaired sections pass the test. 1103-4 April 2014

g. Encase exposed pipe in cement stabilized sand. h. Backfill the excavation as specified in Itme No. 804, Excavation, Trenching and Backfill. i. Perform a post-installation video inspection as specified in Item No. 866, Sewer Main Television Inspection. Point repairs that show offset joints, non-uniform grade, incorrect alignment, excessive deflection or similar conditions are considered defective work. Contractor shall replace pipe and bedding, as required, to correct defective work. 9. Abandonment of Point Repair: a. Notify the Inspector if a pipe is exposed by excavation and is found to be in good condition, not requiring a point repair. That point repair shall not be performed. b. Notify the Inspector if the pre-installation video inspection reveals that no point repair is required. The point repair shall not be performed. c. Backfill the excavation, replace pavement or sidewalk, and repair and seed or sod unpaved areas. No separate pay item. 10. Obstruction Removal: a. Remote Device: Remove obstructions identified on video of a sanitary sewer line segment which could cause a non-uniform liner pipe installation or obstruction of the liner during installation. Obtain authorization from the Inspector for obstruction removal with a remote device before proceeding. b. Use a power-driven cutting device (robotic cutter) to remove protruding taps. Cut protruding taps so that protrusions are no greater than ¾ inch. If a protruding tap cannot be removed by the cutting device, then a point repair may be performed. Obtain authorization from the Inspector before proceeding. c. To remove other obstructions, use a remote device. Pull or drive the device from manhole to manhole up to a continuous length of 500 feet using a solid steel mandrel, porcupine, root saw, bucket, 1103-5 April 2014

robotic cutter or similar device to remove the obstruction. Select a device that is adequately sized to remove the obstruction. d. Use excavation as the method of obstruction removal when installation of the liner in the sanitary sewer is in progress. If during the liner insertion operation, a collapsed sewer, offset joint, or other obstruction is encountered which prevents or blocks the passage or insertion of the liner, notify the Inspector for authorization to excavate. e. Excavate at the point where there is an obstruction. Use a trench safety system as specified in Item No. 550, "Trench excavation Safety Protection." f. Break out the existing sanitary sewer pipe (carrier pipe) as directed by the Inspector. Remove only that amount of material which is causing the obstruction. Remove the minimum amount of carrier pipe. g. Under such conditions, replacement of the carrier pipe is not required. Do not disturb the existing sewer bedding during excavation. However, if embedment is disturbed during the obstruction removal procedure, place cement-stabilized sand or crushed stone beneath the liner. No Separate pay item. h. When the liner is completely in place, encase it with crushed stone or cement- stabilized sand. 1103.4 MEASUREMENT AND PAYMENT: 1. Unit Prices - Point Repair: a. Measurement for sewer line point repair is on a unit price basis for each repair performed. Minimum length of pipe to be replaced for each repair, determined by depth of sewer line measured from natural ground to flow line at point of repair. b. 9 feet minimum length. c. Measurement for sewer line extra length point repair is on a linear foot basis in excess of minimum replacement length specified above. 1103-6 April 2014

d. Payment for service lateral point repair is on a linear foot basis for all sizes of service laterals and for all depths (same unit price per linear foot, regardless of size and depth). No separate payment will be made for point repair done within the limits of a service lateral reconnection as defined in this Section. Minimum length of service lateral point repair is 3 feet. e. Measurement for hand excavation: When authorized by the Inspector in locations where excavation by machine is not suitable, no direct payment shall be made for hand excavation. f. Measurement for abandonment of point repair by excavation: No direct payment shall be made for abandonment of point repair. g. Measurement for abandonment of point repair by video inspection: No direct payment shall be made for abandonment of point repair by video inspection. h. The cost of the following items of work are included in the unit prices for point repairs, and all associated work: (1) Excavation, embedment and backfill; (2) Hauling away and lawful disposal of excess excavated materials and debris; (3) Pipe, pipe fittings, adapters and concrete collars; (4) Smoke testing and any required retesting; (5) Restoration of site improvements, including sodding; (6) Post-cleaning video inspection; (7) All other necessary work to complete. 2. Unit Price - Obstruction Removal: a. Obstruction removal by excavation will be paid per each obstruction removal performed. Obstruction removal can be submitted for payment when the obstruction has been cleared from 1103-7 April 2014

the sewer line to be lined. Liner work must proceed at least 6 feet before payment for removal of another obstruction will be considered (i.e., all obstruction within a distance of 6 feet is considered to be part of the same obstruction.) b. Obstruction removal by remote device will be paid on a unit price basis, per manhole section, and shall include all obstruction removals within a manhole section. c. The cost of the following work items are included in the unit prices for obstruction removal by remote device or excavation: (1) Cleaning of sanitary sewers due to broken pipe, roots, dirt, loose deposits, etc.; (2) Post television inspection; (3) Excavation, embedment and backfill; (4) Hauling away and lawful disposal of excess excavated material and debris; (5) Restoration of site improvements, including sodding; (6) All other necessary effort to complete work. Payment will not be made for obstruction removal if the existing sewer line, service line or tap is damaged and a point repair is required. Payment will not be made for removal of a protruding tap if the service reconnection is performed by excavation. Removal of hard deposits, concrete, debris, pipes or any other material in a manhole, or that is accessible from the manhole wall, will be cleared under work items for rehabilitation of sanitary sewer pipes and manholes. 3. Stipulated Price (Lump Sum): If the Contract is a Stipulated Price Contract, payment for work in this Section is included in the total Stipulated Price. - End of Specification - 1103-8 April 2014