1 Foreign Affairs Security Training Center (FASTC) U.S. General Services Administration U.S. Department of State Supplemental Draft Environmental Impact Statement for U.S. Department of State Foreign Affairs Security Training Center Nottoway County, Virginia Public Information Meeting January 26, 2015, 7 8 p.m.
2 Format of this Public Information Meeting This presentation will be followed by an informal question and answer session Informational posters are on display Representatives from GSA and DOS are available to explain the proposed project, answer questions, and receive your comments Formal written comments on the Supplemental Draft EIS may be submitted tonight or by February 23,
3 Presentation Overview Background & Status of FASTC Build Alternative 3 Environmental Impact Statement (EIS) Process Supplemental Draft EIS Release and Public Comment Period Supplemental Draft EIS Findings Path Forward 3
4 GSA and DOS Project Management The U.S. General Services Administration (GSA) is responsible for conducting environmental studies, acquiring sites and providing construction procurement, construction management, commissioning, and other services necessary to complete the FASTC project. The U.S. Department of State (DOS) performed Master Planning studies for the project and coordinates with GSA during environmental studies, construction procurement, construction management and commissioning. GSA led the Master Plan update effort. 4
5 U.S. Department of State, Bureau of Diplomatic Security (DS) Mission Statement: The Bureau of Diplomatic Security provides a secure platform for the conduct of U.S. foreign policy. The State Department carries on the business of the American government and its people at more than 275 locations, many in challenging security environments where key U.S. national security interests are at stake. Adequate and systematic security training is necessary to protect our personnel and facilities overseas. 5
6 U.S. Department U.S. Department of State of State, FASTC Project Bureau Purpose of Diplomatic and Security Need FASTC would fill a critical need, identified in the 2008 report to the U.S. Congress and re-affirmed by two independent panels in 2013, for a consolidated security training facility. Current hard skills training is conducted at multiple contracted locations creating inefficiencies. Consolidation is needed to improve training efficiency and provide priority access to training venues. Establish a facility from which to conduct hard skills training focused on embassy security to meet increased demands for well-trained personnel. Train 8,000 to 10,000 students per year. 6
7 Chronology July Selected Fort Pickett and began Environmental Impact Statement (EIS) and Master Planning efforts October 2012 Released Draft EIS for full scope FASTC December 2012 Completed Master Plan for full scope FASTC February 2013 DOS decision to reduce scope of FASTC to hard skills only Early 2013 Project activities placed on hold while additional due diligence conducted April 2014 Administration decision to move forward at Fort Pickett 7
8 8 WASHINGTON DC TRAVEL TIME: 3 HOURS FASTC Location
9 WASHINGTON DC TRAVEL TIME: 3 HOURS FASTC Location LEGEND RICHMOND Surrounding Counties Outlying Counties Urban Areas NOTTOWAY COUNTY PETERSBURG Nottoway County FORT PICKETT Fort Pickett 9
10 Original Full Scope Build Plan Project Has will be Been de-scoped De-Scoped LRA PARCEL 10 PARCEL 21/20 LRA PARCEL 9 GRID PARCEL 10
11 Reduced Scope NO PROGRAM CHANGE REVISED PROGRAM DELETED 11
12 FASTC Revised Master Plan Completed September 2014 Mock Urban Training Explosives Training Core Area Driving Tracks 12 Service Area Vehicle Maintenance Firearms Training
13 Current Scope FASTC Activities Hard Skills Training Driving Tracks Indoor/Outdoor Firing & Explosive Ranges Mock Urban Environment Weapons & Explosives Support Classrooms Administrative Offices Fitness Center Infrastructure Power, Water, Sanitary Sewer Buildings and Grounds Telecommunications Logistics Support 13
14 Critical Path Master Plan Update EIS Design Land Acquisition Construction 14
15 Master Critical Master Planning Path Planning Master Reduced Plan Reduced Update Scope Scope In September 2014, the FASTC project team completed evaluation of the 2012 Master Plan against the DOS realignment of the project to a hard skills only training facility, and have updated the Master Plan to reflect the necessary changes. The 2014 Master Plan Update serves as the basis for NEPA studies and design activities moving forward. 15
16 Critical Path NEPA NEPA / EIS / EIS A Supplement to the Draft Environmental Impact Statement (EIS) was completed between September 2014 January Completion of the Final EIS is anticipated Spring 2015 and will be done concurrently with the design of the facility. The EIS process continues to emphasize public involvement. 16
17 Master Critical Master Planning Path Planning Design Reduced Reduced Scope Scope A/E commenced design services on October 31, Project will be Design-Bid-Build. 5 design packages are being prepared by the A/E. Design packages range in size from $20M - $150M. Some design packages may be combined in a single construction contract depending upon funding availability. 17
18 Project Activities Master Plan Update June 2014 September % complete NEPA Supplemental EIS/Final EIS/Record of Decision September 2014 Spring/Summer % complete Design October 2014-January 2016 Construction Procurements Begin Process in January 2015 Award first Construction Procurement in July
19 What Is Addressed in the Supplemental Draft EIS The purpose of the Supplemental Draft EIS is to address changes to the proposed action relevant to environmental concerns and assess new circumstances and information relevant to potential environmental impacts. Based on adjustments made to the proposed FASTC scope of requirements, a Master Plan Update was prepared in 2014 that modifies the previous build alternatives evaluated in the 2012 Draft EIS. Description of the Build Alternative 3. 19
20 Environmental Studies What Was Evaluated? o Climate o Topography, Geology, and Soils o Water Resources o Biological Resources o Air Quality o Noise o Land Use and Zoning o Recreation o Utilities and Infrastructure o Public Health and Safety o Aesthetic and Visual Technical Studies Updated o Cultural Resources/NHPA Archaeological Surveys Architectural Surveys o Socioeconomics Economic & Fiscal Impacts o Hazardous Substances o Traffic and Transportation New Technical Study o Bat Survey 20
21 Environmental Findings Summary Beneficial socioeconomic impacts to Nottoway County, Chesterfield County, and six adjacent counties Direct and indirect adverse impacts to wetlands, streams, and forest Impacts to a potential federal threatened bat species Impacts to traffic, noise, hunting, and utilities are not significant Details are available in the Supplemental Draft EIS 21
22 Minimization of Impacts Included in Supplemental Draft EIS LEED Silver design - energy efficiency, impact reduction Relocation assistance for affected residents and businesses Shuttle buses to reduce traffic Hunting area access whenever possible Reduce clearing and grading to extent feasible o Re-establish native plants and plant community connections o Retain vegetation as visual buffer Best management practices (BMPs) and low impact development (LID) measures to avoid erosion, sedimentation, stormwater changes, and water quality impacts Design modifications to reduce wetland and stream impacts Water application and vegetation buffers for dust control Gates, signage, and containment of hazards for safety 22
23 Mitigation Under Consideration GSA Urban Development/Good Neighbor Program local coordination to maximize positive impacts DOS Community Liaison/Outreach program Avoid tree clearing to extent possible during northern longeared bat maternity season and migratory bird nesting season Treatments or filtration systems for explosives ranges Additional impact analysis for any project changes, if needed 23
24 Commenting on the Supplemental Draft EIS 45-day Comment Period: January 9 February 23, 2015 Comments can be submitted three ways: o Via the FASTC address: [email protected] o Provide written comments during the public information meeting tonight o Mail a comment form or letter to: Ms. Abigail Low GSA Project Manager 20 N 8th Street Philadelphia, PA Written comments postmarked by February 23, 2015 will be responded to in the Final EIS and become part of the official public record 24
25 FASTC EIS Milestones Notice of Intent to Prepare Supplemental Draft EIS (September 3, 2014) 30 Day Public Comment Period (September 3 - October 3, 2014) Supplemental Draft EIS Available to Public (January 9, 2015) We are here 45-Day Public/Agency Comment Period and Public Meeting (January 9 February 23, 2015) Final EIS Available to Public 30-Day Review Period (Spring 2015) Record of Decision (Spring/Summer 2015) 25
26 EIS Next Steps Final EIS Issued Spring 2015 After Final EIS is released, there is a 30 day review period Only new comments not previously received or responded to in the Final EIS are addressed Record of Decision Published: Spring/Summer 2015 Details of the Government s official decision (i.e., whether or not to move forward with project) 26
27 Contact Information Please contact us with any questions or comments about the FASTC project: FASTC Phone line: FASTC FASTC Website: 27
28 Project Contact Project Information Contact Information Abby Low, Project Manager The General Services Administration (GSA) 20 N. 8 th Street Philadelphia, PA [email protected] 28
29 Questions & Answers Thank You For Joining Us Tonight 29
CHAPTER 4 ALTERNATIVES COMPARISON
CHAPTER 4 ALTERNATIVES COMPARISON 4.1 INTRODUCTION This chapter provides a comparison of the and its alternatives as described in EIS/EIR Section 1.8.3 (s Evaluated in this EIS/EIR) and analyzed in Sections
Proposed General Plan Update Goals, Policies, and Implementation Actions
Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental
US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing
US 281 AT PREMONT PUBLIC HEARING Hearing Purpose The purpose of tonight s Public Hearing is for the public to: Learn about the status of the proposed project Review the purpose and need for the project
March 2008. Prepared by: Irvine Ranch Water District. 15600 Sand Canyon Avenue. Irvine, CA 92618. Contact: Natalie Likens (949) 453-5633
ADDENDUM TO THE MICHELSON WATER RECLAMATION PLANT PHASE 2 & 3 CAPACITY EXPANSION PROJECT FEBRUARY 2006 FINAL ENVIRONMENTAL IMPACT REPORT AND THE SAN JOAQUIN FRESHWATER MARSH ENHANCEMENT PLAN REVISED SEPTEMBER
DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment
DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment Water Protection Bureau Name of Project: Applicant: Ueland Land Development LLC Type of Project: Proposed discharge of treated domestic wastewater
Gold Ray Dam Interagency Technical Team Meeting
Gold Ray Dam Interagency Technical Team Meeting Agenda Public Outreach, Funding, Monitoring EA/BA/Permit Updates Deconstruction Plans Fish Passage & Salvage Plan Hydraulic Modeling Next Steps Public Outreach,
Draft Environmental Impact Statement. PORT OF OSWEGO AUTHORITY Lead Agency, State Environmental Quality Review Act
CENTERSTATE NY INLAND PORT DRAFT SCOPING DOCUMENT FOR THE Draft Environmental Impact Statement PORT OF OSWEGO AUTHORITY Lead Agency, State Environmental Quality Review Act SEPTEMBER 30, 2015 INTRODUCTION
Corridor Goals and Objectives
Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty
How To Amend A Stormwater Ordinance
Regulatory Alternatives to Address Stormwater Management and Flooding in the Marlboro Street Study Area Alternative 1: Amend Existing Local Regulations This proposed alternative provides an incremental
1.7.0 Floodplain Modification Criteria
1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:
List of Preparers AKRF, INC. Robert F. Conway, P.E. EIS Project Manager; Construction Impacts
List of Preparers AKRF, INC. Robert F. Conway, P.E. EIS Project Manager; Construction Impacts Masters, Civil Engineering. More than 30 years of experience in modeling pollutant fate for transportation
Environmental Impact Assessment
Environmental Impact Assessment E. Beimborn, University of Wisconsin-Milwaukee NEPA: the National Environmental Policy Act Enacted in 1969 Provides a general statement of federal policy towards the environment:
SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA
SANTA BARBARA COUNTY COMPREHENSIVE PLAN LOMPOC AREA A. LAND USE ELEMENT INTERPRETIVE GUIDELINES B. COMMUNITY BENEFITS C. COUNTY ACTION ITEMS Adopted by the Board of Supervisors November 9, 1999 A. Santa
Land Protection Planning for the National Wildlife Refuge System
March 2012 Planning Information Brochure 1 Land Protection Planning for the National Wildlife Refuge System The following questions are often asked when the U.S. Fish and Wildlife Service (Service) begins
Appendix J Online Questionnaire
Appendix J Online Questionnaire In accordance with the Paperwork Reduction Act, this questionnaire was approved by the Office of Management and Budget (OMB). The OMB control number and expiration date
CITY OF UKIAH TREE MANAGEMENT GUIDELINES TREE MANAGEMENT POLICIES FOR THE PROTECTION, OPERATION AND MAINTENANCE OF CITY PROPERTY
CITY OF UKIAH TREE MANAGEMENT GUIDELINES TREE MANAGEMENT POLICIES FOR THE PROTECTION, OPERATION AND MAINTENANCE OF CITY PROPERTY FINAL DRAFT November 2010 1.0 PURPOSE STATEMENT The purpose of this document
EXETER TOWNSHIP SKETCH PLAN APPLICATION CHECKLIST
EXETER TOWNSHIP SKETCH PLAN APPLICATION CHECKLIST Submission Checklist: Items A through G ARE REQUIRED for the first submission of a Sketch Plan. Only Item C is required for the submission of revisions
Green Spaces to Improve Waterways and Communities
Green Spaces to Improve Waterways and Communities Thomas M. Evans, ASLA LEED AP Green Infrastructure Design Services Director Cleveland, Ohio Northern Michigan Green Infrastructure Conference June 4, 2015
Chapter 8. List of Preparers
Chapter 8 List of Preparers This page intentionally left blank. 8 List of Preparers Name and DEIS Responsibility and Qualifications United States Fish and Wildlife Service Megan Seymour Wildlife Biologist,
AGENDA LARIMER COUNTY PLANNING COMMISSION Wednesday, April 20, 2016/6:30 P.M./Commissioners' Hearing Room
AGENDA LARIMER COUNTY PLANNING COMMISSION Wednesday, April 20, 2016/6:30 P.M./Commissioners' Hearing Room A. CALL TO ORDER B. PLEDGE OF ALLEGIANCE C. PUBLIC COMMENT ON THE COUNTY LAND USE CODE D. PUBLIC
NOTICE OF PREPARATION
PLANNING DIVISION CITY OF SUNNYVALE P.O. BOX 3707 SUNNYVALE, CA 94088-3707 NOTICE OF PREPARATION TO: Responsible, Trustee, and Other Interested Public Agencies FROM: Sunnyvale Community Development 456
Lower Crooked Creek Watershed Conservation Plan EXECUTIVE SUMMARY
EXECUTIVE SUMMARY Project Background Located in southwestern Pennsylvania, Crooked Creek is a major tributary of the Allegheny River, entering near Ford City in Armstrong County. It is rich in natural
APPENDIX 4. Risk Tables
APPENDIX 4 Tables Preliminary Qualitative Criteria The qualitative risk assessment criteria have been developed to identify key risks to the environment, society, heritage and business reputation. The
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010
Interlocking Concrete Pavement Institute (ICPI) Model Stormwater Ordinance for Permeable Interlocking Concrete Pavements August 2010 Background What are permeable interlocking concrete pavements (PICP)?
Proposed Terms of Reference for EIA studies
1 Proposed Terms of Reference for EIA studies Base line data collection will be collected for the Post-Monsoon season 2016 (September to November 2016) in study area and 10 kms radius from project site.
NASA Stennis Space Center Environmental Resources Document
16.0 Major Environmental Considerations for Proposed Actions All construction, rocket testing, and operations that may potentially impact environmental media, such as air, water, land, aquatic and biotic
SITE DEVELOPMENT PLAN CHECKLIST. Project Name: Site Plan No.:
SITE DEVELOPMENT PLAN CHECKLIST 5/12/05 Rev.3/14/06 Project Name: Site Plan No.: REVIEW CRITERIA Plans: A site development plan (signed and sealed) shall be on a 24 x 36 sheet at a scale that is no smaller
PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013
PLANNED UNIT DEVELOPMENT & SIDEWALK WAIVER REQUEST STAFF REPORT Date: November 7, 2013 NAME LOCATION Audubon Properties, LLC. 4700 & 4960 Dauphin Island Parkway West side of Dauphin Island Parkway, 580
Categorical Exclusion Determination Bonneville Power Administration Department of Energy
Categorical Exclusion Determination Bonneville Power Administration Department of Energy Proposed Action: Removal and Relocation of Equipment from Leased Area in Titan Data Center Project Manager: Molly
SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY
SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the
King Fire Restoration Project, Eldorado National Forest, Placer and El Dorado Counties, Notice of intent to prepare an environmental impact statement.
This document is scheduled to be published in the Federal Register on 12/24/2014 and available online at http://federalregister.gov/a/2014-30158, and on FDsys.gov [3410-11- P] DEPARTMENT OF AGRICULTURE
Application No.: 14.074 Steve Rush, representing Rocky Mountain Power Rocky Mountain Power Project Location: approximately 1600 N. 6800 E.
Planning Commission Staff Report Planning and Development Services Croydon Substation Conditional Use Permit Public Meeting August 28, 2014 Application No.: 14.074 Applicant: Steve Rush, representing Rocky
INSTITUTIONAL MASTER PLAN NOTIFICATION FORM / PROJECT NOTIFICATION FORM BOSTON UNIVERSITY MEDICAL CENTER
INSTITUTIONAL MASTER PLAN NOTIFICATION FORM / PROJECT NOTIFICATION FORM BOSTON UNIVERSITY MEDICAL CENTER JUNE 7, 2013 SUBMITTED TO: BOSTON REDEVELOPMENT AUTHORITY ONE CITY HALL SQUARE BOSTON, MA 02201
Dixie Plantation Master Plan
Dixie Plantation Master Plan COLLEGE OF CHARLESTON, SOUTH CAROLINA SCOPE In 1995, naturalist John Henry Dick bequeathed historic Dixie Plantation to the College of Charleston Foundation. Before his death,
Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria
Memorandum TO: FROM: Michael Bergstrom and Robin Cole City of Bellevue Nancy Bird, AICP EDAW, Inc. DATE: July 23, 2008 RE: Technical Memorandum No. 1: Environmental Approach and Decision Making Criteria
COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES. April 20, 2010 EXHIBIT 1
COMPREHENSIVE PLAN SECTION B, ELEMENT 4 WATER RESOURCES April 20, 2010 EXHIBIT 1 ELEMENT 4 WATER RESOURCES TABLE OF CONTENTS 4.1 INTRODUCTION 4.2 GOALS AND POLICIES 4.2.A General Goals and Policies 1 4.2.B
Angora Fire Restoration Activities June 24, 2007. Presented by: Judy Clot Forest Health Enhancement Program
Angora Fire Restoration Activities June 24, 2007 Presented by: Judy Clot Forest Health Enhancement Program California Tahoe Conservancy Independent California State Agency within the Resources Agency Governed
Chapter 3 SENSITIVE AREAS AND VEGETATED CORRIDORS
Chapter 3 3.01 General Provisions 3.01.1 Introduction 3.01.2 Application and Interpretation of Chapter 3.01.3 Unbuildable Lots 3.01.4 Other Permits 3.01.5 Prohibited Activities 3.02 Service Provider Letter
REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 LEECH WATER SUPPLY AREA RESTORATION UPDATE
Making a difference... together Agenda Item #9 REPORT #RWSC 2013-17 REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 SUBJECT LEECH WATER SUPPLY AREA RESTORATION UPDATE
20, 1994. Service on Feb. 20, 1994.
DEPARTMENT OF AGRICULTURE Agricultural Cooperative Service Agricultural Marketing Service Agricultural Research Service Agricultural Stabilization & Conservation Service Animal & Plant Health Inspection
Site Analysis. Floyd Zimmerman, FASLA. Summary CLIENT NEEDS. Supplemental Architectural Services 2000 AIA 1 SITE ANALYSIS SERVICES
Site Analysis Floyd Zimmerman, FASLA Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 Sensitive owners and designers understand that from the facility user s perspective,
Kirkland Zoning Code 113.25
Kirkland Zoning Code 113.25 Chapter 113 COTTAGE, CARRIAGE AND TWO/THREE-UNIT HOMES Sections: 113.05 User Guide 113.10 Voluntary Provisions and Intent 113.15 Housing Types Defined 113.20 Applicable Use
NYCIDA PROJECT COST/BENEFIT ANALYSIS June 5, 2014
NYCIDA PROJECT COST/BENEFIT ANALYSIS June 5, 2014 APPLICANT Skyline Restoration Inc. CGI Northeast, Inc. Spring Scaffolding LLC Metropolitan Northeast LLC 11-20 37 th Avenue Long Island City, NY 11101
Appendix A Alternative Contracting General Engineering Consultant RFP. Appendix A
Appendix A 1 1.0 Requirements and Minimum Qualifications This section outlines requirements and minimum qualifications for the GEC. It is anticipated that the GEC will be used to support and supplement
PROGRAMMATIC ENVIRONMENTAL ASSESSMENT
U.S. Fish and Wildlife Service, Region 1 Wildlife and Sport Fish Restoration Program FINAL PROGRAMMATIC ENVIRONMENTAL ASSESSMENT for a Streamlined Method for Approving Small Land Disposals of State Lands
SEC. 4001. PURPOSE. SEC. 4002. DEFINITIONS. SEC. 4003. COLLABORATIVE FOREST LANDSCAPE RESTORATION PROGRAM.
TITLE IV--FOREST LANDSCAPE RESTORATION SEC. 4001. PURPOSE. The purpose of this title is to encourage the collaborative, sciencebased ecosystem restoration of priority forest landscapes through a process
2010 Salida Community Priorities Survey Summary Results
SURVEY BACKGROUND The 2010 Salida Community Priorities Survey was distributed in September in an effort to obtain feedback about the level of support for various priorities identified in the draft Comprehensive
FILING REQUIREMENTS EXCERPTS FROM THE ZONING ORDINANCE SOLAR ENERGY SYSTEMS
County of San Diego, Planning & Development Services APPLICANT S GUIDE FOR A SOLAR ENERGY SYSTEM ZONING DIVISION These guidelines provide information on how to apply for a Solar Energy System. Review the
Development proposals will require to demonstrate, according to scale, type and location, that they:-
Appendix 2 : Relevant Development Plan Policies Angus Local Plan Review 2009 Policy S1 : Development Boundaries (a) Within development boundaries proposals for new development on sites not allocated on
COMMUNITY CERTIFICATIONS
National Flood Insurance Program Community Rating System COMMUNITY CERTIFICATIONS Public reporting burden for this form is estimated to average 4 hours for annual recertification, per response. The burden
Sec. 22a-1a page 1 (4-97)
Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination
City of Valdosta Land Development Regulations. Table of Contents
TITLE 1 ADMINISTRATION Chapter 102 General Provisions 102-1 Title 102-2 Purpose 102-3 Authority 102-4 Jurisdiction 102-5 Application of Ordinance 102-6 Relationship to Existing Ordinances 102-7 Powers
SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST
This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)
Draft ENVIRONMENTAL IMPACT STATEMENT FOR MULTIPLE PROJECTS IN SUPPORT OF MARINE BARRACKS WASHINGTON, D.C. April 2015
Draft ENVIRONMENTAL IMPACT STATEMENT FOR MULTIPLE PROJECTS IN SUPPORT OF MARINE BARRACKS WASHINGTON, D.C. April 2015 (This page intentionally left blank) DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR MULTIPLE
U.S. DEPARTMENT OF THE INTERIOR BUREAU OF INDIAN AFFAIRS RECORD OF DECISION COYOTE BUSINESS PARK
U.S. DEPARTMENT OF THE INTERIOR BUREAU OF INDIAN AFFAIRS February 2007 RECORD OF DECISION COYOTE BUSINESS PARK Agency: Action: Summary: Bureau of Indian Affairs Northwest Region Record of Decision Bureau
Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview. Why Subdivision and Land Development Regulations?
Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview Purpose of Subdivision/ Land Development Ordinances (SALDO) Municipalities Planning Code Process Design
23.1 RENEWABLE ENERGY
Proposed Hastings District Plan as Amended 23.1 Renewable Energy 23.1 RENEWABLE ENERGY 23.1.1 INTRODUCTION The use of energy is of fundamental importance to the function and development of our society.
Executive Director s Recommendation Commission Meeting: July 11, 2013
Executive Director s Recommendation Commission Meeting: July 11, 2013 PROJECT Russell Road Widening Phase 2 United States Marine Corps Base Quantico Prince William County, Virginia SUBMITTED BY United
understanding Sustainable Landscaping & Tree Preservation Standards
understanding Sustainable Landscaping & Tree Preservation Standards Purpose To promote landscaping around development that is compatible with the existing environment, and which reduces greenhouse gas
Broadmoor Public Golf Course TREE MANAGEMENT GUIDE
Broadmoor Public Golf Course TREE MANAGEMENT GUIDE Conservation of the trees at the Broadmoor Public Golf Course is a priority for environmental, economic and human health reasons. Trees make a difference
APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES
Los Angeles County Metropolitan Transportation Authority (Metro) 2009 Transportation Improvement Program Call for Projects APPENDIX F RIGHTS-OF-WAY PRESERVATION GUIDELINES Los Angeles County Metropolitan
TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015
TOWN OF MONSON CERTIFICATIONS-SPECIAL TOWN MEETING MAY 11, 2015 ARTICLE 8: The Town voted by 2/3 vote to amend its Zoning Bylaws by deleting the current Section 6.14 Wireless Communications Facilities
Background research on the topic of urban forestry is intended to
overview urban forestry Urban Forestry Background research on the topic of urban forestry is intended to help guide the task of integrating trees and urban forestry goals and aspirations into the Portland
U.S. Department of Transportation Federal Highway Administration. Western Federal Lands Highway Division Vancouver, Washington
U.S. Department of Transportation Federal Highway Administration Western Federal Lands Highway Division Vancouver, Washington Juniper Dunes Access Road WA Franklin 2013(1) Finding of No Significant Impact
TERMS OF REFERENCE. for an ENVIRONMENTAL IMPACT ASSESSMENT. for a PROPOSED RESORT DEVELOPMENT
TERMS OF REFERENCE for an ENVIRONMENTAL IMPACT ASSESSMENT for a PROPOSED RESORT DEVELOPMENT at BIG AND LITTLE PELICAN CAY PORTLAND BIGHT, ST. CATHERINE, JAMAICA TABLE OF CONTENTS BACKGROUND 4 1. Executive
How To Plan A Buffer Zone
Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other
Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE
WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This
ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS
ENVIRONMENT ACT PROPOSED TERMS OF REFERENCE FOR PUBLIC REVIEW AND COMMENT NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS Beaver Bank Bypass Highway 101 to the Beaver Bank Road Halifax County,
15 FAM 1000 CAPITAL CONSTRUCTION AND MAJOR REHABILITATION PROJECTS
15 FAM 1000 CAPITAL CONSTRUCTION AND MAJOR REHABILITATION PROJECTS 15 FAM 1010 SCOPE AND POLICY (Office of Origin: OBO) 15 FAM 1011 SCOPE AND APPLICABILITY The provisions of this subchapter pertain to
Chapter 11. List of Preparers/Conflict of Interest and Disclosure Forms
Chapter 11. List of Preparers/Conflict of Interest and Disclosure Forms 11 LIST OF PREPARERS/CONFLICT OF INTEREST AND DISCLOSURE FORMS 11.1 List of Preparers 11.1.1 U.S. Department of Energy, National
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT
LIQUID WASTE TREATMENT FACILITY MENDIS ROAD, HUDSON CREEK DRAFT GUIDELINES FOR A PUBLIC ENVIRONMENTAL REPORT Introduction The purpose of this Public Environmental Report (PER) is to provide the Government
Council Policy for New Telecommunication Facilities
Council Policy for New Telecommunication Facilities 1. Purpose To establish policies and procedures for the installation of new telecommunication antennas, towers and related structures which emphasize
SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing
SPECIAL USE PERMIT 22-01. JCSA Groundwater Treatment Facility Staff Report for the November 5, 2001, Planning Commission Public Hearing This report is prepared by the James City County Planning Division
Section 4 includes a list of the principal participants in the preparation of this Final EIS and associated supporting documentation.
4. LIST OF PREPARERS Section 4 includes a list of the principal participants in the preparation of this Final EIS and associated supporting documentation. 4.1 FEDERAL HIGHWAY ADMINISTRATION George Hoops,
DEPARTMENT OF ENVIRONMENTAL QUALITY
PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized
Appendix C. Municipal Planning and Site Restoration Considerations
Appendix C Municipal Planning and Site Restoration Considerations 67 68 Appendix C - Municipal Planning and Site Restoration Considerations This appendix contains best practice standards for site planning
Environmental guidelines for preparation of an Environment Management Plan
Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use
8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP
8.0 ENVIRONMENTAL PROTECTION MONITORING AND FOLLOW-UP 8.1 INTRODUCTION Mitigation measures, monitoring and other follow-up actions identified in Chapter 7 (Environmental Effects Assessment and Mitigation)
Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site.
Welcome Welcome to the public exhibition for development at Bowman Field. This exhibition provides an overview of the proposals for the site. Background & Planning Context The Site The site is an area
Backyard Buffers that Work for People and Nature by Restoring Ecological Function
Backyard Buffers that Work for People and Nature by Restoring Ecological Function What is a Wetland Buffer? A wetland buffer is a simple land management practice that is employed by municipalities to protect
Downtown Community Planning Council Meeting offebruary 18, 2015
- san diego Item #12 DATE ISSUED: ATTENTION: SUBJECT: February 13, 2015 Downtown Community Planning Council Meeting offebruary 18, 2015 Consideration of Support for Grant Applications for the San Diego