Verification of need. Assessment of options. Develop Procurement Strategy. Implement Procurement Strategy. Project Delivery. Post Project Review
|
|
|
- Douglas Riley
- 10 years ago
- Views:
Transcription
1 Who should read this fact sheet? Many construction clients are not regular purchasers of construction work. This fact sheet is an introduction to construction procurement for occasional clients with a basic to intermediate understanding of the procurement process. How to get started Occasional clients frequently face a steep learning curve on their construction project. Yet establishing a procurement strategy at the outset is key to a successful outcome. A review of the UK Construction Industry called Accelerating Change identified Six Key Steps that a client should take to devise a procurement strategy. This fact sheet looks at those key steps and concludes with some signposts to further useful information. Taking independent advice Clients considering a construction project are likely to want a solution which will meet their needs, at a cost they can afford, at an acceptable date in the future. There could be a variety of strategies to achieve this. Taking impartial professional advice is useful, though there is no standard method of obtaining such advice. The type of professionals who could help an occasional client with impartial advice include architects, surveyors, designers, building contractors and building services companies, provided they are not to be involved in the construction project itself. Step 1 Verifying need for the Construction Project Output: Statement of needs the value proposition Achieving a successful solution depends upon verifying the need for a project. This process should emanate from the client s value proposition or business case for the project and should involve all stakeholders including those who will take the risks associated with the project and those who will be directly involved in using the completed facility. The process will need to establish and prioritise the objectives to be met by the project and the financial and physical programme parameters. STEP 1 STEP 2 STEP 3 STEP 4 STEP 5 STEP 6 If construction phase required Verification of need Assessment of options Develop Procurement Strategy Implement Procurement Strategy Project Delivery Post Project Review Outputs Statement of Business Needs Priorities, objectives, stakeholders & constraints Business case Encompassing all business requirements Strategic Brief In Client s Terminology Selection of the Team Delivery of the Business Solution By focused Team and Client Capture Learning Confirm benefits & inform future projects Figure 1 Key Steps a Client must consider when faced with a business need (from Accelerating Change) 1 Procurement: 15/3/04
2 Step 2 Assessing the Options Output: Business Case Constructing a new facility might not be only way to meet the client s value proposition. Renting, leasing, buying an existing facility or extending or altering existing premises could provide alternative and possibly cheaper solutions. All options must be assessed and evaluated at an early stage in project development. In most cases the priorities of the projects will fall into the areas illustrated as B, C or D in the diagram where two of the three criteria are identified as most important to project success. It is rare for time, cost and quality to be equal in either importance or impact. After confirming the need and assessing all options, a more detailed case for the project should be developed. This will involve considering return on capital investment, the likely benefits to operational efficiency or income flow. Even at this early stage, initial concept designs can be developed to enable the client and those who will use the new facility to look at how initial designs will respond to business needs. Step 3 Developing Procurement Strategy There are procurement strategies which will achieve: Output: Strategic Brief Certainty of cost and time for a design developed by an architect employed by the client. However, this is a sequential and consequently slow process. (known as the traditional procurement process or designbid-build) The bespoke nature of many construction projects increases the inherent risks. These risks include completing a project which does not meet needs, which is delivered late or costs more than the client can pay or fund. All these risks can impact the client s core business, seriously. The procurement strategy developed should balance risks against project objectives at an early stage. The key criteria listed below are interdependent and often in tension: time (speed or certainty of completion date) cost (price level or cost certainty) quality (functionality and performance) Relative speed and cost certainty. However, the design will usually be the responsibility of a contractor and consequently the client will lose some control over the design process. (known as design-build) Relative speed for a design developed by an architect employed by the client. However, cost is uncertain almost until completion. (known as either management contracting or construction management). Emphasis on only one of the key criteria will almost certainly have a negative effect upon the others. The business case will help determine which criteria are most important and which could constitute the greatest risk. Here, we look at each of these strategies in a little more detail: 2 Procurement: 15/3/04
3 Traditional or Design-Bid-Build This is probably the most commonly used method of procurement and it is suitable for: all clients, including inexperienced clients complex projects and projects where functionality is a prime objective time predictability cost certainty. However, it is not suitable for fast track projects. The client develops the business case for the project, provides a brief and budget and appoints a team of consultants to prepare a design, plus tender documents. The client appoints the building contractor to construct the works to the design, by the contract completion date and for the agreed price. Usually much of the work is sub-contracted to specialist firms but the contractor remains liable. The consultants administer the contract on behalf of the client and advise on aspects associated with design, progress and stage payments which must be paid by the client. The separation of the contractor from the design can mean missed opportunities for contractor or specialist contractor to input. This strategy is a low-risk option for clients who wish to minimise their exposure to the risks of overspend, delays or design failure. However, the exposure to risk will increase where the design phase is rushed, where unreasonable time targets are set or where the tender documents are not fully completed. There is a refinements to this method which involves a two stage tender. Two stage tender contractor s tenders are based on a partially developed consultant s design (stage 1 tender). The contractor then assists with the final development of the design and tender documents, against which tenders for the construction works are prepared (stage 2 tender). Whoever put forward the first stage tender has the opportunity to tender or negotiate the second (construction) stage. This approach increases the risks of an increase in overall price and a less certain completion date but contractor involvement is likely to increase the likelihood that both these criteria are realistically established. Design-Build This method of procurement involves the contractor being responsible for design as well as construction, it can be suitable for: all clients, including inexperienced clients and those requiring distance from the project. cost certainty faster track However, it is not suitable for: an uncertain or developing client brief complex buildings The main contractor takes responsibility for both design and construction and will use either in-house designers or employ consultants to carry out the design. Most of the construction work will be carried out by specialist or sub-contractors. The contractor tenders against a client brief and will often follow an initial concept design prepared by consultants appointed to advise the client.. The design will be developed by the contractor and the works will e completed, usually for a fixed price. Tendering is more expensive so it carries more risk for the contractor than the traditional approach. This is because the contractor has to develop an outline design and a detailed price. Tender lists will probably be shorter than for traditional contracts. The Design-Build approach gives the client a single point of contact. However, the client commits to the cost of construction, as well as the cost of design, much earlier than with the traditional approach. Whilst risk is shifted to the contractor, it is important that design liability insurance is maintained to cover that risk. Changes made by the client during design can be expensive, because they affect the whole of the Design-Build contract, rather than just the design team costs. There are variations on this approach: Develop and Construct where the client has the design prepared to concept or scheme design stage and the contractor takes on finishing off the design and construction. The contractor may re-employ the original designers to complete the design. 3 Procurement: 15/3/04
4 Package Deal where the contractor provides an off-the-shelf building. The building type is often modular so that its size can be adjusted. Typical examples are farm, factory, warehouse and straightforward office buildings. Management Contracting This is suitable for: fast track projects complex buildings a developing brief However, it is less suitable for: inexperienced clients cost certainty before starting construction clients wanting to pass risk to the contractor The client appoints designers and a contractor (management contractor) separately and pays the contractor a fee for managing the construction works. A feature is the early appointment of the contractor to work alongside the design team to develop a programme for construction and contribute to the design and costing of the works. The works are let competitively by the management contractor to subcontractors and specialists in appropriate works packages. This approach often means that design and the start on site overlap, with the design and tender packages becoming available just-in-time to suit the construction programme. The management contractor will not carry out construction work. This preserves the management contractor s independence and reinforces a consultancy relationship with the client. Payment is made to the management contractor on the basis of the cost of the works packages plus the agreed fee Much of the success of this approach depends on the contractor s team. Unless the team is drawn from companies which are experienced in this kind of team working, the benefits are not always realised. There is less price certainty at the outset, because construction tends to start ahead of completion of all design stages and at a point when many of the work packages have yet to be tendered. This often means adjustments are made to the design and specification of works packages later in the programme to keep the project within budget. However, the overall process of design and construction tends to be shorter than in either design-bid-build or design and build situations. Construction Management is similar in concept to Management Contracting. Contractors are contracted directly to the client and the construction manager manages the process for the client on a simple consultancy basis. Construction Management requires constant involvement by the client so it is really only suitable for experienced clients. Step 4 Implementing Strategy Output: Selection of the Project Team Selecting a project team is important. Team members should be selected on the quality of their reputation, their track record for similar projects, their capacity to do the work and the size of their fees. The client must feel comfortable with the way the professionals appointed will handled the desired strategy. Again, the client could look to sources of independent advice to assist in the selection process, particularly when it come to evaluating tender packages. Step 5 Project Delivery Output: The Business Solution When the project team has been selected the project can progress through developing initial design work to preparing drawings and documents to illustrate the project, achieving planning consent, defining standards to be met and allocating responsibilities. During this period the client (or project sponsor or project manager) should: ensure land purchase is completed on time, if necessary ensure the design process is consistent with the strategic brief ensure an internal decision-making system is in place to avoid design delays keep the wider client organisation informed set up an appropriate funding framework to ensure payments can be made (which often do not meet the usual trading conditions of the client s core business) The construction phase will progress under the management of the project manager or the project team. 4 Procurement: 15/3/04
5 Step 6: Post Project Review Output: Captured Learning A post-completion assessment by stakeholders involved at the outset will enable both the client and the project team to learn from the experience and assess whether the project objectives have been fully achieved. This is particularly useful if future projects are planned or where stakeholders have not been directly involved with the project during its development. buildings does not stop at the completion of the construction work but that there is a continuing and difficult to predict cost of ownership over the life of the building. Next Steps: A booklet for first time or occasional clients called Building Success: Lessons from Clients who got it Right is available from Constructing Excellence. See the website: or call the helpdesk on Information about other resources related to procurement is also available on the Constructing Excellence website. 5 Procurement: 15/3/04
How To Design A Project
Introduction to Procurement Why is procurement important? Client needs are unique and consequently each project meeting those needs has unique characteristics. This means that achieving the right project
Procurement Routes. Curtin University of Technology
Procurement Routes An Overview Curtin University of Technology Overview of Principal Routes Traditional / conventional design led Design and construct Management (Fee) Traditional Client appoints consultants
6.0 Procurement procedure 1 Infrastructure
Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement
CONCODE Guide to contract strategies for construction projects in the NHS STATUS IN WALES ARCHIVED
CONCODE Guide to contract strategies for construction projects in the NHS 1995 STATUS IN WALES ARCHIVED For queries on the status of this document contact [email protected] or telephone 029 2031 5512
2.6 Select a. procurement route. cabe. Contents
2.6 Select a procurement route 2.6.1 Procurement routes Procurement is the purchasing of products, work and services. It is more important than its unglamorous name suggests and plays a major part in any
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
The programming, design
Understanding Project Delivery for the Design and Construction of Public Buildings architecture The programming, design and construction of important public buildings require the coordinated efforts of
Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services
Specialist Cloud Services Lot 4 Cloud EDRM Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4 3.2 Service description...
Project manager services
Corporate Professional Local Project manager services For use with the RICS Standard form of consultant s appointment and RICS Short form of consultant s appointment The mark of property professionalism
A guide to appointing an architect
A guide to appointing an architect and to being a good client Hurditch Architecture, 24 Botallack, St Just, Penzance, Cornwall, TR19 7EP Page 1 of 7 RIBA Chartered Architects Architects act 1997 In the
PROJECT MANAGEMENT FRAMEWORK
PROJECT MANAGEMENT FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Executive Assistant to
Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services
Specialist Cloud Services Lot 4 Cloud Printing and Imaging Consultancy Services Page 1 1 Contents 1 Contents... 2 2 Transcend360 Introduction... 3 3 Service overview... 4 3.1 Service introduction... 4
The Transport Business Cases
Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business
Developing In-House Vs. Off the Shelf. - A white paper by Clydebuilt Business Solutions Ltd
Developing In-House Vs. Off the Shelf - A white paper by Clydebuilt Business Solutions Ltd Developing In House vs. Off the Shelf Naturally, as a software development company that operates solely within
Report Capital Works Procurement: The Selection of a Building Procurement Method
Report Capital Works Procurement: The Selection of a Building Procurement Method Research Project No: 2006-034-C-01 The research in this report has been carried out by Project Leader Researchers Project
2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY
APM Procurement Guide : Draft7_RevA_Chapter 2.1_Project Procurement Strategy_Jan12 1 2.1 STAGE 1 PROJECT PROCUREMENT STRATEGY In this stage, the project definition is developed so that decisions can be
Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel
Page 1 of 6 ALM Properties, Inc. Page printed from: New York Law Journal Back to Article Design-Bid-Build v. Guaranteed Maximum Price Contracting: The Basics for Owner's Counsel James E. Hughes New York
Risk Management in the Development of a Penta-P Project
Risk Management in the Development of a Penta-P Project Bill Van Meter Regional Transportation District Denver, CO Julie Skeen Jacobs Engineering Denver, CO Damian Carey Jacobs Engineering Denver, CO Don
PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS
PROJECT MANAGEMENT MANUAL PROJECT MANAGEMENT PROCESS for MAJOR CAPITAL PROJECTS FOR ESTATE MANAGEMENT November 2012 PMM REV1.4 CONTENTS INTRODUCTION PROJECT MANAGEMENT PROCESS FLOWCHARTS STAGE ZERO 0.0
Royal Institute of British Architects. Procurement policy. Building teams achieving value
Royal Institute of British Architects Procurement policy Building teams achieving value November 2001 RIBA Procurement Policy The RIBA is committed to construction procurement that: R provides the best
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT. Notice No... 2011
BOARD NOTICE COUNCIL FOR THE BUILT ENVIRONMENT Notice No.... 2011 NOTICE IN TERMS OF THE COUNCIL FOR THE BUILT ENVIRONMENT ACT, 2000 (ACT NO. 43 OF 2000) The Council for the Built Environment has under
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES
ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the
DIRECTORATE OF ESTATES & FACILITIES
DIRECTORATE OF ESTATES & FACILITIES PROCEDURE AND INFORMATION MANUAL EPM PM4 Client Representative (University Project Manager) for Capital Projects Scope of Services Document Originated: April 2006 By:
Capital Works Management Framework
POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset
NSW Government ICT Benefits Realisation and Project Management Guidance
NSW Government ICT Benefits Realisation and Project Management Guidance November 2014 CONTENTS 1. Introduction 1 2. Document purpose 1 3. Benefits realisation 1 4. Project management 4 5. Document control
CLIENT / PROJECT MANAGER AGREEMENT
Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT
Practice Note Deciding on the appropriate JCT contract
Practice Note Deciding on the appropriate JCT contract This Practice Note is intended to provide assistance in deciding the appropriate form of contract but it is not a substitute for professional advice.
Guide to Funding a Major Adaptation
Guide to Funding a Major Adaptation August 2010 Contents Contents... 1 Introduction... 1 Chapter 1: Policy and funding framework... 2 The importance of tenure... 2 The policy framework... 2 Overview of
Guidance on the template contract for social impact bonds and payment by results
Guidance on the template contract for social impact bonds and payment by results Introduction These guidance notes have been prepared to assist users of the Cabinet Office template contract. The guidance
Enhanced Portfolio Management in uncertain times
Enhanced Portfolio Management in uncertain times How businesses can generate and protect value through enhanced, risk return techniques improving portfolio and capital allocation decisions Contents Executive
Selling your home. Better homes and better services for better lives. Better homes and better services for better lives
Selling your home Selling your home You are able to sell your home whether you own a share or own the property outright. This process is known as assignment. It is important to write and tell us before
School Construction Projects
The process of educating young people seems to be continually developing. New insights regarding how students most effectively receive retain and gain understanding of information and principles affect
RIBA Plan of Work 2013: Consultation document. You are invited to complete the online questionnaire by 12 August 2012.
RIBA Plan of Work 2013: Consultation document The RIBA is undertaking a comprehensive review of the RIBA Plan of Work. This document sets out the reasons and the rationale behind that review as well as
Menu of Architecture Services 2009
Menu of Architecture Services 2009 We deliver architecture and interior design services in an accessible, easy to use format. We help you to select services that suit your project, budget and level of
To be used in conjunction with the Invitation to Tender for Consultancy template.
GUIDANCE NOTE Tendering for, choosing and managing a consultant Using this guidance This information is not intended to be prescriptive, but for guidance only. Appointing consultants for relatively small
The role will require the management of consultancy and in-house teams in the successful execution of the estates strategy.
Senior Project Manager Job Description Reference: 102014/51 Job Title: Senior Project Manager Purpose of Role: The University is committed to providing an environment conducive to high quality teaching
1.040 Project Management
MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Project Organization Project
Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000
Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE
A GOOD PRACTICE GUIDE FOR EMPLOYERS
MITIGATING SECURITY RISK IN THE NATIONAL INFRASTRUCTURE SUPPLY CHAIN A GOOD PRACTICE GUIDE FOR EMPLOYERS April 2015 Disclaimer: Reference to any specific commercial product, process or service by trade
THE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT
THE COMPLETE GUIDE TO PERFECT PROJECT MANAGEMENT 1 CONTENTS Introduction 3 Prince2 5 Every as a project tool 6 Major development and building work 7 Further reading and information..9 2 THE COMPLETE GUIDE
Check. They re Chartered. Chartered Project Managers
Check. They re Chartered. Chartered Project Managers The Society of Chartered Surveyors Ireland is the leading organisation of its kind in Ireland for professionals working in the property, land and construction
Contract Management. Brief 22. Public Procurement. September 2011
Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This
Note: This sectoral guidance is incomplete on its own. It must be read in conjunction with the main guidance set out in Part I of the Guidance.
13: Private Equity Overview of the sector Note: This sectoral guidance is incomplete on its own. It must be read in conjunction with the main guidance set out in Part I of the Guidance. 13.1 Private equity
The Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
Please send your responses via email, to: [email protected]. Respondent details. Mark Redhead. Head of Policy
REFORM OF THE PRIVATE FINANCE INITIATIVE RESPONSE Please send your responses via email, to: [email protected] The deadline for responses is Friday 10 February 2012. Respondent details Your
HOW TO RESPOND TO THE BASIC NEED CHALLENGE
HOW TO RESPOND TO THE BASIC NEED CHALLENGE The Situation: unprecedented demand Local Authorities have a statutory duty to provide school places for children of school age, but with recent unprecedented
Management and Leadership. Level 5 NVQ Diploma in Management and Leadership (QCF)
Management and Leadership Level 5 NVQ Diploma in Management and Leadership (QCF) 2014 Skills CFA Level 5 NVQ Diploma in Management and Leadership (QCF) Page 1 Level 5 NVQ Diploma in Management and Leadership
Your guide to the residential architectural process. A step-by-step guide from Context Architects
Your guide to the residential architectural process A step-by-step guide from Context Architects We know that building a new house or renovating your home can seem daunting and complicated. So we ve produced
Explaining an architect s services. General information on the usual tasks undertaken by an architect
Explaining an architect s services General information on the usual tasks undertaken by an architect June 2008 What an architect may do for you Introduction The root cause of disputes and complaints against
Construction Procurement Policy Project Implementation Process
Construction Procurement Policy Project Implementation Process Government of South Australia Copyright. January 2015 ISBN 978-0-7590-0217-3 The text in this document may be reproduced free-of-charge in
CODE OF PRACTICE. Safety Management. Occupational Safety and Health Branch Labour Department CODE OF PRACTICE ON SAFETY MANAGEMENT 1
CODE OF PRACTICE On Safety Management Occupational Safety and Health Branch Labour Department CODE OF PRACTICE ON SAFETY MANAGEMENT 1 This Code of Practice is prepared by the Occupational Safety and Health
DEVELOPMENT MANAGEMENT
DEVELOPMENT MANAGEMENT Sub Heading Sub Heading 2 march 2012 PRE APPLICATION ADVICE SERVICE FOR PLANNING APPLICATIONS Introduction CONTACT DETAILS Telephone 0191 433 3416 / 0191 433 3426 Fax 0191 477 8422
Network Rail Infrastructure Projects Joint Relationship Management Plan
Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf
PROGRAMME MANAGEMENT AND BUSINESS PLANNING
PROGRAMME MANAGEMENT AND BUSINESS PLANNING This paper describes what lessons were learned from the programme management and business planning which was done to support the operation of the Help Scheme
Construction Activity: Audit Strategies
Construction Activity: Audit Strategies Capital construction projects can create significant exposure for organizations that are unaware of the risks associated with excessive cost, project delays and
D-G4-L4-126 Police contact management and demand reduction review Deloitte LLP Service for G-Cloud IV
D-G4-L4-126 Police contact management and demand reduction review Deloitte LLP Service for G-Cloud IV September 2013 Contents 1 Service Overview 1 2 Detailed Service Description 2 3 Commercials 6 4 Our
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK
HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management
MANAGING DIGITAL CONTINUITY
MANAGING DIGITAL CONTINUITY Project Name Digital Continuity Project DRAFT FOR CONSULTATION Date: November 2009 Page 1 of 56 Contents Introduction... 4 What is this Guidance about?... 4 Who is this guidance
Shared service centres
Report by the Comptroller and Auditor General Cabinet Office Shared service centres HC 16 SESSION 2016-17 20 MAY 2016 4 Key facts Shared service centres Key facts 90m estimated savings made to date by
https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework
All interested parties Direct Dial: 020 7901 1849 Email: [email protected] Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance
Project Risk Analysis toolkit
Risk Analysis toolkit MMU has a corporate Risk Management framework that describes the standard for risk management within the university. However projects are different from business as usual activities,
13. Performance Management
13. Performance Management Summary Delivering schemes on time and on budget Management of Capital Programme Management of Risk Gateway Reviews Resource requirements Project Management and skills development
1.1 Objective 4. 1.2 Competencies and resources required 4. 1.3 Scope 4. 1.4 Related documents 5. 3.1 Defining the objectives and scope of projects 7
Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project evaluation 5 3.0 Project feasibility 7 3.1 Defining the objectives
Corporate Procurement Strategy 2014-2017
Strategy 2014-2017 Strategy 2014-2017 Introduction The Brighton & Hove community is distinctive for its strong international flavour and vibrant diversity of cultures. The make-up of the local population,
Appendix 3. BUSINESS PLAN December 2015 Rev C. Property and CLT Development. Phil Rose Strategic Land Advisor
Appendix 3 BUSINESS PLAN December 2015 Rev C Property and CLT Development Phil Rose Strategic Land Advisor Contents 1 EXECUTIVE SUMMARY... 5 2 INTRODUCTION... 6 2.1 Background and purpose... 6 2.2 Strategic
Project, Programme and Portfolio Management Delivery Plan 6
Report title Agenda item Project, Programme and Portfolio Management Delivery Plan 6 Meeting Performance Management and Community Safety Panel 27 April 2009 Date Report by Document number Head of Strategy
Evaluating Project Delivery Options
Evaluating Project Delivery Options Scot A. Bini Vice President, URS August 24, 2004 Design-Bid-Build Overview Design Build Construction Management at Risk Owner Representation Terminology Project Manager
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS
EFFECT OF PROCUREMENT SYSTEMS ON THE PERFORMANCE OF CONSTRUCTION PROJECTS Rosli Abdul Rashid, Ismail Mat Taib, Wan Basiron Wan Ahmad, Md. Asrul Nasid, Wan Nordiana Wan Ali & Zainab Mohd Zainordin Department
Programme Governance and Management Plan Version 2
PROCESS FOR CHANGE - Detailed Design Programme Governance and Management Plan Version 2 1 INTRODUCTION In October 2008, the Council approved the selection of seven opportunity themes to take forward from
Risk Management Plan template <TEMPLATE> RISK MANAGEMENT PLAN FOR THE <PROJECT-NAME> PROJECT
RISK MANAGEMENT PLAN FOR THE PROJECT Prepared by: Approved by: Reference: Version: Date: INTRODUCTION This document is the Risk Management
INTERNSHIP TRAINING SCHEME
EAST AFRICA INSTITUTE OF ARCHITECTS INTERNSHIP TRAINING SCHEME (Rules & Guidelines) As Adopted by Council January 26 th 2013 Arusha Tanzania Fee: UGX.2500 KES.85 TZS.1,600 RWF. 650 Table of Contents. Section
New South Wales Government. Procurement Methodology Guidelines for Construction
New South Wales Government Procurement Methodology Guidelines for Construction Version 1 - February 2005 Establishes common terminology used to describe various options and provides guidance for the selection
Project Assessment Framework Establish service capability
Project Assessment Framework Establish service capability July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below.
Delivering progress towards meeting HMG targets on the SME growth agenda
Delivering progress towards meeting HMG targets on the SME growth agenda Action Plan Version 1.1 dated 16 th August 2013 Author: Robert Astall, Head of Commercial Profession and Capability Background The
Stage. service. Procure a solution. management. communication
Stage 4 communication management service Procure a solution Confi rm a procurement approach and select suppliers that offer best overall value for money (including risk and reward trade-offs). Key better
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3)
PORTFOLIO, PROGRAMME & PROJECT MANAGEMENT MATURITY MODEL (P3M3) 1st February 2006 Version 1.0 1 P3M3 Version 1.0 The OGC logo is a Registered Trade Mark of the Office of Government Commerce This is a Value
1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution
Reducing Bid Costs for Outcome-Based Procurements in NSW Infrastructure and Structured Finance Unit: Partnering to Create Partnerships December 2015 1. Evolution of infrastructure procurement in NSW 2.
Project Management Manual
Project Management Manual PM01 Introduction to the Project Management Manual Ref: PM01 (V7.01) - Uncontrolled once Printed Issued on 20 th December 2006 Manual Owner: James Couper Head of Project Management
A Guide to... Home Renovation Incentive (HRI)
A Guide to... Home Renovation Incentive (HRI) About this guide This guide will tell you what you need to know if you are organising to have construction work done on your house and would like to avail
CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014
CITY OF LONDON LAW SOCIETY, LAND LAW COMMITTEE S INSURANCE PROVISIONS FOR A RACK RENT LEASE OF COMMERCIAL PROPERTY MARCH 2014 Schedule 1 Insurance provisions 1 1 INSURED RISKS AND OTHER DEFINITIONS 1.1
INTEGRATING RECORDS MANAGEMENT
INTERNATIONAL RECORDS MANAGEMENT TRUST INTEGRATING RECORDS MANAGEMENT IN ICT SYSTEMS Good Practice Indicators CONTENTS Figure 1: Designing a Records Management Improvement Programme iv Figure 2: Integrating
Item: 16 Page: 5. 1. Purpose
Item: 16 Page: 5 1. Purpose 1.1 Improving Choice in Verification of Building Standards. A Scottish Government consultation on the introduction of the National House Building Council (NHBC) for the verification
An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan
An Introduction to the PRINCE2 project methodology by Ruth Court from FTC Kaplan Of interest to students of Paper P5 Integrated Management. Increasingly, there seems to be a greater recognition of the
Corporate Risk Management Policy
Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction
COMPANY QUALITY MANUAL
COMPANY QUALITY MANUAL QM/BI/001(03) THE APPROACH TO QUALITY This manual and information within is the property of The Benbow Group Limited. The information contained herein may not be disclosed in whole
How To Write A Contract
Commercial Management the NEC Way Hong Kong Institute of Surveyors [email protected] [email protected], July 2014 Turner & Townsend plc July 14 making the difference Health, safety & wellbeing