Decommissioning of CANDU Nuclear Power Stations. by G.N. Unsworth
|
|
|
- Noel Banks
- 10 years ago
- Views:
Transcription
1 Decommissioning of CANDU Nuclear Power Stations by G.N. Unsworth
2 This publication It a revised edition of a report previously published as Chapter S of AECL-S800.
3 Decommissioning of CANDU Nuclear Power Stations by G.N. Unsworth Mr. Unsworth is Head, Maintenance and Construction Branch, Whiteshell Nuclear Research Establishment at Pinawa, Manitoba. He is an electrical engineer with 20 years' experience in reactor operations. April 1979 AECL
4 This report summarizes the results of a detailed study of the various procedures and costs associated with decommissioning a CANDU reactor. The three internationally recognized "stages" of decommissioning (mothballing, encasement, and dismantling) are discussed. It is concluded that decommissioning is possible with presently available technology, and tha costs could be financed by only a marginal increase in the cost of electricity during the life of the reactor. The environmental impact would be no greater than that of any large construction project. Ce rapport resume les resultats d'une etude detaillee des diverses methodes et des couts associes a la mise hors service d'un reacteur CANDU. Les trois etapes de mise hors service (la mise en reserve, le scellement et le demontage) reconnues internationalement sont examinees. Cette etude conclut que la mise hors service peut etre realisee dans le cadre de la technologie actuelle et que les frais encourus peuvent etre finances facilement par un accroissement marginal du cout de I'electricite durant la vie utile du reacteur. L'incidence de I'impact sur I'environnement ne serait pas plus levee que cede provenant de tout grand projet de construction.
5 INTRODUCTION Operating The term "decommissioning" means shutting down and placing a plant permanently out of service. The operation must be capable of being performed safely and in such a manner as to impose no responsibility on future generations. The decommissioning of nuclear reactors will involve the expenditure of material and manpower and will require careful planning. This summary is based on a study* 11 of decommissioning a single 600 MW(e) CANDU* reactor station (Figure 1). The "design" life of a reactor is normally considered to be 30 years and usually this is chosen as the capital repayment period. There is little likelihood that a utility will choose to decommission a reactor before the end of its design life and, indeed, there will be considerable economic incentive to operate it beyond the design life. Therefore, barring major incidents involving damage to the reactor, it is reasonable to assume that a utility will not consider decommissioning a facility until at least 30 years after start-up and, more likely, will not be involved in decommissioning until more than 40 years after start-up. There are many possible ways to decommission a reactor. They range from simply shutting down the Figure 1 Simplified Vitw of a 600 MW(t) Reactor Building italnment building Calandrla (containing heavy watar moderator ' CANidt Deutarlum Uranium Figure 2 Stage* of Decommissioning a Nuclear Power Station
6 reactor, to completely dismantling the reactor and releasing the site for other uses. It has been agreed internationally 12 ' that, when referring to nuclear power facilities, three "stages" for decommissioning may be defined. In the order of least complexity to greatest complexity, these are: Mothballing, Encasement, and Dismantling and Removal. Figure 2 shows a schematic representation of the different stages. ACTIVITIES PRIOR TO DECOMMISSIONING A number of factors must be considered prior to decommissioning a reactor and they may affect the option selected. The total inventory of radioactive substances on the site must be determined. This allows an assessment of: the man-rem * exposure expected for any operation, the merits of delaying completion of decommissioning to permit the radioactivity to decay, the weight, volume sr>d specific activity of the material to be shipped to and buried in a waste repository, the weight, volume and specific activity of equipment which will be left on site. Removal of the fuel, heavy water and radioactive waste material will reduce the long-lived radioactive inventory by approximately 98.5 per cent. The remaining "fixed" radioactivity will be due to activation of pressure tube, calandria and shielding materials. Negligible amounts of fission products and actinides will be present. After two to three years, the primary source of gamma activity is cobalt-60. After 20 years, the rate of decay of total activity will be governed by the half-life of nickel-63 and there will be approximately 10 6 curies of activity. After 25 years, most of the material will meet IAEA transport regulations for Low Specific Activity material' 3 '. The major proportion of the activity is associated with the calandria shell, end shields and associated equipment. Decontamination will be required if the gamma fields associated with the out-of-core portions of the primary heat transport system are high or if the system is contaminated with fission products and actinides as a result of fuel defects during the life of the reactor. Decontamination costs can be high, and some of the outof-core portions of the primary heat transport system may be seriously contaminated. Therefore, consideration should be given to allowing the activity to decay (and paying for surveillance costs during the decay period) rather than carrying out decontamination. However, on the assumption that decontamination is to be done, aggressive reagents should be used to ensure 2 that a high decontamination factor is obtained. This is * A measure of human radiation exposure; it Is the total dose In rem received by the Individuals In a given population. possible since corrosion of the components by these reagents need no longer be a major concern. In the case of a 600 MW(e) CANDU reactor the cost of a full decontamination would be approximately $ *. It is assumed that decontamination will reduce the radioactive fields to a level that will not require any significant man-rem expenditures. Removal of the fuel, heavy water and radwaste will eliminate the capability of operating the reactor and greatly reduce the probability of release of any radioactive material. Therefore, an application to the regulatory authorities for a change in operating licence would be justified so that manpower and surveillance requirements can be reduced. The availability of facilities for the storage of radioactive waste material and the cost of transportation to the storage site will also affect decisions regarding decommissioning. Decommissioning wastes which contain long-lived radioactivity would be placed in a deep underground waste repository when it is available 14 *. Some points that must be considered when developing the specifications for a repository for waste from the decommissioned station and for transporting the waste to it are: (a) The decontamination procedures associated with decommissioning will be effective in removing long-lived fission products or actinides. Therefore, the material to be stored will be solids of relatively low specific activity. Most of the gamma activity will have short half-lives and will decay fast enough to eliminate the necessity of constructing gamma shielding of high integrity and resistance to aging. The only major concern is to provide facilities that ensure the stored solid components will not corrode or dissolve at a rapid rate. (b) The fuel will be stored, as described elsewhere* 4 ), and it is expected that the amount of actinides and fission products in the decommissioning wastes will be reduced to negligible values by decontamination. Therefore, the only material containing significant amounts of these radioactive substances will be those that can easily be separated and will have relatively small volumes, e.g., ion exchange resins, decontamination products, etc. (c) Consideration should be given to retrievable storage. It would seem desirable to store some of the decommissioning wastes in such a fashion that they could be retrieved and re-used after the radioactivity has decayed. There are advantages to this approach since it means the disposal facility does not need to accommodate them and a future scrap value can be attached to some of the waste. (d) The hazards and risks involved in transporting the decommissioned material will be low and easy to manage, since the specific activity levels are low ' All cost estimates are In 1975 dollars.
7 and the material will be made up primarily of large solid pieces. It can be assumed that the regulations published by the IAEA will apply. Time and cost estimates are required to determine what activities are significant cost items and to obtain an appreciation of what effect the cost of decommissioning might have on a utility's financing. The reactor designer will want to know in which areas the significant cost items lie so that he can investigate whether changes can be made to the original design to reduce decommissioning costs. The owner of a nuclear power plant may use the cost estimates to help decide whether it is more economical to repair a major breakdown or to decommission the reactor. If sinking fund financing is used to defray the eventual costs, only minor changes in cost per kilowatt hour of electricity would be required to cope with large differences in decommissioning costs (Table 1). Actual decommissioning costs are discussed in the next section. Table 1 Assumptions: Discount rate Inflation rate Increments in power cost required to develop a sinking fund of $ after "N" years "N" (years) True discount rate DECOMMISSIONING = 12% per annum = 8% per annum ' 1.08 Increment In Cott (mills per kilowatt hour) = 3.7% per annum Mothballlng For "mothballing", the primary containment (piping and equipment associated with the primary cooling circuits) is maintained intact. All systems containing liquids that are radioactive are drained and sealed to prevent escape of contaminated material. The secondary containment (building) is maintained in a condition such that the probability of a release of radioactive material to the atmosphere is no greater than during reactor operation. The atmosphere inside the containment building is controlled to prevent the spread of contamination, and access to the inside of the containment building is controlled. The entire facility is maintained under surveillance, and equipment for monitoring radioactivity both inside and outside the containment building is kept in working order. Inspections are carried out to ensure that both the primary and secondary containment systems are being maintained in an acceptable condition Ṫhe specific actions involved in mothballing are: 1. Remove fuel from reactor and ship all irradiated fuel from used fuel bays off-site. 2. Remove all heavy water and ship it off-site. 3. Decontaminate systems as required. 4. Process and ship to an active disposal area all active waste such as ion-exchange resin, filters, and decontamination solutions. 5. Perform a detailed radiation survey and calculate the total amount of activity on the site. 6. Apply for a change in licence which will specify a reduced minimum staff requirement based on the fact that the potential hazards and risks have been reduced. The surveillance and monitoring requirements will consist of gathering data and submitting reports for quarterly inspection and semi-annual environmental surveys. In addition, effort will be required to maintain and operate the necessary systems. It is expected that the total cost required for activities necessary to mothball a 600 MW(e) CANDU reactor will be approximately $ and these activities will occupy one year. The annual expenses to maintain and operate the mothballed facility would be approximately $ The cost of mothballing will not be affected greatly by changes in reactor size. When mothballing is complete, the predominant amounts and types of radioactivity remaining will be: 8 x 10* curies of iron-55 3 x 10 6 curies of cobalt-60 7x10= curies of nickel-63 1 x 10 5 curies of zirconium-95 After 25 years, the predominant activities will be: 6 x 10 5 curies of nickel-63 1 x 10 s curies of cobalt-60 7x 10 3 curies of iron-55 Encasement For encasement, all easily removable parts are dismantled and removed, as are all components that are radioactive to the extent that they will remain a health hazard longer than the life of the proposed encasement structure (<100 years). All radioactive components remaining inside the biological shield are sealed and the building is modified as necessary to provide adequate shielding and containment. The containment building itself and the ventilation system can then be modified or removed since they are no longer required as part of the safety system. If the containment building is left standing, access to it would normally be permitted without any monitoring of personnel for radiation exposure. Surveillance will be required but at a reduced level from that of mothballing since the only concern is to detect possible escape of
8 radioactivity from within the encasement due to deterioration of the encased structure with age. With an encasement life of less than 100 years, the vessel and all its internal components, including the steel shot from the shield tank (used to provide shielding around the reactor), must be removed from the site. In addition to the steps involved in mothballing, the following activities are required: 1. Disconnect, cut, and/or remove as much of the process piping and equipment as can be handled using the existing access to the building. 2. Build a water-filled "work bay" in the moderator room to permit handling and loading of active sections removed from the core. 3. Remove pressure tubes and ship off-site. 4. Remove and ship off-site all adjuster rods, ion chambers, flux detectors and other in-reactor equipment that was essentially designed for removal and for which removal facilities and flasks are available as routine maintenance equipment. 5. Install a water-tight cover-plate over the outer face of each end shield. Cut out calandria shell, calandria tubes, and end shield inner tube sheet. Remove the steel shot and drain the shield cavity or shield tank. The total estimated cost for encasing a 600 MW(e) CANDU reactor is $ over a four-year period. The annual monitoring and surveillance costs are estimated to be $ It will cost approximately 30 per cent more to encase a station which is double the size of the reference station, and 20 per cent less for a station which is half the size of the reference station. There will be very little activity left after the encasement work is complete. A very conservative (high) estimate would be 20 curies of cobalt-60 in the vault liner and one curie of iron-55 in the concrete. There will be less than 100 millicuries of nickel-63. The amount of radioactivity that will be sent to burial will be approximately 10 s curies each of nickel- 63, iron-55 and cobalt-60. Dismantling and Removal This is the most complete method of decommissioning. Following the steps outlined for mothballing and encasement, the boilers are removed and the remainder of the active material is dismantled and shipped off-site, including the active concrete from the biological shield. The remaining equipment and structures are dismantled and the material shipped to a local inactive burial site. Finally, the reactor site is backfilled and graded, and released without restriction for other uses. After removal is completed, no further surveillance, inspection or tests will be required. The total estimated cost for dismantling and removal of a 600 MW(e) CANDU power station is $ over a six-year period. It is estimated that the dismantling costs for a plant double the size and half the size of the 600 MW(e) station will be 45 per cent greater and 25 per cent less, respectively, than the costs for dismantling the reference station. Dismantling, although the most expensive method, has the advantage over the others that the site becomes reusable and therefore the value of the site is a credit against the cost. MANREM EXPOSURES There should be no need to experience higher exposures or have a higher man-rem expenditure as a result of decommissioning of a nuclear power plant than would be encountered during normal operation and maintenance of the plant. Estimated exposures for each stage of decommissioning are shown in Table 2. Exposure by ingestion or inhalation of radioactive dust and gases should be negligible. Table. 2 Stag* Dismantling Encasement Mothballing Man-ram Exposures Decommissioning Total exposure (maimem) plus 0.1/yaar of surveillance 250 plus 0.5/ye«rof surveillance ENVIRONMENTAL IMPACT Involved in Avenge exposure, per inaiif per year (run) plus 0.05 during period of surveillance 1.0 plus 0.1 during period of surveillance None of the decommissioning stages will have other than minimal effect on the local environment and, in fact, the only effect that would not normally be encountered with any large construction project would be that due to disposal of the radioactive inventory. All shipments of radioactive material will be in approved shipping containers and made in such a way as to meet all relevant requirements. These shipments will not create any undue hazard to the public or result in exposure of the public to levels of radiation above those permitted by the AECB. None of the decommissioning activities should result in the release of any significant amount of active gases or dust to the atmosphere or otherwise externally from the containment. In respect to disposal requirements, the estimated volumes of the various types of material resulting from each decommissioning method are low. For dismantling, which involves the highest volume, the specific requirements are:
9 1. The highly active material will be encased in concrete or lead liners and will occupy approximately 250 m The remaining active material will occupy a volume roughly estimated at 7000 m The components of systems that are not contaminated will, wherever possible, be sold as scrap but the remaining material to be disposed of will occupy a volume of approximately m 3. For encasement, the highly active material will be the same as for dismantling and the volume will therefore be 250 m 3. For mothballing, there are no disposal requirements. study for the heavy water remaining when the station is decommissioned. The value of this material is comparable to the dismantling costs. Assuming that satisfactory provisions are made for disposal of the fuel, heavy water and radioactive waste, and that suitable sites can be found for disposal of active components, the environmental impact of decommissioning a reactor will be no greater than that of any large construction project. SUMMARY AND CONCLUSIONS Table 3 summarizes the more significant data for each decommissioning stage considered. The following conclusions may also be drawn: 1. Decommissioning to any of the three stages is possible and can be done without development of new technologies or equipment. 2. The cost of decommissioning a nuclear power plant should not be a major concern to a utility; it could be covered by sinking fund financing, which would increase the mill-rate by less than 0.2 mills per kilowatt hour for the most expensive process (dismantling and removal). No financial credit is given in this Tabto 3 Summary of finding* of this study 1. Time required 10 and removal ayeari 4 yeere 1 y&ar 2 Radiation expoeure to personnel during WO Man-ram WO Man-ram 400 Man-ram MO Man-rani decommiaaloninfl.;.. 3. Amount of radioactivity on ene at and of Negligible Negligible 20curlei lixio^curlei decommieatonlng period 4. Amount of radioactivity In dlapoaal at and of decommmlodtng period (does not (Delude fuel, heavy water or radioactlvewaett) 4.2x10 e eufle» 6.3x10* curie* 0 5. Dlepoeal valuma required 72S0m 3 of active 250 m 3 of active 0 (doe* not Mduda fuel, volume volume heavy water or radioactive waata) bytruokofmlnw H 000 m 3 of inactive volume (Ma lafm torap metal) Meooet 1* M0 000 phie M0 ON 0#f WHNM1 ' lermveera ' M eluenoom
10 REFERENCES (1) G.N. Unsworth, Decommissioning of the CANDU- PHW Reactor, Atomic Energy of Canada Limited, Report AECL-5687 (April 1977). (2) Decommissioning of Nuclear Facilities, Report of a Technical Committee Meeting, International Atomic Energy Agency, Report IAEA-179, Vienna (October 20-24, 1975). (3) Regulations for the Safe Transport of Radioactive Materials (Revised Edition), Safety Series No.6, International Atomic Energy Agency, Vienna (1973). (4) R.G. Hart, Management of Nuclear Waste, Atomic Energy of Canada Limited, Report AECL-6333.
11 Copies of this publication are available from: Atomic Energy of Canada Limitad Public Affair* OfNca Shtridan Park Raaaarch Community MiMitsauga, Ontario L5K1B2
12 Atomic Energy L'Energie Atomique of Canada Limited du Canada, Limitee AECL-6332 April 1979 La prgsente publication est egalement disponible en frangais
THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM
THE DECOMMISSIONING OF COMMERCIAL MAGNOX GAS XA9848063 COOLED REACTOR POWER STATIONS IN THE UNITED KINGDOM G. HOLT Magnox Electric pic, Berkeley Centre, Berkeley, Gloucestershire, United Kingdom Abstract
10 Nuclear Power Reactors Figure 10.1
10 Nuclear Power Reactors Figure 10.1 89 10.1 What is a Nuclear Power Station? The purpose of a power station is to generate electricity safely reliably and economically. Figure 10.1 is the schematic of
International Action Plan On The Decommissioning of Nuclear Facilities
International Action Plan On The Decommissioning of Nuclear Facilities A. Introduction Decommissioning is defined by the International Atomic Energy Agency (the Agency) as the administrative and technical
Chemical Decontamination and Fluid Handling Services
Chemical Decontamination and Fluid Handling Services Westinghouse is a global industry expert in decontamination and fluid handling processes, with proven abilities in decontamination and remediation work.
Office for Nuclear Regulation
ONR GUIDE CONTAINMENT: CHEMICAL PLANTS Document Type: Nuclear Safety Technical Assessment Guide Unique Document ID and Revision No: NS-TAST-GD-021 Revision 2 Date Issued: March 2013 Review Date: March
HOW DOES A NUCLEAR POWER PLANT WORK?
HOW DOES A NUCLEAR POWER PLANT WORK? O n t a r i o P o w e r G e n e r a t i o n P U T T I N G O U R E N E R G Y T O U S G O O D E O N T A R I O P O W E R G E N E R A T I O N What a Nuclear Reactor Does
RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay
RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader
Government Degree on the Safety of Nuclear Power Plants 717/2013
Translation from Finnish. Legally binding only in Finnish and Swedish. Ministry of Employment and the Economy, Finland Government Degree on the Safety of Nuclear Power Plants 717/2013 Chapter 1 Scope and
RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES AUSTRALIA NATIONAL NUCLEAR ENERGY CONTEXT
RADIOACTIVE WASTE MANAGEMENT PROGRAMMES IN OECD/NEA MEMBER COUNTRIES AUSTRALIA NATIONAL NUCLEAR ENERGY CONTEXT Australia is one of the only developed countries that does not use electricity, either indigenous
Lessons learned from the radiological accident in Mayapuri, New Delhi, India
Lessons learned from the radiological accident in Mayapuri, New Delhi, India Rajoo Kumar Atomic Energy Regulatory Board Government of India Mumbai, India www.aerb.gov.in 1 Contents About Mayapuri, New
APPENDIX CC NUCLEAR WASTE STORAGE
APPENDIX CC NUCLEAR WASTE STORAGE APPENDIX CC NUCLEAR WASTE STORAGE MICHIEL P.H. BRONGERS 1 SUMMARY Nuclear wastes are generated from spent nuclear fuel, dismantled weapons, and products such as radio
SECTION TWO PACKAGING, TRANSPORTATION AND STORAGE OF RADIOACTIVE MATERIALS
SECTION TWO PACKAGING, TRANSPORTATION AND STORAGE OF RADIOACTIVE MATERIALS LEARNING OBJECTIVES By the end of this section, participants will be able to: Identify three types of packaging for radioactive
NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission
NRC s Program for Remediating Polluted Sites J.T. Greeves, D.A. Orlando, J.T. Buckley, G.N. Gnugnoli, R.L. Johnson US Nuclear Regulatory Commission Background The U.S. Nuclear Regulatory Commission (NRC)
Hazard Classification of the Remote Handled Low Level Waste Disposal Facility
1 Hazard Classification of the Remote Handled Low Level Waste Disposal Facility Abstract Boyd D. Christensen Battelle Energy Alliance, Idaho National Laboratory P.O. Box 1625 Idaho Falls, Idaho 83415 208
RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND
RADIOACTIVE WASTE MANAGEMENT AND DECOMMISSIONING IN FINLAND 1. NATIONAL FRAMEWORK FOR MANAGEMENT AND REGULATION OF RADIOACTIVE WASTE AND DECOMMISSIONING 1.1 National framework 1.1.1 Overview of national
RADIOACTIVE WASTE MANAGEMENT PLAN
RADIOACTIVE WASTE MANAGEMENT PLAN Copies of this plan will be made available to all members of the campus community with the potential to generate radioactive waste. Contents I. Purpose II. Regulatory
Replacement of steam generators at Ringhals nuclear power plant.
Decommissioning of nuclear power plants Replacement of steam generators at Ringhals nuclear power plant. Photo: Börje Försäter/Hallands Bild Repairs provide experience Swedish experience of complete dismantlement
Radioactive Waste Management at Paks NPP
1 Radioactive Waste Management at Paks NPP Content Introduction WAC in Hungary Waste classification and characterization Data collection Transport and Final disposal 2 Facilities and Activities in Hungary
IBC 2100. Nuclear Energy Liability Exclusion. Explained
IBC 2100 Nuclear Energy Liability Exclusion Explained By Colleen DeMerchant Assistant Manager Nuclear Insurance Association of Canada June 22, 2005 Nuclear Energy Liability Exclusion (IBC 2100 CGL form)
Spent Fuel Project Office Interim Staff Guidance - 17 Interim Storage of Greater Than Class C Waste
Spent Fuel Project Office Interim Staff Guidance - 17 Interim Storage of Greater Than Class C Waste Issue: Guidance is necessary on the interim storage of greater than Class C (GTCC) waste due to the revision
Categorisation of Active Material from PPCS Model Power Plants
SESE-IV Categorisation of Active Material from PPCS Model Power Plants Robin Forrest, Neill Taylor and Raul Pampin Euratom/UKAEA Fusion Association Culham Science Centre This work was funded jointly by
Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]
Nuclear Safety Council Instruction number IS-22, of July 1st 2009, on safety requirements for the management of ageing and long-term operation of nuclear power plants Published in the Official State Gazette
Radioactive Waste Storage Facility and Tank System Design Criteria Standards
UCRL-AR-133355 Rev 1 Radioactive Waste Storage Facility and Tank System Design Criteria Standards John Wood Rich Michalik Karen Doiron May 1999 DISCLAIMER This document was prepared as an account of work
Decommissioning situation of Nuclear Power Plant in Japan
Decommissioning situation of Nuclear Power Plant in Japan April, 2015 The Japan Atomic Power Co. The Kansai Electric Power Co., Inc. General Description 1 Operational years of commercial NPP in Japan 40
Trip Parameter Acceptance Criteria for the Safety Analysis of CANDU Nuclear Power Plants
REGULATORY GUIDE Trip Parameter Acceptance Criteria for the Safety Analysis of CANDU Nuclear Power Plants G 144 May 2006 TYPES OF REGULATORY DOCUMENTS Regulatory documents support the Canadian Nuclear
INFO-0545 RADIOISOTOPE SAFETY MONITORING FOR RADIOACTIVE CONTAMINATION
INFO-0545 RADIOISOTOPE SAFETY MONITORING FOR RADIOACTIVE CONTAMINATION 1. INTRODUCTION This document provides general guidance for monitoring and controlling radioactive contamination, and relating the
Maine Yankee INDEPENDENT SPENT FUEL INSTALLATION (ISFSI) OFF-SITE DOSE CALCULATION MANUAL CHANGE NO. 32. Approved: Approval Date: 0"/06
Maine Yankee INDEPENDENT SPENT FUEL INSTALLATION (ISFSI) OFF-SITE DOSE CALCULATION MANUAL CHANGE NO. 32 Approved: Approval Date: 0"/06 ABSTRACT The Maine Yankee Nuclear Power Station Off-Site Dose Calculation
Fact Sheet on U.S. Nuclear Powered Warship (NPW) Safety
Fact Sheet on U.S. Nuclear Powered Warship (NPW) Safety 1. Commitments of the U.S. Government about the Safety of U.S. NPWs U.S. Nuclear Powered Warships (NPWs) have safely operated for more than 50 years
Developing a Safety Case for Ontario Power Generation s L&ILW Deep Geologic Repository
Developing a Safety Case for Ontario Power Generation s L&ILW Deep Geologic Repository T. Kempe, P. Gierszewski, R. Heystee, M. Jensen and H. Leung Ontario Power Generation, Canada NEA/EC/IAEA Symposium
Treatment Centers for Radioactive Waste
Treatment Centers for Radioactive Waste TREATMENT CENTERS FOR RADIOACTIVE WASTE Introduction Nuclear facilities such as nuclear power plants, reprocessing plants, nuclear fuel cycle production units, laboratories
Nuclear power plant systems, structures and components and their safety classification. 1 General 3. 2 Safety classes 3. 3 Classification criteria 3
GUIDE 26 June 2000 YVL 2.1 Nuclear power plant systems, structures and components and their safety classification 1 General 3 2 Safety classes 3 3 Classification criteria 3 4 Assigning systems to safety
Safety Analysis for Nuclear Power Plants
Regulatory Document Safety Analysis for Nuclear Power Plants February 2008 CNSC REGULATORY DOCUMENTS The Canadian Nuclear Safety Commission (CNSC) develops regulatory documents under the authority of paragraphs
Waste Volume Reduction by Studsvik Nuclear AB. Anders Stenmark and Bo Wirendal September 16th, 2010
Waste Volume Reduction by Studsvik Nuclear AB Anders Stenmark and Bo Wirendal September 16th, 2010 Waste Streams from Industry The Nuclear Industry generates operational waste during its lifetime as well
How To Decommission A Nuclear Plant
International Atomic Energy Agency Decommissioning of Nuclear Facilities Management of Decommissioning Projects Lawrence E. Boing Manila, Philippines, October 2006 1 Lesson Objectives Understand the management
Outlook for RWE s nuclear operations. Prof. Dr. Gerd Jäger London, 16 January 2012
Outlook for RWE s nuclear operations Prof. Dr. Gerd Jäger London, 16 January 2012 Overview of German nuclear power plants Power plant Net capacity MW Commercial commissioning Shutdown German nuclear power
IAEA INTERNATIONAL FACT FINDING EXPERT MISSION OF THE NUCLEAR ACCIDENT FOLLOWING THE GREAT EAST JAPAN EARTHQUAKE AND TSUNAMI
IAEA INTERNATIONAL FACT FINDING EXPERT MISSION OF THE NUCLEAR ACCIDENT FOLLOWING THE GREAT EAST JAPAN EARTHQUAKE AND TSUNAMI Tokyo, Fukushima Dai-ichi NPP, Fukushima Dai-ni NPP and Tokai NPP, Japan 24
Naturally Occurring Radioactive Material (NORM)
Guide Naturally Occurring Radioactive Material (NORM) 2000-0036 The Canadian Association of Petroleum Producers (CAPP) represents 150 companies that explore for, develop and produce natural gas, natural
Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2
Operating Performance: Accident Management: Severe Accident Management Programs for Nuclear Reactors REGDOC-2.3.2 September 2013 Accident Management: Severe Accident Regulatory Document REGDOC-2.3.2 Canadian
Importing and Exporting Radioactive Materials and Waste for Treatment, Processing and Recycling
Importing and Exporting Radioactive Materials and Waste for Treatment, Processing and Recycling J.T. Greeves, J. Lieberman Talisman International, LLC 1000 Potomac Street, NW, Suite 300 Washington, DC
How To Clean Up A Reactor Water Cleanup
General Electric Systems Technology Manual Chapter 2.8 Reactor Water Cleanup System TABLE OF CONTENTS 2.8 REACTOR CLEANUP SYSTEM... 1 2.8.1 Introduction... 2 2.8.2 System Description... 2 2.8.3 Component
Radiation Protection s Benefits in the Production of Iodine-131
Radiation Protection s Benefits in the Production of Iodine-131 Daniel M. Cestau *, Ariel N. Novello, Cecilia Bravo, Pablo Cristini, Marcelo Bronca, Eduardo Carranza, Ricardo Bavaro, Julián Cestau and
MATERIALS LICENSE. In accordance with the letter dated January 15, 2009,
NRC FORM 374 U.S. NUCLEAR REGULATORY COMMISSION PAGE 1 OF 5 PAGES Pursuant to the Atomic Energy Act of 1954, as amended, the Energy Reorganization Act of 1974 (Public Law 93-438), and Title 10, Code of
11. Radioactive Waste Management AP1000 Design Control Document
11.4 Solid Waste Management The solid waste management system (WSS) is designed to collect and accumulate spent ion exchange resins and deep bed filtration media, spent filter cartridges, dry active wastes,
Regulatory Compliance Statement
Regulatory Compliance Statement 0560 EU Declaration of Conformity The declaration of conformity may be consulted at www.kobo.com/userguides SAR Limits The exposure standard for wireless devices employs
NUCLEAR POWER PLANT SYSTEMS and OPERATION
Revision 4 July 2005 NUCLEAR POWER PLANT SYSTEMS and OPERATION Reference Text Professor and Dean School of Energy Systems and Nuclear Science University of Ontario Institute of Technology Oshawa, Ontario
Underground Storage Tanks
Underground Storage Tanks An Informational and Guidance Document for the University Community. Please contact Yale Environmental Health and Safety for latest Regulatory Requirements. A typical UST installation
WASTE Application Form - Dublin Waste to Energy SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE
SECTION J ACCIDENT PREVENTION & EMERGENCY RESPONSE Describe the existing or proposed measures, including emergency procedures, to minimise the impact on the environment of an accidental emission or spillage.
DEMONSTRATION ACCELERATOR DRIVEN COMPLEX FOR EFFECTIVE INCINERATION OF 99 Tc AND 129 I
DEMONSTRATION ACCELERATOR DRIVEN COMPLEX FOR EFFECTIVE INCINERATION OF 99 Tc AND 129 I A.S. Gerasimov, G.V. Kiselev, L.A. Myrtsymova State Scientific Centre of the Russian Federation Institute of Theoretical
Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management
Provisional Translation Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management National Report of Japan for the Second Review Meeting October 2005 Government
Nuclear Energy of Ukraine - History
Nuclear Energy of Ukraine - History 1950-s Uranium Industry was started 1962 Ministry of Energy and Electrification of Ukraine was established(ukraine a Republic of Soviet Union) 1965 Unique Energy System
Guide to nuclear decommissioning
Guide to nuclear decommissioning Contents: What is decommissioning? Stages of decommissioning Site restoration Waste management The UK decommissioning industry The international picture What is decommissioning?
INTRODUCTION. Three Mile Island Unit 2
INTRODUCTION here was an accident at Three Mile Island Unit 2 on March 28,1979. It caused extensive damage to the plant's nuclear fuel core. Most of the plant's major systems were relatively undamaged.
5. State the function of pulveriser. The pulverisers are the equipments which are used to powdered coal.
413 POWER PLANT ENGINEERING PART-A 1. Define Power. Power is the rate at which energy is used (or) Energy/time. 2. What are the types of fuels? Solid fuel Liquid fuel Gaseous fuel (Any one among the above
DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT
DEVELOPMENT OF PROCESS TEMPLATES AS A PROJECT MANAGEMENT TOOL FOR THE PLUTONIUM FINISHING PLANT ABSTRACT William G. Jasen, Project Enhancement Corporation Thomas W. Halverson, Fluor Hanford, Inc. Steven
Liquid Effluent Treatment Plant (LETP) Land Clean-Up
Liquid Effluent Treatment Plant (LETP) Land Clean-Up Frequently Asked Questions What is proposed? Magnox Ltd is proposing to remove the redundant Liquid Effluent Treatment Plant (LETP) at Harwell and to
Activities of Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) Yasuharu Igarashi
Nuclear Damage Compensation and Decommissioning Facilitation Corporation Activities of Nuclear Damage Compensation & Decommissioning Facilitation Corporation (NDF) June 3, 2015 Yasuharu Igarashi Executive
SILICON VALLEY CLEAN WATER. May 2015
SILICON VALLEY CLEAN WATER May 2015 Slug Discharge Control and Spill Containment Guidelines This document was revised and used with the permission of the Los Angeles County Sanitation District, Industrial
V K Raina. Reactor Group, BARC
Critical facility for AHWR and PHWRs V K Raina Reactor Group, BARC India has large reserves of Thorium Critical facility Utilisation of Thorium for power production is a thrust area of the Indian Nuclear
NORM MANAGEMENT GUIDELINES & PRINCIPLES
Introducing NORM NORM MANAGEMENT Three is glad to present some basic hints about NORM that should be taken onto consideration whilst dealing with these matters The acronym NORMmeans all Naturally Occurring
The ACR : Advanced Design Features for a Short Construction Schedule
Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for
Technical concepts for storing HLW - Monitoring, renewal and refurbishment of storage facilitites
Technical concepts for storing HLW - Monitoring, renewal and refurbishment of storage facilitites Dipl.-Ing. Dennis Köhnke Dipl.-Ing. Manuel Reichardt Institute for Building Materials, Concrete Construction
Transportation of Radioactive Material
Haza rdo us Reactor Concepts Manual Transportation of Radioactive Material Santa Fe The issues associated with the transportation of radioactive material are very complex due in part to the regulatory
Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation. G.. d Amored
Sino-Italian Cooperation Project Role and tasks of Arpa Piemonte in controlling and monitoring of ionizing and non ionizing radiation G.. d Amored Environmental Protection Agency of Piedmont Region (ARPA
British Nuclear Group Reactor Sites Chemistry Issues NuSAC SCR Meeting - April 4 th 2006
British Nuclear Group Reactor Sites Chemistry Issues NuSAC SCR Meeting - April 4 th 2006 Presented by: Dr Malcolm Pick, Senior Engineering Consultant, Decommissioning Support Branch, Engineering and Technical
Fission fragments or daughters that have a substantial neutron absorption cross section and are not fissionable are called...
KNOWLEDGE: K1.01 [2.7/2.8] B558 Fission fragments or daughters that have a substantial neutron absorption cross section and are not fissionable are called... A. fissile materials. B. fission product poisons.
TYPES OF REGULATORY DOCUMENTS
REGULATORY GUIDE Radiation Safety Training Programs for Workers Involved in Licensed Activities with Nuclear Substances and Radiation Devices, and with Class II Nuclear Facilities and Prescribed Equipment
Andreeva Bay Facilities for SNF Management. CEG IAEA Workshop - February 2010
Andreeva Bay Facilities for SNF Management CEG IAEA Workshop - February 2010 Presentation Outline Technical challenges at Andreeva Bay Strategic objectives and principles applied to the solution Measures
RADON AND HEALTH. INFORMATION SHEET October 2002. What is radon and where does it come from?
INFORMATION SHEET October 2 FINAL RADON AND HEALTH What is radon and where does it come from? Radon is a natural radioactive gas without odour, colour or taste. It cannot be detected without special equipment.
Radioactive waste managment in Estonia past, present and future
Radioactive waste managment in Estonia past, present and future Ivo Tatrik [email protected] Content 1. Status of ALARA 2. Decomission of Paldiski Former Navy Submarine Training Centre 3. Decomission
CRIIRAD report N. 10-07. Analyses of atmospheric radon 222 / canisters exposed by Greenpeace in Niger (Arlit/Akokan sector)
CRIIRAD Commission de Recherche et d Information Indépendantes sur la Radioactivité Site : www.criirad.org Tel : + 33 (0)4 75 41 82 50 Fax : + 33 (0)4 75 81 26 48 E-mail : [email protected] Valence,
www.universityquestions.in
DEPARTMENT OF ELECTRICAL AND ELECTRONICS ENGINEERING QUESTION BANK SUBJECT: ME6701-POWER PLANT ENGINEERING YEAR/SEM: III/V UNIT-I COAL BASED THERMAL POWER PLANTS 1. What are the processes of rankine cycle?
GUIDELINE TITLE: ASBESTOS DISPOSAL AT WASTE DISPOSAL GROUNDS. BRANCH/DIVISION: Environmental Approvals / Environmental Stewardship
GUIDELINE TITLE: ASBESTOS DISPOSAL AT WASTE DISPOSAL GROUNDS BRANCH/DIVISION: Environmental Approvals / Environmental Stewardship Effective Date: June 9, 2015 Approved By: EMC Date Reviewed: Date Revised:
Boiling Water Reactor Systems
Boiling Water (BWR) s This chapter will discuss the purposes of some of the major systems and components associated with a boiling water reactor (BWR) in the generation of electrical power. USNRC Technical
7.1 General 5 7.2 Events resulting in pressure increase 5
GUIDE YVL 2.4 / 24 Ma r ch 2006 Primary and secondary circuit pressure control at a nuclear power plant 1 Ge n e r a l 3 2 General design requirements 3 3 Pressure regulation 4 4 Overpressure protection
GUIDE FOR THE PREPARATION OF RADIOACTIVE MATERIAL APPLICATIONS FOR WELL LOGGING OPERATIONS IN KENTUCKY
GUIDE FOR THE PREPARATION OF RADIOACTIVE MATERIAL APPLICATIONS FOR WELL LOGGING OPERATIONS IN KENTUCKY Radiation Control Cabinet for Human Resources 275 East Main Street Frankfort, Kentucky 40621 JANUARY
Nuclear Waste A Guide to Understanding Where We've Been and Where We're Going
Nuclear Waste A Guide to Understanding Where We've Been and Where We're Going National Conference of State Legislatures The presentation was created by the National Conference of State Legislatures and
OPG READY TO DELIVER REFURBISHMENT OF DARLINGTON NUCLEAR STATION OPG also planning continued operation of Pickering Station
OPG READY TO DELIVER REFURBISHMENT OF DARLINGTON NUCLEAR STATION OPG also planning continued operation of Pickering Station Toronto - Ontario Power Generation (OPG) is ready to deliver on the Government
Regulatory Requirements and Licensing of OPG s DGR Project
Regulatory Requirements and Licensing of OPG s DGR Project OPG s Deep Geologic Repository Project for Low and Intermediate Level Radioactive Waste Presentation to Joint Review Panel July 18, 2012 nuclearsafety.gc.ca
Canadian National Report for the Convention on Nuclear Safety
Canadian National Report for the Convention on Nuclear Safety Canadian National Report for the Convention on Nuclear Safety Minister of Public Works and Government Services Canada 1998 Catalogue number
centre for radiation protection
centre for radiation protection To excel in radiation science so as to: enforce and promote the radiation safety of workers, the public and the environment; ensure that irradiating apparatus and nuclear
DECOMMISSIONING OF THE GEORGIA TECH RESEARCH REACTOR. Steve Marske, Robert Eby, Lark Lundberg CH2M HILL
ABSTRACT DECOMMISSIONING OF THE GEORGIA TECH RESEARCH REACTOR Steve Marske, Robert Eby, Lark Lundberg CH2M HILL Nolan Hertel, Rod Ice Georgia Institute of Technology On July 1, 1997, the Georgia Institute
MBJ Environmental Programmes
MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,
Nuclear Emergency Response Program
Nuclear Emergency Response Program NUCLEAR POWER PLANTS In California, there are two operating nuclear power plant sites: Diablo Canyon in San Luis Obispo County has two active units and San Onofre Nuclear
HOW IT WORKS ELECTRICITY GENERATION
10 2 ELECTRICITY IN ONTARIO Ontario gets its electricity from a mix of energy sources. About half of our electricity comes from nuclear power. The remainder comes from a mix of hydroelectric, coal, natural
A Guide to Hazardous Substance Storage Capacity
New Jersey Department of Environmental Protection Bureau of Release Prevention A Guide to Hazardous Substance Storage Capacity August 7, 2014 Introduction The Spill Compensation and Control Act (the Spill
Nuclear Energy: Nuclear Energy
Introduction Nuclear : Nuclear As we discussed in the last activity, energy is released when isotopes decay. This energy can either be in the form of electromagnetic radiation or the kinetic energy of
CHARACTERISTICS OF RADIOACTIVE WASTE FORMS CONDITIONED FOR STORAGE AND DISPOSAL: Guidance for the Development of Waste Acceptance Criteria
IAEA-TECDOC-285 CHARACTERISTICS OF RADIOACTIVE WASTE FORMS CONDITIONED FOR STORAGE AND DISPOSAL: Guidance for the Development of Waste Acceptance Criteria REPORT BY AN ADVISORY GROUP MEETING ON CONDITIONING
PRESENT ISSUES FOR CENTRE DE LA MANCHE DISPOSAL FACILITY
PRESENT ISSUES FOR CENTRE DE LA MANCHE DISPOSAL FACILITY M. DUTZER, J.P. VERVIALLE, P. CHARTON Andra - Agence Nationale pour la Gestion des Déchets Radioactifs 1-7 rue Jean Monnet, 92298 Châtenay-Malabry
Security and Safeguards Considerations in Radioactive Waste Management. Canadian Nuclear Safety Commission
Security and Safeguards Considerations in Radioactive Waste Management Raoul Awad Director General, Directorate of Security and Safeguards Canadian Nuclear Safety Commission Radioactive Waste Management
Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario
Canadian Energy Research Institute Levelised Unit Electricity Cost Comparison of Alternate Technologies for Baseload Generation in Ontario Matt Ayres Senior Director, Research Electricity Morgan MacRae
ATTACHMENT 1-9 CHWSF CONTAINER MANAGEMENT
1.0 INTRODUCTION ATTACHMENT 1-9 CHWSF CONTAINER MANAGEMENT 1.1 This Attachment provides information about the management of containers in U.S. Army Dugway Proving Ground s (DPG s) Container Storage Building
Engineered Media for Removal of Fission Products from Aqueous Streams 14580. Abigail Holmquist, UOP - A Honeywell Company
Engineered Media for Removal of Fission Products from Aqueous Streams 14580 Abigail Holmquist, UOP - A Honeywell Company ABSTRACT Nuclear fission products from fuel have the potential to be released into
