ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL
|
|
|
- Hubert Hopkins
- 10 years ago
- Views:
Transcription
1 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.1: Checklist of Pre-Construction Planning Activities (page 15) Project Number: Project Name: Location: Estimator: Project Manager: PRE-CONSTRUCTION PLANNING CHECKLIST COMPLETION ACTIVITY ACT. DATE CATEGORY NO. ACTIVITY 1 Finalize selection of project manager, field supervisor and other key team members. Team Hold turnover meeting between estimator and project 2 Selection separate and manager (when applicable). Hold separate turnover meeting between project Turnover 3 manager and field supervisor. 4 Hold pre-job (planning) kickoff meeting with internal team members to assign responsibilities. 5 Review contract for unfavorable or high risk clauses (recommended). 6 Project manager reviews plans, specifications, and schedule. 7 Field supervisor reviews plans, specifications, and schedule. Scope and Create a list of issues that need to be resolved and 8 Contract begin the request for information (RFI) process. Review 9 Conduct site visit (recommended) Compare estimated (bid) work activities and materials to planned performance. Identify value engineering and refabrication opportunities and how to simplify the work. 12 Prepare construction takeoff. 13 Set up project files and create contact list. 14 Set up computerized tracking and control system (forms, database, schedule, tracking). 15 Initiate a change management system. Administrative Setup Initiate a request for information (RFI) tracking and 16 processing system. 17 Initiate a submittal tracking and processing system. 18 Develop a Labor Requirements/Expectations letter (for background check, etc.) (recommended). 42
2 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.1: Checklist of Pre-Construction Planning Activities (continued) Project Number: PRE-CONSTRUCTION PLANNING CHECKLIST COMPLETION ACTIVITY ACT. DATE CATEGORY NO. 19 separate 20 Buyout 21 Process ACTIVITY Price and/or review subcontractor/supplier/vendor prices and qualifications. Negotiate pricing and contract conditions, and select subcontractors/suppliers/vendors. Develop and issue purchase orders and contracts for materials and equipment. 22 Order long-lead-time materials and equipment. 23 Request submittals, cut sheets and shop drawings. 24 Develop and process log and book of submittals, cut sheets and shop drawings. Material 25 Develop material delivery and handling plan. Handling Plan 26 Develop material storage and staging plan. 27 Develop, review or expand cost code scheme. Budget Develop budget by breaking down labor, material, 28 Preparation overhead and profit costs. 29 Develop schedule of values. 30 Develop installation sequence and layout drawings. Layout and 31 Develop field instructions, including panel, pull or Sequencing conduit schedules. Plan Develop prefabrication drawings for field use (when 32 applicable). 33 Review customer s schedule and timeline. 34 Identify work that impacts electrical activities. Schedule 35 Development Review the work sequence and long-lead-time material/equipment delivery dates. 36 Coordinate electrical schedule with customer schedule (recommended). 37 Create a bar chart schedule (recommended). Customize the computerized tracking and control Tracking and Control 38 system (database/schedule/etc.) for the current project. 39 Develop labor and materials tracking report. 43
3 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.1: Checklist of Pre-Construction Planning Activities (continued) Project Number: PRE-CONSTRUCTION PLANNING CHECKLIST COMPLETION ACTIVITY ACT. DATE CATEGORY NO. ACTIVITY 40 Review meeting schedule. 41 Review request for information (RFI) process. Construction 42 Review change order process and field change management process. Execution Kickoff 43 Review submittal processing procedure. Meeting 44 Review billing and invoicing procedures. 45 Review project and field reporting and tracking procedures. 46 Review electrical and customer schedules. 44
4 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.2: Team Selection and Turnover Checklist (page 16) Project Number: Project Name: Location: Estimator: Project Manager: TEAM SELECTION AND TURNOVER CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM SUB-ACTIVITIES DATE NO. 1. Finalize selection of project manager, field supervisor and other key team members Assemble a list of project managers and review their current workload and special skills. Determine whether an ideal match can be made between the project manager and the job, and then select the project manager. Assemble a list of field supervisors and review their current workload and special skills. Determine whether an ideal match can be made between the field supervisor and the job, and then select the project manager. 5 Work with the project manager, field supervisor, and/or the director of operations to select key foreman when appropriate. 2. Hold turnover meeting between estimator and project manager (when applicable). 1 Arrange a meeting time and location and ensure enough time has been allocated to transfer knowledge between the estimator and project manager. 2 Follow and complete a checklist that describes the information that should be transferred (See Table 4.3). 3. Hold separate turnover meeting between project manager and field supervisor. Arrange a meeting time and location and ensure enough time has 1 been allocated to transfer knowledge between the project manager and field supervisor. 2 Follow and complete a checklist that describes the information that must be transferred (see Table 4.3). 4. Hold pre-job (planning) kickoff meeting with internal team members to assign responsibilities. 1 3 Arrange a meeting time and location and ensure enough time has been allocated to assign planning responsibilities. Invite internal team members that will be involved during the 2 construction execution process, such as project manager, field supervisor, accounting, purchasing, and director of field operations. Complete a checklist that describes the planning activities that must be completed and who is responsible for completion (see Table 4.4). 45
5 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.3: Turnover Meeting Agenda (page 16) Project Number: Project Name: Location: Estimator: Project Manager: Review Items: TURNOVER MEETING AGENDA 1. Project overview a. Project name b. Location c. Type of work d. Estimated cost and estimated work hours e. Profit goal f. General scope of work g. Identify potential opportunities and challenges of the project 2. Review the plans and specifications. a. Go page by page through the plans to discuss the quantities and costs. b. Review each section of the specifications. c. Discuss how the estimator assumed the work would be performed (materials and methods). d. Review others work performance. e. Identify discrepancies and ambiguities in the bid documents. f. Identify design discrepancies or issues. g. Identify potential errors in the bid documents. h. Discuss information collected during a site visit. i. Discuss information collected during a pre-bid meeting. j. Identify potential cost savings from changes to materials and methods. k. Identify potential prefabrication or internal value engineering opportunities. l. Discuss alternative routing of conduits. m. Identify any temporary power and lighting requirements. 3. Review the cost estimate and bid price. a. Review each bid line item and its cost. b. Review overhead, profit and contingency funds. c. Discuss wage rates. d. Review the bid submission letter with clarifications and qualifications. 4. Review subcontractor/vendor pricing and qualifications. a. Review subcontractors and suppliers scope of work and qualifications. b. Identify all pre-contract commitments and promises. c. Verify minority business requirements. 46
6 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.3: Turnover Meeting Agenda (continued) Project Number: Review Items: 5. Review the schedule and milestones. a. Review the owner-furnished schedule. b. Review any preliminary schedule submitted with the bid. c. Review work by others that will impact the electrical work. d. Identify important material and equipment delivery dates. e. Discuss holidays, vacations and potential weather events. 6. Review manpower requirements and labor rates. a. Review the manpower loading chart (if available). b. Identify the estimated crew mix. c. Identify any wage increases. d. Review the potential for overtime. 7. Review other items specific to this project: 47
7 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.4: Pre-Job Planning Kickoff Meeting Agenda (page 17) Project Number: Project Name: Location: Estimator: Project Manager: Agenda Items: PRE-JOB PLANNING KICKOFF MEETING AGENDA 1. Project overview a. Project name b. Location c. Type of work d. Contract cost e. General scope of work f. Identify potential opportunities and challenges of the project 2. Introduce internal team members. a. Project manager b. Field supervisor/foreman c. Estimator d. Accounting representative e. Other internal team members (i.e., CAD operator, purchasing agent, etc.) 3. Identify external team members. a. Owner/customer b. Architect/engineer c. General contractor/construction manager d. Other specialty subcontractors e. Vendors/suppliers 4. Review the general scope of work. a. Provide an overview of the project scope of work and the electrical scope. b. Review major work performed by others. 5. Review the contract cost. a. Review direct costs and the contract cost. b. Review overhead, profit and contingency funds. 6. Review purchasing of materials, equipment and services from subcontractors/vendors. a. Review subcontractors and suppliers scope of work and qualifications. b. Identify all pre-contract commitments and promises. c. Verify minority business requirements. 48
8 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.4: Pre-Job Planning Kickoff Meeting Agenda (continued) Project Number: Agenda Items: 7. Review the schedule and milestones. a. Review the owner-furnished schedule. b. Review any preliminary schedule submitted with the bid or construction schedule. c. Review work by others that will impact the electrical work. d. Identify important material and equipment delivery dates. 8. Review manpower requirements and labor rates. a. Review the manpower loading chart (if available). b. Identify the estimated crew mix. c. Identify any wage increases. 9. Review the contract identify any special clauses that require careful consideration. 10. Review administrative procedures. a. Administrative setup b. Request for Information (RFI) procedures and setup c. Submittal process and setting up the submittal tracking system d. Change order procedures and setting up the change management system e. Field reporting requirements f. Budget preparation and billing procedures g. Cost control and setting up the tracking system 11. Review special safety issues. 12. Review site logistics and material storage and staging. a. Site access b. Parking c. Material delivery and movement procedures d. Material storage locations e. Trailer locations (if applicable) f. Site cleanup requirements g. Temporary power and lighting requirements 13. Review bond, permit and certificate of insurance requirements 14. Review other items specific to this project: 49
9 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.5: Scope and Contract Review Checklist (page 17) Project Number: Project Name: Location: Estimator: Bid Due Date: ACT. SCOPE AND CONTRACT REVIEW CHECKLIST FOR PRE-CONSTRUCTION PLANNING COMPLETION DATE ITEM NO. SUB-ACTIVITIES 5. Review contract for unfavorable or high risk clauses (performance recommended). 1 Complete the Contract Review Checklist (Table 4.6). 2 Identify all required bonds, permits and certificates. 3 Review contractual billing requirements. 4 Review and understand procedures for requesting change orders. 5 Identify whether disputes must be resolved through alternative dispute resolution, such as mediation or arbitration. 6. Project manager reviews plans, specifications and schedule. 1 Order extra sets of plans and specifications if necessary. 2 Complete the Scope and Schedule Review checklist (Table 4.7). 3 Compare the scope identified in the contract to the scope from the bid submission to verify that they match. 4 Compare the plans to the specifications to identify any discrepancies. 5 Review the customer-furnished schedule to determine whether the electrical work can be completed within the contractual timeframe. 7. Field supervisor reviews plans, specifications and schedule. 1 Complete the Scope and Schedule Review checklist (Table 4.7). 2 Review best field practices or lessons learned. 3 Identify value engineering and prefabrication opportunities (see Activity 23). 4 Identify labor requirements and begin selecting foremen. 5 Identify special tools that will need to be purchased or assembled. 8. Create a list of issues that need to be resolved and begin the request for information (RFI) process. 1 2 Establish a request for information (RFI) process (see Activity 16) and create a list of questions that require clarification. Formalize the RFIs by assigning them a trackable number and submitting them to the owner/cm/gc. 50
10 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.5: Scope and Contract Review Checklist (continued) Project Number: 9. Conduct a site visit (performance recommended). 1 Complete the Site Visit Checklist (Table 4.8). 2 Examine site access and layout, including parking, material delivery points and material lay-down and storage. 3 Identify locations and availability of matieral and personnel lifts, elevators, cranes, scaffolding and forklifts. 4 Create a plan for installing temporary power (when applicable). 5 Verify existing conditions and compare them to the conditions shown on the plans and described in the specifications. 10. Compare estimated (bid) work activities and materials to planned performance. 1 Compare the estimator s concept of how to perform the work to typical field operations and document differences. 2 Discuss unclear methods or discrepancies with the estimator. 3 Determine the cost difference between the as-bid and planned performance of the work. 11. Identify value engineering and prefabrication opportunities and how to simplify the work. Review value engineering (VE) or prefabrication opportunities that 1 were identified in the turnover meeting between the estimator and project manager. 2 Review procedures for formally requesting VE consideration if required. 3 Search for and identify additional VE and prefabrication items. 4 Identify additional ways to simplify the work. 5 Price out the cost difference between the as-bid and VE options. 10. Compare estimated (bid) work activities and materials to planned performance. 1 Take off the materials, equipment and systems in the order they will be constructed. Code each plan sheet as you take it off so that you can return to it 2 later and immediately identify the quantity of various materials shown on the sheet. 3 The final quantities should be identified by the units in which they will be purchased. 4 All assumptions should be noted on the quantity takeoff sheets. 5 Be sure the quantities that are estimated include a waste factor. 6 Compare the construction takeoff to the bid takeoff to identify significant differences or discrepancies. 51
11 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.6: Contract Review Items 1 (page 17) Project Number: Project Name: Location: Project Manager: Completed Date Completed ITEM Check for ambiguous clauses and seek clarification. Check for one-sided clauses that favor the other party. Cross-reference clauses to understand the whole meaning of clauses. Identify discrepancies and conflicting clauses and seek clarification. Check for agreement between plans and specifications, and seek clarification if there is any discrepancy. Identify any killer clauses that assign full responsibility for everything to the electrical contractor. Determine whether the contract clearly favors the other party (owner/cm/ GC), and seek more equitable contract terms. Review the Indemnification Clause, and ensure your insurance converage can sufficiently cover the risk. Evaluate the Coordination Clause to determine each party s responsibility to coordinate the work. Determine your rights and responsibilities if the sequence of work is changed or if out-of-sequence work impacts the project. Carefully review all time-sensitive clauses that cover commencement, completion, milestones, accelerations, delays and progress. Review and understand your rights to receive damages if the schedule is accelerated or delayed by other parties. Determine whether there is a no-damages-for-delay clause, and review your rights and responsibilities. Review and understand the clause that describes waivers. Review the concealed conditions clause, and identify the circumstances that will entitle you to compensation. Review the Force Majeure clause, and identify the circumstances that will entitle you to a time extension. Evaluate clauses that identify procedures for seeking change orders. Evaluate clauses that identify the compensation for extra work. Identify payment provisions, especially a pay when paid clause and a pay if paid clause. 1 Detailed contract review guidelines can be found in ELECTRI International (2000) Fundamentals of Contract Risk Management for Electrical Contractors. 52
12 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.7: Scope and Schedule Review Items (pages 18, 39) Project Number: Project Name: Location: Estimator: Project Manager: SCOPE AND SCHEDULE REVIEW ITEMS Completed Completed By Date Completed Item Contract Plans Specifications Cost estimate and bid breakdown Referenced/applicable codes or regulations Quality requirements Safety requirements Special conditions Addendums Temporary power and lighting requirements Owner/CM/GC-furnished materials Vendor pricing and qualifications Owner/CM/GC schedule Internal schedule submitted with bid Work sequence and work by others Required coordination with other trades Material and equipment deliveries Anticipated weather problems or holidays Required labor Labor rates and potential increases Crew mix Administrative procedures (submittals/rfis/changes) Other: Other: Other: 53
13 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.7: Scope and Schedule Review Items (continued) Project Number: SCOPE AND SCHEDULE REVIEW ITEMS Completed Who furnishes? Who installs? What to review in the Plans and Specifications Access doors Asbestos abatement Carpentry (miscellaneous) Clean up Conduit (sizes and quantities) Crane Cutting and patching Demolition and removal Electric motors Electric starters Excavation and backfill Fire alarm wiring Fire alarm devices Hand dryers Hoists for personnel Hoists for materials Interior layout Painting Panels Scaffolding Site access Site surveying Temporary power Underground utilities Wire (and/or pipe and wire) Other: Other: Other: 54
14 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.8: Site Visit Checklist (page 19) Project Number: Project Name: Location: Project Manager: Scope Review Completion Date: SITE VISIT REVIEW ITEMS Completed Item to Review Notes Access into and out of the site Circulation throughout the site Material and equipment delivery routes Material storage and staging locations Office trailer or office space Temporary power and lighting locations Existing underground utilities location Existing above ground utility locations Location of existing interior systems Progress of the demolition Progress of the site work Progress of the site layout/surveying Asbestos abatement has been completed Work completed to date Presence/location of the crane Presence/location of the personnel lift Presence/location of the materials lift Potential coordination with others Anticipated weather problems Housekeeping conditions Special site considerations Safety issues or concerns Other: Other: Other: 55
15 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.9: Administrative Setup Checklist (page 21) Project Number: Project Name: Location: Project Manager: Start Date: ADMINISTRATIVE SETUP CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM SUB-ACTIVITIES DATE NO. 13. Set up project files and create contact list. 1 Use the File System Checklist (Table 4.11) to creat paper files. 2 Create a contact sheet that lists all team members and their company contact information. 14. Set up computerized tracking and control system (forms, database, schedule and tracking). 1 Verify the accounting department has assigned a project number and entered intial information in the cost control center. 2 Use the File System Checklist (Table 4.11) to creat computer files. 3 If a separate project management software system is used, set up the project in the system. 4 If a separate project management software system is used, set up the project in the system. 15. Initiate a change management system. 1 Review the contract to identify required change order, field change, and time-and-materials procedures. 2 Review your company s standard procedures for initiating, requesting, and processing change orders and field changes. Develop a log with sequential numbering to track all changes, 3 including change orders, field changes and time-and-materials requests (Table 4.12). 16. Initiate a request for information (RFI) tracking and processing system. 1 2 Develop a log with sequential numbering to track all requests for information (RFIs) (Table 4.13). Determine whether RFIs will be submitted by , fax or postal mail. 3 Review your company s standard procedures for processing RFIs, and use a company standard form for submitting RFIs. 4 Ensure each RFI also identifies a proposed solution. 56
16 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.9: Administrative Setup Checklist (continued) Project Number: 17. Initiate a submittal tracking and processing system. 1 Develop a log with sequential numbering to track all submittals, including those of vendors and subcontractors (Table 4.14). 2 Review your company s standard procedures for processing submittals, and use a company standard form for submissions. Verify that each submittal processing form identifies a respond-no- 3 later-than date, which is associated with timely ordering and delivery of materials and equipment. 18. Develop a Labor Requirements/Expectation letter (for background check, etc.) (performance recommended) For projects that have special requirements such as drug testing, 1 background check or special safety training, develop an expectations letter that must be reviewed and signed by crew members (see Figure 4.8). For projects that will require hiring workers from the union hall, 2 develop an expectations letter that must be reviewed and signed by crew members. 57
17 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.10: File System Checklist (page 21) Project Number: Project Name: Location: Project Manager: SCOPE AND SCHEDULE REVIEW ITEMS Completed File Number File Description Project Information and Contacts Cost Estimate and Bid Submission Contract Agreement Contract Documents Budget and Pay Requests Purchase Orders Subcontracts Materials Folder (Fixtures, Switchgear, Fire Alarm, Low Voltage) Requests for Information Submittals Change Orders Pending Change Orders Approved Correspondence Meeting Minutes Daily/Weekly Field Report Progress Reports Other: Other: Other: 58
18 PRE-CONSTRUCTION PLANNING ACTIVITIES Figure 4.2: Change Order Proposal (pages 22, 39) COMPANY NAME COMPANY ADDRESS CHANGE ORDER PROPOSAL PROJECT NUMBER: PROJECT NAME: DATE: TO: FROM: DESCRIPTION OF CHANGED WORK: COST OF THE CHANGED WORK: Description Labor Materials Equipment Other Subcontracts Total Labor Burden % Bond Premium % Liability Insurance % Overhead Profit TIME EXTENSION calendar days Subtotal TOTAL APPROVED BY: DATE: 59
19 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Figure 4.3: Field Change Form (page 22) PROJECT NUMBER: PROJECT NAME: FIELD SUPERVISOR: WORK PERFORMED BY (EMPLOYEE NAME): DATE: WORK AUTHORIZED BY: TITLE: FIELD CHANGE FORM SCOPE OF WORK: LABOR: EMPLOYEE HOURS WAGE REG OT DT RATE EQUIPMENT/TOOLS: TOTAL EQUIPMENT/TOOL TYPE COST SUBTOTAL % MARKUP TOTAL SUBTOTAL % MARKUP TOTAL MATERIALS: MATERIAL TYPE UNITS QTY UNIT COST SUBCONTRACTORS: TOTAL COMPANY NAME COST SUBTOTAL % MARKUP TOTAL SUBTOTAL % MARKUP TOTAL SUMMARY OF COSTS: TOTAL LABOR TOTAL MATERIALS TOTAL EQUIPMENT/TOOLS TOTAL SUBCONTRACTS TOTAL COST 60
20 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.11: Change Order Log (page 22) Project Number: Project Name: Location: Project Manager: CHANGE ORDER LOG C.O. DATE WHO WHO ASSOCIATED C.O. NUMBER SUBMITTED DESCRIPTION OF CHANGE INITIATED AUTHORIZED RFI NUMBER AMOUNT STATUS 61
21 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.12: Request for Information Log (pages 22, 41) Project Number: Project Name: Location: Project Manager: REQUEST FOR INFORMATION LOG RFI DATE SUBMITTED DATE OF WHO NUMBER SUBMITTED DESCRIPTION OF INFORMATION NEEDED TO RESPONSE INITIATED STATUS 62
22 PRE-CONSTRUCTION PLANNING ACTIVITIES Figure 4.5: Request for Information Form (pages 22, 38) COMPANY NAME COMPANY ADDRESS REQUEST FOR INFORMATION PROJECT NUMBER: PROJECT NAME: DATE: RFI NUMBER: TO: FROM: METHOD SENT: FAX MAIL DESCRIPTION OF REQUEST: ADDITIONAL SUPPORT DOCUMENTS: ARE ARE NOT ATTACHED. DATE REQUIRED: DATE RESPONSE RECEIVED: RESPONSE FROM: RESPONSE: 63
23 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.13: Submittal Log (pages 24, 28, 38, 39) Project Number: Project Name: Location: Project Manager: SUBMITTAL LOG CSI DATE REVISION DATE TO DATE DATE TO ORDER DELIVERY SECTION SUBMITTED NUMBER SUBMITTED ITEM SUPPLIER ARCH/ENG APPROVED SUPPLIER DATE DATE 64
24 PRE-CONSTRUCTION PLANNING ACTIVITIES Figure 4.7: Submittal Transmittal Form (pages 25, 39) COMPANY NAME COMPANY ADDRESS SUBMITTAL TRANSMITTAL FORM PROJECT NUMBER: DATE: PROJECT NAME: CSI SECTION: TO: FROM: FOR FOR FOR SUBMITTAL YOUR FOR YOUR YOUR INFORMATION DATE QTY DESCRIPTION REVIEW APPROVAL FILES ONLY REQ D Please return copies. Additional Comments: Signature: Date: 65
25 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Figure 4.8: Requirements and Expectations Letter (page 25) COMPANY NAME COMPANY ADDRESS COMPANY PHONE NUMBER NAME OF NEW EMPLOYEE: PROJECT NUMBER: PROJECT NAME: DATE OF EMPLOYMENT: TODAY S DATE: SUBJECT: Requirements and Expectations of Personnel Employed on Project Number The purpose of this letter is to notify you of special requirements and expectations of all personnel who will work on Project Number, entitled. The following requirements and expectations must be met as a necessary condition of employment: 1. This project requires weekly random drug testing, which will be conducted by a private company employed by the customer. Any employee who fails a drug test or refuses to submit to a random drug test will be immediately dismissed from employment. 2. This project requires a complete background check and the use of a security badge at all times. Employees who fail to exhibit their security badge or who arrive at the jobsite without their badge will be removed from the premises immediately. 3. Entry into certain parts of the facility will require an escort appointed by the customer. Requests for escorts must be submitted 24 hours in advance. 4. The work hours for this project are Monday through Friday from 7:00 AM to 3:00 PM. 5. No privately owned vehicles or company vehicles will be permitted into the secure work area. All employees must arrive at the security gate each morning no later than 6:45 AM to board a bus that will take employees to the secure work area. All employees must be at the pickup point each afternoon at 3:15 PM to board the bus and be escorted out of the secure area. Late employees will not be permitted into the secure area. 6. Employees may be monitored by closed-circuit television throughout the day. 7. Smoking will not be permitted inside the secure work area. Please acknowledge your acceptance of the requirements and expectations of this project by signing and dating below. I understand and accept the above terms of employment. NAME WITNESS DATE DATE 66
26 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.14: Buyout Process Checklist (page 26) Project Number: Project Name: Location: Project Manager: Start Date: BUYOUT PROCESS CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM SUB-ACTIVITIES DATE NO. 19. Request and/or review subcontractor/supplier/vendor prices and qualifications. 1 Request subcontractor/supplier/vendor pricing if it was not requested or received during the bidding stage. 2 Compare actual subcontractor/supplier/vendor scope of work with the scope identified in the subcontractor/supplier/vendor bid submission. 3 Evaluate the subcontractor/supplier/vendor qualifications. 4 Compare priding and qualifications among the subcontractors/ suppliers/vendors. 20. Negotiate pricing and contract conditions and select subcontractors/suppliers/vendors. 1 2 Discuss potential cost savings with potential subcontractors/ suppliers/vendors. Review the contract or purchase order terms and conditions with potential subcontractors/suppliers/vendors prior to award. 3 Select all successful subcontractors/suppliers/vendors, and issue a letter of intent (if necessary). 21. Develop and issue purchase orders and contracts for materials and equipment. 1 Develop the purchase orders or contracts for subcontractors/ suppliers/vendors. 2 Process and issue the purchase orders or subcontracts. 22. Order long-lead-time materials and equipment. 1 Compare the sequence, schedule and materials/equipment to identify long-lead-time items. Negotiate and issue purchase orders and subcontracts for long-lead 2 time items before negotiating standard purchase orders and subcontracts. 3 Issue a letter of intent or purchase order immediately to release long-lead-time items for order and delivery. 67
27 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.14: Buyout Process Checklist (continued) Project Number: 23. Request submittals, cut sheets and shop drawings. Upon issuing the contract document, the subcontractor/supplier/ 1 vendor should be requested to assemble and submit samples, cut sheets or shop drawings. 2 Identify a deadline by which the submittals, cut sheets, and shop drawings must be submitted to the electrical contractor. 24. Develop and process log and book of submittals, cut sheets and shop drawings. Develop a log, with sequential numbering, to track all submittals, 1 including those of vendors and subcontractors (see also Activity 17 and Table 4.13). 2 Assemble two or more binders of all draft and approved submittals. 3 Submit and track required submittal items. 68
28 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.15: Subcontractor/Supplier/Vendor Comparison Spreadsheet (page 26) Project Number: Project Name: Location: Project Manager: SUBCONTRACTOR/SUPPLIER/VENDOR BID ANALYSIS ITEM TYPE VENDORS REVIEW ITEMS: BUDGET VENDOR A VENDOR B VENDOR C VENDOR D Was the item bid per plans and specs? [Yes/No] Was the item bid per the scope of work? [Yes/No] Are the workers union or non-union? How long will it take to order and deliver the item? List any exclusions. Was tax included in the bid price? [Yes/No] Did the vendor acknowledge all addenda? [Yes/No] Base bid price List any alternate pricing provided. List adjusted bid price if alternates accepted. 69
29 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Figure 4.9: Letter of Intent (page 27) COMPANY NAME COMPANY ADDRESS COMPANY PHONE NUMBER Subcontractor Representative Subcontractor Company Name Subcontractor Company Address Subcontractor Phone Number DATE: December 1, 2005 SUBJECT: Letter of Intent to Award a Contract Dear Subcontractor Representative: You have been selected as the successful bidder on Project Number, entitled. Per our telephone conversation, we are in the process of developing a contract for the scope of work identified in your bid submission. The contract amount will be $1,000,000. This purpose of this letter is to notify you of our intent to award a contract. You can expect to receive the contract no later than, 20. You are authorized to proceed with the work identified in your bid submission. Please feel free to contact me at (222) Sincerely, Electrical Contractor Company Officer Title 70
30 PRE-CONSTRUCTION PLANNING ACTIVITIES Figure 4.10: Purchase Order Form (page 27) COMPANY NAME COMPANY ADDRESS PURCHASE ORDER FORM DATE: P.O. NUMBER: PROJECT NUMBER: PROJECT NAME: TO: SHIP TO: (Home office or jobsite address) SHIP VIA (jobsite) F.O.B. REQUIRED SHIP DATE: QUANTITY DESCRIPTION OF ITEM(S) COST NOTE: MATERIAL SAFETY DATA SHEETS ARE REQUIRED WITH ALL SHIPMENTS SHIPPING INSTRUCTIONS: ADDITIONAL REQUIREMENTS: 1. Submit copies of shop drawings/details/performance data for review/approval 2. Submit copies of OandM manuals or copies of wiring diagrams for review/approval NAME: SIGNATURE: DATE: NAME: SIGNATURE: DATE: 71
31 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.16: Material Handling Planning Process Checklist (page 29) Project Number: Project Name: Location: Project Manager: Start Date: MATERIAL HANDLING PROCESS CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. 25. Develop material delivery and handling plan. 1 SUB-ACTIVITIES Review the Material Delivery/Storage and Site Logistics Best Practices (see Table 4.18). 2 Establish and maintain a file of delivery receipts and packing slips. 3 Establish a material and equipment delivery and storage log 4 Create a material and equipment delivery schedule Develop material storage and staging plan. Establish standard procedures for receiving, handling and storage of materials and equipment. 1 Complete the site logistics review checklist (Table 4.20). 2 Review the Material Delivery/Storage and Site Logistics Best Practices (see Table 4.18). 3 Develop a storage site layout that identifies where the materials and equipment are stored. 72
32 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.17: Material Delivery/Storage and Site Logistics Best Practices (page 29) Project Number: Project Name: Location: Project Manager: MATERIAL DELIVERY/STORAGE AND SITE LOGISTICS BEST PRACTICES Best Practice Number BEST PRACTICE DESCRIPTION 1 Assign one person the responsibility of managing material and equipment delivery, handling storage and staging. 2 Establish a standard unloading crew that consists of laborers or apprentices. 3 Establish standard procedures for receiving, handling and storing materials, and strictly enforce the standard. 4 Develop a storage site layout that identifies where the materials and equipment are stored, and annotate the location on the material and equipment delivery and storage log. 5 Develop a storage site identification system that provides a method to document and track the location of all materials that have been delivered to the jobsite. 6 Establish storage space for each major material item or group (pipe, wire, boxes, etc.). 7 Sort and store the materials as soon as it is delivered to the site. 8 Allow storage space for waste or excess materials, and remove them as soon as possible. 9 Ensure the material and equipment is adequately secured and protected from the elements. 10 Make sure the materials manager is notified of pending deliveries. 11 Return all damaged, excess or incorrect materials to the vendor immediately in order to keep the site free from clutter. 12 Arrange to have materials delivered just before you need them so that storage and handling is kept to a minimum. 13 If materials are ordered in bulk, ask the vendor to store the materials at their office until you need them on the jobsite (also consider paying extra for this option). 14 Consider using a material consignment trailer, where the vendor inventories the trailer each week, restocks it and only charges you for the materials you use. 15 Try to place materials/equipment at the location where they will be used to improve access to the materials/equipment and minimize handling. 16 Arrange to have materials packaged for efficient unloading, handling and installation. 17 Determine ahead of time what equipment will be needed to unload and handle material deliveries. 18 Evaluate the capacity of material lifts, freight elevators and cranes to ensure they can safely move the materials and equipment. 19 Locate your toilet facilities as close to the work areas as possible. 20 Locate your break facilities and trash containers as close to the work areas as possible. 21 Develop a map of facility locations, and distribute it to workers and suppliers/vendors. 73
33 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.18: Material and Equipment Delivery and Storage Log (page 25) Project Number: Project Name: Location: Project Manager: MATERIAL AND EQUIPMENT DELIVERY AND STORAGE LOG DATE P.O. RECEIVED STORAGE DAMAGED RECEIVED NUMBER DESCRIPTION OF ITEM RECEIVED QUANTITY BY LOCATION ITEMS NOTES 74
34 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.19: Site Logistics Review Items (page 29) Project Number: Project Name: Location: Project Manager: SITE LOGISTICS REVIEW CHECKLIST Completed Date Completed ITEM Review the site layout, and identify placement of materials and facilities to maximize productivity. Identify site entry and exit points, and plan possible vehicle circulation. Identify procedures for receiving materials and authorized personnel. Identify material storage locations. Determine and document equipment that will be needed to unload and move materials (cranes, fork lift, pallet jacks, etc.). Evaluate material lifts, freight elevators and cranes to determine whether they can support the size and weight of the material items. Determine and order special tools associated with material handling (box cutters, bar code readers, computers, etc.). Establish a receiving crew that consists of laborers or apprentices who will unload trucks and move materials. Select a worker to be in charge of material handling, including inspection and inventory of delivered items. Establish standard procedures for receiving, logging, handling and storing materials and equipment on the jobsite or at an offsite location. Establish delivery dates for all materials and develop a schedule of deliveries. Evaluate purchasing options to ensure materials are ordered to promote efficient unloading, storage and installation. Evaluate the benefits and pitfalls of prefabrication in terms of delivery, storage, handling and installation. Review the material delivery, handling, storage and staging best practices (see Table 4.18). 75
35 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.20: Budget Preparation Checklist (page 30) Project Number: Project Name: Location: Project Manager: Start Date: BUDGET PREPARATION CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 27. Develop, review or expand the cost code scheme. 1 Decide whether to use a cost code scheme based upon 16 specifications divisions or 48 specifications divisions. 2 Review the cost estimate to identify the existing cost code breakdown, and decide whether additional breakdown is necessary. Review the company standard list of cost codes (or use Table 4.21), 3 and decide which codes will be needed for breaking down the work for tracking and billing. 4 Add new codes for work items that are not on the standard list. 5 Assign additional codes to specify the costs associated with material, equipment, labor, subcontractors and other miscellaneous costs. 28. Develop budget by breaking down labor, material, overhead and profit costs. 1 Create the budget in concert with the labor and materials tracking report. Establish a budget with sufficient line items to identify potential 2 problems yet enough simplicity to avoid complex, time-consuming data entry Develop schedule of values Verify that labor and materials can and will be reported according to the budget line items. 1 Review the contract to identify the contractual format and process for developing a schedule of values. 2 Create the schedule of values in concert with the billing process. 3 Consider rolling up the budget so that the schedule of values has the same summary line items but fewer sub-line items. 76
36 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.21: Cost Code Scheme Based on Masterformat 1995 (16 Divisions) (page 30) DIVISION DESCRIPTION General Requirements/Conditions Temporary Facilities and Controls Temporary Utilities Execution and Closeout Requirements Mobilization Cutting and Patching Cleaning and Waste Management Closeout Submittals Site Preparation Demolition Utility Services Electrical and Communications Structures Precast Concrete Precast Concrete Specialties Cold-Formed Metal Framing Electrical Support Assemblies Identification Devices Illuminated Interior Signage Theater and Stage Equipment Stage Lighting and Controls Controls for Theater & Stage Equipment Audio-Visual Equipment Lightning Protection Conductors Cathodic Protection Conductors Security Access and Surveillance Building Automation and Control Detection and Alarms HVAC Instrumentation and Control Basic Electrical Materials and Methods Grounding and Bonding Hangers and Supports Electrical Identification Electrical Testing Restoration and Repair Wiring Methods Conductors and Cables Raceway and Boxes Wiring Devices Wiring Connections Electrical Power Electrical Utility Services Motors and Generators Generator Assemblies Battery Equipment Static Power Converters Transformers Power Filters and Conditioners DIVISION DESCRIPTION Transmission And Distribution Transmission and Distribution Accessories High-Voltage Switching and Protection Medium-Voltage Switching and Protection Medium-Voltage Switching and Protection Assemblies Unit Substations Low-Voltage Distribution Enclosed Switches and Circuit Breakers Enclosed Controllers Low-Voltage Switchgear Switchboards, Panelboards, and Control Centers Enclosed Bus Assemblies Low-Voltage Transformers Power Distribution Units Components and Accessories Lighting Interior Luminaires Exterior Luminaires Emergency Lighting Classified Location Lighting Special-Purpose Lighting Signal Lighting Dimming Control Lighting Accessories Lighting Restoration and Repair Communications Communications Circuits Telephone and Intercommunication Equipment Communication and Data Processing Equipment Cable Transmission and Reception Equipment Broadcast Transmission and Reception Equipment Microwave Transmission and Reception Equipment Sound and Video Sound and Video Circuits Sound Reinforcement Broadcast Studio Audio Equipment Broadcast Studio Video Equipment Television Equipment Multimedia Equipment 77
37 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.22: Budget Breakdown and Tracking Spreadsheet (pages 30, 36, 40) Project Number: Project Name: Location: Project Manager: CHANGE ORDER LOG CSI OH&P DIVISION DESCRIPTION LABOR MATERIALS EQUIPMENT SUBCONTRACTS (15%) TOTAL 78
38 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.23: Company Schedule of Values (pages 31, 40) Project Number: Project Name: Location: Project Manager: SCHEDULE OF VALUES (A) (C) (D) (E) (F)=(D+E) (G)=(F/C) (H)=(C-F) (B) (I) LINE CONTRACT PREVIOUSLY COMPLETED COMPLETED % BALANCE DESCRIPTION ITEM VALUE COMPLETED THIS PERIOD TO DATE COMPLETE TO FINISH RETAINAGE 79
39 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.24: Layout and Sequencing Planning Checklist (page 32) Project Number: Project Name: Location: Project Manager: Start Date: LAYOUT AND SEQUENCING CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM SUB-ACTIVITIES DATE NO. 30. Develop installation sequence and layout drawings. 1 Organize the project by areas, floors or systems 2 Allocate sufficient time to mentally think through the sequencing of all work processes from start through completion. 3 Determine whether to create sequence and layout drawings by hand (marked-up drawings) or by creating new CAD drawings. Create daily installation drawings at least one day prior to the date 4 when the work needs to be performed so that the drawings can be distributed each morning to foremen and field crews. 5 Review the sequence daily or weekly to ensure the project is progressing as expected. 31. Develop field instructions, including panel, pull or conduit schedules. Review the sequence and installation process to identify any 1 additional information that might minimize questions and improve productivity. Create the panel, pull or conduit schedules in conjunction with the 2 installation drawings so that they can be distributed as a package to the foremen or field crews. 3 When repetitive work is scheduled on a project, develop field instructions and drawings 32. Develop prefabrication drawings for field use (when applicable). For systems that are partially or completely prefabricated in a 1 prefabrication shop, develop drawings that show how the prefabricated parts should be assembled and installed in the field. For systems prefabricated in a shop, ensure the prefabricated parts 2 are clearly labeled and that these labels correspond to an assembly and installation scheme identified on the drawings. If on-site prefabrication is scheduled, the drawings should identify 3 the step-by-step process of how each piece is assembled into the prefabricated system. 4 5 If on-site prefabrication is scheduled, separate drawings should also be created to identify how the prefabricated parts should be installed. Distribute the prefabrication drawings to the foremen or field crews that will perform the work. 80
40 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.25: Schedule Development Planning Checklist (page 34) Project Number: Project Name: Location: Project Manager: Start Date: SCHEDULE DEVELOPMENT CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM SUB-ACTIVITIES DATE NO. 33. Review customer s (general contractor s) schedule and timeline. 1 Complete the Customer s Schedule Review Items checklist (see Table 4.26) 2 Initiate or attend a customer schedule review meeting to identify any special requirements and clarify any questions. 34. Identify work that impacts electrical activities. 1 2 While reviewing the overall construction schedule, annotate work that must be coordinated with other trades. While reviewing the overall construction schedule, annotate potential conflicts that will require coordination. 3 Develop and submit RFIs to resolve open questions about equipment wiring or conflicts among systems. Request an initial (and a recurring) coordination meeting to identify 4 and resolve schedule questions and conflicts before installation begins Review the work sequence and long-lead-time material/equipment delivery dates. 1 Develop a rough draft of the electrical schedule from the sequence and installation plan. 2 Verify the ordering and delivery dates of long-lead-time materials and equipment. Perform a three-way coordination between the sequencing/ 3 installation plan, material/equipment delivery plan and the draft draft electrical schedule. 4 Modify the draft schedule and sequencing/installation plan to accommodate long-lead-time deliveries. 81
41 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.25: Schedule Development Planning Checklist (continued) Project Number: 36. Coordinate electrical schedule with the customer s schedule. After coordinating the sequencing/installation plan, material/equip- 1 ment delivery plan and the draft electrical schedule, coordinate the draft schedule with the customer s schedule and adjust as necessary. Review the final electrical schedule with the customer, general 2 contractor, other trade contractors and suppliers to resolve any final conflicts. 3 Seek approval of the schedule from the customer and general contractor. 4 Seek integration of the electrical schedule into the customer/general contractor s overall project schedule. 24. Develop and process log and book of submittals, cut sheets and shop drawings. In addition to the integration of the electrical schedule into the overall 1 schedule, format the final electrical schedule into an independent bar chart for tracking and control. 2 Select the type of bar chart to develop and track. 3 Save the original approved schedule as the baseline so that progress can be tracked and delays can be documented. 4 Distribute the electrical bar chart schedule to the customer, general contractor, various subcontractors and suppliers. 82
42 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.26: Customer s Schedule Review Items (pages 34, 41) Project Number: Project Name: Location: Project Manager: CUSTOMER S SCHEDULE REVIEW CHECKLIST Completed Item to Review Annotations Identify the overall project start date: Identify the electrical work start date: Identify the overall project completion date: Identify the electrical work completion date: List any interim milestones: Is the project divided into phases? Yes No Identify the start and completion dates for each phase (if applicable): Does the contract include a liquidated damages clause? Yes No Does the contract include an incentive for early completion? Yes No Can the electrical work be completed in the timeframe identified in the contract documents? Yes No If the schedule must be compressed, create a plan for compressing the schedule and completing the work by the contractual completion date. Identify unusual scheduling requirements (such as night work, second shift work, after-school work hours, escort required, etc.): Will the owner furnish any items, such as materials or equipment? Yes No Identify the deliver no later than dates that owner-furnished items must be delivered to the jobsite. Will any portion of the work be installed by the owner s own workforce or a separate contract? (example: automated shelving systems) Yes No Identify the install no later than dates that owner-installed items must be completed. Identify techniques that will speed up the completion of the work. 83
43 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.26: Customer s Schedule Review Items (continued) Project Number: CUSTOMER S SCHEDULE REVIEW CHECKLIST Completed Item to Review Annotations Review the sequencing/installation plan to determine how the electrical work fits into the overall project schedule. Identify work that has already been completed: Identify work in progress and percent complete: Identify non-electrical activities that must be completed before the electrical portion of the work can begin. Are you aware of any pending changes to the overall project or electrical work? Yes No If yes, describe the pending changes: Do you anticipate crowded site conditions? Yes No If yes, consider scheduling some of the electrical work during a second shift to improve productivity. 84
44 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.27: Schedule Development Best Practices and Rules-of-Thumb (page 35) Project Number: Project Name: Location: Project Manager: SCHEDULE DEVELOPMENT BEST PRACTICES AND RULES-OF-THUMB Best Practice Number BEST PRACTICE/RULE-OF-THUMB DESCRIPTION 1 Seek scheduling input from the field superintendent and foremen. They often understand how the work will be accomplished and how the installation method corresponds to the crew size and duration. 2 Develop the first draft schedule using actual durations to determine whether the electrical work can be completed by the contractual completion date. If the schedule must be compressed, build the compression into the second draft schedule. 3 Consider developing a resource-loaded schedule so that the expenditures from the schedule can be compared to the expenditures from the cost report. 4 Compare the estimated work hours for an activity (or work process) to the scheduled duration of that activity (or work process). Then, either adjust the duration based on estimated work hours and expected crew size, or adjust the crew size based on the estimated work hours and allowable duration. 5 Be sure the schedule takes into account the time of year when the work item will be performed and the possible weather that can be expected. Excessive heat, cold, humidity, rain or wind can significantly impact the progress of the work. 6 Understand when major materials and equipment items will be delivered to the jobsite. The schedule may need to be adjusted to accommodate the delivery of those items. 7 Be sure the schedule clearly documents the date when owner-furnished materials and equipment must be received. Also, make sure the owner knows when these items are required, and seek their acknowledgement in writing. 8 Review the schedule of other specialty contractors to identify work that will impact the electrical schedule. For example, if the air conditioning unit will require a power connection, completion of the connection must occur after the unit has been delivered and installed. Hence, the electrical work must be coordinated with the mechanical work. 9 The electrical schedule should incorporate the work of any electrical subcontractors, such as the fire alarm installer and tester. Review and incorporate your subcontractors work into your own schedule and be sure to provide updates if the schedule changes. 10 If crowded conditions or overmanning is expected on a jobsite (due to a small site or an acceleration of the work), consider scheduling some of the electrical work during a second shift to improve workflow and increase productivity. 11 Once the electrical schedule has been reviewed and approved by the customer/general contractor, document delays and changes to the sequence caused by others. Good documentation can improve your chances of receiving a time extension and financial compensation. 85
45 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.27: Schedule Development Best Practices and Rules-of-Thumb (continued) Project Number: SCHEDULE DEVELOPMENT BEST PRACTICES AND RULES-OF-THUMB Best Practice Number BEST PRACTICE/RULE-OF-THUMB DESCRIPTION 12 When developing work activities or elements for the schedule, review the budget, cost codes and installation sequence plan. Create work elements that comprise no more than 5% of the scope of work so that inaccuracy in tracking progress will not have a significant impact on the percent complete. 13 Consider creating a computerized bar chart schedule. Tracking and control will be greatly simplified if the updates can be made in a computer system. 14 Consider dividing the schedule into areas or systems, such as first floor, second floor, etc. This will simplify tracking and control, especially on larger projects. 15 If some of the work is repetitive (such as conduit and wire on the first floor, second floor, etc.), consider creating these activities in your computer scheduling software and simply cutting and pasting as many times as the work occurs. The dates and durations can then be modified for each area of work. 86
46 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.28: Tracking and Control Planning Checklist (page 36) Project Number: Project Name: Location: Project Manager: Start Date: TRACKING AND CONTROL CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. SUB-ACTIVITIES 38. Customize the computerized tracking and control system (database/ schedule/etc.) for the current project. 1 Review the tracking and control best practices (Table 4.31). 2 Complete the tracking and control tools checklist (Table 4.32). 3 Select appropriate computerized tracking and control tools for the project. 4 Modify the tracking and control tools for the project. 39. Develop labor and materials tracking report. 1 Review the cost estimate and associated budget and cost code scheme. 2 Match the cost estimate/budget work items to crew assignments so that labor and materials can be tracked easily. 3 Select the reports to be created and used for monitoring progress. 4 Develop the selected reports by inputting project data into the reporting system (database or accounting system). 87
47 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.29: Tracking and Control Best Practices (page 36) Project Number: Project Name: Location: Project Manager: TRACKING AND CONTROL BEST PRACTICES Best Practice Number BEST PRACTICE/RULE-OF-THUMB DESCRIPTION 1 Remember that tracking and control involves a time-cost tradeoff. The more detailed the tracking and control system is, the more time must be spent on entering data and the greater the overhead costs will be. You must balance detail with simplicity. 2 Be sure to take into account the financial information needs of banks and bonding companies when setting up your control system. 3 If your company keeps track of historic costs, be sure the tracking and control system captures the right data in the proper format so that it can be added to the historic cost database. 4 Match budget/cost control line items with field work items so that labor hours can be easily reported and tracked. 5 Review the daily labor reporting procedures with the field supervisor and foremen. Be sure they understand how to code timecards so that the work performed can be directly associated with line items in the budget and tracking reports. 6 Deviations between actual and estimated costs and work hours should be discussed with the field supervisor each week to identify and correct problems immediately. 7 Seek feedback from the crew members about the causes of poor productivity and cost/labor hours overruns. 8 Work together with crews to improve productivity. Often, management actions or inactions contribute to productivity outcomes. For example, poor instructions can hinder productive work, while speedy responses to questions can help increase productivity. 9 If the crew members complete the work in fewer hours than estimated, provide a reward to thank them for their hard work, such as free lunch or special recognition. 10 Try using incentives regularly to improve productivity. 11 Make sure your data entries are as accurate as possible. Remember that cost reports should provide the project manager with a realistic financial overview of the project. 12 A negative variance between estimated and actual cost and work hours should be addressed through corrective action. One of the main benefits of monthly cost reporting is to identify problems early enough to take corrective action. 88
48 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.30: Tracking and Control Tools Checklist (page 36) Project Number: Project Name: Location: Project Manager: TRACKING AND CONTROL TOOLS CHECKLIST Completed Date Completed ITEM Identify the goals of your tracking and control system. Do you want to: a. Monitor profitability? b. Identify variations in costs and work hours? c. Track productivity of the workforce? d. Contribute to your historical costs database? e. Document costs that are beyond the initial scope of work? f. Track changes in cost and work hours? g. Create contractually-mandated cost reports for the customer? h. Evaluate the effectiveness of your management team? i. Conduct risk analyses on future projects of a similar type? Create a project schedule, and format it so that you can update the progress of all schedule line items (see Activity 37). Match schedule line items to budget line items to facilitate effective tracking. As an alternative, create a resource-loaded schedule that will permit you to track cost and labor hours as you track schedule progress. Create a manpower loading chart that identifies your crew size and composition for each week of the project (see Figure 4.13). Customize the computerized project management program so that you can use it as a tool to track RFIs, submittals, purchase orders, deliveries and change orders. Create a progress report to track variances in costs and labor hours. Your progress report should track budgeted line items. Create a labor productivity report to compare estimated to actual productivity and identify solutions to problems. Daily time sheets should be coded to match budget line items. Other: Other: 89
49 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Figure 4.31: Daily Labor Time Report (pages 36, 40) PROJECT NUMBER: PROJECT NAME: FIELD SUPERVISOR: EMPLOYEE NAME: PAY PERIOD: FROM TO: DAILY TIME SHEET DAY WORK DESCRIPTION COST CODE MON HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS DAY WORK DESCRIPTION COST CODE TUE HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS DAY WORK DESCRIPTION COST CODE WED HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS DAY WORK DESCRIPTION COST CODE THU HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS 90
50 PRE-CONSTRUCTION PLANNING ACTIVITIES Figure 4.31: Daily Labor Time Report (continued) DAY WORK DESCRIPTION COST CODE FRI HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS DAY WORK DESCRIPTION COST CODE SAT HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS DAY WORK DESCRIPTION COST CODE SUN HOURS REGULAR OVERTIME DOUBLE TIME TOTAL HOURS 91
51 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.32: Labor Productivity Report (pages 36, 40) Project Number: Project Name: Location: Project Manager: LABOR PRODUCTIVITY TRACKING CSI DIVISION ESTIMATED ACTUAL DESCRIPTION UNITS QTY OF HOURS/ TOTAL QTY OF HOURS/ TOTAL HOURS HOURS UNITS UNITS COST UNITS UNITS COST 92
52 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.33: Construction Execution Kickoff Meeting Agenda (page 38) Project Number: Project Name: Meeting Date and Location: Estimator: Project Manager: Agenda Items: CONSTRUCTION EXECUTION KICKOFF MEETING AGENDA 1. Project overview a. Project name b. Location c. Type of work d. Contract cost e. General scope of work 2. Introduce internal team members and any changes in team members since planning meeting. a. Project Manager b. Field Supervisor c. Foremen d. Estimator e. Accounting representative f. Purchasing Agent g. Director of Operations h. Other internal team members 3. Identify external team members and any changes in team members since planning meeting. a. Owner/Customer b. Architect/Engineer c. General Contractor/Construction Manager d. Other Specialty Subcontractors e. Vendors/Suppliers 4. Review the general scope of work. a. Provide an overview of the project scope of work and the electrical scope b. Review major work performed by others 5. Review the meetings schedule. a. Internal office and jobsite progress meetings b. Jobsite safety and coordination meetings c. Project progress and coordination meetings d. Other meetings 6. Review the Request for Information (RFI) Process. a. Standard company RFI procedure b. Contractual language regarding RFIs and the RFI process c. Current outstanding RFIs 93
53 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.33: Construction Execution Kickoff Meeting Agenda (continued) Project Number: Agenda Items: 7. Review the change order process. a. Contract language regarding changes and the change order process b. Standard company change order and field change processes c. Documentation of changes, delays, disruptions and disputed work 8. Review the submittal process. a. Contract language regarding submittals and the submittal process b. Standard company submittal processes c. Following up on late submissions and approvals 9. Review the billing process. a. Contract language regarding billing and the payment process b. Standard company billing processes c. Subcontractor/supplier/vendor invoicing and payment d. Following up on late payments or open accounts receivable 10. Review the tracking and control process. a. Labor reporting b. Progress reporting and percent complete c. The progress update timeline d. Standard company progress update procedures 11. Review the schedule and milestones. a. Customer-furnished schedule b. Electrical bar chart schedule c. Work by others that will impact the electrical work d. Important material and equipment delivery dates e. Schedule updating to reflect percent complete 12. Review site logistics and material storage and staging. a. Site access b. Parking c. Material delivery procedures d. Material storage locations e. Trailer locations (if applicable) f. Site cleanup requirements g. Temporary power and lighting requirements 13. Review special safety issues. 14. Review other items specific to this project: 94
54 PRE-CONSTRUCTION PLANNING ACTIVITIES Table 4.34: Construction Execution Kickoff Meeting Checklist (page 38) Project Number: Project Name: Location: Project Manager: Start Date: CONSTRUCTION EXECUTION KICKOFF CHECKLIST FOR PRE-CONSTRUCTION PLANNING ACT. COMPLETION ITEM DATE NO. 40. Review meeting schedule. 1 2 SUB-ACTIVITIES Review the schedule of weekly internal meetings associated with the project. Review the schedule of weekly project meetings conducted by the customer or general contractor. 3 Identify the internal team members that will be responsible for attending the internal and external meetings. 41. Review request for information (RFI) process. 1 2 Review the contract for a customer-mandated request for information (RFI) process. Review the company standard procedure for developing, processing, tracking and closing out a request for information. 3 Modify the company standard RFI procedure, as necessary, to conform to the contractually-mandated process. 42. Develop prefabrication drawings for field use (when applicable) Review the contract for a customer-mandated change order (CO) process and field change request process. Review the company standard change order procedure and field change request/management process. Discuss the process for documenting changes, delays and disruptions in the work flow and sequence. 4 Discuss the process for tracking and following up on change order requests and payment for field change directives. 43. Review submittal processing procedures Review the contract documents for a customer-mandated submittal processing procedures. Review the company standard procedure for developing, processing, tracking and receiving approval for project submittals. Modify the company standard submittal procedure, as necessary, to conform to the contractually-mandated process. 95
55 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 4.34: Construction Execution Kickoff Meeting Checklist (continued) Project Number: 44. Review billing and invoicing procedures 1 Review the customer/general contractor s process and timeline for invoicing, lien waivers and payment. 2 3 Review the internal billing cycle established by the accounting department. If necessary, adjust the internal billing cycle to conform to the customer/general contractor s invoicing cycle. 4 Discuss the process for following up with the customer/general contractor on late unpaid invoices. 45. Review project and field reporting and tracking procedures. 1 Discuss the process for reporting labor hours and submitting timecards to the accounting office. 2 Discuss the process for reporting progress and percent complete. 3 Discuss the process for tracking material and equipment costs and purchase orders. 4 Review and discuss the tracking tools that will be used to monitor progress. 5 Review the monthly update process. 46. Review electrical and customer schedules. 1 Review the electrical bar chart schedule. 2 Review the customer/general contractor s schedule and/or timeline. 3 Discuss the process for updating the schedule. 96
56 Section 3: Planning Assessment and Best Practices 5. The Planning Assessment Process 5.1 Introduction to the Planning Assessment Process Chapter 4 of this manual discusses, in detail, the model electrical pre-construction planning process. This research discovered that projects that implemented a planning process similar to the model process tended to perform more successfully. Furthermore, there appeared to be 16 activities that had an especially strong influence on performance and many of these activities were often overlooked during the planning process. 5.2 Purpose of the Planning Assessment Process Chapter 4 presents a series of instructions and easy-to-use checklists to guide electrical contractors through the pre-construction planning process. The purpose of this chapter is to present a scorecard that can be used to evaluate the effectiveness of the planning that was completed on a project that is about to be executed. The chapter will begin by identifying the 16 activities that had an especially strong influence on performance in order to explain why these activities are weighted more heavily on the planning scorecard. Then, the planning effectiveness scorecard will be introduced, which includes all of the activities from the model planning process, and instructions will be provided on how to score the effectiveness of planning on a new project. Finally, a section on score analysis will present some rules-of-thumb and benchmark score values for projects that have various characteristics, such as large projects versus small projects, complex projects versus simple projects, and so on. 5.3 Important and Influential Planning Activities It is essential to note that each of the 46 preconstruction planning activities in the Model Electrical Pre-Construction Planning Process is an important part of the planning process. It is also worth noting that not every activity will require a great deal of time to complete. Indeed, many of the activities can be completed in a matter of a few minutes, particularly on smaller projects. The project manager will need to exercise skill and judgment when determining how much time to devote to each activity. Many of the activities are clearly critical to an effective planning process. Such obvious activities as reviewing the plans and specifications, administratively setting up the project, and issuing purchase orders can directly impact the smooth execution of a project. Overall, 16 influential activities were identified through careful research, and these activities are identified in the next section. It is critical that the project manager understand the following: All of the 46 pre-construction planning activities are important to project success. However, 16 of those activities have a particularly strong influence on the outcome of a project The 16 Influential Planning Activities Sixteen of the pre-construction planning activities were identified as having an especially strong 97
57 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL correlation to a successful project outcome. These activities include the following: Team Selection and Turnover Activity 2: Hold turnover meeting between estimator and project manager (when applicable). Activity 3: Hold separate turnover meeting between project manager and field supervisor. Scope and Contract Review Activity 7: Field supervisor reviews plans, specifications and schedule. Activity 10: Compare estimated (bid) work activities and materials to planned performance. Activity 11: Identify value engineering and prefabrication opportunities and how to simplify the work. Administrative Setup Activity 16: Initiate a request for information (RFI) tracking and processing system. Activity 17: Initiate a submittal tracking and processing system. Buyout Process Activity 23: Request submittals, cut sheets and shop drawings. Material Handling Plan Activity 25: Develop material delivery and handling plan. Activity 26: Develop material storage and staging plan. Layout and Sequencing Plan Activity 30: Develop installation sequence and layout drawings. Activity 31: Develop field instructions, including panel, pull or conduit schedules. Activity 32: Develop prefabrication drawings for field use (when applicable). Schedule Development Activity 36: Coordinate electrical schedule with the customer's schedule. Construction Execution Kickoff Meeting Activity 43: Review submittal processing procedure. Activity 44: Review billing and invoicing procedures. When performing pre-construction planning, extra care should be taken to include these activities in the planning process. Although it is recommended that all of the 46 activities be completed, under extraordinary circumstances, when the planning process must be abbreviated, these 16 activities should be among those that get completed. 5.4 Planning Assessment Process The planning assessment process provides a simple method for evaluating whether each of the 46 pre-construction planning activities has been completed and whether an activity was completed before or after a project was executed. Under ideal circumstances, all of the planning activities will be completed prior to executing the work. However, ideal circumstances are rare in the construction industry, and often, some of the planning activities must be completed after the project has been executed. The purpose of this section is to introduce the planning effectiveness scorecard and to provide instructions on how to use the scorecard to evaluate the planning that has occurred on a new project The Planning Effectiveness Scorecard The planning effectiveness scorecard was developed as a tool to evaluate how closely a project s actual planning process matches the Model Electrical Pre-Construction Planning Process. The scorecard, which is presented as Table 5.1 (pages ), lists each of the 46 model pre-construction planning activities (Column C). Space is provided in Column D for contractors to identify 98
58 THE PLANNING ASSESSMENT PROCESS whether or not the activity was performed and to assign a performance score. The performance score is assigned based on whether an activity was performed or not performed and whether it was completed before or after execution using the following scale: PERFORMANCE SCORE (Column D) 2 = Activity was completed before executing the work 1 = Activity was completed after executing the work 0 = Activity was not completed Using this scale, a higher summed performance score indicates that more of the pre-construction planning activities were completed before executing the work, which correlates strongly to better project performance. Column E represents the weight assigned to each activity. As mentioned in the previous section, 16 of the activities have a stronger influence on performance, and as a result, these activities are assigned larger weights. To calculate a final score (Column F) for each activity, Column D (Performance Score) is multiplied by Column E (Weight). The planning effectiveness score is the sum of all of the total scores Score Analysis Projects that were investigated as part of the research had various character-istics. In particular, four characteristics were analyzed, including project size, initial uncertainty, bid accuracy and type of construction Project Size Project Size is generally determined by three values: contract cost at award, original estimated total work hours and estimated peak number of electricians. Furthermore, estimated project duration is also strongly related to a project s size. The trend seems to indicate that larger projects will require a higher planning effectiveness score to have a greater chance for successful performance Initial Uncertainty of the Project Initial uncertainty of the project is generally determined by three values: perceived level of uncertainty (high, medium or low), percentage of the total design completed at bid and perceived level of complexity (high, medium or low). The trend indicates that projects with high levels of initial uncertainty will require a higher planning effectiveness score to have a greater chance for successful performance Bid Accuracy Bid Accuracy is generally determined by two concepts: a perceived accurate cost estimate and perceived accurate estimated work hours. The trend indicates that projects with an inaccurate bid will require a higher planning effectiveness score to have a greater chance for successful performance Type of Construction Type of Construction is generally determined by classifying projects as: commercial, industrial, institutional and other. The trend indicates that industrial and institutional projects require a higher planning effectiveness score to have a greater chance for successful performance. 99
59 ELECTRICAL PRE-CONSTRUCTION PLANNING IMPLEMENTATION MANUAL Table 5.1: Planning Effectiveness Scorecard PLANNING EFFECTIVENESS SCORECARD (A) (B) (D) (C) ACTIVITY ACT. PERFORMANCE CATEGORY NO. ACTIVITY SCORE* (E) (D)X(E)=(F) WEIGHT FINAL SCORE 1 Finalize selection of project manager, field supervisor and other key team members Team Selection 2 Hold turnover meeting between estimator and project manager (when applicable) and Turnover 3 Hold separate turnover meeting between project manager and field supervisor Hold pre-job (planning) kickoff meeting with internal team members to assign responsibilities Review contract for unfavorable or high risk clauses Project manager reviews plans, specifications and schedule Field supervisor reviews plans, specifications and schedule Scope and 8 Create a list of issues that need to be resolved, and begin the request for information (RFI) process Contract Review 9 Conduct site visit Compare estimated (bid) work activities and materials to planned performance Identify value engineering and prefabrication opportunities and how to simplify the work Prepare construction takeoff Set up project files, and create contact list Set up computerized tracking and control system (forms, database, schedule, tracking) Administrative 15 Initiate a change management system Setup 16 Initiate a request for information (RFI) tracking and processing system Initiate a submittal tracking and processing system Develop a "Labor Requirements/Expectations" letter (for background check, etc.) Review subcontractor/supplier/vendor pricing and qualifications Negotiate pricing and contract conditions, and select subcontractors/suppliers/vendors Buyout Process 21 Develop and issue purchase orders and contracts for materials and equipment Order long-lead-time materials and equipment Request submittals, cut sheets and shop drawings Develop and process log and book of submittals, cut sheets and shop drawings Material Handling 25 Develop material delivery and handling plan Plan 26 Develop material storage and staging plan * 2 = Activity completed before executing the work 1 = Activity completed after executing the work 0 = Activity not completed 100
60 THE PLANNING ASSESSMENT PROCESS Table 5.1: Planning Effectiveness Scorecard (continued) PLANNING EFFECTIVENESS SCORECARD (A) (B) (D) (C) ACTIVITY ACT. PERFORMANCE CATEGORY NO. ACTIVITY SCORE* (E) (D)X(E)=(F) WEIGHT FINAL SCORE Budget Preparation 27 Develop, review or expand cost code scheme Develop budget by breaking down labor, material, overhead and profit costs Develop schedule of values Layout and Sequencing Plan 30 Develop installation sequence and layout drawings Develop field instructions, including panel, pull or conduit schedules Develop prefabrication drawings for field use (when applicable) Review customer's schedule and timeline Schedule 34 Identify work that impacts electrical activities Development 35 Review the work sequence and long-lead-time material/equipment delivery dates Coordinate electrical schedule with the customer's schedule Create a bar chart schedule Tracking and Control 38 Customize the computerized tracking and control system (database/schedule/etc) for the current project Develop labor and materials tracking report Review meeting schedule Review request for information (RFI) process Construction 42 Review change order process and field change management process Execution Kickoff 43 Review submittal processing procedure Meeting 44 Review billing and invoicing procedures Review project and field reporting and tracking procedures Review electrical and customer schedules PLANNING EFFECTIVENESS SCORE (sum of Column F) * 2 = Activity completed before executing the work 1 = Activity completed after executing the work 0 = Activity not completed 101
How to estimate the cost of installing an Electrical Distribution Center (EDC)
How to estimate the cost of installing an Electrical Distribution Center (EDC) Candidate Number 0112233 June 2012 Table of Contents 1) Introduction 3 2) Types and Methods of Measurement 3 5 3) Specific
Sub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders
INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids
SCHEDULING AND PROJECT MANAGEMENT
SCHEDULING AND PROJECT MANAGEMENT Chapter Survey Scheduling Process Scheduling Methods Scheduling and cash management Who is the Project Manager Project Supervisory Team Project Life Cycle Tracking the
Section 010103 Summary of Work Contract 11-03 Security System, Network Infrastructure and UPS Power
Section 010103 Security System, Network Infrastructure and UPS Power Part 1 General 1.1 Summary (Non-inclusive) A. Section Includes: Construction operations required by Contract Documents, defines aspects
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS NOTICE TO BIDDERS BID FORM INSTRUCTIONS TO BIDDERS CONTRACTOR S BID FOR PUBLIC WORK - FORM 96 MINORITY AND WOMEN S BUSINESS ENTERPRISE PARTICIPATION
How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work. Section 2 Types of Methods of Measurements page 4
How to Estimate the Cost of a Clean Room and Data Center Equipment Electrical Work Table of Contents Section 1 Introduction page 3 Section 2 Types of Methods of Measurements page 4 Section 3 Project Specific
ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1
KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1
REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION
REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION
SUCF PROJECT COST REPORTING GUIDE
SUCF PROJECT COST REPORTING GUIDE State University Construction Fund 353 Broadway / ALBANY, NY 12246 SUCF 900 / 11 Table of Contents Page A. Preface 1 B. Area Takeoff Methodology 1. General 2 2. Net Assignable
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides
Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides for experience in the Construction Company's three areas
Pricing of Construction Contract Change Order Documentation
The contract language contained in this Exhibit will supplement and take precedence over all other change order pricing contract provisions in the Contract Documents provided by the Owner, Design-Builder
PROJECT MANUAL INCLUDING SPECIFICATIONS FOR OXNARD SCHOOL DISTRICT EDUCATIONAL SERVICE CENTER DATA ROOM ALTERATION. Oxnard, CA
PROJECT MANUAL INCLUDING SPECIFICATIONS FOR OXNARD SCHOOL DISTRICT Oxnard, CA Client Project Number: ARCHITECT MVE INSTITUTIONAL, INC. 3 MacArthur Place, Suite 850 Santa Ana, CA 92707 Telephone: 949.809.3380
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES This Professional Design Services (this "Agreement"), made as of 20 by and between the University of Cincinnati (the "University") by the Division of Administration
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS
PREPARING DETAILED BREAKDOWNS FOR CHANGE ORDER PROPOSALS I. GENERAL A. All work to be performed under the change order must be itemized, including the work of all subcontractors. B. Items must be relevant
Exhibit C: Scope of Work and Schedule of Deliverables
Exhibit C: Scope of Work and Schedule of Deliverables Project Scope of Work Phases: A City Hall Envelope Renovations B City Hall Skylight Replacement C City Hall Chiller Replacement D City Hall Annex Plaza
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
SECTION 00 0110 TABLE OF CONTENTS. H. 00 2115.01 - Proposed Material, Product or Equipment Substitution Request
SECTION 00 0110 PROCUREMENT AND CONTRACTING REQUIREMENTS 1.1 DIVISION 00 -- PROCUREMENT AND CONTRACTING REQUIREMENTS A. 00 0101 - Project Title Page B. 00 0105 - Certifications Page C. 00 0110 - Table
Corrected Form: Revised Attachment 7B Cost Proposal Distribution Exhibits A1 and A2 Attached
ADDENDUM #1 RFP: 500 16 Design Build Maintenance & Operations Complex The following changes to the Request for Proposal and clarifications are provided based on questions received and must be added/considered
OBJECTIVE To establish procedures for administration of construction manager agreements, including negotiation, contracting and payments.
OP-B-11-D2 ADMINISTRATION OF CONSTRUCTION MANAGER AGREEMENTS SPECIFIC AUTHORITY Sections 240.209(3)(p), 1001.74, 1013.46, F. S. OBJECTIVE To establish procedures for administration of construction manager
Repair and Remodeling Estimating Methods. 4th Edition. RSMeans
Brochure More information from http://www.researchandmarkets.com/reports/2214808/ Repair and Remodeling Estimating Methods. 4th Edition. RSMeans Description: This estimating guide for repair and remodeling
Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES
SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work
MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
Manage Deliverables - Construction Step 6. July 12, 2012
Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement
TD AMERITRADE Park Omaha
TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email
Invitation to Bid FIRE ALARM & DETECTION SYSTEM
Invitation to Bid FIRE ALARM & DETECTION SYSTEM Responses to an Invitation to Bid will be received by the Purchasing Supervisor, Sumner County Board of Education, 1500 Airport Road, Gallatin, TN 37066
GENERAL SERVICES ADMINISTRATION FEDERAL ACQUISITION SERVICE AUTHORIZED FEDERAL SUPPLY SCHEDULE CATALOG/PRICE LIST
C o n t r a c t o r s MECHANICAL ELECTRICAL PLUMBING GENERAL SERVICES ADMINISTRATION FEDERAL ACQUISITION SERVICE AUTHORIZED FEDERAL SUPPLY SCHEDULE CATALOG/PRICE LIST On-line access to contract ordering
TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION INTERSTATE TRANSPORTATION OF GOODS (FREIGHT) SERVICES PUBLICATION
TEXAS DEPARTMENT OF TRANSPORTATION GENERAL SERVICES DIVISION SPECIFICATION NO. TxDOT 9628622 INTERSTATE TRANSPORTATION OF GOODS (FREIGHT) SERVICES PUBLICATION This specification is a product of the Texas
FREEMAN LABOR JURISDICTIONS
UNION JURISDICTIONS for TAMPA, florida To assist you in planning for your participation in this upcoming exposition, we are certain you will appreciate knowing in advance that union labor may be required
REQUEST FOR PROPOSAL: STRUCTURED CABLING, LAN SWITCHES, LONG DISTANCE SERVICE, ELECTRONIC FAXING, AND HOSTED VOIP SPECIFICATIONS
SECOND ADDENDUM TO RFP DOCUMENTS REQUEST FOR PROPOSAL: STRUCTURED CABLING, LAN SWITCHES, LONG DISTANCE SERVICE, ELECTRONIC FAXING, AND HOSTED VOIP SPECIFICATIONS 11/9/2015 To All Potential Bidders: This
REQUEST FOR PROPOSALS (RFP) - Construction Management Services. Germantown School District Office
REQUEST FOR PROPOSALS (RFP) - Construction Management Services From: Germantown School District Project: Germantown School District Addition & Renovations to Rockfield Elementary School N132 W18473 Rockfield
CSC-DIVISION 1-MASTER SECTIONS Description
CSC-DIVISION 1-MASTER SECTIONS Description 01 11 00 Summary of Work by Consultant 01 12 00 Multiple Contract Summary by Consultant 01 14 00 Work Restrictions see below 01 21 00 Allowances by Consultant
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
RULES AND REGULATIONS CONTRACTOR WORK
RULES AND REGULATIONS CONTRACTOR WORK CARILLON 227 West Trade Street Suite 330 Charlotte, NC 28202 The following Rules and Regulations shall govern the operation of contractor work in the Building. For
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
7. Do you perform any out of state work?... If yes, in what states and provide details of work performed
Applicant s Name* (*If more than one entity, attach separate sheet with description of each entity s operations, relationship to each other and ownership.) Contractors Application Agent Applicant Mailing
FOREMAN TRAINING. John Songer Alan Still Larry Lawrence
FOREMAN TRAINING John Songer Alan Still Larry Lawrence WANTED: FOREMAN Looking for highly motivated, well trained, responsible leaders who can look after a job as good or better than I will. Who treats
14a. Hanging Sign Information. It Is The Responsibility Of The Exhibitor To Ensure Your Sign Conforms To All Published Rules And Regulations.
It Is The Responsibility Of The Exhibitor To Ensure Your Sign Conforms To All Published Rules And Regulations. 14a 1 Important Defined as any materials, including but not limited to, signs and machinery,
SAMPLE REQUEST FOR PROPOSALS TEMPLATE
SAMPLE REQUEST FOR PROPOSALS TEMPLATE Request for Proposals (RFP) For: [Title of RFP Project] Note: This sample is for a fabrication type of RFP. [RFP ID #] Issued: [Date] Submission deadline: [Time/Date]
Transformer Deluge Systems
Transformer Deluge Systems How Do Transformer Fires Ignite? Common causes of transformer failure: Weather-related events such as lightning Short circuits in electrical equipment The most common cause is
Project Implementation Guide for CT, PET/CT, X-Ray, and Nuclear Systems
GE Healthcare Project Implementation Guide for CT, PET/CT, X-Ray, and Nuclear Systems Working together to get your new technology online so you can begin providing patient care. Table of Contents Table
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES. Level III Content Outline
Fire Alarm Systems Level III Content Outline The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 3.1
GUIDELINES FOR AUGUST 1995
GUIDELINES FOR ELECTRICAL ENGINEERING SERVICES AUGUST 1995 PUBLISHED BY: PROFESSIONAL ENGINEERS AND GEOSCIENTISTS OF NEWFOUNDLAND & LABRADOR (PEGNL) P.O. Box 21207, St. John's, NL A1A 5B2 Telephone: (709)
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings. CPE Candidate No. 0714108. December 2014
How to Estimate the Cost of Interior Building Finishes from Schematic Drawings CPE Candidate No. 0714108 December 2014 1 How to Estimate the Cost of Interior Building Finishes from Schematic Drawings Table
ADDENDUM #2 FORMAL BID 2015-174
ADDENDUM #2 FORMAL BID 2015-174 KITSAP COUNTY PARKS DEPARTMENT LOBE FIELD IMPROVEMENTS PHASE 1 TO: FROM: All Respondents Colby Wattling, Buyer CLOSING DATE: December 16, 2015 at 3:00PM (UNCHANGED) REF
Core & Shell Construction. Rules and Regulations
Core & Shell Construction Rules and Regulations 1. Protection: During the construction Contractor shall endeavor to protect all areas of work from damage caused by workers, weather or equipment. 2. Permits
REQUEST FOR PROPOSAL FOR: Fire and Security Alarm Service and Monitoring
MCC13-04 REQUEST FOR PROPOSAL FOR: Fire and Security Alarm Service and Monitoring Manchester Community College PURPOSE: The purpose of this REQUEST FOR PROPOSAL is to establish a contract for Manchester
SECTION 28 05 00 COMMON WORK RESULTS FOR ELECTRONIC SAFETY AND SECURITY
SECTION 28 05 00 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specifications Sections, apply
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES www.nicet.org 888-476-4238. Fire Alarm Systems
Fire Alarm Systems Level IV Content Outline Standard Model/CBT The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
Construction Management Standards of Practice
Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388
All bidders shall indicate in their bid/proposal that this Addendum has been received and considered in their bid proposal.
Addendum #1 Fire Damage Repairs 4316 City View Terrace, Units A and B City View Terrace, OH5-13C, AMP 4 IFB #14-03 October 23, 2014 Greater Dayton Premier Management 400 Wayne Ave. Dayton, Ohio 45410 This
ST. MONICA FOOD PANTRY HOUSTON, TEXAS
PROJECT MANUAL FOR ST. MONICA FOOD PANTRY HOUSTON, TEXAS OWNER: ST. MONICA CATHOLIC CHURCH 8421 W. MONTGOMERY ROAD HOUSTON, TEXAS 77088 ARCHITECT: C SIX ARCHITECTURE, LLC 4606 F.M. 1960 WEST, STE 400 HOUSTON,
Attachment 5 Electrical Engineering
A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Design Consultant Project Management Requirements
Design Consultant Project Management Requirements Version 2 April 25, 2013 AWTP Program Design Consultant Contents 1.0 Introduction... 1 2.0 General Management... 1 3.0 Project Management Plan... 1 4.0
Global Supply Chain Security Recommendations
Global Supply Chain Security Recommendations These minimum security criteria are fundamentally designed to be the building blocks for foreign manufacturers to institute effective security practices designed
Alexandria National Cemetery SECTION 01 32 16.13 NETWORK ANALYSIS SCHEDULE
SECTION 01 32 16.13 PART 1 - GENERAL 1.1 DESCRIPTION: A. The Contractor shall develop a Microsoft Project 2003 (or latest version) Bar Chart schedule demonstrating fulfillment of the contract requirements.
TRANSBAY JOINT POWERS AUTHORITY
STAFF REPORT FOR CALENDAR ITEM NO.: 14 FOR THE MEETING OF: November 13, 2014 BRIEF DESCRIPTION: TRANSBAY JOINT POWERS AUTHORITY Amending Contract No. 08-04-CMGC-000, authorizing Webcor/Obayashi Joint Venture
COMMISSIONING OF FIRE ALARM SYSTEMS
COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference
KIEWIT CM/GC Enabling/Utilities
South Terminal Redevelopment Program KIEWIT CM/GC Enabling/Utilities Contract Value $50 million M/WBE Goal 20 percent Contact John Todd, LEED AP Project Manager 303.930.9046 [email protected] General
1. Is it required that each company that bids on this RFP be pre-registered or pre-qualified prior to bidding?
To: From: All Prospective Bidders Purchasing Department Date: September 9, 2015 Subject: Inquiries and Responses RFP#: Fixed A/V Maintenance/Repairs/Equipment Services 102-2015 Inquiries and Responses:
Wake County Public School System Rogers Lane Elementary School (E40) Raleigh, North Carolina INSTRUCTIONS TO BIDDERS
Wake County Public School System Rogers Lane Elementary School (E40) Raleigh, North Carolina INSTRUCTIONS TO BIDDERS General Information: The work includes the construction of a new three story elementary
STCC Contractor/Vendor Rules and Regulations
STCC Contractor/Vendor Rules and Regulations STCC maintains specific rules and regulations that apply to all contractors and vendors who perform work or provide services. It is the responsibility of the
ATLANTA PUBLIC SCHOOLS
Procurement Services 130 Trinity Avenue, S.W. 5 th Floor Atlanta, Georgia 30303 Request for Qualifications For October 31, 2007 Solicitation Number: 112607-01 Due Date: November 26, 2007 ADVERTISEMENT
Position Classification Standard for Procurement Clerical and Technician Series, GS-1106. Table of Contents
Position Classification Standard for Procurement Clerical and Technician Series, GS-1106 Table of Contents SERIES DEFINITION... 2 EXCLUSIONS... 2 DEFINITIONS... 3 OCCUPATIONAL INFORMATION... 3 TITLES...
Construction Project Scheduling: Keys to Success
View the online version at http://us.practicallaw.com/0-574-8625 Construction Project Scheduling: Keys to Success KELLY M. HEUER AND JAMES G. ZACK, JR., NAVIGANT CONSULTING, INC., WITH PRACTICAL LAW REAL
CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP)
Michigan Department Of Transportation 5100B (05/13) CHECKLIST TO DESIGNATE AREAS OF EVALUATION FOR REQUESTS FOR PROPOSAL (RFP) Page 1 of 2 REQUISITION NUMBER DUE DATE TIME DUE MDOT PROJECT MANAGER JOB
1 OF 7. there will be few "surprises" as the work progresses.
1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result
TruexCullins Architecture Fairfield Center School Bid Documents Kitchen and Bathroom Renovation March 1, 2015
Fairfield Center School Kitchen and Bathroom Renovation Project Specifications Owner: Fairfield Center School, 57 Park Street, Fairfield VT 05455 Franklin Central Supervisory Union, 28 Catherine Street,
See you soon in Scottsdale! December 6-7, 2016 Scottsdale, AZ. Exhibitor Package. 3rd Annual Vegetation Management Conference. www.ceati.
See you soon in Scottsdale! December 6-7, 2016 Scottsdale, AZ Exhibitor Package 3rd Annual Vegetation Management Conference www.ceati.com Tel: +1.514.866.5377 Fax: +1.514.904.5038 [email protected] www.ceati.com
May 29, 2012 Solicitation of quotations
RE CI OFN AL ADMINISTRATIVE CORPORATION JOSEPH P. BORT M ETROCENTER 101 EIGHTH STREET OAKLAND, CA 94607-4700 510/817.5700 TDDITTY 51 W81 7-5769 FAX 510/817.5848 vtetrnxiiitan Transportation (omnitssion
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES
MASTER AGREEMENT CONSTRUCTION MANAGEMENT SERVICES This Master Agreement made this 11 day of December, 2012, by and between the St. Lucie County School Board (hereinafter referred to as the School Board
ADDENDUM NO. 1. DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015
ADDENDUM NO. 1 DATE: February 10, 2015 INVITATION FOR BID: IFB K150015033 1801 Commerce Road Renovations Project DATED: February 9, 2015 RECEIPT DATE: March 17, 2015 at 2:30 p.m. OPENING DATE: March 18,
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION. PRESENTED BY: BAKANG MOENG [email protected]
TLHAMATSI AFRICA PROJECTS CONSTRUCTION MANAGEMENT PRESENTATION PRESENTED BY: BAKANG MOENG [email protected] CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process Contractual arrangement
NextGEN Project Managers
Presenter Ed Coffin Product Advisor/Product Trainer/Database Consultant ConEst Software Systems [email protected] www.conest.com Estimating and Project Management The link between a well built estimate
SECTION 807 PUMP STATION REHABILITATION
SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but
tips How smallchangescan saveyou big, &
warehousesafety tips How smallchangescan saveyou big preventaccidentsreduceinjuries, & increaseproductivity.. Table of Contents Welcome Statement...4 Safety Policy Statement...5 Guiding Principles...6
Mechanical Contractor Pre-Qualification Packet. SPSC N180 Computer Data Room Phase II. Project No. CP 159313. Notice No. Notice 13-11.
Mechanical Contractor Pre-Qualification Packet SPSC N180 Computer Data Room Phase II Project No. CP 159313 Notice No. Notice 13-11 Issued by Department of Facilities Management Delivery address: Research
THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM SHALL BECOME A PART OF THIS SOLICITATION. Amend Invitation to Bid 14-MC-2194 as follows:
Denver Public Schools Purchasing Department 1617 S. Acoma St. Denver, Colorado 80223 INVITATION TO BID 14-MC-2194 ADDENDUM NUMBER ONE January 24, 2014 THIS ADDENDUM MUST BE ACKNOWLEDGED. THIS ADDENDUM
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 REF. LOCATION DESCRIPTION OF CHANGE. Revised Scope of Work. Work tasks have been revised.
RFQ 00318348 NORTHSTAR AUDITING SERVICES ADDENDUM NO. 1 DATE PUBLISHED: MAY 18, 2016 TO ALL PROSPECTIVE SUBMITTERS: THE FOLLOWING CHANGES ARE MADE: REF. LOCATION DESCRIPTION OF CHANGE Attachment A Attachment
ADMINISTRATIVE PROCEDURES
ADMINISTRATIVE PROCEDURES FOR SMALL BUSINESS CONSTRUCTION CONTRACTS HARRISBURG, PENNSYLVANIA MAY 2014 EDITION DEPARTMENT OF GENERAL SERVICES BUREAU OF CONSTRUCTION ADMINISTRATIVE PROCEDURES TABLE OF CONTENTS
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE
REIMBURSEMENT PROCEDURE for FEMA PUBLIC ASSISTANCE Financial Assistance Availability The impact of major or catastrophic emergencies can exceed local financial resources. Financial aid and assistance may
MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
Construction Notification and Start-Up
The University of British Columbia Land and Building Services Prepared by: Frank Geyer Work Procedure Approved by: David Barnes Construction Notification and Start-Up Issue Date: 08 October 2002 Replaces:
Fire Alarm Systems Certification
Fire Alarm Systems Certification The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 2.1 Submittal Preparation
Grid Solutions. PROJECT MANAGEMENT SOLUTIONS for infrastructure projects from Border States. Border States
Border States Grid Solutions PROJECT MANAGEMENT SOLUTIONS for infrastructure projects from Border States Aging infrastructure, increased energy demands and emerging markets have fueled the growth of transmission,
Shawnee County ATTN: Bill Kroll 200 SE 7 th Street, Rm B-30 Topeka, KS 66603 Phone 785.251-4490 [email protected]
SECTION I Shawnee County is requesting qualifications/proposals for the renovation of 2600 SW East Circle Drive, Topeka, Kansas 66606 which will be utilized by the Shawnee County Health Agency per the
