Ninth Round PROJECT MONITORING, REPORTING, REVISION AND EXTENSION GUIDELINES
|
|
|
- Asher Pierce
- 10 years ago
- Views:
Transcription
1 Ninth Round PROJECT MONITORING, REPORTING, REVISION AND EXTENSION GUIDELINES For all reporting templates, please visit the UNDEF website: This document outlines monitoring, reporting, extension and revision guidelines for UNDEFfunded 9 th round projects. Reports submitted to UNDEF are considered to be part of the public domain (unless otherwise agreed) and as such may be shared with UNDEF s Programme Consultative Group, Advisory Board, or may be posted on the UNDEF s website. UNDEF will also use the reports submitted during the lifespan of the project to determine whether projects are making sufficient progress and to recommend adjustments to scope, implementation and funding as needed. All reports must be drafted in English or French, the two working languages of the UN Secretariat. 1. Project Management Arrangement The Civil Society Organization (CSO) receiving the grant bears all substantive, financial, monitoring and reporting responsibilities to UNDEF. The CSO is responsible for the overall management of the project. 2. Project Monitoring UNDEF projects are monitored in several ways: A. All Implementing Agencies for all projects must monitor their own activities. The Implementing Agency (IA) should use the indicators set in the Result Based Framework of the Project Document (PD) to monitor the project throughout its duration. If the IA is required to collect additional baseline date, they are required to do so as soon as possible. Furthermore, the data for the indicators will be used in the final evaluation of the project. B. UNDEF will appoint monitors to observe project milestones as detailed in the project document. C. In addition to the above, for all projects, UNDEF will monitor progress by way of review of mid-term and progress reports and will conduct ad-hoc monitoring visits of the project as needed. 3. Project Reporting The Implementing Agency must submit the following reports to UNDEF: i) Mid-Term Report, ii) Final Narrative Report and iii) Financial Utilization Reports. See Annex I for reporting timelines. Additionally, UNDEF may request ad hoc updates at any time throughout the duration of the project. 1
2 4. Monitoring and Reporting Requirements for CSOP Projects Templates for financial and narrative reporting can be found on the UNDEF website. Reports that do not use the correct template will not be accepted. 4.1 Milestone Reports and Financial Utilization Reports A. UNDEF will appoint an observer to monitor project milestones 2 and 3. This person or entity will bear no responsibility for any aspect of implementation of the project. In order to arrange for monitoring of project milestones as detailed in the disbursement schedule in the project document, the Implementing Agency must provide UNDEF with the logistical details of the milestone activity two months prior to its occurrence. Logistical details include dates, location, contact names, agenda and any accompanying materials. UNDEF will designate a monitor to attend the activity. The UNDEF-appointed monitor will contact the Implementing Agency directly to make final arrangements. The monitor will attend the activity, will take notes and photos, and will collect materials. The Implementing Agency should provide the monitor with necessary documents, such as the event agenda, signed list of participants, publications, brochures etc. The monitor will then compile the details from the monitoring activity and will submit to UNDEF a Milestone Verification Report (MVR). In some cases, UNDEF may decide to conduct a desk review of the milestone activity in lieu of sending monitors. In these cases, the Implementing Agency will be required to submit an MVR, photos of the activity and any additional accompanying materials. B. When the milestone activity has been completed, the Implementing Agency should submit to UNDEF a Milestone Financial Utilization Report (FUR), certified by the independent and external auditor indicated in the project document. These financial reports should be in the required UNDEF format and reflect the amount spent to date. The purpose of the FURs is to compare project expenditures against the project budget as agreed to in the signed project document. Please note that most of the previous tranche [e.g. 70%] must be spent before the next tranche is disbursed. Projects are required to attach a short explanation in cases where there has been a change in the funding schedule or budget allocation. UNDEF will review the FUR and will either approve the funding request or will revert to the project for further information or discussion. Changes to the approved project budget require prior UNDEF approval. Financial reallocations made without prior UNDEF approval will not be accepted, and the funds may have to be reimbursed to UNDEF. The Implementing Agency will be held responsible for over expenditures. *** The milestone activities chosen for the project as per the signed project document should correspond to when a new tranche of funds is needed. Therefore, the Implementing Agency is responsible for informing UNDEF as soon as possible of any changes in the milestone schedule, which in turn affects the disbursement of funds. *** 2
3 4.2 Mid-term Progress Report The Mid-term Progress Report must be submitted to UNDEF no later than 13 months from the project start date (as listed on the cover page of the signed project document). The report should include detailed information on the status of project implementation, including: the activities that have been completed and those in progress, an update on funds utilized, and the achievement of project outputs, outcomes and any unforeseen changes in the project as compared with the signed project document. The report should also justify any changes made to the implementation of the project as compared with the signed project document. UNDEF will use this report to determine whether the project is making sufficient progress and to gauge whether any adjustments in scope, activities or funding are warranted. The Mid-term Progress Report template is available on the UNDEF website. 4.3 Final Narrative Report The Implementing Agency is required to submit a Final Narrative Report one month after the completion of the project. The report must include detailed information on project implementation, describing the achievement of outputs and outcomes as agreed in the signed project document. The report should also justify any changes made to the implementation of the project as compared with the signed project document and should outline lessons learned and best practices. The Final Narrative Report template is available on the UNDEF website. 4.4 Final Financial Utilization Report A Final Financial Utilization Report, certified by the independent and external auditor identified in the project document, must be submitted no later than three months after the project end-date. This report must include all relevant financial details including expenditures and any income or interest earned. The Final Financial Utilization Report template is available on the UNDEF website. 4.5 End of Project Evaluation UNDEF is responsible for devising the final project evaluation modality, and will inform the Implementing Agency if a project evaluation is to be conducted. The Implementing Agency is required to take all necessary measures to facilitate evaluation as and when required by UNDEF or its designated third party. Should an evaluation be conducted, the final evaluation report may be published on the UNDEF website. The Implementing Agency is required to feature UNDEF as a donor in all outreach materials including banners, signs, all written materials and publications associated with the UNDEF-funded project, as well as on the Implementing Agency s website and publications resulting from the implementation of the UNDEF project. All presentation will include the UNDEF logo. Any acknowledgment should include the words ''The United Nations Democracy Fund''. 3
4 5. Project Revisions and Extensions 5.1 -Project Revisions A. Revisions that require prior approval from UNDEF: Changes to a project that affect its scope (outputs, outcomes and objectives), require a project substantive revision (see 5.2) approved by the UNDEF Office. Changes to the approved project budget (including financial reallocations) require prior UNDEF approval. The request should be made using the Budget Revision Request Form which is available on the website. These changes should also be mentioned both in the mid-term and final narrative reports sent to UNDEF. Financial reallocations made without prior UNDEF approval will not be accepted, and the funds may have to be reimbursed to UNDEF. B. Revisions that do not require prior approval from UNDEF Changes to a project that do not affect the scope of the project do not require a project revision approved by the UNDEF Office. For example, changes in activities to ensure achievement of an output do not require a project revision. While no specific approval procedure is required, these changes should be mentioned both in the mid-term and final narrative reports sent to UNDEF Substantive revisions Conditions A substantive revision involves a change either in the objective, outcomes or outputs of the project. Providing that the project remains relevant to the objectives of UNDEF and consistent with the project proposal, revisions can be made at any point during the project lifecycle under one of the following three circumstances: Procedure A) in response to changes in the national, regional or global context, B) to adjust the design and resource allocation to ensure the project operates effectively in a changing environment and/or C) to improve project design and/or implementation by clarifying objectives, adjusting results, indicators, assumptions and/or conditions, and adding or curtailing activities. Substantive project revisions result from a participatory process involving the key stakeholders. They may be prompted by project team deliberations, by reports from beneficiaries or by monitoring, evaluation or review activities. Where a project is not proceeding as planned, the Implementing Agency should discuss with all partners ways to improve project implementation. A revision document should then be drafted and signed by all signatories to the original signed project document 4
5 The revision document must describe changes made to relevant sections of the signed project document and must include: - a cover page with justification as to why the changes are wanted - a separate page which details changes in objectives, outputs, activities or inputs, by including new sections to replace old sections of the project document - a revised Results Framework and budget 5.3 Extension of Project Duration UNDEF prefers projects to be implemented in accordance with the timetable in the project document and will only consider "no cost" extensions in exceptional circumstances. In such cases, project extensions should be sought using the Project Extension Request Form which is available on the website. Such extensions do not entail changes in the overall budget. Please note that salary and support costs should not exceed the amounts allocated in the approved project budget. Extensions will be considered for the shortest justifiable timeframe, and in no circumstances will they exceed 12 months. Procedure In normal circumstances, project extensions need to be requested by the Implementing Agency after consultation with all project partners, at least two months before the initially foreseen project termination date. The form for requesting a project extension is available on the UNDEF website. In addition to the extension request form, an updated Results Framework should be enclosed clearly highlighting the activities already completed at the time of the request and the ones that will be implemented during the project extension. Depending on the duration of the extension, the reporting requirements to UNDEF might be affected and these new requirements will be notified upon approval of the extension request. For extensions of longer than 4 months, an extension status report should be provided to UNDEF half way through the extension period. This report should provide an update on the status of project implementation and disbursement of funds during the extension period, as per the revised Results Framework. This report should not exceed 3 pages. No specific template is required. 5
6 UNDEF REPORTING TIMETABLE Where applicable, templates for the reports mentioned below are available in the 7th Round section of the UNDEF website. All reports should be sent to the relevant UNDEF project officer, with a copy to [email protected]. Report Title Prepared By Submitted By/To Deadline Milestone Verification Report Milestone Financial Utilization Report (FUR) UNDEF-appointed monitor CSO and certified by the designated external auditor By UNDEFappointed monitor to UNDEF By CSO to UNDEF Following attendance of milestone activity Completion of each Milestone (#2 and #3) Mid-term Progress Report CSO By CSO to UNDEF 13 months after PSD (1) Final Narrative Report CSO By CSO to UNDEF 1 month after project end or 25 months after PSD (1) Final Financial Utilization Report (FFUR) CSO and certified by the designated external auditor By CSO to UNDEF 3 months after project end or 27 months after PSD (1) Evaluation Report Independent entity, or as decided by UNDEF in consultation with CSO By Independent entity to UNDEF, or as decided by UNDEF in consultation with CSO After submission of Final Narrative Report Extension Status Report (if applicable) CSO By CSO to UNDEF Halfway through extension period, for extensions longer than 4 months (1) The Project Start Date (PSD) is set by UNDEF according to the date of disbursement of 1 st tranche of funds to the CSO and is indicated on the cover page of the finalized Project Document. 6
PROJECT MONITORING, REPORTING, REVISION AND EXTENSION GUIDELINES
PROJECT MONITORING, REPORTING, REVISION AND EXTENSION GUIDELINES For all reporting templates, please visit the UNDEF website: http://www.un.org/democracyfund/information-grantees This document outlines
United Nations Democracy Fund Project Proposal Guidelines Eighth Round
United Nations Democracy Fund Project Proposal Guidelines Eighth Round 15 November 31 December 2013 Summary The present guidelines describe the application procedure for the Eighth Round of UNDEF grants.
Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme
Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland
URBACT III Programme Manual
URBACT III Programme Manual Fact Sheet 2E Network Management Table of contents Fact Sheet 2E 0. Introduction... 1 1. Roles and responsibilities of Lead and Project Partners... 2 2. The legal framework...
Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014
the European Economic Area (EEA) Financial Mechanism 2009-2014 adopted by the EEA Financial Mechanism Committee pursuant to Article 8.8 of Protocol 38b to the EEA Agreement on 13 January 2011 and confirmed
Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014
Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014 adopted by the Norwegian Ministry of Foreign Affairs pursuant to Article 8.8 of the Agreement between the Kingdom of Norway
South East Europe (SEE) Implementation Manual
South East Europe (SEE) Implementation Manual Version 5.0 Date of approval (v1.2): 8 th May 2009 1 st amendment (v2.1): 7th July 2009 2 nd amendment (v3.1): 21 st January 2011 3 rd amendment (v3.2): 27
URBACT III Programme Manual
URBACT III Programme Manual Fact Sheet 2A Action Planning Networks Table of contents Fact Sheet 2A 1. Main objectives and expected results... 1 2. Network s development... 2 3. Partnership... 3 4. Activities
How To Write Project Management Guidelines
Project Management Guidelines July 2013 FOREWORD I have pleasure to present these BDT Project Management Guidelines 2013 that now supersedes the April 2008 version. These Guidelines are drawn up in accordance
Guide for reporting, documentation of activities and financial management of grants, 2016
Nordplus Adult Guide for reporting, documentation of activities and financial management of grants, 2016 All beneficiaries of the Nordplus Adult programme must submit a final report to the programme administration
Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013
EUROPEAN COMMISSION European Social Fund Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013 Version of June 2015 Please consult http://ec.europa.eu/esf/sco
PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES
Applicants Manual for the period 2014 2020 Version 1 PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Disclaimer This document
Project Management Plan. Project Management Plan Guide. Strategic Capital, Infrastructure and Projects
Project Management Plan Guide A guide to completing the Project Management Plan Strategic Capital, Infrastructure and Projects Prepared by: Andrew Segrott / Strategic Capital, Infrastructure and Projects
United Nations Democracy Fund Project Proposal Guidelines Ninth Round
United Nations Democracy Fund Project Proposal Guidelines Ninth Round 15 November 31 December 2014 Summary The present guidelines describe the application procedure for the Eighth Round of UNDEF grants.
UNDP Programming Manual December 2000. Chapter 7: MONITORING, REPORTING AND EVALUATION Page 1
Chapter 7: MONITORING, REPORTING AND EVALUATION Page 1 Contents Page 7.0 MONITORING, REPORTING AND EVALUATION See the New M & E Framework. 7.1 Policy framework 7.1.1 General policy statements 7.1.2 Coverage
Guidance Note on Developing Terms of Reference (ToR) for Evaluations
Evaluation Guidance Note Series UNIFEM Evaluation Unit October 2009 Guidance Note on Developing Terms of Reference (ToR) for Evaluations Terms of Reference (ToR) What? Why? And How? These guidelines aim
NEPAD Climate Change Fund. Guidelines for applicants
NEPAD Climate Change Fund Guidelines for applicants 1 I. Introduction The NEPAD Climate Change Fund was established in 2014 by the NEPAD Planning and Coordinating Agency with support from the Government
Project Execution Guidelines for SESAR 2020 Exploratory Research
Project Execution Guidelines for SESAR 2020 Exploratory Research 04 June 2015 Edition 01.01.00 This document aims at providing guidance to consortia members on the way they are expected to fulfil the project
SCHEDULE 8 Generalist Project Services Framework 2015
SCHEDULE 8 Generalist Project Services Framework 2015 Nominal Insurer And Schedule 8 (Project Services Framework) Page: 1 of 6 Schedule 8 Generalist Project Services Framework Contents Overview... 3 1.
Due Process for the GRI Reporting Framework
Introduction 1. All documents in the GRI Framework must be developed in accordance with the due process principles approved by the GRI Board of Directors and outlined in this document. The Technical Advisory
Final Document. Title: IMDRF Standards Operating Procedures. Authoring Group: IMDRF Management Committee. Date: 17 December 2014
IMDRF/MC/N2FINAL:2014 (Edition 2) Final Document Title: Authoring Group: IMDRF Standards Operating Procedures IMDRF Management Committee Date: 17 December 2014 Jeff Shuren, IMDRF Chair This document was
A DRAFTER S GUIDE TO CABINET DOCUMENTS
A DRAFTER S GUIDE TO CABINET DOCUMENTS Privy Council Office 2013 A DRAFTER S GUIDE TO CABINET DOCUMENTS Table of Contents 1. Introduction...1 2. When an Item Should Be Brought to Cabinet...1 2.1 Regulations
Project reporting in FP6
Guidance notes for Integrated Projects, Networks of Excellence, Specific Targeted Research or Innovation Projects, Coordination Actions, Specific Support Actions, Co-operative Research Projects and Collective
NATIONAL TRAINING COURSES FOR SPORT ADMINISTRATORS
WORLD PROGRAMMES NOC MANAGEMENT NATIONAL TRAINING COURSES FOR SPORT ADMINISTRATORS Olympic Solidarity 2013-2016 World Programmes NATIONAL TRAINING COURSES FOR SPORT ADMINISTRATORS OBJECTIVE To offer to
Attachment A. Terms of Reference. 1. Background and Justification
Attachment A Terms of Reference 1. Background and Justification In 2011, UNESCO s 195 Member States approved a resolution during their 36th General Conference requesting the Organization to monitor, in
M&E/Learning Guidelines for IPs. (To be used for preparation of Concept Notes and Proposals to LIFT)
Published: 17 March 2015 Background M&E/Learning Guidelines for IPs (To be used for preparation of Concept Notes and Proposals to LIFT) LIFT's new strategy (2015-2018) envisions LIFT as a knowledge platform.
4 Project Implementation and Monitoring
4 Project Implementation and Monitoring Version 3, 29 July 2014 Contents 4. Implementation and Monitoring... 2 4.1 Project Implementation... 3 4.1.1 Setting up project implementation... 3 4.1.2 Development
Project Overview Project Title (in English): Project Title (in Chinese):
Project Overview Project Title (in English): Project Title (in Chinese): HKCAAVQ IT Infrastructure Development Project 香 港 學 術 及 職 業 資 歷 評 審 局 資 訊 系 統 基 建 (Phase 2) 發 展 項 目 ( 第 二 期 ) Executive Summary
EMPIR Reporting Guidelines Part 0 Guide to the parts
Part 0 Guide to the parts EMPIR Reporting Guidelines Part 0 Guide to the parts EURAMET MSU, Hampton Road, Teddington, Middlesex, TW11 0LW, UK Phone: +44 20 8943 6666 Email: [email protected] msu.euramet.org
GUIDANCE FOR COMPLETION OF THE ENHANCED FINANCIAL REPORTING TEMPLATE
GUIDANCE FOR COMPLETION OF THE ENHANCED FINANCIAL REPORTING TEMPLATE Version: November 2007 TABLE OF CONTENTS INTRODUCTION...3 REPORTING ON THE GRANT AS A WHOLE...4 REPORTING PERIODS AND TIMELINES...7
TEMPORARY JOB OPENING ANNOUNCEMENT
UNITED NATIONS NATIONS UNIES Ref. No.: TJO-2014- UNMEER New York Liaison Office-GTA-LO- P4-1 TEMPORARY JOB OPENING ANNOUNCEMENT P-4 Liaison Officer TJO Grade Level Functional Title Ebola Response Liaison
Identification. Preparation and formulation. Evaluation. Review and approval. Implementation. A. Phase 1: Project identification
II. Figure 5: 6 The project cycle can be explained in terms of five phases: identification, preparation and formulation, review and approval, implementation, and evaluation. Distinctions among these phases,
EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD ABDUCTION ALERT MECHANISMS SPECIFIC ACTION GRANTS
EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE Directorate A: Civil justice Unit A.4: Programme management SPECIFIC PROGRAMME "DAPHNE III (2007 2013) CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD
LOAN DISBURSEMENT HANDBOOK FOR IFAD DIRECTLY SUPERVISED PROJECTS
Version 1.01 LOAN DISBURSEMENT HANDBOOK FOR IFAD DIRECTLY SUPERVISED PROJECTS (when IFAD s General Conditions for Agricultural Development Financing apply) CONTENTS ACRONYMS...6 INTRODUCTION...7 1. BASIC
REPORT 2016/066 INTERNAL AUDIT DIVISION. Audit of management of technical cooperation projects in the Economic Commission for Africa
INTERNAL AUDIT DIVISION REPORT 2016/066 Audit of management of technical cooperation projects in the Economic Commission for Africa Overall results relating to the effective management of technical cooperation
Guidelines for the UN.GIFT Call for Proposals from Civil Society Organizations
Guidelines for the UN.GIFT Call for Proposals from Civil Society Organizations 1. INTRODUCTION... 3 1.1. Objective of the guidelines... 3 1.2. UN.GIFT... 3 1.3. UN.GIFT Small Grants Facility... 3 1.4.
INVITATION TO PRE-QUALIFICATION PROCESS FOR ROSTER OF CIVIL SOCIETY ORGANISATIONS IN THE FIELD OF EDUCATION, YOUTH LEADERSHIP AND EMPOWERMENT
INVITATION TO PRE-QUALIFICATION PROCESS FOR ROSTER OF CIVIL SOCIETY ORGANISATIONS IN THE FIELD OF EDUCATION, YOUTH LEADERSHIP AND EMPOWERMENT February 2015 COVERAGE: (opt) WEST BANK & GAZA STRIP United
Aid to make good the damage caused by natural disasters (Article 107(2)(b) TFEU) Checklist for Member States
EUROPEAN COMMISSION Competition DG Aid to make good the damage caused by natural disasters (Article 107(2)(b) TFEU) Checklist for Member States Document version: October 2013 Article 107(2)(b) of the Treaty
The Gavi grant management change process
The Gavi grant management change process Overall change process Frequently asked questions June 2015 1. How was it decided that grant management changes were needed? Over recent years, through a series
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION
REGULATORY ACCOUNTING GUIDELINES FOR TRINIDAD AND TOBAGO ELECTRICITY COMMISSION DRAFT FOR CONSULTATION January 2008 C O N T E N T S Page No. 1. Overview 1 2. Introduction 3 3. RIC s Regulatory Framework
TEMPORARY JOB OPENING ANNOUNCEMENT
UNITED NATIONS NATIONS UNIES Ref. No.: 2013/ICTY/REG/ FS/009-P TEMPORARY JOB OPENING ANNOUNCEMENT P-2 Finance Officer, Payroll and Disbursements TJO Grade Level 1 Functional Title Finance Section Department/Office/Division/
PARTICIPATORY SELF-EVALUATION REPORTS: GUIDELINES FOR PROJECT MANAGERS
PARTICIPATORY SELF-EVALUATION REPORTS: GUIDELINES FOR PROJECT MANAGERS 1 Table of Contents Background A. Criteria B. Definition C. Rationale D. Initiator E. Timing F. Planning G. Involvement of the Independent
INTERNATIONAL DEVELOPMENT COMMITTEE
INTERNATIONAL DEVELOPMENT COMMITTEE OF THE COUNCIL OF MINISTERS MULTI-YEAR GRANT APPLICATION GUIDANCE External Relations Division Government Office, Bucks Road Douglas, Isle of Man, IM1 3PN January 2015
Extractive Industries Transparency Initiative. Validation guide
Extractive Industries Transparency Initiative Validation guide Extractive Industries Transparency Initiative Validation guide Report of the EITI International Advisory Group Annex A: Validation guide Contents
Central Emergency Response Fund Guidelines
Central Emergency Response Fund Guidelines No Cost Extensions, Reprogramming and Redeployment of Funds 1 A. OVERVIEW For grants from the rapid response window, CERF funds must be expended and activities
MANUAL FOR THE EURO-HEALTHY
MANUAL FOR THE EURO-HEALTHY INTERNAL AND PERIODIC PROJECT MONITORING AND REPORTING Coimbra, May, 2015 EURO-HEALTHY project has received funding from the European Union s Horizon 2020 research and innovation
Financial Regulations and Rules of the United Nations
9 May 2003 United Nations Financial Regulations and Rules of the United Nations Secretary-General s bulletin 9 May 2003 United Nations Financial Regulations and Rules of the United Nations Secretary-General
Terms of Reference for Consultant to Support Development of Country Level Land Policy Issues Papers
Terms of Reference for Consultant to Support Development of Country Level Land Policy Issues Papers 1. Background The Australian Government is supporting the Organization of Eastern Caribbean States (OECS)
Monitoring, Evaluation and Learning Plan
Monitoring, Evaluation and Learning Plan Cap-Net International Network for Capacity Building in Sustainable Water Management November 2009 The purpose of this document is to improve learning from the Cap-Net
Terms of Reference. Title of Consultancy: UN Information Technology and Web Support Services and Training
Terms of Reference Title of Consultancy: UN Information Technology and Web Support Services and Training Unit Requesting : UN Resident Coordinator s Office Guyana Duration of : 6 months Background: The
Options for creating working groups, task forces and editorial boards to facilitate the implementation of the work plan. Note by the secretariat
Conference Room Paper 1 13 October 2014 ECONOMIC COMMISSION FOR EUROPE COMMITTEE ON ECONOMIC COOPERATION AND INTEGRATION Team of Specialists on Innovation and Competitiveness Policies Seventh session Geneva,
Template for essential information to be provided for proposals including clinical trials / studies / investigations
Template for essential information to be provided for proposals including clinical trials / studies / investigations Document history Version 2016callsV1 September 2015 Modifications (compared to previous
FINANCIAL AND ADMINISTRATIVE FRAMEWORK AGREEMENT. between. the EUROPEAN UNION represented by the EUROPEAN COMMISSION. and. the UNITED NATIONS
FINANCIAL AND ADMINISTRATIVE FRAMEWORK AGREEMENT between the EUROPEAN UNION represented by the EUROPEAN COMMISSION and the UNITED NATIONS Preamble The United Nations 1 (hereinafter referred to collectively
JOINT MANAGING AUTHORITY OF THE 2007-2013 ENPI CBC MEDITERRANEAN SEA BASIN PROGRAMME OPERATIONAL MANAGEMENT UNIT PUBLIC NOTICE
JOINT MANAGING AUTHORITY OF THE 2007-2013 ENPI CBC MEDITERRANEAN SEA BASIN PROGRAMME OPERATIONAL MANAGEMENT UNIT PUBLIC NOTICE for the constitution of a ranking list for the awarding of coordinated and
Communication - Terms of Reference Service contract
Communication - Terms of Reference Service contract Praia, Jun 2014 I. Organizational Context Under the guidance and direct supervision of the Communications Analyst the Communications the Communications
Resolution adopted by the General Assembly. [without reference to a Main Committee (A/65/L.78)] 65/281. Review of the Human Rights Council
United Nations A/RES/65/281 General Assembly Distr.: General 20 July 2011 Sixty-fifth session Agenda items 13 and 115 Resolution adopted by the General Assembly [without reference to a Main Committee (A/65/L.78)]
Resolution adopted by the Human Rights Council* 16/21 Review of the work and functioning of the Human Rights Council
United Nations General Assembly Distr.: General 12 April 2011 A/HRC/RES/16/21 Original: English Human Rights Council Sixteenth session Agenda item 1 Organizational and procedural matters Resolution adopted
TERMINAL EVALUATION TERMS OF REFERENCE
TERMINAL EVALUATION TERMS OF REFERENCE BASIC INFORMATON Location: Uganda Application Deadline: July 30 th, 2015 Type of Contract: Individual Contract Post Level: International Consultant Languages Required:
4.06 Consulting Services
MANAGEMENT BOARD SECRETARIAT AND MINISTRIES OF THE ENVIRONMENT, FINANCE, HEALTH AND LONG-TERM CARE, NATURAL RESOURCES, AND COMMUNITY SAFETY AND CORRECTIONAL SERVICES 4.06 Consulting Services (Follow-up
GUIDELINES FOR THE PREPARATION OF CONCEPT PAPERS FOR THE 7 TH TRANCHE OF THE DEVELOPMENT ACCOUNT (2008)
GUIDELINES FOR THE PREPARATION OF CONCEPT PAPERS FOR THE 7 TH TRANCHE OF THE DEVELOPMENT ACCOUNT (2008) These guidelines are designed to assist the entities of the Executive Committee on Economic and Social
Annex II: Terms of Reference for Management and Implementation Support Consultant (Firm)
Annex II: Terms of Reference for Management and Implementation Support Consultant (Firm) a. Background: 1. The GoB in accordance with its Public Financial Management (PFM) Strategy & Vision and Medium
Request for Proposals
Request for Proposals IOM invites potential Service Provider to provide Technical and Financial Proposals for the following Services: to develop and deliver a certified training in Leadership and Effectiveness
Accreditation of qualifications for registration as an oral health practitioner
Accreditation of qualifications for registration as an oral health practitioner Purpose Approved by the Dental Council: August 2005 Updated: May 2008 Governance Structure Update: 8 August 2011 Updated:
Islamic Republic of Afghanistan, Post Disaster Need Assessment (PDNA) Training Manual
Islamic Republic of Afghanistan, Ministry of Rural Rehabilitation and Development (MRRD) Ministry of Rural Rehabilitation & Development Post Disaster Need Assessment (PDNA) Training Manual Social Protection
b) Annex II: Proposal Submission Form, to be completed and returned with your proposal; and
Dear Sir/Madam, Subject: Request for Proposals for Translation Services: Project no. Multiple Proposal Ref: RE-RFP/12/002 1. The United Nations Office for Project Services (UNOPS) is seeking qualified
LSE Internal Audit procedures (to be read in conjunction with the attached flowchart)
LSE Internal Audit procedures (to be read in conjunction with the attached flowchart) Audit activity is governed by the HEFCE Code of Audit Practice. 1. Determining audit activity a) Audits will be conducted
Resources for Implementing the WWF Project & Programme Standards. Step 4.3 Analyze Operational and Financial Functions/ Performance
Resources for Implementing the WWF Project & Programme Standards Step 4.3 Analyze Operational and Financial Functions/ Performance March 2007 Step 4.3 Analyze Operational and Financial Performance Contents
Administrative forms (Part A) Project proposal (Part B)
Ref. Ares(2015)2346168-04/06/2015 Project Grants (HP-PJ) Administrative forms (Part A) Project proposal (Part B) Version 2.0 05 June 2015 Disclaimer This document is aimed at informing potential applicants
URBACT III OPERATIONAL PROGRAMME (2014-2020) CALL FOR PROPOSALS FOR THE CREATION OF 20 ACTION-PLANNING NETWORKS
URBACT III OPERATIONAL PROGRAMME (2014-2020) CALL FOR PROPOSALS FOR THE CREATION OF 20 ACTION-PLANNING NETWORKS Open 30 March 2015 16 June 2015 1 TABLE OF CONTENT INTRODUCTION... 3 SECTION 1 - ABOUT URBACT
Collaborative Computational Projects: Networking and Core Support
Collaborative Computational Projects: Networking and Core Support Call type: Invitation for proposals Closing date: 16:00 07 October 2014 Related themes: Engineering, ICT, Mathematical sciences, Physical
Certification Procedure of RSPO Supply Chain Audit
: 1 of 19 Table of Contents 1. Purpose 2. Scope 3. Unit of Certification 3.1 Identity Preserved, Segregation, Mass Balance, 3.2. Book and Claim 4. Definitions 5. Responsibilities 5.1 Head of the Certification
CHAPTER 12 14. CAMPAIGN DEVELOPMENT AND MANAGEMENT
14. CAMPAIGN DEVELOPMENT AND MANAGEMENT 14.1. What is a communication campaign? A communication campaign is defined as a connected series of operations designed to bring about a particular result (Kendall,
SPECIFIC PROGRAMME "CRIMINAL JUSTICE" (2007-2013) CALL FOR PROPOSALS JUST/2012/JPEN/AG/EJT Action grants
EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE SPECIFIC PROGRAMME "CRIMINAL JUSTICE" (2007-2013) CALL FOR PROPOSALS JUST/2012/JPEN/AG/EJT Action grants 1. INTRODUCTION On 12 February 2007, the Council
1. Background and Overview 1 1.1 Why the addendum? 1 1.2 How should this addendum be used? 1 1.3 Organization of the addendum 2
ADDENDUM june 2011 evaluation Updated guidance on EvalUAtion in the Handbook on Planning, Monitoring and EvalUAting for Development Results(2009) Table of Contents 1. Background and Overview 1 1.1 Why
VII. Monitoring and reporting
VII. Monitoring and ing Project monitoring and ing are essential com ponents of project management. The project coordinator and the project coordinator s supervisor are the principal beneficiaries of the
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
Key Considerations for MANAGING EVALUATIONS
Key Considerations for MANAGING EVALUATIONS Authors: (Brief Reference Guide) Dr. Rita Sonko, Addis Berhanu and Rodwell Shamu Pact South Africa June 2011 1 P age This publication is made possible by the
PROJECT MANAGEMENT PLAN HEKLA
MANAGEMENT PLAN HEKLA CONTENT 1. Introduction --------------------------------------------------------------------------- 0 2. Project organisation and management --------------------------------------------
Preparing and Refining a Research Proposal: Tips for Inexperienced Scientists
Preparing and Refining a Research Proposal: Tips for Inexperienced Scientists Topics Proposal format Strengthening elements Internal continuity Funding targets Know your donor Grantee ethics Never too
EUROPEAN COMMISSION Directorate-General for Research & Innovation. Guidelines on Data Management in Horizon 2020
EUROPEAN COMMISSION Directorate-General for Research & Innovation Guidelines on Data Management in Horizon 2020 Version 2.0 30 October 2015 1 Introduction In Horizon 2020 a limited and flexible pilot action
E Distribution: GENERAL RESOURCE, FINANCIAL AND BUDGETARY MATTERS. Agenda item 6 FINAL UPDATE ON THE WINGS II PROJECT.
Executive Board First Regular Session Rome, 8 11 February 2010 RESOURCE, FINANCIAL AND BUDGETARY MATTERS Agenda item 6 For information* FINAL UPDATE ON THE WINGS II PROJECT E Distribution: GENERAL WFP/EB.1/2010/6
2016 Home and Community-Based Services (HCBS) Scholarship Grant Program
2016 Home and Community-Based Services (HCBS) Scholarship Grant Program Application Guidelines Office of Rural Health & Primary Care The purpose of this document is to assist you in preparing an application
Business Plan Template for 2014-2020 Operations
Business Plan Template for 2014-2020 Operations Outline Guidance on Requirements for WEFO Assessment Page 1 of 27 Background Information for Applicants Please note: Key terms that have associated glossary
How To Monitor A Project
Module 4: Monitoring and Reporting 4-1 Module 4: Monitoring and Reporting 4-2 Module 4: Monitoring and Reporting TABLE OF CONTENTS 1. MONITORING... 3 1.1. WHY MONITOR?... 3 1.2. OPERATIONAL MONITORING...
Spillemyndigheden s Certification Programme Change Management Programme
SCP.06.00.EN.1.0 Table of contents Table of contents... 2 1 Objectives of the change management programme... 3 1.1 Scope of this document... 3 1.2 Version... 3 2 Certification... 4 2.1 Certification frequency...
1. Trustees annual report
1. Trustees annual report Accounting and reporting by charities Overview and the purpose of the trustees annual report 1.1. The primary purpose of the trustees annual report (the report) is to ensure that
Audit of UNESCO s Recruitment Process for International Staff
Internal Oversight Service Audit Section IOS/AUD/2015/07 Original: English Audit of UNESCO s Recruitment Process for International Staff September 2015 Auditors: Tuyet-Mai Grabiel Dawn Clemitson EXECUTIVE
OPERATING PROCEDURES OF THE BOARD AND COMMITTEES OF THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA. 20 November 2014 1
OPERATING PROCEDURES OF THE BOARD AND COMMITTEES OF THE GLOBAL FUND TO FIGHT AIDS, TUBERCULOSIS AND MALARIA 20 November 2014 1 1 These Operating Procedures, as approved on 21 November 2011 (GF/B25/DP7),
Financial management of the project, tools and reporting
Financial management of the project, tools and reporting Lead Partner Seminar 4th Call for Proposals Budapest, Hungary 11 December 2012 SEE Joint Technical Secretariat Financial management of the project,
BUDGET HEADING 04.03.01.06 INFORMATION, CONSULTATION AND PARTICIPATION OF REPRESENTATIVES OF UNDERTAKINGS CALL FOR PROPOSALS
EUROPEAN COMMISSION Employment, Social Affairs and Inclusion DG Employment and Social Legislation, Social Dialogue Labour Law BUDGET HEADING 04.03.01.06 INFORMATION, CONSULTATION AND PARTICIPATION OF REPRESENTATIVES
Guidelines for applicants
Funding for the development of products for the prevention, diagnosis and treatment of neglected and poverty related diseases 19 October 2015 Guidelines for applicants Please structure your application
D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E
D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E D 1.1 Document identifier: V-Must.net - D1.1 Definition of quality control procedure V.1.1 Due Date of Delivery to EC End of Month
Project Management: Trainee Guide Module 5 POST IMPLEMENTATION
200 Project Management: Trainee Guide Module 5 POST IMPLEMENTATION Bridges Social Development Project Management Training Program http://training.canadabridges.com 09/09/2009 PROJECT MANAGEMENT TRAINING
COMMISSION DECISION. of 10.7.2015
EUROPEAN COMMISSION Brussels, 10.7.2015 C(2015) 4806 final COMMISSION DECISION of 10.7.2015 setting up the High Level Group of Independent Experts on Monitoring Simplification for Beneficiaries of the
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Fund for Gender Equality MONITORING AND EVALUATION FRAMEWORK (2010-2013)
Fund for Gender Equality MONITORING AND EVALUATION FRAMEWORK (2010-2013) Prepared by Ana de Mendoza July 2010, revised March 2011 1 2 INDEX Page 0. Executive Summary 4 1. Introduction: Fund For Gender
Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.
Administrative + Management Aspects EU - Framework Programme 7 Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.2008 Dr. Jürgen Ertel Department Program Planing and Management Head of Project