C/KOSMOS Work Breakdown Structure Summary

Size: px
Start display at page:

Download "C/KOSMOS Work Breakdown Structure Summary"

Transcription

1 C/OSMOS Work Breakdown Structure Summary Version 2.3 January 13, 2011 Version Date Changes 1.8 November 19, 2009 Final version prior to issuing contract 1.9 December 8, 2009 Added documentation control to WBS dictionary under July 9, 2010 Modified mechanical elements to address parts common to multiple subsystems and fabrication management 1.11 July 14, 2010 Added 9.7 for misc. software and all hardware 2.0 August 5, 2010 Added elements for COSMOS and outlined revised account structure 2.1 August 25, 2010 Explicitly included CTIO computer hardware in December 17, 2010 Both CCD types included explicitly under WBS 8. Wording also acknowledges use of existing dewars for PNO and fabrication of dewars for CTIO 2.3 January 13, 2011 Clarified distribution of tasks under WBS 9 to conform to estimates and ICD 3.1 January 13, 2011 Page 1/18

2 OSMOS WBS V Purpose The purposes of the C/OSMOS Work Breakdown Structure (henceforth, OSMOS WBS) are to: Permit allocating and tracking a project-wide budget across project phases and participating institutions that will allow all interested parties visibility into project budget performance at any phase or level of the project. This includes separate reporting on COSMOS and OSMOS as needed. Permit management control of the project during all phases of the project. After the project is complete, permit one to understand what individual major subsystems and deliverables actually cost. 2. WBS Requirements The key requirements of the OSMOS WBS are as follows: Separate design study phase and fabrication phase. Combine design study and fabrication phases into a single integrated project to understand total project cost without interference (no re-use of WBS numbers across phases). Separate OSU and NOAO work packages, to understand budgets and actual costs of each work package, and sub-work packages assigned to each institution. Separate tasks on COSMOS and OSMOS where these are easily separable, and identify tasks where work is being done on both instruments simultaneously. For the purposes of this separation, all design work is considered as being associated with OSMOS Combine OSU and NOAO work packages into an integrated project to understand total project cost without interference (no re-use of WBS numbers across institutions). Take the WBS down to a level that provides adequate transparency into the project, but not overwhelming detail so that bookkeeping becomes the primary activity on the project, and uses more than the available digits in the allocated charge numbers. To the extent possible, the WBS should be human-readable and recognizable. Break down all of the work required to complete the project. Include all physical deliverables and their subsystems (but not necessarily as separate WBS elements). For each deliverable, include development, design, prototyping, fabrication, assembly, integration and acceptance testing leading to a deliverable product (but not necessarily as separate WBS elements). Include administration, system engineering, purchasing and reporting not directly tied to deliverable products. January 13, 2011 Page 2/18

3 OSMOS WBS V2.3 Organize work in a way to support delivery of "products", not by activities or engineering disciplines. January 13, 2011 Page 3/18

4 OSMOS WBS V OSMOS WBS The OSMOS Work Breakdown Structure (WBS) is as follows: 1. Project Management 1.1. OSMOS Planning and Reporting 1.2. OSMOS Internal Meetings 1.3. Reviews Design Study Review 1.4. COSMOS Planning and Reporting 1.5. COSMOS Internal Meetings 2. Science Team Activities 2.1. Science Requirements Document (SRD) 2.2. Operations Concept Document (OCD) 2.3. OSMOS Commissioning and Science Verification 2.4. COSMOS Commissioning and Science Verification 3. Systems Engineering 3.1. Functional and Performance Requirements Document (FPRD) 3.2. Interface Control Documents (ICDs) 3.3. OSMOS Acceptance Test Plan (ATP) 3.4. Performance Modeling 3.5. CTIO Design Issues 3.6. Safety 3.7. COSMOS Acceptance Test Plan (ATP) 4. Optics 4.1. Optics System Design 4.2. Optics Procurement Collimator Camera Dispersers Filters 5. Spectrograph Mechanical 5.1. Spectrograph Structure/Enclosure Design and Detailing Fabrication and Initial Assembly 5.2. Slit/Mask Wheel Design and Detailing Fabrication and Initial Assembly 5.3. Disperser Wheel Design and Detailing Fabrication and Initial Assembly 5.4. Filter Wheel Assembly Design and Detailing Fabrication and Initial Assembly 5.5. Collimator Focus January 13, 2011 Page 4/18

5 OSMOS WBS V Design and Detailing Fabrication and Initial Assembly 5.6. Camera Focus Design and Detailing Fabrication and Initial Assembly 5.7. Instrument Handling Design and Detailing Fabrication and Initial Assembly 5.8. Common Parts Design and Detailing Fabrication and Initial Assembly 5.9. Fabrication Management 6. Spectrograph Controls & Telemetry 6.1. Electronics 6.2. Software 6.3. Mechanical 7. Facility Modifications 7.1. Mayall Rotator/Guider 7.2. Mayall Calibration 7.3. Mayall Facility Handling 7.4. Blanco Rotator/Guider 7.5. Blanco Calibration 7.6. Blanco Facility Handling 8. Detector Systems 8.1. CCD Procurement 8.2. Controller Electronics 8.3. Controller Software 8.4. OSMOS Mechanical Dewar & Detector Mount Controller Mechanical 8.5. OSMOS Integration and Test 8.6. COSMOS Mechanical Dewar & Detector Mount Controller Mechanical 8.7. COSMOS Integration and Test 9. Top-Level Software 9.1. User Interface 9.2. Instrument Sequencer 9.3. Data Management 9.4. Detector Interface 9.5. Spectrograph Interface 9.6. Telescope Interface 9.7. Misc. Software & Hardware 9.8. CTIO Hardware & Software Modifications 10. Integration and Test OSMOS Lab Integration and Test January 13, 2011 Page 5/18

6 OSMOS WBS V OSMOS On-Site Integration and Test COSMOS Lab Integration and Test COSMOS On-Site Integration and Test 11. Shipping OSMOS Shipping COSMOS Shipping 12. Documentation and Training User and Operations Manual Service and Maintenance Manual PNO Training CTIO Training 13. Slit Mask Fabrication Mask Design Software Mask and Mask Fixture Mechanical Design and Fabrication CTIO mask fabrication modifications The (draft) WBS Dictionary is given as Appendix A. WBS numbers to be used for a schedule Gantt Chart would be formed by pre-pending either the letter D for the Design phase or the letter C for the Construction phase, followed by either the letter O for The Ohio State University or the letter N for NOAO, followed by two or three digits representing the WBS number from the list above. For example, to represent Operations Concept Document (2.2) work done at NOAO performed during the Design Study phase at NOAO, the WBS would be D.N.2.2. Optics design work done at OSU would be D.O.4.1. Procurement of filters would be C.O.4.2.4, assuming OSU does the procurement. The correspondence between WBS numbers and NOAO account numbers is given in Appendix B. WBS elements fall into 3 categories: work associated primarily or entirely with OSMOS, work associated primarily or entirely with COSMOS, and work associated roughly equally with both. Examples of the first would be integration and test or software development; examples of the third would be mechanical fabrication tasks or CCD procurement. Elements are identified in the final column of the Dictionary as, C, or B accordingly. January 13, 2011 Page 6/18

7 OSMOS WBS V2.3 Appendix A Draft WBS Dictionary WBS Element Definition C/ 1. Project Management All activities related to management of the project, including planning, reporting, formal reviews OSMOS Planning and Reporting 1.2. OSMOS Internal Meetings Preparation and updating of project schedules, budgets and related information. Efforts by engineers and scientists to prepare cost and schedule estimates. Progress reporting to funding agency and institutional management. Coordination meetings including travel. Documentation maintenance, including both internal and public websites. Does not include formal reviews. This element and 1.2 are active until OSMOS passes final acceptance (on-telescope) Internal coordination meetings with project staff. Does not include meeting related to specific tasks or issues, which should be covered under the specific WBS element. Coordination meetings involving both institutions are covered under Reviews Formal reviews, including both internal and external reviews. This element comprises preparation for such reviews as well as travel. The WBS structure allows for more than one formal review, although only one review has been identified at this point Final Design Review The final review will mark the end of the design study phase COSMOS Planning and Reporting 1.5. COSMOS Internal Meetings Preparation and updating of project schedules, budgets and related information. Efforts by engineers and scientists to prepare cost and schedule estimates. Progress reporting to funding agency and institutional management. Coordination meetings including travel. Documentation maintenance, including both internal and public websites. Does not include formal reviews. This element and 1.5 start when OSMOS passes final acceptance and run through the end of the project. Internal coordination meetings with project staff. Does not include meeting related to specific tasks or issues, which should be covered under the specific WBS element. Coordination meetings involving both institutions are covered under 1.4. C C January 13, 2011 Page 7/18

8 OSMOS WBS V2.3 WBS Element Definition C/ 2. Science Team Activities All activities by scientists that would not be considered system engineering or project management. These activities are not charged to ReSTAR funds Scientific Requirements Development and updates of the SRD. This WBS element also covers periodic Definition (SRD) briefing of NOAO and OSU scientific staff, as needed Operations Concept Development and revision of the OCD Document (OCD) 2.3. OSMOS Commissioning and Science Verification Planning and execution of OSMOS commissioning and science verification activities. This WBS element does not include personal research intended to result in scientific publications carried out as part of the commissioning and science 2.4. COSMOS Commissioning and Science Verification verification activities. Planning and execution of COSMOS commissioning and science verification activities. This WBS element does not include personal research intended to result in scientific publications carried out as part of the commissioning and science verification activities. 3. Systems Engineering All scientific and technical activities related to system engineering. The technical arm of project management Functional Performance Requirements Document (FPRD) Development and revision of the FPRD 3.2. OSMOS Interface Control Documents (ICDs) Identification, development and revision of top-level interface control documents, primarily those between sub-systems at level 1 of the WBS OSMOS Acceptance Test Plan (ATP) Development and revision of the ATP. This does not include execution of acceptance testing, which is included in Integration and Test (10) 3.4. Performance Modeling Modeling of system-level performance, potentially including throughput, guiding, and observing efficiency. Modeling efforts that fall within a single level 1 WBS element (for example, ray-tracing (falls under 4.1) or finite-element analysis of the spectrograph structure (falls under 5.1)) are not included. As an example, calculations of image degradation due to flexure would be included. C January 13, 2011 Page 8/18

9 OSMOS WBS V2.3 WBS Element Definition C/ 3.5. CTIO Design Issues This task includes documentation of differences between the Blanco and Mayall C telescope, and any efforts required to ensure that the OSMOS design can be adapted to the Blanco. CTIO-specific ICDs are included. These efforts may comprise a design capable of working at both telescopes without modification. Execution of design modifications is not included in this element as it is outside the scope of the OSMOS project Safety Development of safety plans and associated review or reviews B 3.7. COSMOS Acceptance Development and revision of the ATP. This does not include execution of C Test Plan (ATP) acceptance testing, which is included in Integration and Test (10) 4. Optics Design and procurement of optics 4.1. Optics System Design Design of the optics, including recommendations for procurement procedures and identification of critical components for early procurement 4.2. Optics Procurement Procurement of optics, including acceptance testing. Travel to vendors is included B if it is needed. Opto-mechanical assemblies procured as a unit are included. Installation of optics into mechanical assemblies and overall optical alignment are not included; these activities are included in Lab Integration and Test (10.1) Collimator Procurement and acceptance of collimator optics or opto-mechanical assembly Camera Procurement and acceptance of camera optics or opto-mechanical assembly Dispersers Procurement and acceptance of dispersers Filters Procurement and acceptance of filters 5. Spectrograph Mechanical Design and fabrication of the spectrograph mechanical subsystems, including interfaces to instrument electronics, the detector system and to the telescope. Activities not related to specific mechanisms or sub-systems would be charged to 5.1. Spectrograph Structure/Enclosure the top-level element, except as noted below under 5.8 and 5.9. Design and fabrication of the spectrograph enclosure and structure, including flexure analysis. Interfaces for mounting to the telescope and for mounting electronics enclosures, the detector system are included. Shutters are included. Provisions for cable routing and mounting of sensors are also included. January 13, 2011 Page 9/18

10 OSMOS WBS V2.3 WBS Element Definition C/ Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Slit/Mask Wheel Design and fabrication of the slit mask wheel. Software and fixturing for slit mask production is not included in this WBS element Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Disperser Wheel Design and fabrication of the disperser wheel Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Filter Wheel Assembly Design and fabrication of the filter wheel assembly Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Collimator Focus Design and fabrication of the collimator focus mechanism Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Camera Focus Design and fabrication of the camera focus mechanism Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication. January 13, 2011 Page 10/18

11 OSMOS WBS V2.3 WBS Element Definition C/ Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Instrument Handling Design and fabrication of all items related to instrument handling, including instrument cart, handling fixtures, and any permanent shipping crate or fixtures. Items intended to one-time use are not included, and are instead under Shipping (11) Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication Fabrication and Initial Fabrication of parts, initial assembly and re-work. Shipping costs to site of final B Assembly integration, if required. Assembly as part of final integration is not included Common Parts Design and Fabrication of parts used in more than one sub-assembly. Design work is included only if it is performed separately from the design of the sub-assemblies Design and Detailing Design and detailing resulting in production of drawings and solid models suitable for fabrication and costing of fabrication, subject to the note on design under Fabrication and Initial Fabrication of parts. Initial assembly and re-work and shipping costs to site of final B Assembly integration, if required, are included under the WBS elements for the individual sub-assemblies of which these parts are components. Assembly as part of final integration is not included Fabrication Management Management of work-flow in shop, including inventory control. Labor for purchasing materials and components. Designer labor required to manage drawings, including additional detailing as needed. Costs of small parts, raw materials, consumable tooling and other items that may be used in fabricating items under more than one WBS element. B 6. Spectrograph Controls & Telemetry Design and fabrication of electronics and associated software for control of the spectrograph mechanisms and any required telemetry. This element does not include motors or limit switches that are included within the elements for specific mechanisms Electronics Design, fabrication and/or procurement of control electronics, including sensors B 6.2. Software Design and coding of control software B January 13, 2011 Page 11/18

12 OSMOS WBS V2.3 WBS Element Definition C/ 6.3. Mechanical Design and fabrication of electronics enclosures and installation of electronics B components in enclosures. This tasks does not include integration of electronics into the instrument, which is covered under Lab Integration and Test (10.1) 7. Facility Modifications Design and fabrication of modifications to the Mayall and Blanco telescopes and buildings required for efficient operation of the instrument Mayall Rotator/Guider Design and fabrication of modifications to the Mayall rotator/guider, including TV cameras, guide probes, and ADC. The scope of these will be determined during the design phase and this WBS element may be expanded if necessary Mayall Calibration Design and fabrication of modifications to the Mayall calibration systems, including both those on the rotator/guider and the "white spot" Mayall Facility Design and fabrication of modifications to Mayall facility handling capabilities, Handling including modifications to the Cassegrain cage and provisions for liquid nitrogen fill, if needed Blanco Rotator/Guider Design and fabrication of modifications to the Blanco rotator/guider, including TV B cameras, guide probes, and ADC. The scope of these will be determined during the design phase and this WBS element may be expanded if necessary Blanco Calibration Design and fabrication of modifications to the Blanco calibration systems, B 7.6. Blanco Facility Handling including both those on the rotator/guider and the "white spot". Design and fabrication of modifications to Blanco facility handling capabilities, including modifications to the Cassegrain cage and provisions for liquid nitrogen fill, if needed. 8. Detector Systems Design, fabrication and procurement of the CCD detectors and their controllers and dewars. Integration and test of the detector systems is included, but integration of the detector systems into the instruments is not (it is included in Lab Integration and Test (10.1) CCD Procurement Specification, procurement and acceptance of the e2v and LBNL CCDs B 8.2. Controller Electronics Fabrication of the controller electronics for all CCDs. It is assumed that no design effort is needed. B B January 13, 2011 Page 12/18

13 OSMOS WBS V2.3 WBS Element Definition C/ 8.3. Controller Software Implementation of the standard controller software according to the characteristics B of the CCD procured. It is assumed that no software development is required OSMOS Mechanical Design and fabrication of OSMOS mechanical hardware, including dewar modifications and electronics enclosures, for both OSMOS CCDs OSMOS Dewar & Detector Mount Design and fabrication of the OSMOS detector mounts. Modification, refurbishment and acceptance of the dewars is included OSMOS Controller Fabrication of OSMOS CCD electronics enclosures and mounting hardware Mechanical 8.5. OSMOS Integration Integration of OSMOS detector systems, including mechanical integration of and Test dewar, detector, and controller, acceptance testing and shipping to final integration site COSMOS Mechanical Design and fabrication of COSMOS mechanical hardware, including the dewars C and electronics enclosures, for both COSMOS CCDs COSMOS Dewar & Detector Mount Design and fabrication of the COSMOS detector mounts and fabrication of the dewars COSMOS Controller Fabrication of COSMOS electronics enclosures and mounting hardware Mechanical 8.7. COSMOS Integration and Test Integration of COSMOS detector systems, including mechanical integration of dewar, detector, and controller, acceptance testing and shipping to final integration site. 9. Top-Level Software Software and interfaces not associated with specific sub-systems. Integration of the top-level software and associated computer hardware with the instrument and facility is covered under Integration and Test (10) User Interface Design and coding of the user interface. This element includes software associated with tasks such as field acquisition and any provisions for defining sequences of observations. Specific elements included comprise NGUI and related IRAF scripts. C January 13, 2011 Page 13/18

14 OSMOS WBS V2.3 WBS Element Definition C/ 9.2. Instrument Sequencer Design and coding of software to coordinate commands or sequences of commands to mechanisms, detector, telescope, and data storage. Efforts related to the architecture and overall design of the top-level software should be charged to this WBS element. Specific elements included comprise NOCS updates Data Management Design and coding of software for storing data according to observatory requirements. Specific elements included comprise NOHS, DHS and keyword translation updates. Archiving updates are also included Detector Interface Design and coding of software to interface to the detector system. Specific elements included comprise NMSL (Monsoon) updates and implementation with a Torrent controller Spectrograph Interface Design and coding of software to interface to the spectrograph control electronics and software. Specific elements included comprise NOCS, all GWC work, and interfacing with the OSU IebUtils library Telescope Interface Design and coding of software to interface to the telescope control system. Specific tasks included comprise NTCS Misc. Software and Hardware Design and coding of any software not included in elements Specification and purchase of computer hardware needed to develop and operate the software with the instrument. Configuration of computer hardware. System-level software testing prior to shipment to OSU is also included. Shipping of computer hardware to OSU for integration and test is included, but integration and test of the hardware 9.8. CTIO Hardware & Software Modifications with the instrument is covered under Integration and Test (10). Modification of the software as needed for operation on the Blanco telescope. Additional hardware required for COSMOS is included, including configuration of the hardware. System-level pre-ship software testing is also included. Development or test efforts that are primarily related to OSMOS, but are carried out using the COSMOS hardware, should be charged to the appropriate OSMOS-related element and not to 9.8. C January 13, 2011 Page 14/18

15 OSMOS WBS V2.3 WBS Element Definition C/ 10. Integration and Test The element includes all tasks associated with integration and test of the instrument, through final acceptance testing on the telescope. Cross-training required to carry out integration and test (for example, training of OSU staff regarding the detector controller) is not covered under this element, and is covered under Training (12.3) OSMOS Lab Integration and Test Integration of OSMOS sub-systems, testing, and re-work carried out in the laboratory. Pre-ship acceptance testing is included, but not development of the test OSMOS On-Site Integration and Test COSMOS Lab Integration and Test COSMOS On-Site Integration and Test plan. Integration of the LBNL CCD system is expected to occur on-site, under 10.2 Integration of the OSMOS instrument with the telescope, testing and rework. Final acceptance testing is included, but not development of the test plan. Commissioning and science verification are not included and should generally follow completion of the final acceptance testing. Integration of COSMOS sub-systems, testing, and re-work carried out in the laboratory. Pre-ship acceptance testing is included, but not development of the test plan. Integration of the LBNL CCD system is expected to occur on-site, under 10.4 Integration of the COSMOS instrument with the telescope, testing and rework. Final acceptance testing is included, but not development of the test plan. Commissioning and science verification are not included and should generally follow completion of the final acceptance testing. 11. Shipping Shipping of the instrument from the laboratory integration site to the telescope. Design and fabrication of single-use shipping crates and procurement of disposable packing materials is also included. Fixtures and crates intended for re-use are included under Instrument Handling (5.7) OSMOS Shipping OSMOS shipping, as described in (11.) COSMOS Shipping COSMOS shipping, as described in (11.) Includes export licenses as required. C 12. Documentation and Training Development of manuals and similar high-level documentation. Training of observatory personnel in the operation and servicing of the instrument. Crosstraining of project personnel. C C January 13, 2011 Page 15/18

16 OSMOS WBS V2.3 WBS Element Definition C/ User and Operations Development of a manual for the scientific user of the instrument and for the Manual observatory staff. May or may not be a single manual Service and Development of a manual for observatory staff describing maintenance and service Maintenance Manual of the instrument. The manual should cover minor repairs but will not cover repairs requiring intervention of the original development team PNO Training Training of PNO observatory staff and cross-training of project staff. Training may take place prior to and during integration and test or may occur during periods dedicated to training CTIO Training Training of CTIO observatory staff and cross-training of project staff. Training may C take place prior to and during integration and test or may occur during periods dedicated to training. Some CTIO training may take place at PNO. 13. Slit Mask Fabrication Tasks in support of design and fabrication of multi-object slit masks Mask Design Software Development or adaptation of mask design software to allow fabrication of masks from user-supplied coordinates. This task includes all software from the user interface down to the control files supplied to the mask-cutting machine. Verification of the fabrication process is also included Mask and Mask Fixture Mechanical Design and Fabrication CTIO Mask Fabrication Modifications Design and fabrication of fixturing for mask fabrication. Procurement of mask blanks sufficient for all activities through commissioning and science verification. Mask fabrication will be charged to the specific activity for which the masks are being made. Modifications to OSMOS software to allow fabrications of masks as CTIO, or modifications to CTIO software to allow fabrication of masks for COSMOS. Includes design and fabrication of fixtures and additional mask blanks required for all activities through commissioning and science verification. Mask fabrication will be charged to the specific activity for which the masks are being made. C January 13, 2011 Page 16/18

17 OSMOS WBS V2.3 Appendix B NOAO Account Numbers NOAO will have 2 sets of account numbers, corresponding to activities funded from the NSTC base budget and activities funded from the ReSTAR award. The former begin with N-MR11x and comprise everything under WBS 2; the latter begin with N-MR21x and comprise everything else. The letter x is replaced by 0 for OSMOS activities, by 1 for COSMOS activities, and by 2 for combined activities. Accounts will be created and closed as needed according to the following scheme: The first, third, and fourth digits of the WBS number define the last 3 digits of the charge number. For example, a scientist working on the Science Requirements Definition under WBS D.N.2.1 would be charging to N-MR110-D21. Charge accounts will not extend below the second level so (for example) all Detector System Mechanical design phase activities would be charged to N-MR210-D84. WBS elements 10, 11, 12 etc., will correspond to A, B, C, etc. We will produce a list of charge accounts and titles so people do not have to go through this exercise when filling out their time cards (see tentative list at end). When the project cost is estimated from individual task sheets, which will be used to generate a schedule, we will often have multiple tasks for the lowest level of the WBS and certainly for the lowest level of the account structure. This is normal, and to be expected. The WBS implies a total of almost 100 accounts, plus division into design and construction phases, although not all of these will be active at any one time, and not all accounts will be needed at either institution. Furthermore, any one person is likely to charge only a fraction of the accounts as their contribution to the project. Initial NOAO Design Phase Account Numbers: Account WBS Title N-MR110-D21 D.N.2.1 OSMOS SRD N-MR110-D22 D.N.2.2 OSMOS OCD N-MR210-D11 D.N.1.1 OSMOS PM Planning N-MR210-D12 D.N.1.2 OSMOS PM Meetings N-MR210-D31 D.N.3.1 OSMOS FPRD N-MR210-D32 D.N.3.2 OSMOS ICDs N-MR210-D34 D.N.3.4 OSMOS Performance N-MR210-D71 D.N.7.1 Mayall Rotator/Guider N-MR210-D72 D.N.7.2 Mayall Calibration N-MR210-D73 D.N.7.3 OSMOS Fac Handling N-MR210-D81 D.N.8.1 OSMOS CCD Procurement N-MR210-D91 D.N.9.1 OSMOS User Interface N-MR210-D92 D.N.9.2 OSMOS Inst Sequencer January 13, 2011 Page 17/18

18 OSMOS WBS V2.3 N-MR210-D93 D.N.9.3 OSMOS Data Management N-MR210-D94 D.N.9.4 OSMOS Detector Interface N-MR210-D95 D.N.9.5 OSMOS Spectrograph Interface N-MR210-D96 D.N.9.6 OSMOS Telescope Interface This listing is provisional; in particular, some of the D9x accounts may not be needed. Examples of construction phase accounts: N-MR110-C23 C.N.2.3 OSMOS Commissioning and Science Verification N-MR111-C24 C.N.2.4 COSMOS Commissioning and Science Verification N-MR212-C54 C.N Filter Wheel Assembly Fabrication N-MR210-C73 C.N.7.3 Mayall Facility Handling N-MR211-C76 C.N.7.6 Blanco Facility Handling N-MR212-C81 C.N.8.1 CCD Procurement January 13, 2011 Page 18/18

System Engineering Plan

System Engineering Plan Project Documentation Document SPEC-0064 Revision A System Engineering Plan Rob Hubbard, Jeremy Wagner, Larry Daggert, Larry Stepp, Christoph Keller Systems Engineering / Project Management 5 October 2006

More information

STATEMENT OF WORK FOR DESIGN, FABRICATION, INTEGRATION AND TESTING OF THE TELESCOPE STRUCTURE SYSTEM TMT.STR.MGT.12.001.REL01

STATEMENT OF WORK FOR DESIGN, FABRICATION, INTEGRATION AND TESTING OF THE TELESCOPE STRUCTURE SYSTEM TMT.STR.MGT.12.001.REL01 STATEMENT OF WORK FOR DESIGN, FABRICATION, INTEGRATION AND TESTING OF THE TELESCOPE STRUCTURE SYSTEM TMT.STR.MGT.12.001.REL01 27 July, 2012 TMT.STR.TEC.12.001.DRF01 Page 2 of 13 Table of Contents 1. INTRODUCTION

More information

GENI Work Breakdown Structure

GENI Work Breakdown Structure GENI Work Breakdown Structure GDD-06-29 GENI: Global Environment for Network Innovations September 15, 2006 Status: Draft (Version 1.0A) Note to the Reader: This document was prepared as a template for

More information

Space Flight Project Work Breakdown Structure

Space Flight Project Work Breakdown Structure APPENDIX G. (WBS) Space Flight Project Work Breakdown Structure G.1 Introduction G.1.1 The Project Work Breakdown Structure (WBS) is a key element of project management. The purpose of a WBS is to divide

More information

How to buy a telescope for your institution

How to buy a telescope for your institution How to buy a telescope for your institution by Dr. Frank Melsheimer DFM Engineering, Inc. 1035 Delaware Avenue Longmont, Colorado 80501 phone 303-678-8143 fax 303-772-9411 www.dfmengineering.com Table

More information

What methods are used to conduct testing?

What methods are used to conduct testing? What is testing? Testing is the practice of making objective judgments regarding the extent to which the system (device) meets, exceeds or fails to meet stated objectives What the purpose of testing? There

More information

Applying CMMI SM In Information Technology Organizations SEPG 2003

Applying CMMI SM In Information Technology Organizations SEPG 2003 Applying CMMI SM In Information Technology Organizations Mark Servello, Vice President Jim Gibson, Senior Consultant ChangeBridge, Incorporated Page 1 Portions Copyright 2002 Carnegie Mellon University

More information

GENERAL SERVICES ADMINISTRATION Federal Supply Schedule Authorized Federal Supply Schedule

GENERAL SERVICES ADMINISTRATION Federal Supply Schedule Authorized Federal Supply Schedule GENERAL SERVICES ADMINISTRATION Federal Supply Schedule Authorized Federal Supply Schedule On line access to contract ordering information, terms and conditions, up-to-date pricing, and the option to create

More information

Appendix 2-A. Application and System Development Requirements

Appendix 2-A. Application and System Development Requirements Appendix 2-A. Application and System Development Requirements Introduction AHRQ has set up a Distributed Systems Engineering Lab (DSEL) to support all internal development efforts and provide a facility

More information

GSA SCHEDULE: PROFESSIONAL ENGINEERING SERVICES (PES) - FSC GROUP 871 CONTRACT # - GS-10F-0254U

GSA SCHEDULE: PROFESSIONAL ENGINEERING SERVICES (PES) - FSC GROUP 871 CONTRACT # - GS-10F-0254U GSA SCHEDULE: (PES) - FSC GROUP 871 CONTRACT # - GENERAL SERVICES ADMINISTRATION Federal Supply Service Authorized Federal Supply Schedule Price List On-line access to contract ordering information, terms

More information

DESIGN AND INTEGRATION OF EQUIPMENT. (B) Process Flow Guideline

DESIGN AND INTEGRATION OF EQUIPMENT. (B) Process Flow Guideline LLE INSTRUCTION 7700H LLEINST 7700H SUBJECT: APPENDIX: DESIGN AND INTEGRATION OF EQUIPMENT (A) List of Acronyms (B) Process Flow Guideline ENCLOSURES: 1. Equipment Qualification Checklist (EQC) 2. Project

More information

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >

PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name

More information

RTP s NUCLEAR QUALITY ASSURANCE PROGRAM

RTP s NUCLEAR QUALITY ASSURANCE PROGRAM RTP s NUCLEAR QUALITY ASSURANCE PROGRAM RTP operates under one quality program, whether you purchase products that are commercial grade, nuclear safety-related or industrial safety compliant (IEC 61508).

More information

custom software, mobile apps, web design, and network support

custom software, mobile apps, web design, and network support custom software, mobile apps, web design, and network support Spud Software 9468 S. Saginaw Rd. Grand Blanc, MI 48439 Phone: 810.695.0001 Fax: 810.695.4004 President Derek Sommer Phone: 810.771.2124 Fax:

More information

Re: RFP # 08-X-39202 MOTOR VEHICLE AUTOMATED TRANSACTION SYSTEM (MATRX) FOR MVC ADDENDUM #10

Re: RFP # 08-X-39202 MOTOR VEHICLE AUTOMATED TRANSACTION SYSTEM (MATRX) FOR MVC ADDENDUM #10 State of New Jersey DEPARTMENT OF THE TREASURY JON S. CORZINE DIVISION OF PURCHASE AND PROPERTY BRADLEY I. ABELOW Governor PURCHASE BUREAU State Treasurer P.O. BOX 230 TRENTON, NEW JERSEY 08625-0230 September

More information

Introduction to CCDs and CCD Data Calibration

Introduction to CCDs and CCD Data Calibration Introduction to CCDs and CCD Data Calibration Dr. William Welsh San Diego State University CCD: charge coupled devices integrated circuit silicon chips that can record optical (and X-ray) light pixel =

More information

IBM RFID for Supply Chain and Logistics: Reusable Asset Tracking solution

IBM RFID for Supply Chain and Logistics: Reusable Asset Tracking solution IBM Sensor Solutions IBM RFID for Supply Chain and Logistics: Reusable Asset Tracking solution Highlights Transforms your supply chain by automating and error-proofing business processes Provides real-time

More information

Q2A First Article Inspection (FAI) AS9102 * Revised ** Added

Q2A First Article Inspection (FAI) AS9102 * Revised ** Added Page 1 of 5 Q2A First Article Inspection (FAI) AS9102 * Revised ** Added NOTE: A hard copy of this document may not be the document currently in effect. The current version is always the version on the

More information

6500m HOV Project Stage 1: A-4500 HOV

6500m HOV Project Stage 1: A-4500 HOV 6500m HOV Project Stage 1: A-4500 HOV Systems Engineering, Integration & Testing Plan Document Control No.: 0000000 01-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control

More information

Project Cost Guidelines

Project Cost Guidelines Project Cost Guidelines Bonneville Power Administration Energy Smart Industrial Program Developed by the Energy Smart Industrial Quality Assurance Team Revision 12.0 (revised: Q2 2014) Disclaimer: The

More information

Federal Aviation Administration Standard Work Breakdown Structure (WBS) Version 3.1

Federal Aviation Administration Standard Work Breakdown Structure (WBS) Version 3.1 Federal Aviation Administration Standard Work Breakdown Structure (WBS) Version 3.1 July, 2003 Page Intentionally Left Blank INTRODUCTION This Federal Aviation Administration (FAA) Standard Work Breakdown

More information

APPENDIX 25 CONTRACT DEFINITIONS

APPENDIX 25 CONTRACT DEFINITIONS APPENDIX 25 CONTRACT DEFINITIONS SOFTWARE AGREEMENT: Capitalized terms used in this Agreement will have the following meanings: 1. Acceptance Tests - Those tests described in the Contract Sections 12a,

More information

MEDFORD FABRICATION CSC, INC. Quality System Manual. Date of issue: 03/25/2010 Revision : F

MEDFORD FABRICATION CSC, INC. Quality System Manual. Date of issue: 03/25/2010 Revision : F MEDFORD FABRICATION CSC, INC Quality System Manual Date of issue: 03/25/2010 Revision : F Table of Contents System Description 1.0 Introduction 2.0 Company Quality Policy 3.0 Organization Charts 4.0 Quality

More information

Cost-effective supply chains: Optimizing product development through integrated design and sourcing

Cost-effective supply chains: Optimizing product development through integrated design and sourcing Cost-effective supply chains: Optimizing product development through integrated design and sourcing White Paper Robert McCarthy, Jr., associate partner, Supply Chain Strategy Page 2 Page 3 Contents 3 Business

More information

Product Development and Commercialization Lifecycle

Product Development and Commercialization Lifecycle Product Development and Commercialization Lifecycle TM Product Development Life Cycle Definition Phase TM 1. Product Alignment with Company Strategy and Roadmap 2. Competitive Analysis Lessons/feedback

More information

Introduction and Overview

Introduction and Overview Introduction and Overview Definitions. The general design process. A context for design: the waterfall model; reviews and documents. Some size factors. Quality and productivity factors. Material from:

More information

Program/Project Management Series Work Breakdown Structure Reference Guide

Program/Project Management Series Work Breakdown Structure Reference Guide Program/Project Management Series Work Breakdown Structure Reference Guide National Aeronautics and Space Administration May 1994 2 Work Breakdown Structure Reference Guide May 1994 Table of Contents Chapter

More information

Overview of the System Engineering Process. Prepared by

Overview of the System Engineering Process. Prepared by Overview of the System Engineering Process Prepared by Ed Ryen, PE Maintenance ITS March 2008 Introduction This document provides a high level look at the Systems Engineering Process for ITS projects.

More information

Quality Assurance Provisions

Quality Assurance Provisions Page 1 of 5 1. Purpose and Scope. The purpose of this document is to define the Quality Assurance Provisions FLIR Systems Inc. requires for inventory material received from Suppliers. This document applies

More information

Project Management Planning

Project Management Planning Develop Project Tasks One of the most important parts of a project planning process is the definition of activities that will be undertaken as part of the project. Activity sequencing involves dividing

More information

Application Example: Quality Control of Injection-Molded Parts

Application Example: Quality Control of Injection-Molded Parts Application Example: Quality Control of Injection-Molded Parts Measuring Systems: ATOS Keywords: Optical 3D measuring technology, mold try-out, first article inspection, form and dimension inspection of

More information

Goddard Procedures and Guidelines

Goddard Procedures and Guidelines Goddard Procedures and Guidelines DIRECTIVE NO. APPROVED BY Signature: Original signed by NAME: A. V. Diaz TITLE: Director Responsible Office: Title: Code 300 / Office of Systems Safety and Mission Assurance,

More information

IDC Reengineering Phase 2 & 3 US Industry Standard Cost Estimate Summary

IDC Reengineering Phase 2 & 3 US Industry Standard Cost Estimate Summary SANDIA REPORT SAND2015-20815X Unlimited Release January 2015 IDC Reengineering Phase 2 & 3 US Industry Standard Cost Estimate Summary Version 1.0 James Mark Harris, Robert M. Huelskamp Prepared by Sandia

More information

Spectral Measurement Solutions for Industry and Research

Spectral Measurement Solutions for Industry and Research Spectral Measurement Solutions for Industry and Research Hamamatsu Photonics offers a comprehensive range of products for spectroscopic applications, covering the, Visible and Infrared regions for Industrial,

More information

Title: Material Tracking in a Food Factory

Title: Material Tracking in a Food Factory Title: Material Tracking in a Food Factory Author: James T. Luxhoj, Ph.D. Department of Industrial Engineering Rutgers University P.O. Box 909 Piscataway, New Jersey 08855-0909 Warning: This document may

More information

Quality Assurance Program Plan. July 2006. U.S. Department of Energy Office of Legacy Management

Quality Assurance Program Plan. July 2006. U.S. Department of Energy Office of Legacy Management U. S. Department of Energy Office of Legacy Management July 2006 July 2006 Page i DOE-LM Policy Statement The U.S. Department of Energy (DOE) Office of Legacy Management (LM) performs long-term surveillance

More information

LSST Hazard Analysis Plan

LSST Hazard Analysis Plan LSST Hazard Analysis Plan Large Synoptic Survey Telescope 950 N. Cherry Avenue Tucson, AZ 85719 www.lsst.org 1. REVISION SUMMARY: Contents 1 Introduction... 5 2 Definition of Terms... 5 2.1 System... 5

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

Every idea starts with ABC. Electronic Contract Manufacturing Cables and Harnesses System Integration Assembly Engineering

Every idea starts with ABC. Electronic Contract Manufacturing Cables and Harnesses System Integration Assembly Engineering Every idea starts with ABC Electronic Contract Manufacturing Cables and Harnesses System Integration Assembly Engineering ABC Assembly offers a dynamic approach to the electronics industry. We are a full-service

More information

Asset Management for the Public Sector with Total Accountability

Asset Management for the Public Sector with Total Accountability Asset Management for the Public Sector with Total Accountability An asset is a tangible or intangible item of positive economic value which can be owned and managed, or controlled. Asset management (AM)

More information

SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK

SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK Office of Safety and Mission Assurance NASA-GB-9503 SOFTWARE CONFIGURATION MANAGEMENT GUIDEBOOK AUGUST 1995 National Aeronautics and Space Administration Washington, D.C. 20546 PREFACE The growth in cost

More information

PROJECT SCOPE MANAGEMENT

PROJECT SCOPE MANAGEMENT 5 PROJECT SCOPE MANAGEMENT Project Scope Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully

More information

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the

More information

The How Do Guide to AxioVision. Author: Brian Svedberg Image Analysis Specialist Carl Zeiss MicroImaging, Inc.

The How Do Guide to AxioVision. Author: Brian Svedberg Image Analysis Specialist Carl Zeiss MicroImaging, Inc. The How Do Guide to AxioVision Author: Brian Svedberg Image Analysis Specialist Carl Zeiss MicroImaging, Inc. How do I grab a single image? How do I grab a single image? Click on the Camera icon to switch

More information

Linac Coherent Light Source (LCLS)

Linac Coherent Light Source (LCLS) Linac Coherent Light Source (LCLS) An X Ray Free Electron Laser LLNL Quality Implementation Plan PMD 003 r0 May 2004 Prepared for the US Department of Energy under contract numbers: SLAC DE AC03 76SF00515

More information

Using Microsoft SharePoint for Project Management

Using Microsoft SharePoint for Project Management ASPE IT Training Using Microsoft SharePoint for Project Management A WHITE PAPER PRESENTED BY ASPE www.aspe-it.com 877-800-5221 Using Microsoft SharePoint for Project Management A modern Project Management

More information

e-solutions by Thermo Fisher Scientific

e-solutions by Thermo Fisher Scientific e-solutions by Thermo Fisher Scientific You need a partner that s committed to delivering online and on-site solutions that meet your unique requirements our e-solutions are designed to do just that. thermofisher.com

More information

PMO-1.7 Cost Estimating. Project Management

PMO-1.7 Cost Estimating. Project Management Project Management Office Title: Section where used: PMO-1.7 Cost Estimating Project Management Prepared by Date Approved by Date Kurt Deshayes, LBNL EVMS Surveillance Officer Jim Krupnick, Laboratory

More information

Analytical Products and Solutions. Complete service and maintenance solutions for your analytical equipment. usa.siemens.com/analyticalproducts

Analytical Products and Solutions. Complete service and maintenance solutions for your analytical equipment. usa.siemens.com/analyticalproducts Analytical Products and Solutions Complete service and maintenance solutions for your analytical equipment usa.siemens.com/analyticalproducts Support Services for Today, Tomorrow and Years to Come Providing

More information

EyasSAT: A Classroom Nanosatellite for Teaching Space Systems Engineering. EyasSAT 1

EyasSAT: A Classroom Nanosatellite for Teaching Space Systems Engineering. EyasSAT 1 : A Classroom Nanosatellite for Teaching Space Systems Engineering 1 Introduction The Need The Solution Background System Architecture Applications Conclusions Outline 2 The Need Space Systems Engineering

More information

Change Control Process

Change Control Process Large Synoptic Survey Telescope (LSST) Change Control Process George Angeli and Robert McKercher LPM-19 Latest Revision Date: December 10, 2015 This LSST document has been approved as a Content-Controlled

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2

PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2 08/27/91 PURCHASE ORDER TERMS AND CONDITIONS FOR MANUFACTURING MANAGEMENT PROGRAMS MIL-STD-1528A APPENDIX 2 1. The Seller, upon acceptance of this purchase order, shall establish and/or maintain a Manufactured

More information

Models for MES In an Enterprise Architecture

Models for MES In an Enterprise Architecture Models for MES In an Enterprise Architecture Applying Industry Models in a Discrete Manufacturing Environment D. Fraser May 12, 2011 Executive Overview This document describes the modeling techniques applied

More information

CAREER TRACKS PHASE 1 UCSD Information Technology Family Function and Job Function Summary

CAREER TRACKS PHASE 1 UCSD Information Technology Family Function and Job Function Summary UCSD Applications Programming Involved in the development of server / OS / desktop / mobile applications and services including researching, designing, developing specifications for designing, writing,

More information

CCI 1050 Medical Device Test Station

CCI 1050 Medical Device Test Station 6550 Wedgwood Rd. Maple Grove, MN 55311 763-694-4100 CCI 1050 Medical Device Test Station Configuration Guide USA, CANADA, MEXICO, MALAYSIA, CHINA, UNITED KINGDOM www.circuitcheck.com 1 CCI 1050 Medical

More information

The PACS Software System. (A high level overview) Prepared by : E. Wieprecht, J.Schreiber, U.Klaas November,5 2007 Issue 1.

The PACS Software System. (A high level overview) Prepared by : E. Wieprecht, J.Schreiber, U.Klaas November,5 2007 Issue 1. The PACS Software System (A high level overview) Prepared by : E. Wieprecht, J.Schreiber, U.Klaas November,5 2007 Issue 1.0 PICC-ME-DS-003 1. Introduction The PCSS, the PACS ICC Software System, is the

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

CHAPTER 1. Introduction to CAD/CAM/CAE Systems

CHAPTER 1. Introduction to CAD/CAM/CAE Systems CHAPTER 1 1.1 OVERVIEW Introduction to CAD/CAM/CAE Systems Today s industries cannot survive worldwide competition unless they introduce new products with better quality (quality, Q), at lower cost (cost,

More information

Appendix V Risk Management Plan Template

Appendix V Risk Management Plan Template Appendix V Risk Management Plan Template Version 2 March 7, 2005 This page is intentionally left blank. Version 2 March 7, 2005 Title Page Document Control Panel Table of Contents List of Acronyms Definitions

More information

Ames Consolidated Information Technology Services (A-CITS) Statement of Work

Ames Consolidated Information Technology Services (A-CITS) Statement of Work Ames Consolidated Information Technology Services (A-CITS) Statement of Work C.1 Mission Functions C.1.1 IT Systems & Facilities Support System Administration: The Contractor shall provide products and

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page.

INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. What This Is INTRODUCTION: Plan and Schedule Development Create a Work Breakdown Structure (WBS) The detailed guidelines and examples start on the following page. First of a series of guidelines for project

More information

SAN Conceptual and Design Basics

SAN Conceptual and Design Basics TECHNICAL NOTE VMware Infrastructure 3 SAN Conceptual and Design Basics VMware ESX Server can be used in conjunction with a SAN (storage area network), a specialized high speed network that connects computer

More information

Product Liability Risk Control Checklist

Product Liability Risk Control Checklist Product Liability Risk Control Checklist Appendix C1 This material will help you evaluate your products liability exposure. It is designed to enable you to focus on areas that need to be addressed to safeguard

More information

Program Lifecycle Methodology Version 1.7

Program Lifecycle Methodology Version 1.7 Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated

More information

To introduce software process models To describe three generic process models and when they may be used

To introduce software process models To describe three generic process models and when they may be used Software Processes Objectives To introduce software process models To describe three generic process models and when they may be used To describe outline process models for requirements engineering, software

More information

Flame Direct Attach UV-VIS Integrated Sampling System Installation and Operation Instructions

Flame Direct Attach UV-VIS Integrated Sampling System Installation and Operation Instructions Flame Direct Attach UV-VIS Integrated Sampling System Installation and Operation Instructions Description The Flame Integrated Sampling System (FLAME-DA-CUV-UV-VIS) is a snap-on, direct-attach 1 cm cuvette

More information

MWA Project. Configuration Management Plan

MWA Project. Configuration Management Plan Document No.: MWA-XXX-XXX Revision: 0002 Date: 07-OCT-2009 MWA Project Configuration Management Plan MWA Project MWA Consortium Copyright 2009, MWA Consortium. All Rights Reserved. Control Status Document

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

A Comparison of PMI s PMBOK Guide Versions 4 & 3

A Comparison of PMI s PMBOK Guide Versions 4 & 3 PM WORLD TODAY FEATURED PAPER MAY 2009 A Comparison of PMI s PMBOK Guide Versions 4 & 3 By Germán Bernate The Project Management Institute PMI announced on December 31, 2008 the availability of PMBOK Version

More information

Statewide Transportation Management Center Software Library System

Statewide Transportation Management Center Software Library System Statewide Transportation Management Center Software Library System Detailed Work Plan October 16, 2003 Prepared for: Florida Department of Transportation ITS Office 605 Suwannee Street, M.S. 90 Tallahassee,

More information

CS 389 Software Engineering. Lecture 2 Chapter 2 Software Processes. Adapted from: Chap 1. Sommerville 9 th ed. Chap 1. Pressman 6 th ed.

CS 389 Software Engineering. Lecture 2 Chapter 2 Software Processes. Adapted from: Chap 1. Sommerville 9 th ed. Chap 1. Pressman 6 th ed. CS 389 Software Engineering Lecture 2 Chapter 2 Software Processes Adapted from: Chap 1. Sommerville 9 th ed. Chap 1. Pressman 6 th ed. Topics covered Software process models Process activities Coping

More information

Software Engineering. Software Processes. Based on Software Engineering, 7 th Edition by Ian Sommerville

Software Engineering. Software Processes. Based on Software Engineering, 7 th Edition by Ian Sommerville Software Engineering Software Processes Based on Software Engineering, 7 th Edition by Ian Sommerville Objectives To introduce software process models To describe three generic process models and when

More information

Specialties Manufacturing. Talladega Castings & Machine Co., Inc. ISO 9001:2008. Quality Manual

Specialties Manufacturing. Talladega Castings & Machine Co., Inc. ISO 9001:2008. Quality Manual Specialties Manufacturing Talladega Castings & Machine Co., Inc. ISO 9001:2008 This document is the property of TMS and may not be reproduced, wholly, or in part, without the express consent of TMS. Rev.

More information

Appendix B: Work Breakdown Structure (WBS)

Appendix B: Work Breakdown Structure (WBS) : Work Breakdown Structure (WBS) B.1. Introduction The WBS and WBS dictionary are effective management processes for planning, organizing, and administering NASA programs and projects. In accordance with

More information

Fiber Optics: Engineering from Global to Nanometer Dimensions

Fiber Optics: Engineering from Global to Nanometer Dimensions Fiber Optics: Engineering from Global to Nanometer Dimensions Prof. Craig Armiento Fall 2003 1 Optical Fiber Communications What is it? Transmission of information using light over an optical fiber Why

More information

Data Validation and Data Management Solutions

Data Validation and Data Management Solutions FRONTIER TECHNOLOGY, INC. Advanced Technology for Superior Solutions. and Solutions Abstract Within the performance evaluation and calibration communities, test programs are driven by requirements, test

More information

IC 1101 Basic Electronic Practice for Electronics and Information Engineering

IC 1101 Basic Electronic Practice for Electronics and Information Engineering 7. INDUSTRIAL CENTRE TRAINING In the summer between Year 1 and Year 2, students will undergo Industrial Centre Training I in the Industrial Centre (IC). In the summer between Year 2 and Year 3, they will

More information

1. Is it required that each company that bids on this RFP be pre-registered or pre-qualified prior to bidding?

1. Is it required that each company that bids on this RFP be pre-registered or pre-qualified prior to bidding? To: From: All Prospective Bidders Purchasing Department Date: September 9, 2015 Subject: Inquiries and Responses RFP#: Fixed A/V Maintenance/Repairs/Equipment Services 102-2015 Inquiries and Responses:

More information

Q2A First Article Inspection (FAI) AS9102

Q2A First Article Inspection (FAI) AS9102 Page 1 of 7 Q2A First Article Inspection (FAI) AS9102 A hard copy of this document may not be the document currently in effect. The current version is always the version on the Lockheed Martin network.

More information

Copyright 2006 Quality Excellence for Suppliers of Telecommunications Forum

Copyright 2006 Quality Excellence for Suppliers of Telecommunications Forum Release 4.0 4.2.3 4.2.3.C.1 Control of Customer- Supplied Documents and Data The organization shall establish and maintain a documented procedure(s) to control all customer-supplied documents and data

More information

ViZion Installation Guide

ViZion Installation Guide ViZion Installation Guide v2.0 1 ViZion Installation Guide Table of Contents Inventory Hardware Setup Understanding Synchronization Cable Begin by taking an inventory of the required equipment DR Unit

More information

Exhibit R-2, RDT&E Budget Item Justification

Exhibit R-2, RDT&E Budget Item Justification PE NUMBER: 0101120F PE TITLE: ADVANCED CRUISE Exhibit R-2, RDT&E Budget Item Justification BUDGET ACTIVITY PE NUMBER AND TITLE 07 Operational System Development 0101120F ADVANCED CRUISE Cost ($ in Millions)

More information

H.V.A.C. Design Plumbing Design

H.V.A.C. Design Plumbing Design H.V.A.C. Design H.V.A.C. Design Mira Costa College Arts Complex CP Upgrade 1. PART 1 GENERAL 1.1. DESCRIPTION SECTION 23 09 00 HVAC INSTRUMENTATION AND CONTROL 2. PART 2 - PRODUCTS 2.1. Materials

More information