Northrop Grumman Integrated Program and Earned Value Management

Size: px
Start display at page:

Download "Northrop Grumman Integrated Program and Earned Value Management"

Transcription

1 Northrop Grumman Integrated Program and Earned Value Management 13 th Annual International Integrated Program Management Conference November 14-17, 2001 Patti Tisone

2 Program Management Philosophy Northrop Grumman Manages Its Business Using a Program Management Process & Organization Program Managers Are Given Formal Authority for the Accountability and Execution of all Programs Program Management Process Requires That Programs Utilize EVM to Manage the Enterprise Top Level Policy at Corporate Level Additional Policy Guidance and Procedures at Sector/Business Area Levels

3 Office of the Chairman Kent Kresa Chairman and CEO Ron Sugar President and COO Electronic Systems Information Technology Integrated Systems Ship Systems Component Technologies Robert P. Iorizzo President Herb W. Anderson President Ralph D. Crosby, Jr. President Philip A. Dur President Frank Brandenberg President 80,000 Worldwide Employees! 44 States! 25 International Offices

4 Northrop Grumman EVMS Accomplishments " Corporate EVMS Team established to integrate sector/business area activities " Advance Agreement Signed October 31, 2000 " CEO letter to all Managers on Program Management Excellence " Approximately 3000 people trained in EVMS during last 24 months " Includes Program Management, Business Management, CAM s and Customers " Recognition of Northrop Grumman progress at Fall 2000 Integrated Program Management Conference " Team now includes Litton teammates

5 Northrop Grumman EVMS Initiative Corporate CFO Dick Waugh NG Lead Commander DCMA Col Mary Mayer Corporate EVMS Focal Point Patti Tisone DCE Don Springer ES CFO Wylie Smith IS CFO Lance Newquist ES Focal Point Tom Woodling, Jr IS Focal Point George Molitz Col Bradley Oswalt ES DCMA Col Dwight Thomas IS DCMA IT CFO Steve Movius IT Focal Point Gay Infanti Andy Yoo DCMA EV Center SS CFO Bob Spiker SS Focal Point Ron Krotoszynski Capt Phil Johnson USN CT CFO Bill Morgan CT Focal Point TBD N/A Executive Process Owners Corporate EVMS Execution Team

6 Sector Approaches to EVMS # Electronic Systems # Sector organization Sector Director of Program Planning and Control houses people and processes # Processes approved through normal procedure approval channels # Integrated Systems # Business unit organization - Three business units integrated through Program Cost Control Process Council- AGS is the council lead # Information Technology # Sector leadership - Vested EVMS process ownership in VP Contracts, Pricing and Procurement # Program Cost Control Council established to provide leadership & guidance to Sector & business areas relative to policy & process

7 Sector Approaches to EVMS # Ship Systems # Consists of three Business Unit Organization (Ingalls, Avondale & Full Service Center) # Business units integrated through VP Contract Administration and Estimating for execution of EV # Single focal point identified to improve integration and communication at ship systems # Component Technologies # Made up primarily of many commercial catalogue type entities # Business units integrated through the CFO s office

8 ES EVMS Accomplishments " Adopted a Sector EVMS policy compliant with DoD R and ANSI/EIA- 748 " To Implement Policy " Sector Common Procedures - Complete " Sector Common Tools - Complete " Sector Common Training - Complete " Sector Gap Analysis and Implementation Plan for SAP P/S- Complete

9 ES EVMS Accomplishments (continued) " To Enable Compliance " Joint DCM/NG SPI Execution Team Formed " Lt Col Oswalt and Tom Woodling " Results " Sector Advance Agreement Approved 6 Dec 2000 " Sector SPI Approved 12 Dec 2000 " Sector MOA for contract changes approved Jan 2001 " Sector Joint Surveillance Plan approved Oct " To Integrate the Litton Family " Litton EVMS Integration Plan in Place for 2002

10 IS EVMS Accomplishments " Signed Sector Advanced Agreement for EVMS (25 July 2001) " Established Sector Procedures for Integrated Program Management-Earned Value Systems Compliance Matrix (13 July 2001) " Established Business Management Process & Cost Metrics " Established Sector wide EVMS Website " Implemented weekly performance assessment Sector wide " 2002 Plans in place to implement " Standardized Sector Procedures " Standardized computing software " Standardized training " EVMS maturity model

11 IT EVMS Accomplishments " Short term EVMS operating policy implemented for TASC and PRC " Sector program management procedure developed with attributes that: " Support corporate policy & Advanced Agreement " Identifies candidate programs based on risk and other parameters " Established Earned Value Management council that consists of knowledgeable representatives from all business units " Plans in place to: " Process Sector level Advanced agreement " Submit SPI for EVMS leveraging customer accepted process from LTS business area

12 Ship Systems EVMS Accomplishments " IBR Training conducted for NAVSEA/SUPSHIP personnel " IBR on DDG 51 CLASS for the DDG 89/91 Contract completed successfully " Ongoing formal EVMS surveillance in place with SUPSHIP and DCAA " PMB for new LHD contract successfully implemented on schedule " Plans in place to: " Initialize study for more efficient EVMS software " Develop Sector level EVMS policy

13 2002 Northrop Grumman EVMS Team Objectives " Capitalize on accomplishments to date to implement EVMS best practices corporate wide with our Government partners " Integrate the Litton sites into our corporate advanced agreement " Finalize and implement the NOC EVMS maturity model to help us better focus on where to burn our calories " Continue our scheduled activities at all Sectors relative to: " Communication " Tool set standardization " Documentation " Compliance " Surveillance " Training

14 Summary " Northrop Grumman continues to be committed to achieving excellence in Program Management " Significant accomplishments have resulted from the focused efforts of the joint Northrop Grumman & Government EVMS Team which now includes the Litton entities " The use of EVMS to manage contracts is a key to achieving program management excellence and enhancing the value of the enterprise

NDIA Program Management

NDIA Program Management NDIA Program Management Systems Committee (PMSC) Northrop Grumman Our Approach to Program Management August 10, 2011 Dr. John Chino Vice President Corporate Programs, Quality and Engineering Topics Brief

More information

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010

THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 THE UNDER SECRETARY OF DEFENSE 3010 DEFENSE PENTAGON WASHINGTON, DC 20301 3010 ACQUlsmON, TECHNOLOGY AND LOG ISTICS AUG 1 0 2011 MEMORANDUM FOR SECRETARIES OF THE MILITARY DEPARTMENTS CHAIRMAN OF THE JOINT

More information

How To Write Ansi/Eia Evm System Acceptanceance Guide

How To Write Ansi/Eia Evm System Acceptanceance Guide National Defense Industrial Association (NDIA) Program Management Systems Committee (PMSC) ANSI/EIA 748 Earned Value Management System Acceptance Guide Working Release For User Comment January 23, 2006

More information

July 6, 2015 11(1) CHAPTER 11

July 6, 2015 11(1) CHAPTER 11 July 6, 2015 11(1) CHAPTER 11 Table of Contents Paragraph Page 11-000 Audit of Contractor Compliance with Contract Financial Management Requirements 11-001 Scope of Chapter... 1101 11-100 Section 1 ---

More information

Government Contracting and Earned Value Management (EVM)

Government Contracting and Earned Value Management (EVM) Government Contracting and Earned Value Management (EVM) Ida Davis, EVP, PMP, MBA Earned Value Manager DynPort Vaccine Company LLC, A CSC Company Note: This presentation is the property of DynPort Vaccine

More information

From Vision to Implementation: Integrated Strategic Planning

From Vision to Implementation: Integrated Strategic Planning A three-page excerpt from our 18-page Best Practice Guidebook: From Vision to Implementation: Integrated Strategic Planning 1 Best Practice Guidebook From Vision to Implementation: Integrated Strategic

More information

The Changing Government Contractor Environment

The Changing Government Contractor Environment The Changing Government Contractor Environment 1 Federal Government Contracting DCAA FY 2014 Report to Congress DCAA Audit Guidance Business systems Federal regulatory rule changes State Contracting (Dept.

More information

Defense Logistics Agency INSTRUCTION

Defense Logistics Agency INSTRUCTION Defense Logistics Agency INSTRUCTION DLAI 2105 Effective May 13, 2013 SUBJECT: Earned Value Management (EVM) Systems Performance, Oversight, and Governance Referenses: (a) DLA Instruction 2105, Earned

More information

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011

FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 FRA s Earned Value Management System Overview for Self Assessment Surveillance March 07-09, 2011 Dean Hoffer Head, Office of Project Management Oversight Outline EVMS History at the Lab FRA EVMS Documents

More information

structures stack up Tom McMullen

structures stack up Tom McMullen Making sure your organization structures stack up October 21, 2009 Tom McMullen Building effective organizations Trends in organization design Optimizing Focusing resources and reducing headcounts Removing

More information

12 TH NATIONAL SMALL BUSINESS CONFERENCE. Leveraging New Legislation for Growth SEPTEMBER 24, 2015 PROMOTING NATIONAL SECURITY SINCE 1919

12 TH NATIONAL SMALL BUSINESS CONFERENCE. Leveraging New Legislation for Growth SEPTEMBER 24, 2015 PROMOTING NATIONAL SECURITY SINCE 1919 PROMOTING NATIONAL SECURITY SINCE 1919 With recent small business contracting legislation, this year is poised to be a game changer in terms of increased small business participation in defense programs.

More information

Ethics and Compliance Training

Ethics and Compliance Training www.pwc.com Ethics and Compliance Training Keep Up Your Dukes - Benchmarking and Maintaining Your System April 1, 2014 Ethics and Compliance Keep Up Your Dukes - Benchmarking and Maintaining Your System

More information

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP

Earned Value Management and the Government Program Office. Blair Alan Knapp Jr. MSPM PMP Earned Value Management and the Government Program Office Blair Alan Knapp Jr. MSPM PMP Agenda EVM Information Alignment OMB Exhibit 300 and Funding Government Program Office Challenges Government Program

More information

Manitoba Hydro 2015 Report on Executive Compensation

Manitoba Hydro 2015 Report on Executive Compensation Manitoba Hydro 2015 Report on Executive Compensation June 2016 Contents Manitoba Hydro s Approach to Executive Compensation 3 Executive Compensation at Manitoba Hydro Executive Compensation Philosophy

More information

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule

DOECAA Spring Conference Presentation. Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule DOECAA Spring Conference Presentation Cost Reimbursement Contracting Issues - DOE Proposed Business System Rule Mary Karen Wills, CPA Director/Leader, BRG Government Contracts 2014 Berkeley Research Group

More information

DCAA Overview and Resources Available for Small Businesses

DCAA Overview and Resources Available for Small Businesses DCAA Overview and Resources Available for Small Businesses The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations Page 1 Department of Defense

More information

DCMA Software Contract Management Services CMM Based Insight Initiative

DCMA Software Contract Management Services CMM Based Insight Initiative DCMA Software Contract Management Services CMM Based Insight Initiative Presented By: Guy Mercurio, DCMA Software Center Boston, MA 23-27 July 2001 Practical Software and Systems Measurement Users Group

More information

Training Seminars. Description. Core Courses: The core courses consist of the following:

Training Seminars. Description. Core Courses: The core courses consist of the following: Training Seminars Description The POI consists of training courses known as core. The purpose of the core courses is to provide a principles or foundation knowledge baseline to the student in the fundamentals

More information

Overview of SAE s AS6500 Manufacturing Management Program. David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 [email protected].

Overview of SAE s AS6500 Manufacturing Management Program. David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 david.karr@us.af. Overview of SAE s AS6500 Manufacturing Management Program David Karr Technical Advisor for Mfg/QA AFLCMC/EZSM 937-255-7450 [email protected] 1 Outline Background Objectives Requirements Implementation

More information

SAMPLE. Insider Trading Chronology. Microsoft Corp (MSFT) Gates, William H. III -- 2,000,000 Shs. (0.25%)

SAMPLE. Insider Trading Chronology. Microsoft Corp (MSFT) Gates, William H. III -- 2,000,000 Shs. (0.25%) Insider buys Price Chart Insider sells Hastings, Reed -- 77,000 Shs. (43.5%) Turner, Brian Kevin -- 234,000 Shs. (29.17%) Gates, William H. III -- 2,000,000 Shs. (0.25%) Gates, William H. III -- 2,000,000

More information

PMO-1.7 Cost Estimating. Project Management

PMO-1.7 Cost Estimating. Project Management Project Management Office Title: Section where used: PMO-1.7 Cost Estimating Project Management Prepared by Date Approved by Date Kurt Deshayes, LBNL EVMS Surveillance Officer Jim Krupnick, Laboratory

More information

The Program Managers Guide to the Integrated Baseline Review Process

The Program Managers Guide to the Integrated Baseline Review Process The Program Managers Guide to the Integrated Baseline Review Process April 2003 Table of Contents Foreword... 1 Executive Summary... 2 Benefits... 2 Key Elements... 3 Introduction... 4 IBR Process Overview...

More information

DCMA Engineering & Analysis (E&A) Directorate Earned Value Management

DCMA Engineering & Analysis (E&A) Directorate Earned Value Management DCMA Engineering & Analysis (E&A) Directorate Earned Value Management NATIONAL DEFENSE INDUSTRY ASSOCIATION CONFERENCE Presented By: John Cuddy, Executive Director (acting) E&A Directorate 1 Topics Organizational

More information

DCAA Initiatives/Current Issues

DCAA Initiatives/Current Issues Defense Contract Audit Agency DCAA Initiatives/Current Issues Maryland Association of CPAs 2010 Government Contractors' Conference September 21, 2010 Kenneth J. Saccoccia Assistant Director Policy and

More information

earned value management

earned value management earned value management in control of big productions an eyeon white paper october 2013 1 contents 4 ly escalation 5 linking and cost control 6 cost forecasting 6 implementation towards effective project

More information

Executive Search & Management Consulting Since 1979

Executive Search & Management Consulting Since 1979 Executive Search & Management Consulting Since 1979 ringing Leaders to Smart Companies At oyle Ogata regman, we believe a great executive search firm brings its clients A players every time top performers

More information

DICK BRODKORB 714.235.1485 FAX ( ) 3 THEN CHECK THE LOCATION YOU LL BE ATTENDING.

DICK BRODKORB 714.235.1485 FAX ( ) 3 THEN CHECK THE LOCATION YOU LL BE ATTENDING. Instructors VENUE INFORMATION PROJECT SCHEDULING & EVMS LAS VEGAS, NV August 23-27, 2010 The M Resort, Spa and Casino 12300 Las Vegas Blvd. South Henderson, NV 89044 (877) 673-7678 Group block expires:

More information

2015 Global Identity and Access Management (IAM) Market Leadership Award

2015 Global Identity and Access Management (IAM) Market Leadership Award 2015 Global Identity and Access Management (IAM) Market Leadership Award 2015 Contents Background and Company Performance... 3 Industry Challenges... 3 Market Leadership of IBM... 3 Conclusion... 6 Significance

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide May 4, 2011 Revision 1* National Defense Industrial Association (NDIA) 2111

More information

Data Governance: proven steps to transform Information into an Asset

Data Governance: proven steps to transform Information into an Asset Data Governance: proven steps to transform Information into an Asset Apple Maps vs Google Maps Source: http://www.tomshardware.com/picturestory/607-ios-maps-fail.html Bad business because of data Make

More information

PROJECT MANAGEMENT PLAN <PROJECT NAME>

PROJECT MANAGEMENT PLAN <PROJECT NAME> PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome

More information

AACE International Recommended Practice No. 86R 14

AACE International Recommended Practice No. 86R 14 AACE International Recommended Practice No. 86R 14 VARIANCE ANALYSIS AND REPORTING TCM Framework: 9.1 Project Cost Accounting 9.2 Progress and Performance Measurement 10.1 Project Performance Assessment

More information

5/30/2012 PERFORMANCE MANAGEMENT GOING AGILE. Nicolle Strauss Director, People Services

5/30/2012 PERFORMANCE MANAGEMENT GOING AGILE. Nicolle Strauss Director, People Services PERFORMANCE MANAGEMENT GOING AGILE Nicolle Strauss Director, People Services 1 OVERVIEW In the increasing shift to a mobile and global workforce the need for performance management and more broadly talent

More information

Earned Value Management Tutorial Module 8: Reporting. Prepared by:

Earned Value Management Tutorial Module 8: Reporting. Prepared by: Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.

More information

Award Amount. For Grade Criteria Deadline. Scholarship

Award Amount. For Grade Criteria Deadline. Scholarship Scholarship Award Amount For Grade Criteria Deadline Elks National Foundational Scholarship TBD 12 Any high school senior who is a US citizen may apply for the Elks Scholarship. Applications will be judged

More information

NOVEMBER DEFENSE & FEDERAL TECHNOLOGY MARKET UPDATE

NOVEMBER DEFENSE & FEDERAL TECHNOLOGY MARKET UPDATE NOVEMBER DEFENSE & FEDERAL TECHNOLOGY MARKET UPDATE Aronson Capital s, LLC 805 King Farm Boulevard, Suite 300 Rockville, Maryland 20850 Tel: (301) 231-6200 Fax: (301) 231-7630 Philip J. McMann Tel: (301)

More information

Lighting Overview. Eric Rondolat, CEO Philips Lighting

Lighting Overview. Eric Rondolat, CEO Philips Lighting 1 Lighting Overview Eric Rondolat, CEO Philips Lighting Lighting Overview The team presenting today: Eric Rondolat CEO Paul Verhagen CFO Klaas Vegter Chief Strategy and Innovation Officer Pierre Yves Lesaicherre

More information

Earned Schedule application to Project Management

Earned Schedule application to Project Management Earned Schedule application to Project Management Walt Lipke PMI - Oklahoma City +1 405 364 1594 [email protected] www.earnedschedule.com $$ The ES idea is to determine the time at which the EV accrued

More information

Operation IMPACT (Injured Military Pursuing Assisted Career Transition)

Operation IMPACT (Injured Military Pursuing Assisted Career Transition) Operation IMPACT (Injured Military Pursuing Assisted Career Transition) January 2013 Operation IMPACT Program Management Office Northrop Grumman Today Leading global security company providing innovative

More information

Appendix D Glossary Of Terms

Appendix D Glossary Of Terms Appendix D Glossary Of Terms The notational style used in this glossary is to begin the definition of each defined term with a new paragraph beginning with the term in UPPERCASE. Any word or phrase used

More information

Introduction and DCAA Overview

Introduction and DCAA Overview Introduction and DCAA Overview Industry Engagement Session 10/29/2015 The views expressed in this presentation are DCAA's views and not necessarily the views of other DoD organizations DCAA 1965-2015:

More information

Technical Performance Measurement A Program Manager s Barometer

Technical Performance Measurement A Program Manager s Barometer PROGRAM MANAGEMENT TOOLS Technical Performance Measurement A Program Manager s Barometer DCMA Pilots a Modified Approach to TPMs Technical Performance Measurement has been in widespread use for many years

More information

NORTHROP GRUMMAN CORP /DE/

NORTHROP GRUMMAN CORP /DE/ NORTHROP GRUMMAN CORP /DE/ FORM 8-K (Current report filing) Filed 02/07/13 for the Period Ending 02/06/13 Address 2980 FAIRVIEW PARK DRIVE C/O NORTHROP GRUMMAN CORP FALLS CHURCH, VA 22042 Telephone 703-280-2900

More information

BY ORDER OF THE COMMANDER USTRANSCOM INSTRUCTION 33-48 UNITED STATES TRANSPORTATION COMMAND 22 JUNE 2015

BY ORDER OF THE COMMANDER USTRANSCOM INSTRUCTION 33-48 UNITED STATES TRANSPORTATION COMMAND 22 JUNE 2015 BY ORDER OF THE COMMANDER USTRANSCOM INSTRUCTION 33-48 UNITED STATES TRANSPORTATION COMMAND 22 JUNE 2015 Communications and Information DATA MANAGEMENT POLICY AND RESPONSIBILITIES COMPLIANCE WITH THIS

More information

NAVSEA Leadership Development Continuum

NAVSEA Leadership Development Continuum NAVSEA Leadership Development Continuum The Continuum allows employees to focus on leadership development through various stages of their careers, in preparation for future opportunities with the organization.

More information

Earned Value Management Systems Application Guide

Earned Value Management Systems Application Guide National Defense Industrial Association Integrated Program Management Division Earned Value Management Systems Application Guide January 27, 2015 Revision 2 National Defense Industrial Association (NDIA)

More information

Q1 2016 Company Presentation

Q1 2016 Company Presentation Q1 2016 Company Presentation Safe Harbor Statement and Disclosure This presentation contains forward-looking statements. These statements are made under the "safe harbor" provisions of the U.S. Private

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Prepare for Self-Certification of the Government Property Management System

Prepare for Self-Certification of the Government Property Management System Prepare for Self-Certification of the Government Property Management System By Jackie Luo, CEO, E-ISG Asset Intelligence Summary: Government Property Management is one of the 6 mandatory business systems

More information

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015

AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network

More information

Northrop Grumman Corporation

Northrop Grumman Corporation Northrop Grumman Corporation 2015 NHOA, 1 St Annual Business Summit Conference August 4, 2015 Tizoc S. Loza Corporate Manager, GSDP/Government Relations Northrop Grumman Today Leading global security company

More information

Xerox Completes Acquisition of ACS Industry Analyst / Advisor Call

Xerox Completes Acquisition of ACS Industry Analyst / Advisor Call Xerox Completes Acquisition of ACS Industry Analyst / Advisor Call Tom Blodgett Executive Vice President COO, Commercial Operations ACS, A Xerox Company Jim Firestone Executive Vice President President,

More information

Module 1: Supply Chain Design

Module 1: Supply Chain Design Module 1: Supply Chain Design Module 1 Introduction Section A: Develop the Supply Chain Strategy Chapter 1: Inputs to Supply Chain Strategy o Topic 1: Business Model o Topic 2: External Inputs to Supply

More information

FOREWORD. Page 2 of 88

FOREWORD. Page 2 of 88 FOREWORD Earned Value Management (EVM) is one of the DoD s and industry's most powerful program management tools. Government and industry program managers use EVM to assess cost, schedule and technical

More information

a GAO-02-635 GAO DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting Issues Remain

a GAO-02-635 GAO DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting Issues Remain GAO United States General Accounting Office Report to the Chairman, Committee on Government Reform, House of Representatives May 2002 DOD CONTRACT MANAGEMENT Overpayments Continue and Management and Accounting

More information

News Release. Contact: Randy Belote (Media) 703-280-2720 [email protected]. Steve Movius (Investors) 703-280-4575 steve.movius@ngc.

News Release. Contact: Randy Belote (Media) 703-280-2720 randy.belote@ngc.com. Steve Movius (Investors) 703-280-4575 steve.movius@ngc. Northrop Grumman Reports Fourth Quarter and 2015 Financial Results News Release Contact: Randy Belote (Media) 703-280-2720 [email protected] Steve Movius (Investors) 703-280-4575 [email protected]

More information

Defense Health Information Technology Symposium 2014

Defense Health Information Technology Symposium 2014 CDR James Ellzy Navy FAC representative Defense Health Information Technology Symposium 2014 EHR Modernization: Where are we and where are we going? 29 31 July 2014 1 DHA Vision A joint, integrated, premier

More information

Apple: Another Byte 5/12/2009. Agenda. Strategic Issue Recommendation Environmental Analysis Firm Analysis Options Implementation Conclusion

Apple: Another Byte 5/12/2009. Agenda. Strategic Issue Recommendation Environmental Analysis Firm Analysis Options Implementation Conclusion Apple: Another Byte Agenda Strategic Issue Recommendation Environmental Analysis Firm Analysis Options Conclusion Strategic Issue Apple is facing a projected decline in earnings per share in 2009 and must

More information

Strategic Meetings Management Getting Started

Strategic Meetings Management Getting Started Strategic Meetings Management Getting Started Introduction and Welcome Kevin Iwamoto Vice President Enterprise Strategy, StarCite 25+ Industry Veteran 14 years as a Global Travel & Meetings Procurement

More information

ROI Building The Business Case For Professional Services Automation

ROI Building The Business Case For Professional Services Automation ROI Building The Business Case For Professional Services Automation Robert D. Anderson, CPA Director Specialized Services Hitachi Consulting Kimberly McDonald Baker Vice-President, Sales and Marketing

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

MISS AN ANNOUNCEMENT?? *All old newsletters can be found online at isp.ucsd.edu*

MISS AN ANNOUNCEMENT?? *All old newsletters can be found online at isp.ucsd.edu* University of California, San Diego International Studies Program Opportunities Newsletter October 2006 Vol.II MISS AN ANNOUNCEMENT?? *All old newsletters can be found online at isp.ucsd.edu* In this Newsletter:

More information

Defense Contract Management Agency

Defense Contract Management Agency Fiscal Year (FY) 2011 Budget Estimates February 2010 Procurement, Defense-Wide Page Intentionally Blank PROCUREMENT, DEFENSE WIDE DEFENSE CONTRACT MANAGEMENT AGENCY EXHIBIT TITLE PAGE Purpose and Scope/Justification

More information

Thought Leadership THE 5 STAGES TO A SUSTAINABLE BUSINESS

Thought Leadership THE 5 STAGES TO A SUSTAINABLE BUSINESS Six Degree People Thought Leadership THE 5 STAGES TO A SUSTAINABLE BUSINESS Six Degree People - Thought Leadership The 5 Stages to a Sustainable Business Six Degree People is a leading executive search

More information

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN?

IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? 1 IS EARNED VALUE + AGILE A MATCH MADE IN HEAVEN? Presented at The Nexus of Agile Software Development and Earned Value Management, OSD-PARCA, February 19 20, 2015 Institute for Defense Analysis, Alexandria,

More information

Welcome. Launch of bluekiwi Zen. Atos vision for Social IT Gilles Grapinet, Senior Executive Vice President, Atos

Welcome. Launch of bluekiwi Zen. Atos vision for Social IT Gilles Grapinet, Senior Executive Vice President, Atos Welcome Atos vision for Social IT Gilles Grapinet, Senior Executive Vice President, Atos Demonstration JL Valente, CEO at bluekiwi bluekiwi case studies Gilles Grapinet and JL Valente Questions and Answers

More information

Business Process Optimization Certificate Program

Business Process Optimization Certificate Program Education and Business Business Process Optimization Certificate Program extension.uci.edu/bpo University of California, Irvine Extension s professional certificate and specialized studies Improve Your

More information

Recognizing and Mitigating Risk in Acquisition Programs

Recognizing and Mitigating Risk in Acquisition Programs Professional Development Institute May 27 th to May 29 th 2015 Recognizing and Mitigating Risk in Acquisition Programs D e b r a E. H a h n D e b b i e. h a h n @ d a u. m i l 703-805- 2830 1 DoD Risk

More information

Project Management Office Charter

Project Management Office Charter Old Dominion University Office of Computing and Communication Services Project Management Office Charter Version: 1.0 Last Update: February 18, 2010 Created By: Anthony Fox, PMP OCCS Project Management

More information

Sidoti Investor Presentation March 2014

Sidoti Investor Presentation March 2014 eplus E X C E L L E N C E T H R O U G H E X P E R I E N C E Sidoti Investor Presentation March 2014 eplus inc. EX C E L L E N C E T H R O U G H EX P E R I E N C E Safe Harbor Statement Statements in this

More information

Janna Systems Inc. Scotia Capital Telecom & Tech Conference November 8, 2011. Track Record of Success. William M. Tatham Chief Executive Officer

Janna Systems Inc. Scotia Capital Telecom & Tech Conference November 8, 2011. Track Record of Success. William M. Tatham Chief Executive Officer William M. Tatham Chief Executive Officer CUSTOMER 1 Scotia Capital Telecom & Tech Conference November 8, 2011 Janna Systems Inc. 19.63 Financial Services CRM >100% CAGR last 6 years Highly Profitable

More information