Hat Head Flood Levee Audit

Size: px
Start display at page:

Download "Hat Head Flood Levee Audit"

Transcription

1 KEMPSEY SHIRE COUNCIL Hat Head Flood Levee Audit April 2014

2 Hat Head Flood Levee Audit i

3 Executive Summary This report represents a complete and thorough Audit of the Hat Head Flood Levee System as at April, It forms part of a widespread audit of the entire Lower Macleay Flood Levee System. The Scope of this Audit included but was not limited to: 1. Compilation of all the known reports and information available on the levees and a summary of their currency, findings and recommendations. 2. Comparison of the Levee Design Levels with the Existing Levels and recommendations to reinstate the levees to the Design Levels. 3. A Geotechnical Investigation to assess the structural adequacy of the levees during prolonged flooding and recommendations as to any remediation measures required 4. A Defects Inspection of the levees to identify areas of anomalies, such as missing levees, low sections, localised depressions, and signs of erosion/scour or instability. Specifically, the following items were not included in the Scope of the Audit and should be carried out at later date: 1. Preparation of an estimate of cost to remediate each individual defect and a total cost to repair the levees. 2. Preparation of a condition rating for each levee based on the risk of failure and the likely severity of a failure. 3. Review of the Flood Structures including the Flood Gates. This was already carried out in May 2012 and no major issues were found. 4. Preparation of an Operation & Maintenance Manual including a Maintenance and Inspection Plan. It is proposed to develop one document for the entire Lower Macleay Floodplain. As part of the Audit, Consultants JK Geotechnics were engaged to Carry out field and laboratory work to assess the structural integrity of the levees under prolonged flood events. Evaluate the likelihood of failure of the levees under prolonged flood events including the stability of the levee cross section and protection against seepage. Undertake an inspection of the general defects of the levees Provide recommendations to remediate any inadequacies found. JK Geotechnics complete reports are attached as Appendix 6. The findings of the entire Audit are summarised in the Combined Action and Defects Inspection Report (Appendix 7). Specific issues identified included, but were not limited to, the need to address the effectiveness of Rowes Cutting - an emergency overflow spillway through the coastal sand dunes determine a revised design flood height and associated requirements to raise the levees repair the general defects in the levees Hat Head Flood Levee Audit ii

4 Hat Head Flood Levee Audit iii

5 Table of Contents 1.0 INTRODUCTION AUDIT SCOPE DESCRIPTION AND CONDITION OF LEVEE SYSTEMS LEVEE CONSTRUCTION HISTORY CONTROL LEVEE VILLAGE LEVEE SOUTH WESTERN LEVEE OCEAN BREAKOUT SPILLWAY (ROWES CUT) PREVIOUS REPORTS AND INFORMATION - SUMMARY OF CURRENCY, FINDINGS AND RECOMMENDATIONS COMPARISON OF LEVEE DESIGN LEVELS WITH THE EXISTING LEVELS LEVEE DESIGN LEVELS EXISTING LEVEE LEVELS COMPARISON OF LEVEE DESIGN LEVELS AND EXISTING LEVELS Village Levee South West Levee Control Levee CONFIRMATION OF DESIGN LEVELS RECOMMENDED ACTIONS TO REINSTATE THE LEVEES TO THE DESIGN LEVELS GEOTECHNICAL INVESTIGATION OF LEVEES COMBINED ACTION AND DEFECTS INSPECTION REPORT AND AUDIT FINDINGS JK Geotechnics Report Rowes Cut Channel Flood Damage Claim for Riverbank Erosion of Levee along Korogoro Creek Erosion of Village Levee Crest by Pedestrians, Cyclist and Vehicles Preparation of an Operation & Maintenance Manual including a Maintenance and Inspection Plan APPENDICES Hat Head Flood Levee Audit iv

6 1.0 INTRODUCTION The Audit of the Hat Head Levee System forms part of a widespread audit of the entire Lower Macleay Flood Levee System. The village of Hat Head is located at the mouth of Korogoro Creek, 32 kilometres east of Kempsey. Korogoro Creek forms part of the flood mitigation and drainage system for the Belmore- Kinchela area of the Lower Macleay River floodplain. The Hat Head flood mitigation system comprises the following works: 1. Floodgates on a 9 cell box culvert (3000 wide and 1800 high) across Korogoro Creek at Hat Head Road approximately 3 kilometres upstream of Hat Head Village 2. A Control Levee fitted with 7 control box culverts (2400 wide and 1800 high) and gates constructed across Korogoro Creek between the coastal and inner sand dunes The levee is constructed approximately 2 kilometres upstream of the village 3. An emergency overflow spillway known as Rowes Cut excavated through the coastal sand dunes some 300 metres upstream of the Control Levee 4. Flood Levees on both sides of Korogoro Creek through Hat Head village known as the town levee and the South West Levee. The locations of the levees investigated as part of this Audit are shown in the Plan in Appendix AUDIT SCOPE The Scope of the Hat Head Audit included but was not limited to: 1. Compilation of all the known reports and information available on the levees and summarise their currency, findings and recommendations. 2. Comparison of the Levee Design Levels with the Existing Levels and provide recommended actions to reinstate the levees to the Design Levels. This was undertaken by a. Obtaining the Levee Design Levels from either: i. The original design plans, or Hat Head Flood Levee Audit 1

7 ii. Previous flood studies b. Undertaking a desktop review of the current Laser Imaging Detection and Ranging (LIDAR) information to ascertain Existing Levels. c. Surveying of sections of the levees to confirm Existing Levels where LIDAR information was not considered accurate. d. A Geotechnical Investigation to assess the structural adequacy of the levees during prolonged flooding and provide recommendations as to any remediation measures required. e. A Defects Inspection of the levees to identify areas of anomalies, such as missing levees, low sections, localised depressions, and signs of erosion/scour or instability. Specifically, the following items were not included in the Scope of the Audit and should be carried out at later date: 5. Preparation of an estimate of cost to remediate each individual defect and a total cost to repair the levees. 6. Preparation of a condition rating for each levee based on the risk of failure and the likely severity of a failure. 7. Review of the Flood Structures including the Flood Gates. This was already carried out in May 2012 and no major issues were found. 8. Preparation of an Operation & Maintenance Manual including a Maintenance and Inspection Plan. It is proposed to develop one document for the entire Lower Macleay Floodplain. 3.0 DESCRIPTION AND CONDITION OF LEVEE SYSTEMS 3.1 LEVEE CONSTRUCTION HISTORY The history of the construction of the Hat Head Levees is detailed in Table 1 below. Hat Head Flood Levee Audit 2

8 Table 1 Flood Mitigation Works within the Study Area Flood Mitigation Work Hat Head Control Levee and Headworks and Village Levee Date of Construction 1968 Ryans Cut Ocean Outlet, Headworks and Drain 1973 Hat Head Control and Village Levees raised and reinforced 1999 Maintenance works have been carried out over the years on an ad hoc basis. 3.2 CONTROL LEVEE The control levee is located approximately 2 kilometres upstream of the Korogoro Creek Bridge. The levee is approximately 500 metres long and runs perpendicular across the Creek tying Hat Head road into the coastal sand dunes. The levee is an earth bank fitted with a 7 cell 1.83m H x 2.44m W box culvert designed to limit the amount of flood water flowing through Korogoro Creek to the ocean outlet. Flood water flows from the Swanpool plain into Korogoro Creek and builds up behind the control levee. Excess floodwater behind the control levee should result in a breakout of the ocean spillway to allow the flood water to reach the ocean and prevent the control levee from over topping. This ocean spillway is known as Rowes Cut. The levee s existing surface level averages at AHD 4.0m which is approximately 1.7 m above the natural surface level. It has an average crest width of 3.2 m. Batter slopes are approximately 1 in 5 on the water side and 1 in 8 on the town side. There is a rock retaining wall that varies in height between 0.5m and 1.0m at the toe of the town side batter. The vegetation at the top of the control levee is generally limited to native and exotic grasses with a few small trees along the toe on the town side. In comparing heights and embankment materials listed in the 1993 Audit of Flood Levees by the Department of Public Works with the current position, it appears that the levee has been subsequently raised with a layer of clay. This was confirmed by the Geotechnical Report prepared by specialised Flood Levee Geotechnical Consultants JK Geotechnics (Appendix 6). The control levee ties into the coastal sand dunes at its Eastern end. Aerial LIDAR survey have identified that there are points in these coastal sand dunes that are lower than the levee height by approximately 500mm. This can be seen in Figure 2 of Appendix 4. These low points may have always existed or it may be more likely that they have been caused by wind and rain erosion or when the levee was raised the sand dunes were not. In any event, there Hat Head Flood Levee Audit 3

9 is a potential low point in the coastal sand dunes which may result in water escaping into Hat Head Village. Erosion is present around the wing walls of the control culvert and the geo-fabric designed to cover the embankment material behind the wing wall is failing. Due to vehicle and pedestrian access along the top of the levee, some undulations are evident in the crest of the levee. These undulations do not affect the crest height of the levee, however, they store water when it rains and allows the water to seep down into the levee embankment. 3.3 VILLAGE LEVEE The Village Levee runs from the Korogoro Creek Bridge (on Hat Head Road at the entrance to the Village) along the Northern bank of Korogoro Creek and terminates at high ground within the Caravan Park. The levee is approximately 1.6 kilometres long and its crest varies between 2.4m to 2.9m AHD (1 and 1.5 m above natural surface level) It has a rounded crest which varies in width between 1.5 to 2.0 m. Batter slopes are approximately 1 in 3 on the water side and 1 in 3 to 1 in 4 on the town side. The batter slopes are steeper on the water side where the creek has eroded the bank/ levee. The levee embankment materials and subsurface conditions are outlined in the consultant s report by JK Geotechnics (Appendix 6). The levee batters are for the most part covered in native and exotic grasses. The crest of the levee however is often bare exposing a layer of clay material and occasionally sand. In comparing heights and embankment materials listed in the 1993 Audit of Flood Levees by the Department of Public Works with the current position, it appears that the levee has been raised with a layer of clay. This was confirmed by the Geotechnical Report prepared by Consultants JK Geotechnics (Appendix 6). As the levee runs alongside Korogoro Creek, it is often used by the residents as a bike and walking trail. Because of this, over time the crest has been eroded into a non-uniform shape as can be seen in the long section and cross sections in Appendix 5. Localised erosion of the levee crest and batters is also caused by vehicles driving across or along the levee to access the creek. Erosion of the levee as described above is severe in some points creating low points and destabilised sections of the levee. The water side batter is highly vegetated and for the majority of the levee is unmaintained. This makes inspecting the batters of the levee very difficult and critical defects such as burrows and erosion could be missed. There are a number of mature trees growing on and at the toe of the levee along its entire length. The roots of these trees are visible in the levee crest and batters at numerous locations along the levee. An impermeable plastic membrane within the levee is designed as a cut-off to prevent seepage of water through the levee. Due to erosion of the levee crest the plastic liner is visible in a number of locations along the levee. Tree roots are also visibly penetrating the Hat Head Flood Levee Audit 4

10 plastic barrier and it can be assumed that due to the number of trees along the levee the condition of this plastic layer is poor or at the very least, its purpose has been compromised. There are a number of concrete pipe culverts that run beneath the levee to remove stormwater from the town into Korogoro Creek. The headwalls of these culverts are often close to the levee embankment and erosion is present around the headwalls in some cases. A number of the headwalls are also cracked and in need of repair. The flood flaps at the outlets are generally in good condition; however the outlet drains are generally silted up resulting in the flood flaps being unable to operate effectively. 3.4 SOUTH WESTERN LEVEE The South-Western Levee extends some 1.8 kilometres downstream from the Korogoro Creek Bridge. The levee is effectively the embankment for Gap Road which is a two lane sealed road. The crest of the levee is approximately 7 metres wide with a 5 metre wide sealed road pavement. The road surface is in relatively good condition with only minor patches. No significant subsidence of the road formation is evident. As the road/levee is generally maintained in good condition, any defects associated with the structural integrity of the levee are minor and accordingly are of very low priority The levee was therefore not inspected in detail. However, a visual inspection of the road/levee was carried out and revealed no defects of significance. 3.5 OCEAN BREAKOUT SPILLWAY (ROWES CUT) The Hat Head Flood Levee System was designed to have an ocean breakout spillway located in the sand dunes upstream of the control levee. The original design allowed for floodwaters to build up behind the control levee and spill into the coastal storage area. Once the water level behind the control levee reaches 2.4m AHD, the floodwater should then breakout through the sand dunes into the ocean. A pilot channel, known as Rowes Cut, was constructed through the sand dunes to the ocean. The base level of the pilot channel at Korogoro Creek was at 2.4m AHD and had a 4m base width with sides sloping at 1 V and 2H. A plug at the ocean end of the channel at 2.3m AHD with a 10m wide base was constructed to enable Council to remove it during a flood. The ocean breakout spillway was modelled in 1994 and 1996 by Webb, Mckeown and Associates assuming an ocean outlet width of 10m with a base level at 2.3m AHD. This model produced a 1 in 100 year flood height of 3.63m AHD at the control levee. The design level of the control levee is 4.03m AHD. The levee s existing surface level averages at 4.0m AHD. Hat Head Flood Levee Audit 5

11 The original formalised channel has eroded and is now overgrown by vegetation. This is highlighted in the comparison of aerial photographs from when it was constructed in 1969 and in 2009 (Appendix 4). Rowes Cut channel can be clearly seen in the 1969 image extending from the bend in Korogoro Creek approx. 300m upstream of the control levee into the sand dunes. In the 2009 photograph this channel can no longer be seen and the area is densely vegetated. An aerial LIDAR survey was used to determine whether an ocean breakout was still possible at Rowes Cut. Figure 1 of Appendix 4 is a terrain model that highlights the ground height that exceeds 2.4m AHD upstream of the control levee. Rowes Cut is designed to breakout to the ocean at a flood height of 2.4m. For this to occur there must be a flow path at 2.4m AHD or lower from Korogoro Creek to the frontal sand dunes. It can be seen clearly that the high point of the sand dunes (highlighted in red) creates a continuous barrier significantly higher than 2.4m AHD which will stop water flowing through Rowes Cut from reaching the ocean. All flood modelling conducted has assumed that the ocean breakout spillway is functional. If in a large flood event the ocean spillway was not opened, the protection of Hat Head against the 1 in 100 year flood level could not be guaranteed. 4.0 PREVIOUS REPORTS AND INFORMATION - SUMMARY OF CURRENCY, FINDINGS AND RECOMMENDATIONS The following activities were carried out in order to correlate the existing information: All of the known information and reports available on the levees were compiled. This included a thorough search of Council Records together with enquires from Council employees working in the area. All reports were than electronically scanned, filed and summarised (see Table 2 below).. Hat Head Flood Levee Audit 6

12 TABLE 2 Summary of Scanned Hat Head Reports Report Macleay River County Council Swanpool Drainage, Korogoro Creek Scheme Design Drawings, Drawing Nos to Macleay River Flood Study Webb, Mckeown and Associates Pty Ltd NSW Public Works, Report No , Audit of Flood Levees for NSW Village of Hat Head NSW Public Works Hat Head Levee Hydraulic Review Webb, Mckeown and Associates Pty Ltd Date of Summary of Aims Findings / Recommendations Currency Report 1962 Not applicable as only Design Drawings Not applicable as only Design Drawings Current April 1989 November 1993 October 1994 Flood Study of the Lower Macleay River to determine the design conditions for the 1 in 20, 1 in 50 and 1 in 100 probability floods and an extreme event Appraise the flood security and structural adequacy of the levee system at Hat Head No investigation of the scour protection at the mouth of Korogoro Creek or the effectiveness of the escape spillway to carry excess flood water Determine the 1% AEP Design Flood Levels Provide an indication of the extreme flood levels which would occur during an extreme ocean surge Flood behaviour throughout the study area for the 1 in 20, 1 in 50 and 1 in 100 probability floods and the extreme flood calculated and results provided on plan views Numerous recommendations none of which appear to have been implemented 1% flood level is approximately 2.39m and extreme flood level is 3.0 m AHD (both downstream of Korogoro Creek Bridge) Not Current Superseded See Section 5 of this Audit Report for the flood levels adopted and the reasons thereof Hat Head Flood Levee Audit 7

13 Report Investigation of Hat Head Flood Levees Final Report, Paterson Consultants Pty Ltd Date of Report June 1995 Summary of Aims Findings / Recommendations Currency Determine the flood levels at which there is a definite possibility of levee failure including the impact of overtopping Remedial works to be undertaken to provide a nominated level of protection There appears to be no definition of the risk of overtopping of the levee system as built to the design crest level of 2.35m (includes 0.3m freeboard) Foundation structurally adequate to support levees Plastic internal liner in levees in good condition Significant risk of levee failure due to patchy grass Current To be updated as part of this audit Hat Head Levee Hydraulic Review Supplementary Report Webb, Mckeown and Associates Pty Ltd May 1996 Carry out further studies to the October 1994 Report to determine flood levels in Korogoro Creek for various combinations of tide, gate openings in the throttle control and the size of Rowes Cut ocean breakout Reducing the gate openings in the throttle control from 7 to 5 has a small benefit downstream with no dis-benefit upstream Any reasonable combination of design floods will not exceed the critical level Current Variations in the dimensions of Rowes Cut have no discernible impact on flood levels It is noted that the report did not investigate the implications of Rowes Cut not function in a flood event Hat Head Flood Levee Audit 8

14 Report Seepage analysis of the Village Levee Department of Land and Water Conservation Date of Report August 1997 Summary of Aims Findings / Recommendations Currency Review of Critical flood level envelope and survey data to determine the critical; levee sections for analysis Determine levee bank and foundation representative permeability and reassess the seepage analyses to determine required remedial works Review remedial options and revise costs in the light of field survey and permeability data Raise the levee crest levels to obtain a uniform freeboard of 400mm above the expected flood level, a crest of 2m and establish batters of 1 vertical to 3 horizontal On completion of above and where differential heads exceed 850mm, undertake one of four recommended remedial options to protect against seepage In areas of confined width, incorporate gabion retaining walls and seepage control measures into the levee formation to provide a safe levee configuration Not current / superseded by JKGeotechnics Current Report Revised seepage analysis undertaken as part of this Audit NSW Levee Study for Emergency Management SES September 2008 Provide current information of a number of levees throughout NSW including those of the Lower Macleay Difficult to determine whether any of these recommendations were implemented but only of historical significance as report superseded by JKGeotechnics current report Specifically with respect to Hat Head Summarised all available information on the levee system Current Levees structurally adequate Overtopping Crest Height of 2.35 Hat Head Flood Gates and Culvert Inspection Reports May 2012 Inspect Flood Gate and Culvert for structural and maintenance issues No accessible high ground for evacuation No major issues found Current Does not form part of the Scope of this Audit Hat Head Flood Levee Audit 9

15 5.0 COMPARISON OF LEVEE DESIGN LEVELS WITH THE EXISTING LEVELS 5.1 LEVEE DESIGN LEVELS The Hat Head levee system is designed for a 1 in 100 year flood. Design levels for the Hat Head levees have been determined by Webb, Mckeown and Associates Pty Ltd using a model developed in 1994 which was then supplemented in Two flooding cases considered in the 1996 report are based on the following: 1in 100 year flood with ocean level of 2.0m AHD 1 in 20 year flood with an ocean level of 2.1m AHD The levee design levels were based on the maximum flood envelope from these two flooding cases, being the 1 in 100 year flood with ocean level of 2.0m AHD. The 1 in 100 year flood levels assume that all 7 flood gates on the Control Levee Culverts are open and Rowes Cut has been opened to a width of 10m with a base level at 2.3m AHD. These flood levels are summarised on Table 3 below. Based on the recommendations of the 1997 Seepage Analysis Report (see above in Table 2), Council has adopted a freeboard of 400mm above the 1 in 100 flood height. This results in levee design levels set out in Table 3 below. Hat Head Flood Levee Audit 10

16 Table 3 Adopted 1 in 100 Year Flood Levels for the Village, South West and Control Levees Location 1 in 100 Year Flood Height (m AHD) Design Freeboard (m) Levee Design Levels (m AHD) Control Levee Control Levee U/S Village and South Western Levee Korogoro Creek Bridge U/S Korogoro Creek Bridge D/S Dodds Street Mason Street Vine Street Myrtle Street Footbridge Boat Ramp These levels are set out in the long sections in Appendix EXISTING LEVEE LEVELS A desktop review of the current Laser Imagining Detection and Ranging (LIDAR) information was undertaken to attempt to ascertain the Existing Levee Levels for the Village, South West and Control Levees. Ground cover (trees and long grass) affected the accuracy of the survey readings. LIDAR generally requires flat open ground for accuracy. It was therefore necessary to physically survey all the levees to confirm the Existing Levels. A survey was carried out using Global Navigation Satellite System (GNSS) Surveying Equipment which can be considered accurate to approximately 30mm. The survey plans produced are attached in Appendix COMPARISON OF LEVEE DESIGN LEVELS AND EXISTING LEVELS Long sections were prepared showing the Design, Flood and Existing Levels of the Village, South West and Control Levees. Hat Head Flood Levee Audit 11

17 The Design Level is the 1 in 100 year Flood Level plus 400mm freeboard. Village Levee The Existing Levels are below the Design Levels in various sections for a total length of approximately 1017m which equates to 58% of the length. However, the Existing Levels are above the 1 in 100 year Flood level for the total length. The Minimum Actual Freeboard (existing level minus 1 in 100 year flood level) is 150 mm but ranges between 300 mm to 400 mm for the majority of the levee. South West Levee The Existing Levels are below the Design Levels in various sections for a total length of approximately 80m which equates to 5% of the length. However, the Existing Levels are above the 1 in 100 year Flood level for the total length. The Minimum Actual Freeboard (existing level minus 1 in 100 year flood level) is 280mm but ranges between 400 mm to 700 mm for the majority of the levee. Control Levee The Existing Levels are below the Design Levels in various sections for a total length of approximately 290m which equates to 53% of the length. However, the Existing Levels are above the 1 in 100 year Flood level for the total length. The Minimum Actual Freeboard (existing level minus1 in 100 year flood level) is 170 mm (at the Headworks Control Culvert) but ranges between 300 mm to 400 mm for the majority of the levee. 4.4 CONFIRMATION OF DESIGN LEVELS JK Geotechnics Report (Village Levee Report Section 4.2 and Control Levee Report Section 4.1.2) has identified different design levels to the above. This report went on to recommend that a hydraulic/water resources engineer be engaged to revisit the1% AEP design flood levels, extreme flood events and minimum freeboard requirements. The reasons put forward for this recommendation were: the age of the previous reports (mid 1990s) the different Council s Design Flood Levels compared to JK Geotechnics findings the need to now consider the effects of global warming. This is an important issue. Design levels must be determined as accurately as possible before any work is carried out on the levee system. The Combined Action and Defect Inspection Report has noted this. Hat Head Flood Levee Audit 12

18 6.0 RECOMMENDED ACTIONS TO REINSTATE THE LEVEES TO THE DESIGN LEVELS In order to provide a consistent satisfactory factor of safety for the flood mitigation system, it is recommended that the existing levels be raised to the design levels on the entire levee system. Recommended actions to reinstate the existing levels to the design levels were prepared by Consultants JK Geotechnics. The raising of the levees should not take place until a hydraulic/water resources engineer is engaged to revisit the1% AEP design flood levels, extreme flood events and minimum freeboard requirements as outlined previously. The details of the above are set out in JKGeotechnics Report (Appendix 6) and are also summarised in the Combined Action and Defects Inspection Report (Appendix 7). 7.0 GEOTECHNICAL INVESTIGATION OF LEVEES Consultants JK Geotechnics, were engaged to carry out: Field and laboratory work as required to assess the structural integrity of the earth levees under prolonged flood events. Evaluation of the likelihood of failure of the levee under prolonged flood events including the stability of the levee cross section and protection against seepage. An inspection of the general defects of the Levees Provide recommendations to remediate any inadequacies found. JK Geotechnics complete reports are attached as Appendix 6. The findings of the report have been incorporated into the Combined Action and Defects Inspection Report (Appendix 7). 8.0 COMBINED ACTION AND DEFECTS INSPECTION REPORT AND AUDIT FINDINGS An important part of this audit is the Combined Action and Defects Inspection Report (Appendix 7). This Combined Action and Defects Inspection Report incorporates the defects from the following areas: The findings and recommendations of this Audit Defects identified as part of JK Geotechnics report. Hat Head Flood Levee Audit 13

19 Detailed inspections were carried out on the Village and Control Levees. The South Western Levee is generally in good condition and accordingly a quick visual assessment was only required to confirm this fact. Defects such as geotechnical issues missing levees, low sections, localised depressions, trees in the levee and signs of erosion/scour or instability were compiled The defects identified in the Levee Levels Investigation, The Combined Defects Inspection Report therefore provides a summary of all defects associated with the Levee Levels, Geotechnical Issues and General Defects. A cost estimate will need to be prepared to rectify each of these defects. The recommended actions will than need to be prioritised. Specific issues are detailed below. JK Geotechnics Report The findings and of the JK Geotechnics Report and the associated Defects Inspection Report are concurred with. They form part of the Combined Defects Inspection Report (Appendix 7). Rowes Cut Channel The channel is effectively non-existent and will need significant rehabilitation to ensure its effective operation. Detailed survey, design and environmental approvals would be required before physical work could commence. These activities would be difficult due to the extensive vegetation existing within the channel and the fact that the channel is located within a National Park. All flood modelling conducted to date has assumed that the ocean breakout spillway is functional. In the light of the significant time and cost in carrying out the design, obtaining approvals and physically reconstructing the channel, it is recommended that additional flood modelling work be carried out based on Rowes Cut Channel not providing any flood relief (ie no flood water escaping to the ocean via the channel). This additional modelling will ascertain whether the reinstatement of Rowes Cut Channel is necessary to provide adequate protection to Hat Head Village. Alterative protective measures may be found to be more appropriate such as raising the levee heights Hat Head Flood Levee Audit 14

20 It is also recommended that an investigation be carried as to the Environmental Approvals required to reinstate Rowes Cut. This investigation should also ascertain whether State Environmental Planning Policy (Infrastructure) 2007 is applicable. Depending on the findings of the above, it may also be necessary to have a Contingency Operational Plan for when it is necessary to open Rowes Cut. The plan should detail: 1. when and how plant such as excavators are to be bought to site and placed on standby 2. the environmental requirements of the work 3. the exact trigger for the opening of Rowes Cut. Flood Damage Claim for Riverbank Erosion of Levee along Korogoro Creek JK Geotechnics has identified riverbank erosion of the levee along sections of Korogoro Creek. It appears that this damage has been caused by previous natural flood disasters. It is recommended that funding for the repair of this river bank/levee erosion be sought from the appropriate NSW Department as a late natural disaster claim. Erosion of Village Levee Crest by Pedestrians, Cyclist and Vehicles Erosion of the levee by pedestrians, cyclists and vehicles has been described in Section 2.3 and is also discussed in JK Geotechnics Report. It is severe in some points creating low points and destabilised sections of the levee. Once the levee design levels are finalised, it is recommended that consideration be given to provide a concrete pedestrian / cycleway on the crest of the levee to eliminate any further erosion issues. This would form part of the overall Hat Head Cycleway. Preparation of an Operation & Maintenance Manual including a Maintenance and Inspection Plan An up to date Operation & Maintenance Manual which includes Maintenance and Inspection Plans needs to be developed as one document for the entire Lower Macleay Floodplain. In respect to the Operation of Rowes Cut, it is understood that there is a requirement to close the two outer gates of the Korogoro Creek Choke when Rowes Cut is operating. This requirement needs to be fully investigated and if found correct needs to be incorporated into the Manual. The preparation of this Manual was not part of the Scope of this Audit. It has not yet commenced. It has been listed as an action in the Combined Action and Defects Inspection Report. Hat Head Flood Levee Audit 15

21 9.0 APPENDICES The following Appendices are attached: Appendix 1 - Hat Head Levee Site Plan Appendix 2 - Original Design Plans Appendix 3 Photographs of Levees Appendix 4 - Rowes Cut Terrain Maps and Aerial Photography Appendix 5 Levee Plan and Long Sections Appendix 6 - JK Geotechnics Reports Village Levee and Control Levee Appendix 7 - Combined Action and Defects Inspection Report Hat Head Flood Levee Audit 16

22 Appendix 1 Hat Head Levee Site Plan Hat Head Flood Levee Audit 17

23 Appendix 2 Original Design Plans HAT HEAD ORIGINAL DESIGN PLANS COMBINED.pdf See separate PDF File (HAT HEAD ORIGINAL DESIGN PLANS COMBINED) Hat Head Flood Levee Audit 18

24 Hat Head Flood Levee Audit 19

25 Appendix 3 Photographs of Levees Hat Head Flood Levee Audit 20

26 Hat Head Flood Levee Audit 21

27 Hat Head Control Levee Photos Hat Head Flood Levee Audit 22

28 Hat Head Flood Levee Audit 23

29 Hat Head Village Levee Photos Hat Head Flood Levee Audit 24

30 Hat Head Flood Levee Audit 25

31 Hat Head Flood Levee Audit 26

32 Hat Head Flood Levee Audit 27

33 Hat Head South West Levee Photos Hat Head Flood Levee Audit 28

34 Hat Head Flood Levee Audit 29

35 Rowes Cut Photos Hat Head Flood Levee Audit 30

36 Hat Head Flood Levee Audit 31

37 Hat Head Flood Levee Audit 32

38 Hat Head Flood Levee Audit 33

39 Appendix 4 Rowes Cut Terrain Models and Aerial Photography Hat Head Flood Levee Audit 34

40 Hat Head Flood Levee Audit 35

41 Figure 1: Terrain model showing location of low points in coastal sand dunes Hat Head Flood Levee Audit 36

42 Figure 2: Terrain model showing ground surface at Rowes Cut Hat Head Flood Levee Audit 37

43 Hat Head Control Levee Aerial Photograph 1969 Hat Head Control Levee Aerial Photograph 2009 Hat Head Flood Levee Audit 38

44 Hat Head Flood Levee Audit 39

45 Appendix 5 Levee Plan and Long Sections Hat Head Flood Levee Audit 40

46 Hat Head Flood Levee Audit 41

47 Plan and Long Sections Hat Head Control Levee CONTROL LEVEE PLAN.pdf See separate PDF File (Hat Head Control Levee Plan) Hat Head Flood Levee Audit 42

48 Hat Head Flood Levee Audit 43

49 Plan and Long Sections Hat Head Village Levee Hat Head Village Levee.pdf See separate PDF File (Hat Head Village Levee Plan) Hat Head Flood Levee Audit 44

50 Hat Head Flood Levee Audit 45

51 Plan and Long Sections Hat Head South West Levee Hat Head SW Levee PLAN.pdf See separate PDF File (Hat Head SW Levee Plan) Hat Head Flood Levee Audit 46

52 Hat Head Flood Levee Audit 47

53 Appendix 6 JK Geotechnics Reports Hat Head Flood Levee Audit 48

54 Hat Head Flood Levee Audit 49

55 JK Geotechnics Report Village Levee 27111LA5rpt-Rev1 Hat Head Village Levee JK Getechnics Final Report 9 April 2014.pdf See separate PDF File (27111LA5rpt-Rev1 Hat Head Village Levee JK Getechnics Final Report 9 April 2014) Hat Head Flood Levee Audit 50

56 Hat Head Flood Levee Audit 51

57 JK Geotechnics Report Control Levee 27111LA4rpt Hat Head Control Levee JK Getechnics Final Report 9 April 2014.pdf See separate PDF File (27111LA4rpt Hat Head Control Levee JK Getechnics Final Report 9 April 2014) Hat Head Flood Levee Audit 52

58 Hat Head Flood Levee Audit 53

59 Appendix 7 Combined Action and Defects Inspection Report Hat Head Flood Levee Audit 54

60 Hat Head Flood Levee Audit 55

61 Combined Action and Defects Inspection Report General Findings Defect No. Description Comments A Prepare estimates, prioritise and obtain funding to rectify the defects identified in the Combined Defects Inspection Report. Not Commenced. B Preparation of a condition rating for each levee based on the risk of failure and the likely severity of a failure. Not Commenced. C D E F G H Preparation of an Operation & Maintenance Manual including a Maintenance and Inspection Plan. Specifically with respect to the Operation of Rowes Cut investigate the requirement to close the two outer gates of the Korogoro Creek Choke when Rowes Cut is operating. A hydraulic/water resources engineer be engaged to revisit the1% AEP design flood levels, extreme flood events and minimum freeboard requirements of the entire levee system. Modelling work should also be carried out based on Rowes Cut Channel not providing any flood relief (i.e. no flood water escaping to the ocean via the channel) and the levee design levels adjusted accordingly. Depending on the findings of Defect No D, and if necessary, raise the existing levee levels to the design levels on the entire levee system in accordance with the recommended design/actions of JK Geotechnics. Depending on the findings of Defect No D, investigate the potential low point in the coastal sand dunes which may result in water escaping into Hat Head Village. Investigate the Environmental Approvals required to reinstate Rowes Cut. This investigation should also ascertain whether SEPP (Infrastructure) 2007 would be applicable. Depending on the findings of Defect No D, prepare a Contingency Operational Plan for when it is necessary to open Rowes Cut The plan should detail: 1. when and how plant such as excavators are to be bought to site and placed on standby 2. the environmental requirements of the work 3. the exact trigger for the opening of Rowes Cut. Not Commenced.. Proposed to develop one document for the entire Lower Macleay Floodplain. Not Commenced Not Commenced Not Commenced Discussions with NPWS commenced Not Commenced I Submit a late Natural Disaster Claim for funding for the repair of the Korogoro Creek bank/levee erosion. Not Commenced J Once the levee design levels are finalised, provide a concrete pedestrian / cycleway on the crest of the levee to eliminate any Not Commenced further erosion issues. This would form part of the overall Hat Head Cycleway.

62 Combined Action and Defects Inspection Report Village Levee Defect No. Chainage Description J K Geotechnics Report Section 1-80 Large tree in upstream shoulder & Flood Gate: Concrete headwall surrounded the flood gate. The gate was not completely closed. A crack was present in the assembly. The concrete connection was cracked, contained a penetration as well as concrete cancer Stormwater Inlet: The inlet comprised a 450mm diameter concrete pipe and contained leaf litter and eroded debris. Priority Level 4.5 & (repair flood gate) 3 (repair head wall) 4.2 (Item 2), 4.5 & Two large trees in upstream shoulder. 4.2 (Item 2), & Stormwater Inlet: The inlet comprised a 450mm diameter concrete pipe surrounded by a concrete headwall. Flood Gate: Concrete headwall surrounded the flood gate. The gate was closed. The concrete encasement surrounding the pipe outlet had broken off in some sections, revealing voids Stormwater Inlet: The inlet comprised a 375mm diameter concrete pipe surrounded by an ad-hoc dry stacked boulder wall. A 100mm diameter ag pipe daylighted adjacent to the crown of the concrete pipe. Both inlets contained leaf litter and grass clippings. Flood Gate: Concrete headwall surrounded the flood gate. The gate was closed. Debris had accumulated in front of the gate however it did not appear to impede operation. The concrete encasement surrounding the pipe outlet had broken off in some sections, revealing voids. 1 (investigate creek bank stabilisation) 2 (for clean out) 3 (for improvement) 1 (investigate creek bank stabilisation) 3 (for reconstruction) 4.5 & (for clean out and CCTV inspection & treatment of ag pipe) 3 (for repair/improvement) Frangipani tree on downstream shoulder Stormwater Inlet: The inlet comprised a letterbox pit. To the south-west of the pit, adjacent to the tree, a low spot existed. Leaf litter and debris were observed at the letterbox pit opening. Flood Gate: Concrete headwall surrounded the flood gate. The gate was closed and partially buried/obstructed by debris. The condition of the head wall and concrete surrounds to the pipe could not be observed due to dense vegetation (for clean out and topping up of low spot )

63 Combined Action and Defects Inspection Report Village Levee Defect No. Chainage Description J K Geotechnics Report Section to 485 Tree root, approximately 100mm diameter, extended over levee crest. The tree root most likely belonged to the gum tree located 2.5m beyond the downstream toe. Black builder s plastic exposed along levee crest. Priority Level Tree roots extended over levee crest Stormwater Inlet: The inlet was completely blocked by debris and obscured by long grass. Flood Gate: Concrete headwall surrounded the flood gate. The gate was closed and partially buried/obstructed by debris. The condition of the head wall and concrete surrounds to the pipe could not be inspected due to the accumulated debris Tree roots up to 80mm diameter extended over crest for a 13.5m length of levee & Stormwater Inlet: The inlet comprised a letterbox pit. The letterbox pit opening was partially buried by leaf litter and debris. Flood Gate: Concrete headwall surrounded the flood gate. The gate was closed. The head wall and concrete surrounds to the pipe appeared to be in good condition Stormwater Inlet: The inlet comprised a letterbox pit. The letterbox pit opening was mostly obstructed by (uncut) long grass. Flood Gate: In this area, the upstream toe of the levee had eroded out and was undercut. Despite the upstream shoulder being covered with dense grass, there was evidence of erosion and subsidence on the shoulder itself. A concrete headwall surrounded the flood gate. The erosion had exposed the back of the headwall. Debris had jammed open the flood gate to 745 Riverbank Erosion: An approximately 40m length of riverbank had eroded. The erosion, which included soil slumping, had undercut the upstream toe of the levee. Some rock armour was observed along the riverbank to 810 Riverbank Erosion: An approximately 65m length of riverbank had eroded but to a lesser extent than observed between CH705 & CH745 (Item 20). The erosion had undercut the upstream toe of the levee. Rock armour was present along the riverbank to 810 Large Trees: Three large trees were located on the downstream shoulder. Along this 40m length of levee, tree roots extended over the crest. Black builders plastic exposed along the crest was quite noticeable along this root affected section of levee (Item 2) 1 (investigate creek bank stabilisation) 4.2 (Item 2) 1 (investigate creek bank stabilisation) & 4.8 3

64 Combined Action and Defects Inspection Report Village Levee Defect No. Chainage Description J K Geotechnics Report Section Birds Nest: A 100mm diameter horizontal nest hole was observed mid-slope on the upstream shoulder. The nest hole was 800mm deep when probed with a steel tape measure Stormwater Inlet on Town Side of Creek Street: The inlet comprised a letterbox pit. The letterbox pit opening was partly obstructed by (uncut) long grass. Stormwater Inlet on Creek Side of Creek Street: The inlet comprised a letterbox pit. The letterbox pit opening was partly obstructed by (uncut) long grass. Flood Gate: Concrete headwall surrounded the flood gate. The gate was closed. The head wall appeared to be in good condition. Debris had accumulated in front of the gate however it did not appear to impede operation Stormwater Inlet: The inlet comprised a letterbox pit. The letterbox pit opening was partly obstructed by (uncut) long grass. Flood Gate: The flood gate could not be found amongst the dense fern and leaf litter coverage. Priority Level to 1038 Tree roots extended over crest for an approximate 20m length of levee & to 1085 Birds Nests: Five 50mm diameter horizontal nest holes were observed mid-slope on the upstream shoulder. The nest holes ranged in depth between 50mm and 900mm when probed with a steel tape measure Stormwater Inlets: Grated stormwater pits on either side of Creek Street. Flood Gate: Located approximately 10m beyond the upstream toe of the levee, within the creek inter-tidal zone. The gate was closed. Concrete headwall surrounded the flood gate and appeared to be in good condition. There was some erosion of rock fill/armour adjacent to the headwall Stormwater Inlet: The inlet comprised a letterbox pit. The letterbox pit opening was partly obstructed by (uncut) long grass and litter. Flood Gate: The flood gate was located on the creek bank, within the inter-tidal zone. The gate was closed. The pipe behind the flood gate was surrounded by concrete which appeared to have been placed in an ad-hoc manner. The bank material surrounding the concrete had eroded out, resulting in cracking of the concrete (for clean out) 3 (for improvement) Crest erosion due to pedestrian/bicycle traffic. 4.7 & Fig tree at toe of downstream shoulder & 4.8 3

65 Combined Action and Defects Inspection Report Village Levee Defect No. Chainage Description J K Geotechnics Report Section Priority Level Gouge in downstream shoulder of levee. 4.2 (Item 8) 2 or Stormwater Inlet: Grated stormwater pit at downstream toe of levee. Flood Gate: Located approximately 7m beyond the upstream toe of the levee. The gate was closed. Concrete headwall surrounded the flood gate. The headwall was in poor condition with a vertical crack adjacent to the flood gate. There was faulting across the crack by approximately 10mm. Debris and leaf litter had accumulated in front of the gate however it did not appear to impede operation (for clean out) 3 (for improvement) Tree root up to 100mm diameter extended over levee crest Stormwater Inlet: Grated stormwater pit at downstream toe of levee. Flood Gate: Located approximately 6m beyond the upstream toe of the levee. Concrete headwall surrounded the flood gate and appeared to be in good condition. The gate was closed and partially buried/obstructed by debris. Beyond the flood gate was an unlined drainage channel through the beach. Water was ponding in the channel to 1578 Tree roots extended over crest for an approximate 18m length of levee. Large trees were located within 2.5m of the upstream toe Stormwater Inlet: The inlet comprised a concrete pipe and appeared to be partially obstructed by vegetation, eroded debris, leaf litter and litter. The diameter of the pipe could not be measured as a campsite had been set up over the inlet. Flood Gate: Concrete headwall surrounded the flood gate. The flood gate was almost completely buried by debris and was forced closed. General Various Dense tree coverage adjacent to upstream toe of levee. Chainages -110 to -20, 0 to 50, 90 to 510, 675 to 710, 810 to 1070, 1570 to (for clean out) 3 (for improvement) General - Increasing the height of the levee where required. 4.7, 4.8 &

66 Combined Action and Defects Inspection Report Control Levee Defect No Chainage Description J K Geotechnics Report Section(s) Box culvert investigation (if required). 4.2 (Item 4) 1 Priority Level Timber plank protection above box culvert. 4.2 (Item 4) Patchy tree coverage along downstream toe Erosion behind south-western wing wall of box culvert Restricting vehicular access onto the levee 4.2 (Item 5) Increasing the height of the levee and box culvert where required and construction of an unsealed access road The recommended priority levels are based on the following criteria: Priority Level Description 1 The hydraulic assessment and additional geotechnical investigations should be commissioned as soon as possible. 2 Preliminary works that should be completed as soon as practicable by KSC whilst the hydraulic assessment and additional geotechnical investigations are being completed. 3 Specific remedial works that will likely be included in the raising or reconstruction of the levee. Once the hydraulic assessment, additional geotechnical investigations and detailed design have been completed, this work must be carried out as soon as practicable.

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Scheduling Maintenance for Infiltration Basins and Trenches

Scheduling Maintenance for Infiltration Basins and Trenches Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections

More information

Seattle Public Utilities. Natural Drainage Systems (NDS) Maintenance Manual

Seattle Public Utilities. Natural Drainage Systems (NDS) Maintenance Manual Seattle Public Utilities Natural Drainage Systems (NDS) Maintenance Manual 1 Revision Date: December 2007 2 Table of Contents I. Overview... 4 II. How to Use This Manual... 4 III. NDS Contacts... 4 List

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

This plan forms one part of a suite of Asset Management Plans that have been developed:

This plan forms one part of a suite of Asset Management Plans that have been developed: E: D1: Levee Footpath Bank Asset Management Plan March July 2014 2015 This plan forms one part of a suite of Asset Management Plans that have been developed: A. Bridges B. Buildings C. Drainage D. Footpaths

More information

CLIFTY CREEK PLANT MADISON, INDIANA

CLIFTY CREEK PLANT MADISON, INDIANA 2015 DAM AND DIKE INSPECTION REPORT GERS-15-018 CLIFTY CREEK PLANT MADISON, INDIANA PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Annual Dam and Dike Inspection

More information

Document No 62/04/03 Issue Date: 16 December 2004 FLOOD DAMAGE REPAIRS TO LOCAL ROADS SPECIAL FUNDING ASSISTANCE PROCEDURE MANUAL

Document No 62/04/03 Issue Date: 16 December 2004 FLOOD DAMAGE REPAIRS TO LOCAL ROADS SPECIAL FUNDING ASSISTANCE PROCEDURE MANUAL Document No 62/04/03 Issue Date: 16 December 2004 FLOOD DAMAGE REPAIRS TO LOCAL ROADS SPECIAL FUNDING ASSISTANCE PROCEDURE MANUAL This document is owned and authorised by the Manager Budget and Program

More information

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS

PROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

3. Design Procedures. Design Procedures. Introduction

3. Design Procedures. Design Procedures. Introduction Design Procedures 3. Design Procedures Introduction This chapter presents a procedure for the design of natural channels. The chapter primarily focuses on those physical properties of the channel required

More information

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses.

Minimizes sediment and debris from entering storm drains that lead to waterways and watercourses. 4.5-p DRAIN INLET PROTECTION Alternative Names: DI protection, Drop Inlet Protection DESCRIPTION Storm drain inlet (DI) protection slows and ponds stormwater, and filters sediment and debris before it

More information

6.0 Results of Risk Analyses

6.0 Results of Risk Analyses 6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk

More information

Local Road Assessment and Improvement Drainage Manual

Local Road Assessment and Improvement Drainage Manual Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University

More information

Homeowner s Guide to Drainage

Homeowner s Guide to Drainage Homeowner s Guide to Drainage a scottsdale homeowner s guide to drainage produced by the city of scottsdale s stormwater management division Transportation Department TABLE OF CONTENTS Introduction 2 Drainage

More information

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT

ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT ASSET MANAGEMENT GUIDE FOR PROJECT DESIGN FORMAT 1. BACKGROUND There has been an increasing awareness of design features, which produce poor whole-of-life costs. These poor whole-of-life costs manifest

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

Asset Management Guide For Project Design Format

Asset Management Guide For Project Design Format NZ Transport Agency Page 1 of 6 Asset Management Guide For Project Design Format 1 Background There has been an increasing awareness of design features, which produce poor wholeof-life costs. These poor

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies. RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa Review Report and Recommendations for the Remediation of Flood Damage at the Berg River Causeway and the Dam Bypass Channel on Portion of Farms 1646 and 1014, Franschhoek Contact person: Colin Whittemore

More information

SEYMOUR FLOOD MITIGATION PROJECT PRELIMINARY DESIGN REPORT

SEYMOUR FLOOD MITIGATION PROJECT PRELIMINARY DESIGN REPORT SEYMOUR FLOOD MITIGATION PROJECT PRELIMINARY DESIGN REPORT Report prepared for the SHIRE OF MITCHELL October 2009 1 TABLE OF CONTENTS 1. Executive Summary 4 2. Background 9 2.1 Previous Studies 9 2.2 Modelled

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (BMP) PLAN REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site- Specific BMP Plans for projects. plan reviewers will use this checklist to review the Site-Specific

More information

Neversink River East Branch

Neversink River East Branch Neversink River East Branch Management Unit 10 Summary of Post-Flood Recommendations Intervention Level Full restoration of the stream reach including the eroding bank site between Station 38380 and Station

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

SE-10 STORM DRAIN INLET PROTECTION. Objectives

SE-10 STORM DRAIN INLET PROTECTION. Objectives STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,

Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Wolverhampton, WV6 0PJ Tel 01902 712200 Fax 01902 714096 e-mail sales@hy-tengabions.com

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices

More information

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY

SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY SCHEDULE 2 TO THE DEVELOPMENT PLAN OVERLAY Shown on the planning scheme map as DPO2 WAVERLEY GOLF COURSE, LYSTERFIELD VALLEY 1.0 Conditions and requirements for permits A permit to use and develop the

More information

Permeable Pavement Construction Guide

Permeable Pavement Construction Guide Permeable Pavement Construction Guide Permeable pavement at Olympic Park, Waitakere Final Construction result What are permeable pavements? Permeable pavements are hard surface paving systems that reduce

More information

Storm Drain Inlet Protection for Construction Sites (1060)

Storm Drain Inlet Protection for Construction Sites (1060) Storm Drain Inlet Protection for Construction Sites (1060) Wisconsin Department of Natural Resources Conservation Practice Standard I. Definition A temporary device installed in or around a storm drain

More information

GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS

GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS GUIDE TO SETTLEMENT OF CANTERBURY FLAT LAND CLAIMS April 2013 i Introduction This guide focuses on repair methods for some of the types of land damage that occurred on flat residential land as a result

More information

NDRRA Flood Restoration Guideline for Queensland Local Governments

NDRRA Flood Restoration Guideline for Queensland Local Governments NDRRA Flood Restoration Guideline for Queensland Local Governments Prepared by: IPWEAQ Page 1 of 34 Revision No.2.0 Quality Information Document Ref NDRRA Flood Restoration Guideline for Queensland Local

More information

Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage

Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage Pavement Asset Management Guidance Section 5.3: Condition Surveying and Rating - Drainage December 2014 Document Information Title Author Description Pavement Asset Management Guidance, Section 5.3: Condition

More information

STORM DRAINS CHAPTER 7

STORM DRAINS CHAPTER 7 CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect

More information

DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS

DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS DRAINAGE :: DRAINAGE CONCERN FREQUENTLY ASKED QUESTIONS The City of DeSoto s Department of Development Services is the point of contact for storm drainage related issues. The following are some frequently

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures. BMP: SUBSURFACE DRAIN Definition A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. PurRoses 1. To prevent sloping soils from becoming

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

FLOOD INFORMATION SERVICE EXPLANATORY NOTES

FLOOD INFORMATION SERVICE EXPLANATORY NOTES FLOOD INFORMATION SERVICE EXPLANATORY NOTES Part 1 About the flood maps Limitations of the mapping What the maps don t show Where to find more information Definitions of words used to describe flooding.

More information

Tobique Employment & Training

Tobique Employment & Training APPENDICES 3 Tobique Employment & Training Flood Mitigation July 30, 2012 Overview This proposal outlines the work required and budget for flood mitigation measures on Tobique First Nation which is required

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Watershed Works Manual

Watershed Works Manual National Rural Employment Guarantee Act Watershed Works Manual DRAINAGE LINE TREATMENT: GABION STRUCTURE Baba Amte Centre for People s Empowerment Samaj Pragati Sahayog September 2006 Drainage Line Treatment:

More information

Action plans for hotspot locations - Ash Study

Action plans for hotspot locations - Ash Study Appendix 9 Action plans for hotspot locations - Ash Study Ash Vale North 1. Local evidence indicates the culvert could not discharge during December 2013 because the outlet was blocked on the western side

More information

11.4 Voluntary Purchase. 11.5 House Raising and Flood Proofing

11.4 Voluntary Purchase. 11.5 House Raising and Flood Proofing 11.4 Voluntary Purchase As mentioned in Section 10 in certain high hazard areas of the floodplain, it may be impractical or uneconomic to mitigate flood hazard to existing properties at risk, or flood

More information

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein

More information

CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21

CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21 Issue: 2 Date: 26/09/08 Page: 1 of 21 TRACK AND CIVIL INFRASTRUCTURE CODE OF PRACTICE VOLUME TWO - TRAIN SYSTEM [CP2] DRAINAGE 2004 No part of this document may be reproduced without prior written consent

More information

Property Care White Papers. Site Drainage: Monitor and Maintain

Property Care White Papers. Site Drainage: Monitor and Maintain Monitor and Maintain Site Drainage Good site drainage is an important part of keeping water issues from affecting the building. The upkeep of existing systems should be an important part of any maintenance

More information

Chapter 5: Drainage, Ditches, and Culverts

Chapter 5: Drainage, Ditches, and Culverts Chapter 5: Drainage, Ditches, and Culverts chapter contents Characteristics of Good Drainage 82 Elements of Good Surface Drainage 82 Crown 82 Shoulders 82 Slope 82 Ditches 83 Culverts 83 Inlets 83 Optimal

More information

Flood Damage Report. Central Desert Regional Council Controlled Roads. Yuendumu to Mt Wedge road 57 Kilometre. Yuendumu to Nyirripi road 6 Kilometre

Flood Damage Report. Central Desert Regional Council Controlled Roads. Yuendumu to Mt Wedge road 57 Kilometre. Yuendumu to Nyirripi road 6 Kilometre Flood Damage Report Central Desert Regional Council Controlled Roads Yuendumu to Mt Wedge road 57 Kilometre Yuendumu to Nyirripi road 6 Kilometre Inspected on 29 th,30 th January and 02 nd,03 rd and 04

More information

Approved Natural Disaster Recovery Round Green Army projects

Approved Natural Disaster Recovery Round Green Army projects Approved Natural Disaster Recovery Round Green Army projects Project Title Project Description State Territory Belmont Wetlands East Coast This project will reduce erosion and revegetate and control weeds

More information

PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS

PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS Check here for Address or phone number change the fiscal year (July 1 June 30), and date(s) maintenance was performed. Under Inspection,

More information

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section:

8.1.3 General Design Guidelines. The following guidelines shall be used when designing inlets along a street section: . Introduction Presented in this chapter are the criteria and methodology for design and evaluation of storm sewer inlets located in Town of Castle Rock. The review of all planning submittals will be based

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information

NATURAL DISASTER ARRANGEMENTS JANUARY 2012 MONTH YEAR

NATURAL DISASTER ARRANGEMENTS JANUARY 2012 MONTH YEAR NATURAL DISASTER ARRANGEMENTS JANUARY 2012 MONTH YEAR TABLE OF CONTENTS Page Number 1 Introduction 3 Purpose of these Guidelines What Roads are eligible? What is a Declared Natural Disaster? Funding Responsibility

More information

Architectural Processing and Inspections for Home Mortgage Insurance

Architectural Processing and Inspections for Home Mortgage Insurance Page 1 of 5 [Text Only] Architectural Processing and Inspections for Home Mortgage Insurance Directive Number: 4145.1 SITE GRADING AND DRAINAGE GUIDELINES Construction complaints and structural defect

More information

UNDER DRAINAGE AND FILTER DESIGN

UNDER DRAINAGE AND FILTER DESIGN UNDER DRAINAGE AND FILTER DESIGN Tailings and HLP Workshop 28 April to 1 May 2010 INTRODUCTION The internal drainage is of crucial importance to the reliability and safety of a tailings dam throughout

More information

www.nams.au.com National Asset Management Strategy Australia

www.nams.au.com National Asset Management Strategy Australia DEVELOPMENT OF A ROAD ASSET REGISTER USING DIGITAL VIDEO TECHNOLOGY DUNGOG SHIRE COUNCIL Matt Ryeland, mailto:matthew.ryeland@cardno.com.au Senior Technical Officer, Management Services. Cardno Terry Wilson,

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.

Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. Small Dam Repair The Stone Lake Dam Story Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. 29601 1 Historical background of Stone Lake A series of three

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION

STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall

More information

Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office

Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office Lisgar District Basement Water Infiltration Investigation Part A Answers to Technical Questions 1. There has been a tremendous amount of work done everywhere along the creek. If there was nothing wrong

More information

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587

CCTV of Stormwater Systems. Cairns Regional Council. Commentary Guidelines #4037587 CCTV of Stormwater Systems Cairns Regional Council Commentary Guidelines Introduction Councils inherit assets through the donated asset process. In doing so, Councils immediately receive assets that are

More information

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN

SECTION 6A STORM DRAIN DESIGN Mar. 2002 S E C T I O N 6A STORM DRAIN - DESIGN S E C T I O N 6A STORM DRAIN - DESIGN 6A.l Scope 6A.2 Storm Water Quantity 6A.3 Storm Drain Hydraulics 6A.4 Depths 6A.5 Locations 6A.6 Curved Storm Drains 6A.7 Manholes 6A.8 Catch basins 6A.9 Storm Drain

More information

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations

More information

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk

1 Introduction. 1.1 Key objective. 1.2 Why the South Esk 1 Introduction 1.1 Key objective The aim of this study is to identify and assess possible options for improving the quality of the river channel and habitats in the River South Esk catchment whilst helping

More information

CHAPTER 7 DRAINAGE OF PAVEMENTS

CHAPTER 7 DRAINAGE OF PAVEMENTS CHAPTER 7 DRAINAGE OF PAVEMENTS 7-1. Drainage control Adequate drainage of surface and ground water is one of the most important considerations in the design, construction, and maintenance of roads, railroads,

More information

A guide to preventing structural damage

A guide to preventing structural damage A guide to preventing structural damage Home owners guide to planning landscaping and maintenance of foundations Structural damage can result from movement in clay soils caused by varying moisture conditions

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems

Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems Indiana State Department of Health Construction Guidelines for Gravity and Flood-Dose Trench Onsite Systems The septic tank-absorption field sewage treatment system is composed of two major elements; the

More information

The site is Lot 1 DP 837271. Survey of this lot and Willarong Road and Koonya Circuit is given in Figure 2.

The site is Lot 1 DP 837271. Survey of this lot and Willarong Road and Koonya Circuit is given in Figure 2. Our Ref : NA49913151-019-L02:BCP/bcp Contact: Dr Brett C. Phillips 8 th May 2015 Cardno (NSW/ACT) Pty Ltd ABN 95 001 145 035 The Manager Bunnings Group Limited, c/- C&M Consulting Engineers 1/142 James

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

Moving Small Mountains Vesuvius Dam Rehab

Moving Small Mountains Vesuvius Dam Rehab Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,

More information

Trenching and Excavation Safety

Trenching and Excavation Safety 1.0 ACTIVITY DESCRIPTION 1.1 This document provides basic safety guidelines related to excavation and trenching in pipeline construction activities. These guidelines are applicable to the locating, marking

More information

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods

DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES. Run-off Analysis Methods DOÑA ANA COUNTY DESIGN STORM CRITERIA GUIDELINES FOR COMMERCIAL AND RESIDENTIAL SITES Run-off Analysis Methods This document sets forth the minimum design, technical criteria and specifications for the

More information

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness 3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component

More information

WSUD maintenance guidelines. A guide for asset managers

WSUD maintenance guidelines. A guide for asset managers WSUD maintenance guidelines A guide for asset managers Table of contents Introduction 2 How to use the guidelines 3 1 Asset management framework 5 1.1 Types of maintenance 6 1.1.1 Proactive maintenance

More information

Essex County Council Flood Investigation Report

Essex County Council Flood Investigation Report Essex County Council Stock City of Chelmsford Rev Date Details Author Checked and Approved By 01 February 2015 Draft report for stakeholder consultation Ed Clarke Flood Investigation Engineer Lucy Shepherd

More information

Appendix C. Project Opportunities. Middle Twisp River (RM 7.8 18.12)

Appendix C. Project Opportunities. Middle Twisp River (RM 7.8 18.12) Appendix C Project Opportunities Middle Twisp River (RM 7.8 18.12) This table describes project opportunities by project area. Locator maps of the project opportunities are included below the table. Reach

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

Crossing creeks Stream crossings on farms

Crossing creeks Stream crossings on farms Crossing creeks Stream crossings on farms Looking after all our water needs Crossing creeks Stream crossings on farms Looking after all our water needs Department of Water 168 St Georges Terrace Perth

More information

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

Design Considerations for Water Storage Structures on Porous Foundation in South West Western Australia

Design Considerations for Water Storage Structures on Porous Foundation in South West Western Australia Design Considerations for Water Storage Structures on Porous Foundation in South West Western Australia Michael Ashley, Robert Wark GHD The construction of service reservoirs has been an integral part

More information

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM Giang Pham Hong, Michel Hotakhanh, Nga Pham Hong, Hoai Nam Nguyen, Abstract:Dams have been taken an important role in time and surface redistribution of water for

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

VEHICLE CROSSOVER INFORMATION PACK

VEHICLE CROSSOVER INFORMATION PACK VEHICLE CROSSOVER INFORMATION PACK CONTENTS Introduction Section A Section B Section C Section D Section E Criteria for approving a vehicle crossover application (Diagrams to demonstrate measurement criteria)

More information

FIRST RESPONSE: STORM DAMAGE MITIGATION OF A BMP FAILURE

FIRST RESPONSE: STORM DAMAGE MITIGATION OF A BMP FAILURE FIRST RESPONSE: STORM DAMAGE MITIGATION OF A BMP FAILURE Author: Audrey G. Beaulac, P.E., CPSWQ Company: (Hoyle, Tanner), Manchester, New Hampshire INTRODUCTION In early July 2013, 2 inches of rain fell

More information

Sutton Harbour Holdings PLC. March 2007

Sutton Harbour Holdings PLC. March 2007 Sutton Harbour Holdings PLC March 2007 Contents!! " # # $ % % &'(&'' ) ) ( * + ', *!$ -,!'! #. / $$ #% 00& ' 00&1 $ Executive Summary!! " WSP Development and Transportation has been engaged by Sutton

More information

NJ650.1404 Interception Drainage

NJ650.1404 Interception Drainage NJ650.1404 Interception Drainage Interception drainage is used to intercept surface and subsurface water. The investigation, planning, and construction of surface interception drains follow the requirements

More information