A case study on volatile demand

Size: px
Start display at page:

Download "A case study on volatile demand"

Transcription

1 A case study on volatile demand Connecting craftsmanship, QRM and Lean at Eijkelkamp Agrisearch Equipment BV Stef Tiggeloven,

2 Contents Introduction Current state Problem definition Leagility concept Steps to implement Lectoraat Lean / WCP 2

3 Introduction Lectoraat Lean / WCP 3

4 Introduction Eijkelkamp Agrisearch Equipment (EAE) system supplier of a wide range of equipment for soil and water research. Founded 1911 auger range: Small but important No sample, no... Strong focus on efficiency Mix of ERP and kanban-system Lectoraat Lean / WCP 4

5 Current state Starting point of project Lectoraat Lean / WCP 5

6 FTMS/Productrange 1 product family (+ 1 family related but not in project) 155 SKU's in total. 32 varieties of forged bodies. 1-2 FTE are directly involved (total 2-3 in related family) yearly demand 8000 assemblies Low risk of changes Relatively low costs of inventory Lectoraat Lean / WCP 6

7 MCT map 13 steps, 62 days leadtime Lectoraat Lean / WCP 7

8 Value stream map Lectoraat Lean / WCP 8

9 Classification of demand Variability of the demand size The coefficient of variation (CV), CV^2 =squared (standard deviation/average). Average demand interval The average number of time periods between successive demands (total number of periods devidedby the number of time periods with demand) Lectoraat Lean / WCP 9

10 Classification of demand source: Syntetos et al Lectoraat Lean / WCP 10

11 Demand characterisation EAE Source: author, based on Syntetos et al, 2005 Lectoraat Lean / WCP 11

12 Aggregated demand Aggregated demand full range of augers, , weekly demand total numbers of SKU sold year-week Total per week 4 week average 12 week average Lectoraat Lean / WCP 12

13 Demand analysis at EAE Lumpiness" of demand Forecasting is not possible with simple statistical tools. Also on semi aggregated level, demand is still Erratic or Lumpy. Inventory Management System therefore must have high responsiveness to meet demand. Aggregated level of full product range is relatively constant (compared to single SKU s). Total workload and capacity are within manageable limits. Current buffers not sufficient for required service level Lectoraat Lean / WCP 13

14 Problem definition 1. Demand of single SKU s is volatile and can not be forecasted with common methods. 2. Level of WIP is high, long lead times of subs, up to 9 weeks. 3. Planning and scheduling of processes is complex takes 2 days per week (!) daily changes in schedule Chaos ( flexotic?), disturbes rest of manufacturing 4. Service level is unsatisfactory (not measured for range, response time estimated 1-2 weeks 5. Workload is unbalanced and difficult to anticipate on (one week overtime, next week idle) Lectoraat Lean / WCP 14

15 Aim of the project (according to EAE) 1. Simplify and reduce planning and control effort on product range, 2. Service level of 95-99%: next day delivery, for as many products as possible (99%?) 3. Level demand to constant workload, make required 4. Reduce WIP and stocks (more: reduce the complixity). Lectoraat Lean / WCP 15

16 Leagility source: Christopher and Towill, 2001 Lectoraat Lean / WCP 16

17 Surge/base Demand Separation source: Christopher and Towill, 2001 Lectoraat Lean / WCP 17

18 Leagility 80/20 not an option, keep full range in same proces Decoupling point Product range is modular, parts are recurrent DP can be moved to assemble (weld) to order (#SKU from 155 to appr60) Surge base demand separation can level demand to capacity. Lectoraat Lean / WCP 18

19 Steps to implement (1) Move the customer decoupling point option 2 (Cristopherand Towill, 2001)to "partially create and deliver to order Create single kanbancontrolled buffers of heads, with sufficient safety levels Assemble products daily on customer sequence. Lectoraat Lean / WCP 19

20 Steps to implement (2) Give assembly of customer orders the highest priority in the group, option 3 (Cristopherand Towill, 2001), Spend rest of capacity on adding to buffers of heads. Add capacity when buffers are below safety level. Direct customer orders direct from sales to production Lectoraat Lean / WCP 20

21 Steps to implement (3) Work towards a situation with minimal setup times to be able to make every full end product on customer order Lectoraat Lean / WCP 21

22 Conclusion/summary QRM was starting point of analysis Smoothing of demand covered by leagility concept Next steps: Implement cell High level planning, POLCA(?): Planning and control simplified Various routings and combining of processteps to reduce leadtime Reduce setup times and batch (kanban) quantity to... Reduce buffers to minimal capacity buffer Lectoraat Lean / WCP 22

23 Lectoraat Lean / WCP 23

24 SKU classification Glenday Sieve Colour code Cumulative % of Sales Cumulative % of SKU range green 50% 6% yellow 95% 50% blue 99% 70% red last 1% last 30% Source: Glenday(2005) Lectoraat Lean / WCP 24

25 SKU classification SKU Cum percentage Type Percentage Sales number Sales Combi boorlich. 7 40,4% 40,4% Combi boorlich. 5 16,2% 56,6% Combi boorlich. 4 6,1% 62,7% Klei boorlich. 7 5,8% 68,5% Grind boorlich. 7 5,1% 73,6% Riverside boorlich. 7 4,1% 77,7% Combi boorlich. 10 4,0% 81,7% Zand boorlich. 7 2,9% 84,6% Riverside boorlich. 10 2,3% 86,9% Combi boorlich. 15 2,0% 88,9% Zachte klei boorlich. 7 1,9% 90,7% Grofzand boorlich. 7 1,7% 92,4% Combi boorlich. 6 1,5% 93,9% Combi boorlich. 12 1,2% 95,1% Klei boorlich. 10 1,22% 96,4% Grind boorlich. 10 0,75% 97,1% Combi boorlich. 8 0,68% 97,8% Zand boorlich. 10 0,59% 98,4% Riverside boorlich. 5 0,42% 98,8% Zachte klei boorlich. 10 0,27% 99,1% Klei boorlich. 8 0,25% 99,3% Combi boorlich. 20 0,22% 99,5% Grofzand boorlich. 10 0,20% 99,7% Riverside boorlich. 8 0,16% 99,9% Riverside boorlich. 15 0,10% 100,0% Combi boorlich. 4,5 0,0064% 100,0% Combi boorlichaam linksdr. 10 0,0024% 100,0% Combi boorlichaam linksdr. 7 0,0012% 100,0% Grind boorlich. 15 0,0000% 100,0% Cum percentage of product range 7% of SKU = 56,6% cum sales 48% of SKU = 95% cum sales 66% of SKU = 99% cum sales last 34% SKU = 1 % of sales Lectoraat Lean / WCP 25

26 Inventory management strategies (IMS) Inventory Optimisation high service level is key factor: a well defined buffer in the process is acceptable as long as it pull based (products are relatively low priced). reduction of WIP: use inventory to facilitate aspects 2 and 3. Reduce WIP to only one stage Lectoraat Lean / WCP 26

27 Inventory management strategies (IMS) Production and Scheduling Reduction in planning and control: costs are relatively high (17 hours per week) and non value adding. Group in manufacturing should be "self-managing" Capacity Management Balanced workload: Variability in total aggregated demand seems relatively low (appendix 2) Craftsmanship of forgers is not exchangeable Lectoraat Lean / WCP 27

28 EPEC Lean perspective: Glenday Sieve results Green: Optimize to one stream Yellow: standardize,add to green (or add to:) Blue: separate from green/yellow Red: eliminate? Pricing? Lectoraat Lean / WCP 28

29 Safety stocks Veiligheidsvoorraad: Voorraad bovenop afzet Meest eenvoudige benadering, bij wekelijkse bestelling: Vraag+ k x st.devvraag Betrouwbaarheid K (sigma) 95% 1,65 sigma 98% 2,06 sigma 99% 2,33 sigma Lectoraat Lean / WCP 29

30 Safety stocks Required safety stock Cum percentage Average 2013 Cum percentage Average Average per week 2013 Artikelnummer dim Omschrijving Groep Current stock 99% Saldo stock st.dev Totaal combi 7 Combi boorlich ,42% 46,2553% 63,792 48, Totaal combi 5 Combi boorlich ,18% 15,8575% 25,528 46, Totaal combi 10 Combi boorlich ,99% 6,8250% 6,302 4, Totaal combi 12 Combi boorlich ,22% 1,4648% 1,925 3, Totaal combi 15 Combi boorlich ,97% 2,7976% 3,113 3, Totaal combi 20 Combi boorlich ,22% 0,4725% 0,340 0, Totaal combi 4 Combi boorlich ,13% 5,0621% 9,679 9, Totaal combi 45 Combi boorlich. 4, ,00% 0,1309% 0,000 0, Totaal combi 6 Combi boorlich ,48% 2,4293% 2,340 2, Totaal combi 8 Combi boorlich ,68% 1,7823% 1,075 1, Totaal klei 10 Klei boorlich ,22% 1,7399% 1,925 3, Totaal klei 7 Klei boorlich ,79% 7,5713% 9,132 8, Totaal klei 8 Klei boorlich ,25% 0,6240% 0,396 0, Totaal links 10 Combi boorlichaam linksdr ,00% 0,0012% 0,000 0, Totaal links 7 Combi boorlichaam linksdr ,00% 0,0024% 0,000 0, Totaal z klei 10 Zachte klei boorlich ,27% 0,3502% 0,434 0, Totaal z klei 7 Zachte klei boorlich ,85% 1,7811% 2,925 2, Totaal zand 10 Zand boorlich ,59% 1,2261% 0,925 1, Totaal zand 7 Zand boorlich ,87% 4,3206% 4,528 3, Totaal grind 10 Grind boorlich ,75% 1,0904% 1,189 3, Totaal grind 15 Grind boorlich ,00% 0,0061% 0,000 0, Totaal grind 7 Grind boorlich ,06% 6,5233% 7,981 10, Totaal grofzand 10 Grofzand boorlich ,20% 0,3792% 0,321 0, Totaal grofzand 7 Grofzand boorlich ,72% 2,1882% 2,717 2, Totaal riv 10 Riverside boorlich ,34% 2,8654% 3,698 3, Totaal riv 15 Riverside boorlich ,10% 0,0642% 0,151 0, Totaal riv 5 Riverside boorlich ,42% 0,6821% 0,660 1, Totaal riv 7 Riverside boorlich ,11% 6,4852% 6,491 3, Totaal riv 8 Riverside boorlich ,16% 0,3465% 0,245 0,989 Totaal 553, , ,00% 157, ,273 Lectoraat Lean / WCP 30

Lean Strategies Used to Optimize Automation. Why Lean Six Sigma? Laboratory Goals. Decreased TAT. Accurate Results. LEAN Goals.

Lean Strategies Used to Optimize Automation. Why Lean Six Sigma? Laboratory Goals. Decreased TAT. Accurate Results. LEAN Goals. Lean Strategies Used to Optimize Automation Linda Stubbs, ASQ CSSBB Senior Workflow Specialist Why LEAN Six Sigma? Why Lean Six Sigma? Laboratory Goals Decreased TAT Accurate Results LEAN Goals Increase

More information

Push and Pull Production Systems

Push and Pull Production Systems Push and Pull Production Systems You say yes. I say no. You say stop. and I say go, go, go! The Beatles 1 The Key Difference Between Push and Pull Push Systems: schedule work releases based on demand.

More information

Take Time and Cost Out of Your Inventory and Supply Chain - Exploit the Constraints of Forecasting!

Take Time and Cost Out of Your Inventory and Supply Chain - Exploit the Constraints of Forecasting! Take Time and Cost Out of Your Inventory and Supply Chain - Exploit the Constraints of Forecasting! A Thought-Leadership Whitepaper from MCA Associates By Howard W. Coleman, Principal Introduction: Do

More information

ERP Support for Pull Production

ERP Support for Pull Production Trends in Production Control ERP Support for Pull Production Daryl Powell, Researcher & PhD Candidate Department of Production and Quality Engineering, Norwegian University of Science and Technology SINTEF

More information

Supply Chain Leaders Understanding and Improving Supply Chain Performance Where It Counts

Supply Chain Leaders Understanding and Improving Supply Chain Performance Where It Counts Leaders Understanding and Improving Performance Where It Counts What is the Leaders Programme? Leaders is an action-oriented, practical programme which identifies the most vital supply chain improvements

More information

Module 5 The R+ Available Stock Calculation

Module 5 The R+ Available Stock Calculation Welcome to Demand Driven Technologies, the home of Replenishment plus and module 5 of our education tutorials Understanding the R+ Available Stock Calculation This module is intended to provide a basic

More information

INVENTORY MANAGEMENT. 1. Raw Materials (including component parts) 2. Work-In-Process 3. Maintenance/Repair/Operating Supply (MRO) 4.

INVENTORY MANAGEMENT. 1. Raw Materials (including component parts) 2. Work-In-Process 3. Maintenance/Repair/Operating Supply (MRO) 4. INVENTORY MANAGEMENT Inventory is a stock of materials and products used to facilitate production or to satisfy customer demand. Types of inventory include: 1. Raw Materials (including component parts)

More information

ISE 421 QUANTATIVE PRODUCTION PLANNING

ISE 421 QUANTATIVE PRODUCTION PLANNING ISE 421 QUANTATIVE PRODUCTION PLANNING LECTURE III MRP, MRPII, ERP, APS Dr. Arslan ÖRNEK 2013 2014 Fall Term PRODUCTION PLANNING & SCHEDULING (PP&S) PP&S is one of the most critical activities in a manufacturing

More information

QRM POLCA. Hans-Heinrich Glöckner - Aldert van der Stoel Stef Tiggeloven - Vincent Wiegel - Jana Pejchinovska

QRM POLCA. Hans-Heinrich Glöckner - Aldert van der Stoel Stef Tiggeloven - Vincent Wiegel - Jana Pejchinovska QRM POLCA Hans-Heinrich Glöckner - Aldert van der Stoel Stef Tiggeloven - Vincent Wiegel - Jana Pejchinovska An initiative of HAN University of Applied Sciences Based on the work of Rajan Suri This product

More information

Basics of Supply Chain Management (BSCM) Curriculum

Basics of Supply Chain Management (BSCM) Curriculum Basics of Supply Chain Management (BSCM) Curriculum Version 4.0 Session 1 to Supply Chain Management to Manufacturing Role of Manufacturing Global Citizenship Manufacturing Business Model Business Environment

More information

"Kanban Do It Now but Do It Right" Workshop Illustrates the Importance of Kanban as a Tool in Lean Production

Kanban Do It Now but Do It Right Workshop Illustrates the Importance of Kanban as a Tool in Lean Production "Kanban Do It Now but Do It Right" Workshop Illustrates the Importance of Kanban as a Tool in Lean Production Helping to empower and motivate employees. Jeff Schaller, Ph.D. Just-In-Time (JIT) production

More information

TOOL FOR MAPPING MANUFACTURING CRTICAL-PATH TIME IN JOB SHOP ENVIRONMENT Chong Kuan Eng 1, How Whee Ching 2 1,2 Faculty of Manufacturing Engineering,

TOOL FOR MAPPING MANUFACTURING CRTICAL-PATH TIME IN JOB SHOP ENVIRONMENT Chong Kuan Eng 1, How Whee Ching 2 1,2 Faculty of Manufacturing Engineering, Sci.Int.(Lahore),26(4),1585-1589,2014 ISSN 1013-5316; CODEN: SINTE 8 1585 TOOL FOR MAPPING MANUFACTURING CRTICAL-PATH TIME IN JOB SHOP ENVIRONMENT Chong Kuan Eng 1, How Whee Ching 2 1,2 Faculty of Manufacturing

More information

Lean in the Supply Chain! MNASQ 10/12/2015. Advance your supply chain

Lean in the Supply Chain! MNASQ 10/12/2015. Advance your supply chain Lean in the Supply Chain! MNASQ 10/12/2015 Advance your supply chain Your Presenter: Ashley Yentz Career Focus Areas: Responsibilities in vision creation and deployment, project coordination, team leadership,

More information

Datasheet Electronic Kanban Ultriva vs. ERP ekanban Modules By Narayan Laksham

Datasheet Electronic Kanban Ultriva vs. ERP ekanban Modules By Narayan Laksham Datasheet Electronic Kanban Ultriva vs. ERP ekanban Modules By Narayan Laksham Summary: Several ERP vendors offer rudimentary Kanban modules to compliment their MRP systems. However, these Kanban modules

More information

Glossary of Inventory Management Terms

Glossary of Inventory Management Terms Glossary of Inventory Management Terms ABC analysis also called Pareto analysis or the rule of 80/20, is a way of categorizing inventory items into different types depending on value and use Aggregate

More information

Hessel Visser NCOI Les 6 A P 373. Operations Management, 7E: Chapter 14 en15

Hessel Visser NCOI Les 6 A P 373. Operations Management, 7E: Chapter 14 en15 1 Lecture Planning and Control 14 Enterprise Resource Planning (ERP) 15 Lean synchronization 16 Project Management (zie andere sheets) 17 Quality Management (zie andere sheets) Hessel Visser NCOI Les 6

More information

Lead Time Reduction in SME s; A Survey

Lead Time Reduction in SME s; A Survey Lead Time Reduction in SME s; A Survey - Research and experiences from the HAN LEAN-QRM Center - Wilfred Knol MSc http://www.han.nl/lectoraatlean Introduction Quantitative research on the relevance of

More information

Risk Pooling Chap. 14

Risk Pooling Chap. 14 Risk Pooling Chap. 14 Risk Pooling Theory Applications Differentiation Postponement/Delay Location, HP Case - handed out preparation questions 1. On page 1, it said We can t run our business with this

More information

Big Data for Supply Chain Optimization By: Anders Richter, SAS Institute, Denmark

Big Data for Supply Chain Optimization By: Anders Richter, SAS Institute, Denmark Big Data for Supply Chain Optimization By: Anders Richter, SAS Institute, Denmark Agenda Demand-Driven Planning & Optimization and Big data Inventory Optimization (IO) The Matas case Results and takeaways

More information

Five Tips to Achieve a Lean Manufacturing Business

Five Tips to Achieve a Lean Manufacturing Business Five Tips to Achieve a Lean Manufacturing Business Executive Overview Introduction The more successful manufacturers today are those with the ability to meet customer delivery schedules while maintaining

More information

A Pragmatic Approach to Inventory Management

A Pragmatic Approach to Inventory Management A Pragmatic Approach to Inventory Management By Björn Erlandsson and Jacob Duhan Applied Value s Series on Capital Efficiency Ref: CAP-1011 December 2008 Inventory management is an important area that

More information

講 師 : 周 世 玉 Shihyu Chou

講 師 : 周 世 玉 Shihyu Chou 講 師 : 周 世 玉 Shihyu Chou Logistics involves the following activities: sourcing and purchasing inputs, managing inventory, maintaining warehouses, and arranging transportation and delivery. There are three

More information

THE BEGINNER S GUIDE TO LEAN

THE BEGINNER S GUIDE TO LEAN THE BEGINNER S GUIDE TO LEAN Professor Daniel T Jones Lean Enterprise Academy Who am I? Writer Machine and Lean Thinking books Researcher on how to do lean everywhere! Founder of the non-profit Lean Enterprise

More information

Material Requirements Planning (MRP)

Material Requirements Planning (MRP) Material Requirements Planning (MRP) Unlike many other approaches and techniques, material requirements planning works which is its best recommendation. Joseph Orlicky, 1974 1 History Begun around 1960

More information

Managing the demand for spare parts

Managing the demand for spare parts SAP EXCELLENCE PRACTICE Managing the demand for spare parts ARTICLE By Mathias Maegaard Mikalsen Monthly demand for three intermittent spare parts Units 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15

More information

I. INTRODUCTION A. There are two aspects to an effective operating system: 1. Design 2. Control.

I. INTRODUCTION A. There are two aspects to an effective operating system: 1. Design 2. Control. Operations Control Chapter 8 CHAPTER OUTLINE I. INTRODUCTION A. There are two aspects to an effective operating system: 1. Design 2. Control. B. Effective operations control is attained by applying the

More information

Keep the balance with 8 inventory management viewpoints

Keep the balance with 8 inventory management viewpoints ARTICLE Keep the balance with 8 inventory management viewpoints BALANCE YOUR NET WORKING CAPITAL TIED UP IN INVENTORY WITH YOUR DESIRED DELIVERY PERFORMANCE By Christian Guldager,, cgu@implement.dk FIGURE

More information

Manufacturing Systems Modeling and Analysis

Manufacturing Systems Modeling and Analysis Guy L. Curry Richard M. Feldman Manufacturing Systems Modeling and Analysis 4y Springer 1 Basic Probability Review 1 1.1 Basic Definitions 1 1.2 Random Variables and Distribution Functions 4 1.3 Mean and

More information

Small Lot Production. Chapter 5

Small Lot Production. Chapter 5 Small Lot Production Chapter 5 1 Lot Size Basics Intuition leads many to believe we should manufacture products in large lots. - Save on setup time - Save on production costs Costs associated with Lots

More information

INVENTORY MANAGEMENT

INVENTORY MANAGEMENT 7 INVENTORY MANAGEMENT MGT2405, University of Toronto, Denny Hong-Mo Yeh Inventory management is the branch of business management that covers the planning and control of the inventory. In the previous

More information

ERP Meets Lean Management

ERP Meets Lean Management Meets Lean Management James M. Noblitt, CPIM, CIRM Sr. Management Consultant High-Tech meets No-Tech! Digital Lean Visual Work Orders Push Data Entry Reports Security/Access Data Accuracy Complicated Spread

More information

EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY

EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY EVERYTHING YOU NEED TO KNOW ABOUT INVENTORY Introduction Inventory is considered the necessary evil of the supply chain. In fact, there has been a whole movement; lean manufacturing that has tried to reduce

More information

Chapter 9. Inventory management

Chapter 9. Inventory management Chapter 9 Inventory management Slack et al s model of operations management Direct Design Operations Management Deliver Develop Supply network management Capacity management Inventory management Planning

More information

Combining Lean and Agile

Combining Lean and Agile An Integrated Approach to Supply Chain Strategy: Combining Lean and Agile Solutions Professor Martin Christopher Cranfield School of Management Cranfield University Cranfield Bedford MK43 0AL United Kingdom

More information

Lean Management. KAIZEN Training of Trainers. KAIZEN Facilitators Guide Page to.

Lean Management. KAIZEN Training of Trainers. KAIZEN Facilitators Guide Page to. Lean Management KAIZEN Training of Trainers KAIZEN Facilitators Guide Page to. Objectives of the session At the end of the session, trainees are able to: 1) Understand the philosophy on lean management

More information

Lecture No. 12: Delivery Improvement and Inventory System. Takahiro Fujimoto

Lecture No. 12: Delivery Improvement and Inventory System. Takahiro Fujimoto Business Administration Lecture No. 12: Delivery Improvement and Inventory System 1.Reduction of Production Period 2.Variety and Function of Inventory 3.Fixed-Quantity Order and Fixed-Period Order 4.Kanban

More information

The Lean Sustainable Supply Chain

The Lean Sustainable Supply Chain The Lean Sustainable Supply Chain How to Create a Green Infrastructure with Lean Technologies Robert Palevich Contents Foreword Preface xi xvii Part I: Applied Savings to the Collaborative Supply Chain

More information

Ud Understanding di inventory issues

Ud Understanding di inventory issues Lecture 10: Inventory Management Ud Understanding di inventory issues Definition of inventory Types of inventory Functions of inventory Costs of holding inventory Introduction to inventory management Economic

More information

J-Curve effect, 38, 274 276 JIT. See Just-in-Time Inventory Just Enough Design Initially (JEDI), 6, 283

J-Curve effect, 38, 274 276 JIT. See Just-in-Time Inventory Just Enough Design Initially (JEDI), 6, 283 A Accounting for change, 180, 224, 245 Accounting for rework, 224, 245 246 Activity Based Costing (ABC), 26 Adaptive behavior, emergence of, 109 Agile management theory and roles, 109, 185 Agile Manifesto

More information

Key Concepts: Week 8 Lesson 1: Inventory Models for Multiple Items & Locations

Key Concepts: Week 8 Lesson 1: Inventory Models for Multiple Items & Locations Key Concepts: Week 8 Lesson 1: Inventory Models for Multiple Items & Locations Learning Objectives Understand how to use different methods to aggregate SKUs for common inventory policies Understand how

More information

Appendix O MANUFACTURING YOUTH APPRENTICESHIP PRODUCTION OPERATIONS MANAGEMENT PATHWAY PRODUCTION OPERATIONS MANAGEMENT (UNIT 8)

Appendix O MANUFACTURING YOUTH APPRENTICESHIP PRODUCTION OPERATIONS MANAGEMENT PATHWAY PRODUCTION OPERATIONS MANAGEMENT (UNIT 8) Appendix O MANUFACTURING YOUTH APPRENTICESHIP PRODUCTION OPERATIONS MANAGEMENT PATHWAY PRODUCTION OPERATIONS MANAGEMENT (UNIT 8) Pathway: (Unit 8) PAGE 1 OF 17 Unit 8: Pathway 1. Assist to purchase materials

More information

Planning Optimization in AX2012

Planning Optimization in AX2012 Planning Optimization in AX2012 Streamline your manufacturing operations with Master Planning and Forecasting Kevin Cosman 11 June 2013 About the Presenter Kevin Cosman, Senior Solutions consultant with

More information

Pharmacy Supply Chain

Pharmacy Supply Chain Pharmacy Supply Chain A Structured Approach to Managing Pharmacy Inventory David Stead Chief Pharmacist Royal Bournemouth & Christchurch Hospitals David Owens Supply Chain Development Manager NHS Logistics

More information

GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE

GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE ECAP 21 / PROD2100 GESTION DE LA PRODUCTION ET DES OPERATIONS PICASSO EXERCICE INTEGRE 2004-2005 Prof : Pierre Semal : semal@poms.ucl.ac.be Assistants : Eléonore de le Court : delecourt@poms.ucl.ac.be

More information

Agenda. TPPE37 Manufacturing Control. A typical production process. The Planning Hierarchy. Primary material flow

Agenda. TPPE37 Manufacturing Control. A typical production process. The Planning Hierarchy. Primary material flow TPPE37 Manufacturing Control Agenda Lecture 2 Inventory Management 1. Inventory System Defined 2. Inventory Costs 3. Inventory classification 4. Economic order quantity model 5. Newsboy problem 6. Reorder

More information

Getting Started with Lean Process Management

Getting Started with Lean Process Management Getting Started with Lean Process Management Hi-Tec Exchange Conference San Francisco July 25, 2011 Missions To team with Organizational Leaders, Managers, & Employees to focus on customers & improve competitiveness,

More information

School of Management and Languages Capacity Planning

School of Management and Languages Capacity Planning School of Management and Languages Capacity Planning Dr Neil Towers 1 Learning Objectives a. To understand Capacity Planning and Control b. To manage the supply chain capabilities effectively Dr Neil Towers

More information

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling

TU-E2020 ADVANCED OPERATIONS MANAGEMENT. Demand management Sales & Operations Planning Master Production Scheduling TU-E2020 ADVANCED OPERATIONS MANAGEMENT Demand management Sales & Operations Planning Master Production Scheduling 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999

More information

Appendix Lean Glossary Page 1

Appendix Lean Glossary Page 1 Appendix Lean Glossary Page 1 Andon Board A visual control device in a work area giving the current status on performance to expectations and alerting team members to emerging issues. Batch-and- Queue

More information

Chapter 6. Inventory Control Models

Chapter 6. Inventory Control Models Chapter 6 Inventory Control Models Learning Objectives After completing this chapter, students will be able to: 1. Understand the importance of inventory control and ABC analysis. 2. Use the economic order

More information

Gaining Control: Exploring Push v Pull Manufacturing

Gaining Control: Exploring Push v Pull Manufacturing Gaining Control: Exploring Push v Pull Manufacturing InSync Solutions Paper 1 Contents 1 Push v Pull Planning and Execution Systems in Manufacturing 2 Plan-Driven Push-Based Systems 5 Customer Order-Driven,

More information

VALUE STREAM MAPPING ICONS

VALUE STREAM MAPPING ICONS Material Material ASSEMBLY Process I 300 Pieces 1 Day Inventory MRP Control Center "Go-See" Scheduling XYZ Corporation Outside Source Takt = 50 sec. C/T = 45 sec. C/O = 30 min. Uptime = 95% Scrap = 2%

More information

Strategic Framework to Analyze Supply Chains

Strategic Framework to Analyze Supply Chains Strategic Framework to Analyze Supply Chains 1 Andy Guo A Strategic Framework for Supply Chain Design, Planning, and Operation Part I: Understand the supply chain Part II: Supply chain performance Part

More information

Plan forecast optimise

Plan forecast optimise Plan forecast optimise Don t Forecast the future, CONTROL IT Reflex Business Forecasting breaks new ground. This is sales forecasting software with unique features that allow you to create real value for

More information

Lean Healthcare Simulation Segment I: Baseline Performance

Lean Healthcare Simulation Segment I: Baseline Performance Lean Healthcare Simulation Segment I: Baseline Performance Learning Objectives At the end of this module, you should be able to: Explain the mechanics and rules of the simulation Execute the process in

More information

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning

Universidad del Turabo MANA 705 DL Workshop Eight W8_8_3 Aggregate Planning, Material Requirement Planning, and Capacity Planning Aggregate, Material Requirement, and Capacity Topic: Aggregate, Material Requirement, and Capacity Slide 1 Welcome to Workshop Eight presentation: Aggregate planning, material requirement planning, and

More information

IMPACT OF PROCESS VARIABILITY ON LEAN MANUFACTURING SYSTEMS

IMPACT OF PROCESS VARIABILITY ON LEAN MANUFACTURING SYSTEMS IMPACT OF PROCESS VARIABILITY ON LEAN MANUFACTURING SYSTEMS Mel Adams and Bernard J. Schroer Center for Automation & Robotics University of Alabama in Huntsville Huntsville, AL 35899 adamsm@email.uah.edu

More information

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 -

BSCM Sample TEST. CPIM(Certified In Production & Inventory Management) - 1 - BSCM Sample TEST. 1. Which of the following demand fulfillment approaches typically provides the longest delivery time? A) Engineer-to-order. B) Make-to-order. C) Assemble-to-order. D) Make-to-stock. 2.

More information

Chapter 11. MRP and JIT

Chapter 11. MRP and JIT Chapter 11 MRP and JIT (Material Resources Planning and Just In Time) 11.1. MRP Even if MRP can be applied among several production environments, it has been chosen here as a preferential tool for the

More information

The Application of Lean Production Control Methods within a Process-Type Industry: The Case of Hydro Automotive Structures

The Application of Lean Production Control Methods within a Process-Type Industry: The Case of Hydro Automotive Structures The Application of Lean Production Control Methods within a Process-Type Industry: The Case of Hydro Automotive Structures Daryl Powell 1, Erlend Alfnes 1 and Marco Semini 2 1 Department of Production

More information

Lean Supply Chain Best Practice Process Benchmark Framework. Overview

Lean Supply Chain Best Practice Process Benchmark Framework. Overview Lean Best Process Benchmark Framework Overview This document draws from the results of an APICS 2004 survey on the development and adoption of lean principles in supply chain management. It does not represent

More information

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner

ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner ERP Course: Production and Materials Management Reading: Chapter 6 from Mary Sumner Peter Dolog dolog [at] cs [dot] aau [dot] dk 5.2.03 Information Systems September 16, 2008 2 Sales Finished and packaged

More information

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource.

APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource. APICS acknowledges the Basics of Supply Chain Management Committee for its contributions in the development of this resource. Jim Caruso, CPIM, CSCP (chair) Carol Bulfer, CPIM James F. Cox, Ph.D., CFPIM,

More information

Manufacturing Planning and Control for Supp Chain Management

Manufacturing Planning and Control for Supp Chain Management Manufacturing Planning and Control for Supp Chain Management Sixth Edition F. Robert Jacobs Indiana University William L. Berry The Ohio State University (Emeritus) D. Clay Whybark University of North

More information

Choosing Planning & Scheduling solutions for Metals

Choosing Planning & Scheduling solutions for Metals Choosing Planning & Scheduling solutions for Metals White Paper The planning and scheduling of metals production presents special problems because of the complexity of the manufacturing process and the

More information

Manufacturing Flow Management

Manufacturing Flow Management Manufacturing Flow Management Distribution D Distribution Authorized to Department of Defense and U.S. DoD Contractors Only Aim High Fly - Fight - Win Supply Chain Management Processes Information Flow

More information

New Ways to Painless Inventory Management. Ugne Kontare Business Development Manager ugne@soft4.eu +370 682 55216 www.soft4.eu

New Ways to Painless Inventory Management. Ugne Kontare Business Development Manager ugne@soft4.eu +370 682 55216 www.soft4.eu New Ways to Painless Inventory Management Ugne Kontare Business Development Manager ugne@soft4.eu +370 682 55216 www.soft4.eu Introduction What is Softera Baltic Softera Baltic is an enterprise resource

More information

Operations Management

Operations Management 11-1 Inventory Management 11-2 Inventory Management Operations Management William J. Stevenson CHAPTER 11 Inventory Management 8 th edition McGraw-Hill/Irwin Operations Management, Eighth Edition, by William

More information

Logistics Management SC Performance, SC Drivers and Metrics. Özgür Kabak, Ph.D.

Logistics Management SC Performance, SC Drivers and Metrics. Özgür Kabak, Ph.D. Logistics Management SC Performance, SC Drivers and Metrics Özgür Kabak, Ph.D. Outline Supply Chain Performance: Achieving Strategic Fit and Scope Competitive and supply chain strategies Achieving strategic

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 36 Location Problems In this lecture, we continue the discussion

More information

Lean Manufacturing and Six Sigma

Lean Manufacturing and Six Sigma Lean Manufacturing and Six Sigma Research Questions What have we done in the past? What must we do in the future? How do we know these are the correct actions? 1 Lean Definitions Key concepts of lean:

More information

15. How would you show your understanding of the term system perspective? BTL 3

15. How would you show your understanding of the term system perspective? BTL 3 Year and Semester FIRST YEAR II SEMESTER (EVEN) Subject Code and Name BA7201 OPERATIONS MANAGEMENT Faculty Name 1) Mrs.L.SUJATHA ASST.PROF (S.G) 2) Mr. K.GURU ASST.PROF (OG) Q.No Unit I Part A BT Level

More information

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부

CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 CHAPTER 6 AGGREGATE PLANNING AND INVENTORY MANAGEMENT 명지대학교 산업시스템공학부 Learning Objectives You should be able to: Describe the hierarchical operations planning process in terms of materials planning & capacity

More information

VALUE STREAM MAPPING KITS

VALUE STREAM MAPPING KITS Our Value Stream Mapping Icons are made of self-sticking notes (sticky notes) for an easy mapping experience. Each Icon is characterized by a symbol as well as its name, so that participants who are new

More information

Job Manager for Metal Fabrication

Job Manager for Metal Fabrication Job Manager for Metal Fabrication What makes Metal Fabrication unique? First, most metal shops are building to unique specifications. The Jobs are service type jobs, not production type jobs. Mass Production

More information

The rest of this document describes how to facilitate a Danske Bank Kanban game.

The rest of this document describes how to facilitate a Danske Bank Kanban game. Introduction This is a Kanban game developed by Sune Lomholt for Danske Bank Kanban workshop. It is based on Software development Kanban which can be found here: http://www.skaskiw.biz/resources.html The

More information

Business System Software

Business System Software Business System Software BUSINESS SYSTEM SOFTWARE For Custom Product Manufacturing Engineering Fabrication & Jobbing Food & Chemical Process Industries Distribution & Wholesale Sales, Service & Repair

More information

Live Learning Center. Solution-Driven Integrated Learning Paths. Make the Most of Your Educational Experience

Live Learning Center. Solution-Driven Integrated Learning Paths. Make the Most of Your Educational Experience Solution-Driven Integrated Learning Paths Educational Sessions Lean Global Supply Chain Basics of Operation Management Demand Management, Forecasting, and S & OP Professional Advancement Special Interest

More information

Inventory Management, Just-in-Time, and Backflush Costing

Inventory Management, Just-in-Time, and Backflush Costing Inventory Management, Just-in-Time, and Backflush Costing Inventory Management in Retail Organizations Inventory Management is planning coordinating controlling activities related to the flow of inventory

More information

VISUAL management techniques for optimum INVENTORY form, fit and function

VISUAL management techniques for optimum INVENTORY form, fit and function You won t GET LEAN... until you GET VISUAL! VISUAL management techniques for optimum INVENTORY form, fit and function Raw materials, work-in-process, finished goods, location and product flow Kanban Min/max

More information

Lean Kitting: A Case Study

Lean Kitting: A Case Study Lean Kitting: A Case Study Ranko Vujosevic, Ph.D. Optimal Electronics Corporation Jose A. Ramirez, Larry Hausman-Cohen, and Srinivasan Venkataraman The University of Texas at Austin Department of Mechanical

More information

Forecasting Workshop: Intermittent Demand Forecasting

Forecasting Workshop: Intermittent Demand Forecasting Workshop: Intermittent Demand Software and Freeware for Intermittent Demand Nikolaos Kourentzes nikolaos@kourentzes.com Introduction Research over the last years has developed multiple methods and innovations

More information

NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES

NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES NETWORK BUSINESS SYSTEMS SOFTWARE SYSTEM DOCUMENTATION MANUFACTURING SYSTEM FEATURES WORK ORDERS Standard Mfg. vs. Full Mfg./MRP Manufacturing Target date, open date, closed date You can make and buy the

More information

ADVANTAGES OF E-KANBAN SYSTEM COMPARED TO CLASSIC KANBAN SERVING PRODUCTION LINE

ADVANTAGES OF E-KANBAN SYSTEM COMPARED TO CLASSIC KANBAN SERVING PRODUCTION LINE 1 st Logistics International Conference Belgrade, Serbia 28-30 November 2013 ADVANTAGES OF E-KANBAN SYSTEM COMPARED TO CLASSIC KANBAN SERVING PRODUCTION LINE Vasa V. Svirčević Lames d.o.o., vasasv@hotmail.com

More information

MRP, ERP och JIT. Styrningsnivåer. Johann Packendorff. The development of ERP. Increasing impact on the whole supply

MRP, ERP och JIT. Styrningsnivåer. Johann Packendorff. The development of ERP. Increasing impact on the whole supply MRP, ERP och JIT Johann Packendorff Styrningsnivåer The development of ERP Increasing impact on the whole supply network Manufacturing Resource Planning (MRPII) Material Requirements Planning (MRP) Web-integrated

More information

The Last Planner System of Production Planning & Control. Glenn Ballard Trondheim, Norway May 21, 2014

The Last Planner System of Production Planning & Control. Glenn Ballard Trondheim, Norway May 21, 2014 The Last Planner System of Production Planning & Control Glenn Ballard Trondheim, Norway May 21, 2014 Outline Peculiarities of ETO projects Characteristics of construction and shipbuilding Last Planner

More information

Lean Principles by Jerry Kilpatrick

Lean Principles by Jerry Kilpatrick Lean Principles by Jerry Kilpatrick Introduction Lean operating principles began in manufacturing environments and are known by a variety of synonyms; Lean Manufacturing, Lean Production, Toyota Production

More information

Lean supply chain control in Hydro Automotive Structures

Lean supply chain control in Hydro Automotive Structures Lean supply chain control in Hydro Automotive Structures Håkon Fauske 1 Erlend Alfnes 2 Marco Semini 2 1 SINTEF Technology and Society, Operations Management, N-7465 Trondheim, Norway; email: hakon.fauske@sintef.no

More information

PERFORMANCE ANALYSIS OF A CONTRACT MANUFACTURING SYSTEM

PERFORMANCE ANALYSIS OF A CONTRACT MANUFACTURING SYSTEM PERFORMANCE ANALYSIS OF A CONTRACT MANUFACTURING SYSTEM Viswanadham.N 1, Vaidyanathan.G 2 The Logistics Institute- Asia Pacific National University of Singapore Singapore 11926 mpenv@nus.edu.sg 1 engp9778@nus.edu.sg

More information

Basic Queuing Relationships

Basic Queuing Relationships Queueing Theory Basic Queuing Relationships Resident items Waiting items Residence time Single server Utilisation System Utilisation Little s formulae are the most important equation in queuing theory

More information

ERP emphasizes organization, discipline, and control.

ERP emphasizes organization, discipline, and control. Page 1 The objective of this white paper is to provide a basic road map for companies wishing to merge MRP and Lean Manufacturing methods. Illustration 1 ERP Planning and Control Dan Reed Planning Demand

More information

Antti Salonen KPP227 - HT 2015 KPP227

Antti Salonen KPP227 - HT 2015 KPP227 - HT 2015 1 Inventory management Inventory management concerns short-range decisions about supplies, inventories, production levels, staffing patterns, schedules and distribution. The decisions are often

More information

Rules to Consider. All work shall be highly specified as to content, timing, sequence, and outcome.

Rules to Consider. All work shall be highly specified as to content, timing, sequence, and outcome. Lean Manufacturing An operational system that maximizes Value Added, reduces Essential Support and eliminates Waste in all processes throughout the Value Stream. What is Value-added? What is Essential

More information

Lean manufacturing and ERP: How to leverage ERP to get lean

Lean manufacturing and ERP: How to leverage ERP to get lean E-Book Lean manufacturing and ERP: How to leverage ERP to get lean A manufacturing firm adopting the principles of lean manufacturing can effectively leverage the company s ERP system during its transition

More information

Chapter 11. Lean synchronization

Chapter 11. Lean synchronization Chapter 11 Lean synchronization Slack et al s model of operations management Direct Design Operations Management Deliver Develop Supply network management Capacity management Inventory management Planning

More information

How LEAN is QRM? Dirk Van Goubergen (dirk@vangoubergen.com) 2014 Van Goubergen P&M gcv - Lille Belgium

How LEAN is QRM? Dirk Van Goubergen (dirk@vangoubergen.com) 2014 Van Goubergen P&M gcv - Lille Belgium How LEAN is QRM? Dirk Van Goubergen (dirk@vangoubergen.com) 1 V1.0 Who am I? Dirk Van Goubergen Lean : Studying, learning, researching, coaching implementations for more than 20 years of which 8 years

More information

www.mesa.org 2008 North American Plant-to-Enterprise Conference September 21-23, Orlando, FL

www.mesa.org 2008 North American Plant-to-Enterprise Conference September 21-23, Orlando, FL Applying Lean, Six Sigma, MES, and Sense & Respond to Improve Yields and Reduce the COGS John Rassieur Associate Partner IBM Supply Chain Planning & Operations www.mesa.org 2008 North American Plant-to-Enterprise

More information

World Class Manufacturing

World Class Manufacturing World Class Manufacturing The right tool for the right purpose Year(s) Strategic Supply Chain Design & Operational Strategies Sales & Operations Planning SCP Tools Months Tactical Master Planning / Supply

More information