1 Trnkova BRNO Supplier Quality Manual Zetor Tractors approved by/date Koláček Jiří Design Mng. Vavroušek Milan QA Mng. Hodovanec Petr Logistic Mng. Shimoyama Yasuhiro Procurement Mng. Tichý Luděk Engineering Mng.
2 TABLE OF CONTENTS TABLE OF CONTENTS QUALITY POLICY AT ZETOR TRACTORS, A. S AREA OF APPLICATION OF THE ZETOR TRACTORS, A. S. SUPPLIER QUALITY MANUAL 3 3 SCOPE DEFINITION TERMS AND DEFINITIONS OF THE SUPPLIER QUALITY MANUAL DEFINITION OF THE CATEGORIZATION OF THE COMPONENTS ACRONYMS AND ABBREVIATIONS TERMS QUALITY PLANNING APPROVAL PROCEDURE ENGINEERING SAMPLES APPROVAL (SAMPLES PROCEDURES) Documentation needed for the Engineering Samples Approval The declaration of Engineering Samples Approval APPROVING FOR THE PILOT ( 0 ) RUN Documents for Approval for the Pilot Run The Approval for the Pilot Run Declaration THE DEVIATION APPROVAL AUDIT DOCUMENTATION AND REFERENCE SAMPLE KEEPING CLAIM PROCEDURES A SIGNIFICANT NUMBER OF NON-CONFORMAL PIECES, AFFECTING THE ZETOR TRACTORS, A. S. PRODUCTION LINE OPERATION A NUMBER OF NON-CONFORMAL PIECES THAT WILL NOT AFFECT THE ZETOR TRACTORS, A. S. PRODUCTION LINE OPERATION DIRECTLY THE REMEDY AND PRECAUTIONARY MEASURES 8D-REPORT SUPPLIERS QUALITY RATING APPENDICES Supplier Quality Manual 2/28
3 SUPPLIER QUALITY MANUAL 1 Quality Policy at Zetor Tractors, a. s. One of the main goals of the Zetor Tractors, a. s. company is to achieve a high quality production and delivery of its products (without defects) to the customers. This goal can be achieved only by a coordinated procedure during all the operations within the value-creating chain. The suppliers are an integral part of this chain. On this account, it is necessary to insist on continual improving and subsequent process standardization at the Supply Chain Management (SCM). We believe that the application of the following procedures is the only way to achieve out goals; therefore all the procedures contained in this manual are mandatory for all our present and future suppliers. 2 Area of Application of the Zetor Tractors, a. s. Supplier Quality Manual This Supplier Quality Manual describes and defines the requirements on suppliers and serves as an agreement on quality between Zetor Tractors, a. s. and its suppliers. Zetor Tractors, a. s. expects an intensive cooperation from its suppliers, aimed to the prevention and quality ensuring in all phases of the process, especially in the phase of planning, implementation and delivery. The supplier is in principle held liable for the quality of purchased components within the whole delivery. The requirements from the Zetor Tractors, a. s. Supplier Quality Manual should be transferred by all suppliers towards the sub-suppliers. Zetor Tractors, a. s. is expecting a continuous and consistent realisation of imposed methods and procedures. The company Zetor Tractors, a. s. reserves its right to check the realization of this methods and procedures within audits. 3 Scope Definition This manual is effective as of 1 April 2008 and is mandatory for all the suppliers supplying Zetor Tractors, a. s. 4 Terms and Definitions of the Supplier Quality Manual 4.1 Definition of the Categorization of the Components All purchased components are divided into 4 categories: Supplier Quality Manual 3/28
4 Category A Critical components These are components that have direct impact on security, health protection and environment. Category B Functionally important components These are components that have direct impact on the product (tractor) operation; its failure results in expensive repairs. Category C Other and catalogue components These are components that are important from the functional point of view; their failure disables only some less important function of the product (tractor). Category D Standardized components These are components that are fabricated according to binding international standards and are not part of categories neither A nor B. 4.2 Acronyms and Abbreviations QMS Quality Management System ppm parts per million the number of non-conforming components of one million of delivered components FMEA Failure Mode and Effect Analysis ISIR Initial Sample Inspection Report MSA Measurement System Analysis SCM Supply Chain Management SRC Sourcing VUTR Tractor Research Institute (Výzkumný ústav traktorů) VZŘ Samples Procedures VSTK Input Control 4.3 Terms Component is an individual piece, part or the final result. Process is a set of interconnected sources and activities that transform the inputs into outputs. Cover sheet (ISIR) is a document that is required as an application for approval; the supplier confirms in it that all the controls and tests performed on the components prove conformity with customers requirements. Component submission for approval means the withdrawal of a small amount of components of a significant lot that were produced by imposed production tools, processes and time standards. The components for approval are checked for all technical parameters. Reference sample is a component that is submitted to the customer in order to release the production. Supplier Quality Manual 4/28
5 Specifications are the technical characteristics for judging the acceptability of the component s characteristics. Submission level is the range of documents required when submitting the components. Visual-appearance component is a component that will be visible after finishing the vehicle. The customer will indicate the visual-appearance components on technical drawings. In such a case, the separate approval of the appearance is required before submitting the component. Pilot run is the first portion of serial production after the approval of the components; serves to check if the supplier complies with the parameters of the approved components. 5 Quality Planning The supplier undertakes to plan, organize and implement the production process and quality provision at its own liability, in order to meet all the quality provision requirements posed on the product. The pre-production phases have to be properly planned, including control. The supplier has to determine the goals and evaluate them regularly. The bilateral designation of contact persons within the area of quality and sourcing is a condition of a successful cooperation based on confidence between Zetor Tractors, a. s. and the supplier. Zetor Tractors, a. s. requires a quality provision system from the supplier, according to the categorization of the components produced by the supplier. Components category A B C D QMS requirements Has to be certified by QMS according to the international quality standards (TS 16949, QS 9000, VDA 6.1, ISO ) Has to be certified by QMS according to the international quality standards (TS 16949, QS 9000, VDA 6.1, ISO ) Doesn t have to be certified by QMS, but there has to be a qualityprovision system verified by Zetor Tractors, a. s. Has to be certified by QMS according to the international quality standards (TS 16949, QS 9000, VDA 6.1, ISO ) 6 Approval Procedure Approving the components for manufacturing is always required according to the scope of the Supplier Quality Manual. Supplier Quality Manual 5/28
6 The supplier also applies at Zetor Tractors, a. s. for approval before the first delivery in the following cases: - Using alternative structural design, specifications or materials, different from those originally approved for the component. - Manufacturing using new or changed tools, stamping dies, moulds, etc, including additional or substitute tools. - Manufacturing using repaired equipment or tools or equipment or tools relocated to a different supplier. - Change of the supplier of the component, materials or services. - Manufacturing following any changes in manufacturing methods or procedures. - Relocation of the manufacturing or applying a new production facility, - Component to be re-delivered after an interruption of supply longer than 6 months. 6.1 Engineering Samples Approval (Samples procedures) Releasing of samples runs according Zetor Tractors, a. s. requirements. The approval of the samples from the supplier is realized according to the effectively given documentation, approved by Zetor Tractors, a. s. The samples have to be submitted for approval in cases under the chapters 3, 6, Documentation needed for the Engineering Samples Approval The supplier will deliver the following documents to Zetor Tractors, a. s. together with the samples Component categorization Document A B C D 01 Cover sheet (ISIR) V V V V 02 Samples V V V V 03 Design documentation V V V V 04 Dimensional report V V V N 05 Material certificate V V V N 06 Data sheet regarding the safety of the material V N N X 07 Process Flowchart V V N X 08 Surface testing V V V N 09 Process FMEA N X X X 10 List of means of control N N N X 11 Documents on approved modifications V V V X 12 Control plan V V V N Supplier Quality Manual 6/28
7 13 Process capability (CA) N X X X 14 Measurement equipment capability (R&R) N X X X 15 Packaging instructions, delivery marking V V V V 16 List of approved sub-suppliers V V N N 17 Technical specifications tests X X X X V The supplier has to supply it for samples procedures and store a copy at a convenient place. N The supplier has to store it at a convenient place and show it to the customer upon request. X The supplier has to create and present it to the customer upon request and store it at a convenient place. Cover sheet (ISIR) The supplier, in conjunction with the SRC Department, will present the request for sample approval ISIR together with all the requirements for the approval process (see Appendix 1). Samples The supplier will provide samples manufactured using the same tools, measurement facilities, processes, materials, staff, operation, environment and technological parameter settings to be used within the serial production. The SRC is liable for providing the samples and mutual approval of the design documentation. The supplier has to label the samples properly and number them (for example, see Appendix 2). Design documentation We distinguish: a) The drawing is owned by Zetor Tractors, a. s. or VUTR the supplier will get the drawing and manufacture the required component following it b) The drawing is owned by the supplier the drawing has to be approved by VUTR. Approval procedure: 1. The supplier will deliver the drawing of the component to Zetor Tractors, a. s., or VUTR 2. VUTR approves the drawing 3. VUTR will insert the supplier s drawing of the component into the VUTR-stamped drawing comp. XZY xxx.xxx.xxx- Zetor Tractors a.s. XX.XXX.XXX / Supplier Quality Manual 7/28
8 The supplier will provide the constructional documentation of the product, component or product detail and will send the samples with a copy of the constructional documentation with positioning of the measured proportions (marked according to the Dimensional report) and subsidiary drawings and sketches used within the manufacturing process. The design documentation has to contain information on the surface finish. In case of a catalogue component, the supplier will provide the catalogue sheet containing the drawing with important dimensions. Dimensional report The supplier will provide the characteristics and a complete dimensional report with the measurement methods. The dimensional report shall contain all the important dimensions of individual parts and other important parameters (accessories control...). It is used to verify the dimensional requirement according to the manufacturing documentation. All the dimensions, characteristics and specifications that are marked out in the technical documentation and in the control plan (for example, see Appendix 3). Material certificate The supplier will provide a proof of individual materials used within the manufacturing of the respective component (unit) and a proof that the data conform with all the requirements of Zetor Tractors, a.s. (according to ČSN EN , for example Appendix 4) Data sheet regarding the safety of the material Where appropriate, the supplier will provide the safety data sheet of the material (colours, plastic...) (for example see Appendix 5). Process Flowchart The supplier will provide the process flowchart that clearly describes all the steps and the progression of the manufacturing process and satisfies the requirements and needs of Zetor Tractors, a. s. (starting with input control, ending with despatching) (for example see Appendix 6). Surface testing The supplier will provide data on the quality of surface finish (colour, zinc, chrome, mechanical pre-finishing, chemical pre-finishing, coating specification, colour shade, gloss scale, coating thickness, coating type for repairs and repair proceedings...). Process FMEA The supplier will provide the failure mode and effect analysis for the process. Supplier Quality Manual 8/28
9 List of means of control The supplier will provide the list of measurement equipment, preparations, models and instruments used to ensure the quality within the manufacturing process of the components. The customer can ask for a proof of calibration and the accuracy of the measuring instrument. Documents on approved modifications (Modification sheet) The supplier provides any documents on approved constructional modifications that are not included into the documentation so far and are already used on the component (for example see Appendix 7). Control plan The supplier will provide the control plan for the component and the process that defines all the methods used for control, management and control instruction combined with the key parameters and characteristics control (for example see Appendix 8). Process capability (CA) The goal of this requirement is to find out whether the process is likely to produce components that will meet the Zetor Tractors, a. s. requirements. Measurement equipment capability (R&R, MSA) The supplier will provide a study on the variation in the measurement system for all new or modified measurement and test instruments and equipment, based on the repeatability and reproducibility values of the measurement and testing methods. Packaging instructions The supplier will fill-in and provide the Packaging instruction sheet, where it will specify the packaging specifications (see Appendix 9). Each portion, including the pilot run, has to be labelled with the Declaration of completed and quality delivery (see Appendix 10). List of approved sub-suppliers The supplier will provide a list of sub-suppliers approved by the supplier to inform Zetor Tractors, a. s. about the origin of the components. Technical specifications tests The supplier will provide the record of the technical specification tests of the component, especially required by the client. Supplier Quality Manual 9/28
10 The tests are realised in all cases when the components have some characteristics specification (climatic, material, appearance, noise, function, reliability...). The supplier performs all the tests resulting from the technical documentation. If the supplier is not able to perform the required special measurement, it will ensure the testing in a qualified external test laboratory or, in case of special agreement, in the Zetor Tractors, a. s. test laboratory. If the supplier uses a third-party test laboratory for the tests, the results are stated on its headed paper The declaration of Engineering Samples Approval When the samples procedures are concluded, one evaluated copy of the ISIR, with the samples procedures evaluation, will be sent back to the supplier. The output of the approval process is the Engineering Samples Approval. The result can be as follows: APPROVED - the Zetor Tractors, a. s. criteria were met and the supplier can provide a portion of the component for the pilot run (see chapter 6.2). CONDITIONALLY APPROVED the supplier can provide the pilot run according to the documentation and Zetor Tractors, a. s. order. Together with the pilot run, a plan of corrections realization has to be submitted for approval. In case this plan is not submitted or is not realised, the supplier cannot supply unless it meets all the required criteria. NOT APPROVED it means that the application, samples supplied or the documentation attached does not meet the Zetor Tractors, a. s. requirements. The supplier cannot deliver the pilot run and it has to apply for new samples procedures at SRC department in Zetor Tractors, a. s. The samples procedures release does not relieve the supplier from liability for the quality of the products. Incomplete records and incomplete documentation will automatically lead to the disapproval of the samples procedures. 6.2 Approving for the Pilot ( 0 ) Run After releasing the samples (see chapter 6.1), the supplier has to deliver the pilot run to Zetor Tractors, a. s. to verify the compliance of the serial supplies with the samples approved Documents for Approval for the Pilot Run The supplier has to label the pilot run properly (see Appendix 11). Together with the pilot run, the supplier will provide the following documents according to an agreement with Zetor Tractors, a. s.: Supplier Quality Manual 10/28
11 Dimensional report The supplier shall always provide the dimensional report, regardless of the result of the samples proceedings (see chapter 6). The supplier provides the characteristics and a complete dimensional report with the measurement methods. The dimensional report shall contain all the important dimensions of individual parts and other important parameters (accessories control...). It is used to verify the dimensional requirement according to the manufacturing documentation. All the dimensions, characteristics and specifications that are marked out in the technical documentation and in the control plan (for example, see Appendix 3). Material certificate The supplier will provide the material certificate after an agreement with a Zetor Tractors, a. s. representative, depending on the result of the samples procedures. The supplier will provide a proof of individual materials used within the manufacturing of the respective component (unit) and a proof that the data conform with all the requirements of Zetor Tractors, a.s. (according to ČSN EN , for example Appendix 4) The Approval for the Pilot Run Declaration When the pilot run approvals is concluded, one evaluated copy of the ISIR, with the pilot run evaluation, will be sent back to the supplier. The output of the approval process is the Approval for Serial Manufacturing. The result can be as follows: APPROVED - the Zetor Tractors, a. s. criteria were met and the supplier can deliver to the serial manufacturing. CONDITIONALLY APPROVED the supplier can deliver to the serial manufacturing according to the documentation and Zetor Tractors, a. s. order. Together with the first delivery, a plan of corrections realization has to be submitted for approval. In case this plan is not submitted or is not realised, the supplier cannot supply unless it meets all the required criteria. NOT APPROVED it means that the application, pilot run supplied or the documentation attached does not meet the Zetor Tractors, a. s. requirements. The supplier cannot deliver to the serial manufacturing and it has to apply for new samples proceedings at SRC department in Zetor Tractors, a. s. THE SUPPLIER CANNOT DELIVER THE PRODUCT BEFORE THE DELIVERY OF THE APPROVAL OF SERIAL MANUFACTURING SUPPLY. Supplier Quality Manual 11/28
12 6.3 The Deviation Approval In case that the supplier is not able to keep the parameters agreed within the Samples Procedures during a certain period of time, it has to send a Deviation Approval Request to the Zetor Tractors, a. s., SRC Department, before delivering the components. The supplier has to request the Deviation Approval in writing (by , fax and others). 6.4 Audit Zetor Tractors, a. s., as a customer, has the right to examine the QMS, the process capability of the conformity of the products with the audit. The external audit at the supplier is realised by commissioned employers of the Zetor Tractors, a. s. Quality Department. The results of the audit inform about the capability of the examined area of audit and draw the attention to the possibilities of improvement. Within the scope of the audits realised by Zetor Tractors, a. s. at the supplier, the supplier undertakes to: grant the information on organizational set-up, quality provision and management, safety and environment answer all the questions related to the quality provision grant access to the suppliers premises to the Zetor Tractors, a. s. employers in order to find out the audit-related information. The audit date will by announced by Zetor Tractors, a. s. sufficiently in advance. The output of the audit will be sent to the supplier. 6.5 Documentation and Reference Sample Keeping Zetor Tractors, a. s. keeps the complete documentation on all measurements and tests related to every Approval Request Submission. The conformity with all the dimensional, chemical, metallurgical, physical and other requirements arises from the documentation. The samples are identified and the date of approval by the customer is stated on them. If keeping of the samples is difficult due to their dimensions, these requirements can be amended or cancelled in writing by the approving department of Zetor Tractors, a. s. Unless stated otherwise, the samples will be kept by the suppliers. Together with the request, a sample labelled with the Approval Declaration will be delivered to the supplier. 7 Claim Procedures After discovering the non-conformance of the delivered approved components in Zetor Tractors a.s., the non-conformance announcement is sent to the supplier. The Claim Procedures, depending on the criticalness of the non-conformance found, can be as follows: Supplier Quality Manual 12/28
13 7.1 A significant number of non-conformal pieces, affecting the Zetor Tractors, a. s. production line operation In case of a non-conformance found in more delivered components, or in case of a non-conformal delivery that might affect the production fluency at Zetor Tractors, a. s., the supplier is immediately informed on the non-conformance found by phone and , using the 8D-Report (see chapter 7.3). This information is always provided by the respective Claim Department operator of the Input Control. The supplier has to react as directed in 8D-Report. By closing the weekly production at Zetor Tractors, a. s., all the information is processed on the last day of the week. After the data processing at the beginning of the following, the Claim Department operator sends the Claim List (see Fig. 1) to the supplier that serves as a basis for the statistician claim processing. The supplier fills in the document and sends it back to Zetor Tractors, a. s. within 20 working days at the latest. 7.2 A number of non-conformal pieces that will not affect the Zetor Tractors, a. s. production line operation directly In case that the non-conformance was found only in several pieces or the whole portion was suspended that would not affect the production fluency at Zetor Tractors, a. s. directly, only the Claim List (see Fig. 1) is sent to the supplier at the beginning of the following week. This form is sent by the Claim Department operator of the Input Control (VSTK PQA). The supplier fills in the document and sends it back to Zetor Tractors, a. s. within 20 working days at the latest. If the supplier does not express its opinion on the claim within the limits stated above, the claim is considered admitted in behalf of Zetor Tractors, a. s. The claims will subsequently appear in the supplier rating (see chapter 8.2 Suppliers Quality Rating). Fig.1 Claim List 7.3 The Remedy and Precautionary Measures 8D-Report The 8D-Report is a tool to document the eight steps for the team problem solving process (Appendix 12). Precautionary Measures: These are the measures to eliminate the possible non-conformance causes. Supplier Quality Manual 13/28
14 They make use of the methods that serve to estimate the risk of possible non-conformance, reveal the possible causes, consider its consequences and adopt measures to prevent their appearance even before the task/project realization. Immediate Measures: They eliminate the non-conformance of the product; impede its future use as well as the penetration into the following operations, workplaces and especially to the customer. They eliminate the non-conformance with the environmental objectives, company target values and the environmental legislation. Corrective Measures: They eliminate the non-conformance causes and Prevent their re-appearing. 8 Suppliers Quality Rating The client rates 2 indicators on a monthly basis (for the respective month): a) The quality of the supplies to Zetor Tractors, a. s.: Defectiveness [ppm] = Number of non-conformal pieces/number of total pieces delivered in a portion * The rules for the defectiveness calculations: In case that the whole portion is returned to the supplier, the whole number of pieces is counted into the number of non-conformal pieces In case the portion is sort out by Zetor employees, the whole number of pieces is counted into the number of non-conformal pieces In case the portion is sort out by supplier s employees in the Zetor Tractors, a. s premises, only the defective pieces are counted into the number of non-conformal pieces b) The tractors-in-operation component quality (Number of failures for supplier and month) Number of failures (for supplier and month) = The component quality at the tractors within the warranty period Supplier Quality Manual 14/28
15 The quality targets are determined individually for every supplier in December and are based on the actual quality level and the continuous improvement requirement. The targets are valid as of 1 January of the following year for a period of 12 months. The total score is a weighted average with the following weights: the quality of supplies to Zetor a.s: 0,70. the tractors-in-operation component quality: 0,30. Point evaluation: Maximum: 100 points Minimum: 0 points Performance score: Preferred supplier Acceptable supplier Needs improvement Unacceptable supplier points points points 29 0 points Supplier Quality Manual 15/28
16 9 Appendices Appendix 1: COVER SHEET Supplier Quality Manual 16/28
17 Appendix 2: SAMPLES LABELLING Supplier Quality Manual 17/28
18 Appendix 3: DIMENSIONAL REPORT Supplier Quality Manual 18/28
19 Appendix 4: MATERIAL CERTIFICATE Supplier Quality Manual 19/28
20 Appendix 5: DATA SHEET REGARDING THE SAFETY OF THE MATERIAL Supplier Quality Manual 20/28
21 Supplier Quality Manual 21/28
22 Appendix 6: PROCESS FLOWCHART Supplier Quality Manual 22/28
23 Appendix 7: DOCUMENT ON APPROVED MODIFICATIONS (MODIFICATIONS SHEET) Supplier Quality Manual 23/28
24 Appendix 8: CONTROL PLAN Supplier Quality Manual 24/28
25 Appendix 9: PACKAGING INSTRUCTIONS Supplier Quality Manual 25/28
26 Appendix 10: DECLARATION OF COMPLETED AND QUALITY OF DELIVERY Supplier Quality Manual 26/28
27 Appendix 11: THE PILOT 0 RUN LABELLING Supplier Quality Manual 27/28
28 Appendix 12: 8D-REPORT Supplier Quality Manual 28/28
Supplier quality guideline. VOSS Automotive Group Issue 02.06.2014 Rev00
Supplier quality guideline VOSS Automotive Group Issue 02.06.2014 Rev00 Table of Contents 1. General requirements 1.1 Scope of application 1.2 Quality objectives 1.3 Quality management system 1.4 Supplier
Forth Engineering (Cumbria) Limited QUALITY MANUAL. Quality Manual Issue 4 Updated April 2012. Authorised by: Managing Director.
Quality Manual Issue 4 Forth Engineering (Cumbria) Limited QUALITY MANUAL Copy Number: 1 The information contained in this Manual is the property of Forth Engineering (Cumbria) Limited and must not be
Quality Assurance Agreement
QUALITY ASSURANCE AGREEMENT APPENDIX 2 To the Development Framework Agreement To the Manufacturing und Supply Agreement Quality Assurance Agreement between Willi Elbe Gelenkwellen GmbH & Co. KG Hofäckerstraße
GLB QM 02. Supplier Quality Manual 03. 7/11/12 Supplier Quality 1 of 18. Revision Level. Issue Date Issuing Department Page
7/11/12 Supplier Quality 1 of 18 7/11/12 Supplier Quality 2 of 18 Table of Contents 1.0 Introduction 3 2.0 Manual 4 2.1 Application 4 2.2 Quality Management System of the Supplier 4 2.3 Quality Management
Application for Approved (Overseas/Local) Third Party Inspection Agency for Lifting Equipment
Occupational Safety and Health Division 18 Havelock Road #03-02 Singapore 059764 Tel: 64385122 www.mom.gov.sg [email protected] Application for Approved (Overseas/Local) Third Party Inspection Agency
Agreement on Quality, Occupational Health and Safety, Environmental Protection and Social Responsibility (Quality Assurance Agreement)
Agreement on Quality, Occupational Health and Safety, Environmental Protection and Social Responsibility (Quality Assurance Agreement) between Robert Bosch GmbH Robert-Bosch-Platz 1, 70839 Gerlingen, Germany
Comparison ISO/TS 16949 (1999) to VDA 6.1 (1998)
1 APPLICABILITY VDA 6.1: Section: 3.1; 7 new: In addition to the applicability for supplier sites for production, services and their subcontractors for: products and production materials, or services like
Ege Fren Ege Fren San. ve Tic. A.Ş.
Page : 1 / 8 1. Purpose: This manual is formed in order to create a business environment based on a partnership understanding with our suppliers, determine and develop our relationships in this context
STEEL fabrication quality SySTEmS guideline
STEEL fabrication quality systems guideline Copyright 2002 by Canadian Institute of Steel Construction All rights reserved. This book or any part therof must not be reproduced in any form without written
Quality Management System
LH Sleightholme Ltd, Westfield Works, Helperthorpe, Malton, North Yorkshire YO17 8TQ Quality Management System MANUAL ISO 9001:2008 This Quality Management System Manual has been issued on the authority
PPG SUPPLIER DEVELOPMENT ASSESSMENT
Supplier: Address: Products: Assessment Date: Assessment Team: Certification: Supplier Contacts Position E-mail Phone General Comments: Assessment Results Summary Sections Non-conformity Action Point Quality
Supplier Quality Requirements
Key Elements Procedures # 2 Supplier Quality Requirements Section List of content Page 1.0 Foreword 2 2.0 Definitions and acronyms 2 3.0 Basic Quality Requirements 3 4.0 Part Specific Quality Requirements
EUROPEAN INSPECTION AND CERTIFICATION COMPANY S.A.
EUROPEAN INSPECTION AND CERTIFICATION COMPANY S.A. 89 CHLOIS & LIKOVRISEOS STR. - 144 52 METAMORFOSI TEL: +30 210 6253927, 210 6252495 INTERNET SITE: www.eurocert.gr E-mail: [email protected] FAX: +30
Quality Management System Manual ISO9001:2008
Quality Management System Manual ISO9001:2008 Controlled Copy Rev. 3 Page 1 of 21 7/1/13 Table of Contents Company Profile...5 Past...5 Present...5 Mission...5 Vision...5 Locations...6 1 Scope...6 1.1
UNCONTROLLED COPY FOR REFERENCE ONLY
CLOVER MACHINE AND MFG. 800 MATHEW ST. #101 SANTA CLARA, CA 95050 727-3380 727-7015 fax REVISION: DATE: PAGE 1 OF 45 QUALITY POLICY MANUAL DISTRIBUTION LIST: President Purchasing Manager Vice President
ISO 14001:2004 Environmental Management System Manual
ISO 14001:2004 Environmental Management System Manual Company Name/Logo Document No Rev Uncontrolled Copy Controlled Copy Date COMPANY PROPRIETARY INFORMATION Prior to use, ensure this document is the
Compliance Management Systems
Certification Scheme Y03 Compliance Management Systems ISO 19600 ONR 192050 Issue V2.1:2015-01-08 Austrian Standards plus GmbH Dr. Peter Jonas Heinestraße 38 A-1020 Vienna, Austria E-Mail: [email protected]
Measuring equipment in a laboratory.
Measuring equipment in a laboratory. Laboratory and metrology are two words that practically do not function separately. They are integrally connected to measuring equipment for tests and measurements.
ISO 9001:2008 Requirements Explained - An Adobe PDF File for Use on a Network System
1-2 3 4 5 6 9 9 29 37 44 57 64 67 70 77 85 90 93 97 101 110 112 113 122 125 127 135 139 146 150 157 161 165 168 172 175 180 187 190 193 201 206 209 212 216 227 233 235 247 251 258 264 272 274 286 1 of
Product Liability Risk Control Checklist
Product Liability Risk Control Checklist Appendix C1 This material will help you evaluate your products liability exposure. It is designed to enable you to focus on areas that need to be addressed to safeguard
Quality Assurance Agreement (QAA)
Quality Assurance Agreement (QAA) History and Release Notes: Version Date Acronym 0.1 15.04.2010 AB Draft 0.2 10.06.2010 AB Revision in the core team 1.0 28.03.2011 AB,RK, RH Release Status of revision;
SQM-H. This Handbook is a summary of the processes and documents of the supplier quality management 1/13
SQM-H Supplier Quality Management Handbook MAHLE Behr - global This Handbook is a summary of the processes and documents of the supplier quality management 1/13 Scope of Application The Supplier Quality
ISO/IEC 17025 QUALITY MANUAL
1800 NW 169 th Pl, Beaverton, OR 97006 Revision F Date: 9/18/06 PAGE 1 OF 18 TABLE OF CONTENTS Quality Manual Section Applicable ISO/IEC 17025:2005 clause(s) Page Quality Policy 4.2.2 3 Introduction 4
AS9100 Quality Manual
Origination Date: August 14, 2009 Document Identifier: Quality Manual Revision Date: 8/5/2015 Revision Level: Q AS 9100 UNCONTROLLED IF PRINTED Page 1 of 17 1 Scope Advanced Companies (Advanced) has established
GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM
GUIDE TO IMPLEMENTING A REGULATORY FOOD SAFETY AUDITOR SYSTEM FEBRUARY 2016 2 Contents Introduction... 4 Scope and objectives... 5 Scope... 5 Objectives... 5 Responsibilities... 5 The role of the licensee
MINIMUM AUTOMOTIVE QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR SUB-TIER SUPPLIERS
MINIMUM AUTOMOTIVE QUALITY MANAGEMENT SYSTEM REQUIREMENTS FOR SUB-TIER SUPPLIERS CONTENTS 1. CONTROL PLANS 2. PROCESS APPROACH 3. PERFORMANCE 4. INTERNAL AUDITING 5. CONTROL OF NON-CONFORMING PRODUCT 6.
General Description of The CMC- Services
STANDARD FOR CERTIFICATION No.1.1 General Description of The CMC- Services JANUARY 2013 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version The
Guidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables
(1987) Guidelines for the Acceptance of Manufacturer's Quality Assurance Systems for Welding Consumables 1. General 1.1 Introduction 1.1.1 The present guidelines are to serve as a supplement to the IACS
Quality Agreement Template
Quality Agreement Template Prepared by Dan O Leary Ombu Enterprises, LLC 3 Forest Ave. Swanzey, NH 03446 603-209-0600 This document is intended to form the basis for a Supplier Agreement. The document
JOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
Copies of this document shall be classified either as Controlled or Uncontrolled, and shall be identified as such on the cover sheet.
INTRODUCTION This document describes an inspection system broken down into four separate levels. When Inspection Level IV is invoked, this system meets the requirements of former MIL-I-45208A. The primary
Supplier Manual. Version 2013_1.4
Supplier Manual Version 2013_1.4 I Content COVER SHEET...I CONTENT...... II I. Introduction... 1 II. Basic requirements... 2 III. Qualification process... 3 1. Selection and qualification process... 4
AS9100 B to C Revision
AS9100 B to C Revision Key: Additions Deletions Clarifications 1.2 Application AS9100C Key Additions This standard is intended for use by organizations that design, develop and/or produce aviation, space
Supplier Quality Assurance
Supplier Quality Assurance Preface We strive to continually improve our process performance by meeting quality objectives. It is imperative that our suppliers operate under the zero defects and 100% on
TERMS AND CONDITIONS OF PURCHASING Europe Version as of July 2009
TERMS AND CONDITIONS OF PURCHASING Europe Version as of July 2009 Unless otherwise agreed in writing in framework contracts, orders and individual contracts, the following TERMS AND CONDITIONS OF PURCHASING
Measuring instruments in industry.
Measuring instruments in industry. Measuring instruments that are present in any branch of industry, are subject to different levels of supervision, like in case of laboratories. Supervision relates to
GENERAL CONTRACT OF USE FOR WAGONS GCU
GENERAL CONTRACT OF USE FOR WAGONS GCU Edition dated 1 January 2016 CONTENTS PREAMBLE 5 CHAPTER I OBJECT, SCOPE OF APPLICATION, TERMINATION, FURTHER DEVELOPMENT OF THE CONTRACT, DISCONTINUANCE OF BEING
Generic CMMS Quality Assurance Plan
Generic CMMS Quality Assurance Plan Scope In accordance with the Quality Policy, the Quality System of CMMS is based upon the requirements and structure of ISO (the International Organization for Standardization)
Enhanced calibration High quality services from your global instrumentation partner
Products Solutions Services Enhanced calibration High quality services from your global instrumentation partner Services 2 Calibration One trusted advisor Get the best to meet all your critical application
General Contractual Terms and Conditions of KRÁLOVOPOLSKÁ SLÉVÁRNA, s.r.o.
General Contractual Terms and Conditions of KRÁLOVOPOLSKÁ SLÉVÁRNA, s.r.o. 1. General provisions 1.1. These terms and conditions (TC) govern the sale of products and services (hereinafter as goods ) of
TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS. LEC (Company Audit) Guidance Notes
TRANSPORT FOR LONDON (TfL) LOW EMISSIONS CERTIFICATE (LEC) GUIDANCE NOTES FOR THE COMPANY AUDIT PROCESS LEC (Company Audit) Guidance Notes Glossary of Terms Transport for London (TfL) London Low Emission
MSC Group Chain of Custody (CoC) Guidance for Non-Reduced Risk Groups
MSC Group Chain of Custody (CoC) Guidance for Non-Reduced Risk Groups 1. About this document This document is a non-normative guidance document intended to help companies understand CoC requirements. The
KEBA 2014 We reserve the right to make technical modifications. No liability accepted for information provided. All rights reserved.
Supplier Handbook Contact address KEBA AG Headquarters, Gewerbepark Urfahr, A-4041 Linz phone: +43 732 7090-0, fax: +43 732 730910, e-mail: [email protected], www.keba.com KEBA Group worldwide Austria Germany
ROMANIAN AUTOMOTIVE REGISTER PRODUCTS CERTIFICATION BODY
CE T PRODUCTS CERTIFICATION ROMANIAN AUTOMOTIVE REGISTER PRODUCTS CERTIFICATION BODY 391A Calea Griviţei,distr.1, zip code 010719, Bucharest Tel/fax: (4021) 350.82.88 code: DG-01-13, ediţia 3, revizia
QSS 0: Products and Services without Bespoke Contracts.
QSS 0: Products and Services without Bespoke Contracts. Amendment History Version Date Status v.1 Dec 2014 Updated For 2015 deployment Table of Contents 1. DEFINITIONS 3 2. INTRODUCTION 3 3. WORKING WITH
Purchase Order Clauses and Conditions
Purchase Order Clauses and Conditions All purchase orders for materials, special processes, machining and fabrication services and end items are subject to the following requirements: General Requirements:
IRIS International Railway Industry Standard
English Addendum, 19th June 2008 IRIS International Railway Industry Standard Hier kann ein kleiner Text stehen Hier kann ein kleiner Text stehen Hier kann ein kleiner Text stehen Chapter 1 3 IRIS Certification
Supplier Requirements Manual M M 0 3
Supplier Requirements Manual M M 0 3 Conformance to this manual is a requirement for all of Merrill Technologies Group and Ranger s suppliers & subcontractors, unless otherwise specified on purchase orders.
Example of a food company quality
Appendix A manual Example of a food company quality Contents Date: 13/03/95 RME-QLMN-OO Page 1 of 3 Section Title ISO 9001 reference 01 In trod uction 02 Purpose 03 Scope 04 Definitions 05 Management responsibility
Company Quality Manual Document No. QM Rev 0. 0 John Rickey Initial Release. Controlled Copy Stamp. authorized signature
Far West Technology, Inc. ISO 9001 Quality Manual Document No.: QM Revision: 0 Issue Date: 27 August 1997 Approval Signatures President/CEO Executive Vice President Vice President/CFO Change Record Rev
Application for Approval of Overseas Inspection Agency for Pressure Vessels
Occupational Safety and Health Division 18 Havelock Road #03-02 Singapore 059764 Tel: 64385122 www.mom.gov.sg [email protected] Application for Approval of Overseas Inspection Agency for Pressure Vessels
SUPPLIER QUALITY MANAGEMENT SYSTEM QUESTIONNAIRE
Company Name Street Address City, State, Zip code Phone Number Fax Company Website Email Address ORGANIZATION NAME PHONE NUMBER EMAIL ADDRESS President/CEO General Manager Engineering Manager Production
Supplier Quality Management System Audit Checklist (ISO 9000:2000, TS 16949:2002)
Supplier Quality Management System Audit Checklist (ISO 9000:2000, TS 16949:2002) Supplier: Plant/Location: Date: Audit Team: Scope of Audit: Number of C.A.R. s: Corrective Action Due: Potential suppliers
CORPORATE QUALITY MANUAL
Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance
Quality Management System Manual
Effective Date: 03/08/2011 Page: 1 of 17 Quality Management System Manual Thomas C. West Eric Weagle Stephen Oliver President ISO Management General Manager Representative Effective Date: 03/08/2011 Page:
VELUX General Quality Requirements
VELUX General Quality Requirements Introduction In VELUX we want to work towards zero defects and it is our belief that the quality of the products is best secured at our suppliers thereby enabling ship
Supplier Quality Requirements (SQR) for External Process and/or Product Providers
Supplier Quality Requirements (SQR) for External Process and/or Product Providers Document Revision History Revision No Revision Date Revision Description Approved By Apr 2, 2 Initial Release Joel Sodowsky
ACCEPTANCE CRITERIA FOR QUALITY DOCUMENTATION (AC10) June 2014
ACCEPTANCE CRITERIA FOR QUALITY DOCUMENTATION (AC10) 1.0 INTRODUCTION June 2014 1.1 Purpose: The purpose of this acceptance criteria is to establish requirements for information that is provided to ICC-ES
ABSTRACT. The Guidelines Section F is related to the Purchasing requirements of NSQ100 (Chapter 7.4). Summary
Page 1 / 9 ABSTRACT This document is the Section F to NSQ-100 Guidelines. Its objective is to help to the understanding of NSQ-100 requirements through some examples or recommendations and descriptions
COMMISSION REGULATION (EU)
L 122/22 Official Journal of the European Union 11.5.2011 COMMISSION REGULATION (EU) No 445/2011 of 10 May 2011 on a system of certification of entities in charge of maintenance for freight wagons and
Quality Manual ALABAMA RESEARCH & DEVELOPMENT. This Quality Manual complies with the Requirements of ISO 9001:2008.
ALABAMA RESEARCH & DEVELOPMENT This complies with the Requirements of ISO 9001:2008. Prepared By: Phyllis Olsen Release Date: 03/19/09 Quality Policy & Objectives s quality policy is to achieve sustained,
Surgi Manufacturing Quality Manual
Surgi Manufacturing Page 1 of 18 Approvals: QA: Eng. Mgt. : A Date: 18Aug98 1. Introduction... 4 1.1 Scope... 4 1.2 Purpose... 4 1.3 Authority... 4 1.4 Issue of the Manual... 4 1.5 Amendments... 4 1.6
TOOLING DEFINITIONS, COST AND AUDIT GUIDELINES
INTRODUCTION AND SCOPE This document sets forth the rights of Lear Corporation or its subsidiaries or affiliates (Lear) with regard to the auditing of 1) tooling paid for by Lear and used either (a) by
Helical Products Co., Inc.
Q01 GENERAL REQUIREMENTS 1. Supplier Responsibilities 1.1. Delivery Certification By delivering products or services on the Contract, the Supplier certifies that such products or services are in compliance
QUALITY MANAGEMENT PLAN
QUALITY MANAGEMENT PLAN Project Name EfW CHP Facility, North Yard, Devonport Project Number: C1005 Location: North Yard, Devonport Dockyard, Plymouth Approved by: Dated: Signed: KIER Project Manager Reviewed
IKM-I-K-01E Standard conditions of purchase IKM Gruppen Side 1 av 6
IKM-I-K-01E Standard conditions of purchase IKM Gruppen Side 1 av 6 Løvås Svein Firma/Company: IKM Gruppen AS 1. GENERAL 1.1 These conditions of purchase shall apply unless otherwise agreed in writing.
RTP s NUCLEAR QUALITY ASSURANCE PROGRAM
RTP s NUCLEAR QUALITY ASSURANCE PROGRAM RTP operates under one quality program, whether you purchase products that are commercial grade, nuclear safety-related or industrial safety compliant (IEC 61508).
ISO/TS 16949:2002 Guidance Document
ISO/TS 16949:2002 Guidance Document Introduction ISO/TS 16949:2009 emphasizes the development of a process oriented quality management system that provides for continual improvement, defect prevention,
GLOBAL AEROSPACE PROCEDURE
1 of 13 1. PURPOSE: This procedure establishes the minimum PPG Aerospace requirements for a Supplier's Quality Plan. These requirements pertain to the documentation and inspection/testing necessary to
CUSTOMER SPECIFIC REQUIREMENTS
CUSTOMER SPECIFIC REQUIREMENTS For Use With ISO 9001:2008 & ISO/TS 16949:2009 Page 1 SYSTEMS POLICY MANUAL CONTENTS Revision History Approval Document Distribution and Control General Application Background
Supplier Manual. for Hutchinson GmbH, Mannheim
Supplier Manual for Hutchinson GmbH, Mannheim Prepared by Elke Stelz Version V. 1.0. Last change made on 14.05.2013 Print date from 14.05.2013 roxtra Q Hutchinson - Purchasing Page 1 of 15 Contents 1.
LinkTech LLC 3000 Bunsen Ave. #A Ventura, CA 93003
D LT-422-001 Page 1 of 12 QUALITY MANUAL LinkTech LLC 3000 Bunsen Ave. #A Ventura, CA 93003 Based on ISO 9001:2008 D LT-422-001 Page 2 of 12 INTRODUCTION: This Quality Manual establishes the quality system
Article 1: Subject. Article 2: Orders - Order Confirmation
GENERAL CONDITIONS OF PURCHASE Article 1: Subject 1.1 The following general conditions of purchase (the "General Conditions") establish the contractual conditions governing the purchase of raw materials,
Quality Assurance Agreement with Production Material Suppliers. History of revisions
Modifications S 296001 Part 1 revision 2008/11 to 2015/04 Editorial changes (displayed in green letters) Project Classification PE changed to "Risk Level RL" also in Appendices 2 to 5 Chapter 4: SupplyOn
Production Part Approval Process AIAG PPAP 4 th Edition
Production Part Approval Process AIAG PPAP 4 th Edition Supplier Production Part approval process GHSP 11/24/2014 What is PPAP? Defines generic requirements for production parts approval, including production
Supplier Quality System Requirements
AUTOMOTIVE AXLES LIMITED Supplier Quality System Requirements Supplier Quality System Requirement, New Release, January 20, 2014 Page 1 AAL QUALITY POLICY We shall be a world class Automotive Tier I organisation
Supplier Quality Agreement EK 25
1. Purpose and Scope of Agreement Supplier Quality Agreement EK 25 1.1. In order to exceed the expectations and ensure the satisfaction of its customers, Benteler is committed to achieving a level of quality
Criminal Justice Offender Tracking System Certification Program Requirements
U.S. Department of Justice Office of Justice Programs National Institute of Justice Criminal Justice Offender Tracking System Certification Program Requirements NIJ CR-1004.00.00 June 2012 NCJ xxxxxx National
Food Safety and Quality Management System
Introduction The company has planned, established, documented and implemented a food safety and quality management system for the site, which is maintained in order to continually improve its effectiveness
Management System Procedure. 4.06 30 004 N 4/01/2012 2 of 14
4.06 30 004 N 4/01/2012 2 of 14 TABLE OF CONTENTS 1. Introduction 1.1 Policy and Vision 1.2 Purpose 1.3 Scope 1.4 Responsibility 2. Quality System Requirements 2.1 ISO/TS 16949: 2009 and Alternatives 2.2
VDA Structure Component Requirement Specification. Module I CRS Universal Requirements. <Title> <Number> Version 1.0
VDA Structure Component Requirement Specification Module I CRS Universal Requirements Version 1.0 Technical department/function Release Name Date Signature CRS author Technical department
BLOOM AND WAKE (ELECTRICAL CONTRACTORS) LIMITED QUALITY ASSURANCE MANUAL
130 Wisbech Road Outwell Wisbech Cambridgeshire PE14 8PF Tel: (01945) 772578 Fax: (01945) 773135 Copyright 2003. This Manual and the information contained herein are the property Bloom & Wake (Electrical
Quality Assurance Agreement (QAA)
Quality Assurance Agreement (QAA) between W. GESSMANN GmbH Eppinger Str. 221, D-74211 Leingarten - hereafter "W. GESSMANN" - and Company Road, house number Postal code and city - hereafter called "Supplier"
Welcome! Frank Teleso. Quality Manager
Welcome! We appreciate your interest in Excelsior s Quality Management System. The objective of this document is to provide a quick method for you to do a preliminary quality qualification of Excelsior
Quality Assurance Manual. QAM-2013-Rev2
QAM-2013-Rev2 President s Policy and Authorization of Quality Control The management system for the Steel Structural Fabrication of Pinnacle Industrial Services entrusted through furnishing high quality
SUPPLIER QUALITY PROGRAM, V (U)
FEDERAL MANUFACTURING & TECHNOLOGIES PQR 1060 PAGE 1 OF 17 SUPPLIER QUALITY PROGRAM, V (U) CHANGE HISTORY ISSUE DESCRIPTION OF CHANGE AUTHOR DATE E CORRECTED CHANGE HISTORY S. L. HALTER 10/18/2000 F UPDATED
PUBLICATIONS. Introduction
Page: 1 of 10 Introduction 1. The requirements of this document supplement the Factory Production Control requirements given in Table 1 of PN111 by giving the specific requirements for Factory Production
Quality Management System Manual
Quality Management System Manual Assurance ISO / AS Manual Quality Management System EXCEEDING ALL EXPECTATIONS Since our inception in 1965, Swiss-Tech has supplied the medical, aerospace, hydraulic, electronic
DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS
WELDING FABRICATOR CERTIFICATION SCHEME DOCUMENT CS/1: SCHEME DESCRIPTION AND BENEFITS 6 th Edition July 2012 Issued under the authority of the Governing Board for Certification All correspondence should
General Terms and Conditions
1zu1 Prototypen GmbH & Co KG, Färbergasse 15, A-6850 Dornbirn T +43 (0)5572 52946-0, F -15, [email protected], www.1zu1.eu General Terms and Conditions Färbergasse 15, 6850 Dornbirn, Austria -- in the following
VEHICULAR EQUIPMENT PURCHASE EXHIBIT. This Exhibit modifies the Terms and Conditions for Materials and Related Services:
VEHICULAR EQUIPMENT PURCHASE EXHIBIT This Exhibit modifies the Terms and Conditions for Materials and Related Services: The following definitions are added to DEFINITIONS of the Terms and Conditions. Contract:
Supplier Quality Agreements
Supplier Quality Agreements Dan O Leary CBA, CQA, CQE, CRE, SSBB, CIRM President Ombu Enterprises, LLC [email protected] www.ombuenterprises.com 603-209-0600 1 Speaker Biography Dan O Leary Dan O
Implementing ISO 9001
If you are faced with implementing ISO 9001, or anticipate it may soon become a requirement for your organization, keep reading. This article identifies reasons to implement the standard, summarizes its
THE FOLLOWING ARE INSTRUCTIONS FROM THE FRONT SIDE OF SEAGATE PURCHASE ORDERS:
THE FOLLOWING ARE INSTRUCTIONS FROM THE FRONT SIDE OF SEAGATE PURCHASE ORDERS: INSTRUCTIONS: Read this entire order form, including the incorporated terms and conditions located at http://www.seagate.com/about/legal-privacy/purchasing-and-pricing/purchase-orders-legal-overview/
Your essential guide to CE Marking
Your essential guide to CE Marking CE marking A guide for window and door fabricators This guide provides essential information that will help you with your preparations for CE marking. A flowchart is
Procedure PS-TNI-001 Information Security Management System Certification
Table of Contents 1. Purpose 2. Scope 3. Definitions 4. Responsibilities 4.1 Head of the Certification Body 4.2 QM Manager / Management Representative 4.3 Auditors 4.4 Order Service 4.5 Certification Service
Regulations for certification of quality management systems
Regulations for certification of quality management systems 00 24/04/2013 Annulla e sostituisce il documento Regulations for certification of quality management systems in rev. 14 SG DIR AD Rev. Data Descrizione
Standard conditions of purchase
Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out