1 Workshop W10 Wednesday, November 14 1:30 3:30 p.m. WRAP-UP FEASIBILITY BEYOND THE NUMBERS Presented by Kathleen Creedon President Wrap Strategies Catherine Wells Manager, Risk Consulting Solutions Ron Rakich & Associates, Inc., a Bickmore Risk Services Company Controlled insurance programs (CIPs) have become a very popular way of financing risks on large construction projects. While CIPs can offer a number of benefits, including consistency of coverage and potential cost savings, they are not the best option for every project. A comprehensive and balanced feasibility study, which goes beyond the savings model, can provide essential information about the requirements, potential pitfalls, and staffing and planning required for a successful CIP. This session provides a technical review of critical elements to consider before entering into a CIP from a variety of perspectives: owner, contractor, subcontractor, construction or project manager, and design professional. Learn how to develop a comprehensive risk profile, identify project-specific risks, prepare a cost/ benefit analysis, and uncover the regulatory and market conditions to determine whether a CIP is suitable for a specific project. Workshop W10 Copyright 2012 International Risk Management Institute, Inc. 1

2 Construction Confident. Old Republic offers breakthrough solutions for the most demanding insurance needs. Our high-level services in Risk Control, Claims and Underwriting are tailored to insure the most diverse construction risks. Behind it all is the expertise and insight that inspires confidence and true partnership. Pasadena New York Chicago Dallas Atlanta Baltimore Kansas City (866) Old Republic Construction Insurance Agency, Inc. CLS# Old Republic Construction Insurance Agency of New York, Inc., LS#668042

3 Kathi Creedon Owner Wrap Strategies Ms. Creedon is one of the presenters for Workshop W10, Wrap-Up Feasibility Beyond the Numbers, on Wednesday afternoon. Ms. Creedon has worked in the insurance industry for 35 years and has been involved in construction-related risk management and insurance for the past 25 years. She started the independent consulting firm Wrap Strategies in 2001 to provide consulting, training, program management and oversight, and hiring and audit services to project owners, brokers, contractors, and other consultants relating to wrap-ups and their administration with an emphasis on continual process improvement. Prior to Wrap Strategies, Ms. Creedon spent 4 years with Aon Risk Services and worked exclusively on wrap-up programs. Prior to Aon, Ms. Creedon managed a California branch office for a regional insurance broker based in New York. For those 6 years she was also the account executive for a large national residential and tunneling contractor headquartered in California. Catherine Wells, MBA, CPCU, ARM, CRIS Manager, Risk Consulting Solutions Ron Rakich & Associates, Inc., a Bickmore Risk Services Company Ms. Wells is one of the presenters for Workshop W10, Wrap-Up Feasibility Beyond the Numbers, on Wednesday afternoon. Ms. Wells is a former public entity risk manager for the California Department of Transportation (Caltrans). She developed and managed the Caltrans Statewide Rolling OCIP. She also developed and managed several single project OCIPs including the Devil s Slide Tunnel (mile-long tunnel project), several OCIPs for the San Francisco-Oakland Bay Bridge $6 billion construction program, and the San Francisco Doyle Drive $1 billion replacement project, which includes a P3. Ms. Wells has a diverse background in insurance and risk management that includes start-up and management roles in nine large public entity OCIPs. Her experience includes insurance underwriting, insurance brokerage, and account management for a variety of construction contractors. She has extensive experience in environmental risk management, surety and professional liability/e&o underwriting, and coverage arrangement. She has been a senior instructor for the University of Phoenix MBA program and has won numerous awards and recognition for her work as an instructor with the University and as an instructor for the Society of CPCU. Ms. Wells is currently Manager, Risk Consulting Solutions, Ron Rakich & Associates, Inc., a Bickmore Risk Services Company, an independent risk management consulting firm located in California. Workshop W10 She recently earned the Associate in Risk Management (ARM) designation. 3

4 Notes This file is set up for duplexed printing. Therefore, there are pages that are intentionally left blank. If you print this file, we suggest that you set your printer to duplex. 4

5 W10. Wrap-Up Feasibility Beyond the Numbers Presented by: Kathleen Creedon, CIC, CRM President Wrap Strategies & Catherine Wells, CPCU, ARM, CRIS, MBA Manager Bickmore Risk Services Wrap-Up Feasibility Beyond the Numbers Workshop W10 Controlled Insurance Programs (CIPs) have become a very popular way of financing risks on large construction projects. While CIPs can offer a number of benefits, including consistency of coverage and potential cost savings, they are not the best option for every project. A comprehensive and balanced feasibility study, which goes beyond the savings model, can provide essential information about the requirements, potential pitfalls, staffing, and planning required for a successful CIP. This session provides a technical review of critical considerations before entering into a CIP from a variety of perspectives: owner, contractor, subcontractor, construction or project manager, and design professional. Learn how to develop a comprehensive risk profile, identify project-specific risks, prepare a cost/benefit analysis, and uncover the regulatory and market conditions to determine whether a CIP is suitable for a specific project. 2 5

6 Project I Project Bridge Tie-In/Roadway Description: Objectives: On-time delivery Streamlined administration Risk Finance CCIP Structure: Issue(s): Owner-mandated CCIP GC new to CCIP approach GC lacked resources & experience Result: 3 Project II Project New Shopping Mall Project Description: Objectives: On-time delivery Savings Risk Finance OCIP Structure: Issue(s): Fast track project Production over safety Scarce labor supply No drug screening utilized Result: 4 6

7 Project III Project Description: Portfolio of New Construction & Renovation Projects Objectives: 30% small business participation Risk Finance Traditional Structure: Issue(s): Owner would not lower insurance requirements Owner refused to consider OCIP Conflicting politics Result: 5 Agenda I. Risk Financing Options II. Non-Financial Objectives III. Feasibility Study: IV. Interactive Case Studies V. Best Practice Recap Workshop W10 6 7

8 Risk Financing Options Traditional Owner Controlled Insurance Program (OCIP) Contractor Controlled Insurance Program (CCIP) General Liability Only 7 Non-Financial Objectives Project on time/on budget Coverage certainty Enhanced coverage Streamlined administration Adequate limits Safe project 8 8

9 Non-Financial Objectives Ability to utilize small business contractors Minimal litigation Positive project team relations Positive public relations 9 Feasibility Study: Ideal time to evaluate risk financing options Workshop W10 Project stakeholder motivations Project goals and objectives Political environment 10 9

10 Feasibility Study: Project Project scope, type, and size Sources, timing, and stability of funding Project location(s) Construction schedule Project delivery method 11 Feasibility Study: Project Means and methods Multiple general contractors P3 % self-performed Payroll component 12 10

11 Feasibility Study: CIP Sponsor Profile Risk tolerance Knowledge Experience Involvement 13 Feasibility Study: CIP Sponsor Profile (Continued) Commitment o Resources o Risk control/safety o Long term Workshop W

12 By Participant Feasibility Study: Objectives Staffing & resources CIP experience Protection Coordination with existing program Owner CM/PM GC Sub PSP 15 Feasibility Study: Developing a Risk Assessment Workers Compensation General Liability Builders Risk Professional Liability Environmental Liability Other Project-Specific Risks 16 12

13 Feasibility Study: Options for Risk Financing Owner CM/PM GC Sub PSP WC GL Builders Risk Professional Environmental Other Risks 17 Feasibility Study: Insurance Market Insurer stability Insurer appetite Hard versus soft market Identifying potential markets Workshop W

14 Feasibility Study: Insurance Coverage and Terms Forms and endorsements Limits Guaranteed cost versus loss sensitive Rate guarantees 19 Feasibility Study: Insurance Coverage and Terms (Cont.) Term Cancellation or withdrawal Warranty period Completed operations Loss development factors and closeout parameters 20 14

15 Feasibility Study: Regulatory Considerations Enabling legislation Statutory requirements Implementation Considerations Timing Broker selection process and timing Document preparation 21 Feasibility Study: Construction Market Potential contractor pool Local construction market conditions Workshop W10 Small Business Participation Existing versus new participation goals Facilitating participation 22 15

16 Feasibility Study: Who Should Prepare? In-house risk management staff Broker Consultant Project manager Construction manager 23 Feasibility Study: Their Attributes? Knowledge of construction risk management and insurance Knowledge of and experience with wrap-ups Acceptable level of bias Minimal conflict of interest 24 16

17 Project A Project University Description Objectives Safety Save money Coverage Project Facts 3-year project CV $400 million Multiple general contractors 25 Project Description Project B Highway and Bridge Connector to Larger Project Objectives Enhance project delivery Safety Project Facts CV $175 million Master project behind schedule Master project over budget GC 80% self-performed work Workshop W

18 Project C Project Apartment Building Description Objectives Save money Coverage Project Facts CV $30 million Urban environment Out-of-state general contractor Broker unfamiliar with wrap-ups 27 Project D Project Hospital Demolition/Rebuild Description Objectives Adequate coverage for all participants Savings Project Facts CV $400 million Strong owner commitment, resources, and involvement Prior unsuccessful OCIP Adequate lead time Two general contractors each with active CCIPs 28 18

19 Project E Project High-Rise Office Building Description Objectives Savings Coverage Project Facts CV $150 million One general contractor with CCIP 29 Project F Project Bridge Replacement Description Objectives Small business participation Savings Coverage Project Facts CV $200 million Project manager anti-ocip Lack of owner resources and commitment Governing body convinced OCIPs promote small business utilization Contractor superior CCIP program 30 Workshop W10 19

20 Project G Project Tunnel Description Objectives Enhance project delivery Savings Project Facts CV $300 million GC 80% self-perform work Heavy equipment component GC superior risk financing program Owner lacks CIP experience 31 Best Practices Recap Clearly define objectives Ensure objectives align with decision Integrate risk planning process early Obtain reliable data Utilize team approach to avoid bias Adapt to fluid conditions Look at multiple scenarios Look beyond the numbers! 32 20

BLUEPRINT CONTRACTOR ROLLING GENERAL LIABILITY ONLY PROJECT INSURANCE CONSTRUCTION PRACTICE ROLLING GL ONLY CCIP BACKGROUND

BLUEPRINT CONTRACTOR ROLLING GENERAL LIABILITY ONLY PROJECT INSURANCE CONSTRUCTION PRACTICE ROLLING GL ONLY CCIP BACKGROUND CONSTRUCTION PRACTICE BLUEPRINT October 2014 www.willis.com CONTRACTOR ROLLING GENERAL LIABILITY ONLY PROJECT INSURANCE PROJECT INSURANCE IS WRITTEN TO COVER A SPECIFIED PROJECT OR PROJECTS AND IS SPECIFIC

More information

RISK MANAGEMENT STRATEGIES FOR APARTMENT-TO-CONDO CONVERSIONS

RISK MANAGEMENT STRATEGIES FOR APARTMENT-TO-CONDO CONVERSIONS Workshop W4 Wednesday, November 20 9:00 10:15 a.m. and 10:45 a.m. noon RISK MANAGEMENT STRATEGIES FOR APARTMENT-TO-CONDO CONVERSIONS Presented by Workshop W4 Chad M. Hall Senior Vice President, Construction

More information

USING OCIPs AND CCIPS TO BRING ORDER TO PROJECT INSURANCE

USING OCIPs AND CCIPS TO BRING ORDER TO PROJECT INSURANCE USING OCIPs AND CCIPS TO BRING ORDER TO PROJECT INSURANCE CMAA Southern California Chapter October 30, 2014 8:00 a.m. The Grand Conference Center 4101 E. Willow Street Long Beach, CA Panel Greg Kildare

More information

AAPA Legal & Risk Management Seminar Introduction to Wrap-up or Owner Controlled Insurance Programs

AAPA Legal & Risk Management Seminar Introduction to Wrap-up or Owner Controlled Insurance Programs AAPA Legal & Risk Management Seminar Introduction to Wrap-up or Owner Controlled Insurance Programs July, 2005 Table of Contents What Is An OCIP Or Wrap-Up? When Should An OCIP Or Wrap-up Be Considered?

More information

"Wrap Ups" For Schools: IT S ABOUT TIME

Wrap Ups For Schools: IT S ABOUT TIME Owner Controlled Programs Presented By: Bill Poland, Keenan & Associates Owner Controlled Programs (OCIPs) "Wrap Ups" For Schools: IT S ABOUT TIME Legislative History Schools & Risk Management Pre 1999

More information

BUILDING A BRIDGE WITH SUBCONTRACTORS: THE KEY TO A SUCCESSFUL PROJECT

BUILDING A BRIDGE WITH SUBCONTRACTORS: THE KEY TO A SUCCESSFUL PROJECT WORKSHOP T7 Tuesday, November 10 2:30 p.m. 4:00 p.m. BUILDING A BRIDGE WITH SUBCONTRACTORS: THE KEY TO A SUCCESSFUL PROJECT Presented by Panelists Moderator Deborah Heden Risk Manager Gonsalves & Santucci,

More information

Taking the Stress Out of Controlled Insurance Programs: Guidance for Subcontractors

Taking the Stress Out of Controlled Insurance Programs: Guidance for Subcontractors Taking the Stress Out of Controlled Insurance Programs: Guidance for Subcontractors December 2012 Lockton Companies Before you bid on a construction contract, knowing your insurance obligations will help

More information

Bonding and Insurance Workshop. Presented by Ingrid Merriwether, President & CEO

Bonding and Insurance Workshop. Presented by Ingrid Merriwether, President & CEO Bonding and Insurance Workshop Presented by Ingrid Merriwether, President & CEO 1 What is to Be Gained? Practical Knowledge of insurance and bonding How insurance and bonding protects you and others How

More information

PEO and Temp Staffing

PEO and Temp Staffing PEO and Temp Staffing What to look for when auditing A more in depth discussion What is the difference between PEOs and Temp Staffing? PEO s Do not supply labor to worksites, PEOs supply services and benefits

More information

Article: Nuts & Bolts of Modern Wrap-Up Liability Insurance by Theodore L. Senet, Esq.

Article: Nuts & Bolts of Modern Wrap-Up Liability Insurance by Theodore L. Senet, Esq. Article: Nuts & Bolts of Modern Wrap-Up Liability Insurance by Theodore L. Senet, Esq. After years of hard learned lessons, your company has finally mastered the purchasing of insurance for your construction

More information

Spring 2014 WCCA IMAGINE YOUR SUCCESS

Spring 2014 WCCA IMAGINE YOUR SUCCESS IEATM Workers Compensation Disability Management Property and Casualty Fraud Identification Agents and Brokers Case Management Risk Management NEW THIS SPRING REVISED COURSES & CONTENT IEA WCCA Workers

More information

Bonding for Contractors. Barrie Construction Association September 17, 2015

Bonding for Contractors. Barrie Construction Association September 17, 2015 Bonding for Contractors Barrie Construction Association September 17, 2015 1 Topics What do bonds do? How does a bond benefit you? How do you get a bond? What are the information requirements? What is

More information

PENTARISK PERSPECTIVES

PENTARISK PERSPECTIVES PENTARISK PERSPECTIVES PentaRisk Insurance Services Newsle er Volume 2 Issue 2 February 2015 40 Tips for Contractors to Reduce Insurance Costs The following list of 40 tips provides suggestions on how

More information

PLUGGING HOLES IN CONTRACTORS LIABILITY COVERAGE

PLUGGING HOLES IN CONTRACTORS LIABILITY COVERAGE WORKSHOP W7 Wednesday, November 11 12:30 p.m. 2:00 p.m. PLUGGING HOLES IN CONTRACTORS LIABILITY COVERAGE Presented by Karen A. Reutter Executive Vice President and Director, Construction Insurance Willis

More information

Program Management for School Construction

Program Management for School Construction Program Management for School Construction Presented to: Pasadena Unified School District Board of Education January 13, 2009 Project Delivery Options Design Bid Build Design/Build Construction Management

More information

Legal and Legislative Conference

Legal and Legislative Conference Legal and Legislative Conference Workers Compensation What if the PEO Client Secures It? Copyright 2004 The Nugent Law Firm, P.C. All Rights Reserved Traditional PEO PEO Secures WC Insurance through Master

More information

Understanding Captives and Alternative Risk Transfer

Understanding Captives and Alternative Risk Transfer Understanding Captives and Alternative Risk Transfer Putting your insurance premiums to work for you Managing risk as you manage your bottom line What do Verizon, Coca-Cola, BP and most Fortune 500 sized

More information

OCIP III Insurance Procedures and Enrollment Manual

OCIP III Insurance Procedures and Enrollment Manual Owner Controlled Insurance Program OCIP III Insurance Procedures and Enrollment Manual This Manual is a Contract Document 1 TABLE OF CONTENTS Section 1 Section 2 Section 3 Section 4 Section 5 Section 6

More information

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS:

CONSTRUCTION RISK MANAGEMENT. TABLE of CONTENTS: CONSTRUCTION RISK MANAGEMENT TABLE of CONTENTS: 1. Introduction 2 2. Project Start Up Risk Exposure Analysis 3 3. Insurance 5 4. Additional Advice 8 5. Bonding 9 6. Subcontractor Default Insurance 11 1

More information

OCIPs and Professional Responsibility

OCIPs and Professional Responsibility OCIPs and Professional Responsibility Rosary A. Hernandez Wood Smith Henning & Berman LLP 2525 E. Camelback Road, Suite 450 Phoenix, AZ 85016-4210 (602) 441-1305 [email protected] Rosary A. Hernandez,

More information

Credit Union Liability with Third-Party Processors

Credit Union Liability with Third-Party Processors World Council of Credit Unions Annual Conference Credit Union Liability with Third-Party Processors Andrew (Andy) Poprawa CEO, Deposit Insurance Corporation of Ontario Canada 1 Credit Union Liability with

More information

12/14/2015 HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT INTRODUCTION AND OVERVIEW

12/14/2015 HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT INTRODUCTION AND OVERVIEW HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT Philip K. Glick, CPCU, RPLU Two Liberty Place 50 S. 16 th Street, Suite 3600 Philadelphia, PA 19102 P: 267-702-1374 C: 610-551-4734

More information

HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT

HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT HOT TOPICS IN MULTI-USE BUILDINGS: INSURANCE, CONSTRUCTION AND DEVELOPMENT Philip K. Glick, CPCU, RPLU Two Liberty Place 50 S. 16 th Street, Suite 3600 Philadelphia, PA 19102 P: 267-702-1374 C: 610-551-4734

More information

PROJECT LIABILITY PROGRAM INSURANCE PROCEDURES MANUAL PROJECT NAME PROJECT NUMBER FOR THE

PROJECT LIABILITY PROGRAM INSURANCE PROCEDURES MANUAL PROJECT NAME PROJECT NUMBER FOR THE PROJECT LIABILITY PROGRAM INSURANCE PROCEDURES MANUAL FOR THE PROJECT NAME PROJECT NUMBER Presented By: Swinerton Builders and Arthur J. Gallagher & Co. Insurance Brokers of California, Inc. Table of Contents

More information

LAYTON RISK MANAGEMENT CONTRACTOR CONTROLLED INSURANCE PROGRAM MANUAL FOR THE PROJECT NAME. Layton Construction and Gallagher Construction Services

LAYTON RISK MANAGEMENT CONTRACTOR CONTROLLED INSURANCE PROGRAM MANUAL FOR THE PROJECT NAME. Layton Construction and Gallagher Construction Services LAYTON RISK MANAGEMENT CONTRACTOR CONTROLLED INSURANCE PROGRAM MANUAL FOR THE PROJECT NAME Presented By: Layton Construction and Gallagher Construction Services 1 Table of Contents Insurance Coverages...

More information

PREVENTING WATER DAMAGE DURING CONSTRUCTION

PREVENTING WATER DAMAGE DURING CONSTRUCTION Workshop W7 Wednesday, November 12 1:30 2:45 p.m. and 3:05 4:20 p.m. PREVENTING WATER DAMAGE DURING CONSTRUCTION Presented by Scott Foyer National Construction Practice Leader Travelers Inland Marine Peter

More information

Complete Application & Fax to (845) 279-7768 APPLICANT INFORMATION OPERATIONS

Complete Application & Fax to (845) 279-7768 APPLICANT INFORMATION OPERATIONS Complete Application & Fax to (845) 279-7768 Attn: Full Name of Applicant: Address: Website Address: Separately list and describe all operations: APPLICANT INFORMATION List states in which the applicant

More information

DOES YOUR BUILDERS RISK COVERAGE PASS INSPECTION?

DOES YOUR BUILDERS RISK COVERAGE PASS INSPECTION? WORKSHOP M5 Monday, November 9 10:30 a.m. 11:45 a.m. DOES YOUR BUILDERS RISK COVERAGE PASS INSPECTION? Presented by Workshop M5 Steven A. Coombs President Risk Resources, Inc. Although construction contracts

More information

Non Employee Labor WC & GL

Non Employee Labor WC & GL Non Employee Labor WC & GL Presented by: Becky Garry, CPCU, APA, ARM, AU Overland Solutions, Inc. Subcontractors/Contract Laborers/Independent Contractors General Liability & Workers Compensation Who What

More information

UNDERSTANDING OCIPS. FCA CONTRACTINSIGHT Vol. 1, Issue 2 JUNE 2007 I. WHAT IS AN OCIP? Owner Controlled Insurance Program

UNDERSTANDING OCIPS. FCA CONTRACTINSIGHT Vol. 1, Issue 2 JUNE 2007 I. WHAT IS AN OCIP? Owner Controlled Insurance Program FCA CONTRACTINSIGHT Vol. 1, Issue 2 JUNE 2007 UNDERSTANDING OCIPS I. WHAT IS AN OCIP? Owner Controlled Insurance Program Contractors and subcontractors are normally required to provide insurance for work

More information

Owner-Controlled Insurance Program Feasibility Study. The Wisconsin Department of Transportation

Owner-Controlled Insurance Program Feasibility Study. The Wisconsin Department of Transportation Owner-Controlled Insurance Program Feasibility Study High Speed Passenger Rail Madison-Watertown Infrastructure Improvements Prepared For: The Wisconsin Department of Transportation February 26, 2010 Prepared

More information

RESOLVING INSURANCE COVERAGE AND CLAIMS DISPUTES

RESOLVING INSURANCE COVERAGE AND CLAIMS DISPUTES Workshop T1 Tuesday, November 11 10:20 a.m. 12:10 p.m. and 2:40 4:30 p.m. RESOLVING INSURANCE COVERAGE AND CLAIMS DISPUTES Presented by Workshop T1 Bill Wilson Assoc. VP, Education & Research Independent

More information

The Davis Companies are comprised of Specialized Risk Experts in the areas of

The Davis Companies are comprised of Specialized Risk Experts in the areas of The Davis Companies are comprised of Specialized Risk Experts in the areas of Insurance Brokerage, Financial Consulting, and Contractor Development Services. Through common ownership, The Davis Companies

More information

Fundamentals of a Construction Audit. August 7, 2014

Fundamentals of a Construction Audit. August 7, 2014 Fundamentals of a Construction Audit August 7, 2014 Agenda Definitions Risk Based Approach What Determines Risk Fraud Construction Risks What to Audit Red Flags Why Audit Prevention Wrap-up 1 Definitions

More information

CCIP Insurance Manual. Turner Construction Company

CCIP Insurance Manual. Turner Construction Company Turner Construction Company Contractor Controlled Insurance Program (CCIP) Learned Hall, Engineering Expansion Phase Two (LEEP2) 1520 E 15 th Street, Lawrence, KS 66045 CCIP Insurance Manual This Manual

More information

The Use of Controlled Insurance Programs as a Risk Management Alternative on Construction Projects

The Use of Controlled Insurance Programs as a Risk Management Alternative on Construction Projects The Use of Controlled Insurance Programs as a Risk Management Alternative on Construction Projects J. Mark Taylor, PhD, JD Auburn University Auburn, AL This paper discusses the use of controlled insurance

More information

The promise and pitfalls of cyber insurance January 2016

The promise and pitfalls of cyber insurance January 2016 www.pwc.com/us/insurance The promise and pitfalls of cyber insurance January 2016 2 top issues The promise and pitfalls of cyber insurance Cyber insurance is a potentially huge but still largely untapped

More information

ACE Renewable Energy

ACE Renewable Energy ACE Renewable Energy Powering Insurance Solutions ACE Renewable Energy A Leading Provider of Insurance for Renewable Energy Production ACE USA specializes in Renewable Energy insurance solutions for diverse

More information

Note: It is suggested that you examine your current Policies and contact your Insurance Broker before answering the following questions.

Note: It is suggested that you examine your current Policies and contact your Insurance Broker before answering the following questions. FORM 1 Page 1 of 2 INSURANCE COST INFORMATION WORKSHEET All Contractors, Subcontractors, and Sub subcontractors of every tier, are required to complete this worksheet and submit as part of your bid. Note:

More information

BUILDING AN EFFECTIVE STRATEGY FOR MANAGING CONSTRUCTION RISK

BUILDING AN EFFECTIVE STRATEGY FOR MANAGING CONSTRUCTION RISK BUILDING AN EFFECTIVE STRATEGY FOR MANAGING CONSTRUCTION RISK A COMPREHENSIVE RISK MANAGEMENT STRATEGY PROVIDES REAL RETURNS David Landrum Kevin Crossan Allen Abrahamsen BUILDING AN EFFECTIVE STRATEGY

More information

2008 Builders insurance group annual report. Road to the future

2008 Builders insurance group annual report. Road to the future 2008 Builders insurance group annual report Road to the future road to the future Letter from the Chairman & CEO In our 2007 Annual Report, we discussed how Builders Insurance Group is a company in motion,

More information

NEW YORK STATE-WIDE PAYROLL CONFERENCE. Presented to:

NEW YORK STATE-WIDE PAYROLL CONFERENCE. Presented to: NEW YORK STATE-WIDE PAYROLL CONFERENCE Presented to: Felicia Cheek, Practice Leader Global Time to Pay Advisory 15 September 2014 Statement of Confidentiality and Usage Restrictions This document contains

More information

Contractors Pollution Liability Project-Specific Insurance Policies

Contractors Pollution Liability Project-Specific Insurance Policies Illinois Union Insurance Company Contractors Pollution Liability Project-Specific Insurance Policies Occurrence-Based Coverage Application Instructions: Please type or print clearly. Answer ALL questions

More information

CGL COVERAGE FOR RIP AND TEAR COSTS

CGL COVERAGE FOR RIP AND TEAR COSTS Workshop W2 Wednesday, November 14 9:00 10:15 a.m. and 10:45 a.m. noon CGL COVERAGE FOR RIP AND TEAR COSTS Presented by Jeffrey D. Masters Partner Cox, Castle & Nicholson LLP Claims involving damage to

More information

Franklin L. Burns School of Real Estate & Construction Management

Franklin L. Burns School of Real Estate & Construction Management University of Denver 1 Franklin L. Burns School of Real Estate & Construction Management Office: Daniels College of Business, Room 380 Mail Code: 2101 S. University Blvd. Denver, CO 80208 Phone: 303-871-3432

More information

The Regents of the University of California

The Regents of the University of California The Regents of the University of California Analysis of the Master University of California Controlled Insurance Program for construction projects with values over $25,000,000 Prepared by: Grace M. Crickette,

More information

Contractor s Dangerous Coverage Gaps Update. 2013 Additional Insured Forms Require Revised Contract Wording

Contractor s Dangerous Coverage Gaps Update. 2013 Additional Insured Forms Require Revised Contract Wording Contractor s Dangerous Coverage Gaps Update 2013 Additional Insured Forms Require Revised Contract Wording By Robert J. Marshburn, CRM, CIC, ARM, CRIS, CISC R. J. Marshburn & Associates Laguna Beach, California

More information

Vice President, Marketing and Customer Experience Wealth Management

Vice President, Marketing and Customer Experience Wealth Management Vice President, Marketing and Customer Experience Wealth Management About the Organization: CUNA Mutual Group is the leading financial services provider to credit unions and their members worldwide. For

More information

How To Choose and Use a Risk Management Consultant

How To Choose and Use a Risk Management Consultant How To Choose and Use a Risk Management Consultant A WHITE PAPER FOR ORGANIZATIONS CONSIDERING THE SERVICES OF A RISK MANAGEMENT CONSULTANT Warren, McVeigh & Griffin, Inc. R I S K M A N A G E M E N T C

More information

How To Manage Risk In Your Contingent Workforce

How To Manage Risk In Your Contingent Workforce Wednesday 3:45 pm Veranda C Concurrent Session: Workers Compensation Costs and Safety Risks in Your Contingent Workforce Making the Business Case for Strong Risk Management in the Contingent Workforce

More information

That s A Wrap What Every Claims And Construction Professional Needs To Know About Wrap-up Insurance Programs

That s A Wrap What Every Claims And Construction Professional Needs To Know About Wrap-up Insurance Programs 2015 CLM Atlanta Conference November 5-6, 2015 in Atlanta, GA That s A Wrap What Every Claims And Construction Professional Needs To Know About Wrap-up Insurance Programs In the construction industry,

More information

NIF Insurance Services of California Artisan Pak Land Improvement Contractor Qualifier General Liability ( GL )

NIF Insurance Services of California Artisan Pak Land Improvement Contractor Qualifier General Liability ( GL ) NIF Insurance Services of California Artisan Pak Land Improvement Contractor Qualifier General Liability ( GL ) a division of NIF Group, Inc. Phone: (916) 566-1000 P.O. Box 13456 [email protected]

More information

Owner Controlled Insurance Program OCIP II Online Enrollment Procedures Supplement

Owner Controlled Insurance Program OCIP II Online Enrollment Procedures Supplement Owner Controlled Insurance Program OCIP II Online Enrollment Procedures Supplement Contracts with a Notice to Proceed date after January 1, 2012 A. Online OCIP Enrollment Process All eligible Contractors

More information

Wrap-Ups: Beyond the Basics from Concept to Closeout. Presented By: Kathleen A. Creedon. Tracy Alan Saxe. Christopher T. Smith

Wrap-Ups: Beyond the Basics from Concept to Closeout. Presented By: Kathleen A. Creedon. Tracy Alan Saxe. Christopher T. Smith Wrap-Ups: Beyond the Basics from Concept to Closeout Presented By: Kathleen A. Creedon Owner, Wrap Strategies Middleboro, MA Tracy Alan Saxe Partner Saxe Doernberger & Vita, P.C. Hamden, CT & Christopher

More information

NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) Submission to WorkCover Western Australia. Legislative Review 2013

NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) Submission to WorkCover Western Australia. Legislative Review 2013 NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) ABOUT NIBA Submission to WorkCover Western Australia Legislative Review 2013 February 2014 NIBA is the peak body of the insurance broking profession

More information

Aon Risk Solutions (에이온의 리스크 처리)

Aon Risk Solutions (에이온의 리스크 처리) Aon Risk Solutions (에이온의 리스크 처리) Investment Opportunities in California Insurance Compliance and Risk Advisory (캘리포니아에 투자 기회 보험규정준수 및 리스크 자문) Presented By: Ken Caldwell, Senior Executive Vice President,

More information

The Good, The Bad & The Ugly

The Good, The Bad & The Ugly The Good, The Bad & The Ugly OCIP/CCIP from a Subcontractor s Perspective Presented By: Richard. B Usher and Donald W. Gregory, Esq. 1 INSURANCE IS: The business of accepting/financing Risk Transfer for

More information

Insurance and the Construction Failure

Insurance and the Construction Failure Insurance and the Construction Failure 18 th Annual Construction SuperConference December 12, 2003 San Francisco, California James D. Hollyday [email protected] 1 Introduction 1. Contract Drafting

More information

Owner Controlled Insurance Program (OCIP) Overview

Owner Controlled Insurance Program (OCIP) Overview Owner Controlled Insurance Program (OCIP) Overview Prepared for Caltrans Oakland Touchdown Outreach Presented by: Willis One Bush Street, Suite 900 San Francisco CA 94104 (415) 981-1141 WHAT IS AN OCIP

More information

INFORMATION CONNECTED

INFORMATION CONNECTED INFORMATION CONNECTED Business Solutions for the Utilities Industry Primavera Project Portfolio Management Solutions Achieve Operational Excellence with Robust Project Portfolio Management Solutions The

More information

CONTRACTORS APPLICATION WESTCAP INSURANCE SERVICES, INC. 4. PRODUCER CONTACT NAME 6. PRODUCER E-MAIL

CONTRACTORS APPLICATION WESTCAP INSURANCE SERVICES, INC. 4. PRODUCER CONTACT NAME 6. PRODUCER E-MAIL 1. PRODUCER : 2. PRODUCER : 3. PRODUCER TELEPHONE: 5. PRODUCER FAX 7. APPLICANT 4. PRODUCER CONTACT 6. PRODUCER E-MAIL INDIVIDUAL PARTNERSHIP CORPORATION JOINT VENTURE LLC OTHER 8. APPLICANT STREET 9.

More information

SOLAR CHECKLIST FOR CHOOSING AN INSTALLER

SOLAR CHECKLIST FOR CHOOSING AN INSTALLER SOLAR CHECKLIST Congrats! You ve decided to save with solar but how do you choose your installer? Here s a checklist with guidelines for selecting the right company for your solar project. These tips and

More information

PEO Myths vs. Reality. By Clay Kelley

PEO Myths vs. Reality. By Clay Kelley PEO Myths vs. Reality By Clay Kelley 1 Clay Kelley Background Clay Kelley has been in the HR Outsourcing and PEO business since 1985. He has participated in seven mergers and acquisitions and assisted

More information

REAL ESTATE & HOSPITALITY. Real Insurance Solutions for Real Estate and Hospitality

REAL ESTATE & HOSPITALITY. Real Insurance Solutions for Real Estate and Hospitality REAL ESTATE & HOSPITALITY Real Insurance Solutions for Real Estate and Hospitality Real Estate & Hospitality Risk Management Services We Understand Your Business Understanding the specific issues facing

More information