PROJECT CHARTER DOMINO APPLICATIONS MIGRATION
|
|
|
- Cuthbert Martin
- 9 years ago
- Views:
Transcription
1 PROJECT CHARTER DOMINO APPLICATIONS MIGRATION STONY BROOK UNIVERSITY STONY BROOK, NY Project Charter Version Control Version Date Author Change Description /14/2011 Raymond Chan First Draft
2 EXECUTIVE SUMMARY Stony Brook University will be replacing the existing IBM Domino/Lotus Notes system with a new and collaboration services solution. All existing Domino applications that continue to serve a useful purpose will need to be migrated to other platforms by the end of PROJECT PURPOSE/JUSTIFICATION The IBM Domino application platform that Stony Brook University has used over the last decade and a half has become stagnant and outdated. It is considerably less versatile and less friendly to use than other competing products. The limitations with Domino, such as data connectivity with other databases that is critical in modern business applications are nonexistent with other platforms. With Stony Brook s growing need for applications that facilitate business objectives, fewer solutions have been developed using the IBM Domino application platform. The cost and resources associated with maintaining IBM Domino/Lotus Notes can be redirected to other opportunities. PROJECT DESCRIPTION & APPROACH There are 2,119 Domino application files located on two Domino application servers maintained by DoIT. Although each application file is considered a unique application, not every application will need to be migrated. Applications that are no longer used or only used by Domino administrators to support the Domino environment will not be migrated. Shared departmental mailboxes, although considered applications, will be handled by the & Collaboration Services project. This eliminates about 75% of the applications required to be migrated. A migration path for each remaining application will be identified and managed to completion. This project will be managing the migration of applications in consideration of the timeline established for the implementation of the new and Collaboration Services solution. In a multi-stage approach, applications will be migrated by priority. High-priority applications are applications deemed critical by their respective owners and have a broad user base where logging on is necessary. The latter is a significant factor because it is predicted that after the new and collaboration services is launched in the beginning of 2012, that the creation of new Lotus Notes accounts will be reduced. We do not want to inconvenience new employees and students with the additional step of requesting a Lotus Notes account to access legacy applications. The first stage focuses on completing the migration of high-priority applications by December This will coincide with the stage of the and Collaboration Services project where 65% of the non-student users will be migrated. The final stage will focus on migrating the remainder of the applications by the end of
3 Teams of experts in each migration path will be setup. These experts will have the responsibility of providing guidance in proven best practices to the developers. The experts will also research and recommend tools that can be used to ease the migration to their respective paths. E.g. A standard operating procedures Domino application that houses policies and procedural documents can be recommended by the MS SharePoint experts to be moved into MS SharePoint. To reduce the time required to migrate applications, third-party tools sold specifically for migrating Domino applications will be used when feasible. Project Objectives Project Component Complete a master inventory of Domino applications to track migration progress Target Date 10/31/2011 Setup teams of experts as advisors to the developers 10/31/2011 Meet with the developers: categorize their applications, identify possible migration paths, define the list of high priority applications, determine their available resources 11/18/2011 Determine the primary developers, owners of each application 11/18/2011 Determine the applications that no longer serve a useful purpose and can be safely deleted 11/18/2011 Work with the developers to develop a timeline for completion of each application migration 11/30/2011 Complete the migration of all high priority applications 12/31/2012 Complete the migration of all applications 12/31/2013 Scope Within Scope This project will include the migration of applications housed in DoIT s two application servers. Outside Scope Mail-in Databases, including shared departmental mailboxes, fax databases, shared address books, and shared calendars will be handled by the & Collaboration Services project. Domino applications housed on servers outside of DoIT s control. Administrative Domino applications that were used to support the Domino/Lotus Notes platform. Applications planned for migration due to prior initiatives, such as the PeopleSoft Applicant Tracking system. Constraints Common applications should use the same migration path when possible. This allows for the standardization of systems Lack of adequate skills: Twelve subject matter experts (SME) will be provided as resources for this project on an as-needed basis. The subjects include: MS 2
4 SharePoint, ASP.Net, Content Management System, Event/Resource Scheduling, Box Office/e-Commerce, PeopleSoft, Issue Tracking, Single Sign-On, Server Infrastructure On average, it will take one junior developer 480 hours or one developer 200 hours or one senior developer 180 hours to complete the migration of a medium complex application Assumptions This project has the full support of the project sponsor, stakeholders, developers, and all departments The & Collaboration Services project will be completed as scheduled The project sponsor will provide additional resources if necessary RISKS Risks will be classified and managed as shown in the following two diagrams. Probability Low Medium High High Significant Maximum Medium Minor Significant Low Minor Minor Significant Impact Classification Impact Action Required Maximum Could result in project failure Risk is identified and documented Significant Minor Material impact on project scope, schedule or budget Material Impact on system functionality Project has sufficient resources to contain the risk A Risk Containment Plan is developed Resources are allocated to execute the Risk Containment Plan Risk is identified and documented Containment Plan may be developed Risk is identified and documented Risk Classification Action Required Many applications are discovered where the original developer is no longer available. Additional developers will be acquired to handle the migration of these applications 3
5 It is discovered that there are many more applications that require migration than the current developers are able to complete within the project schedule. Original developers of Domino applications lack the skills to develop in a different platform. A high priority application is not completed on time. Significant Additional developers will be acquired to handle the migration of these applications Developers will require mentoring from existing developers of other platforms and additional developers will be acquired to handle the migration of these applications Ensure that any users who need access to this application can obtain a Lotus Notes account. Deliverables Project Milestone Target Date Project Start 10/26/2011 Midpoint of High Priority Applications Migration 7/1/2012 Completion of High Priority Applications Migration 12/31/2012 Midpoint of Remaining Applications Migration 7/1/2013 Project Completion 12/31/2013 Project Team Organization Plans Project Team Role Subject Matter Experts Junior Developers Developers Project Team Member(s) Andrew Kirsch Brian Heller Daniel Pincas David Ecker Jacob Levich Jason Kanaris John Passaro Kim Rant Melissa Bishop Sanjay Kapur Shady Azzam-Gomez Victor Montanez Jonathan Rodriguez Joonho Lee Kristen Stewart Nicholas Trombetta Patrick Malley William Fischer John Leone Jose Tejada 4
6 Senior Developers Daniel Pincas Jason Kanaris PROJECT MANAGER Raymond Chan is named Project Manager for the Domino Applications Migration Project. Mr. Chan s responsibility is to manage all project tasks, scheduling, and communication regarding the project. His team, consisting of twelve IT specialists will be matrix support from the IT department. Any additional funding must be requested through the Project Sponsor, Chris Kielt. Mr. Chan will provide monthly updates to the Project Sponsor. AUTHORIZATION Approved by the Project Sponsor: Chris Kielt Chief Information Officer Date: 5
Change Management Procedure For Increase Bandwidth to University Buildings Project
Change Management Procedure For Increase Bandwidth to University Buildings Project Version number 1.0 Draft as of 4/11/2011 Printed on 7/1/2011 Author William M. Jones Owner William M. Jones Change Management
Initiating Forms COPYRIGHTED MATERIAL 1.0 INITIATING PROCESS GROUP
1 Initiating Forms 1.0 INITIATING PROCESS GROUP The purpose of the initiating process group is to authorize a project, provide a high-level definition of the project, and identify stakeholders. There are
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
PROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
Prepared by Jenn Coast and Christina Konstantinidou, ITS Last Edited May 8, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Project Charter Executive Summary With the
Project Charter. Office 365 2015 Migrations Document Version 2.0 Prepared by Sabina Winters, ITS Last Edited February 19, 2015
Prepared by Sabina Winters, ITS Last Edited February 19, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Executive Summary In December of 2014, the IT Governance Architecture
Project Management Plan. Project Management Plan Guide. Strategic Capital, Infrastructure and Projects
Project Management Plan Guide A guide to completing the Project Management Plan Strategic Capital, Infrastructure and Projects Prepared by: Andrew Segrott / Strategic Capital, Infrastructure and Projects
TRANSITION PLAN TEMPLATE
TRANSITION PLAN TEMPLATE In this template, instructions are included in italics. When you have completed the template and no longer need the instructions, delete them. Provide a brief overview of the transition
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
Project Planning Worksheet
Project Planning Worksheet Project Name: Prepared by: Department: Date: Background and Overview Give the business reason for requesting this project, and an overview of the work to be completed. Risks
Integrating the Worldwide Project Management Method (WWPMM) into an IBM Global Services Method Project
IBM Global Services Integrating the Worldwide Project Management Method (WWPMM) into an IBM Global Services Method Project Technique Paper (TP) Copyright International Business Machines Corporation, 2000
Project Charter Content Management System REPLACEMENT
Project Created By Executive Sponsor Content Management System Replacement System Kelly Mullin, Paul Burr, Parporn Metharom, Jason Bogal, Barbara Barry, Lori Piccinini Nancy Leuenhagen, Laura Schmidt Date
ITIL Implementation Planning
White Paper ITIL Implementation Planning Overview Introduction This paper describes the items that need to be considered in advance of starting an ITIL implementation effort. It is critical to make sure
LDAP Authentication Configuration Appendix
1 Overview LDAP Authentication Configuration Appendix Blackboard s authentication technology is considered a focal point in the company s ability to provide true enterprise software. Natively, the Blackboard
COMPLETED EXAMPLE PMM Interactive Flow
COMPLETED EXAMPLE PMM Interactive Flow Project Charge Document (M101) 1. Project Information Project Name: PMM Interactive Flow PlanView Number: Project Sponsor: Project Size: Project Director: Project
1. Project Charter. Sheri Kellogg. Phyllis Short. Project Title: PeopleSoft CSS / HCM Split Description:
1. Stakeholder Name Cecilia Castellano Chris Cox Laura Emch Andy Grant Sheri Kellogg Chastity McCartney Beth Ann Rife Phyllis Short Michelle Simmons Brian Skelding Sharon Swartz Department Admissions Registrar
Information Technology Services ServiceNow: Change Management Phase I Project Charter
ServiceNow: Change Management Phase I Project Charter VERSION: 1.3 REVISION DATE: 9/28/2011 Approval of the Project Charter indicates an understanding of the purpose and content described in this deliverable.
Guidelines: Project Schedule Project Management Office (PMO)
Guidelines: Project Schedule Project Management Office (PMO) Process The project Schedule outlines the tasks and activities of the project; the duration; start and end dates for each individual task and
Gartner, Inc. DIR-SDD-2042
Texas Department of Information Resources STATEMENT OF WORK (SOW) FOR DELIVERABLES-BASED INFORMATION TECHNOLOGY SERVICES Identity & Access Management Analysis IT Assessment & Planning Gartner, Inc. DIR-SDD-2042
5.2. 5.2 Template for IT Project Plan. Template for IT Project Plan. [Project Acronym and Name]
231 5.2 Template for IT Project Plan Name of the Tool: Source: Usage: Description: Template for IT Project Plan GIZ This template has been designed as a tool to support the planning of IT projects for
Draft Requirements Management Plan
BAO111: Core Competencies for the Business Analyst Draft Requirements Management Plan 1.0 INTRODUCTION 1.1 Purpose This document outlines requirements roles and responsibilities, presents a stakeholder
Information Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
Installation Steps on Desktop Clients
Installation Steps on Desktop Clients Table of Contents TABLE OF CONTENTS... 2 INSTALLATION STEPS FOR APPLE MAC BOOK... 3 XGEN PLUS INSTALLATION STEPS ON IPAD... 7 XGEN PLUS INSTALLATION STEPS ON MICROSOFT
Waterloo CMS Project. Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada
Waterloo CMS Project Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada Charter Date: September 4, 2009 Revision Date: February 10, 2010 Maintained
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit
Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and
Migrating Lotus Notes Applications to Google Apps
Migrating Lotus Notes Applications to Google Apps Introduction.................................................... 3 Assessment..................................................... 3 Usage.........................................................
Strategic Plan for the Enterprise Portfolio Project Management Office Governors Office of Information Technology... Ron Huston Director
Strategic Plan for the Enterprise Portfolio Project Management Office Governors Office of Information Technology.......... June 2010 Ron Huston Director Message from the State Enterprise Portfolio Project
IT Project Management Methodology. Project Execution Support Guide. Version 0.3
NATIONAL INFORMATION TECHNOLOGY AUTHORITY - UGANDA IT Project Management Methodology Project Execution Support Guide Version 0.3 Table of Contents 1 INTRODUCTION... 4 1.1 When should Project Execution
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
How To Create A Single Sign On For Blackboard
1 Overview Single Sign-On Authentication Appendix Blackboard s authentication technology has been identified as a dynamic, adaptable factor to supporting elearning Systems Integration strategy and implementation.
Project Management Fundamentals. Office of the Senior Associate Vice President for Finance
Project Management Fundamentals Project Management Institute PMI is an aggregation of best practices from thousands of professional project managers Principles in this training are based on PMI methodologies,
Microsoft Active Directory Project
Microsoft Active Directory Project Simcoe County District School Board Project Kick-off Meeting Rami Wehbe (Solution Architect) January 18, 2012 Agenda Introductions Project objectives and drivers Approach
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
Pulmonary Rehabilitation Proposal for On-Line Competencies
Pulmonary Rehabilitation Proposal for On-Line Competencies Fran Strauss MIT 520 December 7, 2006 Executive Summary Pulmonary Rehabilitation (PR) is a department within the Coastal Heart Division of New
PROJECT PLAN TEMPLATE
Treasury Board of Canada Secretariat Secrétariat du Conseil du Trésor du Canada Enhanced Management Framework for Information Management/Information Technology PROJECT PLAN TEMPLATE Document Revision Draft
Best Practices for Migrating from Lotus Notes to Microsoft Exchange and SharePoint
Best Practices for Migrating from Lotus Notes to Microsoft Exchange and SharePoint A White Paper Written by Technology Strategy Research, LLC and Sponsored by Quest Software - Best Practices for Migrating
Risk/Issue Management Plan
Risk/Issue Management Plan Centralized Revenue Opportunity System November 2014 Version 2.0 This page intentionally left blank Table of Contents 1. Overview... 3 1.1 Purpose... 3 1.2 Scope... 3 2. Roles
Process Improvement Program Project Process
Process Improvement Program Project Process 1 P a g e 12/3/2014 The Process Improvement Program is part of the City of Fort Lauderdale s FL 2 STAT Approach to Exponential Improvement. Its objective is
Project Processes. Media Snapshot. Project Management Process Groups
Project Processes PROJECT LIFECYCLE A project normally requires a number of processes. A process is a series of actions directed toward a particular result Project management can be viewed as a number
The Job of the Project Manager. Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 [email protected].
The Job of the Project Manager Robert Youker World Bank (retired) 5825 Rockmere Drive Bethesda, Md. USA 20816 [email protected] For any organization and for any project manager it is vitally important
Central Agency for Information Technology
Central Agency for Information Technology Development of a National IT Governance Framework Project Management Agenda 1 What is project management? Why it is important? 2 Leading practices 3 Project management
Madison Area Technical College Technology Services. Project Charter. For the. MATC Customer Relations Management Initiative.
Project Charter Madison Area Technical College Technology Services Project Charter For the MATC Customer Relations Management Initiative April 23, 2008 Prepared By: Peri Mills and Regina Mosher C:\DOCUME~1\AKKoenig\LOCALS~1\Temp\XPgrpwise\MATC
The Business Case for HP ControlPoint
The Business Case for HP ControlPoint White Paper Revision: 2 Date created: 13 November 2015 Principal author: Nigel Carruthers-Taylor icognition reference: 15/16495 Executive Summary Table of Contents
Module 7 Human Resources Management PMP Exam Questions
Module 7 Management PMP Exam Questions PMP, PMBOK and the Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Question 1 You and your manager are discussing
DELIVERING TRUSTED, PROVEN SOLUTIONS FOR THE EFFICIENT MANAGEMENT OF UNSTRUCTURED DATA SOARSOFTINTERNATONAL.COM
DELIVERING TRUSTED, PROVEN SOLUTIONS FOR THE EFFICIENT MANAGEMENT OF UNSTRUCTURED DATA SOARSOFT INTERNATIONAL PROVIDES INFORMATION MANAGEMENT SOLUTIONS THAT ENABLE LARGE AND MEDIUM ENTERPRISES TO EFFICIENTLY
Organization. Project Name. Project Overview Plan Version # Date
Project Overview Plan Template Organization Project Name Project Overview Plan Version # Date REVISION HISTORY VERSION # REVISION DATE COMMENT 1 APPROVALS: Authorized Signature DATE 2 Table of Contents
SCHEDULE 8 Generalist Project Services Framework 2015
SCHEDULE 8 Generalist Project Services Framework 2015 Nominal Insurer And Schedule 8 (Project Services Framework) Page: 1 of 6 Schedule 8 Generalist Project Services Framework Contents Overview... 3 1.
ITS Projects Systems Engineering Process Compliance Checklist
ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Project Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group Phone: (202) 994-6867 Cell: (240) 472-2171 Email: [email protected] Objectives Basic understanding
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in the Project Scope Statement is implicitly excluded from the project. Project Name: Prepared by: BI - IT Governance Amy Winkel Date: 12/20/2010
Data Classification Technical Assessment
Data Classification Update: February 13th, 2015 Statement of Confidentiality This Confidential Information is being provided to Customer ABC as a deliverable of this consulting engagement. The sole purpose
IBM Unstructured Data Identification & Management An on ramp to reducing information costs and risk
Amir Jaibaji - Product Management Program Director IBM Information Lifecycle Governance IBM Unstructured Data Identification & Management An on ramp to reducing information costs and risk Enterprise big
LOTUS to SharePoint Migration Services
LOTUS to SharePoint Migration Services Key Discussion Points StarSoft Value Proposition Microsoft Office SharePoint Server 2007 (MOSS) Lotus Notes: Current Marketplace Trends Migration Planning Questions:
State of Alaska Enterprise Messaging and Directory Services Strategy Vision and Scope
State of Alaska Enterprise Messaging and Directory Services Strategy Vision and Scope State of Alaska Document ID: Title: Supersedes: Status: 1010 Enterprise Messaging and Directory Services Strategy Vision
December 21, 2012. The services being procured through the proposed amendment are Hosting Services, and Application Development and Support for CITSS.
Justification for a Contract Amendment to Contract 2012-01: Interim Hosting and Jurisdiction Functionality for the Compliance Instrument Tracking System Service (CITSS) December 21, 2012 Introduction WCI,
Virtual Node Integrated Project Team (IPT) Charter
Virtual Node Integrated Project Team (IPT) Charter This Charter defines the objectives, leadership, and membership of an Integrated Project Team (IPT) that will guide the requirements definition for a
Department of Administration Portfolio Management System 1.3 June 30, 2010
E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2
Integration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
The Department for Business, Innovation and Skills IMA Action Plan PRIORITY RECOMMENDATIONS
PRIORITY RECOMMENDATIONS R1 BIS to elevate the profile of information risk in support of KIM strategy aims for the protection, management and exploitation of information. This would be supported by: Establishing
A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition
Brochure More information from http://www.researchandmarkets.com/reports/2326795/ A Project Manager's Book of Forms. A Companion to the PMBOK Guide. 2nd Edition Description: A compendium of ready made
CA Single Sign-On Migration Guide
CA Single Sign-On Migration Guide Web access management (WAM) systems have been a part of enterprises for decades. It is critical to control access and audit applications while reducing the friction for
<PROJECT NAME> PROJECT MANAGEMENT PLAN
PROJECT MANAGEMENT PLAN Version VERSION HISTORY [Provide information on how the development and distribution of the Project Management Plan was controlled and tracked.
Cloud Based Email and Collaboration Project Charter
Cloud Based Email and Collaboration Project Charter Business Case Analysis Phase Version 0.9.5 May 23, 2012 Prepared by: Carol Gravatt Project Directors: Bob Micielli, DNR Dave Kirk, OCIO Document Revision
[BSU Mobile] [Version Number 1.2] Project Charter. Bridgewater State University Information Technology. BSU Mobile. Project ID: 209358
Project Charter Bridgewater State University Information Technology BSU Mobile Project ID: 209358 VERSION: [1.2] REVISION DATE: [10 May 2013] i Contents Section 1. Project Overview... 1 1.1 Problem Statement...
Profesor: Francisco Javier Sanz Pérez. by fjspsv, 2011. PMP Test C13_01
PMP Test C13_01 1. Near the end of your last project, additional requirements were demanded by a group of stakeholders when they learned they would be affected by your project. This became a problem because
Audit Report. Effectiveness of IT Controls at the Global Fund Follow-up report. GF-OIG-15-20b 26 November 2015 Geneva, Switzerland
Audit Report Effectiveness of IT Controls at the Global Fund Follow-up report GF-OIG-15-20b Geneva, Switzerland Table of Contents I. Background and scope... 3 II. Executive Summary... 4 III. Status of
Cloud Computing for Small to Mid Size Businesses. Tech66, LLC William Burleson [email protected] www.tech66.com
Cloud Computing for Small to Mid Size Businesses Tech66, LLC William Burleson [email protected] www.tech66.com Why Tech66 and the Cloud? You want to focus on your core business, not on running your IT infrastructure
Microsoft Premier Deployment. Office 365 Service Description
Microsoft Premier Deployment Office 365 Service The information contained in this document represents the current view of Microsoft Corporation on the issues discussed as of the date of publication and
How To Build A New System For A College
Application Development Methodology The main objective of Enterprise Applications is to design, develop, and maintain quality software. This document out lines the requirements for requesting new systems,
Project Management Quick Reference Guide for MS Project 2010
Project Management Quick Reference Guide for MS Project 2010 Project 2010 offers flexibility and choice by providing tailored work management solutions for individuals, teams, and the enterprise. Besides
exchange.parchment.com
Automation Parchment Send Implementation K-12 Guide: User Guide Ellucian exchange.parchment.com Table of Contents Overview... 2 Product Overview... 3 Access... 3 Transcript Ordering... 3 Request Processing:...
Prepared by Mythtech Limited OFFICE 365 EMAIL MIGRATION MANUAL GUIDELINE
Prepared by Mythtech Limited OFFICE 365 EMAIL MIGRATION MANUAL GUIDELINE Table of Contents Change Password... 1 Send New Email... 2 Forward E-mail... 3 Reply E-mail... 4 Archive old emails... 5 Office
Support and Service Management Service Description
Support and Service Management Service Description Business Productivity Online Suite - Standard Microsoft Exchange Online Standard Microsoft SharePoint Online Standard Microsoft Office Communications
Request for Proposals for Microsoft Project Server 2013 Implementation
Request for Proposals for Microsoft Project Server 2013 Implementation SOLICITATION SA005797 DUE APRIL 2, 2015 @ 11:00 A.M. Gary R. Cavin, CIO Deliver Proposals To: City of Columbus Purchasing Office 77
Municipality of Anchorage. SAP Project. Executive Steering Committee Charter V9.2
Municipality of Anchorage SAP Project V9.2 April 7, 2016 TABLE OF CONTENTS 1 Summary of Changes... 3 2 Purpose... 3 2.1 Responsibilities... 3 3 Membership... 4 4 Meetings... 4 4.1 Standing Meeting Frequency...
Guide Parchment to Implementation and User Automation: Guide PeopleSoft
Guide Parchment to Implementation Send K-12 and User Automation: Guide PeopleSoft 2 Contents OVERVIEW 3 PRODUCT OVERVIEW 4 Access 4 Transcript Ordering 4 Request Processing 4 Transcript Request Fulfillment
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME >
PROJECT MANAGEMENT PLAN TEMPLATE < PROJECT NAME > Date of Issue: < date > Document Revision #: < version # > Project Manager: < name > Project Management Plan < Insert Project Name > Revision History Name
Project Management System Services
Project Management System Services Today's projects need to deal with increasing amounts of information that require better tools to help navigate through all the data produced by projects. Our services
IBM Lotus Domino 8.5 System Administration Bootcamp
IBM Lotus Domino 8.5 System Administration Bootcamp Overview In this course, you will: Be introduced to basic concepts that provide the foundation for Lotus Domino and Lotus Notes Practice performing basic
STRATEGIC WEBSITE INTEGRATION FACELIFT TEAM
STRATEGIC WEBSITE INTEGRATION FACELIFT TEAM Team Leader Faiqa Yazdani TEAM SWIFT LEAP TEAM 2013 Team Members Sarah Ehrsam Belinda Acuña Daniel Corbet Roy Kramer Noel Lopez Mentor Dr. Barry Gribbons Leap
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
IT PROJECT GOVERNANCE GUIDE
IT PROJECT GOVERNANCE GUIDE P1133-ITGG-NNA V1.2 04/24/06 UCLA Office of Information Technology UCLA IT GOVERNANCE TABLE OF CONTENTS 1 IT GOVERNANCE OVERVIEW...1 1.1 STEP 1- PROJECT IDENTIFICATION...1
How To Write A Project Management Plan
Enter Project Name Project Management Plan (PMP) Kickoff Month, Day, Year 1 Purpose The Project Management Plan (PMP) is a formal, approved document used to manage project execution. The PMP documents
UNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK
UNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK Table of Contents Document Purpose:... 3 What is a Project?... 3 What is not a Project? (e.g. Operational Tasks)... 3 What is Project Management?... 4