1 IT PROJECT GOVERNANCE GUIDE P1133-ITGG-NNA V1.2 04/24/06 UCLA Office of Information Technology

2

3 UCLA IT GOVERNANCE TABLE OF CONTENTS 1 IT GOVERNANCE OVERVIEW STEP 1- PROJECT IDENTIFICATION STEP 2 - PROJECT CLASSIFICATION STEP 3 IT PROJECT PORTFOLIO MANAGEMENT STEPS 4-5 IT PROJECT GOVERNANCE CONFIGURATION PROJECT CLASSIFICATION WORKSHEET GOVERNANCE PROCESS TRIGGERS IT GOVERNANCE ARRANGEMENTS MATRIX IT GOVERNANCE PROCESS FRAMEWORK IT GOVERNANCE PROCESS FLOW DIAGRAM...10 IP1133-PDG-NNA V1.2 04/24/06 PAGE i

4 UCLA IT GOVERNANCE REVISION HISTORY 03/09/2006 Version 1.0 First Draft 03/23/2006 Version 1.1 Second Draft 04/24/2006 Version 1.2 Third Draft

5 IT PROJECT GOVERNANCE GUIDE 1 IT GOVERNANCE OVERVIEW This document provides an overview of the IT Project Governance process at UCLA. IT Governance comprises of the leadership, organizational structures, and processes to ensure that UCLA s IT capabilities continue to sustain and extend its strategies and objectives. The UCLA IT Governance structure specifies the decision rights and accountability framework to encourage desirable behavior in using IT to further the University s mission. This desirable behavior is characterized by: Integration of IT strategic planning with campus strategic planning Appropriate accountability for IT initiatives Transparency - IT plans and investments are made visible beyond their origination point (subject to the application of some defined thresholds). Adoption of a broad campus-wide view A willingness to share and use IT best practices across the UCLA community Entrepreneurial spirit and creativity in applying IT Participants understanding the value of the governance process and actively participating in it The overall IT Project governance process flow is shown in Figure 1. A larger version of this diagram may be found on page 10 of this guide. The overall process is broken down in six major steps and these are described in broad terms in this section. The remaining sections of this document provide more specific guidance on certain key aspects of the governance process. Figure 1 IT Governance Process Overview 1.1 Step 1- Project Identification The first step in the IT Governance process is the identification of those IT Projects across the campus that may have significant impact on the campus in terms of outside funding requirements, technological integration, deployment impact, and project management needs. IP1133-PDG-NNA DRAFT 4/24/2006 PAGE 1

6 OIT A major source of information for this step is the identification of such projects through the annual campus strategic planning process. In addition, some projects may arise on an ad hoc basis in response to emergent needs. It is neither necessary nor practical for all IT Projects to pass through the entire IT Governance Process described in this guide. The intent of the governance process is to apply good judgment and to focus attention and resources only on those projects that truly require it and that have the greatest impact on the campus. The primary means of making this judgment is human interaction. Thus this process step requires dialog and discussion between OIT, ITMG and other stakeholders to make an initial assessment on what projects to pass through the process and what projects to filter out. Key questions asked at this stage are: Does project need outside funding? How is project aligned with strategic direction? What is the project motivation (is there a legal mandate?) What is the end user impact of the project? Is there a reason to fast track the project? Will the project be controversial? Based on this initial assessment some projects will move on through the process to Step 2 for further governance consideration, some will be deemed to not require any further IT Governance, and some will be fast tracked through the process. It is important to note that this step does not constitute the official approval of a project, it simply decides if a project should move through a more rigorous governance process. Project approvals remain with the Executive Sponsors of an IT project. 1.2 Step 2 - Project Classification A one to two page Project Bio is created by OIT for every project that enters this process step. The Project Bio is compiled through discussions with the Project Sponsor and the Project Manager. The Project Bio is a brief synopsis of the purpose and scope of the intended project. It captures the basic data that is required to classify the project for governance purposes. Project classification is an integral part of the governance process. The purpose of project classification is threefold: 1. Clearly and objectively identify projects that are likely to have a major impact on the campus. 2. Enable the IT Governance process to be scaled appropriately to the magnitude and impact of a particular IT project. 3. Aid in IT risk management. By dividing IT projects in this way the 80/20 principle can be employed to apply a more flexible governance process that focuses time and attention on major projects that have the largest impact on the campus as whole. Other projects may then be routed through less rigorous and rapid paths in the governance process according to their level of risk and impact. Such an approach begs the question: What constitutes a major project? A Project Classification Worksheet (Page 4) is used to help Project Sponsors, Project Managers and OIT to answer this question in a consistent manner. The Project Classification worksheet consists of a series of questions in three categories:

7 UCLA IT GOVERNANCE Project Management Complexity IT Solution Complexity Deployment Complexity These questions should be answered in a project classification meeting between the Project Manager, the Project Sponsor and an OIT director (with other participants as required). As a guideline this meeting should require no more than one hour. Although the worksheet uses a simple scoring mechanism to encourage discussion, the classification process should not be an empirical exercise. The worksheet is intended as an aid and guide for the project classification discussion. Ultimately the combined knowledge and experience of the participants should determine the appropriate Project Class that makes sense. The resultant project classification is then used to steer the project through the governance process. Class 1 Projects are considered to be low risk and do not need to continue any further in the governance process. They can therefore proceed normally. Class 2-5 Projects move on to Step Step 3 IT Project Portfolio Management Project Classes 2-5 are added to the Campus IT Portfolio. The Campus IT Portfolio is a strategic inventory of IT project information maintained by OIT for planning and IT Governance purposes. Although individual projects in the IT Portfolio may be managed by specific divisions, the IT Portfolio provides overall visibility to Executive leadership of the key IT investments the campus is undertaking. Class 2 projects are simply recorded in the IT Portfolio for general information and monitoring purposes. No further IT Governance is required for this class of project beyond the normal accountability and responsibility of the unit or division that is sponsoring the project. Status information on Class 3-5 projects is updated by OIT as the projects progress through their life cycle. 1.4 Steps 4-5 IT Project Governance Configuration As mentioned earlier, project classification is used to scale the governance process appropriately for the project at hand. In steps 4-5 a specific governance path is determined for the project. This governance configuration is determined by key triggers or characteristics of each project (Page 7). For example, if in the classification process the IT solution complexity of a project is considered to be high (H) or Very High (V) this will trigger the need for a Technical Assessment by OIT/CSG. If the end user scope of impact is deemed to be High (H) then the project should be reviewed by OIT/ITPB for alignment with campus direction & policy. OIT will then use this governance configuration to steer the process through the appropriate IT governance path in terms of committees, review, endorsement and executive approvals. IP1133-PDG-NNA DRAFT 4/24/2006 PAGE 3

8 OIT 2 PROJECT CLASSIFICATION WORKSHEET The Project Classification Worksheet is designed to be used within the UCLA IT Governance process. It is a tool to encourage a frank and open discussion of the potential impact of a planned IT project on the campus and how that project might be properly routed through the IT Governance process. Risk Factor Descriptions/Questions PROJECT MANAGEMENT COMPLEXITY 1. Team Size (# of people) Total number of project team members who will be developing the solution, excluding the Project Manager. 2. # of Units Involved Total number of distinct organizational units within or outside UCLA that must be managed and coordinated to provide requirements for the project. 3. Development Effort Hrs Total estimated solution development effort hours that will be spent by the team excluding project management time. 4. Duration The estimated total elapsed calendar time required to complete the project.

9 UCLA IT GOVERNANCE IT SOLUTION COMPLEXITY 5. Technology/Technique/Process What is the knowledge, skills and expertise of the project team in employing the chosen technologies, techniques, methods and processes to be used on the project? 6. Product Maturity (If purchased) If software packages or commercial software products are to be included the solution, what is the general maturity of these products and their usage within other institutions of higher education? 7. Solution Complexity What is the level of technical complexity of the solution? 8. System Interface Profile What is the complexity of the required system interfaces for the solution in terms of the number software interfaces that need to be developed? 9. IT Architectural Impact What is the architectural impact of the solution in terms of how it will fit with IT Architectural standards (data, applications and technology), and coexist and integrate with other applications? 10. Maintainability What is the degree of complexity of maintaining the application in terms of the level of technical skills required and the specific availability of those skills to UCLA? DEPLOYMENT COMPLEXITY 11. Process Impact What is the implementation scope, boundaries and expected degree of change on academic or administrative processes? 12. End User scope of impact What is the implementation impact in terms of the range and types of campus personnel affected? 13. Project Profile What is the degree of acceptance and readiness level of the affected user constituency for the solution? 14. Project Motivation To what degree is the project being driven by an external mandate from the Federal, State or UCOP level? Project Budget The total estimated development costs for the project (hardware, software, facilities, and people). Ongoing Cost The estimated average annual maintenance cost for the application. This should include regular hardware and software upgrades and maintenance, hosting fees, and vendor support. IP1133-PDG-NNA DRAFT 4/24/2006 PAGE 5

10 OIT Project Class The assigned project class (High 5 to Low 1) based on overall scoring and the group discussion.

11 UCLA IT GOVERNANCE 3 GOVERNANCE PROCESS TRIGGERS The Governance Process Triggers worksheet below maps the results of project classification (Risk Factor ratings) against the recommended Governance Actions that need to be taken. The entries in the Process Steps column are cross references to the IT Process Governance Framework Diagram on page 9. IP1133-PDG-NNA DRAFT 4/24/2006 PAGE 7

12 OIT 4 IT GOVERNANCE ARRANGEMENTS MATRIX The IT Governance Arrangements Matrix below describes who is empowered to make decisions about specific aspects of IT Projects. The matrix maps the decision rights of the various Governance Entities (Committees, Stakeholders and IT groups) against a set of mutually exclusive IT Governance Decision Domains 1. The IT Governance Decision Domains serve to separate project IT decisions into categories for Strategic Direction and Policy, Application Needs, common IT Infrastructure needs and IT Investments. Figure 2 IT Governance Arrangements Matrix Descriptions of the Governance Entities may be found on the OIT website ( 1 This framework is based on the work of Peter Weill & Jeanne W. Ross, IT Governance. Harvard Business School Press, 2004.

13 UCLA IT GOVERNANCE 5 IT GOVERNANCE PROCESS FRAMEWORK The IT Governance Process framework graphically illustrates the reviews, approvals and endorsements that may be applied to projects. Not all projects go through all steps; the specific path taken will be determined by the Governance Triggers analysis (Page 7). IP1133-PDG-NNA DRAFT 4/24/2006 PAGE 9

14 OIT 6 IT GOVERNANCE PROCESS FLOW DIAGRAM

15 IT PROJECT GOVERNANCE GUIDE IP1133-PDG-NNA DRAFT 4/24/2006 PAGE 1

Beyond Mandates: Getting to Sustainable IT Governance Best Practices. Steve Romero PMP, CISSP, CPM IT Governance Evangelist

Beyond Mandates: Getting to Sustainable IT Governance Best Practices. Steve Romero PMP, CISSP, CPM IT Governance Evangelist Beyond Mandates: Getting to Sustainable IT Governance Best Practices Steve Romero PMP, CISSP, CPM IT Governance Evangelist Agenda > IT Governance Definition > IT Governance Principles > IT Governance Decisions

More information

University of Wisconsin Platteville IT Governance Model Final Report Executive Summary

University of Wisconsin Platteville IT Governance Model Final Report Executive Summary University of Wisconsin Platteville IT Governance Model Final Report Executive Summary February 2013 Project Objectives & Approach Objectives: Build on the efforts of the Technology Oversight Planning

More information

The Role of ITIL in IT Governance

The Role of ITIL in IT Governance The Role of ITIL in IT Governance Leveraging IT Governance around IT Service Management Presented By: Rick Leopoldi RL Information Consulting LLC Q2 2005 People Process Technology Why Focus on IT Governance

More information

Institutional Data Recommendations for UC Berkeley: A Roadmap for the Way Forward

Institutional Data Recommendations for UC Berkeley: A Roadmap for the Way Forward InstitutionalDataRecommendations forucberkeley: ARoadmapfortheWayForward June29,2009 Preparedby:MaryBethBaker,ExternalConsultant InstitutionalDataRoadmap,06/29/09 1 I. OVERVIEW of INSTITUTIONAL DATA RECOMMENDATIONS

More information

Department of Administration Portfolio Management System 1.3 June 30, 2010

Department of Administration Portfolio Management System 1.3 June 30, 2010 E 06/ 30/ 2010 EX AM PL 1. 3 06/ 28/ 2010 06/ 24/ 2010 06/ 23/ 2010 06/ 15/ 2010 06/ 18/ 2010 Portfolio System 1.3 June 30, 2010 Contents Section 1. Project Overview... 1 1.1 Project Description... 1 1.2

More information

The University of Alabama at Birmingham. Information Technology. Strategic Plan 2011 2013

The University of Alabama at Birmingham. Information Technology. Strategic Plan 2011 2013 The University of Alabama at Birmingham Information Technology Strategic Plan 2011 2013 Table of Contents Message from the Vice President... 3 About UAB... 4 About UAB Information Technology Meeting needs

More information

The ICT Strategic plan execution toolbox

The ICT Strategic plan execution toolbox The ICT Strategic plan execution toolbox Agenda Elements of an ICT strategic plan Processes and roles needed to deliver on an ICT strategic plan Tools to support the effort needed to deliver on an ICT

More information

Governance of Evaluation, Proof of Concept and Pilot Projects

Governance of Evaluation, Proof of Concept and Pilot Projects Governance of Evaluation, Proof of Concept and Pilot Projects (OCIO) Government of Newfoundland & Labrador Prepared By: (PMO) Table of Contents 1.... 2 2. Definition of an Evaluation... 2 2.1 Example...

More information

Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software

Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software Implementing an Information Governance Program CIGP Installment 2: Building Your IG Roadmap by Rick Wilson, Sherpa Software www.sherpasoftware.com 1.800.255.5155 @sherpasoftware information@sherpasoftware.com

More information

Project Scope Management in PMBOK made easy

Project Scope Management in PMBOK made easy By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating

More information

Visual Enterprise Architecture

Visual Enterprise Architecture Business Process Management & Enterprise Architecture Services and Solutions October 2012 VEA: Click About to edit Us Master title style Global Presence Service and Solution Delivery in 22 Countries and

More information

UNIVERSITY OF MIAMI SCHOOL OF BUSINESS ADMINISTRATION MISSION, VISION & STRATEGIC PRIORITIES. Approved by SBA General Faculty (April 2012)

UNIVERSITY OF MIAMI SCHOOL OF BUSINESS ADMINISTRATION MISSION, VISION & STRATEGIC PRIORITIES. Approved by SBA General Faculty (April 2012) UNIVERSITY OF MIAMI SCHOOL OF BUSINESS ADMINISTRATION MISSION, VISION & STRATEGIC PRIORITIES Approved by SBA General Faculty (April 2012) Introduction In 1926, we embarked on a noble experiment the creation

More information

MedIT Strategic Plan. Mission: To support excellence in health education, research, and service with innovative and sustainable technology solutions.

MedIT Strategic Plan. Mission: To support excellence in health education, research, and service with innovative and sustainable technology solutions. MedIT Strategic Plan 2010 2013 Mission: To support excellence in health education, research, and service with innovative and sustainable technology solutions. The UBC Faculty of Medicine and MedIT work

More information

Information Technology (IT) Governance

Information Technology (IT) Governance Information Technology () Governance A Position Paper Michael Ridley Chief Information Officer and Chief Librarian University of Guelph September 2006 1. Objective This paper outlines an incremental approach

More information

Strategic Plan for the Enterprise Portfolio Project Management Office Governors Office of Information Technology... Ron Huston Director

Strategic Plan for the Enterprise Portfolio Project Management Office Governors Office of Information Technology... Ron Huston Director Strategic Plan for the Enterprise Portfolio Project Management Office Governors Office of Information Technology.......... June 2010 Ron Huston Director Message from the State Enterprise Portfolio Project

More information

ID Task Name Time Pred

ID Task Name Time Pred 0 UC Modernization Project Plan 1115 d 1 1 Phase I - Business Case Development and Competitive Procurement 205 d 2 1.1 Complete Initial Feasibility Study 55 d 3 1.2 Prepare and Issue LBR 30 d 2 4 1.3 Competitive

More information

PTC RETAIL PLM SOLUTION

PTC RETAIL PLM SOLUTION PTC RETAIL PLM SOLUTION PTC Retail PLM Solution On Time, On Trend, On Cost The PTC Retail PLM Solution can transform the way your company collaboratively plans, designs, develops, and sources products.

More information

Strategic Direction 7 Vision for Shared Administrative Services

Strategic Direction 7 Vision for Shared Administrative Services Strategic Direction 7 Vision for Shared Administrative Services Strategic Direction 7 - Centralize the System s business/administrative functions, where appropriate, in order to leverage resources and

More information

INTERNAL SERVICES GROUP PMO

INTERNAL SERVICES GROUP PMO Ownership & Awareness Program 1 Program 3 Program 4 Program 5 Program 6 Program 7 Program 2 Cap ability Development Infra structure Program n INTERNAL SERVICES GROUP ESSENTIAL FUNCTIONS Act as an interface

More information

Software Assurance E-Learning

Software Assurance E-Learning Software Assurance E-Learning Official Microsoft E-Learning courses are designed to provide maximum learning in minimal time. These courses, available to Software Assurance customers on the Microsoft E-Learning

More information

IT Portfolio Management Software Project OBJECTIVES AND REQUIREMENTS

IT Portfolio Management Software Project OBJECTIVES AND REQUIREMENTS Introduction: IT Portfolio Management Software Project OBJECTIVES AND REQUIREMENTS This document summarizes the business objectives, project sponsorship, desired functionality and evaluation criteria (both

More information

Architecture Principles

Architecture Principles Architecture Principles Table of Contents 1 GENERAL INFORMATION...2 2 INTENT...2 3 OWNERSHIP...2 4 APPLYING THE PRINCIPLES...2 5 ARCHITECTURAL OBJECTIVES...2 6 ARCHITECTURE PRINCIPLES...3 6.1 General...

More information

IT Governance (Worthwhile Exercise?) January 10, 2013 Presented by Chad Murphy, CISA

IT Governance (Worthwhile Exercise?) January 10, 2013 Presented by Chad Murphy, CISA IT Governance (Worthwhile Exercise?) January 10, 2013 Presented by Chad Murphy, CISA Things we hear! You are making it much too complex. It is an IT problem! We do not know where to start! We do this already!

More information

Global Delivery Excellence Best Practices for Improving Software Process and Tools Adoption. Sunil Shah Technical Lead IBM Rational

Global Delivery Excellence Best Practices for Improving Software Process and Tools Adoption. Sunil Shah Technical Lead IBM Rational Global Delivery Excellence Best Practices for Improving Software Process and Tools Adoption Sunil Shah Technical Lead IBM Rational Agenda Organization s Challenges from a Delivery Perspective Introduction

More information

Colorado Department of Health Care Policy and Financing

Colorado Department of Health Care Policy and Financing Colorado Department of Health Care Policy and Financing Solicitation #: HCPFRFPCW14BIDM Business Intelligence and Data Management Services (BIDM) Appendix B BIDM Project Phases Tables The guidelines for

More information

How To Write A Successful Automation Project

How To Write A Successful Automation Project ch01.fm Page 1 Thursday, November 4, 1999 12:19 PM Chapter 1 Lights Out Exposed Planning and executing a successful automation project begins by developing realistic expectations for the purpose and scope

More information

Improving Service Asset and Configuration Management with CA Process Maps

Improving Service Asset and Configuration Management with CA Process Maps TECHNOLOGY BRIEF: SERVICE ASSET AND CONFIGURATION MANAGEMENT MAPS Improving Service Asset and Configuration with CA Process Maps Peter Doherty CA TECHNICAL SALES Table of Contents Executive Summary SECTION

More information

Practical Approaches to Achieving Sustainable IT Governance

Practical Approaches to Achieving Sustainable IT Governance Practical Approaches to Achieving Sustainable IT Governance Beyond Mandates: Getting to Sustainable IT Governance Best Practices Agenda IT Governance Definition IT Governance Principles IT Governance Decisions

More information

Rice University Task Force on Information Technology. Report on IT Principles, Governance & Organization

Rice University Task Force on Information Technology. Report on IT Principles, Governance & Organization Rice University Task Force on Information Technology Report on IT Principles, Governance & Organization April 22, 2014 1 IT Principles, Governance, Organization Information technology, across all missions

More information

STATE OF NEW JERSEY IT CIRCULAR

STATE OF NEW JERSEY IT CIRCULAR NJ Office of Information Technology P.O. Box 212 www.nj.gov/it/ps/ Chris Christie, Governor 300 River View E. Steven Emanuel, Chief Information Officer Trenton, NJ 08625-0212 STATE OF NEW JERSEY IT CIRCULAR

More information

State of Minnesota IT Governance Framework

State of Minnesota IT Governance Framework State of Minnesota IT Governance Framework June 2012 Table of Contents Table of Contents... 2 Introduction... 4 IT Governance Overview... 4 Process for Developing the New Framework... 4 Management of the

More information

Whitepaper Enable Talent Management Through Fusion

Whitepaper Enable Talent Management Through Fusion Enable Talent Through Fusion Hexaware Technologies. All rights reserved. Enable Talent Through Fusion Table of Contents 1. Why Talent 3 2. Employee engagement through Talent 3 2.1. Fusion as a Technology

More information

Industry Metrics for Outsourcing and Vendor Management

Industry Metrics for Outsourcing and Vendor Management Industry Metrics for Outsourcing and Vendor Management Scott Goldfarb Q/P Management Group, 10 Bow Street Stoneham, Massachusetts 02180 sgoldfarb@qpmg.com Tel: (781) 438-2692 FAX (781) 438-5549 www.qpmg.com

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11

More information

IT Governance Framework. Western Illinois University. September 2013

IT Governance Framework. Western Illinois University. September 2013 IT Governance Framework Western Illinois University September 2013 Developed by: Subcommittee on IT Governance of the University Technology Advisory Group v8.7 2 TABLE OF CONTENTS EXECUTIVE SUMMARY...

More information

Understanding of Enterprise Architecture - Essences and Framework

Understanding of Enterprise Architecture - Essences and Framework [Term Project Report] Understanding of Enterprise Architecture - Essences and Framework InBong(I.B) Jeon MBA 2007 April 28, 2007 BADM590: IT Governance, Information Trust, and Risk Management Professor

More information

Use of External Consulting Services Fiscal Years 2007/08 through 2010/11 April 2012

Use of External Consulting Services Fiscal Years 2007/08 through 2010/11 April 2012 Use of External Consulting Services Fiscal Years 2007/08 through 2010/11 April 2012 Office of the Auditor General Page 1 Use of External Consulting Services Fiscal Years 2007/08 through 2010/11 March 2012

More information

2011 NASCIO Nomination Business Improvement and Paperless Architecture Initiative. Improving State Operations: Kentucky

2011 NASCIO Nomination Business Improvement and Paperless Architecture Initiative. Improving State Operations: Kentucky 2011 NASCIO Nomination Business Improvement and Paperless Architecture Initiative Improving State Operations: Kentucky Kevin Moore 6/1/2011 Executive Summary: Accounts Payable was a time consuming, inefficient

More information

Critical Success Factors for Enterprise Architecture Engineering

Critical Success Factors for Enterprise Architecture Engineering Visible Solutions Critical Success Factors for Enterprise Architecture Engineering By Alan Perkins Chief Solutions Architect ASG Federal This paper describes critical success factors for developing, implementing,

More information

Open Group SOA Governance. San Diego 2009

Open Group SOA Governance. San Diego 2009 Open Group SOA Governance San Diego 2009 SOA Governance Aspects A comprehensive view of SOA Governance includes: People Organizational structures Roles & Responsibilities Processes Governing processes

More information

Service Catalog Management: A CA Service Management Process Map

Service Catalog Management: A CA Service Management Process Map TECHNOLOGY BRIEF: SERVICE CATALOG MANAGEMENT Catalog : A CA Process Map JULY 2009 Enrico Boverino SR PRINCIPAL CONSULTANT, TECHNICAL SALES ITIL SERVICE MANAGER ITAC CERTIFIED Table of Contents Executive

More information

Organizational Structure for Innovative Software Development

Organizational Structure for Innovative Software Development Joseph C. Thomas Regent University Center for Leadership Studies LEAD606 Strategic Vision and Organizational Effectiveness 30-Sep-2002 Introduction The computer software development industry has been struggling

More information

Based on 2008 Survey of 255 Non-IT CEOs/Executives

Based on 2008 Survey of 255 Non-IT CEOs/Executives Based on 2008 Survey of 255 Non-IT CEOs/Executives > 50% Ranked ITG as very important > 75% of businesses consider ITG to be an integral part of enterprise governance, but the overall maturity level is

More information

Campus Mobile Framework Service Level Agreement (SLA)

Campus Mobile Framework Service Level Agreement (SLA) Campus Mobile Framework Service Level Agreement (SLA) Table of Contents Revision History... 3 1. General Overview... 4 1.1 Service Owners... 4 2. Service Description... 4 2.1 Service Scope... 4 2.2 Mobile

More information

The Strategic Management Maturity Model TM

The Strategic Management Maturity Model TM The Strategic Management Maturity Model TM Many Institute clients ask a similar question as they work to improve their strategic management at their organizations: where do we stand compared with other

More information

MICROSOFT OFFICE PROJECT - SYLLABUS

MICROSOFT OFFICE PROJECT - SYLLABUS MICROSOFT OFFICE PROJECT - SYLLABUS Sessions Session 1 Description 1. INTRODUCTION a. Introduction to CADFORUM and PPM b. Project c. Examples of project d. Project Triangle e. Project Management f. Life

More information

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010

Guideline. Records Management Strategy. Public Record Office Victoria PROS 10/10 Strategic Management. Version Number: 1.0. Issue Date: 19/07/2010 Public Record Office Victoria PROS 10/10 Strategic Management Guideline 5 Records Management Strategy Version Number: 1.0 Issue Date: 19/07/2010 Expiry Date: 19/07/2015 State of Victoria 2010 Version 1.0

More information

Begin Your BI Journey

Begin Your BI Journey Begin Your BI Journey As part of long-term strategy, healthcare entities seek opportunities for continuous improvement in order to meet the changing needs of their patients while also maintaining compliance

More information

Developing Effective IT Governance to Unleash Business Value

Developing Effective IT Governance to Unleash Business Value Developing Effective IT Governance to Unleash Business Value Is IT Governance just a buzz word and fashion theme? Most frequently asked questions about IT Governance Why does IT Governance remain an on-going

More information

ITSM Process Description

ITSM Process Description ITSM Process Description Office of Information Technology Incident Management 1 Table of Contents Table of Contents 1. Introduction 2. Incident Management Goals, Objectives, CSFs and KPIs 3. Incident Management

More information

POSITION SPECIFICATION ENTERPRISE ARCHITECT UK&I

POSITION SPECIFICATION ENTERPRISE ARCHITECT UK&I POSITION SPECIFICATION ENTERPRISE ARCHITECT UK&I THE POSITION The Enterprise Architect will be supporting the Experian Consumer Services UK&I Architecture functions and processes. The Enterprise Architect

More information

Industry Metrics for Outsourcing and Vendor Management

Industry Metrics for Outsourcing and Vendor Management Industry Metrics for Outsourcing and Vendor Management Scott Goldfarb Q/P Management Group, Inc. 10 Bow Street Stoneham, Massachusetts 02180 sgoldfarb@qpmg.com Tel: (781) 438-2692 FAX (781) 438-5549 www.qpmg.com

More information

Project, Program & Portfolio Management Help Leading Firms Deliver Value

Project, Program & Portfolio Management Help Leading Firms Deliver Value in collaboration with Project, Program & Portfolio Help Leading Firms Deliver Value Managing Effectively & Efficiently Through an Enterprise PMO Program & Portfolio : Aligning IT Capabilities with Business

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

The Business Value of Call Accounting

The Business Value of Call Accounting WHITE PAPER The Business Value of Call Accounting How Call Accounting Software Helps Reduce Business Expenses and Improve Productivity Introduction Call accounting software has been available for more

More information

Measuring Success Service Desk Evaluation Guide for the Midsized Business: How to Choose the Right Service Desk Solution and Improve Your ROI

Measuring Success Service Desk Evaluation Guide for the Midsized Business: How to Choose the Right Service Desk Solution and Improve Your ROI BEST PRACTICES WHITE PAPER Measuring Success Service Desk Evaluation Guide for the Midsized Business: How to Choose the Right Service Desk Solution and Improve Your ROI Table of Contents INTRODUCTION...1

More information

Information Technology Projects Evaluation Process

Information Technology Projects Evaluation Process I - Objective The purpose of this document is to describe a process for surfacing and evaluating ideas that might lead to informatics projects or information technology capital expenditures. Such projects

More information

15.571 Generating Business Value from Information Technology

15.571 Generating Business Value from Information Technology MIT OpenCourseWare http://ocw.mit.edu 15.571 Generating Business Value from Information Technology Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.

More information

Professional Services in Cloud ERP

Professional Services in Cloud ERP Photo copyright 2012 Michael Krigsman. Professional Services in Cloud ERP Prepared by Michael Krigsman June 2012 NetSuite sponsored this independent white paper; Asuret does not endorse any vendor s product

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

COURSE TITLE. Project Management for Web designers + Developers CE 2444C INSTRUCTOR. Todd Mariani tmariani@reciprocalpress.

COURSE TITLE. Project Management for Web designers + Developers CE 2444C INSTRUCTOR. Todd Mariani tmariani@reciprocalpress. COURSE TITLE Project Management for Web designers + Developers CE 2444C INSTRUCTOR Todd Mariani tmariani@reciprocalpress.com MEETING TIMES Tuesday 7-10pm Oct 4-Dec 6 COURSE DESCRIPTION This course is ideal

More information

Creating and Maturing a Service Catalog

Creating and Maturing a Service Catalog Creating and Maturing a Service Catalog By Wendy Kuhn and Pam Erskine Third Sky, Inc. Introduction Developing a service catalog can seem like a simple marketing and communications activity or a daunting

More information

W H I T E P A P E R E n a b l i n g D a t a c e n t e r A u t o mation with Virtualized Infrastructure

W H I T E P A P E R E n a b l i n g D a t a c e n t e r A u t o mation with Virtualized Infrastructure W H I T E P A P E R E n a b l i n g D a t a c e n t e r A u t o mation with Virtualized Infrastructure Sponsored by: VMware Tim Grieser August 2008 IDC OPINION Global Headquarters: 5 Speen Street Framingham,

More information

2014 Guide to IT Governance

2014 Guide to IT Governance 2014 Guide to IT Governance What is IT Governance? IT governance provides the conceptual framework, structures, processes, resources and information aligned to university strategies and objectives, enabling

More information

Strategic Plan 2015-2017

Strategic Plan 2015-2017 Strategic Plan 2015-2017 Page 1 Table of Contents Information Technology Mission... 5 Information Technology Vision Statement... 5 Information Technology Values... 5 The Information Technology s Alignment

More information

Assessing the Appropriate Level of Project, Program, and PMO Structure

Assessing the Appropriate Level of Project, Program, and PMO Structure PMI Virtual Library 2011 Daniel D. Magruder Assessing the Appropriate Level of Project, Program, and PMO Structure By Daniel D. Magruder, PMP Executive Summary Does your organization have in-flight projects

More information

Enabling IT Performance & Value with Effective IT Governance Assessment & Improvement Practices. April 10, 2013

Enabling IT Performance & Value with Effective IT Governance Assessment & Improvement Practices. April 10, 2013 Enabling IT Performance & Value with Effective IT Governance Assessment & Improvement Practices April 10, 2013 Today's Agenda: Key Topics Defining IT Governance IT Governance Elements & Responsibilities

More information

Share the webinar Ask a question Votes (polling questions) Rate (before you leave) Attachments (you can download today s presentation)

Share the webinar Ask a question Votes (polling questions) Rate (before you leave) Attachments (you can download today s presentation) Data Center Migration Primer Mark Smith Wednesday, June 27, 2012 General Information Share the webinar Ask a question Votes (polling questions) Rate (before you leave) Attachments (you can download today

More information

INFORMATION TECHNOLOGY SERVICES IT CHANGE MANAGEMENT POLICY & PROCESS

INFORMATION TECHNOLOGY SERVICES IT CHANGE MANAGEMENT POLICY & PROCESS INFORMATION TECHNOLOGY SERVICES IT CHANGE MANAGEMENT POLICY & PROCESS Revised: 12/5/2011 Table of Contents Overview... 3 Roles and Responsibilities... 4 Management Process Definition... 6 Management Process

More information

Work Performance Statement

Work Performance Statement Work Performance Statement Enterprise Date Services Service Management Tool Introduction Acronyms, and Abbreviations AQS FAA Office of Quality, Integration and Executive Services ARB Airmen Records Building

More information

Statement of Direction

Statement of Direction Microsoft Dynamics SL Statement of Direction Product strategy and roadmap for Microsoft Dynamics SL Date: January 2012 www.microsoft.com/dynamics/sl Page 1 CONTENTS Welcome... 3 Overview of Microsoft Dynamics

More information

Anatomy of an Enterprise Software Delivery Project

Anatomy of an Enterprise Software Delivery Project Chapter 2 Anatomy of an Enterprise Software Delivery Project Chapter Summary I present an example of a typical enterprise software delivery project. I examine its key characteristics and analyze specific

More information

MANAGING OTT MESSAGING SERVICES FOR A GLOBAL TELECOM PROVIDER

MANAGING OTT MESSAGING SERVICES FOR A GLOBAL TELECOM PROVIDER MANAGING OTT MESSAGING SERVICES FOR A GLOBAL TELECOM PROVIDER Sytel Reply was commissioned by a client (a large global telecom operator) to provide quality Service Assurance. Over a period of 12 months,

More information

MGMT 4135 Project Management. Chapter-16. Project Oversight

MGMT 4135 Project Management. Chapter-16. Project Oversight MGMT 4135 Project Management Chapter-16 Project Oversight Project Oversight: defined as a set of principles and processes to guide and improve the management of projects. Ensures projects meet the needs

More information

Availability Management: A CA Service Management Process Map

Availability Management: A CA Service Management Process Map TECHNOLOGY brief: AVAILABILITY MANAGEMENT Availability : A CA Process Map Malcolm Ryder ARCHITECT CA SERVICES Table of Contents Executive Summary 1 SECTION 1: CHALLENGE 2 Simplifying ITIL How to Use the

More information

IT UNIFICATION Vision, Impact & Strategy. May 2015

IT UNIFICATION Vision, Impact & Strategy. May 2015 IT UNIFICATION Vision, Impact & Strategy May 2015 Presentation Agenda Why Unification Embracing Business Drivers UC San Diego Strategic Plan IT Unification Vision Campus Impact What s in it for campus?

More information

SOA Adoption and Context Levels

SOA Adoption and Context Levels SOA Adoption and Context Levels Prepared by: http://www.integratedsecure.com 8605 Westwood Center Drive, Suite 206 Vienna, Virginia 22182 Version: 1.0 February, 2010 Table of Contents 1. Intended Audience...

More information

OPTIMUS SBR. Optimizing Results with Business Intelligence Governance CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE.

OPTIMUS SBR. Optimizing Results with Business Intelligence Governance CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE. OPTIMUS SBR CHOICE TOOLS. PRECISION AIM. BOLD ATTITUDE. Optimizing Results with Business Intelligence Governance This paper investigates the importance of establishing a robust Business Intelligence (BI)

More information

Global Solution Services Overview

Global Solution Services Overview O V E R V I E W Corporate Headquarters 750 Central Expressway, Santa Clara, California 95050-2627 USA Contact Information: + 1 408 970 1000 www.hds.com / info@hds.com Asia Pacific and Americas 750 Central

More information

Enterprise Architecture (Re)Charter Template

Enterprise Architecture (Re)Charter Template Enterprise Architecture (Re)Charter Template To learn more about this full research or to inquire about membership, contact us: +1-866-913-8101 IT.Support@ executiveboard.com www.cebglobal.com/it CEB Enterprise

More information

Architecture Maturity: The PDCA Cycle

Architecture Maturity: The PDCA Cycle Architecture Maturity: The PDCA Cycle The architecture maturity cycle is based on the well recognized Plan-Do-Check-Act cycle, a four phase cycle for implementing change. Refer to Figure 11.1-1. Repetition

More information

QEx WHITEPAPER. Increasing Cost Predictability in Performance Testing Services via Unit-Based Pricing Model. www.hcltech.com

QEx WHITEPAPER. Increasing Cost Predictability in Performance Testing Services via Unit-Based Pricing Model. www.hcltech.com www.hcltech.com QEx WHITEPAPER Increasing Cost Predictability in Performance Testing Services via Unit-Based Pricing Model Business Assurance & Testing Across the spectrum of IT projects, whether it is

More information

WhitePaper. The Business Value of Call Accounting Software How Call Accounting Helps Reduce Telecom Expenses and Improve Productivity

WhitePaper. The Business Value of Call Accounting Software How Call Accounting Helps Reduce Telecom Expenses and Improve Productivity The Business Value of Call Accounting Software How Call Accounting Helps Reduce Telecom Expenses and Improve Productivity WhitePaper We innovate. You benefit. The Business Value of Call Accounting Software

More information

METRO REGIONAL GOVERNMENT Records Retention Schedule

METRO REGIONAL GOVERNMENT Records Retention Schedule Program: Administration IS Administration provides strategic planning, direction, and central management oversight of the Information Services that includes the following programs: Desktop Support Services,

More information

IT Project Management Practices Guide

IT Project Management Practices Guide IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or

More information

IT Service Provider and Consumer Support Engineer Position Description

IT Service Provider and Consumer Support Engineer Position Description Engineer Position Description February 9, 2015 Engineer Position Description February 9, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level Definitions...

More information

Ubertas Cloud Services: Service Definition

Ubertas Cloud Services: Service Definition Ubertas Cloud Services: Service Definition February 2013 Innovation. Power. Trust. Contents 1. About Ubertas... 2 Our Company... 2 Our Approach to Service Delivery... 2 Our Partner Network & the UK Cloud

More information

The Importance of Organizing Your SJSU Information Assets

The Importance of Organizing Your SJSU Information Assets Standard: Asset Control Page 1 Executive Summary The Asset Control Standard defines the requirements for controlling and ensuring all SJSU computing hardware, software, and confidential assets are identified,

More information

Information Technology Strategic Plan 2014-2017

Information Technology Strategic Plan 2014-2017 Information Technology Strategic Plan 2014-2017 Leveraging information technology to create a competitive advantage for UW-Green Bay Approved December 2013 (Effective January 2014 December 2017) Contents

More information

Contents. Evolving Trends in Core Banking Transformation (CBT) Challenges Faced in Core Banking Transformation (CBT)

Contents. Evolving Trends in Core Banking Transformation (CBT) Challenges Faced in Core Banking Transformation (CBT) Contents Preface From the Editor s Desk Evolving Trends in Core Banking Transformation (CBT) 01. Customer Expectations and Next Generation Banking 05 02. Survival Driving Core Banking Transformation (CBT)

More information

Business Architecture Innovation Summit. March 26, 2014

Business Architecture Innovation Summit. March 26, 2014 Architecture Innovation Summit March 26, 2014 WHO IS NATIONWIDE? Nationwide Mutual Insurance Company Full range of insurance and financial services Sales network for property and casualty insurance Columbus

More information

Finance Division. Strategic Plan 2014-2019

Finance Division. Strategic Plan 2014-2019 Finance Division Strategic Plan 2014-2019 Introduction Finance Division The Finance Division of Carnegie Mellon University (CMU) provides financial management, enterprise planning and stewardship in support

More information

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions

Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Fixed Scope Offering for Implementation of Sales Cloud & Sales Cloud Integration With GTS Property Extensions Today s Business Challenges Adopt leading CRM practices and stream line processes Take advantage

More information

Three Fundamental Techniques To Maximize the Value of Your Enterprise Data

Three Fundamental Techniques To Maximize the Value of Your Enterprise Data Three Fundamental Techniques To Maximize the Value of Your Enterprise Data Prepared for Talend by: David Loshin Knowledge Integrity, Inc. October, 2010 2010 Knowledge Integrity, Inc. 1 Introduction Organizations

More information

October 8, 2014. User Conference. Ronald Layne Manager, Data Quality and Data Governance rlayne@gwu.edu

October 8, 2014. User Conference. Ronald Layne Manager, Data Quality and Data Governance rlayne@gwu.edu Ensuring the highest quality data is delivered throughout the university providing valuable information serving individual and organizational need October 8, 2014 Ronald Layne Manager, Data Quality and

More information

Ten Steps to Comprehensive Project Portfolio Management Part 1 An Introduction By R. Max Wideman Introduction Project

Ten Steps to Comprehensive Project Portfolio Management Part 1 An Introduction By R. Max Wideman Introduction Project August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 1 An Introduction By R. Max Wideman This series of papers has been developed from our work in upgrading TenStep's PortfolioStep.

More information

Structuring Information Management (IM) around a Service Centric Framework. Date: 6th May 2015. www.inl.gov. Ian Mckirdy

Structuring Information Management (IM) around a Service Centric Framework. Date: 6th May 2015. www.inl.gov. Ian Mckirdy Structuring Information Management (IM) around a Service Centric Framework Date: 6th May 2015 www.inl.gov Ian Mckirdy Information Management (IM) Service Management Approach to Service Portfolio and Service

More information

NCOE whitepaper Master Data Deployment and Management in a Global ERP Implementation

NCOE whitepaper Master Data Deployment and Management in a Global ERP Implementation NCOE whitepaper Master Data Deployment and Management in a Global ERP Implementation Market Offering: Package(s): Oracle Authors: Rick Olson, Luke Tay Date: January 13, 2012 Contents Executive summary

More information

5053A: Designing a Messaging Infrastructure Using Microsoft Exchange Server 2007

5053A: Designing a Messaging Infrastructure Using Microsoft Exchange Server 2007 5053A: Designing a Messaging Infrastructure Using Microsoft Exchange Server 2007 Course Number: 5053A Course Length: 3 Days Course Overview This three-day instructor-led course provides students with the

More information