Project Charter Content Management System REPLACEMENT
|
|
|
- Tamsin Ward
- 10 years ago
- Views:
Transcription
1 Project Created By Executive Sponsor Content Management System Replacement System Kelly Mullin, Paul Burr, Parporn Metharom, Jason Bogal, Barbara Barry, Lori Piccinini Nancy Leuenhagen, Laura Schmidt Date Created 3/01/2013 Date Last Updated Project Champions 4/15/ :19:00 PM Kelly Mullin Mission Practical Problem to Solve and/or Opportunity to Gain Internet Architecture has greatly advanced in the last 10 years and our County website is not currently able to keep up with the latest security requirements to be a safe and secure website, and is very cumbersome to support and maintain. Many of the features and functionality are outdated and since it was an in house developed system and due to staff turnover and budget reductions, the site is nearing the unsupported state. This would put the county and its citizens at risk if the site was down. The mission of this project is to : Replace the existing home grown legacy Content Management application (CMS) and implement a new CMS system which is more secure and usable. Process Project Initialization o Define requirements/scope. o Identifying initial and on-going funding cost and sources. o Produce Project document. (Project Charter) Planning o Create RFP if needed o Evaluate vendors and select an application. o Select third parties contract/partner if needed. o Produce Planning Document. (Project Milestones, Project Scope /High-level Work Breakdown structure(wbs), Swim Lane Diagram, Migration plan.) o Create plan and implement Project change management. (Newsletter, Training, etc.) Development and Testing o Create Testing environment. o Create user manual. o Train users. o Transfer data to new system. o Create/implement Citizen testing plan. Implementation and Training o Get Production environment ready. o Transfer data to new system. o Quality Assurance. o Put in place plans for ongoing support, upgrades, trainings. Post implementation review. CMS Project Charter.docx Page 1
2 Objectives Enhance county www site hardware and software security. Support the implementation of county site new look and feel. Simplify software maintenance and support. Streamline site building processes. Increase online citizen access and involvement. Comply with Section 508. Deliverables New Hardware & the new chosen software. Stakeholders Project Documentation. (Vendor matrix, Project Charter, Project Scope, Project Milestones, Work Breakdown structure, Swim lane diagram) Change Management Plan & Implementation. Communication Plan including Service-in-kind agencies. Testing Plan & Implementation. Go live and on-going support Plan & Implementation. Training Plan & Document. Post implementation document. Major Stakeholders: (Org.) BCC Functional Development / Technical Support Customer /Business Process Impacted Supplier/ Vendor Funding Sources Community Relations Technology Services On-going Departments with more complex needs. E.g. Assessors, Clerks, Health, etc. Departments with simple needs. Third parties contract/partner Citizen Sponsor with Roles and The of Sponsor are: Be responsible for making project decisions that cannot be made by the CMS Selection Committee. CMS Project Charter.docx Page 2
3 Fund Finder with The of Fund Finder are: Be responsible for identifying funding sources for the project. Negotiating a contract. Determine how long-term cost and on-going maintenance are to be managed. CMS Selection and Planning Subcommittee with IWG CMS Subcommittee with The of CMS Selection and Planning Subcommittee are: Determine the final direction. (Evaluate vendors and select an application) Determine/select a third parties contract/partner. Define timeline of the project. The IWG Subcommittee team members are as follows: The of IWG CMS Subcommittee are: Define requirements. Identify a list of viable vendors and/or systems. Evaluate and score each vendor/system and narrow the list down to 3 vendors/systems. Help testing the final 3 systems. Agree on the completion of key milestones including the deliverables and timelines. Training CMS Project Charter.docx Page 3
4 Implementation Team with The of Implementation Team are: Create Project related Documentation (Project Charter, Project Scope, Project Milestones, High-level Work Breakdown structure (WBS), Swim Lane Diagram, Migration plan) Create plan and implement Project change management. Work with third parties contract/partner. Create Testing and Production environment (Install the system, Configure the system, Set Security, etc.) Create/Implement the Project using Work Breakdown structure (WBS) and Swim Lane Diagrams Create/Implement Testing plan including Citizen involvement. Quality Assurance. Create user manual. Train users. Content Expert with The of Content Expert are: Help testing the final 3 systems. Transfer data to new system from Test to Production. Quality Assurance. Support Team with The of Support Team are: Put in place plans for ongoing support, upgrades, trainings. Perform on-going system upgrade. Perform on-going system technical support. Perform on-going system user training/user manual update. CMS Project Charter.docx Page 4
5 Assumptions Funding is available for our first choice option 1. ($100,000 limit for not to go to BCC.) Every Department has a content expert. Content expert participate in a timely manner. Will find a system that meets our needs. Any system we choose will require some amount of customization. There will be a separate parallel project to design the look and feel and brand the County. This project includes replacement of county intranet (eww) and service in kinds. This project has the support of County Management. Time line accommodates/reflects staff work load from other projects. Risks Availability of Funding. Boundaries Not in the scope Communications and Change Management Decision Making Process Availability of staff resources. Stability and vulnerability of existing system. The project depends on the design of look and feel project s deliverables. Find a reliable third parties contract/partner. Section 508 Compliance Focus on stability and security and not business aspects of the project Departments resistance to change. Design the new look and feel of the county and intranet sites. New content from content expert is not in this scope. Regular Meetings - May be weekly after the vendor is selected. Status Report - Weekly after the vendor is selected. Monthly Project Status update to Department heads / Elected Official, Content Experts, and Service-in-kind agencies. Lunch-n-Learn Sessions. Various Project documents. (Project SharePoint site, Project Charter, Project Scope, Project Milestones, Work Breakdown structure(wbs), Swim Lane Diagram, Training, Manual) Training. Implementation team will be empowered to make decisions for the project. All significant decisions or disputes will be brought to the Executive Sponsor. 1 From Joan Rueda in Purchasing. Nevada Revised Statute allows computer software to be exempt from competitive bidding. While NRS allows computer software to be purchased without competitive bids (RFP) it is recommend that we at least get three quotes if the cost is greater than $25,000. If the software system is being purchased with grant funds we would be required to follow the guidelines of the granting agency. If the purchase price is over $100,000, we will still need to get BCC approval on the purchase order, as the purchasing and contacts manager s signature limit is $100,000. This is a quick RFP 101, please let me know if you would like to have a more detailed explanation. CMS Project Charter.docx Page 5
Converse County Website Design & Development
No. IT-16-01 Converse County Website Design & Development Converse County 107 North 5 th Street Suite B4 Douglas, WY 82633 Inquiries Inquiries about this must be in writing and directed to: Justin Lane
Charter & Scope Statement Web & Portal Redesign. Brookdale Community College
Charter & Scope Statement Web & Portal Redesign Brookdale Community College May October, 2012 Table of Contents PROJECT PURPOSE AND JUSTIFICATION 3 EXECUTIVE SUMMARY 3 PROJECT SCOPE AND DELIVERABLES PROJECT
Program Lifecycle Methodology Version 1.7
Version 1.7 March 30, 2011 REVISION HISTORY VERSION NO. DATE DESCRIPTION AUTHOR 1.0 Initial Draft Hkelley 1.2 10/22/08 Updated with feedback Hkelley 1.3 1/7/2009 Copy edited Kevans 1.4 4/22/2010 Updated
AUTHORIZE THE CITY MANAGER TO ENTER INTO A CONTRACT WITH SHARESQUARED TO FURNISH AND DELIVER AN ENTERPRISE CONTENT MANAGEMENT SYSTEM
TO: Honorable Mayor and City Council THROUGH: Finance Committee FROM: SUBJECT: Department of Information Technology AUTHORIZE THE CITY MANAGER TO ENTER INTO A CONTRACT WITH SHARESQUARED TO FURNISH AND
Template K Implementation Requirements Instructions for RFP Response RFP #
Template K Implementation Requirements Instructions for RFP Response Table of Contents 1.0 Project Management Approach... 3 1.1 Program and Project Management... 3 1.2 Change Management Plan... 3 1.3 Relationship
City of Crestview, Florida Website Design & Development
No. 16-02 City of Crestview, Florida Website Design & Development City of Crestview 198 Wilson North Street Crestview, Florida 32536 Inquiries Inquiries about this should be directed to: Elizabeth Roy
Project Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
SharePoint 2013 Social Intranet Case Study
Social Business Interactive SharePoint 2013 Social Intranet Case Study Middleburg Bank Anna Kaur Manager, Business Solutions and Quality Assurance Social Business Interactive BACKGROUND Middleburg Financial
Project Management Fundamentals. Office of the Senior Associate Vice President for Finance
Project Management Fundamentals Project Management Institute PMI is an aggregation of best practices from thousands of professional project managers Principles in this training are based on PMI methodologies,
DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE
Prepared by Jenn Coast and Christina Konstantinidou, ITS Last Edited May 8, 2015 SOLUTION PLAN REQUIREMENTS ANALYSIS DESIGN BUILD TEST TRAIN/DEPLOY MAINTENANCE Project Charter Executive Summary With the
Canadian Kennel Club (CKC) Request for Proposals to Document Detailed Business Requirements for the Selection and Implementation of a New ERP System
Canadian Kennel Club (CKC) Request for Proposals to Document Detailed Business Requirements for the Selection and Implementation of a New ERP System Issue Date: April 30, 2015 Closing Time: May 28, 2015,
Attachment G - Required Response Format for ERP Implementation Service Providers
Page 1 of 5 Attachment G - Required Response Format for ERP Implementation Service Providers A. Transmittal Letter The Transmittal Letter must address the following topics: 1. Summary of Ability and Willingness
Project Processes. Media Snapshot. Project Management Process Groups
Project Processes PROJECT LIFECYCLE A project normally requires a number of processes. A process is a series of actions directed toward a particular result Project management can be viewed as a number
Helping Coyotes Catch Road Runners Since 1949. Project Alpha: Call Tracking System Upgrade
Helping Coyotes Catch Road Runners Since 1949 Project Alpha: Call Tracking System Upgrade Project Charter V2.0 July 8, 2013 TABLE OF CONTENTS 1 INTRODUCTION/HISTORY... 3 1.1 About this Document What is
STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840
MARYLAND STATE BOARD OF ELECTIONS P.O. BOX 6486, ANNAPOLIS, MD 21401-0486 PHONE (410) 269-2840 Bobbie S. Mack, Chairman David J. McManus, Jr., Vice Chairman Rachel T. McGuckian Patrick H. Murray Charles
Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects
State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement
PROJECT DELIVERY METHODOLOGY (PDM) Florida Department of Transportation Office of Information Systems. Business Systems Support Office
2013 Florida Department of Transportation Office of Information Systems Business Systems Support Office Version 1.6 : 5/17/2013 PROJECT DELIVERY METHODOLOGY (PDM) Index May 17, 2013 1 CHAPTER 1 INTRODUCTION
ITS Projects Systems Engineering Process Compliance Checklist
ITS Projects Systems Engineering Process Compliance Checklist FHWA Final Rule (23 CFR 940) This checklist is to be completed by the MDOT or LPA Project Management Staff. Please refer to the accompanying
Project Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
Attachment 7 Requirements Traceability Matrix (RTM) ATMS RFP. New York State Department of Transportation Advanced Traffic Management System
Attachment 7 Requirements Traceability Matrix (RTM) ATMS RFP New York State Department of Transportation Advanced Traffic Management System i 1. INTRODUCTION This Requirements Traceability Matrix (RTM)
SharePoint Implementation Planning Document 1 Template
Suite 3, Level 7, 16 Wentworth Street, Parramatta NSW 2150 Tel: 1300 797 838 - Fax: 1300 797 848 URL: www.empowercs.com.au SharePoint Implementation Planning Document 1 Template Attention: Prepared by:
Information Technology Services Project Management Office Operations Guide
Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...
Waterloo CMS Project. Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada
Waterloo CMS Project Project Charter Information Systems and Technology (IST) University of Waterloo (UW) Waterloo, Ontario, Canada Charter Date: September 4, 2009 Revision Date: February 10, 2010 Maintained
Second Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract
Second Amendment To the HIPAA 5010 and ICD-10 Technical Assistance and Support Services Contract This second Amendment to Contract Number is effective as of December 12, 2011, between the Iowa Department
REQUESTS FOR PROPOSAL RFP TGF-16-017. Title: Professional Services for the Implementation of the Board Governance Performance Assessment Framework
REQUESTS FOR PROPOSAL RFP TGF-16-017 Title: Professional Services for the Implementation of the Board Governance Performance Assessment Framework Issue Date: March, 9th 2016 RFP Submission Date: March,
MNLARS Project Audit Checklist
Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?
Project Scope and Approach
Oakland County Department of Information Technology Project Scope and Approach Project Name: IVR Platform Upgrade Project ID: D90186IV Leadership Group: Information Technology Steering Committee Department:
SAMPLE WORK BREAKDOWN STRUCTURES VARIOUS TYPES OF PROJECT
Applications Development Project Sample WBS Management and support Provide project management Provide quality control Conduct meetings and reviews Materials and supplies Travel and living costs Miscellaneous
SECTION I PROJECT SUMMARY (TRW)
SECTION I PROJECT SUMMARY (TRW) Table I Summary Agency/Department Information TRW Information Executive Sponsor: Cynthia Lorenzo Received Date: Managers: Ron McCranie/Andy Loveland Status Meeting Date:
Cloud Based Email and Collaboration Project Charter
Cloud Based Email and Collaboration Project Charter Business Case Analysis Phase Version 0.9.5 May 23, 2012 Prepared by: Carol Gravatt Project Directors: Bob Micielli, DNR Dave Kirk, OCIO Document Revision
Facilities Portfolio Management Tool
2016 Facilities Portfolio Management Tool Project Charter Budget- Facilities Oversight Office of Financial Management 4/10/2016 CONTENTS Overview... 2 Purpose Statement... 2 Background... 2 Goals & Objectives...
Department of Training and Workforce Development Western Australia. RPL Assessment Tool Kit. BSB51407 Diploma of Project Management
Department of Training and Workforce Development Western Australia RPL Assessment Tool Kit BSB51407 Diploma of Project Management First published 2010 ISBN 978-1-74205-511-4 Department of Training and
CONTENTS. List of Tables List of Figures
Prelims 13/3/06 9:11 pm Page iii CONTENTS List of Tables List of Figures ix xi 1 Introduction 1 1.1 The Need for Guidance on ERP System Validation 1 1.2 The Need to Validate ERP Systems 3 1.3 The ERP Implementation
REQUEST FOR PROPOSAL WEB SITE DESIGN, DEVELOPMENT & HOSTING December 19, 2013 Table of Contents 1. Summary... 2 2. Proposal Guidelines and Requirements... 2 3. Contract Terms... 2 4. Purpose, Description
CounselorMax and ORS Managed Hosting RFP 15-NW-0016
CounselorMax and ORS Managed Hosting RFP 15-NW-0016 Posting Date 4/22/2015 Proposal submission deadline 5/15/2015, 5:00 PM ET Purpose of the RFP NeighborWorks America has a requirement for managed hosting
System/Data Requirements Definition Analysis and Design
EXECUTIVE SUMMARY This document provides an overview of the Systems Development Life-Cycle (SDLC) process of the U.S. House of Representatives. The SDLC process consists of seven tailored phases that help
PROJECT SCOPE STATEMENT
PROJECT SCOPE STATEMENT Note: Any work not explicitly included in this Project Scope Statement is implicitly excluded from the project. Create links to referenced documents (e.g., Link_To_ ) by using Insert
Minnesota Health Insurance Exchange (MNHIX)
Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration
Information Technology Project Management (ITPM)
FUNCTIONAL AREA 10 Project Management (ITPM) Incumbents in this functional area direct information technology system solution and/or improvement projects for cost, time, scope, risk, and quality. They
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
Request for Proposal Permitting Software
Request for Proposal Permitting Software Date Issued: October 7, 2015 Proposals Due no later than: 2:00pm EST on November 10, 2015 Page 1 of 10 Revised 10/5/2015 TABLE OF CONTENTS Section I Introduction
REQUEST FOR PROPOSAL Website Design and Development. DUE DATE: FEBRUARY 19, 2016-12:00 p.m.
REQUEST FOR PROPOSAL Website Design and Development DUE DATE: FEBRUARY 19, 2016-12:00 p.m. City of Willow Park 516 Ranch House Rd. Willow Park, Texas 76087 (817) 441 7108 www.willowpark.org Inquiries Inquiries
Appendix G: Organizational Change Management Plan. DRAFT (Pending approval) April 2007
Appendix G: Organizational Change Management Plan DRAFT (Pending approval) April 2007 Table of Contents TABLE OF CONTENTS... 1 INTRODUCTION:... 2 ABT ORGANIZATIONAL CHANGE MANAGEMENT SCOPE... 2 PEOPLESOFT
KIPP Austin Public Schools Human Resources Information Systems (HRIS)
Human Resources Information Systems (HRIS) Request for Proposals February 26th, 2015 PROPOSAL DATE DUE: 3-17-2015 5:00 P.M. CST Request for Proposals Contents Project Overview... 2 Background... 2 Schedule...
Information Technology Project Management
Information Technology Project Management by Jack T. Marchewka Power Point Slides by Jack T. Marchewka, Northern Illinois University Copyright 2006 John Wiley & Sons, Inc. all rights reserved. Reproduction
Project Scope Management in PMBOK made easy
By Dr. TD Jainendrakumar The main objective of any project is to fulfill the scope of the project on time and within the budget. What is Project Scope? Scope refers to all the work involved in creating
REQUEST FOR PROPOSAL INFORMATION SECURITY PROGRAM PROVIDER
REQUEST FOR PROPOSAL INFORMATION SECURITY PROGRAM PROVIDER OCTOBER 18, 2013 1 Table of Contents I. EXECUTIVE OVERVIEW... 3 II. BACKGROUND... 3 A. Goals & Objective of Request... 3 B. Project Scope... 4
Company A Project Plan
Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures
Chapter 6 Implementation Planning
Chapter 6 Planning Planning- Division into Work Packages The following are the recommended Work Packages Overall Change Programme Work Package 1 E-Cabinet Model Work Package 2 Security Policy Design Work
Procurement Reporting - OBIEE
UC BERKELEY Procurement Reporting - OBIEE Project Charter Tracey Bolton 9/7/2011 0 P age Version 3 Project Name: Prepared by: EDW Procurement Reporting Project Tracey Bolton Date (MM/DD/YYYY): 08/4/2011
How To Manage The Health Benefit Exchange At Mhix
Minnesota Health Insurance Exchange (MNHIX) 1.1.2 Project Charter Date: 09/21/2012 11/9/2012 12:10 PM Page 1 of 18 T A B L E O F C O N T E N T S 1. MNHIX Introduction... 3 1.1 MNHIX Scope... 4 1.2 Critical
EMR Implementation Planning Guide
EMR Implementation Planning Guide A Ten-Step Guide to Planning for Successful Implementation of an Electronic Medical Record (EMR) System 1 Contents Purpose of this guide... 3 Step 1: Establishing the
CITY OF STARKE. Project # 2016-02
CITY OF STARKE Project # 2016-02 Request for Proposals For Enterprise Content Management System 209 N. Thompson Street Post Office Drawer C Starke, Florida 32091 00 Contents CITY OF STARKE REQUEST FOR
Request for Proposal For: PCD-DSS Level 1 Service Provider St. Andrew's Parish Parks & Playground Commission Bid Deadline: August 17, 2015 at 12 Noon
Request for Proposal For: PCD-DSS Level 1 Service Provider St. Andrew's Parish Parks & Playground Commission Bid Deadline: August 17, 2015 at 12 Noon Request for Proposal P a g e 2 Table of Contents 1.
How To Write An Slcm Project Plan
SLCM 2003.1 Artifacts in a Nutshell ( as of 01/21/2005) Project Development Phases Pension Benefit Guaranty Corporation s (PBGC) System Life Cycle Methodology (SLCM) is comprised of five project development
Information Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
1. PURPOSE 2. BACKGROUND. 2.1 Functionalities of the Current GCIS ECMS. BID SPECIFICATIONS FOR GCIS SHAREPOINT Page 1 of 9
BID SPECIFICATIONS Upgrade and Extend SharePoint as the GCIS Extranet, Enhance, Support and Maintenance of GCIS Enterprise Content Management System (ECMS) for a period of three (3) years Reference: GCIS
Project Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
Agenda. 0 Agenda review 2 minutes. 0 Chapter of the week 50 minutes. 0 Q&A of chapter 10 minutes. 0 Break 10 minutes. 0 Exercises 25 minutes
Agenda 0 Instructor Introduction 3 minutes 0 Agenda review 2 minutes 0 Chapter of the week 50 minutes 0 Q&A of chapter 10 minutes 0 Break 10 minutes 0 Exercises 25 minutes 0 Round table 15 minutes 0 Closure
OE PROJECT CHARTER TEMPLATE
PROJECT : PREPARED BY: DATE (MM/DD/YYYY): Project Name Typically the Project Manager Project Charter Last Modified Date PROJECT CHARTER VERSION HISTORY VERSION DATE (MM/DD/YYYY) COMMENTS (DRAFT, SIGNED,
MUNICIPALITY OF CHATHAM-KENT CORPORATE SERVICES INFORMATION TECHNOLOGY SERVICES INFORMATION REPORT
MUNICIPALITY OF CHATHAM-KENT CORPORATE SERVICES INFORMATION TECHNOLOGY SERVICES INFORMATION REPORT TO: FROM: Mayor and Members of Council Joann Kjeldsen, Project Manager, ITS DATE: October 17, 2011 SUBJECT:
REQUEST FOR PROPOSAL NO. RFP09502 FOR WEBSITE REFRESH FOR SEATTLE PUBLIC SCHOOLS
Seattle Public Schools Contracting Services 2445 Third Avenue South Seattle, WA 98134 Telephone: (206) 252-0566 Fax: (206) 743-3018 [email protected] REQUEST FOR PROPOSAL NO. RFP09502
Education Data Portal ( EDP ) Data Dashboard Solutions
NYSED DATA DASHBOARD SOLUTIONS RFP Attachment 6.8 Statement of Work Template THIS IS STATEMENT OF WORK dated [Date] (the SOW ) to the Contract dated [Date] (the Agreement ) between NEW YORK STATE EDUCATION
Step by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
Case Study SharePoint Implementation
Case Study SharePoint Implementation This proposal includes data that shall not be disclosed outside of the client and shall not be duplicated, used or disclosed in whole or in part for any purpose other
Crosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
SOUTH FLORIDA INTERNATIONAL CHARTER SCHOOL
SOUTH FLORIDA INTERNATIONAL CHARTER SCHOOL 1225 SE 2nd Avenue, Ft. Lauderdale, FL sfics.org South Florida International Charter School is a Florida not for profit corporation, which will be operating Public
Request For Proposal Redesign, Development, and Ongoing Hosting of the Monterey Peninsula College website (www.mpc.edu)
Request For Proposal Redesign, Development, and Ongoing Hosting of the Monterey Peninsula College website (www.mpc.edu) 980 Fremont Street Monterey, California 93940 Telephone (831.646.4000) Email: [email protected]
PHASE 5: DESIGN PHASE
PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed
Microsoft Active Directory Project
Microsoft Active Directory Project Simcoe County District School Board Project Kick-off Meeting Rami Wehbe (Solution Architect) January 18, 2012 Agenda Introductions Project objectives and drivers Approach
C. La Plata County is exempt from all state taxation including state sales and use tax.
Informal Bid (Request for Quotes) Drupal Hosting and Development Service Project Number 12-062-2201 Let Date: August 17, 2012 Bid Deadline: 2:00 p.m. August 30, 2012 I. Administrative Information A. La
IT Project Management Practices Guide
IT Project Management Practices Guide Introduction The IT Project Management Practices Guide (Guide) contains a repeatable, institutionwide approach for the management of application development and/or
Oakland County Department of Information Technology Project Scope and Approach
Oakland County Department of Information Technology Project Scope and Approach Project Name: Mobile Device Management Project ID: TN5186MD Leadership Group: Information Technology Steering Committee Department:
Project Management for Everyone
Project Management for Everyone Contact Information Adam Donaldson, PMP Business Management & Analysis Group System, Analytics & Insights Group Phone: (202) 994-6867 Email: [email protected] Objectives Basic
A Practical Guide for Creating an Information Management Strategy and Strategic Information Management Roadmap
A Practical Guide for Creating an Information Management Strategy and Strategic Information Management Roadmap Principal Author Sam McCollum, CRM, MBA Director of End User Consulting Parity Research LLC
OTSEGO COUNTY REQUEST FOR PROPOSALS WEBSITE DEVELOPMENT BID 2008-4
OTSEGO COUNTY REQUEST FOR PROPOSALS WEBSITE DEVELOPMENT BID 2008-4 Part 1: Introduction, Background and General Information Otsego County has maintained a presence on the World Wide Web since early 2005.
City of Cotati Sonoma County, California
March 10, 2016 RE: REQUEST FOR PROPOSALS FOR REDESIGN, DEVELOPMENT AND HOSTING OF THE CITY OF COTATI WEBSITE Introduction The City of Cotati (City) invites proposals from consulting firms interested in
Project Management Plan for the VDI Data Center Project
Project Management Plan for the VDI Data Center Project Prepared by: Moe Yousof A paper submitted to the Project Management Training Program in partial fulfillment of the requirements for the Project Management
Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.
INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing
Village of. Website Design & Development. Request for Proposal
Village of Website Design & Development Request for Proposal Inquiries Phone calls will not be accepted. Inquiries about this Request for Proposal must be in writing and directed to: Cindy Galbreath Clerk
IT Project Governance Manual Version 1.1
IT Project Governance Manual Version 1.1 A Mandatory Reference for ADS Chapter 577 New Reference: 04/13/2010 Responsible Office: CIO File Name: 577mak_041310 UNITED STATES AGENCY FOR IT Project Goverance
CSSE 372 Software Project Management: Software Project Scheduling