1 Wind Power Programme in India Ministry of New & Renewable Energy 1 st August 2012, New Delhi 1
2 Renewable Power Sector in INDIA Share of Installed Renewable Capacity 13% 4% 13% 70% Wind Solar Hydro Biomass Total installed Capacity: 25,410 MW 2
3 Global Scenario Wind Power Total global installed capacity: 2,37,669 MW (Dec.2011) Country Installed capacity (MW) China 62,364 USA 46,919 Germany 29,060 Spain 21,674 India 16,084 (now 17,644) France 6,800 Italy 6,737 U.K. 6,540 Rest of the World Source: GWEC Data 3
4 Wind Power - Progress Potential (at 50 m) : 49,130 MW Achievement so far : 17,644 MW Achievement in 10 th Plan : 5427 MW 11 th Plan Target : 9,000 MW Achievement during 11 th Plan : 10,250 MW Achievement during : 3,196 MW Target for 12 th Plan : 15,000 MW Target for : 3,000 MW 4
5 Wind Power Progress (Contd.) Wind Cumulative Installed Capacity (MW) 5
6 Wind Power Progress (Contd.) State Potential (MW) Achievement (MW) Andhra Pradesh Gujarat Karnataka Madhya Pradesh Maharashtra Rajasthan Tamil Nadu Others
7 Wind Power Policies Income Tax Holiday under section 80 1A Excise Duty relief Concessional Customs Import Duty on specified parts and components IREDA provides loan for commercial wind power projects Preferential Tariff by State regulators Accelerated Depreciation (80%) in first year (withdrawn w.e.f ). Now an Accelerated Depreciation of 35% for the first year Generation Based Incentive 7
8 Generation Based Incentive To Encourage higher generation/improve CUF Transition from investment based incentive to outcome based incentive Scheme for 4,000 MW in 11 th Plan GBI- 50 paise/kwh subject to max. Rs. 62 lakh /MW Duration : > 4 years, and < 10 years Total of 1900 MW projects installed Evaluation carried out by CRISIL To increase from 50 p to 81 p To continue during 12 th Plan without any ceiling GBI proposed to be continued in 12 th Plan 8
9 Recent Developments Guidelines for installation of prototype wind turbines issued on to facilitate indigenization Condition of min. 200 W/m2 of wind power density withdrawn in September, 2011 Benefit of AD withdrawn w.e.f. 1 st April, 2012 Import of parts/sub-parts of rotor blades now covered under Concessional Customs Duty Benefit (Notification No. 12/2012- Customs, , of Min. of Finance, for ). Proposal to continue GBI 9
10 Renewable Regulatory Fund (RRF) Mechanism As per Grid Code, complementary commercial mechanism was to be implemented from On request of IWTMA, implementation of RRF Mechanism postponed to CERC directed MNRE to convene a meeting among stakeholders to resolve RRF related issues Task Force constituted to resolve the RRF issues formed under the chairmanship of Shri S.K. Soonee, CEO, POSOCO After several rounds of discussions among the stakeholders and experts, Task Force submitted its report recently which is under consideration 10
11 Wind Resource Assessment Issues Wind Resource Re-assessment at 100 m height Wind resource re-assessment at 100 m height to be done at 75 sites across seven states. State No. of sites NOCs awaited Andhra Pradesh 10 - Karnataka 13 1 Rajasthan Tamil Nadu 12 6 Maharashtra 8 - Gujarat Madhya Pradesh 8 - States requested to send remaining NOCs 11
12 General Wind Resource Assessment Programme of C-WET WRA for 54 sites sanctioned in stations already commissioned (AP all 15; Karnataka-10; Kerala-2) No response from Tamilnadu(3), Puducherry(2), Rajasthan(2) States are requested to commission the remaining sites 10 sites finalised under WRA Programme for NE States. NOCs for all 10 sites received. Year Odisha - 7 sites finalised, masts being set-up 12
13 Offshore Wind Power in India India has a coast line of about 7600 km. Preliminary assessment at 54 locations on the coast in the states of Tamil Nadu, Gujarat, Odisha, Maharashtra, Andhra Pradesh, Karnataka, Kerala, West Bengal, Puducherry and Goa. 13
14 Offshore Wind Power in India A Steering Committee formed by the Ministry A subcommittee of the Steering committee assigned the task of preparing draft policy for offshore wind power development. Preliminary assessment done by Scottish Agency shows a potential of around 1000 (Rameshwaram) and another 1000 MW (Kaniyakumari). This needs validation. 14
15 Re-powering of Old Sites About 4000 MW with unit size below 500 kw For better potential harnessing replace old and smaller generators by larger capacity & new generation wind turbines. Issues - Land ownership, land costing and decommissioning cost States reluctant to go for new PPA Realistic assessment of re-powering potential Creation of an appropriate policy framework for re-powering including- Revision of PPA for repowered projects, transmission of power to other states 15
16 C-WET S ROLE Established at Chennai as an autonomous institution of MNRE Objectives and Functions: Technical focal point for wind power development Wind Resource Assessment Standardization and certification Testing facilities as per international standards Type approval for wind turbines Information, Training & Commercial Services Research and Development 16
17 Organization of C-WET Divisions in C-WET: The Centre for Wind Energy Technology is working with the following structure Research & Development unit Wind Resource Assessment Unit Wind Turbine Testing Unit Standards and Certification Unit Information, Training & Commercial Service Unit Solar Radiation Resource Assessment 17
18 Issues in Wind Power Development Forest land clearance, mainly in Karnataka Creation of infrastructure for power evacuation and transmission facilities Availability of land Potential land mostly acquired by manufacturers/ developers States to revise Tariff as per CERC guidelines Development of scheduling and forecasting system Industry and LDCs not yet fully prepared Withdrawal of Accelerated Depreciation Continuation of GBI Scheme 18
19 State Specific Issues ANDHRAPRADESH Target for is 500 MW. Inadequate Tariff at low PLF sites. For Captive Generation, Banking and Wheeling not permitted Entire cost of evacuation infrastructure has to be borne by the developer No time limit on private wind monitoring due to which a few developers are holding potential land for long time 150 MW installed but not commissioned (as on ) 19
20 State Specific Issues - GUJARAT Target for is 300 MW and for 12 th Plan 2100 MW Tariff control period and wind policy ending in current year Identification and purchase of land for compensatory afforestation is costly and long drawn process Direct purchase of private land is not allowed Construction of evacuation lines has to be done by developer without any assistance from GETCO/GUVNL 20
21 State Specific Issues - KARNATAKA Target for is 604 MW. Difficulty in getting forest land clearances on Western Ghats retarding the growth. Formulation of policy for private wind resource assessment in consultation with C-WET. Purchase of private land by developer not allowed Procedure for conversion to Non-Agricultural use- Alienation Procedure is time consuming Actual potential of the state not clear - required to have long-term plan for development of the sector. To take up repowering of the old sites in the state. 21
22 State Specific Issues - KERALA In potential sites, availability of land a major concern since most of them fall in tea or coffee estates. Grid network in estate areas very weak, investments required from state government to strengthen the connectivity State has to take pro-active approach to attract private investors Delays in power evacuation clearances from KSEB 22
23 State Specific Issues - MADHYA PRADESH Target for is 250 MW and for its 590 MW. Proposal for licensing of tribal land at the value of land for a fixed period. Has prepared detailed guidelines for implementation of projects giving time lines Time taken for various clearances long To carry out survey for re-powering of old sites Working on a model of repowering where the owner of the old machines may be given share as per the average generation of the old machines for the remaining period of the otherwise replaced project. 23
24 State Specific Issues - MAHARASHTRA Target for 12 th Plan is 1800 MW Only slight addition to the potential when revised from 50 m to 80 m mast height. Difficulty in getting forest clearance in the buffer area at Tiger Reserves. Different rates of Gram Panchayat Tax and Right of Way charges (for erection of poles) across the state which should be uniform. Sharing of Capital Subsidy from State Government, between MSEDCL and developer. Issue of Mining Royalty levied on Wind Power developers. 24
25 State Specific Issues - RAJASTHAN With most of the high wind potential areas utilized by developers, fresh studies are required to be carried at new sites on higher altitude Grid needs to be strengthened in Jaisalmer region to support the development of more wind power projects A few instances of delay in payments have been reported, which needs to be improved 25
26 State Specific Issues - TAMIL NADU Target for is 1000 MW and for 12 th Plan it is 5000 MW Target for Repowering is 80 MW During peak windy season, many wind power projects were disconnected from grid, which caused a lot of wastage of power A few instances of delay in payments have been reported, which needs to be addressed. TNEB has constraints in providing power evacuation facilities to the new developers 26
27 Thank You! 27
Existing Wind Power Policies and Incentives
Existing Wind Power Policies and Incentives Consultation on National Wind Energy Mission January 9, 2014 New Delhi Wind Power Progress (in MW) Potential (at 80 m) : 1,02,000 Achievement so far : 20,150
Tamil Nadu WiNd ENErgy ProfilE
Tamil Nadu WiNd ENErgy ProfilE Wind energy in Tamil Nadu has witnessed tremendous growth propelling the State to the number one position in India in terms of renewables. However the challenge that remains
Grid Connected Solar Power in India. Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India
Grid Connected Solar Power in India Tarun Kapoor Joint Secretary Ministry of New and Renewable Energy Government of India Indian Power Sector (31 March 2012) Thermal Hydro Nuclear Renewable 1,31,353 MW
TWO NEW MUST-HAVE RESEARCH REPORTS ON THE RENEWABLE ENERGY SECTOR
TWO NEW MUST-HAVE RESEARCH REPORTS ON THE RENEWABLE ENERGY SECTOR A) Renewable Energy Development in India 2009 B) Biofuels in India (For details, see overleaf) Two New Reports on Renewable Energy and
Procedure for classification of wind power projects into wind zone class
Procedure for classification of wind power projects into wind zone class a. The value of annual mean Wind Power Density (WPD) of the windy sites declared by Centre for Wind Energy Technology (C-WET) under
Environmental Sustainability Index: Tamil Nadu
Environmental Sustainability Index: Tamil Nadu Increasing importance has been given to the integration of environment and economic development in policy-planning process. However, particularly in case
INDIA S NATIONAL INITIATIVES AND EXPERIENCES RELATED TO WIND RESOURCE ASSESSMENT
INDIA S NATIONAL INITIATIVES AND EXPERIENCES RELATED TO WIND RESOURCE ASSESSMENT Dr.S.Gomathinayagam ED/CWET & K.Boopathi Scientist & Unit Chief i/c Wind Resource Assessment Unit Centre for Wind Energy
a) Whether there is a need to revisit the existing approach for debt: equity ratio or to continue with the existing composition?
Summary of the comments and suggestions received on Approach Paper on Terms and Conditions of Tariff Regulations for the tariff period 1.4.2014 to 31.3.2019 ( Ref No. 20/2013/CERC/Fin(Vol-I)/Tariff Reg/CERC
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM IN THE MATTER OF
KERALA STATE ELECTRICITY REGULATORY COMMISSION THIRUVANANTHAPURAM PRESENT: Shri. K.J.Mathew, Chairman Shri. C. Abdulla, Member Shri. M.P.Aiyappan, Member Petition No. CT/SOLAR JNNSM/KSERC/2010 August 4,
THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE
THE INDIAN MARKET FOR RENEWABLE ENERGY THE 100 GW SOLAR INITIATIVE PRESENTATION BY : MR KESHAV PRASAD MEMBER, DELEGATION OF THE CONFEDERATION OF INDIAN INDUSTRY (CII) & CHIEF OPERATING OFFICER, IL&FS ENERGY
Press Note on Poverty Estimates, 2011-12
Press Note on Poverty Estimates, 2011-12 Government of India Planning Commission July 2013 GOVERNMENT OF INDIA PRESS INFORMATION BUREAU ***** POVERTY ESTIMATES FOR 2011-12 New Delhi: 22 July, 2013 The
Analysis of state-wise RPO Regulation across India
The Renewable Purchase Obligations (RPO) has been the major driving force in India to promote the renewable energy sector. But the State Electricity Regulatory Commissions (SERCs) have defined their respective
Renewable Energy Certificate Mechanism
Opportunities in Financing Renewable Energy Projects focusing on FiT and RECs Balawant Joshi Director, [email protected], [email protected] In this presentation.. Investment Potential for Renewable
Presentation Title ( Arial, Font size 28 )
Presentation Title ( Arial, Font size 28 ) Acquisition of 1,140 MW Welspun Renewable Portfolio Date, Venue, etc..( Arial, Font size 18 ) June, 2016 Message Box ( Arial, Font size 18 Bold) Disclaimer Certain
Solar Power Plants FAQs
Solar Power Plants FAQs Solar Power industry in India is gaining more and more prominence with each passing day. The domestic/off-grid industry is picking up speed too. Owing to the queries we are receiving
Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : [email protected] [email protected]
Draft ver2 Solar Power Policy Uttar Pradesh 2012 Suggestions to be sent to : [email protected] [email protected] 1 TABLE OF CONTENTS S.No Contents Page No 1. PREAMBLE 3 2. OBJECTIVES 3 3. OPERATIVE
Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading
Renewable Purchase Obligation (RPO) / Renewable Energy Certificates (REC) Advisory and Trading Target Clients v Renewable Energy Generators in India v RPO mandated entities in India v Investors seeking
WIND POWER IN INDIA: PROS AND CONS AN OVERVIEW
Int. J. Elec&Electr.Eng&Telecoms. 2013 Sunita Singh, 2013 Review Article ISSN 2319 2518 www.ijeetc.com Vol. 2, No. 2, April 2013 2013 IJEETC. All Rights Reserved WIND POWER IN INDIA: PROS AND CONS AN OVERVIEW
DRAFT National Mission on Small Hydro
DRAFT National Mission on Small Hydro Enriching Remote Areas through Small Hydro 1. Introduction The National Mission on Small Hydro will be a joint initiative of the Government of India and State Governments
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH. Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.
PUNJAB STATE ELECTRICITY REGULATORY COMMISSION SCO 220-221, SECTOR 34-A, CHANDIGARH Petition No.26 of 2010 (Suo Motu) Date of Order: 7.7.2010 In the matter of : Determination of generic levellised generation
In Focus. India s Renewable Energy Certificate Market
2011 1 India s Renewable Energy Certificate Market In Focus India s Renewable Energy Certificate Market Carbon Credit Capital LLC 561 Broadway New York, NY 10012 Tel: 212-925-5697 (Main Office) www.carboncreditcapital.com
F. No. 66/185/2016 -WE Ministry of New & Renewable Energy
F. No. 66/185/2016 -WE Ministry of New & Renewable Energy India has set an ambitious target of reaching 175 GW of installed capacity from renewable energy sources including 100 GW from solar and 60 GW
I M P L E M E N TAT I O N O F T H E R E N E WA B L E E N E R GY C E R T I F I CAT E ( R EC) F RA M E WO R K I N I N D I A
I M P L E M E N TAT I O N O F T H E R E N E WA B L E E N E R GY C E R T I F I CAT E ( R EC) F RA M E WO R K I N I N D I A S H O R T-T E R M S O L U T I O N S ACKNOWLEDGEMENTS We acknowledge the support
Karnataka Electricity Regulatory Commission. Discussion note on
Karnataka Electricity Regulatory Commission Discussion note on Draft KERC (Forecasting, Scheduling, Deviation settlement and related matters for Wind and Solar Generation sources) Regulations, 2015. 1.0.
Analysis of Solar Energy Industry in India & Its Future Prospects
Brochure More information from http://www.researchandmarkets.com/reports/1285411/ Analysis of Solar Energy Industry in India & Its Future Prospects Description: The Indian solar energy sector has been
DRAFT KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE. No. 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015
DRAFT 31.3.2015 KERALA STATE ELECTRICITY REGULATORY COMMISSION, NOTICE 442/CT/2014/KSERC Dated, Thiruvananthapuram 31 st March, 2015 The Kerala State Electricity Regulatory Commission hereby publishes
Government of India Earth System Science Organization Ministry of Earth Sciences India Meteorological Department
Government of India Earth System Science Organization Ministry of Earth Sciences India Meteorological Department Press Release Dated: 1 October, 2015 Subject: Current status of southwest monsoon 2015 and
ESTIMATES OF MORTALITY INDICATORS
CHAPTER 4 ESTIMATES OF MORTALITY INDICATORS Mortality is one of the basic components of population change and related data is essential for demographic studies and public health administration. It is the
GOVERNMENT OF INDIA PRESS INFORMATION BUREAU *****
GOVERNMENT OF INDIA PRESS INFORMATION BUREAU ***** POVERTY ESTIMATES FOR 2004-05 New Delhi, March, 2007 The Planning Commission as the Nodal agency in the Government of India for estimation of poverty
WORKING PAPER. India: Implementing incentives focused on energy. Anuradha R.V., Sumiti Yadava (Clarus Law Associates)
WORKING PAPER N 06/12 april 2012 CliMate India: Implementing incentives focused on energy Anuradha R.V., Sumiti Yadava (Clarus Law Associates) www.iddri.org Challenges for climate policy and governance
G.O.MS.No. 8 Dated 12.02.2015 Read the following:-
GOVERNMENT OF ANDHRA PRADESH ABSTRACT ENERGY, INFRASTRUCTURE & INVESTMENT DEPARTMENT - Development of Solar Power in Andhra Pradesh Andhra Pradesh Solar Power Policy, 2015 Orders Issued. ------------------------------------------------------------------------------------------------------------
Sub: States Fiscal Consolidation (2010-2015)
O M No. F.1 (1)/2010-FRU Government of India Ministry of Finance Department of Expenditure *** North Block, New Delhi 110 001 Dated: 14 th January 2011 Sub: States Fiscal Consolidation (2010-2015) States
Strategy for Providing 24x7 Power Supply. Forum of Regulators
Strategy for Providing 24x7 Power Supply Forum of Regulators December, 2014 Strategy for Providing 24x7 Power Supply Forum of Regulators December, 2014 Table of Contents 1. INTRODUCTION...12 2 POWER
Initiatives by TEDA and
Initiatives by TEDA and Tamil Nadu Solar Policy 2012 1 POWER SECTOR AT A GLANCE (AS ON 30.09.12) INDIA TAMIL NADU Nuc2% Nuc3% RES 12% Hydro 19% RES 44% Thermal 41% Thermal 67% Hydro 12% Thermal Hydro 138806.18
Government of India Ministry of New and Renewable Energy MNRE
Government of India Ministry of New and Renewable Energy MNRE 2 Renewable Power Installed Capacity (As on 11.6% 30.09.2015) 11.9% Wind 11.1% Small Hydro Bio mass 65.4% Solar Wind Small Hydro Solar Biomass
BASEL DISCLOSURES DOCUMENT AS ON 31 st December 2014 TABLE DF-3 CAPITAL ADEQUACY
BASEL DISCLOSURES DOCUMENT AS ON 31 st December 2014 Qualitative Disclosures (a) A summary discussion of the Bank s approach to assessing the adequacy of its capital to support current and future activities.
Name of Service Provider : Tata Teleservices Limited (Broadband Service) Customer Complaints Redressal Report for the Quarter ending - March 2015
ANDHRA PRADESH Details of and of of Customer Complaints Redressal Report for the ending - March 2015 Details of [8] = of Details of during the and of of of to be [12] Details of during the [15] = Billing
Web Edition: PROVISIONAL POPULATION TOTALS. Chapter 5. Census of India 2001 Series 1, India, Paper 1 of 2001. Chapter 5
Web Edition: PROVISIONAL POPULATION TOTALS Chapter 5 Census of India 2001 Series 1, India, Paper 1 of 2001 Chapter 5 Density of Population 1 D e n s i t y o f P o p u l a t i o n One of the important indices
Success in Scaling-up Solar Energy in Rajasthan, India
Success in Scaling-up Solar Energy in Rajasthan, India Shreemat Pandey Principal Secretary to Chief Minister Rajasthan, India 1. Introduction Solar power is attractive because it is abundant and offers
Wind Energy Sector: Re-introduction of Accelerated Depreciation benefit remains a key Fver
Wind Energy Sector: Re-introduction of Accelerated Depreciation benefit remains a key positive Fver for the sector, though concerns on RPO compliance continue Summary February 2015 ICRA RESEARCH SERVICES
Can India s Future Needs of Electricity be met by Renewable Energy Sources? S P Sukhatme Professor Emeritus IIT Bombay.
Can India s Future Needs of Electricity be met by Renewable Energy Sources? S P Sukhatme Professor Emeritus IIT Bombay August 2014 Outline of Talk 1. Introduction - The Present Scenario 2. Estimating India
Rooftop Solar PV Power : Potential,Growth and Issues related to
177 th Capacity Building Program for Officers of the Regulatory Commissions IIT Kanpur Rooftop Solar PV Power : Potential,Growth and Issues related to B D Sharma Connectivity and Metering 30 th January
STATE WISE DATA As on 29.02.2016
STATE WISE DATA As on 29.02.2016 Table No. Contents 1 Sector wise targets for 11th plan 2 Yearly achievements of Growth rates-11th five year plan for major/small States and UT's. 3 Sector wise targets
Trends in Private and Public Investments in Agricultural Marketing Infrastructure in India
Agricultural Economics Research Review Vol. 21 (Conference Number) 2008 pp 371-376 Trends in Private and Public Investments in Agricultural Marketing Infrastructure in India M.S. Jairath* National Institute
Status of Renewable Energy in Liberia
Status of Renewable Energy in Liberia Augustus V. Goanue Principal Officer Prototype Rural and Renewable Energy Agency of Liberia Email: [email protected] Mobile: +231 655 9266 Presentation Outline Background
Climate Parliament Climate Change & Energy Access for the Poor March 26-28, 2010, Limbe, Cameroun
Climate Parliament Climate Change & Energy Access for the Poor March 26-28, 2010, Limbe, Cameroun SHEP Ghana s Self-help Electrification Programme By Henry Vanderpuye Energy Consultant, Ministry of Energy
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI. Petition No. SM/354/2013 (Suo-Motu)
CENTRAL ELECTRICITY REGULATORY COMMISSION NEW DELHI Petition No. SM/354/2013 (Suo-Motu) Coram: 1. Shri Gireesh B. Pradhan, Chairperson 2. Shri M. Deena Dayalan, Member 3. Shri A. K. Singhal, Member 4.
Renewable Energy Certificate Mechanism for India. ABPS Infrastructure Advisory. Background
Renewable Energy Certificate Mechanism for India Background ABPS Infrastructure Advisory India is abundantly gifted with a variety of renewable energy (RE) sources. However, not all states are endowed
Financing of Renewable Energy in India: Implications for Policy. Gireesh Shrimali Climate Policy Initiative gireesh.shrimali@cpihyd.
Financing of Renewable Energy in India: Implications for Policy Gireesh Shrimali Climate Policy Initiative [email protected] CPI analyzes the effectiveness of policies relevant to climate change
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014
Uttar Pradesh Rooftop Solar Photovoltaic Power Plant Policy, 2014 Table of Contents 1- PREAMBLE - 1 2- OBJECTIVES - 1 3- OPERATIVE PERIOD - 1 4- IMPLEMENTATION PLAN - 2 5- ELIGIBLE ENTITIES - 2 6- TARGETS
Maternal & Child Mortality and Total Fertility Rates. Sample Registration System (SRS) Office of Registrar General, India 7th July 2011
Maternal & Child Mortality and Total Fertility Rates Sample Registration System (SRS) Office of Registrar General, India 7th July 2011 Sample Registration System (SRS) An Introduction Sample Registration
Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency
RENEWABLE ENERGY INDUSTRIAL ENERGY EFFICIENCY BUILDING ENERGY EFFICIENCY Financing Energy Efficiency and Renewable Energy through the India Renewable Energy Development Agency A RANGE OF FINANCIAL SUPPORT
Case No. 100 of 2014. Smt. Chandra Iyengar, Chairperson Shri Vijay L. Sonavane, Member ORDER (SUO-MOTU)
Before the MAHARASHTRA ELECTRICITY REGULATORY COMMISSION 13 th Floor, Centre No.1, World Trade Centre, Cuffe Parade, Mumbai- 400 005 Tel: 22163964/65/69 Fax: 22163976 E-mail: [email protected] Website:
Press Note on Poverty Estimates, 2009-10
Press Note on Poverty Estimates, 2009-10 Government of India Planning Commission March 2012 GOVERNMENT OF INDIA PRESS INFORMATION BUREAU ***** POVERTY ESTIMATES FOR 2009-10 New Delhi, 19 th March, 2012
IWL: NO!: 06: 2016 08th February, 2016. The Secretary BSE Limited Phiroze Jeejeebhoy Towers Limited Dalal Street, Mumbai 400 001
IWL: NO!: 06: 2016 08th February, 2016 The Secretary BSE Limited Phiroze Jeejeebhoy Towers Limited Dalal Street, Mumbai 400 001 The Secretary National Stock Exchange Limited Exchange Plaza Bandra Kurla
TELANGANA SOLAR POWER POLICY 2015
TELANGANA SOLAR POWER POLICY 2015 1 GLOSSARY COD CII GoTS GoI MNRE MoP NCE NOC NSM PCB PPA PV R&D REC RPPO RLDC SGST SLDC SPC SPP SPV SRP Scheduled Commercial Operations Date Confederation of Indian Industry
INDIA RENEWABLE ENERGY STATUS REPORT 2014. May 14. NOVONOUS www.novonous.com
INDIA RENEWABLE ENERGY STATUS REPORT 2014 May 14 NOVONOUS www.novonous.com Table of Contents 1. Executive Summary...5 2. India s Energy Position...7 2.1 Future Energy Requirements and Supply Options...
RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR
RAJASTHAN ELECTRICITY REGULATORY COMMISSION JAIPUR NOTIFICATION 23 rd December, 2010 No.RERC/Secy/Reg. 82 : In exercise of powers conferred under sections 61, 66, 86(1)(e) and 181 of the Electricity Act,
Ministry of Power & Energy
Ministry of Power & Energy Institutional Frame work Power sector overview Renewable energy policy Major issues and barriers Institutional Framework Sustainable Energy Authority The Sri Lanka Sustainable
Renewable Energy Promotion Policies in Chinese Taipei
Renewable Energy Promotion Policies in Chinese Taipei Bureau of Energy, Ministry of Economic Affairs Chinese Taipei November 12, 2014 RE for CT - 1 Current Development of Renewables in Chinese Taipei RE
Renewable Energy Strategy for 2020 and Regulatory Framework. Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency
Renewable Energy Strategy for 2020 and Regulatory Framework Eng. Hatem Amer Egyptian Electric Regulatory and Consumer Protection Agency Objectives of the Agency Regulate, supervise, and control all matters
State Data Centre. Round Table Conference 30 th July 2009
State Data Centre Round Table Conference 30 th July 2009 State Data Centre Key-supporting element of e-government initiatives & businesses for delivering services to the citizens with greater reliability,availability
DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT NOTIFICATION
DRAFT REGULATIONS FOR ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION UNDER SECTION 86(1)(e) OF THE ACT No. Dated: -12-2011 NOTIFICATION In exercise of powers conferred under sections 61, 66, 86(1)(e)
RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS
RENEWABLE ENERGY DEVELOPMENT IN LITHUANIA ACHIEVEMENTS AND DRAWBACKS Ieva Kuodė Ministry of Energy of the Republic of Lithuania SOLINVEST 2015-06-02 RES TARGETS BY 2020 23% the share of energy from renewable
HDFC BANK CREDIT CARDS FEATURES CUM APPLICATION FORM REGULAR CARD OFFERINGS
HDFC BANK CREDIT CARDS FEATURES CUM APPLICATION FORM REGULAR CARD OFFERINGS My City Benefit Card Smart Alerts Complement your life style with My City Benefit Card : Load your card with Smart Alerts - SMS
ESTIMATION OF LIFE EXPECTANCY AT BIRTH
CHAPTER V ESTIMATION OF LIFE EXPECTANCY AT BIRTH 5.1 Introduction Life expectancy at birth (e 0 0) is one of the most preferred indicators in demographic and health analysis. Life expectancy at birth reflects
all that you want to know About Rajasthan Solar Energy
all that you want to know bout Rajasthan Solar Energy Policy, 2014 General 01 Registration Land Timelines Fee & Charges 06 08 11 13 all that you want to know bout Rajasthan Solar Energy Policy, 2014 Rajasthan
Government of India Ministry of Power ULTRA MEGA POWER PROJECTS
Government of India Ministry of Power ULTRA MEGA POWER PROJECTS 1. Background Central Government in 2005-06 has taken the initiative for facilitating the development of a few Ultra Mega Power Projects
Case Study 5 Use of Wind Turbine Technology
Case Study 5 Use of Wind Turbine Technology 1. Context Hong Kong relies on an adequate and reliable electricity supply for its economic development. Our electricity needs are met by the two electricity
( Extract from Haryana Government Gazette, dated the 6 th December,2005) HARYANA GOVERNMENT
( Extract from Haryana Government Gazette, dated the 6 th December,2005) HARYANA GOVERNMENT RENEWABLE ENERGY DEPARTMENT NOTIFICATION The 23 rd November, 2005 POLICY FOR PROMOTING GENERATION OF ELECTRICITY
INDIA. Road Accidents in India Issues & Dimensions. Ministry of Road Transport & Highways Government of India
INDIA Road Accidents in India Issues & Dimensions Ministry of Road Transport & Highways Government of India Country s Profile INDIA Home to 1.21 billion people (about 1/6th of world s population) Around
Women s Energy Justice Network: CDM Financing and Microlending for Appropriate Technology REEEP Output # N3123
Women s Energy Justice Network: CDM Financing and Microlending for Appropriate Technology REEEP Output # N3123 Center for Energy and Environmental Security University of Colorado at Boulder August 2010
FAQS FOR MEMBERS OF COMMODITY DERIVATIVES EXCHANGES
FAQS FOR MEMBERS OF COMMODITY DERIVATIVES EXCHANGES Q1. What are the registration requirements for existing members of commodity derivatives exchanges? Ans: Existing members of commodity derivatives exchanges
Overview of Sustainable Renewable Energy Potential of India
Overview of Sustainable Renewable Energy Potential of India Prepared: October 2006 Updated: January 2010 Peter Meisen President, Global Energy Network Institute (GENI) www.geni.org [email protected] (619)595-0139
EVALUATION STUDY OF INTEGRATED RURAL DEVELOPMENT PROGRAMME (IRDP)
PEO Study No. 134 EVALUATION STUDY OF INTEGRATED RURAL DEVELOPMENT PROGRAMME (IRDP) 1. The Study The integrated Rural Development Programme (IRDP) was launched in 1978-79 in order to deal with the dimensions
COMBINED SUMMARY OF STATE POLICIES FOR SOLAR POWER
COMBINED SUMMARY OF STATE POLICIES FOR SOLAR POWER Sl. Name of State/ Description Andaman and Nicobar Island 1 Order Date Policy for power Generation through New and Renewable Energy Sources in Andaman
Farmers Cultural Practices. Availability of Planting Material
Identification of Appropriate Postharvest Technologies for Improving Market Access and Incomes for Small Farmers in Sub Saharan Africa and South Asia Commodity Systems Assessment Sunil Saran Amity International