1 Wastewater Collection Practice Test #3 Page 1 of 26 1) A 54 in. storm sewer flowing half full, at a velocity of 1.35 Ft./sec., will discharge how much flow into a creek in MGD? a) MGD b) MGD c) 1.85 MGD X d) 6.92 MGD Right Area of Pipe = D 2 x.785 Ft 3 /sec. = 1.55 x MGD Calculate the Area of the Pipe; 54 in. pipe = 5 ft. D 2 5 ft. x ft. x 5 ft. x.785 = ft 2 x 1.35 f/s Multiply by the Velocity to ft 3 /sec get flow in ft 3 /sec Divide ft 3 /sec. by 1.55 to convert to MGD ft 3 /sec MGD 2 = = MGD 6.92 MGD = "D" This is the full pipe flow. This pipe is only half full. Divide the flow in half. ***** Half Full ******* 1.4 ft./sec. 2) Shoring must protude above the top of the excavation. A) 3 feet B) 24 inches Right X C) 18 inches D) 1 foot
2 Wastewater Collection Practice Test #3 Page 2 of 26 3) A degreasing agent is added to a 16.0 ft. diameter wet well that is 18.4 ft. deep. 4.5 lbs. is required for every 1 ft 2 of surface area. If the degreaser weighs 8.5 lbs. per gallon and has a concentration of 13.8 mg/l, how many lbs. Of chemical must be added to the well? a) 16,639.5 lbs. b) 0.78 lbs. c) 6,764.3 lbs. X d) lbs. Right!. area of a circle = D 2 x.785 1) Calculate the surface area of the well; area of a circle = D 2 x ft. (201.0 ft. 2 ) = 16.0 ft. x 16.0 ft. x 2 x.785 = ft 2) Multiply the required dosage by the surface area; ft. x lbs./ft. = lbs. ="D" 18.4 ft. None of the other information is needed 4) In a trench deep enough to require a ladder(s), the worker must not be required to travel more than to get to the ladder A) Three steps B) 10 feet Right X C) 25 feet D) 15 feet
3 Wastewater Collection Practice Test #3 Page 3 of 26 5) What is the detention time in hours in a tank measuring 312 ft. x 97 ft. x 86 ft., if the tank receives 945,023 GPH? a) b) Hours 2.75 Hours X c) Hours Right d) Hours 1 ft 3 = 7.48 Gallons Flow = Volume Time 86 ft. 945,023 Gal./Hr. or Inflow 97 ft. 312 ft. Convert from gallons to ft 3 ; Calculate tank Volume; 945,023 Gal./Hr. Volume = L x W x H 7.48 gal./ft. 3 = 126,340 cu.ft./hr. = 312 ft. x 97 ft. x 86 ft. 3 = 2,602,704 ft. Use flow formula to calculate hours; Volume Flow = Time 126,340 ft. 3 /hr. = Time = 2,602,704 ft. Time 2,602,704 ft. 126,340 ft. 3 /hr. = Hrs. "C" 6) Any excavation over must have a ladder for the worker to get in and out of the trench A) 25 feet long Right X B) 4 feet deep C) 8 feet deep D) 3 feet wide
4 Wastewater Collection Practice Test #3 Page 4 of 26 7) A wet well is 9 feet deep by 21 feet in diameter. When the pump is not running, the water rises 33.4 in. in 3 min. 14 sec. If the level falls 4.5 in. in 10.3 min. while the pump is running, what is the pump rate in GPM? a) 2,135 Gal./Min X b) 2,323 Gal./Min. Right 2229 Off GPM 7207 c) 2,380 Gal./Min d) 6,801 Gal./Min On GPM 971 Volume of Cylinder = D 2 x.785 x Depth Flow = Volume Time 1 ft. 3 = 7.48 Gal. 21 feet Simplify; 33.4 in. 4.5 in. = 2.8 ft. = 0.4 ft. 14 sec. 3 min, + = 3.23 min. 60 sec/min 9 feet Calculate inflow with the pump off; Pump off Volume of Cylinder = D 2 x.785 x Depth = 21 ft. x 21 ft. x.785 x 2.8 ft. Pump on = ft. 3 Convert to gallons; falls = ft. 3 x gal/ft 3 = 7, Gal. 2.8 ft. in 3.23 min. rises 0.4 ft. in 10.3 min. level falls Flow = Volume Time Flow = 7, Gal min. = 2,229 Gal./Min. (Inflow) Calculate change in volume with the pump on; Add or subtract the change in volume to the inflow Volume of Cylinder = D 2 x.785 x Depth The level falls when the pump is on. = 21 ft. x 21 ft. x.785 x 0.4 ft. This means the pump is keeping up add the = ft. 3 to the 2,229 GPM Inflow. Convert to gallons; = ft. 3 x gal/ft 3 = Gal. 2,229 GPM + 94 GPM Flow = Volume Gal. 2,323 GPM = "B" Flow = Time min. = 94 Gal./Min.
5 Wastewater Collection Practice Test #3 Page 5 of 26 8) Given the data below, what is the most likely cause of the lift station problem? DATA: Wet well inlet is normal Well drops normally when pump #1 is running Well level rises slowly when pump #2 or pump #3 is running Run amperage is the same for all three pumps One of the pump motors turn backwards when off. Level system is reading correctly. Electrical controls are all in automatic. A) Pump #1 & #2 are air-bound Right X B) Pump #1 check valve stuck open. C) Either pump #1 or #2 is wired backwards D) Check valve on pump #3 is clogged.
6 Wastewater Collection Practice Test #3 Page 6 of 26 9) Sewer A has 106,000 people at 95 GPCD. Sewer "B" has 94,875 people at 100 GPCD. Sewer C has 88,756 people at 90 GPCD. What percent of the flow is due to I&I if the total plant flow is MGD? a) 43.1% b) 64.1% c) 51.2% X d) 35.9% Right Plant Flow = 43,000,000 Gal./Day GPCD = Gallons Per Capita Per Day 106,000 People x 95 GPCD. Add up known flows; Sewer A Sewer "B" Sewer C 10,070,000 Gal./Day 9,487,500 Gal./Day + 7,988,040 Gal./Day 27,545,540 Gal./Day Subtract know flows from the plant flow to get to get I & I; 43,000,000 Gal./Day - 27,545,540 Gal./Day 15,454,460 Gal./Day Divide I & I flow by the plant flow & multiply by 100; (I & I) = 10,070,000 Gal./Day Sewer A 94,875 People x 100 GPCD. Sewer "B" = 9,487,500 Gal./Day 88,756 People x 90 GPCD. Sewer C = 7,988,040 Gal./Day I & I =? (43.00 MGD) 15,454,460 Gal./Day 43,000,000 Gal./Day x 100 = 35.9% ="D" ** Before picking your answer, look at your I & I flows, does 15,454,460 Gal./Day I & I look like it might be 35.9% of 43,000,000 Gal./Day plsnt flow? If not, you probably divided by the wrong number. 10) An engineer must approve any trench shoring design above A) 4 feet deep B) A water line C) 50 feet in length Right X D) 20 feet deep
7 Wastewater Collection Practice Test #3 Page 7 of 26 11) All simple slope excavations 20 feet or less in depth shall have a maximum allowable slope of A) 1:1 B) 4 feet C) 20 feet Right X D) 1 1/2:1 12) A certain town s household flow rate is measured at 90 GPCD. If the plant receives but 12% of that is inflow & infiltration, then what is the population of the town? MGD, X a) 334,889 People Right b) 45,667 People c) 3,699,000 People d) 256,875 People GPCD = Gallons per capita per day If you have 12% I&I, then 88% of the flow is from people (Assuming no industry) 34,250,000 Gal./Day x 88% = 30,140,000 Gal./Day (from People) If each person uses 90 Gal./Day, then 30,140, GPCD. = 334,889 People = 'A' 13) According to "Ten State Standards" When a sewer is installed parallel to a water line, it must be a minimum of away (measured from the outside diameters) A) 6 feet B) 48 inches C) 36 inches Right x D) 10 feet 14) What is the minimum distance from the edge of the spoils to the edge of the trench A) 10 feet B) 18 inches Right X C) 2 feet D) 6 feet
8 Wastewater Collection Practice Test #3 Page 8 of 26 15) What capacity blower is required to ventilate a manhole 54 in. in diameter and 49 feet deep, if 8 air change(s) are required every 60 minutes? a) 13 Ft 3 /Min. X b) 104 Ft 3 /Min. Right c) 6231 Ft 3 /Min. d) 249 Ft 3 /Min. Volume = Flow Time 4.5 ft. Convert inches to feet; 54 in. 12 in./ft. = 4.5 ft. Volume of a Cylinder = D 2 x.785 x Depth 4.5 ft. x 4.5 ft. x.785 x 49 ft. = Ft. 3 Formula; Flow = Volume Time = Ft min. = 13.0 Ft. 3 Multiply ft3/min x Number of air changes required; 13.0 Ft. 3 /Min x 8 Air Changes Req'd = 104 Ft. 3 /Min ="B" 49 feet 16) A(n) is required for any CSO outfall pipe. A) Netting facility Right X B) NPDES Permit X C) Outfall flow meter D) Monthly inspection 17) Shoring must protude above the top of the excavation. A) 3 feet B) 24 inches wrong X C) 1 foot Right X D) 18 inches
9 Wastewater Collection Practice Test #3 Page 9 of 26 18) A wastewater treatment plant receives the following: Pump Station = Sewer A = I&I = Ind. Waste = Sewer B = 6,500 GPM 70, GPCD 50,000 gal/day 92,000 gal/day If the plant receives 21.5 MGD, what percentage of the total flow is contributedby sewer B? a) 69.7% b) 30.3% c) 76.8% X d) 23.2% Right Plant Flow = GPCD = Gallons Per Capita Per Day Add up known flows; Pump Station Sewer A I&I Ind. Waste 9,360,000 Gal./Day 7,000,000 Gal./Day 50,000 Gal./Day + 92,000 Gal./Day 16,502,000 Gal./Day 6,500 GPM x 70,000 People x 21,500,000 Gal./Day 1,440 Min./Day = 9,360,000 Gal./Day Pump Station 100 GPCD. = 7,000,000 Gal./Day Sewer A Subtract know flows from the plant flow to get to get Sewer 'B'; Sewer B =? 21,500,000 Gal./Day - 16,502,000 Gal./Day 4,998,000 Gal./Day (Sewer B ) 50,000 gal/day I & I Divide I & I flow by the plant flow & multiply by 100; 92,000 gal/day Industrial Waste 4,998,000 Gal./Day x 100 = 23.2% 21,500,000 Gal./Day ="D" ** Before picking your answer, look at your I & I flows, does 4,998,000 Gal./Day I & I look like it might be 23.2% of 21,500,000 Gal./Day plsnt flow? If not, you probably divided by the wrong number. (21.50 MGD)
10 Wastewater Collection Practice Test #3 Page 10 of 26 19) Before any excavation can be done, you must notify. A) The Ohio EPA B) The Ohio Department of Transportation C) The County sewer Department Right X D) The Ohio Utilities Protection Service 20) The bottom of a water line crossing above a sewer line must be from the crown of the sewer. Right X A) 18 inches B) 10 feet C) 24 inches D) 3 feet 21) In keeping records, A) Every test result should be included in an annual report. B) Poor records are better than no records C) Records should be destroyed every two years. Right X D) Records should be kept up-to-date and maintained as long as they are useful.
11 Wastewater Collection Practice Test #3 Page 11 of 26 22) The interior of 1,750 ft. of 27 in. pipe is uniformly coated with 1.75 in. of grease. How many gallons will this pipe hold when filled with water? X a) 39,408 Gal. Right b) 9,337,556 Gal. c) 43,939 Gal. d) 7,329,982 Gal. 1 FT. 3 = 7.48 Gallons Vol. Of a Cylinder = D 2 x.785 x L 1.75 in. (0.15 ft.) in. (1.96 ft.) in. (2.3 ft.) 1.75 in. (0.15 ft.) 1,750 ft. Subtract the grease from the diameter for new diamerter; (Because the grease is on both sides, it must be subtracted twice) 2.25 ft ft ft. = 1.96 ft. Calculate the Volume of the Pipe: Vol. Of a Cylinder = D 2 x.785 x L = 1.96 ft. x 1.96 ft. x.785 x 1,750 ft. = 5, ft. 3 Convert ft 3 to Gallons; 1 FT.3 = 7.48 Gallons 5, ft. x 7.48 = 39,408 Gal. = "A"
12 Wastewater Collection Practice Test #3 Page 12 of 26 23) Colored dye is dumped into a manhole. The dye first appears 3 min., 32 sec. later in a manhole 975 feet downstream and disappears 7 min. and 55 sec. after the dye was first dumped into the manhole. What is the velocity of the flow in the sewer? time 2 Avg. Time Sec. a) 2.05 Ft./Sec. X b) 2.84 Ft./Sec. Right c) 4.60 Ft./Sec. d) 0.70 Ft./Sec. velocity = Distance Time Convert Min., Sec. To Seconds; Dye first appears: 3 min., 32 sec. = 3 min. x 60 sec./min. = 180 sec sec. 212 sec. Dye disappears: 7 min., 55 sec. = 7 min. x 60 sec./min. = 420 sec sec. 475 sec. Average thestart & finish times;; 212 sec sec. 2 = 344 sec. 975 ft. To find the average velocity, you must find when the center of the dye passed through the manhole. Average = 344 sec. Use the formula to calculate the velocity; Distance velocity = Time 975 ft. 344 sec. = 2.84 ft./sec. = "B" 24) A mechanical ventilation system for the wet well portion of a lift station which operates continuously should be able to exchange the air in the wet well times an hour Right X A) 6 B) 20 C) 30 D) 60
13 Wastewater Collection Practice Test #3 Page 13 of 26 25) A tanker truck was involved in an accident a few miles upstream from the treatment plant. Storm water inlets to the combined wastewater collection system are receiving a large quantity of an unknown chemical. What is the first action that would be taken? Right X A) Determine type of chemical from shipper B) Evacuate all homes in the vicinity of the sewer C) Immediately instruct treatment plant to start bypassing wastewater. D) Warn downstream treatment plant 26) A 480 v AC pump motor draws 27 amps, What is the horsepower output of the motor if the power factor is.77 and the pump efficiency is 81%? a) HP b) HP X c) HP Right d) HP 1 hp = 746 W atts Ampsx Volts = Watts 2) Calculate Watts; 4) Calculate BHP Ampsx Volts = Watts HP 27 a x 480 v = 12,960 W atts x.77 P.F. ="B" HP 3) Convert Watts to HP; 81% eff. 1 hp = 746 W atts P.F. =.77 BHP WHP 12,960watts 746 Watts/HP = 17.4 HP 27) What is the greatest distance at which manholes should be installed for an 8-inch sewer line? A) 100 feet. B) 200 feet. Right X C) 300 feet. D) 400 feet. 28) "Hz" stands for Right X A) Cycles per second. B) Hand control. C) Horizontal phase. D) Polyphase.
14 Wastewater Collection Practice Test #3 Page 14 of 26 29) Which of the following are reasonable or valid objectives of a cost accounting program for a wastewater utility? A) Identify methods or measures for controlling increases in operating costs. B) Provide data for budget development and preparation. C) Provide data that helps in making decisions about making repairs verses replacement of equipment. Right X D) All of the above. 30) A pump has an efficiency of 80% and a motor has a power factor of.91. If the water horsepower is 213 HP and electricity has a cost of 12.3 cents per KWH, how much will it cost to run the pump for one month, (30 days) at 11.5 hrs./day? X a) $9, /mo. Right b) $7, /mo. c) $1, /mo. d) $4, /mo. FORMULAS NEDED; 1 HP = 746 Watts or 1 HP =.746 KW 1) Convert WHP to Brake HP; 213 HP HP P.F. = 266 HP 80% = HP Eff. 213 HP 2) Convert BHP to Wire HP; BHP WHP 266 HP = HP.91 3) Convert Wire HP to KW (Kilowatts); 1 HP =.746 KW HP x.746 KW per HP = KW 3) To find the Cost, multiply KW x Hrs. x $/hr. x Days KW x 11.5 hrs./day x.123 cents/kw x 30 days/month = $ 9, per mo. = "A" 31) Ideally, the ph meter should be standardized Right X A) Before each use B) Weekly C) Monthly D) Once
15 Wastewater Collection Practice Test #3 Page 15 of 26 32) An automatic chemical feeder treats 67 MGD at a concentration of 73 mg/l. How many lbs./day of chemical is required? a) 5,453 lbs./day b) 36,585 lbs./day X c) 40,791 lbs./day Right d) 4,387 lbs./day lbs./day = MGD x mgl x ) Use formula to Calculate lbs./day; lbs./day = MGD x mgl x 8.34 = 67 MGD x 73 mg/l. x 8.34 = 40,791 lbs./day ="C" 33) Which of the following would be the safest action to take in the event of a major chlorine container leak? A) Call the fire department to hose down the container. Right X B) Notify local police or sheriff. C) Roll the container so that liquid, rather than gas escapes. D) Submerge the container in a basin or stream if feasible. 34) Emergency stoppages in pipelines may be cleared safely by use of A) Bar screens Right X B) High velocity cleaners C) TV cameras D) All of the above 35) Which of the following are appropriate uses of closed-circuit television by wastewater collection system workers? A) Chemical addition Right X B) Evaluating effectiveness of sewer cleaning & clearing techniques C) Removing sources of infiltration D) All of the above
16 Wastewater Collection Practice Test #3 Page 16 of 26 36) 35 mg/l. of chlorine is required to treat a flow of 55.3 MGD. The solution available to you, however, is only 81% of chlorine. How many lbs./day of solution are requires to treat the flow? a) 97,802 lbs./day X b) 19,928 lbs./day Right c) 16,142 lbs./day d) 1,172,681 lbs./day lbs./day = MGD x mgl x ) Use formula to Calculate lbs./day; 2) The solution is only 81% pure. You will need more; lbs./day = MGD x mgl x 8.34 How much more? = 55 MGD x 35 mg/l. x ,142 lbs./day = 16,142 lbs./day.81 (81%) = 19,928 lbs./day ="B" 37) 61 mg/l. of root control must be added to a 66 in. sewer that is 3,125 feet long. If the root control chemical is in a solution that consists of only 41% of the chemical, how many lbs. of the solution must be added to the sewer? X a) lbs. Right b) lbs. c) lbs. d) 16, lbs. lbs./day = MGD x m gl x 8.34 Volum e of a cylinder = D 2 x.785 x L 1 ft 3 = 7.48 Gallons (66 in.) 5.5 ft. 1) Calculate the Volume of Pipe, then convert to Million Gallons; Volum e of a cylinder = D 2 x.785 x L 5.5 ft. x 5.5 ft. x 3,125 ft. x.785 = 74,207 ft. 3 1 ft 3 = 7.48 Gallons 74,207 ft 3 x 7.48 gal./ft 3 = 555,069 gal. 1,000,000 =.56 MGD 3,125 ft. 2) Use formula to Calculate lbs./day; 3) The chemical is only 41% pure. You will need more; lbs./day = MGD x m gl x 8.35 lbs./day =.56 MGD x 61 mg/l. x lbs./day lbs./day = 282 lbs./day.41 = lbs./day = "A"
17 Wastewater Collection Practice Test #3 Page 17 of 26 38) Given the data below, what is the most likely cause of the problem? DATA: Wet well inlet is normal for dry weather flow Lead pump amperage is lower than normal Lead pump starts at right level, level continues to rise. Lead pump check valve arm remains stationary in lowered position when pump starts Lag pump check valve arm rises when lag pump starts & lowers when it stops. Force main pressure remains the same when lead pump runs, but increases when lag pump runs. Level drops when lag pump runs. Rattling noise coming from lead pump Low-level pressure switch normal High-level pressure switch normal Electrical controls are all in automatic. A) Lag pump clogged B) Force main pressure too high C) Lag pump is air-bound Right X D) Lead pump air-bound 39) 73 mg/l. of chemical was previously used to treat a flow of 85,500,500 gal./day. The chemical cost is $3.31 /lb. A chlorine residual test determined that 54 mg/l. of chemical would be satisfactory. How much money would be saved per month by using the 54 mg/l. dose instead of the 73 mg/l. dose? (1 mo. = 30 days) a) $1,206, /mo. X b) $1,345, /mo. Right c) $5,169, /mo. d) $3,823, /mo. lbs./day = MGD x mgl x ,500,500 gal./day. 1,000,000 = MGD 1) Subtract the amount of chemical you are using from what you were previously using, to get the amount of chemical you are saving; 73 mg/l mg/l. = 19 mg/l. (not used) 2) Use the chemical formula to determine how much the chemical "not used" would have costed; lbs./day = MGD x mgl x 8.34 lbs./day = MGD x 19 mg/l. x 8.34 lbs./day = 13,548.4 lbs./day 13,548.4 lbs./day x 30 days x $3.31 /lb. = Mo. $ 1,345, per month ="B"
18 Wastewater Collection Practice Test #3 Page 18 of 26 40) Important considerations when reviewing the plans for a lift station include: Right X A) Access B) Industrial development potential C) Trench soil conditions and availability of suitable materials D) All of the above 41) If the grade of a sanitary sewer has a slope of 0.80% for 445 feet, what is the rise of the pipe? a) Feet X b) 3.56 Feet Right c) 0.04 Feet d) 0.36 Feet RISE SLOPE = RUN Slope = (Slope =.008 = 0.80% or.01) RISE 445 ft..008 x 445 ft. = RISE.008 x 445 ft. = 3.56 ft. = "B" 42) What prevents any solution or water from backing up into the chlorine line? A) Release valve Right X B) Check valve C) Auxiliary valve D) Blow-off valve
19 Wastewater Collection Practice Test #3 Page 19 of 26 43) A(n) 11 ft. wide x 2,150 ft. long trench must be excavated and the spoils removed from the premises. The spoil weighs 2,344 lbs./cu. yd. and each truck can carry 13 tons. How many truck loads are required if the trench is 14.0 feet deep? a) 2,211 Trucks X b) 1,106 Trucks Right c) 3,316 Trucks d) 1,105 Trucks Volume of a rectangle = L x W x H 1 ton = 2,000 lbs. 1 yd. 3 = 27 ft. 3 1) Calculate the volume of the trench in (Yd 3 ); Volume of a rectangle = L x W x H Volume of a rectangle = ft. 11 ft. x ft. x 2,150 ft. 11 ft. = 331,100 ft. 3 Convert to yd 3 331,100 ft. 3 = 27 ft 3 /yd 3 12,263 cu. yd. 3) Calculate the wieght of fill in tons; 2,344 lbs./cu. yd x 12,263 cu. yds. = 28,744,385 lbs. 2,000 lbs./ton = 14,372.2 tons 2,150 ft. 4) Calculate the number of trucks; 14,372.2 tons = 1,105.6 Trucks 13 tons/truck 1,106 Trucks = 'C' You must round up to 1,106 Trucks or there will be.6 truckoads left over. 1,105
20 Wastewater Collection Practice Test #3 Page 20 of 26 44) Estimate the total cost and cost per linear foot of a sewer construction project. The project consists of installin 7 manholes and 3,275 feet of 36 inch sewer Costs are estimated as shown below: TOTAL JOB COST: a) b) c) $ $ $ 1,408, ,334, ,681, X d) $ 2,709, Right COST PER LINEAR FOOT: a) $407 b) $819 X c) $827 Right d) $430 EXCAVATION AND BACKFILL $ per foot COST OF PIPE $ per foot MANHOLE + INSTALLATION $ 4, each TOTAL JOB COST; 1) Excavation and backfill of trench. 4) Total cost per ft. x 3,275 ft. = $ 1,375, $ 1,375, (Excavation) 2) Cost of pipe. $ 1,300, (pipe) per ft. x 3,275 ft. = $ 1,300, $ 33, (Backfill) 3) Cost of manholes. $ 2,709, = "D" 7 manholes x 4,725 ea. = $ 33, COST PER LINEAR FOOT; 1) Divide the total job cost by linear feet of pipe. $ 2,709, ,275 ft. = $ per ft. = 'C'
21 Wastewater Collection Practice Test #3 Page 21 of 26 45) The average cost for contractors to clean the city sewers is $ 5.30 per foot for 2.20 miles of 12 in. pipe, $ 6.25 per foot for 2.25 miles of 15 in. pipe, and $ 7.89 per foot for 1.75 miles of 18 in. pipe, The city is considering purchasing a new jet & vac truck for $ 312,750 and hiring a 3 man crew to operate it. Operator A makes $18.43 per hour, operator B makes $19.67 per hour, operator C makes $ per hour. Health care & benefits cost 37% of wages. The cost/year of the jet truck will be $ 39, for 10 years. The time for the crew to clean 100 feet of sewer is as follows: 12 sewer takes 15 sewer takes 18 sewer takes 1.80 hours hours hours..50 hours. of non-productive time (travel, cleanup, etc.) will be used for every hour spent cleaning sewers Which is the least expensive option (contractor or in-house) and by how much over the 10 year period? X a) Cheaper to buy a jet-vac, cost savings will be $541, Right b) Cheaper to contract out, cost savings will be $435, c) Cheaper to buy a jet-vac, cost savings will be $54, d) Cheaper to contract out, cost savings will be $53, SEE NEXT PAGE FOR SOLUTION
22 Wastewater Collection Practice Test #3 Page 22 of 26 Convert miles of sewer to feet. size miles feet/mile feet 12 in. = 2.20 miles x 5,280 ft./mile = 11,616 ft. 15 in. = 2.25 miles x 5,280 ft./mile = 11,880 ft. 18 in. = 1.75 miles x 5,280 ft./mile = 9,240 ft. CONTRACTOR COST/YEAR: Convert feet of sewer cost. feet x cost/ft. = total 11,616 ft. x $ 5.30 = $ 61, (12 in.) 11,880 ft. x $ 6.25 = $ 74, (15 in.) 9,240 ft. x $ 7.89 = $ 72, (18 in.) $ 208, = TOTAL CONTRACTOR COST/YEAR IN HOUSE COST/YEAR 1) Calculate labor cost/hr. Add wages of A,B & C operators. $18.43 (Operator A) $19.67 (Operator B) + $20.49 (Operator C) $58.59 (Total hourly rate) travel & fringe Total labor hourly rate clean up benefits Cost/hr. $58.59 x 1.50 hrs. x 1.37 = $ ) Set up grid to calculate in-house costs. hrs. per travel time Size ft. of pipe 100' sections x 100 ft. x hourly rate pipe size 12 in. = 11, ft. sections x 1.80 x $ = 25, in. = 11, ft. sections x 3.00 x $ = 42, in. = 9, ft. sections x 4.25 x $ = 47, COMPARE COST/YEAR $208, $154, $54, CONTRACTOR COST/YEAR IN HOUSE COST/YEAR Cheaper to do the work in-house 10 year cost difference $ 54, x 10 = In-house labor cost = 115, Jet-vac cost/year = 39, Total cost/year = 154, $541, = "A"
23 Wastewater Collection Practice Test #3 Page 23 of 26 46) 32 mg/l. of chlorine is required to treat a flow of 4.44 MGD. The solution available to you, however, is only 66% of chlorine. If the S.G. of the chemical is 0.94, How many lbs./day of solution are requires to treat the flow? a) 74,619 lbs./day b) 6,223 lbs./day c) 1,115 lbs./day X d) 1,689 lbs./day Right Multiply 8.34 x S.G. & use it instead of 8.34 lbs/gal lbs/gal. x 0.94 = 7.84 lbs/gal. Enter the data into the formula: lbs./day = MGD x mg/l x 7.84 lbs/gal. = = 4.44 MGD 1, lbs/day x 32 mg/l. x 7.84 lbs/gal. The solution is only 66% You will need more, divide lbs/percent = 1, lbs/day 66% = 1, lbs/day = "D"
24 Wastewater Collection Practice Test #3 Page 24 of 26 47) Prepare a cut sheet for a sewer laid on a.66 % grade with the given stake elevations and invert grade. Consider a pipe thickness of 2.3 in. and assume the pipe will be installed on 1.0 ft. of bedding. 0 = 50 = 100 = 150 = 198 = Station Stake Elev. Invert Grade Cut For Each row Calculate the RUN: = 9.47 Run = 2nd station - 1st station = 9.77 Run = = = 9.66 For Each row Calculate RISE: = 9.75 Slope = Rise = = Rise = Run 50 Rise = Add the rise to the previous Invert Grade = For cut, subtract Stake Elev. - Invert grade Then Add the pipe bedding and thickness = ft. (2.3 in./ 12") ft. Beding ft Repeat steps for the other Rows
25 Wastewater Collection Practice Test #3 Page 25 of 26 48) A trench is dug at 8.5 ft. wide x 10.8 ft. deep x 2,235 ft. long. A 27 in. Sewer is going to be installed in this trench. 18 in. must be left out of the top for concrete. How many trucks would be needed if the material weighed 3,146 lbs. per yd 3 and each truck carries 14.5 tons? X a) 675 Trucks Right ### b) 18,203 Trucks 789 c) 789 Trucks 674 d) 674 Trucks ### Volume of Trench (ft 3 ); 18 in. = 1.50 ft. L x W x H 9.30 ft. x 8.5 ft. x 2,235 ft. = 176,677 Ft ft ft. Volume of pipe (ft 3 ): = 9.30 ft. D 2 x.785 x Length 2.25 ft. x 2.25 ft. x x.785 x 2,235 ft. 8.5 ft. = 8,882 Ft. 3 2,235 ft. 27 inch pipe = 2.25 ft. Calculate Backfill Volume (ft 3 ): 176,677 Ft ,795 Ft. 3-8,882 Ft ft 3 /yd 3 = yd 3 167,795 Ft. 3 Calculate Backfill Weight (Tons): yd 3 x 3,146 lbs. per cu. Yd. = 19,551,192 2,000 lbs/yd 3 = 9,775.6 Tons Calculate Trucks: tons 14.5 tons/truck = Trucks (A) (Round up one truck to carry away the extra.2 tons)
26 Wastewater Collection Practice Test #3 Page 26 of 26 49) Which of the following are accepted means for applying herbicides to control roots in wastewater collection A) Aeration Right X B) Foaming C) Stem injection D) All of the above. 50) A(n) 54 in. sewer has a flow of MGD at a velocity of 2.62 ft./sec. The sewer size changes to a(n) 48 in. sewer with the same slope and flow. Assuming no friction loss, what is the new velocity? (Both sewers are flowing full.) a) X b) c) d) 5.08 ft./sec ft./sec. Right! ft./sec ft./sec. ft 3 /sec. = ft 2 x ft./sec. ft 3 /sec. = MGD x in. 48 in. Flow 1) Convert MGD to ft. 3 /sec.; ft 3 /sec. = MGD x ) Calculate the area of the new pipe size: ft 3 /sec. = ft 3 /sec 48 in. = 4.0 ft. Area = D 2 x ft. = 4.0 ft. x 4.0 ft. x.785 = 3) Calculate the new velocity; ft.³/sec ft.² = 5.40 ft./sec. = "B" ft.²
Wastewater Collection Practice Test #3 Page 1 of 15
Wastewater Collection Practice Test #3 Page 1 of 15 1) A 54 in. storm sewer flowing half full, at a velocity of 1.35 Ft./sec., will discharge how much flow into a creek in MGD? 13.85 MGD 10.73 MGD 1.85
MATHEMATICS FOR WATER OPERATORS
MATHEMATICS FOR WATER OPERATORS Chapter 16: Mathematics The understanding of the mathematics of water hydraulics (flows, pressures, volumes, horsepower, velocities) and water treatment (detention time,
ABC & C 2 EP Formula/Conversion Table for Water Treatment, Distribution, & Laboratory Exams
ABC & C EP Formula/Conversion Table for Water Treatment, Distribution, & Laboratory Exams Alkalinity, as mg CaCO 3 /L = (Titrant, ml) (Acid Normality)(50,000) Sample, ml Volts Amps = Ohms * of Circle =
Practice Tests Answer Keys
Practice Tests Answer Keys COURSE OUTLINE: Module # Name Practice Test included Module 1: Basic Math Refresher Module 2: Fractions, Decimals and Percents Module 3: Measurement Conversions Module 4: Linear,
Module 9: Basics of Pumps and Hydraulics Instructor Guide
Module 9: Basics of Pumps and Hydraulics Instructor Guide Activities for Unit 1 Basic Hydraulics Activity 1.1: Convert 45 psi to feet of head. 45 psis x 1 ft. = 103.8 ft 0.433 psi Activity 1.2: Determine
BASIC MATH FORMULAS - CLASS I. A. Rectangle [clarifiers, ponds] I = length; w = width; A = area; area in square ft [sq ft]
WASTEWATER MATH CONVERSION FACTORS 1. 1 acre =43,560 sq ft 2. 1 acre =2.47 hectares 3. 1 cu ft [of water] = 7.48 gallons 4. 1 cu ft [of water] = 62.4 Ibs/ft 3 5. Diameter =radius plus radius, D =r + r
Math. The top number (numerator) represents how many parts you have and the bottom number (denominator) represents the number in the whole.
Math This chapter is intended to be an aid to the operator in solving everyday operating problems in the operation of a water system. It deals with basic math that would be required for an operator to
Sanitary Sewer Overflow (SSO) Incident Report Form
Submit completed form to EHS. Date of SSO spill: Sanitary Sewer Overflow (SSO) Incident Report Form Identify the SSO category (check one): Category 1 SSO Spills of any volume that reach surface water Category
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING
ATTACHMENT 3: SPECIFICATION FOR SEWER CLEANING 1.0 General 1.1 The work covered by this section consists of providing all labor, equipment, material and supplies, insurance, accessories, tools, transportation,
CLEANING, INSPECTION, AND TESTING OF SEWERS
CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and
Illinois Environmental Protection Agency Division of Water Pollution Control Class K Study Guide Industrial Wastewater Operator Certification
Illinois Environmental Protection Agency Division of Water Pollution Control Class K Study Guide Industrial Wastewater Operator Certification Revised March 2003 The purpose of this study guide is to help
Work Practice: Wastewater Collection System Maintenance Plan Potential Safety Hazards
Potential Safety Hazards Required items Potential PPE None Additional References - Collection System Related Work Practices & Forms Jet Truck Cleaning Work Practice (Do not drive on peoples driveway) CDL
SANITARY SEWER SPECIFICATIONS
SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,
SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE
SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final
Repair and Disinfection of Water Mains Water Protection Program fact sheet
Repair and Disinfection of Water Mains Water Protection Program fact sheet 9/2012 Every year waterborne disease outbreaks occur in the United States as a result of public water distribution system defi
SECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
ABC & C 2 EP Formula/Conversion Table for Wastewater Treatment, Industrial, Collection, & Laboratory Exams
ABC & C EP Formula/Conversion Table for Wastewater Treatment, Industrial, Collection, & Laboratory Exams Alkalinity, as mg CaCO /L (Titrant, ml) (Acid Normality)(50,000) Sample, ml Volts Amps Ohms * of
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
32-02.05 Precast Manhole Sections and Castings. These items shall conform to Section 31, "Storm Drain Installation," of these Standard Provisions.
SECTION 32: SANITARY SEWER INSTALLATION 32-01 SCOPE. The Work shall consist of furnishing and installing sewer mains, manholes, laterals, cleanout fittings and appurtenances; and testing, flushing and
( ) ABC Formula/Conversion Table for Wastewater Treatment, Industrial, Collection and Laboratory Exams. Alkalinity, as mg CaCO 3 /L =
ABC Formula/Conversion Table for Wastewater Treatment, Industrial, Collection and Laboratory Exams Alkalinity, as mg CaCO 3 /L = (Titrant Volume, ml) (Acid Normality)(50,000) Volts Amps = Ohms Area of
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET
PART 6 - STANDARD DESIGN AND CALCULATION FORMS 6.1 SANITARY SEWER DATA SHEET Name of Municipality or Sewer District Name of Project Original Township and Lot Number Name of Engineer of Firm Preparing Plans
SECTION 3 - SUMMARY OF KEY WATER PLANT OPERATOR MATH FORMULAS
MATH FORMULAS Most mathematics problems found on Grade I - IV level examinations are process control problems that are responsive to a host of math formulas that have been developed over a period of time
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe
Before H 2 Town of South Windsor, CT Evaluates Large Diameter Concrete Pipe September 11, 2012 NEWEA Collection Systems Conference Presented by: Laurie L. Perkins, PE Dennis A. Dievert, PE C. Frederick
CHAPTER 3 STORM DRAINAGE SYSTEMS
CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
SANITARY SEWER SYSTEM ASSESSMENT
SANITARY SEWER SYSTEM ASSESSMENT What is this tool? The Sanitary Sewer System Assessment is a form that helps your utility identify and document all of the components in your utility s sanitary sewer system.
Collection Systems Technology Fact Sheet Sewers, Conventional Gravity
United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment
Waste Collection Systems
Waste Collection Systems System Maintenance and Repair Maintenance and Repair Training Objectives To gain an understanding of: System Maintenance and Repair vocabulary System Maintenance and Repair techniques
Chapter 9 Sanitary Sewers
Chapter 9 Sanitary Sewers S:/Engineering/Design Standards/Chapter 9 12/29/2014 Section 9.1 Topic General Requirements Chapter 9 Sanitary Sewers Page 9-1 9.2 Plan Submittals 9-1 9.3 Determination of Flow
FREQUENTLY ASKED QUESTIONS
FREQUENTLY ASKED QUESTIONS VILLAGE OF CORRALES WASTEWATER UTILITY (SEWER) SYSTEM AND INDIVIDUAL PROPERTY OWNER SERVICE CONNECTIONS I. AVAILABILITY OF SEWER SERVICE; WHEN CONNECTION IS REQUIRED. Q. Where
San Antonio Water System Standard Specifications for Construction ITEM 866 SEWER MAIN TELEVISION INSPECTION
ITEM 866 SEWER MAIN TELEVISION INSPECTION 866.1 DESCRIPTION: The Contractor shall furnish all labor, materials, equipment, and incidentals to provide the televising and a NASSCO-(PACP) standard video,
Storm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
Beacon Hill Sewer District Standard Specifications
Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions
SECTION 810 SEWER LINE CLEANING
SECTION 810 SEWER LINE CLEANING I. GENERAL 1.1 DESCRIPTION OF WORK The work covered by this section consists of providing all labor, equipment, material and supplies and performing all operations required
Texas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems
Texas Commission on Environmental Quality Page 1 217.31. Applicability. SUBCHAPTER B: TREATMENT FACILITY DESIGN REQUIREMENTS 217.31-217.39 Effective August 28, 2008 This subchapter details the design values
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
Chemigation Calibration for Center Pivot Irrigation Systems
April 1993 (reformatted May 2000) Chemigation Calibration for Center Pivot Irrigation Systems A Workbook for Certified Pesticide Applicators To accompany the VHS tape Chemigation Calibration Based on materials
Formula/Conversion Table for Water Treatment and Water Distribution
Formula/Conversion Table for Water Treatment and Water Distribution Measurement Conversion Measurement Conversion Measurement Conversion Measurement Conversion 1 ft. = 12 in. 1 MGD = 1.55 cfs 1 grain /
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST
DIVISION OF WATER QUALITY CONSTRUCTION GRANTS & LOANS SECTION FAST TRACK AUDIT CHECKLIST CERTIFICATION 1. Did the engineer submit a certificate of completion utilizing the appropriate page of the issued
SEWER CLEANING, INSPECTION AND ASSESSMENT
3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity
CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General
General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
Centrifugal Fans and Pumps are sized to meet the maximum
Fans and Pumps are sized to meet the maximum flow rate required by the system. System conditions frequently require reducing the flow rate. Throttling and bypass devices dampers and valves are installed
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM
CITY OF SALEM DEPARTMENT OF PUBLIC WORKS ADMINISTRATIVE RULES CHAPTER 109 DIVISION 003 SANITARY SEWER COLLECTION SYSTEM SECTION 3.1 INTRODUCTION... 1 (a) Objectives...1 (b) Applicability...1 (c) Drafting
CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN
CITY OF WASHINGTON SPILL PREVENTION, CONTROL AND COUNTERMEASURE PLAN Adopted October 5, 2009 Table of Contents Chapter Description Page 1 Facility Descriptions... 3 1.1 Municipal Power Plant, 1001 Park
VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES
VILLAGE OF GRANVILLE SEWER BACK-UP and WATER LEAK POLICIES SEWER BACK-UP POLICY General Sewer back-ups are an unfortunate, but common problem in older communities. A sewer back-up can create a health or
ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.
ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
Kansas City s Overflow Control Program
Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
Design of Sewage Pumping Stations by John Zoeller, PE, CEO/President
Design of Sewage Pumping Stations by John Zoeller, PE, CEO/President This article provides guidelines for designing municipal pumping systems. There are three types of sewage handling systems: 1. Municipal
Routine Maintenance and Inspection
THE CORPORATION OF THE VILLAGE OF WARFIELD POLICY TITLE: Sanitary Sewer Operations POLICY: #5435 PURPOSE: This policy is to provide the Village of Warfield s procedures for maintaining its sanitary sewer
CHAPTER 2 HYDRAULICS OF SEWERS
CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS
2.0 DESIGN CRITERIA FOR WATER DISTRIBUTION SYSTEMS Water system improvements proposed for inclusion into Western s service area shall be designed in accordance with all appropriate AWWA standards, include
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES
AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing
Improper storage of potential pollutants will increase the risk of water pollution that may occur because of spills.
WQ-3 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design and Operation Standards Section 1. Introduction According to the EPA, the majority of water pollution
The checklist utilized by the Authority will be similar to that which is shown below. Project Name: Location: Consulting Engineering Firm:
Page 1 of 6 Section 1. PURPOSE This policy is an Engineering checklist of the Local Review Program for sanitary sewer improvement projects by the Bedford Regional Water Authority ( Authority ). Section
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1
Glen Hills Area: Septic System and Public Sewer Q & A Information Sheet Page 1 The Montgomery County Dept. of Environmental Protection, in cooperation with the Dept. of Permitting Services and the Washington
Example Calculations Evaluation for Fine Bubble Aeration System. Red Valve Company, Inc. 700 NORTH BELL AVENUE CARNEGIE, PA 15106-0548
Revision Date 6/10/02 9:52 Red Valve Company, Inc. 700 NORTH BELL AVENUE CARNEGIE, PA 15106-0548 PHONE (412) 279-0044 FAX (412) 279-5410 Red Valve Representative Sample Air Diffuser Calcs.xls Input Data
Open Channel Diffusers
Open Channel Diffusers Application Information: Open channel diffusers are used to increase mixing and absorbance efficiency of a chemical solution into the process water. Specifically designed penetrations
SANITARY SEWER BACKUP. Causes & Prevention
SANITARY SEWER BACKUP Causes & Prevention A. PURPOSE The purpose of this publication is twofold: 1. It provides homeowners with basic information on the causes of sanitary sewer backups. 2. It provides
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
Elev. A = 200.05, Elev. B = 325.25, horizontal distance = 1625 feet a. 7.7 b..077 c. 12.98 d. 1.28
1. If the percent grade is 7.25 % and the horizontal length of grade is 1625 feet, what is the change in elevation? a. 117.81 feet b. 1178.13 feet c. 11.78 feet d. 1.17 feet 2. In surveying, the distance
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
ETL listed for installations within 5 ft. (1.5M) of outer edge of water www.srsmith.com 79-15152-00 Rev E2 9.14 Page 1 of 10
Color Light Streams Large Laminar Installation Manual (CLSLL) Input Power: Total Power: 12V AC 5W 4008814 ETL listed for installations within 5 ft. (1.5M) of outer edge of water 79-15152-00 Rev E2 9.14
ONSITE WASTEWATER TREATMENT SYSTEM Property Transfer Certification Instructions and Inspection Report
ONSITE WASTEWATER TREATMENT SYSTEM Property Transfer Certification Instructions and Inspection Report These instructions are for homeowners and inspectors completing the onsite wastewater treatment system
3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
CHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL. 1.01 Testing - General
SECTION IV - TESTS AND INSPECTIONS PART 1 - GENERAL 1.01 Testing - General Testing shall be of the type and frequency described in each section and summarized in Item 1 of this section. In addition to
CENTRIFUGAL PUMP OVERVIEW Presented by Matt Prosoli Of Pumps Plus Inc.
CENTRIFUGAL PUMP OVERVIEW Presented by Matt Prosoli Of Pumps Plus Inc. 1 Centrifugal Pump- Definition Centrifugal Pump can be defined as a mechanical device used to transfer liquid of various types. As
CHAPTER 17: STORM SEWER STANDARDS. 17.00 Introduction. 17.01 Administration. 17.02 Standards 17.1
CHAPTER 17: STORM SEWER STANDARDS 17.00 Introduction 17.01 Administration 17.02 Standards 17.1 17.00 INTRODUCTION The purpose of this chapter is to provide guidance for the design and construction of storm
SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING
812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,
Most agencies think about cleaning because of debris in the line.
Most agencies think about cleaning because of debris in the line. If we have an effective cleaning program there should not be a lot of debris in the line after the line is cleaned and tv d for acceptance.
Energy and Cost Required to Lift or Pressurize Water
University of California Tulare County Cooperative Extension Energy and Cost Required to Lift or Pressurize Water Bill Peacock, Tulare County Farm Advisor Pub. IG6-96 Power Requirements to Lift Water It
DRAFT Public Outreach Document for What s an SSMP?
DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
CITY OF FARMERSVILLE, TEXAS
CITY OF FARMERSVILLE, TEXAS MANUAL FOR THE DESIGN OF WATER AND SANITARY SEWER LINES Subdivision Ordinance #2007-08 Exhibit B February 13, 2007 TABLE OF CONTENTS Description Page No. General... 1 Water
Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41
Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41 ITEM #6 1) Scope of Work The scope of this proposal is: Hudson Street Well #1A and Hudson Street Well #2 - clean and rehabilitate,
How To Calculate An Average Daily Flow
DESIGN GUIDELINES FOR WASTEWATER FACILITIES MARYLAND DEPARTMENT OF THE ENVIRONMENT ENGINEERING AND CAPITAL PROJECTS PROGRAM 2013 Purpose: Recommended Standards for Wastewater Facilities (as revised) for
March 2006 DIVISION 3 - CW 2140-R3 TABLE OF CONTENTS
March 2006 CW 2140 - SEWER AND MANHOLE CLEANING TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Constructions... 1 3. CONSTRUCTION METHODS... 1 3.1 High
LS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
Guidelines for Precast Concrete Grease Interceptors
Guidelines for Precast Concrete Grease Interceptors Purpose Provide an overview of the basic design principals that govern why gravity grease interceptors work Provide a forum for discussion of common
SECTION 7- STORM SEWER
SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)
SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer
COMPRESSED AIR ULTRASONIC LEAK DETECTION GUIDE
COMPRESSED AIR ULTRASONIC LEAK DETECTION GUIDE COMPRESSOR ROOM INTAKE FILTER AIR COMPRESSOR AFTERCOOLER MOISTURE SEPARATOR RECEIVER MAIN FILTER SECONDARY FILTERS AND LUBRICATORS V 1406R Increased Productivity
Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
Septic System Design Manual
Septic System Design Manual Prince George s County Health Department Largo Government Center 9201 Basil Court, Suite 318 Largo, Maryland 20774 (Office) 301-883-7681 (Fax) 301-883-7266 (January 2007) Table
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in
Minimum Design Criteria for the permitting of Gravity Sewers
Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document
812-3 LIMITATIONS: b. No fire hydrant shall be obstructed or used when there is a fire in the area.
812-1 SCOPE OF WORK: SECTION 812 SEWER LINE, MANHOLE AND WET WELL CLEANING a. The Contractor shall provide all labor, materials, equipment, and incidentals necessary to perform the cleaning of sewer lines,
SECTION 5 DRAFTING STANDARDS
SECTION 5 DRAFTING STANDARDS 1 SECTION FIVE TABLE OF CONTENTS Description Page TABLE OF CONTENTS... 5-2 GENERAL... 5-3 DRAFTING STANDARDS... 5-5 DRAFTING MINIMUM REQUIREMENTS HANDOUT... 5-8 2 GENERAL 1.
MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS
MODEL WEB CONTENT FOR CITY SANITARY SEWER DEPARTMENTS The following information is designed to be used in conjunction with the Sewer Toolkit, located in the Wastewater section of the Florida Rural Water
Exhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
ADVANCED MATH HANDBOOK. For Class III & IV Water Operators
ADVANCED MATH HANDBOOK For Class III & IV Water Operators 2009 ADVANCED MATH HANDBOOK Overview This handbook is designed for operators taking the Class III or Class IV water operator certification exam.