Region of Durham Basement Flooding Prevention Study. Public Information Centre #2

Size: px
Start display at page:

Download "Region of Durham Basement Flooding Prevention Study. Public Information Centre #2"

Transcription

1 Region of Durham Basement Flooding Prevention Study Public Information Centre #2 October 27, 2009

2 Welcome Today is an opportunity for you to hear about and offer input on the Annes Street Basement Flooding Prevention Study that was initiated by the Region of Durham in the spring The study team is now at the point where input from stakeholders has been received about the existing issues, and computer modeling and analysis have been completed. Tonight, you will hear about the package of solutions that are being considered. Please let us know what you think. This Public Open House Booklet will help you to navigate the evening s activities. Project Team Contacts Alfred Ho, P. Eng, Project Manager The Regional Municipality of Durham ext alfred.ho@durham.ca Phil Gray, P. Eng., Project Manager XCG Consultants Ltd ext. 232 philg@xcg.com Agenda for October 27, 2009 The Regional Municipality of Durham Headquarters, Room 1G. 605 Rossland Rd. E, Whitby, ON 6:00 p.m. Sign In, Review Poster Boards 6:15 p.m. Introduction/study presentation 6:45 p.m. Questions and answers 7:30 p.m. Next steps 8:00 p.m. Adjourn Thank you for your time and input! Please take time to fill in the attached questionnaire and a meeting evaluation. Page 2

3 Why? Region of Durham Basement Flooding Prevention Study Project information There was significant surface and basement flooding at various locations in the Annes Street Sewershed during a number of heavy rain events, including the years 1986, 2005 and What is the study area? Page 3

4 What is being considered? Once the issues were identified by the community and the study team, a number of options were identified to address them including: Source control measures (at the individual property level); Conveyance control measures (within the sanitary sewer system); Storage Facilities. Decision-making criteria: In order to identify the solution(s) that are the best fit for the study area, a number of decision-making criteria were used. Please let the study team know if you have any feedback related to these criteria, how they are described, or how they were used to make the preliminary recommendation presented. Evaluation Criteria Comparative Criteria Terrestrial System Aquatic System Community Impact Description Natural Environment Criteria Potential to impact terrestrial habitats or systems, including terrestrial features/functions (Areas of Natural and Scientific interest - ANSIs, Environmentally Sensitive Areas - ESAs), unique vegetation species, mature trees, existing park/open spaces linkages or wildlife. Potential to impact aquatic habitats or systems, including possible impacts on aquatic life, features/functions. Social/Cultural Environment Potential to impact the community either during construction or long-term operation, including: short-term construction impacts such as noise, emissions, traffic congestion consideration for access to the site, visibility, road access, use/loss of valley lands/parks, possible noise/odour / light due to operations requirement for access to private property to implement, effects on school, community or social service facilities, tourism, etc. Measures for Evaluating Does not impact (+) Has comparatively small impact (O) Has comparatively large impact (-) Does not impact (+) Has comparatively small impact (O) Has comparatively large impact (-) Does not impact (+) Has comparatively small impact (O) Has comparatively large impact (-) Page 4

5 Evaluation Criteria Comparative Criteria Land Use Compatibility Description The extent to which the control measure is consistent with the existing land uses in the area and regulatory requirements. Measures for Evaluating Demonstrates good compatibility (+) Demonstrates fair compatibility (O) Demonstrates poor compatibility (-) Implementation The time required to complete design and construction of project elements Cultural Impact Impacts on any local cultural facilities or practices. Potential to affect First Nations Lands such as areas of traditional use, or of sacred or cultural and natural heritage significance. Effectiveness of Control Measure Feasibility of Control Measure Downstream Impacts on Downstream Trunk Sewers / Treatment Facilities / Receiving Water Capital Cost Operation & Maintenance (O&M) Cost Technical Considerations Effectiveness of the alternative to reduce the risk of basement flooding from the sanitary system in the study area. The extent to which the alternative is feasible in terms of availability of space, accessibility, ease of construction,, disruption of utilities, life cycle (durability), construction requirements and minimizing impacts such as upstream flooding. The negative impacts of the alternative in increasing the peak flow rate and total flow in the downstream receiving water system. Cost Considerations The capital cost associated with the construction of the alternative including labour, material, equipment and possibly property acquisition. Post-construction operation and maintenance activities associated with various mitigation measures including regulation inspection, grass cutting/weed control, performance monitoring, sediment/ trash removal and other operational requirements. Shortest implementation period (+) Mid-implementation period (O) Longest implementation period (-) Does not impact (+) Has comparatively small impact (O) Has comparatively large impact (-) Effective in achieving stated requirements (+) Slightly effective (O) Minimal or no effectiveness (-) Feasible in terms of stated considerations (+) Partially feasible (O) Not feasible (-) Does not have an impact (+) Comparatively minor impact (O) Significant impact (-) Capital cost is lowest (+) Capital cost is medium (O) Capital cost is highest (-) O&M cost is lowest (+) O&M cost is medium (O) O&M cost is highest (-) Page 5

6 Please Get Involved Any additional comments should be forwarded by November 6, Comments received will be compiled and summarized in the project documentation. Copies of the presentation and posterboards from tonight s meeting will soon be available on the Region s website at: or by request from the project contacts listed. Thank you for your participation today! We hope that you will continue to contribute as this project moves to completion. Page 6

7 Notes: Region of Durham Basement Flooding Prevention Study Page 7

8 Tear-off Comment Sheet Please return this sheet to a project team member before you leave, or you can mail it in later if you prefer. (Optional information) Name Street Address Phone number Note: Any information added to these comment sheets will be accessible to the general public. By providing comments hereto, you are hereby consenting to the disclosure of your name and comments as part of the public record of consultation for this project. Tonight we heard about the issues that were identified, the possible solutions that were identified, how they were evaluated, and a preliminary recommendation for your neighbourhood. 1. Do you have any comments about the evaluation criteria? Additions, deletions, modifications, clarifications? Page 8

9 Do any comments about the preliminary recommendations? Are you in support? Please explain. Do you have other comments or questions that you feel need to be responded to before the recommendations are finalized? Do you need any additional information? Page 9

10 Evaluation Form (Please return this form to a project team member) Today s event was the second of two public information centres for the Annes Street Sewershed Basement Flooding Prevention Study. We would appreciate any comments you have that could help to improve future meetings. What did you like most about today? What should we improve? Do you have any other ideas about this process? Thank you for your thoughts! Page 10

Duggan Dry Pond and Storm Sewer Improvements. Public Information Session #1 - May 30, 2013

Duggan Dry Pond and Storm Sewer Improvements. Public Information Session #1 - May 30, 2013 Duggan Dry Pond and Storm Sewer Improvements Public Information Session #1 - May 30, 2013 Introduction Introduction of project team Housekeeping items Presentation Question period Information boards Exit

More information

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby

Phases 2 & 3, & Addendum Urban Structure Plan Options for West Whitby 7. 5 A d v a n t a g e s a n d D i s a d v a n t a g e s Table 22 summarizes the advantages and disadvantages of each option based on the evaluation of Table 16. Dillon Consulting Limited Page 75 Table

More information

Stouffville Corridor Rail Service Expansion

Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Stouffville Corridor Rail Service Expansion Class Environmental Assessment Study WELCOME PUBLIC INFORMATION CENTRE #2 Tuesday January 28, 2014 Agincourt Recreation

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment

DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment DEPARTMENT OF ENVIRONMENTAL QUALITY Environmental Assessment Water Protection Bureau Name of Project: Applicant: Ueland Land Development LLC Type of Project: Proposed discharge of treated domestic wastewater

More information

DEPARTMENT OF ENVIRONMENTAL QUALITY

DEPARTMENT OF ENVIRONMENTAL QUALITY PROJECT IDENTIFICATION DEPARTMENT OF ENVIRONMENTAL QUALITY City of Burton Sanitary Sewer Collection System Improvements State Revolving Fund (SRF) Environmental Assessment April 2015 Applicant: Authorized

More information

Lansdowne Stormwater UPDATE

Lansdowne Stormwater UPDATE Lansdowne Stormwater UPDATE August 22, 2012 Ann Arbor Footing Drain Disconnection Stormwater Review Presentation Agenda Welcome and introductions Background on stormwater and sanitary sewer issues Footing

More information

Notice of Study Commencement and Invitation to Participate

Notice of Study Commencement and Invitation to Participate REGION OF WATERLOO Wastewater Treatment Master Plan Class Environmental Assessment Notice of Study Commencement and Invitation to Participate Background The Regional Municipality of Waterloo is responsible

More information

Renseignements supplémentaires. Supplementary Information. Présentation d. Presentation from Ontario Power Generation Inc.

Renseignements supplémentaires. Supplementary Information. Présentation d. Presentation from Ontario Power Generation Inc. Deep Geologic Repository Joint Review Panel Commission d examen conjoint du projet de stockage dans des couches géologiques profondes PMD 13-P1.1Q File / dossier : 8.01.07 Date: 2013-08-27 Edocs: 4191165

More information

Thank you to all of our 2015 sponsors: Media Partner

Thank you to all of our 2015 sponsors: Media Partner Thank you to all of our 2015 sponsors: Media Partner Channel Naturalization: Planning and Implementation in Peel Region TRIECA March 25 & 26, 2015 Peel Region Channel Remediation Strategy An Urban Context

More information

Basement Flooding Loan Program Resulting From a Sanitary Sewer Backup

Basement Flooding Loan Program Resulting From a Sanitary Sewer Backup Basement Flooding Loan Program Resulting From a Sanitary Sewer Backup Dear Owner: On April 1, 2009, Regional Council approved a Basement Flooding Loan Program for those residents who have experienced basement

More information

Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview. Why Subdivision and Land Development Regulations?

Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview. Why Subdivision and Land Development Regulations? Model Subdivision and Land Development (SALDO) Subdivision/ Land Development Presentation Overview Purpose of Subdivision/ Land Development Ordinances (SALDO) Municipalities Planning Code Process Design

More information

Sec. 22a-1a page 1 (4-97)

Sec. 22a-1a page 1 (4-97) Department of Environmental Protection Sec. 22a-1a page 1 (4-97) TABLE OF CONTENTS Connecticut Environmental Policy Act Definitions... 22a-1a- 1 Determination of sponsoring agency.... 22a-1a- 2 Determination

More information

Foreign Affairs Security Training Center (FASTC) U.S. General Services Administration U.S. Department of State

Foreign Affairs Security Training Center (FASTC) U.S. General Services Administration U.S. Department of State Foreign Affairs Security Training Center (FASTC) U.S. General Services Administration U.S. Department of State Supplemental Draft Environmental Impact Statement for U.S. Department of State Foreign Affairs

More information

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH

MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS DURING AUGUST 31, 2014 STORM EVENT COMMUNITY OUTREACH MARYLAND AVENUE BACKUPS COMMUNITY OUTREACH MEETING AGENDA Introductions History of PWSA Actions August 31 Storm Impacts Short

More information

Attachment 1 CARRUTHERS CREEK FLOOD MANAGEMENT and ANALYSIS DRAFT TERMS OF REFERENCE

Attachment 1 CARRUTHERS CREEK FLOOD MANAGEMENT and ANALYSIS DRAFT TERMS OF REFERENCE 1.0 INTRODUCTION In early 2010, the Town of Ajax was provided with updated floodplain mapping for Carruthers Creek, based on a Regional Storm event (i.e., Hurricane Hazel), prepared by the Toronto and

More information

Low Impact Development Checklist

Low Impact Development Checklist New Jersey Stormwater Best Management Practices Manual February 2004 A P P E N D I X A Low Impact Development Checklist A checklist for identifying nonstructural stormwater management strategies incorporated

More information

REQUEST FOR PROPOSAL BANFF TRAIL MASTER PLAN. Issued by the Town of Banff. P.O. Box 1260, 110 Bear St. Banff, AB T1L 1A1

REQUEST FOR PROPOSAL BANFF TRAIL MASTER PLAN. Issued by the Town of Banff. P.O. Box 1260, 110 Bear St. Banff, AB T1L 1A1 REQUEST FOR PROPOSAL TOWN OF BANFF TRAIL MASTER PLAN Issued by the Town of Banff Date of RFP Issue: June 2, 2014 Closing Date for Response: June 17, 2014 Contract Name: Agency Contact Person: Address:

More information

STAFF REPORT TO COMMITTEE OF THE WHOLE

STAFF REPORT TO COMMITTEE OF THE WHOLE STAFF REPORT TO COMMITTEE OF THE WHOLE DATE: November 7 2012 TO: FROM: SUBJECT: ATTACHMENT(S): COMMITTEE OF THE WHOLE GINA LAYTE-LISTON, SUPERVISOR, WASTEWATER Stormwater Management Funding Strategy None

More information

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Whitby CLOCA Whitby CLOCA LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT June 2008 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 STUDY AREA AND SCOPE... 4 3.0 METHODOLOGY...

More information

Bowmanville Marsh Habitat Restoration and Public Access Project

Bowmanville Marsh Habitat Restoration and Public Access Project Bowmanville Marsh Habitat Restoration and Public Access Project Terms of Reference for Detailed and Conceptual Design Works December 2015 1.0 Background and Purpose The Bowmanville Marsh Habitat Restoration

More information

How To Install An Overhead Sewer

How To Install An Overhead Sewer Village of Broadview Flood Control Assistance Program Village of Broadview 2350 S. 25 th Avenue, Broadview, IL 60155 INTRODUCTION The Village of Broadview is served by combined sewers which carry sewage

More information

Off-road Vehicle Regulation. discussion paper

Off-road Vehicle Regulation. discussion paper Off-road Vehicle Regulation discussion paper Yukon is developing a set of regulations to assist in creating the process and tools that will enable us to manage potential environmental damage caused by

More information

4. Environmental Impacts Assessment and Remediation Targets

4. Environmental Impacts Assessment and Remediation Targets 4. Environmental Impacts Assessment and Remediation Targets 4.1 Environmental Impacts Significant additional development in the Alder Creek watershed is not anticipated at this time; however, there are

More information

Toronto Basement Flooding Protection Program

Toronto Basement Flooding Protection Program Toronto Basement Flooding Protection Program In August 2005, a storm exceeding a 1-in-100 year return frequency, hit the City of Toronto with over 150 mm of rainfall within a three hour period. While surface

More information

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This

More information

Corralling the evidence about the value of Green Infrastructure. Martin Moss. Senior Advisor Green Infrastructure Operations England.

Corralling the evidence about the value of Green Infrastructure. Martin Moss. Senior Advisor Green Infrastructure Operations England. Corralling the evidence about the value of Green Infrastructure Martin Moss. Senior Advisor Green Infrastructure Operations England. Flow of discussion. Part 1 - What do we mean by GI? Part 2 - What are

More information

SITE PLAN APPROVAL PROCESS INTRODUCTION

SITE PLAN APPROVAL PROCESS INTRODUCTION SITE PLAN APPROVAL PROCESS INTRODUCTION File Manager System for Site Plan Approval Process Site Plan Control in the City of London The City of London utilizes site plan control to ensure high quality site

More information

A Self Assessment to Address Climate Change Readiness in Your Community Midwest Region

A Self Assessment to Address Climate Change Readiness in Your Community Midwest Region A Self Assessment to Address Climate Change Readiness in Your Community Midwest Region 0 Climate Change Readiness Index A Self Assessment to Address Climate Change Readiness in Your Community Communities

More information

Town of Essex NE Lagoon. Service Area. Essex Plant. Service Area. Pumping Station No. 4. Wastewater Pumped To NE Lagoons (Treatment Plant No.

Town of Essex NE Lagoon. Service Area. Essex Plant. Service Area. Pumping Station No. 4. Wastewater Pumped To NE Lagoons (Treatment Plant No. Town of Essex Basement Flooding Study Town of Essex NE Lagoon Service Area Pumping Station No. 4 Essex Plant Service Area Wastewater Pumped To NE Lagoons (Treatment Plant No. 2) Essex Treatment Plant (Treatment

More information

BEYOND THE STORM: Toronto s Climate Change Adaptation Program. Its about Risk and Cost Management. David MacLeod Toronto Environment Office

BEYOND THE STORM: Toronto s Climate Change Adaptation Program. Its about Risk and Cost Management. David MacLeod Toronto Environment Office BEYOND THE STORM: Toronto s Climate Change Adaptation Program Its about Risk and Cost Management David MacLeod Toronto Environment Office June 16, 2011 Agenda Mitigation & Adaptation: Both are needed Impacts

More information

Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting

Urban Stream Restoration Defining the Full Benefits of a Project. Warren C. High MACTEC Engineering and Consulting Urban Stream Restoration Defining the Full Benefits of a Project Warren C. High MACTEC Engineering and Consulting Economics in the Decision Process Return on Investment Willingness to Pay Municipal Growth

More information

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project.

The purpose of this meeting is to inform the public of the updates to the project, and to get input before the finalization of the project. The purpose of this meeting is inform the public of the updates the project, and get input before the finalization of the project. The following panels describe the purpose and hisry of the project, along

More information

Sustainable Landscape Maintenance Planning and Strategies

Sustainable Landscape Maintenance Planning and Strategies Chapter 2 Sustainable Landscape Maintenance Planning and Strategies In this Chapter What are our goals for sustainable landscape maintenance? What is sustainable landscape maintenance? How is a sustainable

More information

Scheduling Maintenance for Infiltration Basins and Trenches

Scheduling Maintenance for Infiltration Basins and Trenches Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections

More information

Chapter 8. List of Preparers

Chapter 8. List of Preparers Chapter 8 List of Preparers This page intentionally left blank. 8 List of Preparers Name and DEIS Responsibility and Qualifications United States Fish and Wildlife Service Megan Seymour Wildlife Biologist,

More information

CHAPTER 4 ALTERNATIVES COMPARISON

CHAPTER 4 ALTERNATIVES COMPARISON CHAPTER 4 ALTERNATIVES COMPARISON 4.1 INTRODUCTION This chapter provides a comparison of the and its alternatives as described in EIS/EIR Section 1.8.3 (s Evaluated in this EIS/EIR) and analyzed in Sections

More information

DRAFT ENVIRONMENTAL ASSESSMENT TEMPLATE

DRAFT ENVIRONMENTAL ASSESSMENT TEMPLATE DRAFT ENVIRONMENTAL ASSESSMENT TEMPLATE I. SUMMARY A. PROJECT IDENTIFICATION Applicant: Address: Project No. B. CONTACT PERSON Mr.\Ms. City or County Manager P.O. Box, Colorado 80 C. ABSTRACT Briefly summarize

More information

Climate Adaptation and Preparedness

Climate Adaptation and Preparedness Climate Adaptation and Preparedness Aaron Durnbaugh, Adaptation Coordinator & Deputy Commissioner, City of Chicago Department of Environment Rahm Emanuel, Mayor Climate Impact: Lake Michigan Decreased

More information

NEW BRUNSWICK DEPARTMENT OF SUPPLY AND SERVICES EEL RIVER DAM REMOVAL/ DECOMMISSIONING PROJECT

NEW BRUNSWICK DEPARTMENT OF SUPPLY AND SERVICES EEL RIVER DAM REMOVAL/ DECOMMISSIONING PROJECT NEW BRUNSWICK DEPARTMENT OF SUPPLY AND SERVICES EEL RIVER DAM REMOVAL/ DECOMMISSIONING PROJECT August 2006 Prepared by: NB Department of Environment Environment 1. INTRODUCTION This General Review Statement

More information

REQUEST FOR PROPOSAL to provide ON-CALL ENVIRONMENTAL CONSULTING SERVICES for the RIVERSIDE COUNTY TRANSPORTATION DEPARTMENT

REQUEST FOR PROPOSAL to provide ON-CALL ENVIRONMENTAL CONSULTING SERVICES for the RIVERSIDE COUNTY TRANSPORTATION DEPARTMENT REQUEST FOR PROPOSAL to provide ON-CALL ENVIRONMENTAL CONSULTING SERVICES for the RIVERSIDE COUNTY TRANSPORTATION DEPARTMENT Table of Contents I. Events Calendar. 1 II. Introduction.. 2 III. Inquires.

More information

Assiniboine River and Lake Manitoba Basins Flood Mitigation Study: Providing Greater Protection For Manitobans From Flood Risks

Assiniboine River and Lake Manitoba Basins Flood Mitigation Study: Providing Greater Protection For Manitobans From Flood Risks Assiniboine River and Lake Manitoba Basins Flood Mitigation Study: Providing Greater Protection For Manitobans From Flood Risks Welcome! Manitoba Infrastructure and Transportation is studying flooding

More information

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO.

COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO. COUNTY OF LAMBTON OFFICIAL PLAN UPDATE BACKGROUND REPORT NO. 6 RENEWABLE ENERGY Image Source: (Word Clip Art Stock Photo, 2011) Date: May, 2015 BACKGROUND PLANNING AND DEVELOPMENT SERVICES DEPARTMENT 789

More information

Gold Ray Dam Interagency Technical Team Meeting

Gold Ray Dam Interagency Technical Team Meeting Gold Ray Dam Interagency Technical Team Meeting Agenda Public Outreach, Funding, Monitoring EA/BA/Permit Updates Deconstruction Plans Fish Passage & Salvage Plan Hydraulic Modeling Next Steps Public Outreach,

More information

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County

Mission Creek Flood Control & Restoration Project. City of Fremont, Alameda County Mission Creek Flood Control & Restoration Project City of Fremont, Alameda County Agenda Background Why are proposed improvements necessary? Proposed project components Challenges Construction schedule/phasing

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION Elba Liquefaction Company, L.L.C. Southern LNG Company, L.L.C. Elba Express Company, L.L.C. Docket No. PF13-3-000 NOTICE OF INTENT TO PREPARE

More information

Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office

Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office Lisgar District Basement Water Infiltration Investigation Part A Answers to Technical Questions 1. There has been a tremendous amount of work done everywhere along the creek. If there was nothing wrong

More information

Parkhill Road Sewage Pumping Station Class EA Study

Parkhill Road Sewage Pumping Station Class EA Study Parkhill Road Sewage Pumping Station Class EA Study Public Information Centre October 4, 2011 6:30 pm 8:30 pm Westmount Public School DRAWING ON EXPERIENCE BUILDING ON STRENGTH Sewage Pumping Station (SPS)

More information

Addendum D. Nomination of Moody Wash ACEC

Addendum D. Nomination of Moody Wash ACEC Addendum D Nomination of Moody Wash ACEC Moody Wash ACEC is hereby nominated by Citizens for Dixie s Future to: BLM St. George Field Office 345 East Riverside Drive St. George, UT 84790 Moody Wash is a

More information

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Harmony Creek subwatershed Harmony Creek subwatershed BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT April 2011 TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

AGENDA LARIMER COUNTY PLANNING COMMISSION Wednesday, April 20, 2016/6:30 P.M./Commissioners' Hearing Room

AGENDA LARIMER COUNTY PLANNING COMMISSION Wednesday, April 20, 2016/6:30 P.M./Commissioners' Hearing Room AGENDA LARIMER COUNTY PLANNING COMMISSION Wednesday, April 20, 2016/6:30 P.M./Commissioners' Hearing Room A. CALL TO ORDER B. PLEDGE OF ALLEGIANCE C. PUBLIC COMMENT ON THE COUNTY LAND USE CODE D. PUBLIC

More information

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure (December 2013) IUCN does not engage in projects which involve the design, construction or rehabilitation

More information

PUBLIC NOTICE Application for Permit

PUBLIC NOTICE Application for Permit PUBLIC NOTICE Application for Permit 30-Day Notice Issue Date: June 20, 2016 Expiration Date: July 20, 2016 US Army Corps of Engineers No: NWP-2010-535 Oregon Department of State Lands No: 58311-RF Interested

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

Lawrence Park Neighbourhood Investigation of Basement Flooding and Road Improvement Study Municipal Class Environmental Assessment

Lawrence Park Neighbourhood Investigation of Basement Flooding and Road Improvement Study Municipal Class Environmental Assessment Lawrence Park Neighbourhood Investigation of Basement Flooding and Road Improvement Study Municipal Class Environmental Assessment December 2013 Public Information Center #2 Summary Report Prepared by

More information

Climate Change: A Local Focus on a Global Issue Newfoundland and Labrador Curriculum Links 2010-2011

Climate Change: A Local Focus on a Global Issue Newfoundland and Labrador Curriculum Links 2010-2011 Climate Change: A Local Focus on a Global Issue Newfoundland and Labrador Curriculum Links 2010-2011 HEALTH Kindergarten: Grade 1: Grade 2: Know that litter can spoil the environment. Grade 3: Grade 4:

More information

COMMUNITY CERTIFICATIONS

COMMUNITY CERTIFICATIONS National Flood Insurance Program Community Rating System COMMUNITY CERTIFICATIONS Public reporting burden for this form is estimated to average 4 hours for annual recertification, per response. The burden

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

COASTAL APPLICATION FOR A MAJOR SITING PERMIT

COASTAL APPLICATION FOR A MAJOR SITING PERMIT Frank M. Rabauliman Administrator Commonwealth of the Northern Mariana Islands OFFICE OF THE GOVERNOR Bureau of Environmental and Coastal Quality Division of Coastal Resources Management Gualo Rai Center

More information

Construction Specification for Sewer Bypass Flow Pumping

Construction Specification for Sewer Bypass Flow Pumping Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 4.01 April 2013 Pumping Table of Contents TS 4.01.01 SCOPE... 2 TS 4.01.02 REFERENCES... 2 TS 4.01.03

More information

Proposed General Plan Update Goals, Policies, and Implementation Actions

Proposed General Plan Update Goals, Policies, and Implementation Actions Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental

More information

Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities

Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities Summary and Description of 2014 Enhancements to New Jersey Model Stormwater Control Ordinance for Municipalities This document summarizes and provides explanation for the purpose and intent of major recommended

More information

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439)

CALDER PARK PROJECT STAGE 1. EPBC Act Approval Compliance Report (EPBC 2012/6439) CALDER PARK PROJECT STAGE 1 EPBC Act Approval Compliance Report (EPBC 2012/6439) Prepared for: METRO TRAINS MELBOURNE Level 28, 80 Collins Street, Melbourne, VIC 3000 Prepared by: Kellogg Brown & Root

More information

Rural Flooding: The Potential Role of Forestry

Rural Flooding: The Potential Role of Forestry Rural Flooding: The Potential Role of Forestry Nadeem Shah, Tom Nisbet, & Huw Thomas Centre for Forestry and Climate Change Structure Background Woodland and Flood Alleviation The Theory. Studies on Woodland

More information

Designed and produced by geo-graphicsdesign.com DP 300 3/02

Designed and produced by geo-graphicsdesign.com DP 300 3/02 Designed and produced by geo-graphicsdesign.com DP 300 3/02 Guidance for Developers and Regulators Purpose This booklet is produced on behalf of the North East Scotland Flooding Advisory Group and is intended

More information

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT

STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY FINDINGS OF FACT STATE OF MINNESOTA MINNESOTA POLLUTION CONTROL AGENCY IN THE MATTER OF THE DECISION ON THE NEED FOR AN ENVIRONMENTAL IMPACT STATEMENT FOR THE PROPOSED ELKO NEW MARKET INTERCEPTOR, CSAH 2 SEGMENT SCOTT

More information

Energie Saguenay Project Update and Preliminary Consultation Results. June 3, 2015

Energie Saguenay Project Update and Preliminary Consultation Results. June 3, 2015 Energie Saguenay Project Update and Preliminary Consultation Results June 3, 2015 Meeting Agenda Time (pm) 7:00 Activity Energie Saguenay Project update and results of the preliminary consultation process

More information

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet WELCOME Please sign in Representatives are available to answer questions Please complete a comment sheet Place it in the box or send it to the Consultant undertaking the study or to the Town of Wasaga

More information

BOROUGH OF CRESSKILL MAYOR AND COUNCIL CRESSKILL BERGEN COUNTY NEW JERSEY REGULAR MEETING APRIL 6, 2016

BOROUGH OF CRESSKILL MAYOR AND COUNCIL CRESSKILL BERGEN COUNTY NEW JERSEY REGULAR MEETING APRIL 6, 2016 45 BOROUGH OF CRESSKILL MAYOR AND COUNCIL CRESSKILL BERGEN COUNTY NEW JERSEY REGULAR MEETING APRIL 6, 2016 1. Barbara Mann led the Salute to the Flag and Pledge of Allegiance. 2. The Deputy Borough Clerk

More information

SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM

SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM SCHNEIDER CREEK REMEDIATION CLASS ENVIRONMENTAL ASSESSMENT ADDENDUM PUBLIC MEETING FEBRUARY 8 TH, 2012 The City of Kitchener and Grand River Conservation Authority (GRCA) are undertaking an Environmental

More information

understanding Sustainable Landscaping & Tree Preservation Standards

understanding Sustainable Landscaping & Tree Preservation Standards understanding Sustainable Landscaping & Tree Preservation Standards Purpose To promote landscaping around development that is compatible with the existing environment, and which reduces greenhouse gas

More information

Regulatory Features of All Coastal and Inland Ecological Restoration Limited Projects

Regulatory Features of All Coastal and Inland Ecological Restoration Limited Projects Eligibility Checklist This Ecological Restoration Limited Project Eligibility Checklist guides the applicant in determining if their project is eligible to file as an Inland or Coastal Ecological Restoration

More information

Department of the Interior. Departmental Manual

Department of the Interior. Departmental Manual Page 1 of 10 Department of the Interior Departmental Manual Effective Date: 10/23/2015 Series: Public Lands Part 600: Public Land Policy Chapter 6: Implementing Mitigation at the Landscape-scale Originating

More information

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL

CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL CONSTRUCTION MANAGEMENT PLAN REQUIREMENTS MANUAL This manual applies to all development projects within Pitkin County. A Construction Management Plan (CMP) shall be submitted for all projects in Pitkin

More information

West London Dyke Flood Control Structure Master Plan Appendix A

West London Dyke Flood Control Structure Master Plan Appendix A West London Dyke Flood Control Structure Master Plan Appendix A Introduction The West London Dyke runs along the west bank of the North Branch of the Thames River from Oxford Street to the forks of the

More information

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?

More information

NOTICE OF COMPLETE APPLICATIONS AND PUBLIC INFORMATION MEETING

NOTICE OF COMPLETE APPLICATIONS AND PUBLIC INFORMATION MEETING NOTICE OF COMPLETE APPLICATIONS AND PUBLIC INFORMATION MEETING PLAN OF SUBDIVISION APPLICATION: S-S-2015-02 SCUGOG OFFICIAL PLAN AMENDMENT APPLICATION: SOP/02/2015 ZONING BY-LAW AMENDMENT APPLICATION:

More information

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a

River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a River Wensum Restoration Strategy Swanton Morley Restoration Scheme Reach 14a At a glance River restoration benefits: Improved planform, channel cross-section, flow variation and sediment process. Improved

More information

TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES

TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES TRANSPORTATION SERVICE STANDARDS ELEMENT GOALS, OBJECTIVES & POLICIES Background One of the most critical public services provided by a community is the community s transportation system. An effective

More information

CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center

CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center CMOM How to Develop Your Collection System Maintenance Program NWOWEA Pre-Conference Utility Workshop June 22, 2015 Kalahari Conference Center Thomas A. Fishbaugh Ohio RCAP What is CMOM? CMOM: Capacity,

More information

How To Plan A Buffer Zone

How To Plan A Buffer Zone Backyard Buffers Protecting Habitat and Water Quality What is a buffer? A buffer (also called a riparian buffer area or zone) is the strip of natural vegetation along the bank of a stream, lake or other

More information

How To Protect A Floodplain From Flooding

How To Protect A Floodplain From Flooding EXECUTIVE SUMMARY This Class Environmental Assessment (Class EA) was undertaken to examine alternative flood protection systems, and their environmental effects, for the elimination of the flood risk on

More information

A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1

A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1 A Cost Analysis of Stream Compensatory Mitigation Projects in the Southern Appalachian Region 1 J. Bonham 2 and K. Stephenson Abstract Recently the US Army Corps of Engineers (the Corps) has increased

More information

US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing

US 281 AT PREMONT PUBLIC HEARING. US 281 at Premont Public Hearing US 281 AT PREMONT PUBLIC HEARING Hearing Purpose The purpose of tonight s Public Hearing is for the public to: Learn about the status of the proposed project Review the purpose and need for the project

More information

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation

Position Statement regarding Offshore Wind Proposals on Lake Huron. Lake Huron Centre for Coastal Conservation Position Statement regarding Offshore Wind Proposals on Lake Huron Lake Huron Centre for Coastal Conservation June 2010 Lake Huron Centre for Coastal Conservation (LHCCC) Corporate Position related to:

More information

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems

ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems ecmar SECTION INSTRUCTIONS: Sanitary Sewer Collection Systems Please see the DEFINITIONS of terms at the end of this section. If you have any questions about these definitions, do not understand a question,

More information

Asset Management and Industry Solutions - A Municipal Perspective

Asset Management and Industry Solutions - A Municipal Perspective Asset Management and Industry Solutions - A Municipal Perspective Saidur Rahman, Ph.D., P. Eng. Senior Infrastructure Project Manager Town of Oakville Highlights Municipal Infrastructure in Canada Scope

More information

Whitby. Key Requirements. Primary Municipal Contact. Documentation

Whitby. Key Requirements. Primary Municipal Contact. Documentation Key Requirements Application should be submitted 10 business days in advance Location fee Required for filming on streets and property, including parks and facilities, under the jurisdiction of the Corporation

More information

A Developer s Guide: Watershed-Wise Development

A Developer s Guide: Watershed-Wise Development A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another

More information

Summary of the Heritage Tree Ordinance Updated July 2013

Summary of the Heritage Tree Ordinance Updated July 2013 Summary of the Heritage Tree Ordinance Updated July 2013 Purpose of the Ordinance See also: Chapter 13.24 of the Menlo Park Municipal Code (Available at www.menlopark.org or by calling 330-6740) The City

More information

Oil Sands Environmental Coalition

Oil Sands Environmental Coalition Oil Sands Environmental Coalition 2 December 2013 Canadian Environmental Assessment Agency Attention: David Haddon Panel Manager 160 Elgin Street, 22nd Floor Ottawa ON K1A 0H3 Frontier.Review@ceaa-acee.gc.ca

More information

Celebrating over 50 years of service MEMORANDUM

Celebrating over 50 years of service MEMORANDUM Celebrating over 50 years of service MEMORANDUM TO: Town of Tyre Ronald F. McGreevy, Supervisor JN. 1650.001.001 FROM: Adam Cummings, P.E., BCEE DATE: 3 September 2015 SUBJECT: Project Proposal SEQRA Documentation

More information

Construction Management Plan Template

Construction Management Plan Template Plan Template Planning Permit Number:... Date Planning Permit Issued:... Approval Stamp (Office Use only): Standard Plan Template Project details Company Operational Details.. Directors Name Company Name

More information

A Century of Progress with Pride

A Century of Progress with Pride The City of Berwyn Engineering Department A Century of Progress with Pride November 12, 2014 Re: Waiting List Application I am interested in the following programs and would like to be added to the waiting

More information

CHAPTER 8 ASSET MANAGEMENT

CHAPTER 8 ASSET MANAGEMENT CHAPTER 8 ASSET MANAGEMENT 8.1 Introduction An additional task of the WRMP was to educate and engage GWA personnel in the concepts of asset management. Three specific areas of asset management have been

More information

Bjerkness, Kolodge, Langley, Maki, Manderfeld, Wilkinson, Mayor Ahlgren.

Bjerkness, Kolodge, Langley, Maki, Manderfeld, Wilkinson, Mayor Ahlgren. 17 Council Chambers, Cloquet, Minnesota 7:00 o clock P.M. February 19, 2013 Regular Meeting. Roll Call. Councilors Present: Councilors Absent: Bjerkness, Kolodge, Langley, Maki, Manderfeld, Wilkinson,

More information

GENESEE COUNTY DRAIN COMMISSIONER S OFFICE

GENESEE COUNTY DRAIN COMMISSIONER S OFFICE GENESEE COUNTY DRAIN COMMISSIONER S OFFICE DIVISION OF SURFACE WATER MANAGEMENT G-4608 BEECHER ROAD, FLINT, MI 48532 PHONE (810) 732-1590 FAX (810) 732-1474 JEFFREY WRIGHT COMMISSIONER October 1, 2012

More information

Request for Proposals Sanitary Sewer System Condition Assessment (PILOT PROJECT)

Request for Proposals Sanitary Sewer System Condition Assessment (PILOT PROJECT) Request for Proposals Sanitary Sewer System Condition Assessment (PILOT PROJECT) Utilizing CCTV equipment, equipment use training, NASSCO PACP defect coding, and infrastructure program management software

More information

District of Columbia Water and Sewer Authority George S. Hawkins, General Manager

District of Columbia Water and Sewer Authority George S. Hawkins, General Manager District of Columbia Water and Sewer Authority George S. Hawkins, General Manager FLOODING ISSUES IN BLOOMINGDALE AND LeDROIT PARK A DC Water Presentation Given to the Mayor s Task Force on the Prevention

More information

Section 5: Conserve to Enhance Program Goals What is Conserve to Enhance All About?

Section 5: Conserve to Enhance Program Goals What is Conserve to Enhance All About? Section 5: Conserve to Enhance Program Goals What is Conserve to Enhance All About? Conserve to Enhance (C2E) was originally conceptualized as an approach to giving the environment a seat at the table

More information

FY 2015-2019 Capital Improvement Program Arroyo Projects - Lower Arroyo. 13 - Summary

FY 2015-2019 Capital Improvement Program Arroyo Projects - Lower Arroyo. 13 - Summary LOWER ARROYO FY 215-219 Capital Improvement Program Description FY 214 FY 215 FY 216 FY 217 FY 218 FY 219 1 Bird Sanctuary Improvements (7749) 35, 225, 125, 2 Lower Arroyo - Implement Master Plan - Signage

More information