Is Overproduction Costing You?
|
|
|
- Myron Hopkins
- 9 years ago
- Views:
Transcription
1 Is Overproduction Costing You? A review of the impacts of solar resource data on financing and revenues for PV plants Presented by: Marie Schnitzer Vice President of Consulting Services Paul Thienpont Meteorologist
2 Denver Colorado Albany New York (HQ) Barcelona Spain Warsaw Poland (*) Istanbul Turkey (*) Bangalore India Buenos Aires Argentina (*) Rio de Janeiro Brazil Company Snapshot Renewable energy professionals providing technical consulting, software, data, and advisory services for the wind and solar energy markets Established in 1983; over 30 years of renewable energy industry experience Assessed over 100,000 MW Project roles in over 80 countries Offices around the globe and *with partnerships in Argentina, Poland and Turkey
3 Key Messages Obtaining an accurate, reliable solar resource assessment Overproduction from unreliable data sources can result in lost revenue Overproduction can result in lost returns
4 Financial Impacts Power Purchase Agreements (PPA) Over/Under production penalties PPA bid process Financial Models Tax Equity Financing Debt to Equity ratios Debt Service Coverage Ratio (DSCR) Cost of Capital and Rate of Return
5 Investor Interests Equity Investors Long-Term Productions Estimates Tax Equity Investors Interests are greatest in the beginning of the project life-cycle Debt Lenders Interested only in the minimum ability to pay back loan P50 Estimates P50 Estimates P90/99 Estimates
6 How do you quantify these risks? And how the variables impact your bottom line.
7 Study Approach Solar Resource GHI, DNI, DHI POA Energy Revenue Financial Model
8 Resource Assessment Methods Irradiance Data NASA SSE National Solar Radiation Database (NSRDB) -TMY 3 Satellite Derived Datasets Publicly available Commercially available (for purchase) Site Specific Typical Meteorological Year AWS Truepower Analysis Onsite measurements Satellite derived datasets Measured reference networks Conversion to Plane of Array (POA) Measured Reference Networks USCRN NREL On-Site Measurements
9 Study Approach Solar Resource Energy Losses Uncertainty Revenue Financial Model
10 Energy Modeling Satellite Reference Station Site Specific (Advanced) TMY Onsite Measurement Plant Specifications Energy Simulation Model Environmental & System Losses Uncertainty from all inputs Annual Energy Prediction P50, P90, P99
11 Sources of Energy Uncertainty Annual Degradation (0.5 1 %) Transposition To Plane of Array (0.5 2%) Energy Simulation, Plant Losses (3 5 %) Solar Resource Uncertainty (5 17%)
12 Energy Estimates and Probability of Exceedance Probability of exceedance: the level of confidence that a plant s actual energy production will be at least a certain value P90 Based on project uncertainty High Quality Resource Data P90 Reduced uncertainty Increased value of P90(99)
13 Study Approach Solar Resource Energy Revenue PPA Over/Under Financial Model
14 PPA Pricing Time of Day Pricing Base Price based on Locational Marginal Pricing (LMP) Time of Day Pricing (TOD) multipliers are used to adjust base price based on time of day and seasonal adjustments Production Thresholds PPA s typically include maximum annual production restrictions Restrictions are commonly applied at 110% of the estimated annual P50 plant production Net metering caps
15 Study Approach Solar Resource Energy Revenue Financial Model CapEx OpEx Debt Sizing
16 Financial Model Capital Expenses: EPC (full wrap) Permitting Developer fees Land lease Other Production Estimates: P50, P90, P99 Energy estimates PPA pricing Operational Expenses: Operating costs General administration Project Finance Structures Debt finance Debt Service Coverage Ratio Tax equity or cash equity finance Internal Rate of Return
17 Quantifying financial risk Case study results for three project locations
18 Case Studies: Methodology Three sites collocated with United States Climate Reference Network (USCRN) measured reference stations were selected for evaluation based on geographic location and consistency of the observations. Three resource methods were examined for each location: Actual resource data (measured) Satellite Derived TMY NSRDB TMY3 Uncertainty and Probability of Exceedance (P-tables) were assessed for each method Energy was simulated in PVsyst using the AWS Truepower standard approach for each location
19
20 Case Study: Methodology Plant Design: 12.5 MW DC 10 MW AC DC/AC Ratio: 1.25 Generic 300 W polycrystalline module Generic 500 kw inverter Row tilt optimized for each location using PVsyst Modeled without near shading Plant loss assumptions were applied consistently for each project location and resource analysis
21 Solar and Met Resource Variation Difference From Actual (%) 20% 15% 10% 5% 0% -5% -10% -15% -20% Merced, CA Satellite TMY3 GHI DNI DHI POA Temp Difference From Actual (%) 20% 15% 10% 5% 0% -5% -10% -15% -20% Millbrook, NY Satellite TMY3 Difference From Actual (%) 30% 25% 20% 15% 10% 5% 0% -5% -10% -15% -20% -25% -30% Tucson, AZ Satellite TMY3 GHI DNI DHI POA Temp GHI DNI DHI POA Temp
22 Energy Variation 10% 8% 6% Difference From Actual (%) 4% 2% 0% -2% -4% -6% -8% -10% Gross Energy Long-Term Net Energy Merced, CA Satellite Merced, CA TMY3 Tucson, AZ Satellite Tucson, AZ TMY3 Millbrook, NY Satellite Millbrook, NY TMY3
23 Case Study: PPA Revenue Assumptions PPA Pricing Assumptions: Base price: $66/MWh TOD and seasonal multipliers PPA overproduction: Assumed 75% decreased payment structure beyond 110% of the guaranteed energy production level (P50 Production) Energy > Annual P50 Production = 0.75 x (Base Price x TOD Multiplier) Financial model used LMP data to calculate baseline PPA pricing and TOD based off of the Day Ahead Market (DAM) prices
24 Case Study: PPA Revenue 4.0% Financed With Satellite TMY Financed with NSRDB TMY3 Difference in Revenue From Actual(%) 3.0% 2.0% 1.0% 0.0% -1.0% -2.0% -3.0% -4.0% TOD Revenue Lost Revenue to Cap TOD revenue is based of long-term energy 8760 results for each resource file utilizing the TOD and seasonal multipliers to the baseline PPA price Lost revenue is based off of using 110% of the estimated long-term net energy P50
25 Case Study: Debt Finance Structure Model Assumptions Financial Model Assumptions: CAPEX: $2.2/W AC installed capacity OPEX: $25/kW AC /year installed capacity Debt sizing: Debt ratio sized using a DSCR of 1.0 and P99 production estimates Financial Models: Three independent models were created: 1. Actual resource data 2. Satellite derived TMY 3. NSRDB TMY3 Analysis: Satellite and TMY3 model financing assumptions were stressed using the actual resource data
26 Case Study: Debt Finance Structure Key Metrics Debt Ratio: The amount of acquired debt Projected IRR: The estimated IRR for the cash equity investor when financing with each resource dataset Actual IRR: The realized IRR for the cash equity investor when running the actual resource data file through the financial model for the Satellite TMY and NSRDB TMY3
27 Case Study Results: Debt Financing Merced, CA 1.0% Financed With Satellite TMY Financed With NSRDB TMY3 Difference From Ground Corrected (%) 0.0% -1.0% -2.0% -3.0% -4.0% -5.0% -6.0% -7.0% Debt Ratio Projected IRR Actual IRR The project should have financed using 3% more debt The forecasted IRR was 2% lower than optimal results As a result the actual IRR was 0.5% lower than optimal results
28 Case Study: Tax Equity Financial Model Assumptions Financial Model Assumptions: CAPEX: $2.2/W AC installed capacity OPEX: $25/kW AC /year installed capacity Tax Equity Investment: Tax equity investment sized assuming an 8.0% IRR Financial Models: Three independent models were created: 1. Actual resource data 2. Satellite derived TMY 3. NSRDB TMY3 Analysis: Satellite and TMY3 model financing assumptions were stressed using the actual resource data.
29 Case Study: Tax Equity Finance Structure Key Metrics Tax Equity Contribution: The difference in tax equity contribution Projected IRR: The estimated IRR for the cash equity investor when financing with each resource dataset Actual IRR: The realized IRR for the cash equity investor when running the actual resource data file through the financial model for the Satellite TMY and NSRDB TMY3
30 Case Study Results: Tax Equity Financing Merced, CA 1.0% 0.5% Financed With Satellite TMY Financed With NSRDB TMY3 Difference From Optimal (%) 0.0% -0.5% -1.0% -1.5% -2.0% -2.5% -3.0% Tax Equity Contribution Projected IRR Actual IRR The project should have financed using 0.3% more Tax Equity Contribution The forecasted IRR was 0.9% lower than optimal results As a result the actual IRR was 0.5% lower than optimal results
31 Conclusions Site Specific Resource yields more accurate P50 analysis and improved uncertainty bounds Many sources of unreliable data resulting in higher uncertainty Overproduction results in lost revenue Overproduction results in lost returns for both debt, tax equity and cash equity finance
32 Thank You awstruepower.com Marie Schnitzer Vice President of Consulting Services Paul Thienpont Meteorologist
Solar Input Data for PV Energy Modeling
June 2012 Solar Input Data for PV Energy Modeling Marie Schnitzer, Christopher Thuman, Peter Johnson Albany New York, USA Barcelona Spain Bangalore India Company Snapshot Established in 1983; nearly 30
REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES
REDUCING UNCERTAINTY IN SOLAR ENERGY ESTIMATES Mitigating Energy Risk through On-Site Monitoring Marie Schnitzer, Vice President of Consulting Services Christopher Thuman, Senior Meteorologist Peter Johnson,
EVALUATING SOLAR ENERGY PLANTS TO SUPPORT INVESTMENT DECISIONS
EVALUATING SOLAR ENERGY PLANTS TO SUPPORT INVESTMENT DECISIONS Author Marie Schnitzer Director of Solar Services Published for AWS Truewind October 2009 Republished for AWS Truepower: AWS Truepower, LLC
Power Purchase Agreement Financial Models in SAM 2013.1.15
Power Purchase Agreement Financial Models in SAM 2013.1.15 SAM Webinar Paul Gilman June 19, 2013 NREL is a national laboratory of the U.S. Department of Energy, Office of Energy Efficiency and Renewable
Development of a. Solar Generation Forecast System
ALBANY BARCELONA BANGALORE 16 December 2011 Development of a Multiple Look ahead Time Scale Solar Generation Forecast System John Zack Glenn Van Knowe Marie Schnitzer Jeff Freedman AWS Truepower, LLC Albany,
Solar Resource Measurement Importance. Wil Grady P.E. Southern California Edison Power Supply NREL PV Solar Resource Workshop Denver 2015
Solar Resource Measurement Importance Wil Grady P.E. Southern California Edison Power Supply NREL PV Solar Resource Workshop Denver 2015 1 Overview of SCE Large service territory 14 million residents 4.9
Feasibility studies - for successful tendering. Felix Eichhorn CEO Solarpraxis Engineering GmbH
Feasibility studies - for successful tendering Felix Eichhorn CEO Solarpraxis Engineering GmbH HistoryofSolarpraxis Milestones 1998 FoundedbyKarl-Heinz Remmers andkay Neubert assolarpraxis GbR in Berlin
IFC ESMAP- RENEWABLE ENERGY TRAINING PROGRAM. Wind Module. II. Wind Project Development, Implementation, and Financing
IFC ESMAP- RENEWABLE ENERGY TRAINING PROGRAM Wind Module II. Wind Project Development, Implementation, and Financing Washington DC, June 16th 2014 Index Wind Project Development, Implementation, and Financing
Overview of Rooftop Solar PV Green Bank Financing Model
Overview of Rooftop Solar PV Green Bank Financing Model Sponsored by The Connecticut Clean Energy Finance and Investment Authority and The Coalition for Green Capital Developed by Bob Mudge & Ann Murray,
Guidelines for Detailed Wind Resource Measurements on Islands
Guidelines for Detailed Wind Resource Measurements on Islands Matthew V. Filippelli Principal Engineer IRENA Island Energy Transitions: Pathways for Accelerated Uptake of Renewables Martinique 22-24 June
Introduction to Project Finance Analytic Methods
Introduction to Project Finance Analytic Methods Renewable Energy and Project Development and Financing for California Tribes Sacramento, CA Jack Whittier, McNeil Technologies January 2008 Why? Use a model
Technology Advantage
Technology Advantage 2 FIRST SOLAR TECHNOLOGY ADVANTAGE 3 The Technology Advantage Cadmium Telluride (CdTe) photovoltaic (PV) technology continues to set performance records in both research and real-world
Husum Wind Energy 6th of June 2013. Johannes Ritter Partner Solution Matrix [email protected] +49-178-8586084
Husum Wind Energy 6th of June 2013 Johannes Ritter Partner Solution Matrix [email protected] +49-178-8586084 Solution Matrix Europe s nr. 1 authority on Business Case 326 Business Case
Bigger is Better: Sizing Solar Modules for Microinverters
Bigger is Better: Sizing Solar Modules for Microinverters Authors: David Briggs 1 ; Dave Williams 1 ; Preston Steele 1 ; Tefford Reed 1 ; 1 Enphase Energy, Inc. October 25, 2012 SUMMARY This study analyzed
Community and Renewable Energy Scheme Project Development Toolkit
Community and Renewable Energy Scheme Project Development Toolkit Balance Sheet Equity Investment Community Bond Issues Community Vehicle Crowd Funding Debentures a form of bond Debt Debt Service Cover
User Perspectives on Project Feasibility Data
User Perspectives on Project Feasibility Data Marcel Šúri Tomáš Cebecauer GeoModel Solar s.r.o., Bratislava, Slovakia [email protected] http://geomodelsolar.eu http://solargis.info Solar Resources
Irradiance. Solar Fundamentals Solar power investment decision making
Solar Fundamentals Solar power investment decision making Chilean Solar Resource Assessment Antofagasta and Santiago December 2010 Edward C. Kern, Jr., Ph.D., Inc. Global Solar Radiation Solar Power is
Overview of Solar Guidebook and Knowledge Management Project Sustainable Business Advisory
Overview of Solar Guidebook and Knowledge Management Project Sustainable Business Advisory April 2012 Knowledge Management Project - the Aim to build capacity, capture lessons learned and disseminate and
Simple project evaluation spreadsheet model
Simple project evaluation spreadsheet model Africa Electricity Institute Practitioner Workshop 15 November 2011 -- Dakar, Senegal Chris Greacen Two very different models Used by: Excel financial model
Application Note - How to Design a SolarEdge System Using PVsyst
March 2015 Application Note - How to Design a SolarEdge System Using PVsyst As of version 5.20, PVsyst - the PV system design software - supports the design of SolarEdge systems. This application note
Solar Variability and Forecasting
Solar Variability and Forecasting Jan Kleissl, Chi Chow, Matt Lave, Patrick Mathiesen, Anders Nottrott, Bryan Urquhart Mechanical & Environmental Engineering, UC San Diego http://solar.ucsd.edu Variability
Financial and Cash Flow Analysis Methods. www.project-finance.com
Financial and Cash Flow Analysis Methods Financial analysis Historic analysis (BS, ratios, CF analysis, management strategy) Current position (environment, industry, products, management) Future (competitiveness,
Financing Solutions for Renewable Temporary / Off-grid Power. Daniel Zywietz, CEO, Enerwhere
Financing Solutions for Renewable Temporary / Off-grid Power Daniel Zywietz, CEO, Enerwhere CEBC Sustainable Energy Financing in MENA event, November 5 th 2014 1 WHAT IS TEMPORARY / OFF-GRID POWER? 2 Diesel
OFF-GRID ELECTRICITY GENERATION WITH HYBRID RENEWABLE ENERGY TECHNOLOGIES IN IRAQ: AN APPLICATION OF HOMER
Diyala Journal of Engineering Sciences ISSN 1999-8716 Printed in Iraq Second Engineering Scientific Conference College of Engineering University of Diyala 16-17 December. 2015, pp. 277-286 OFF-GRID ELECTRICITY
SECURITIES AND EXCHANGE COMMISSION FORM ABS-15G. Asset-backed securities report pursuant to Section 15G
SECURITIES AND EXCHANGE COMMISSION FORM ABS-15G Asset-backed securities report pursuant to Section 15G Filing Date: 2015-09-15 Period of Report: 2015-09-15 SEC Accession No. 0001193125-15-320457 (HTML
2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015
2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015 2015 Electric Reliability Council of Texas, Inc. All rights reserved. Long-Term Hourly Peak Demand and Energy
Results Presentation Jan-Sep 2014. November 25 th, 2014
Results Presentation Jan-Sep 2014 November 25 th, 2014 Disclaimer This document has been prepared by Grupo Isolux Corsán, S.A.; therefore no part of it may be published, disclosed or distributed in any
Residential Consumer Guide to Solar Power June 2015
Residential Consumer Guide to Solar Power 505 9 th Street NW Suite 800 Washington DC 20004 202.682.0556 www.seia.org SEIA RESIDENTIAL CONSUMER GUIDE TO SOLAR POWER Introduction How Solar Works Panels (or
U.S.A. and China Solar PV Market
U.S.A. and China Solar PV Market & PPA Solar Project Development Kevin Gao VP, CA Solar LLC [email protected] Table of Content Solar Panel Pricing & Cost Trend USA Solar Market China Solar Market
Corporate Presentation December 2013
SUSTAINABLE ENERGY CONSULTANTS Corporate Presentation December 2013 ABOUT US Company Profile Sustainable Energy Consultants is a Business Consultancy Firm specializing in Renewable Energy with a focus
Xantrex Acquisition. July 2008
Xantrex Acquisition July 2008 Disclaimer All forward-looking statements are Schneider Electric management s present expectations of future events and are subject to a number of factors and uncertainties
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted.
The image cannot be displayed. Your computer may not have enough memory to open the image, or the image may have been corrupted. Restart your computer, and then open the file again. If the red x still
Running the Electric Meter Backwards: Real-Life Experience with a Residential Solar Power System
Running the Electric Meter Backwards: Real-Life Experience with a Residential Solar Power System Brooks Martner Lafayette, Colorado University of Toledo Spring 2015 PHYS 4400 - Principles and Varieties
Residential Consumer Guide to Solar Power
Residential Consumer Guide to Solar Power 505 9 th Street NW Suite 800 Washington DC 20004 202.682.0556 www.seia.org Table of Contents Residential Consumer Guide to Solar Power... 2 Introduction... 2 How
Supported by. Energy for the Telecom Towers India Market Sizing and Forecasting
Supported by Energy for the Telecom Towers 2 Contents 1 Objectives 1 Definition 1 Executive Summary 2 Telecom Tower Market Sizing 3 Towers Connected to the Electricity Grid 3 Towers not Connected to the
Energy Efficiency in the Greek Hotel Sector November 17th, 2009, Berlin, Germany Current Situation of PV systems deployment in Greece
Energy Efficiency in the Greek Hotel Sector November 17th, 2009, Berlin, Germany Current Situation of PV systems deployment in Greece Dr. Stathis TSELEPIS, CRES, [email protected] Overview Presentation of
Solar Asset Management and Performance Monitoring: Panel-to- Grid
High Performance Monitoring Solar Asset Management and Performance Monitoring: Panel-to- Grid Justin Robinson Program Manager DAS October 1, 2012 Draker Company Overview Oldest, largest U.S. Based independent
The Real Cost of Electrical Energy. Outline of Presentation
2 Outline of Presentation Data Sources Electricity Demand and Supply Cost to Meet Demand Profile Electricity Pricing Cost Impact of Dispatching Generation (Load Following) Simplifying Assumptions Electricity
Tools for Utility-Scale PV At Your Co-op. Presented by: Paul Carroll As part of the DOE-Funded SUNDA Project
Tools for Utility-Scale PV At Your Co-op Presented by: Paul Carroll As part of the DOE-Funded SUNDA Project SOLAR UTILITY NETWORK DEPLOYMENT ACCELERATION Four year DOEfunded project to reduce co-op barriers
Business Opportunities in the Mexican PV market. September 2013 Nikolai Dobrott, Managing Partner
Business Opportunities in the Mexican PV market September 2013 Nikolai Dobrott, Managing Partner Agenda. Apricum The Cleantech Advisory The global solar market Solar market and opportunities in Mexico
How KASIKORNBANK Plans to Support Green Projects
How KASIKORNBANK Plans to Support Green Projects Clean Power Asia 29-30 April 2013, Bangkok Thongchai Kangvanchai KASIKORNBANK Pcl. 1 Content Government s Policy of Promoting Green Energy KBank s Green
Application of photovoltaic s in the building and construction industry as a power generating facility
Application of photovoltaic s in the building and construction industry as a power generating facility Matthew P. Peloso Science and Technology Business Services LLP 10 Gopeng Street, ICON #34-22 Singapore,
SunEdison Global Services. Safeguard Your Assets, Maximize Your Performance
SunEdison Global Services Safeguard Your Assets, Maximize Your Performance ASSET MANAGEMENT SOLUTIONS 2 ENSURING SAFETY, QUALITY, AND VALUE Solar technology is rapidly changing the way people work and
Proposal prepared for Happy Solar Owner
Happy Solar Owner 1234 Sunny Lane Portland, OR 97201 Mailing Address: Happy Solar Owner 1234 Sunny Lane Portland, OR 97201 RE: SolarWorld Sunkits System Proposal: CASSK-## Presented by: SolarWorld Authorized
Alternative Energy Made in Florida. Solar Power Plants for Commercial, Government, and Utility
Alternative Energy Made in Florida Solar Power Plants for Commercial, Government, and Utility L a w r e n c e H e f l e r C a r l o s G o n z a l e z I d put my money on the sun and solar energy. What
Certified Renewable Energy Project Developer
Certified Renewable Energy Project Developer Project planning and financing with a technology-specific focus Online training on economic indicators, support mechanisms and bankability. Focus on: Photovoltaic,
APPLICATIONS OF RESOURCE ASSESSMENT FOR SOLAR ENERGY
APPLICATIONS OF RESOURCE ASSESSMENT FOR SOLAR ENERGY Joseph McCabe PE ASES Fellow PO Box 270594 Littleton, CO 80127 [email protected] ABSTRACT There are many data sets and numbers quantifying the potential
California Solar Incentives. California Solar Incentives
California Solar Incentives California Solar Incentives William W. Westerfield, III Stoel Rives LLP 770 L Street, Suite 800 Sacramento, CA 95814 (916) 319-4749 The Universe of of Solar Incentives Rebate
Power Project - Debt Financing. Bill Sutherland Senior Managing Director Project Finance April 9, 2014
Power Project - Debt Financing Bill Sutherland Senior Managing Director Project Finance April 9, 2014 Project Finance Investment Manulife Project Finance Defined Principal Risks / Mitigates Challenges
MODELING DISTRIBUTION SYSTEM IMPACTS OF SOLAR VARIABILIY AND INTERCONNECTION LOCATION
MODELING DISTRIBUTION SYSTEM IMPACTS OF SOLAR VARIABILIY AND INTERCONNECTION LOCATION Matthew J. Reno Sandia National Laboratories Georgia Institute of Technology P.O. Box 5800 MS 1033 Albuquerque, NM
Solar Solutions and Large PV Power Plants. Oscar Araujo Business Development Director - Americas
Solar Solutions and Large PV Power Plants Oscar Araujo Business Development Director - Americas Solar Business of Schneider Electric The Solar Business of Schneider Electric is focused on designing and
Executive summary. - It has a favorable geographical location with significant direct solar irradiation.
Executive summary Introduction The use of solar concentrated energy in thermal applications has very little presence in Spain. In particular, the integration of solar thermal systems in district heating
Rooftop Solar Potential
Rooftop Solar Potential Distributed Solar Power in NW Massoud Jourabchi June 2013 1 Renewables made up 9% of National Energy Consumption in 2011 2 1 National Shipment of PV increasing 300,000 Nationwide
Sample Property 930 LaVergne Ln La Vergne, TN 37086
Property Report Sample Property Presented by: My Company 123 Main St Anywhere, CA 12345 Office: Mobile: Fax: You can customize the footer too! 1 Overview Sample Property Purchase Info Square Feet (2 Units)
Innovative Technology Solutions for Sustainability ABENGOA. Understanding the Value in Concessions. Analyst & Investor Day.
Innovative Technology Solutions for Sustainability ABENGOA Understanding the Value in Concessions Eduard Soler Analyst & Investor Day May 2012 1 Our Portfolio of Concessions today 2 Our Business Model
Discretionary Capital Expenditures. Discretionary Capital Expenditure. Presented by Byron Smith, CCIM
Discretionary Capital Expenditures Discretionary Capital Expenditure Presented by Byron Smith, CCIM Discretionary Capital Expenditure Case Study Overview During the holding period of a commercial real
How oversizing your array-to-inverter ratio can improve solar-power system performance
How oversizing your array-to-inverter ratio can improve solar-power system performance By Jon Fiorelli and Michael Zuercher-Martinson, Solectria Renewables, Contributors PV system designers are tasked
How To Use The Csi Ebpp Calculator
CSI EPBB Design Factor Calculator User Guide 1. Guide Overview This User Guide is intended to provide background on the California Solar Initiative (CSI) Expected Performance Based Buydown (EPBB) Design
Breakeven Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities (Report Summary)
Breakeven Cost for Residential Photovoltaics in the United States: Key Drivers and Sensitivities (Report Summary) Paul Denholm Robert M. Margolis Sean Ong Billy Roberts December 2009 NREL/PR-6A2-47248
A Decision Support Tool for the Risk Management of Offshore Wind Energy Projects
A Decision Support Tool for the Risk Management of Offshore Wind Energy Projects, Michael H. Breitner Leibniz Universität Hannover Outline for presentation Motivation and relevance Research questions Characteristics
Solar Project Pricing Index
Solar Project Pricing Index May, 2012 www.dgenergypartners.com Disclaimer The provision of a report by DG Energy Partners (DGEP) does not obviate the need for potential investors to make further appropriate
Solar Energy. Airports Going Green Aimee Fenlon
Solar Energy Airports Going Green Aimee Fenlon 1 Renewable vs. Non-Renewable Electrical Generation Renewables: Source Advantages Disadvantages Solar PV No CO2; Needs no Fuel Intermittent no power at night,
Financial Statements and Ratios: Notes
Financial Statements and Ratios: Notes 1. Uses of the income statement for evaluation Investors use the income statement to help judge their return on investment and creditors (lenders) use it to help
High Fraction Hybrid Solar in Canada s North
High Fraction Hybrid Solar in Canada s North Making $ s and Sense Now! Dave H. Gerwing B.Eng., M.Sc., P. Eng. Sr. Technical Engineer Lockheed Martin Canada [email protected] www.lockheedmartin.ca/renewables
JEDI Capital Expenditure Update
JEDI Capital Expenditure Update U.S. Offshore Wind Market and Supply Chain Workshop Presented by Aaron Smith National Renewable Energy Laboratory Brent Cooper Ocean & Coastal Consultants, Inc. 2014 Navigant
Explanation of Net Energy Metering and Annual Net Surplus Electricity Settlement Options
Explanation of Net Energy Metering and Annual Net Surplus Electricity Settlement Options Applicability This document is applicable to any City of Palo Alto Utilities ( CPAU ) Customer Generator currently
Solar and PV forecasting in Canada
Solar and PV forecasting in Canada Sophie Pelland, CanmetENERGY IESO Wind Power Standing Committee meeting Toronto, September 23, 2010 Presentation Plan Introduction How are PV forecasts generated? Solar
H1 2014 LEVELISED COST OF ELECTRICITY - PV
H1 2014 LEVELISED COST OF ELECTRICITY - PV JENNY CHASE 4 FEBRUARY 2014 LCOE OF PV, FEBRUARY 2014 1 PV EXPERIENCE CURVE, 1976-2013 (2013 $/W) 100 Cost per W (2013 $) 1976 10 1985 2003 2006 1 2012 2013 Q3
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application DWP s new Solar Partnership Program is available to help offset your investment in a PV system and get you
The Importance of Accurate Lifetime Assessment to PV Investors
The Importance of Accurate Lifetime Assessment to PV Investors Jon Previtali Wells Fargo Environmental Finance Solar Power International September 2015 Wells Fargo s Investment in Solar $1,600 350 $1,400
Commercial Outlook for Solar Power Generation
Commercial Outlook for Solar Power Generation International Conference on Alternative Energy 2010 March 27, 2010 Karachi Expo Center Nadeem Haque Nadeem Haque Energy Potential Inc. Topics 1. Market Scenario
by Ben Bourne 2009 PVSim and Solar Energy System Performance Modeling
by Ben Bourne 2009 PVSim and Solar Energy System Performance Modeling EXECUTIVE SUMMARY SunPower Corporation develops and maintains a custom photovoltaic (PV) simulation tool called SunPower PVSim for
Close the Deal with Finance. Ben Peters AEE Solar Market Analyst
Close the Deal with Finance Ben Peters AEE Solar Market Analyst Tuesday October 9, 2012 What is the Value of Solar? Sandia Labs PV Value A spreadsheet tool developed by Sandia National Laboratories It
Additional Solar System Information and Resources
Additional Solar System Information and Resources Background information a. Roughly 400 schools in NJ already have solar systems, producing more than 91 MW, out of approximately 2500 K- 12 schools in NJ.
Predicting Solar Power Production:
$1,995 Non-Member Price Free for members only Predicting Solar Power Production: Irradiance Forecasting Models, Applications and Future Prospects Steven Letendre, PhD Miriam Makhyoun Mike Taylor Green
Small PV Systems Performance Evaluation at NREL's Outdoor Test Facility Using the PVUSA Power Rating Method
National Renewable Energy Laboratory Innovation for Our Energy Future A national laboratory of the U.S. Department of Energy Office of Energy Efficiency & Renewable Energy Small PV Systems Performance
Developing solar in emerging markets
Developing solar in emerging markets Swedbank Conference March 17, 2016 Our values Predictable Driving results Change makers Working together Disclaimer The following presentation is being made only to,
TECHNICAL REPORT ZA 2015. Energy. Potential for integration of distributed solar photovoltaic systems in Drakenstein municipality
TECHNICAL REPORT ZA 2015 Energy Potential for integration of distributed solar photovoltaic systems in Drakenstein municipality EXECUTIVE SUMMARY Using Drakenstein Municipality as a case study, this report
Update on Austin Energy Solar and Leasing
Update on Austin Energy Solar and Leasing Presentation to CCAE December 4, 2014 Filename, Version 1 Local Solar Growth 2004 2014 25,000 20,000 kw ac Customer Sited Solar Installed (does not include Webberville)
INTEGRATION OF PV IN DEMAND RESPONSE PROGRAMS
INTEGRATION OF PV IN DEMAND RESPONSE PROGRAMS Prepared by Richard Perez et al. NREL subcontract # AEK-5-55057-01 Task # 2, Deliverable # 2 Robert Margolis, Project Manager ABSTRACT This article makes the