AN EXAMINATION OF THE RISK MANAGEMENT PROCESS IN VENEZUELAN CONSTRICTION PROJECTS
|
|
|
- Laurence Lamb
- 9 years ago
- Views:
Transcription
1 AN EXAMINATION OF THE RISK MANAGEMENT PROCESS IN VENEZUELAN CONSTRICTION PROJECTS Erika Calzadilla, Kenneth Awinda and Anna Parkin School of Civil Engineering and Surveying, University of Portsmouth, Portland Street, Portsmouth, PO1 3AH, UK. The construction industry has many sources of risk some of which can be attributed to the complexity of processes, the environment of construction projects, financial aspects, organizational structures and technology usage. In the success of construction projects, the importance of identifying and managing risks is widely acknowledged. Delays in time and cost overrun have become the most common risks facing the industry worldwide. However, they are particularly prevalent in developing countries where adversities such as shortage of materials, lack of management skills, unskilled labour as well as socio economic and political problems must be dealt with; all of which make construction projects more difficult to manage. Interviews with project managers responsible for projects in the public and private sectors were carried out in order to evaluate their perception of risks, how they manage these risks and the effects of the risks on their projects. The results of the investigation show the main sources of risk identified relate to: the risk management process; organizational structure; labour unions; and economic factors. For example, the Venezuelan construction companies face risks as a result of the current economic situation brought about by the currency exchange controls applied 10 years ago. This is causing a negative impact on the procurement and costs of construction projects. This paper explains how these factors are managed and their impact on time and cost. One of the recommendations proposed as a way of improving the risk management process in Venezuelan construction projects is to assess the internal processes and organizational structure of project management companies. This will aid advanced identification of the sources of risk in order to allow timely decision making. Keywords: organizational structure, risk management, sources of risk, time delays. INTRODUCTION The construction industry has to deal with constant change due to its dynamic environment and, as a consequence, has to face many risks (Ofori, 2000). A study by Baloi & Price, (2003) shows that risk factors are present in all construction projects everywhere. In fact, delays in time and cost overruns have become the most common risks facing the construction industry worldwide according to Raftery (1994), (as cited in Baloi & Price, 2003). It is important for the stakeholders involved such as clients, owners, contractors, project managers, etc., to deal with these apparent risks because the construction industry brings many benefits for the economies of countries and the value of the domestic construction enterprises (Ofori, 2000). Calzadilla E; Awinda K and Parkin A (2012) An examination of the risk management process in Venezuelan constriction projects In: Smith, S.D (Ed) Procs 28 th Annual ARCOM Conference, 3-5 September 2012, Edinburgh, UK, Association of Researchers in Construction Management,
2 Calzadilla, Awinda and Parkin This research aims to identify the key sources of risk faced by Venezuelan construction projects and explain how they were managed. Furthermore, the Venezuelan construction companies may have to face risks as a result of the current economic situation, especially with the currency exchange control applied 10 years ago which causes a negative impact in areas such as procurement and costs within construction projects (Bascaran, 2003). This research is based on different kinds of construction projects developed in Venezuela for public and private clients. This study also reflects the current risk management doctrine adopted by Venezuelan companies, and shows the crucial role that such aspects as planning, scheduling and risk management have on construction projects. Finally this research attempts to find a framework for improving the risk management process in construction projects for this country. LITERATURE REVIEW The concept of risk has been explained by researchers such as Baloi and Price (2003) aims in terms of cost, time and quality. Authors such as Perry & Hayes (1985) and Porter (1981) indicated that risks are the economic losses or gains within the construction environment, while Manson (1973) and Moanvenzadeh (1979) argue that risk is just about loss (as cited in Akintoye & Macleod, 1997). On the other hand, Winch (2010) explains the concept of risk is based on four schools of thought. 1. Objectivist school: the likelihood of an event happening can be predicted from previous occurrences of a similar event in the past. 2. Logical school: engineers use logic to identify risk sources and their likelihood because they do not have enough data or limited data do so, during the design and construction system. 3. Subjectivist school: based on the experience and expertise, or belief, of the life cycle. 4. Behavioural school: the decisions are made based on human behaviours. The fact that risk is very much related to the likelihood of an event happening, leads to the necessity of implementation of risk management processes by project managers. As a consequence, there is a very close relationship between the behaviour, experience, and education of project managers and the way they deal with risk factors. THE RISK MANAGEMENT PROCESS The risk management process has become an important activity in the construction industry. According to Akintoye & Macleod (1997), it is important for minimising losses and increasing profits. At the same time, it can also be seen as a tool to reduce the chance of failure or to maximise opportunities in the projects (Loosemore et al. 2006). However, for a more practical understanding of this concept, this research uses a simple framework to explain the risk management process as: risk identification, risk analysis and risk response (Raftery, 1994). Risk Identification: Through this stage the potential risks affecting construction projects can be identified. However, the careless way in which this process is undertaken in many construction companies is one of the causes of failure of construction projects (Loosemore et al. 2006). Moreover, the nature of risks could be 1210
3 Risk Management internal and/or external. Consequently, the identification process should be carried out by a professional with enough experience (Raftery, 1994), as if a risk is not identified in early stages, it will be handled in a reactive way, rather than a proactive manner (Loosemore et al. 2006). Risk Analysis: Through the analysis it is possible to identify the scale of the risk, which areas of the project will be affected, what the possible responses could be and the necessary resources required to face the risks (Loosemore et al. 2006). Risk Response: According to PMI, (2004, p. 260),"risk response is the process of developing options and determining actions to enhance opportunities and reduce Nevertheless, risks cannot be eliminated; the challenge is identifying, assessing and managing them effectively (Loosemore et al. 2006). Therefore, Willians (1995) risks as well as the manner in which project managers in Venezuelan companies carry out risk management processes. Thus, any inconsistency between the knowledge and the application of risk management skills by project managers and contractors can be determined. In some cases there is a lack of adequate knowledge in this field in the construction industry (Mulholland & Christian, 1999; Flanagan & Norman, 1993). This view is supported by Baloi & Price (2003) who argue that contractors in developing countries do not have enough experience and knowledge to deal with risk factors. They also identify the consequences of these factors through the outcomes in construction projects such as: delays in completion, deficient cost performance and bad quality. A study by Bascaran (2003), found that just 4% of the civil engineers in Venezuela have got a masters degree in construction project management. As a consequence, there is a shortage of skilled staff in this field. It is important to highlight, that from the data gathered for this study, there is a lack of knowledge in Venezuelan companies, about how to carry out the risk analysis process which would account for the outcomes related to time and costs in construction projects. SOURCES OF RISK AND CLASSIFICATION A study by Zou, Zhang, & Wang (2007) states that the primary sources of risk are two: internal, related to the type of project; and external, associated with the environment in which the project is developed. Zhi (1995) reinforces this assertion stating that external factors are those linked with the national and regional market or local construction industry, and the internal factors are those related to the behaviour of the companies and that intrinsic to the project. Zhi (1995) also identified that in developing countries, projects are significantly influenced by external factors such as economic, political and social issues, meaning that the risk management process is affected by several sources of risk at the same time. Although it is true that there are different classifications of risks in developing countries, Bascaran (2003), who conducted a study in Venezuela in relation to risk in construction project management, reveals that the main risks in this country are: design changes, organizational structure, shortage of material and lack of knowledge in risk management. 1211
4 Calzadilla, Awinda and Parkin Delays in construction projects Many studies have been undertaken in order to identify the causes of time delays in construction projects. Laufer & Tucker (1987), claim that time delays are the result of inadequate managerial actions. In contrast, other researchers (Assaf & Al-Hejji,2006; Zou, Zhang, & Wang,2007; and Odeh & Bataineh, 2002) state that the main causes of time delays originate from internal and external sources such as design variations, poor labour productivity, unpredictable weather conditions, shortage of skilled labour, inappropriate planning, project complexity, poor project scope definition and shortage of materials. A study by Gonzalez (2010) reveals that delays in Venezuelan construction projects are caused by internal factors, such as poor quality of the programme and project scheduling, shortage of skilled staff, lack of management skills and design changes. Organizational structure The way in which the goals of a construction project are accomplished is linked to organizational structure; how people work together, the way that work flows and the line of decision making in an organization (Martin & Martin, 2010). However, the organizational target is addressed by humans, so human behaviour greatly influences the way in which risks are identified and dealt with. As a result of the close relationship between human behaviour and organizational structures, companies can face structural deficiencies such as: slow and poor quality decision making; conflict and lack of coordination; and rising costs. Moreover, according to Ogunlana & Olomalaiye (1989) the deficiencies of organizational structures of companies in developing countries happen because most of them are managed by entrepreneurs who are in the business of making money at the expense of good management. According to Loosemore et al. (2006), there are two main organizational structures: mechanistic and organic. Mechanistic structure is characterized by centralise decision making, vertical communications, rigid rules and procedures, whilst, organic structure is characterized by decentralise decision making, lateral communication and few rigid rules and procedures. Guerra (2006), who studied a construction company in Venezuela, found that organizational structure and human behaviour had an important influence on the risk management process. The organizational structure of companies would seem to be a significant factor and, therefore, it will be discussed in this research. METHODOLOGY AND DATA COLLECTION As the aim of this research is to identify risks and explain how they are managed in Venezuelan construction projects, rather than test a hypothesis, an inductive approach was adopted. This was implemented using a case study strategy which was useful in gaining detailed information about a small number of cases (Robson, 2002). This to issues behind the reality. Qualitative data was sought for this research in order to obtain different points of view of the subject studied (Saunders et al. 2003). This was important in this management research, not only because of the complex subject matter, analysing risk management, but also because the situation within different cases studies may be unique (Saunders et al. 2003). Semi-structured interviews were also undertaken enabling the researcher to explore chance to surface using other methods (Saunders et al. 2003). 1212
5 Risk Management Case studies Three construction projects were selected each with different characteristics. Interviews were conducted with project managers from each case. The questions were divided into three sections. The first section sought to discover what risks were faced on a project and how they were identified. The second section was focused on the risk management process, the organizational structure of the companies involved and the decision making process. This was in order to obtain a general idea about how risks were managed. The last section was concerned with the effects of risks on the projects. For the development of this paper the real names of the projects as well as the names of the interviewees have been kept anonymous. The three case study projects are summarised in Table 1. Table 1: Case studies Project Type of Project Area Description Client Date Project 1 Hypermarket 11,600 m2 Mixed structure of reinforced concrete and steel Project 2 Bank Headquarters 30,000 m2 Mixed structure of reinforced concrete and steel Private Private Project 3 Housing Development 11,100 m2 Concrete reinforced structure. Block of flats were built using Tunnel Formwork system Public Tables 2 and 3 present a summary of the results obtained through semi-structured interviews of the relevant project managers. Table 2: Main topics of the interviews and results Theme Research Questions Results Risk Identification Risk Management Process Definition of risk Tools and techniques used to identify risks Organizational structure of main contractors Risks management process undertaken Decision making process PMs perceive risks as any event can affect the time, cost and quality of the projects. They did not apply any formal method to identify risks in advance. PMs mainly used their experience to solve problems as they arose. Most main contractor companies did not have structured departments such as planning, budgets, procurement of material. Only one company had a departmental structure but they did not have skilled staff to manage them Mostly reactive or applied in an empirical way to face risks. The decision making was carried out by the owners of the companies. 1213
6 Calzadilla, Awinda and Parkin Table 2: Main topics of the interviews and results Theme Research Questions Results Risk Management process Tools and techniques applied for planning and tracking the activities of the projects The planning process activity was developed using Microsoft project software. Effects of risks Effects of risks on time Time delays (See Table 4). Other areas affected by risks Costs overrun. Poor quality and low productivity in projects. Table 3: Risks and sources identified Source Risks Identified Source Risks Identified Designers Political and economic situation Subcontractors Owners Projects incomplete Labour union, foreign exchange control Shortage of materials Unskilled labours Slow decision making Main Contractors Organizational structure problems Centralised decision making Deficiencies in risks management process Poor quality of planning and scheduling Deficiencies in internal process The impact on time in the three cases is shown in Table 4. Table 4: Time delays of case studies Project Estimated Time Delivered Time Exceeded Time Date Project 1 17 months 22 months 5 months Project 2 14 months 24 months 10 months Project 3 9 months 24 months 15 months LIMITATION It is important to highlight that the philosophy chosen for this research allowed only a small sample to be taken to meet the stated objectives. The interviews were carried out with key practitioners such as project managers, who provided the specific information to document this research. Furthermore, it can be stated that at least in these three case studies broadly similar sources of risks and risk management problems were found. However, it is not the intention of this research to generalize these factors to all the projects in Venezuela, as it is obvious that external factors like social, political and economic aspects have an important influence in the source of risks in Venezuela. These may have variations over time, and they can produce different effects in construction projects. DATA ANALYSIS The analysis of this research report is focused on two main areas: source of risks and risk management process. Therefore, after identifying the risks in the data collection 1214
7 Risk Management section, they were classified using as a basis the studies developed by Zou et al. (2007) and Wang et al. (2004), which stated that the sources of risk can be classified as external and internal. Figure 1 shows the sources of risks obtained in this research and their effects. Figure 1: Sources of risks and their effects in Venezuelan construction projects This classification is a result of the analysis based on the opinion of project managers on risks in each case study. There were risks which were the result of organizational structure or behaviour of the people linked to the projects, that is, internal source of risks, and there were other risks that affected the projects as a consequence of external factors. Organizational structure and human behaviour have an important role in construction projects, because they are the basis of the risk management process (Willians, 1995); the success of the construction projects depends mainly on these factors. It was found that project management companies faced these internal problems in the three case studies presented in this research. The project management companies studied can be identified as having a mechanistic organizational structure (Loosemore, et al. 2006) as they used a centralised decision- not have structured departments with strong functional identities. This fact can be attributed to the size of the companies; Project 1 and Project 2 were carried out by small companies, whereas Project 3 was carried out by a medium size company. Furthermore, it can be said, that organizational structure and human behavioural factors were important in these cases. This research stated that the perception of risk adopted by the project manager was from the subjectivist school. Consequently, risks were faced in a reactionary way rather than in an anticipatory manner. Therefore, risks were perceived according to the experience or beliefs of project managers (Loosemore 1215
8 Calzadilla, Awinda and Parkin et al. 2006). What is more, the organization always managed the crisis rather than preventing them, and did not fully understand how human behaviour can affect perception of risks and therefore their impact on projects. These statements are supported by interviewed project managers, who agreed that they had not developed a risk management plan before the project execution phase. In addition to this, it was found that the project managers perceived a scheduling programme as a tool to predict and monitor risks. A scheduling programme can be classified as a good tool to monitor time and resources but it is not enough to manage risks. Essentially risks were managed in an empirical manner in these case studies. All these case studies were affected by the foreign exchange currency control applied in Venezuela since Therefore, the main areas affected by this source of risk were procurement of material and equipment which increased the costs. In some cases the contractors had to buy the construction products through the parallel foreign exchange market, as a result of the inefficient exchange regulation applied by the national government. Another external source of risk was the impact of the labour union on construction projects in Venezuela that has roots in political, social and economic factors. The construction industry has been impacted by this situation, as a result of the new labour legislation since 2007 which states that 75% of the workforce must be provided by the labour unions. Quality, time and costs have been negatively affected in construction projects because the majority of the workers are unskilled, resulting in low productivity. This last fact could be verified in the sample of cases studied, as the projects were constructed between 2002 and As shown in Table 4, Project 2 finished in nearly double the time that had been originally estimated and Project 3 finished in more than double the time while Project 1 had the shortest delay on time. It can be argued that poor risk management processes, the lack of knowledge or the lack of effective tools and techniques to handle risk were the fundamental causes of delays in these construction projects. However, costs and quality were other areas which were also impacted as consequences of delays in construction projects, according to the results obtained in the interviews with project managers. It can be argued that the time delays and cost overruns experienced by construction projects in Venezuela are linked, to the risk management process undertaken which has many technical deficiencies and is greatly influenced by human behaviours. Therefore, the final results are exceeded time and costs overruns. CONCLUSION The main sources of risks that the three different case study projects faced were identified as internal and external. As was mentioned earlier, the significant internal sources identified include organizational structure, poor risk management process, unskilled staff, slow decision making, design changes, and poor quality of contractors. External source of risk as stated by Zhi (1995) arise from political, economic and social environments in developing countries. As a consequence in Venezuela economic factors such as foreign currency exchange control and inflation have affected costs of projects due to the material and equipments prices. Social factors such as unskilled labour have had an impact on quality and productivity. Similarly political factors, such as nationalization of basic industries, have caused shortages of 1216
9 Risk Management materials, while the increasing influence of labour unions in Venezuela in the last 10 years have reduced productivity in construction. These projects also show the empirical way in which risks were managed, how some factors, such as organization structure and human behaviour, have an important According to the findings of this research, based on a qualitative analysis, it is important to improve areas such as risk management process and Organizational structure, which can be considered as the basis of a successful project. Adopting suitable organizational structures in the project management and contractor companies would be a good first step to achieving success. In this way, the organizations should assess their internal processes in order to improve procedures for decision making, which was one of the areas that showed clear deficiencies in this study. Also, organizations should provide their staff with training in the management field to underpin their strengths and minimise their weaknesses and thus get better results in terms of time, cost and quality of projects. Human behaviour and its influence on projects is another important aspect to be analysed and improved within the organizations in Venezuela because it would allow project managers and owners to modify their judgements and their perception of risk and thus help them respond properly to risks, rather than in a reactive manner. The sources of risks can be predicted in advance and their impact assessed allowing project managers and clients to make timely decisions to reach the objectives of the project. Finally, it can be said that with an adequate risk management process and a good organizational structure, both internal and external risks and their impact on projects can be mitigated. REFERENCES Akintoye, A. S., & Macleod, M. J. (1997). Risk analysis and management in construction. International Journal of Project Management, 15, Assaf, S. A., & Al-Hejji, S. (2006). Causes of delays in large construction projects. International Journal of Project Management, 24, Baloi, D., & Price, A. D. (2003). Modelling global risk factors affecting construction cost performance. International Journal of Project Management, 21, Bascaran, E. (2003). Evaluacion del Uso de la Gerencia del Tiempo en la Gerencia de Proyectos en Venezuela [ Assessing the use of Time Management in Venezuelan Projects]. Caracas: Unpublished Master Dissertation. Catholic Andrés Bello University. Flanagan, R., & Norman, G. (1993). Risk Management and Construction. Oxford: Blackwell Scientific. Gonzalez, M. (2010). Propuesta de Mejoras de la Gestión de Tiempo del Departamento de Proyectos de la Empresa Arturo Arenas [ A framework to improve the time management of project s department in Arturo Arenas company]. Caracas: Unpublished Master Dissertation of Catholic Andrés Bello University. Guerra, A. (2006). Diagnostico de los aspectos organizacionales en una compañía de construcción venezolana [ A study of the organizational structure in a Venezuelan construction company]. Caracas: Unpublished Master Dissertation of Catholic Andres Bello University. 1217
10 Calzadilla, Awinda and Parkin Laufer, A., & Tucker, R. (1987). Is construction planning really doing its job? A critical examination of focus, role and process. Construction Management and Economies, 5 (3), Loosemore, M., Raftery, J., Reilly, C., & Higgon, D. (2006). Risk Management in Projects. 2nd. London: Taylor & Francis. Martin, J., & Martin, F. (2010). Organizational Behaviour & Management. Andover: Cengage Learning EMEA. Mulholland, B., & Christian, J. (1999). Risk assessment in construction schedules. Journal of Construction Engineering and Management, 125 (1), Odeh, A., & Bataineh, H. (2002). Causes of construction delays: traditional contracts. International Journal of Project Management, 20, Ofori, G. (2000). Challenges facing the construction industry in developing countries. 2nd International Conference on Construction in Developing Countries (págs. 1-11). Gaborone: Printing and Publishing Company (Pty) LTD. Ogunlana, S. O., & Olomalaiye, P. (1989). A survey of site management practice on some selected sites in Nigeria. Building Environ, 24, Perry, J., & Hayes, R. (1985). Risks and its management in construction projects. Proceedings of Institution of Civil Engineers, Part 1., 78, PMI. (2004). A Guide to the Project Management Body of Knowledge, PMBOK Guide, third edition. Pennsylvania: Project Management Institute, Inc. Porter, C. (1981). Risk Allowance in Construction Contracts. Unpublished MSc. project report. Manchester: University of Manchester. Raftery, J. (1994). Risk Analysis in Project Management. London: E & FN Spon. Robson, C. (2002). Real World Research: a resource for social scientist and practitioners. 2nd ed.. Oxford: Blackwell. Saunders, M., Lewis, P., & Thornhill, A. (2003). Research Methods for Business Students. Third Edition. Essex: Pearson Education Limited. Wang, S. Q., Dulaimi, M. F., & Aguria, M. Y. (2004). Risk management framework for construction projects in developing countries. Construction management and economics, 22, Willians, T. (1995). A classified biography of recent research relating to project risk management. European Journals of Operational Research, 85, Winch, G. M. (2010). Managing Construction Projects. Chichester: Wiley-Blackwell. Zhi, H. (1995). Risk management for overseas construction projects. International Journal of Project Management, 13 (4), Zou, P. X., Zhang, G., & Wang, J. (2007). Understanding the key risk in construction projects in China. International Journal of Project Management, 25,
Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry
CIB World Building Congress 2007 549 CIB2007-370 Project Risk Management in Oman: A Survey of Risk Practices in the Construction Industry Dr Tabarak Ballal 1, Dr Taha Elhag 2 and Mr Salim Ambusaidy 3 1
Using Risk Assessment to Improve Highway Construction Project Performance
Using Risk Assessment to Improve Highway Construction Project Performance Mohamed F. Diab, MBA, Ph.D. and Amiy Varma, Ph.D., PE North Dakota State University Fargo, ND Khaled Nassar, Ph.D. American University
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT
CONTRACT DOCUMENTS IS EFFECTIVE TOOL FOR RISK MANAGEMENT Chaitali S. Pawar 1, Suman S. Jain 2, Abhijeet M. Gaikwad 3 1 Post Graduate Student, RMDSSOE, Pune, India. Email: [email protected] 2 Asso.
INVESTORS IN PEOPLE: WHAT S IT ALL ABOUT? Sue Greener and Tom Bourner
INVESTORS IN PEOPLE: WHAT S IT ALL ABOUT? Sue Greener and Tom Bourner Sue Greener and Tom Bourner, May 2005 Brighton Business School University of Brighton Occasioal/Working Paper Series Working Paper
2 Business, Performance, and Gap Analysis
2 Business, Performance, and Gap Analysis The performance consulting process generally includes identifying business needs, performance needs, and work environment and capability needs. All strategic performance
Review of Business Information Systems Second Quarter 2009 Volume 13, Number 2
An Investigation Into Computerized Estimating Software Used In Accounting For Cost Estimates By Residential Builders Mark D. Law, Bloomsburg University, USA Gary S. Robson, Bloomsburg University, USA ABSTRACT
Achieve. Performance objectives
Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.
Six Sigma, ISO 9001 and Baldrige
Six Sigma, ISO 9001 and Baldrige Many organizations ask How Do these programs, processes and standards support each other? These initiatives are not mutually exclusive, in fact, understanding and applying
Employer Demand for Qualifications for Sales Professionals
Employer Demand for Qualifications for Sales Professionals Chichester CWL Development Fund Project Final Report Prepared by: Sandra Coley Business Development Manager 24 th June 2011 Contents Page 1. Introduction
Steel procurement in major projects: Guidance on the application of social issues. Purpose
Steel procurement in major projects: Guidance on the application of social issues Purpose 1. This is a practical guide on how to incorporate social issues in major projects with a significant steel component.
WARSAW SCHOOL OF ECONOMICS
WARSAW SCHOOL OF ECONOMICS mgr Ewelina Florczak The summary of doctoral dissertation THE TITLE SOCIAL ENTERPRISE IN LOCAL ENVIRONMENT 1 Rationale topic A social enterprise as a business entity is subject
Competency profiling: definition and implementation
Competency profiling: definition and implementation By Stephen Shellabear, Consultant at ConsultSeven Author s Biography Steve Shellabear is a consultant at ConsultSeven. He holds a M.Sc. in Change Agent
Causes, Effects and Minimization of Delays in Construction Projects
Causes, Effects and Minimization of Delays in Construction Projects Divya.R 1, S.Ramya 2 Assistant Professor Department of Civil Engineering Bharathiyar Institute of Engineering for Women, Deviyakurichi
360 feedback. Manager. Development Report. Sample Example. name: email: date: [email protected]
60 feedback Manager Development Report name: email: date: Sample Example [email protected] 9 January 200 Introduction 60 feedback enables you to get a clear view of how others perceive the way you work.
PERCEPTION OF BASIS OF SHE AND SHE RISK MANAGEMENT
PERCEPTION OF BASIS OF SHE AND SHE RISK MANAGEMENT Per Berg and Roger Preston Safety Section, Global SHE, AstraZeneca INTRODUCTION After the merger between the two pharmaceutical companies Astra and Zeneca
# # % &# # ( # ) + #, # #./0 /1 & 2 % 3 4 2 5 3 6 6 7 & 6 4 & 4 # 6 76 /0 / 6 7 & 6 4 & 4 # // 8 / 5 & /0 /# 6222 # /90 8 /9: ; & 0 0 6 76 /0 /!<!
! # # % &# # ( # ) + #, # #./0 /1 & 2 % 3 4 2 5 3 6 6 7 & 6 4 & 4 # 6 76 /0 / 6 7 & 6 4 & 4 # // 8 / 5 & /0 /# 6222 # /90 8 /9: ; & 0 0 6 76 /0 /!
Preventive Maintenance Characteristics towards Optimal Maintenance Performance: A Case Study of Office Buildings
/ World Journal of Engineering and TechnoloiY, 2014, 2, 1-6 Published Online September 2014 in SciRes. http://www.scirp.org/journal/wjet http://dx.doi.org/l0.4236/wjet.2014.23bool ++;:. Scientific :. Research
Challenges of Intercultural Management: Change implementation in the context of national culture
12-ICIT 9-11/4/07 in RoC Going for Gold ~ Best Practices in Ed. & Public Paper #: 07-08 Page- 1 /7 Challenges of Intercultural Management: Change implementation in the context of national culture Prof.
Name Chapter 1: Introduction to Project Management Description Instructions
Name Chapter 1: Introduction to Project Management Description Instructions Modify Question 1 / 0 points Modify Remove Question Until the 1980s, project management primarily focused on providing schedule
Multiproject Scheduling in Construction Industry
Multiproject Scheduling in Construction Industry Y. Gholipour Abstract In this paper, supply policy and procurement of shared resources in some kinds of concurrent construction projects are investigated.
Summary of the Master Thesis. Implementation of Business Ethics in International Construction Projects
Summary of the Master Thesis Master s Degree International Project Management (Building, Real Estate and Infrastructure) Implementation of Business Ethics in International Construction Projects The Perception
Business Continuity Policy. Version 1.0
Business Continuity Policy Version.0 January 206 Contents Contents Version control Foreword Policy. Scope.2 Aim and objectives.3 Methods and standards.4 Responsibilities.5 Governance.6 Training and exercises
Reforming the UK border and immigration system
Report by the Comptroller and Auditor General Home Office Reforming the UK border and immigration system HC 445 SESSION 2014-15 22 JULY 2014 4 Key facts Reforming the UK border and immigration system Key
DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY
DERBYSHIRE COUNTY COUNCIL BUSINESS CONTINUITY POLICY VERSION 1.0 ISSUED JULY 2015 CONTENTS Page CONTENTS VERSION CONTROL FOREWORD i ii iii POLICY 1 Scope 1 Aim and Objectives 1 Methods and Standards 1
European Commission: Business Insurance Sector Inquiry. Interim Report Consultation Response. Brighter Business Limited
European Commission: Business Insurance Sector Inquiry Interim Report Consultation Response Introduction Brighter Business Limited Brighter Business was created to provide a direct service for Small and
The labour market, I: real wages, productivity and unemployment 7.1 INTRODUCTION
7 The labour market, I: real wages, productivity and unemployment 7.1 INTRODUCTION Since the 1970s one of the major issues in macroeconomics has been the extent to which low output and high unemployment
The Importance of Trust in Relationship Marketing and the Impact of Self Service Technologies
The Importance of Trust in Relationship Marketing and the Impact of Self Service Technologies Raechel Johns, University of Canberra Bruce Perrott, University of Technology, Sydney Abstract Technology has
PM in construction industry
PM in construction industry Construction 2. Lepel BME Department of Construction Technology and Management 19-03-2014 PM in general Project integration Project plan development Project plan execution Integrated
Shared service centres
Report by the Comptroller and Auditor General Cabinet Office Shared service centres HC 16 SESSION 2016-17 20 MAY 2016 4 Key facts Shared service centres Key facts 90m estimated savings made to date by
Grounded Theory. 1 Introduction... 1. 2 Applications of grounded theory... 1. 3 Outline of the design... 2
Grounded Theory Contents 1 Introduction... 1 2 Applications of grounded theory... 1 3 Outline of the design... 2 4 Strengths and weaknesses of grounded theory... 6 5 References... 6 1 Introduction This
Building Public Trust: Ethics Measures in OECD Countries
Building Public Trust: Ethics Measures in OECD Countries Annex 1998 Recommendation of the OECD Council on Improving Ethical Conduct in the Public Service, 36 Including Principles for Managing Ethics in
Assessment Policy. 1 Introduction. 2 Background
Assessment Policy 1 Introduction This document has been written by the National Foundation for Educational Research (NFER) to provide policy makers, researchers, teacher educators and practitioners with
If Your HR Process is Broken, No Technology Solution will Fix It
If Your HR Process is Broken, No Technology Solution will Fix It Joyce Y. Quindipan, Partner, Cambria Consulting Audit and align your HR processes before you invest in and implement a At the HR Technology
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
Barriers to the implementation of Integrated Marketing Communications: The client perspective.
Barriers to the implementation of Integrated Marketing Communications: The client perspective. Discussions on Integrated Marketing Communications (IMC) in the academic and practitioner journals are gradually
Project management skills for engineers: industry perceptions and implications for engineering project management course
Project management skills for engineers: industry perceptions and implications for engineering project management course Kriengsak Panuwatwanich Griffith University, Gold Coast, Australia [email protected]
SUCCESSFUL INTERFACE RISK MANAGEMENT FROM BLAME CULTURE TO JOINT ACTION
SUCCESSFUL INTERFACE RISK MANAGEMENT FROM BLAME CULTURE TO JOINT ACTION SUMMARY Axel Kappeler, Principal James Catmur, Director Interfaces are important because they are everywhere. However, interfaces
DEVELOPING A MODEL FOR PLANNING AND CONTROLLING PRODUCTION IN SMALL SIZED BUILDING FIRMS
Developing a Model for Planning and Controlling Production in Small Sized Building Firms DEVELOPING A MODEL FOR PLANNING AND CONTROLLING PRODUCTION IN SMALL SIZED BUILDING FIRMS Carlos T. Formoso 1, Maurício
Helping consumers to manage their money
Report by the Comptroller and Auditor General Money Advice Service Helping consumers to manage their money HC 879 SESSION 2013-14 5 DECEMBER 2013 4 Key facts Helping consumers to manage their money Key
Risk Management & Business Continuity Manual 2011-2014
ANNEX C Risk Management & Business Continuity Manual 2011-2014 Produced by the Risk Produced and by the Business Risk and Business Continuity Continuity Team Team February 2011 April 2011 Draft V.10 Page
Major IT Projects: Continue Expanding Oversight and Strengthen Accountability
Secretary of State Audit Report Jeanne P. Atkins, Secretary of State Gary Blackmer, Director, Audits Division Major IT Projects: Continue Expanding Oversight and Strengthen Accountability Summary Information
IT strategy. What is an IT strategy? 3. Why do you need an IT strategy? 5. How do you write an IT strategy? 6. Conclusion 12. Further information 13
IT strategy made simple What is an IT strategy? 3 Why do you need an IT strategy? 5 How do you write an IT strategy? 6 step 1 Planning and preparation 7 step 2 Understanding your organisation s IT needs
Writing a degree project at Lund University student perspectives
1 Writing a degree project at Lund University student perspectives Summary This report summarises the results of a survey that focused on the students experiences of writing a degree project at Lund University.
Risk analysis and management in construction
Pergamon International Journal of Project Management Vol. 15, No. 1, pp. 31-38, 1997 Copyright 1996 Elsevier Science Ltd and IPMA Printed in Great Britain. All rights reserved 0263-7863/96 $17.00 + 0.00
The Office of Public Services Reform The Drivers of Satisfaction with Public Services
The Office of Public Services Reform The Drivers of Satisfaction with Public Services Research Study Conducted for the Office of Public Services Reform April - May 2004 Contents Introduction 1 Executive
Research and Innovation Strategy: delivering a flexible workforce receptive to research and innovation
Research and Innovation Strategy: delivering a flexible workforce receptive to research and innovation Contents List of Abbreviations 3 Executive Summary 4 Introduction 5 Aims of the Strategy 8 Objectives
Dr Rosie Tope and Dr Eiddwen Thomas and Dr Suzanne Henwood. Introduction
Measuring the impact of NLP Communication Seminars on clinical practice in nursing: An evaluation using the Henwood CPD (Continuing Professional Development) Process Model Dr Rosie Tope and Dr Eiddwen
ICT in pre-service teacher education in Portugal: trends and needs emerging from a survey
Interactive Educational Multimedia, Number 11 (October 2005), pp. 153-167 http://www.ub.es/multimedia/iem ICT in pre-service teacher education in Portugal: trends and needs emerging from a survey João
TRANSPORT FOR LONDON CORPORATE PANEL
AGENDA ITEM 4 TRANSPORT FOR LONDON CORPORATE PANEL SUBJECT: EMPLOYEE ENGAGEMENT DATE: 17 NOVEMBER 2009 1 PURPOSE AND DECISION REQUIRED 1.1 The purpose of this report is to advise the Panel on TfL s approach
The Purpose of PR 2016
The Purpose of PR 2016 Research Report Contents Introduction Key findings Purpose of PR Tactics Budget Social media, SEO Media Relevance and importance of PR INTRODUCTION FROM XANTHE VAUGHAN WILLIAMS PR
PH.D THESIS ON A STUDY ON THE STRATEGIC ROLE OF HR IN IT INDUSTRY WITH SPECIAL REFERENCE TO SELECT IT / ITES ORGANIZATIONS IN PUNE CITY
ABSTRACT OF PH.D THESIS ON A STUDY ON THE STRATEGIC ROLE OF HR IN IT INDUSTRY WITH SPECIAL REFERENCE TO SELECT IT / ITES ORGANIZATIONS IN PUNE CITY SUBMITTED TO THE UNIVERSITY OF PUNE FOR THE AWARD OF
Managerial Decision Making when values take over rational economical thought
Student Self-administered case study Managerial Decision Making when values take over rational economical thought Case duration (Min): 45-60 Principles of Management (PoM) Organizational Behaviour (OB)
A Theoretical Perspective on Leadership Development in the Construction Industry
A Theoretical Perspective on Leadership Development in the Construction Industry Abstract Murendeni Liphadzi 1, Clinton Aigbavboa 2, and Wellington Thwala 3 The construction industry is one of the largest
DATA QUALITY ASPECTS OF REVENUE ASSURANCE (Practice Oriented)
DATA QUALITY ASPECTS OF REVENUE ASSURANCE (Practice Oriented) Katharina Baamann MioSoft [email protected] Abstract: Revenue Assurance describes a methodology to increase a company s income
The Academic Collocation List
The Academic Collocation List # Addition Component I POS I Component II POS II Addition 1 abstract adj concept n 2 academic adj achievement n 3 academic adj career n 4 (in) academic adj circles n 5 academic
Ealing, Hammersmith and West London College
FURTHER EDUCATION COMMISSIONER ASSESSMENT SUMMARY Ealing, Hammersmith and West London College JANUARY 2016 Contents Assessment... 3 Background... 3 Assessment Methodology... 3 The Role, Composition and
BSO Board Director of Human Resources & Corporate Services Business Continuity Policy. 28 February 2012
To: From: Subject: Status: Date of Meeting: BSO Board Director of Human Resources & Corporate Services Business Continuity Policy For Approval 28 February 2012 The Board is asked to agree the attached
Disability Employment Services Quality Framework Advice V 2.0
Disability Employment Services Quality Framework Advice V 2.0 Disclaimer This document is not a stand-alone document and does not contain the entirety of Disability Employment Services Providers' obligations.
Risk Allocation in Public-Private Partnership (PPP) Projects for Wastewater Treatment Plants
Risk Allocation in Public-Private Partnership (PPP) Projects for Wastewater Treatment Plants Samuel Capintero, Ole H. Petersen Abstract This paper examines the utilization of public-private partnerships
7 Directorate Performance Managers. 7 Performance Reporting and Data Quality Officer. 8 Responsible Officers
Contents Page 1 Introduction 2 2 Objectives of the Strategy 2 3 Data Quality Standards 3 4 The National Indicator Set 3 5 Structure of this Strategy 3 5.1 Awareness 4 5.2 Definitions 4 5.3 Recording 4
PESTLE TECHNIQUE A TOOL TO IDENTIFY EXTERNAL RISKS IN CONSTRUCTION PROJECTS
PESTLE TECHNIQUE A TOOL TO IDENTIFY EXTERNAL RISKS IN CONSTRUCTION PROJECTS NITANK RASTOGI 1, Dr. M.K TRIVEDI 2 1POST GRADUATE STUDENT ( M.E ), CIVIL ENGINEERING DEPARTMENT, MADHAV INSTITUTE OF TECHNOLOGY
STRATEGIC COST MANAGEMENT ACCOUNTING INSTRUMENTS AND THEIR USAGE IN ALBANIAN COMPANIES ABSTRACT
STRATEGIC COST MANAGEMENT ACCOUNTING INSTRUMENTS AND THEIR USAGE IN ALBANIAN COMPANIES Marsel Sulanjaku Lecturer at A.Xhuvani University ALBANIA Ali Shingjergji Lecturer at A.Xhuvani University ALBANIA
All the Truth about NGO Funding in Kyrgyzstan: Numbers and Facts. Kanykey Jailobaeva
All the Truth about NGO Funding in Kyrgyzstan: Numbers and Facts Kanykey Jailobaeva Ph.D Candidate, School of Social and Political Studies, University of Edinburgh Visiting Research Fellow, Social Research
Common weaknesses in local authorities judged inadequate under the single inspection framework a summary
Common weaknesses in local authorities judged inadequate under the single inspection framework a summary November 2015 Introduction Purpose of this slide deck This slide deck gives a summary of common
Short Report. Life-Cycle-Oriented Risk Management for PPP-Projects in Public Real Estate
Short Report Life-Cycle-Oriented Risk Management for PPP-Projects in Public Real Estate Project Director: Project Team: Prof. Dr.-Ing. Dipl.-Wirtsch.-Ing. Hans Wilhelm Alfen Dipl.-Ing. Alexander Riemann
NSPCC JOB DESCRIPTION. Database Training and Support Manager. (Grade 5 - Senior Business Support Officer)
NSPCC JOB DESCRIPTION Job Title: Database Training and Support Manager (Grade 5 - Senior Business Support Officer) Function: Department: Supporter Services and Database Administration Supporter Experience
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT
INVESTIGATING THE CRITERIA FOR CONTRACTORS SELECTION AND BID EVALUATION IN EGYPT M. Salama 1, H. Abd El Aziz 2, H. El Sawah 3 and A. El Samadony 3 1School of Built Environment, Heriot Watt University,
Design Verification The Case for Verification, Not Validation
Overview: The FDA requires medical device companies to verify that all the design outputs meet the design inputs. The FDA also requires that the final medical device must be validated to the user needs.
Risk Management Strategy and Policy. The policy provides the framework for the management and control of risk within the GOC
Annex 1 TITLE VERSION Version 2 Risk Management Strategy and Policy SUMMARY The policy provides the framework for the management and control of risk within the GOC DATE CREATED January 2013 REVIEW DATE
How Industrial Contractors are Handling Skilled Labor Shortages in the United States
How Industrial Contractors are Handling Skilled Labor Shortages in the United States Darren Olsen, Mark Tatum and Christopher Defnall Auburn University Auburn, AL In the United States, industrial construction
Risk profile table for deployment of releases to the main web site. High Acceptable Unacceptable Unacceptable
ITIL V3 Intermediate Capability Stream: RELEASE, CONTROL AND VALIDATION (RC&V) CERTIFICATE SCENARIO BOOKLET Scenario One A global company develops their own applications to support the business. The Service
Investors in People First Assessment Report
Investors in People First Assessment Report K.H.Construction Cambridge Assessor: Lesley E Ling On-site Date/s: 3 rd September 2008. Recognition Date: Contents 1. Introduction Page 2 2. Assessment and Client
Risky Business: Organisational Effectiveness at Managing Risk of Outsourced Projects
Risky Business: Organisational Effectiveness at Managing Risk of Outsourced Projects An ESI International Study +44(0) 20 7017 7100 www.esi-emea.com Nearly 95 percent of organisations buy, provide or both
NEW CONCEPTS IN THE CHANGE MANAGEMENT WITHIN PUBLIC ORGANIZATIONS
NEW CONCEPTS IN THE CHANGE MANAGEMENT WITHIN PUBLIC ORGANIZATIONS Ph.D Student Laurentiu Barcan University of Craiova Faculty of Economics and Business Administration, Craiova, Romania Abstract: Knowledge
Executive summary. Climate change assessments Review of the processes and procedures of the IPCC
Executive summary Climate change is a long-term challenge that will require every nation to make decisions about how to respond. The Intergovernmental Panel on Climate Change (IPCC) was established by
Ensuring Accountability in Disaster Risk Management and Reconstruction
Ensuring Accountability in Disaster Risk Management and Reconstruction Date: 08 December 2015 Time: 8.30 am until 4.30 pm Venue: Jaic Hilton Hotel, Colombo, Sri Lanka Organised by SPARC, University of
Synergies for Better Learning
Synergies for Better Learning AN INTERNATIONAL PERSPECTIVE ON EVALUATION AND ASSESSMENT How can assessment and evaluation policies work together more effectively to improve student outcomes in primary
Care service inspection report
Care service inspection report Full inspection SSCN Social Care Housing Support Service Suite 3, Floor 2 ELS House 555 Gorgie Road Edinburgh Inspection completed on 03 May 2016 Service provided by: Support
Job Grade: Band 5. Job Reference Number:
Job Title: Business Analyst Job Grade: Band 5 Directorate: Job Reference Number: People and Transformation P01216 The Role: This is a challenging role working with and across all services to support the
Safety Management Systems (SMS) guidance for organisations
Safety and Airspace Regulation Group Safety Management Systems (SMS) guidance for organisations CAP 795 Published by the Civil Aviation Authority, 2014 Civil Aviation Authority, CAA House, 45-59 Kingsway,
Topic 1 Introduction. to the Fundamentals of Project Management INTRODUCTION LEARNING OUTCOMES
Topic 1 Introduction to the Fundamentals of Project Management LEARNING OUTCOMES By the end of this topic, you should be able to: 1. Describe the nature of projects; 2. Identify the project life cycle;
Government Communication Professional Competency Framework
Government Communication Professional Competency Framework April 2013 Introduction Every day, government communicators deliver great work which supports communities and helps citizens understand their
These guidelines can help you in taking the first step and adopt a sustainability policy as well as plan your further sustainability communication.
SUSTAINABILITY POLICY AND COMMUNICATION GUIDELINES Why communicate about sustainability? IFU encourages all our investments to be transparent and informative about business and sustainability performance
Competitive Organisational Structures
Competitive Organisational Structures Organisational structure basics Introduction The way in which a business is organised has a direct effect on its competitiveness. For a business to be able to achieve
Applications and Benefits of Ethnographic Research
Hitachi Review Vol. 62 (2013), No. 6 317 Applications and Benefits of Ethnographic Research Case Study of Management System Upgrade for Power Plant Construction Site Takafumi Kawasaki Masaki Takano Kazuaki
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
Environment Sustainability and Highways
Job Title: Marketing Intelligence Officer Job Grade: Band 4 Directorate: Environment Sustainability and Highways Job Reference Number: P01851 The Role The Marketing Intelligence Officer will: Devise intelligence
Introduction. Page 2 of 11
Page 1 of 11 Introduction It has been a year since The Walton Centre brought its recruitment function in-house and it was critical that the organisation took this step. This is a specialist organisation
Corporate Risk Management Policy
Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction
CUSTOMER SERVICE SATISFACTION WAVE 4
04/12/2012 GFK CUSTOMER SERVICE SATISFACTION WAVE 4 GfK NOP Amanda Peet 2 Customer Service Satisfaction Table of Contents: Executive Summary... 3 Objectives and Methodology... 5 Overview of all sectors...
Risk Management approach for Cultural Heritage Projects Based on Project Management Body of Knowledge
1 Extreme Heritage, 2007 Australia, 19-21 July 2007, James Cook University, Cairns, Australia Theme 6: Heritage disasters and risk preparedness approach for Cultural Heritage Projects Based on Project
School of Accounting Financial Services and Law. External Examiner Reports 2013/14
School of Accounting Financial Services and Law Eternal Eaminer Reports 2013/14 EDINBURGH NAPIER UNIVERSITY ETERNAL EAMINER ANNUAL REPORT 2013/14 All Eternal Eaminers are requested to fill in a report
UFHRD 2013 CONFERENCE- HRD IN TURBULENT SEAS. Research Topic:
UFHRD 2013 CONFERENCE- HRD IN TURBULENT SEAS Research Topic: A GENDERED APPROACH TO ORGANISATIONAL CHANGE MANAGEMENT: DIFFERENCES IN THE WAY MEN AND WOMEN MANAGE ORGANISATIONAL CHANGE IN NIGERIA. Author
Author: Carlos Eduardo Martins Serra, MSc, PMP [email protected] Supervisor: Martin Kunc, PhD [email protected]
Benefits Realization Management and its influence on project success, project governance, and execution of business strategy - Analysis of Brazil, the United Kingdom, and the United States of America This
Zainab Zahran The University of Sheffield School of Nursing and Midwifery
Understanding advanced nursing practice: perspectives from Jordan RCN-The 2010 International Nursing Research Conference Zainab Zahran The University of Sheffield School of Nursing and Midwifery Aims and
G13 USE OF RISK ASSESSMENT IN AUDIT PLANNING
IS AUDITING GUIDELINE G13 USE OF RISK ASSESSMENT IN AUDIT PLANNING The specialised nature of information systems (IS) auditing and the skills necessary to perform such audits require standards that apply
Overseas Investment in Oil Industry and the Risk Management System
Overseas Investment in Oil Industry and the Risk Management System XI Weidong, JIN Qingfen Northeast Electric Power University, China, 132012 [email protected] Abstract: Based on risk management content,