1 X-C-4 JUNE 2, 2014 MEMORANDUM TO: FROM: MAYOR AND CITY COMMISSION CITY ATTORNEY S OFFICE DATE: June 2, 2014 RE: Agreement with Open Systems International, Inc. for SCADA/EMS and DMS Equipment/Maintenance Attached hereto for your consideration is a proposed Agreement and corresponding contract documents with Open Systems International, Inc. (OSI) for the procurement of a SCADA/EMS system and a Distribution Management System (DMS) for Lakeland Electric. The EMS system will replace the existing GE XA21 Energy Management System (EMS) and maintenance support agreement which will expire at the end of December The DMS system will replace Lakeland Electric s in-house Outage Management System (OMS). The SCADA/EMS system is the integral portion of the City s electrical system that allows real-time metering and remote control of key elements of electrical generation, transmission and delivery of electricity to maintain the balance between load and generation. The DMS is a fully integrated system that will bring multiple interfaces into one system for the Electric System Operators, providing better situational awareness that correlates into improved safety for Lakeland Electric s crews and the general public, as well as enhanced reliability. OSI supplies and supports both of the EMS and DMS platforms. The Agreement with OSI is the culmination of a Joint Utility Project (JUP). The JUP group, which includes Lakeland Electric, Gainesville Regional Utilities (GRU), City of Tallahassee (Tallahassee), Memphis Light, Gas and Water (MLGW), Minnkota Power Cooperative (Minnkota), City of South Mississippi Electric Power Association (SMEPA) and Wolverine Power Supply Cooperative (WPSC) issued a Request for Qualifications (RFQ) through KEMA, Inc. a/k/a DMV KEMA (KEMA), its SCADA/EMS consultant since 2003, seeking proposals from companies interested in supplying the EMS services beyond the expiration date of the GE contract. OSI was selected as the JUP s vendor of choice. On April 21, 2014, the City Commission approved a Task Order with KEMA to provide additional procurement services (including DMS), contract preparation and commence contract negotiations with OSI. As a member of the JUP, Lakeland Electric is able to leverage its position with KEMA to provide these services under one Agreement. In conjunction with the JUP selection process, Lakeland Electric staff evaluated multiple vendors of EMS and DMS platforms since these systems are fully integrated and work simultaneously with
2 each other. Throughout the evaluation process it became apparent that choosing one vendor for both the EMS and DMS, afforded multiple benefits to Lakeland Electric and its customers including, but not limited, to the following: Major cost savings % reduction of EMS/DMS cost as a concurrent system vs. stand-alone market priced systems. Single support source---single point of contact 24/7 365 day 2 hour response for vendor support. Single maintenance contract---all maintenance applies to both systems from single source, ensuring coordination and efficiencies. Elimination of systems integration---both systems built together by one vendor eliminating major integration expense/issues. Single source security and software patching--all security and patch updates thoroughly tested to perform properly on both systems. Combined software licensing---database and software joint use reducing multiple license fees. Combined software and system upgrades---contract will require periodic system upgrades for EMS/DMS; one vendor ensures these are coordinated and functional. Implementation coordination---ems/dms built in conjunction at OSI and implemented as one. Combined training on unified platform systems---major efficiencies involved with combined training for Electric System Operators and EMS staff due to one combined system provided by OSI. Enhanced North American Electric Reliability Corporation (NERC) Critical Infrastructure Protection (CIP) compliance all CIP documentation/ security requirements are coordinated between the systems by OSI as one product. Factory Acceptance Testing and Site Acceptance Testing typically require 3 to 5 weeks of staff time and travel to vendor site. Independent vendors and systems would double this expense and staff time. The Agreement shall become effective upon approval by the City Commission and execution by the parties and will continue in accordance with a mutually approved schedule until completion. Upon final acceptance of the System, the Agreement will continue for a period of ten (10) years. The base
3 cost for the EMS system deliverables and the first year of maintenance that will begin upon system acceptance in January 2016 is $1,341,000. The maintenance cost for years two (2) through ten (10) is $182,723 per year, or $1,644,507 over the ten (10) year period, bringing the total cost of the EMS system for equipment/maintenance over the ten (10) years to $2,985,507. The total cost reflects a total JUP discount for the EMS system deliverables/maintenance for the ten (10) year period of $869,482. The cost for the DMS system deliverables, if purchased in conjunction with the EMS under the JUP umbrella, is estimated at $780,000 compared to a standalone purchase cost of $1,400,000. With the addition of the first year s maintenance, the base cost of the DMS is $912,600. The maintenance cost for years two (2) through ten (10) is estimated to be $132,600 per year, or $1,193,400 over the ten (10) year period, bringing the total estimated cost of the DMS system, including maintenance, to $2,106,000. The consolidated ten (10) year cost for both the EMS and DMS is as follows: EMS DMS (Estimated Cost) TOTAL System $1,341,000 $912,600 $2,253,600 Deliverables & Year 1 Maintenance Maintenance for $1,644,507 $1,193,400 $2,837,907 Years 2 through 10 TOTAL: $2,985,507 $2,106,000 $5,091,507 Payments are based on specified milestones identified in the Agreement. The capital cost for the EMS system is included in Lakeland Electric s capital budget. While the DMS system is not currently budgeted, Lakeland Electric anticipates the DMS system being budgeted. However, in the event funds for the DMS system are not budgeted, it will be postponed until such time as sufficient budgeted funds are available. Furthermore, if the actual DMS cost exceeds the estimates specified above, any increase will be handled in accordance with the City s standard procurement practices/policies and will be brought to the City Commission for final approval. It is recommended that the appropriate City officials be authorized to execute this Agreement with OSI for the EMS and DMS systems, including maintenance, provided that approval of the DMS system shall be contingent upon available funds in Lakeland Electric s budget. RS attachment
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51
52
53
SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist
SCADA The Heart of an Energy Management System Presented by: Doug Van Slyke SCADA Specialist What is SCADA/EMS? SCADA: Supervisory Control and Data Acquisition Retrieves data and alarms from remote sites
Agenda Report. April 8, 2013. Honorable Mayor and City Council TO: THROUGH: Finance Committee (April 8, 2013) FROM: Water and Power Department
Agenda Report April 8, 2013 TO: Honorable Mayor and City Council THROUGH: Finance Committee (April 8, 2013) FROM: SUBJECT: Water and Power Department AUTHORIZATION TO ENTER INTO CONTRACTS WITH DESIGNATED
Getting Outage Management Systems Ready for Outage Events
Getting Outage Management s Ready for Outage Events Getting Outage Management s Ready for Outage Events Benefits are magnified during catastrophic events and major outages Upgrading or replacing an Outage
How the distribution management system (DMS) is becoming a core function of the Smart Grid
How the distribution management system (DMS) is becoming a core function of the Smart Grid Reducing risks and costs by optimizing distribution network operations Abstract As utilities identify their components
Quick guide: Implementing an IT solution
Quick guide: Implementing an IT solution This Quick Guide is part of a series of information products aimed to assist small to medium sized businesses purchasing an Information Technology (IT) solution.
Electric Field Operations Organization
NSTAR Electric Transmission Function Job Summaries Electric Field Operations Organization Vice President, Electric Field Operations (Transmission) This position has primary responsibility for the planning,
Department of Children and Families (DCF) Request for Information (RFQ) #01U013DS1 HIPAA Compliance Review DCF Answers to Vendor Questions
Department of Children and Families (DCF) Request for Information (RFQ) #01U013DS1 HIPAA Compliance Review s to Vendor Questions Questions as Submitted by Vendors (Duplicates omitted) 1. Have controls
CONTROL SYSTEM VENDOR CYBER SECURITY TRENDS INTERIM REPORT
Energy Research and Development Division FINAL PROJECT REPORT CONTROL SYSTEM VENDOR CYBER SECURITY TRENDS INTERIM REPORT Prepared for: Prepared by: California Energy Commission KEMA, Inc. MAY 2014 CEC
Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation. July 2015
Energy Management System (EMS) 3.0 Implementation Overview for BRP Consultation July 2015 Background Energy Management System EMS - Used by System Controllers to monitor, control and optimize the performance
SAMPLE WORK BREAKDOWN STRUCTURES VARIOUS TYPES OF PROJECT
Applications Development Project Sample WBS Management and support Provide project management Provide quality control Conduct meetings and reviews Materials and supplies Travel and living costs Miscellaneous
Request for Quote HIPAA Security Risk Analysis
Request for Quote Security Risk Analysis 4/26/13 Florida Department of Children and Families Purpose The Florida Department of Children and Families (DCF or the Department) is looking for a qualified information
Big Data in Smart Grid. Guangyi Liu China Electric Power Research Institute
Big Data in Smart Grid Guangyi Liu China Electric Power Research Institute 1 Outline 一 二 Sources and Feature of Big Data in Smart Grid Use Scenarios of Big Data in Smart Grid 2 Sources of Big Data in Smart
APPLICATION FOR THE E911 RURAL COUNTY GRANT PROGRAM
APPLICATION FOR THE E911 RURAL COUNTY GRANT PROGRAM W Form 1A, incorporated by reference in Florida Administrative Code Rule 60FF1-5.002 Rural County Grants, E911 Rural County Grant Application, effective
Utilities the way we see it
Utilities the way we see it Advanced Distribution Management Systems How to choose the right solution to improve your utility s safety, reliability, asset protection and quality of service Photo provided
Job Descriptions. Job Title Reports To Job Description TRANSMISSION SERVICES Manager, Transmission Services. VP Compliance & Standards
Updated July 11, 2013 Job Descriptions Job Title Reports To Job Description TRANSMISSION SERVICES VP Compliance & Standards Develops strategy and business plans for efficient, safe, reliable, regulatorycompliant
REQUEST FOR INFORMATION for Procurement Front-End System Modernization for The CITY OF PHILADELPHIA PROCUREMENT DEPARTMENT
REQUEST FOR INFORMATION for Procurement Front-End System Modernization for The CITY OF PHILADELPHIA PROCUREMENT DEPARTMENT Issued by: The Office of Innovation and Technology (OIT) June 25, 2014 Vendor
METER DATA MANAGEMENT LESSONS LEARNED LIFE AFTER GO LIVE Insight on Leveraging Integration While Preserving Technical Investment
METER DATA MANAGEMENT LESSONS LEARNED LIFE AFTER GO LIVE Insight on Leveraging Integration While Preserving Technical Investment November 2015 FMEA Energy Connections Conference Presenters: Matt Matherne
COST EFFICIENCIES/PRODUCTIVITY
Updated: 0-0-0 EB-0-0 Schedule Page of 0 COST EFFICIENCIES/PRODUCTIVITY.0 INTRODUCTION Hydro One has updated this exhibit to improve the information on Cost Efficiencies and Productivity initiatives and
Open Enterprise Architectures for a Substation Password Management System
CIGRÉ Canada 21, rue d Artois, F-75008 PARIS (154) Conference on Power Systems http : //www.cigre.org Toronto, October 4-6, 2009 Open Enterprise Architectures for a Substation Password Management System
Electric Operations Manager
CITY OF ANAHEIM invites applications for the position of: Electric Operations Manager SALARY: $10,602.75 - $14,578.75 Monthly $127,233.00 - $174,945.00 Annually OPENING DATE: 04/07/16 CLOSING DATE: Continuous
OUTAGE MANAGEMENT SYSTEMS What, How, Why. Steven E Collier Director, Smart Grid Strategies MILSOFT Utility Solutions
OUTAGE MANAGEMENT SYSTEMS What, How, Why Steven E Collier Director, Smart Grid Strategies MILSOFT Utility Solutions DETECT LOCATE assess analyze INFORM RESTORE INVESTIGATE IMPROVE WHAT IS OMS? Outage
Self-Hosted Applications
Volume Licensing brief Self-Hosted Applications Table of Contents Summary... 1 What s New in This Brief... 1 Details... 1 Licensing Options for Self-Hosted ISVs... 1 What is a Qualified Unified Solution?...
FERC, NERC and Emerging CIP Standards
Protecting Critical Infrastructure and Cyber Assets in Power Generation and Distribution Embracing standards helps prevent costly fines and improves operational efficiency Bradford Hegrat, CISSP, Principal
EVN SMART GRID PLAN. Technical and Operational Dept., Vietnam Electricity Nguyễn Hải Hà [email protected]
EVN SMART GRID PLAN Technical and Operational Dept., Vietnam Electricity Nguyễn Hải Hà [email protected] Frankfurt, 14 th November 2013 1 Content 1. Introduction of Vietnam Electricity (EVN) 2. EVN Smart
DATA MANAGEMENT & ANALYTICS FOR UTILITIES 2014
DATA MANAGEMENT & ANALYTICS FOR UTILITIES 2014 In-depth briefing Author Stephen Witt DATA MANAGEMENT FOR UTILITIES DATA MANAGEMENT & ANALYTICS FOR UTILITIES 2014 In-depth briefing About Smart Grid Update
Moving Towards the Smart Grid. Southern California Edison s Advanced Metering Infrastructure (AMI) Program
Moving Towards the Smart Grid Southern California Edison s Advanced Metering Infrastructure (AMI) Program 1 Copyright 2006, Southern California Edison www.sce.com/ami Select SCE Projects using Smart Grid
Contract Management The Mavericks Won t Like This!
Contract Management The Mavericks Won t Like This! Keith Wallis How Much Did That Project Cost? Real Life Example Original contract amount $500K Variations scope changes not visible Total variations =
Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change
Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change For Decision Member Champion(s): Cllr A Alford, Corporate - Director:
AGENDA ITEM TO: CITY COUNCIL FROM: CITY MANAGER. Item Number: Submitted By: Eric R. Nuñez Chief of Police
AGENDA ITEM TO: CITY COUNCIL FROM: CITY MANAGER Item Number: Submitted By: Eric R. Nuñez Chief of Police 11 Meeting Date: Subject: Agreement with Spillman Technologies, Inc., for Computer Aided Dispatch
LHRIC Network Support - Additional Service Features
LHRIC Network Support - Additional Service Features It is important to note that costs associated with LHRIC Network Support service not only cover an on-site support engineer but also include a number
CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH
CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH ABSTRACT Aditya Ramamurthy, PMP, ARCADIS US, Inc. Like most water and sanitary sewer utilities around the nation,
Cyber Security and Privacy - Program 183
Program Program Overview Cyber/physical security and data privacy have become critical priorities for electric utilities. The evolving electric sector is increasingly dependent on information technology
APPLICATION FOR THE E911 RURAL COUNTY GRANT PROGRAM
APPLICATION FOR THE E911 RURAL COUNTY GRANT PROGRAM W Form 1A, incorporated by reference in Florida Administrative Code Rule 60FF1-5.002 Rural County Grants, E911 Rural County Grant Application, effective
COMPANY PROFILE- INDUSTRIAL DEFENDER
COMPANY PROFILE- INDUSTRIAL DEFENDER MarketsandMarkets [email protected] www.marketsandmarkets.com MarketsandMarkets is a global market research and consulting company based in the U.S. We publish
Hosted vs On-Site IP-PBX A Guide for SMEs
A Guide for SMEs When switching to Voice over Internet Protocol (VoIP) telephony, the decision of whether to use a hosted or on-site phone system (IP-PBX) must be made. Both have fundamental differences
PROFESSIONAL SERVICES AGREEMENT FOR FINANCIAL ADVISOR
PROFESSIONAL SERVICES AGREEMENT FOR FINANCIAL ADVISOR This agreement for the provision of financial advisory services ( Agreement ) has been entered into this 21 st day of April, 2015 ( Effective Date
4. Technology Assessment
4. Technology Assessment KAT Transit Development Plan A technology study for KAT was prepared in 2005. That work provides the basis for this chapter as much of the information is germane and tied to the
Utility Telecom Forum. Robert Sill, CEO & President Aegis Technologies February 4, 2008
Utility Telecom Forum Robert Sill, CEO & President Aegis Technologies February 4, 2008 1 Agenda Asked to describe his job, Mike Selves, director of Emergency Management and Homeland Security in Johnson
Vendor Relationship Management
Vendor Relationship Management Getting What You Paid For (and More) Stephen Guth VP, Vendor Management Thursday, February 26 th, 2015, 8:00 9:00 a.m. Topics Case Study Company Intro Begin with the End
The calm after the storm
The calm after the storm Human decision support in storm outage recovery Rafael Ochoa, Amitava Sen It s a fact of life that interruptions in an electrical distribution utility happen. Although they can
Turbine Controls Update
Turbine Controls Update David Cicconi, Business Development Manager Emerson Process Management Power & Water Solutions Define Project Scope and Objectives Address obsolescence Best solution for new operational
Hosted vs On-Site IP-PBX A Guide for SMEs
A Guide for SMEs 1 When switching to Voice over Internet Protocol (VoIP) telephony, the decision of whether to use a hosted or on-site phone system (IP-PBX) must be made. Both have fundamental differences
Commercial Software Licensing
Commercial Software Licensing CHAPTER 4: Prepared by DoD ESI January 2013 Chapter Overview Publishers generally create one or more of three major types of software products: Applications software for transactions,
Weather-readiness assessment model for Utilities. Shy Muralidharan Global Product Manager Energy Solutions Schneider Electric
Weather-readiness assessment model for Utilities Shy Muralidharan Global Product Manager Energy Solutions Schneider Electric 1 Agenda > Impact of weather on Utilities businesses > Why should you be weather
New Jersey Transportation Authority (NJTA) Request For Proposal And Optional PeopleSoft Financial System
January 14, 2010 TO ALL PROPOSERS: RE: Request for Proposal New Jersey Turnpike Authority The Upgrade and Enhancement of the PeopleSoft Financial System And Optional PeopleSoft Financial System for South
Olav Mo, Cyber Security Manager Oil, Gas & Chemicals, 28.09.2015 CASE: Implementation of Cyber Security for Yara Glomfjord
Olav Mo, Cyber Security Manager Oil, Gas & Chemicals, 28.09.2015 CASE: Implementation of Cyber Security for Yara Glomfjord Implementation of Cyber Security for Yara Glomfjord Speaker profile Olav Mo ABB
City of Houston Budget and Fiscal Affairs Committee
City of Houston Budget and Fiscal Affairs Committee Electricity Procurement Update December 1, 2011 1 Electricity Procurement Current electricity contract with GLO / Reliant expires June 30, 2013 Currently
REQUEST FOR QUOTES FOR. On-Call Plumbing Contractor
Department of Public Services REQUEST FOR QUOTES FOR On-Call Plumbing Contractor November 2013 One Detjen Drive Crestwood, Missouri 63126 314-729-4720 Fax 314-729-4729 http://www.ci.crestwood.mo.us 1 Request
Consolidating Siloed GIS Data and Processes for Strategic Benefit
Consolidating Siloed GIS Data and Processes for Strategic Benefit John Marshall, Hydro One Networks Hydro One Networks Inc. Overview Hydro One Networks is in the midst of a major GIS consolidation effort
How Much Cyber Security is Enough?
How Much Cyber Security is Enough? Business Drivers of Cyber Security Common Challenges and Vulnerabilities Cyber Security Maturity Model Cyber Security Assessments September 30, 2010 Business in the Right
EAMS for Future Grids
EAMS for Future Grids Presenter: Nguyen Khanh-Loc Senior Consultant DNV GL Clean Technology Centre Singapore 1 SAFER, SMARTER, GREENER Objectives What is EAMS? Why EAMS? How EAMS helps? 2 DNV GL - Organized
SHARED SERVICES CAPITAL - CORNERSTONE
Filed: May, 0 EB-0-00 Exhibit D Schedule Page of SHARED SERVICES CAPITAL - CORNERSTONE.0 OVERVIEW The Cornerstone Project is part of the overall information technology ( IT ) strategy to replace several
Document Management System Request for Proposals April 22, 2013
FINANCE DEPARTMENT Office (402) 562-4231 Fax (402) 563-1380 Document Management System Request for Proposals April 22, 2013 Overview: The City of Columbus, Nebraska (hereafter referred to as City ) is
EDPR North America Condition Monitoring System Retrofits An Operator s Experience
EDPR North America Condition Monitoring System Retrofits An Operator s Experience Adam Johs 18 th February 2015 EDPR NA Current Active CMS Implementation Vibration Hardware EDPR s installed base of turbines
Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055
Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights
Veramark White Paper: Reducing Telecom Costs Why Invoice Management is the Best Place to Start. WhitePaper. We innovate. You benefit.
Veramark White Paper: Reducing Telecom Costs Why Invoice Management is the Best Place to Start WhitePaper We innovate. You benefit. Veramark White Paper: Reducing Telecom Costs Why Invoice Management is
Data Center Consolidation: Lessons From The Field. John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy
Data Center Consolidation: Lessons From The Field John Tsiofas, Kraft Kennedy David Carlson, Kraft Kennedy Agenda Factors to consider Technology strategy Building a project team How to use vendors wisely
NERC Cyber Security. Compliance Consulting. Services. HCL Governance, Risk & Compliance Practice
NERC Cyber Security Compliance Consulting Services HCL Governance, Risk & Compliance Practice Overview The North American Electric Reliability Corporation (NERC) is a nonprofit corporation designed to
Secure Electronic Voting RFP Kit
Secure Electronic Voting RFP Kit The purpose of this document is to assist election officials in jurisdictions with DRE voting systems in identifying and selecting qualified independent security experts
An Update on Utility Outage Communication Programs & Recent Developments in the Sector
Outage Communications: Kaihen White Paper White Paper An Update on Utility Outage Communication Programs & Recent Developments in the Sector Introduction This White Paper (Version 2.0) is an update to
CITY OF LAKE WORTH 7 North Dixie Highway Lake Worth, Florida 33460 Phone: 561-586-1600 Fax: 561-586-1750
CITY OF LAKE WORTH 7 North Dixie Highway Lake Worth, Florida 33460 Phone: 561-586-1600 Fax: 561-586-1750 1. ROLL CALL: 2. PLEDGE OF ALLEGIANCE: AGENDA-Revised CITY OF LAKE WORTH ELECTRIC UTILITY ADVISORY
How to Integrate NERC s Requirements in an Ongoing Automation and Integration Project Framework
How to Integrate NERC s Requirements in an Ongoing Automation and Integration Project Framework Jacques Benoit, Cooper Power Systems Inc., Energy Automations Solutions - Cybectec Robert O Reilly, Cooper
Risk Management, Equipment Protection, Monitoring and Incidence Response, Policy/Planning, and Access/Audit
Page 1 of 10 Events Partners Careers Contact Facebook Twitter LinkedIn Pike Research Search search... Home About Research Consulting Blog Newsroom Media My Pike Logout Overview Smart Energy Clean Transportation
Consolidated I&T Data Centre - P3 Canada Fund
STAFF REPORT ACTION REQUIRED Consolidated I&T Data Centre - P3 Canada Fund Date: January 16, 2012 To: From: Wards: Reference Number: Government Management Committee Deputy City Manager & Chief Financial
IT Governance. UIS Monthly Update October 2015
IT Governance UIS Monthly Update October 2015 UIS October 2015 Enterprise Services Update Projects Update 2 IT GOVERNANCE OCTOBER 2015 ENTERPRISE SERVICES UPDATE 3 Enterprise Services Issues October 15
Application Maintenance and Development Attachment C for RFP#
Application Maintenance and Development Attachment C for RFP# Service Level Agreements and Operating Level Agreements Issue: 1.0 Issue Date: November 17, 2015 Issue 1.0 November 17, 2015 1 Copyright 2015
Cloud Sourcing G-Cloud 5 Framework
Cloud Sourcing G-Cloud 5 Framework Cloud Sourcing Service Definition Document April 2014 Warnford Court, 29 Throgmorton Street, London, EC2N 2AT T: +44 20 7947 4176 Table of contents 1 Cloud Sourcing 3
THE BUSINESS CASE FOR SOFTWARE ASSET MANAGEMENT. by Peter Alderson, SAM Practice Leader, Computacenter
THE BUSINESS CASE FOR SOFTWARE ASSET MANAGEMENT by Peter Alderson, SAM Practice Leader, Computacenter Executive Summary ʻSAMʼ is an often misused, misunderstood term with many interpretations A properly
New York State 2100 Commission Report: Energy
New York State 2100 Commission Report: Energy Improving Strength and Resilience Phil Mihlmester New York Bar Association Columbia University Law School New York, NY May 14, 2014 Context: Aftermath of Hurricane
GE Measurement & Control. Cyber Security for NERC CIP Compliance
GE Measurement & Control Cyber Security for NERC CIP Compliance GE Proprietary Information: This document contains proprietary information of the General Electric Company and may not be used for purposes
Securing the Electric Grid with Common Cyber Security Services Jeff Gooding
Securing the Electric Grid with Common Cyber Security Services Jeff Gooding TCIPG Seminar April 4, 2014 Southern California Edison (SCE) is committed to safely providing reliable and affordable electricity
IESO Supply Deliverability Guidelines
PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents
GENe Software Suite. GENe-at-a-glance. GE Energy Digital Energy
GE Energy Digital Energy GENe Software Suite Today s utilities have complex requirements that need sophisticated solutions. GE Energy s GENe provides these solutions. Using the latest advances in technology,