CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH

Size: px
Start display at page:

Download "CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH"

Transcription

1 CAPITAL IMPROVEMENT PROGRAM (CIP) MANAGEMENT & TRACKING PROCESS, SYSTEMS, & PEOPLE APPROACH ABSTRACT Aditya Ramamurthy, PMP, ARCADIS US, Inc. Like most water and sanitary sewer utilities around the nation, rehabilitation and/or replacement of aging sanitary sewer infrastructure is a top priority for the City of Virginia Beach, Department of Public Utilities (DPU). The City is currently mandated to be in compliance with the regional Consent Order and is also in the process of developing a mandatory, multi-year, rehabilitation implementation plan. As a result, limited capital improvement program (CIP) funds are available for other programs. With an industry new-normal of having to do more with less, prioritization and effective program/project management of all capital programs is critical and necessary. The objective of this initiative is to develop a robust change management process to efficiently plan for CIP project funding needs, track CIP project schedules, encumbrances and expenditures, and train Sewer Pump Station Project Managers with the adoption of the methodology. DPU s sanitary sewer system is comprised of more than 1,621 miles of gravity sewer lines, 190 miles sewer force main, and 406 sewer pump stations. Given that the typical useful life of a sewer pump station is approximately 50 years and in order to stay ahead of the pump station deterioration rate, it is DPU s intent to replace approximately 8-10 pump stations each year resulting in significant annual capital investments. Upgrades or rehabilitation of 406 sewer pump stations experiencing hydraulic, mechanical, safety, or structural problems and stations subjected to corrosion and odor problems falls under the purview of the Pump Station Modifications program, making it one of the largest and the most complex programs within DPU s annual CIP. The Process-Systems-People methodology has been adopted and is being actively implemented for the Pump Station Modifications program. The process has been established, necessary information management systems have been aligned, and all Sewer Pump Station Project Managers have been trained to successfully implement this methodology. This presentation will describe the methodology used by the City of Virginia Beach, DPU as part of a process-systems-people approach to program management of the Sewer Pump Stations Modifications Program by developing a standardized program/project management framework, leveraging existing technology, and training Sewer Pump Station Project Managers to manage the City-owned, operated, and maintained sewer pump stations. The change management approach that identifies the requirements, systems and resource dependencies of capital program management in

2 order to depict critical program and project management Key Performance Indicators (KPI) and make them accessible to key stakeholders within DPU will also be presented. INTRODUCTION The purpose of the work effort described in this paper is to provide the City of Virginia Beach Department of Public Utilities (DPU) with a robust and systematic process to manage, track, report, and annually administer its CIP projects. The information contained in this paper supports an efficient CIP funding management strategy built from a strong foundation based on asset management principles. This also helps DPU to ensure financial sustainability and assist management and staff with the efficient and effective implementation of CIP projects. These concepts are in alignment with key elements of DPU s Asset Management Program Vision including: Implement a unified and consolidated Departmental strategy for meeting goals related to regulatory compliance, customer service, management of resources and management of infrastructure assets Improve the process of identifying, comparing, prioritizing and implementing Capital Improvement Projects (CIP) for existing infrastructure Encourage better communication and collaboration across the Department to promote more efficient operations Improve education and communication with City Council and other stakeholders BACKGROUND DPU provides water and sanitary sewer services to over 441,000 citizens within the City of Virginia Beach. The water distribution system is comprised of 11 water tanks, 8 water pump stations, and more than 1,580 miles of water mains. The sanitary sewer system is comprised of more than 1,621 miles of gravity sewers (including laterals) and more than 190 miles of sewer force mains. Additionally, DPU plans, designs, constructs, operates, and maintains 406 sewer pump stations. Capacity of these pump stations range from 80 gallons per minute (gpm) to approximately 3,700 gpm. Management of these sewer pump stations and associated assets are funded out of Sewer Pump Stations Modifications Capital Program. The Sewer Pump Stations Modification Capital Program is managed and administered by a Program Manager and supported by approximately Project Managers. Key stakeholders involved in the management of this program include, DPU Engineering Division, DPU Operations Division, City Attorney Office (Deeds), Department of Public Works (DPW) Survey Department, Consultants, Contractors, and citizens. Together, this Capital Program encumbers approximately $6 million to $8 million annually and designs and/or constructs approximately 7 to 8 pump stations annually. Given that the typical useful life of these pump stations are approximately 50 years, it is

3 critical that approximately 8-10 pump stations are rehabilitated or replaced annually. The Sewer Pump Stations Modification program funds the replacement and/or rehabilitation of pump station projects. This capital program also funds pump station rehabilitation projects such as wet well rehabilitation, HVAC replacement, and electrical assets rehabilitation and are primarily driven by the age and condition of these asset groups. Sewer Pump Stations are identified and prioritized for rehabilitation or replacement based on the following: Input from the Operations and Maintenance (O&M) crew Review of SCADA data Capacity issues identified by the Planning and Analysis Bureau at DPU Engineering Condition of assets at the pump station Age of assets within certain asset groups (HVAC, Wet Well assets, Electrical assets) In order to successfully design and construct the sewer pump stations based on the above criteria, the following engineering approach has been adopted: Pre-Preliminary Engineering Report (Pre-PER) Phase This is typically an internal initiative process where a detailed desktop assessment of the selected pump station is conducted by Sewer Pump Station Project Managers. Service area maps, pressure data, capacity, run time statistics, rain gauge data, and master planning reports are reviewed by multiple Project Managers. Results of this assessment are presented to the pump station committee at the monthly pump station committee meeting. Based on this evaluation, Project Managers recommend if the pump station should be rehabilitated or replaced. If the pump station has to be rehabilitated, specifics on assets/asset groups (wet well, HVAC, and/or electrical assets) that need to be replaced is recommended Preliminary Engineering Report Phase (PER) As part of the PER phase, a detailed on-site field inspection, data collection, preliminary design calculations, and existing station viability analysis is conducted at the pump station. Based on the recommendations of the viability analysis, preliminary design (35% Design) is completed as part of this phase. Preliminary design includes the development of site layout and staging plan, elevation view plan, off-site improvement plans, traffic control plans, detailed design calculations, and cost estimates. Site Acquisition Any site acquisition associated with the replacement of a pump station is coordinated with the Real Estate Division within the Public Works Department. The Real Estate

4 Division further coordinates with the Survey Division within Public Works and the City Attorney s office. Design Phase As part of the Design Phase, all engineering services associated with the preparation of final design, development of project manual, construction drawings, including the interaction with the associated regulatory agencies is completed. Additionally, documentation associated with bid preparations and the bidding process is completed as part of this phase Construction This phase involves the construction and construction management of rehabilitation or replacement of a pump station and/or its associated assets. The Design Phase is either completed in-house or contracted out to Consultants as part of Annual Services Engineering Contracts, whereas the Construction Phase is contracted out based on a formal bidding process. METHODOLOGY Replacement of a pump station typically takes 2-3 years to complete. At any given time, Sewer Pump Stations Project Managers manage multiple pump stations in various stages of either replacement or rehabilitation. Although a well-documented engineering process discussed above, is in place and used by Project Managers to design, construct and/or rehabilitate sewer pump stations, there was no formal process in place to efficiently and effectively manage, track, and report status and performance of these projects. With a need to rehabilitate or replace approximately 10 pump stations each year, a standardized Process-Systems-People approach was used for efficient and effective management of this program. Additionally, this necessitated an automated process to manage, track and report project status and performance of all pump station projects. PROCESS SYSTEM PEOPLE APPROACH PROCESS Project Schedule Management As a first step, it was critical to understand all the existing processes that were being utilized by the Project Managers to Manage each individual pump station project and identify potential gaps and areas of improvement. Although scope and budget for the project were well defined and documented as part of the Engineering assessment phases, there was no standardized process to measure and report schedule

5 performance of these projects. It was therefore important to establish standardized schedule management templates for all projects under the purview of this program. As part of the schedule development process, a work breakdown structure was established, tasks were identified and defined, and duration for each task was assigned for all pump station projects. These steps ensured that a baseline schedule with timelines and costs was established for all pump station replacement projects and could be used to track and report project performance from a schedule stand-point. This would enable the Project Managers to manage costs, identify and address schedule delays and effectively plan the management of a project. Automated Financial Reporting In order to enable an automated process to track and report project performance, it was critical to ensure that individual project activities (design, construction, design study etc) for each pump station project are uniquely tracked in the City s enterprise financial system. Historically, projects were tracked at a program level in the financial system. As a result, the granularity of financial metrics was limited at a program level. For example, the financial system reported the amount of program expenditures or encumbrances for design projects but did not provide a breakdown of the expenditures or encumbrance at an individual project level. In other words, it was not possible to ascertain from the data in the financial system the actual expenditure or encumbrance for a particular project within a capital program. Additionally, the monthly financial metrics had to be computed manually for stakeholder reporting purposes resulting in increased Project Manager time. In order to accomplish the above business need, a process change workflow associated with the creation of accounts in the financial system for each project resulting in the tracking of financial data at an individual project level was developed and implemented. As a result of this process change, it is now possible to report on the exact project encumbrance for the design of a sewer pump station project.

6 Project Management Adoption With schedules being developed for each project, it was important to create, adopt and subsequently track schedule performance for each project directly within the project management system rather than stand-alone systems or databases. Having all the data in one enterprise system will provide the opportunity to automate tracking and reporting of data. An additional benefit to adopting and tracking the projects in the City s project management system is the elimination of redundant data sources and project management steps resulting in significant time saving opportunities for Project Managers. SYSTEMS In order to track and report progress of projects, it was important to understand existing information system capabilities and functionalities. At the City of Virginia Beach, Project Planning and Tracking Systems (PPATS) is the project management system of choice and the finance module of Integrated Services In The Enterprise (InSITE) system is the system of choice for financial reporting. It was therefore critical to leverage these two enterprise systems to track and report progress of projects. A detailed system assessment was performed on PPATS and InSITE to evaluate their respective capabilities and functionalities. The goal was to leverage existing technology instead of investing in new enterprise/custom technology applications. The detailed system assessment indicated that PPATS has the ability to manage, track and report schedules for each project. However, this application is outdated and did not provide the flexibility to report all the desired performance measures. Similarly, the detailed system

7 assessment indicated that InSITE recorded all the financial transactions such as capital project encumbrances, capital project expenditures, and available funding. Although, InSITE has reporting capabilities the desired reports were not readily available and had to be developed. With the implementation of the process changes discussed in the PROCESS section above, Project Managers now manage project data for pump station projects (scope, budget, and schedule) in PPATS, and financial information for capital projects is being tracked and reported at a project level in InSITE financial system. However, despite the fact that PPATS and InSITE are enterprise systems, these two systems are not setup within the City s Information Technology framework to seamlessly exchange and report information. As a result, an existing enterprise reporting system currently used by the City was utilized to develop performance tracking and reporting dashboards. Performance Tracking and Reporting Dashboards As noted above, due to the existing limitations in PPATS and InSITE, it was determined to develop performance tracking and reporting dashboards using existing enterprise reporting systems. Here again, the emphasis was to leverage existing technology in use within the City rather than procure new systems and technologies. The performance tracking and reporting dashboards were designed to seamlessly draw relevant data from the two enterprise source systems and report the information on the dashboard in a logical and meaningful way. As a result of this dashboard, sewer pump station Project Managers are able to review both financial information and project management information (scope, budget, and schedule) in one location for any individual Sewer Pump Station Project Manager or for a specific pump station project. Additionally, as this dashboard provides all applicable CIP data in one location, Program Managers save significant amount of time by not having to gather and consolidate individual project information from various data sources. Some of the Key Performance Metrics that are being developed and implemented on the dashboard include: Percentage of annual planned funds to available funds Cost management metric Percentage of CIP projects that are on schedule - Schedule management metric Percentage of CIP funding managed by a Project Manager Resource management metric Percentage of CIP projects managed by a Project Manager Resource management metric The performance tracking and reporting dashboards have been designed to leverage data associated with the above metrics directly from the source systems (InSITE and PPATS) to automatically compute and report information. These dashboards provide

8 a schedule and cost performance status on ongoing CIP programs and projects and allow for comparison across CIP programs and between CIP projects. PEOPLE Change Management Adoption of any process change is typically a challenge within any organization. To change the way business is conducted is one of the most challenging tasks to implement. If there is no universal adoption of such process changes, the true impact of the process and system changes will not be realized within the organization and will render the entire effort futile. The sewer pump station Program Manager organized a series of meetings with sewer pump station Project Managers and emphasized the need to adopt and apply these process changes. Initially, significant resistance to change was observed (mostly due to existing deficient systems), but as Project Managers began to use the new process and were able to see the benefits of these changes, adoption of the process was more acceptable and achievable. Additionally, having strong Executive Committee sponsorship further reinforced the need for the adoption of the process changes. Strong Executive Committee sponsorship combined with multiple Project Manager Meetings to demonstrate the true value and potential of these process changes enabled the implementation of a successful change management process Process Change Training Another critical aspect to successfully adopt newly implemented processes has been extensive Project Manager training. Multiple training sessions were setup to communicate all the new process changes and train the Project Managers in the use of associated systems. These training sessions not only communicated the details of the process changes, but also constantly emphasized the macro level need and value of this process change from an organizational level. As a result, Project Managers at all levels in the organization were able to appreciate the impact of the process changes at an organizational level. In addition to training, detailed reference documentation (SOPs, Process change memorandum etc) was also developed and distributed to all Project Managers for future reference and use.

9 RESULTS The following overarching goals of this effort were successfully accomplished: Developed and implemented robust business processes that will enable efficient and effective management of CIP Programs Leveraged existing technology for data management Communicated and trained Project Managers and empowered them to own and use the new process Fostering a dynamic process that can consistently respond to changing business needs and drivers Specific results of this effort include: The pump station modification program has developed and adopted standard schedule management (with standard tasks and task durations) methodologies to manage the implementation of all pump station projects. Most all standalone systems and databases used by individual Project Managers have been eliminated. All project management data is now recorded in the enterprise project management system (PPATS) All financial management data is now recorded in the enterprise financial management system (InSITE). Financial Reporting Process Change Memorandum documentation has been developed and outlines all the process change steps. Performance Reporting and Tracking Dashboards were developed and are leveraging data directly from the enterprise systems. This process has been automated and has significantly reduced project manager reporting and tracking times. Standard Operating Procedures (SOPs) with step-by-step guidance have been developed to assist Project Managers with change management. Project Manager training sessions have been held to communicate, train, and empower Project Managers with process and system changes With the successful implementation of this Process-Systems-People approach on the Sewer pump station modifications program, this approach is currently being implemented for all the water and sanitary sewer Capital Improvement Programs within DPU. Given the existing limitations in PPATS, an inter-departmental collaborative effort is underway to evaluate potential upgrades or replacement of PPATS with a

10 more current project and program management enterprise system. It is noted that regardless of which system is selected, processes and data developed as part of this approach is expected to be seamlessly transitioned into the new system. New Sub-Project Account Creation InSITE PPATS Adoption PPATS PPATS NEEDS ASSESSMENT InSITE Reports InSITE TRACKING & REPORTING DASHBOARD CONCLUSIONS While DPU has been proactive in operating and maintaining its infrastructure to ensure regulatory compliance and service level commitments are met, this work effort provided a formal approach to efficiently and effectively manage track and report performance and status of capital projects. One of the most compelling success stories of operational optimization at DPU is process automation and reporting maturity achieved through the monitoring, tracking, and reporting of performance metrics associated with delivery of existing Capital Projects. DPU Project Managers have adopted a standardized program management process through the native technology systems available. The department-wide adoption of the PPATS is demonstrating to the DPU program management team the benefits of a standardized schedule management and reporting approach, leveraging past investment in existing technology, and is enabling DPU CIP Project and Program Managers to proactively administer, track, and report performance of all DPU CIP Project through a scalable, secure and dynamic dashboard built in the enterprise reporting system.

Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective

Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Affordable Asset Management Workshop Making Use of the Data You Have An Owners Perspective Building the Foundation for an Effective Asset Management Program Scott D. Kelly, P.E. Assistant City Administrator

More information

TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates. Private Sewer Lateral Inspection and Repair Program

TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates. Private Sewer Lateral Inspection and Repair Program TOWN OF HILLSBOROUGH Compliance with Regulatory Mandates Private Sewer Lateral Inspection and Repair Program SEWER SYSTEM- BACKGROUND 116 miles of gravity sanitary sewer pipelines 1 mile of force main

More information

ClOP CHAPTER 1351.39. Departmental Information Technology Governance Policy TABLE OF CONTENTS. Section 39.1

ClOP CHAPTER 1351.39. Departmental Information Technology Governance Policy TABLE OF CONTENTS. Section 39.1 ClOP CHAPTER 1351.39 Departmental Information Technology Governance Policy TABLE OF CONTENTS Section 39.1 Purpose... 1 Section 39.2 Section 39.3 Section 39.4 Section 39.5 Section 39.6 Section 39.7 Section

More information

High-Performing Information Systems Aligned With Utility Business Strategy [Project #4316]

High-Performing Information Systems Aligned With Utility Business Strategy [Project #4316] High-Performing Information s Aligned With Utility Business Strategy [Project #4316] ORDER NUMBER: 4316 DATE AVAILABLE: June 2013 PRINCIPAL INVESTIGATORS: David W. Harris, Esteban Azagra, Rod van Buskirk,

More information

STATEMENT OF CHARLES EDWARDS DEPUTY INSPECTOR GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY BEFORE THE

STATEMENT OF CHARLES EDWARDS DEPUTY INSPECTOR GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY BEFORE THE STATEMENT OF CHARLES EDWARDS DEPUTY INSPECTOR GENERAL U.S. DEPARTMENT OF HOMELAND SECURITY BEFORE THE COMMITTEE ON HOMELAND SECURITY SUBCOMMITTEE ON OVERSIGHT AND MANAGEMENT EFFICIENCY U.S. HOUSE OF REPRESENTATIVES

More information

CHAPTER 8 ASSET MANAGEMENT

CHAPTER 8 ASSET MANAGEMENT CHAPTER 8 ASSET MANAGEMENT 8.1 Introduction An additional task of the WRMP was to educate and engage GWA personnel in the concepts of asset management. Three specific areas of asset management have been

More information

A Final Report for City of Chandler Strategic IT Plan Executive Summary

A Final Report for City of Chandler Strategic IT Plan Executive Summary A Final Report for City of Chandler 6 January 2004 Table of Contents 1. Executive Summary... 1 1.1 Background... 2 1.2 Chandler Business and IT Context... 3 1.3 Chandler s IT Strategic Direction... 5 1.4

More information

Hospital Performance Management: From Strategy to Operations

Hospital Performance Management: From Strategy to Operations Hospital Performance Management: From Strategy to Operations Every hospital wants to be on top in terms of revenue and quality of care. It is tough enough to get to the top, but tougher still to stay there.

More information

IT Standards & Contract Management

IT Standards & Contract Management Appendix F IT Standards & Table of Contents Vision of Action... 2 Background... 3 Goals and Objectives... 4 Projects... 5 Metrics and Measures... 6 F IT Standards & Carol Steffanni Director, MDIT Bureau

More information

Portfolio Management 101:

Portfolio Management 101: THOUGHT LEADERSHIP WHITE PAPER In partnership with Portfolio Management 101: Moving from Just Project Management to True PPM A lot of organizations claim that they carry out project & portfolio management

More information

IT and Business Alignment

IT and Business Alignment 4 IT and Business Alignment 4.1. Introduction A close alignment between the city s business and IT imperatives is critical to developing a viable IT strategy for the city. A business imperative is an initiative

More information

Business Support Services Assessment Communications Plan

Business Support Services Assessment Communications Plan Business Support Services Assessment Communications Plan Background In his budget message in May of 2010 and Memorandum to employees in October 2010, County Manager Harry Jones said that the new economic

More information

Project Management Terms

Project Management Terms FDM 2-1 Attachment 1.1 Terms Terms Baseline Term Baseline Budget Baseline Schedule Baseline Scope Budget Budget Change Control Communication Corrective Action Cost-Benefit Analysis Critical Path Decision

More information

COMPREHENSIVE ASSET MANAGEMENT STRATEGY

COMPREHENSIVE ASSET MANAGEMENT STRATEGY COMPREHENSIVE ASSET MANAGEMENT STRATEGY APPROVED BY SENIOR MANAGEMENT COMMITTEE ON AUGUST 23, 2012 (TO BE FINALIZED AFTER APPROVAL OF CAM POLICY BY COUNCIL) August 2012 Contents CONTENTS EXECUTIVE SUMMARY

More information

How To Manage A Public Safety Department Risk Management Program

How To Manage A Public Safety Department Risk Management Program Information Technology Risk Management (ITRM) Program NOMINATING CATEGORY: RISK MANAGEMENT INITIATIVES NOMINATOR: TERESA A. SHUCHART DEPARTMENT OF PUBLIC WELFARE (DPW) COMMONWEALTH OF PENNSYLVANIA 1006

More information

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF FEBRUARY 17, 2015

CITY OF VAUGHAN EXTRACT FROM COUNCIL MEETING MINUTES OF FEBRUARY 17, 2015 EXTRACT FROM COUNCIL MEETING MINUTES OF FEBRUARY 17, 2015 Item 3, Report No. 5, of the Finance, Administration and Audit Committee, which was adopted without amendment by the Council of the City of Vaughan

More information

Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective

Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective Affordable Asset Management Making Use of the Data You Have: An Owner s Perspective An Owner Operator s Approach for Asset Management on a Budget Lane Longley, City of St. Petersburg Presented by the April

More information

Enterprise IT Portfolio Governance and Management Model

Enterprise IT Portfolio Governance and Management Model STATE OF MICHIGAN Department of Information Technology Enterprise IT Portfolio Governance and Management Model NASCIO 2007 RECOGNITION AWARDS CATEGORY: IT PROJECT AND PORTFOLIO MANAGEMENT Enterprise IT

More information

Department of Technology Services

Department of Technology Services Department of Technology Services 2016-2019 Strategic Plan DTS Dept. of Technology Services Utah Code 63F- 1-203 explicitly requires the Chief Information Officer (CIO) to prepare an executive branch strategic

More information

Human Capital Update

Human Capital Update Finance & Administration Committee Information Item IV-A July 10, 2014 Human Capital Update Washington Metropolitan Area Transit Authority Board Action/Information Summary Action Information MEAD Number:

More information

Implementing a Workflow Solution Leveraging SCADA and GIS/CMMS at the Waterford Township DPW. Charter Township of Waterford Oakland County, Michigan

Implementing a Workflow Solution Leveraging SCADA and GIS/CMMS at the Waterford Township DPW. Charter Township of Waterford Oakland County, Michigan Implementing a Workflow Solution Leveraging SCADA and GIS/CMMS at the Waterford Township DPW Charter Township of Waterford Oakland County, Michigan DPW Assets 360 Miles of Water Main and Appurtenances

More information

U.S. Nuclear Regulatory Commission

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission 2011 Data Center Consolidation Plan and Progress Report Version 2.0 September 30, 2011 Enclosure Contents 1 Introduction... 2 2 Agency Goals for Data Center Consolidation...

More information

Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN. CR_2215 Attachment 1

Financial Services FINANCIAL SERVICES UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN. CR_2215 Attachment 1 CR_2215 Attachment 1 Financial Services FINANCIAL SERVICES & UTILITIES 57 FINANCIAL SERVICES AND UTILITIES 2016-2018 BUSINESS PLAN Acting Branch Manager: Stacey Padbury Table of Contents INTRODUCTION Our

More information

Introducing ConceptDraw PROJECT

Introducing ConceptDraw PROJECT Introducing ConceptDraw PROJECT Introducing ConceptDraw PROJECT Contents Introducing ConceptDraw PROJECT... 1 What is ConceptDraw PROJECT?... 6 Visualize Project Data...6 Plan Projects and Manage Change...7

More information

LSF HEALTH SYSTEMS Information Technology Plan

LSF HEALTH SYSTEMS Information Technology Plan LSF HEALTH SYSTEMS Information Technology Plan I. INTRODUCTION The LSF Health Systems software is a web-enabled, secure website providing access to LSF, the Provider Network and DCF. At this time, the

More information

Aligning Quality Management Processes to Compliance Goals

Aligning Quality Management Processes to Compliance Goals Aligning Quality Management Processes to Compliance Goals MetricStream.com Smart Consulting Group Joint Webinar February 23 rd 2012 Nigel J. Smart, Ph.D. Smart Consulting Group 20 E. Market Street West

More information

Value to the Mission. FEA Practice Guidance. Federal Enterprise Architecture Program Management Office, OMB

Value to the Mission. FEA Practice Guidance. Federal Enterprise Architecture Program Management Office, OMB Value to the Mission FEA Practice Guidance Federal Enterprise Program Management Office, OMB November 2007 FEA Practice Guidance Table of Contents Section 1: Overview...1-1 About the FEA Practice Guidance...

More information

Migration Planning Guidance (Draft)

Migration Planning Guidance (Draft) Financial Management Line of Business Migration Planning Guidance (Draft) Section 1.1 Overview The purpose of the Migration Planning Guidance document is to help agencies prepare for, and manage, a migration

More information

Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015

Office of the Auditor General AUDIT OF IT GOVERNANCE. Tabled at Audit Committee March 12, 2015 Office of the Auditor General AUDIT OF IT GOVERNANCE Tabled at Audit Committee March 12, 2015 This page has intentionally been left blank Table of Contents Executive Summary... 1 Introduction... 1 Background...

More information

UPTIME MAGAZINE. june/july15 JUNE/JULY 2015. uptimemagazine.com

UPTIME MAGAZINE. june/july15 JUNE/JULY 2015. uptimemagazine.com june/july15 UPTIME MAGAZINE JUNE/JULY 2015 uptimemagazine.com AM Developing Plans Creating Value From Physical Assets by Mark Ruby 46 june/july 15A sset management plans form the cornerstone of an effective

More information

Audit of Financial Management Governance. Audit Report

Audit of Financial Management Governance. Audit Report Audit of Financial Management Governance Audit Report March 2015 TABLE OF CONTENTS Executive Summary... 2 What we examined... 2 Why it is important... 2 What we found... 2 Background... 4 Objective...

More information

INTERNAL AUDIT REPORT REVIEW OF PHYSICAL FACILITIES MAINTENANCE AND REPAIRS

INTERNAL AUDIT REPORT REVIEW OF PHYSICAL FACILITIES MAINTENANCE AND REPAIRS INTERNAL AUDIT REPORT REVIEW OF PHYSICAL FACILITIES MAINTENANCE AND REPAIRS FAIRFAX COUNTY, VIRGINIA INTERNAL AUDIT OFFICE M E M O R A N D U M TO: Anthony H. Griffin DATE: March 22, 2001 County Executive

More information

One solution, countless benefits

One solution, countless benefits www.exordia.co.za One solution, countless benefits exsam New generation strategic asset management PwC s exsam is built to empower the strategic management of diverse assets. 2 exsam One solution, countless

More information

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into

The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into The following is intended to outline our general product direction. It is intended for information purposes only, and may not be incorporated into any contract. It is not a commitment to deliver any material,

More information

Collaboration Tools: Innovation Management and Solution Infusion Benefits

Collaboration Tools: Innovation Management and Solution Infusion Benefits 2007 NASCIO Recognition Awards Information Communications Technology Innovations Collaboration Tools: Innovation Management and Solution Infusion Benefits Michigan Department of Information Technology

More information

Information Technology Master Plan Update: IMTech February 28, 2011

Information Technology Master Plan Update: IMTech February 28, 2011 Information Technology Master Plan Update: IMTech February 28, 2011 Information Technology Master Plan Update: Agenda Background City of Georgetown s Vision Technology Transformation Approach Assessment

More information

strategic workforce planning: building blocks to success

strategic workforce planning: building blocks to success strategic workforce planning: building blocks to success Foreword by Tom Kaminsky The ability to attract and retain people with valuable skills that meet business objectives is vital for companies seeking

More information

Presented By: Leah R. Smith, PMP. Ju ly, 2 011

Presented By: Leah R. Smith, PMP. Ju ly, 2 011 Presented By: Leah R. Smith, PMP Ju ly, 2 011 Business Intelligence is commonly defined as "the process of analyzing large amounts of corporate data, usually stored in large scale databases (such as a

More information

Data Governance. Unlocking Value and Controlling Risk. Data Governance. www.mindyourprivacy.com

Data Governance. Unlocking Value and Controlling Risk. Data Governance. www.mindyourprivacy.com Data Governance Unlocking Value and Controlling Risk 1 White Paper Data Governance Table of contents Introduction... 3 Data Governance Program Goals in light of Privacy... 4 Data Governance Program Pillars...

More information

Welcome to the Data Analytics Toolkit PowerPoint presentation on data governance. The complexity of healthcare delivery, the exploding demand for

Welcome to the Data Analytics Toolkit PowerPoint presentation on data governance. The complexity of healthcare delivery, the exploding demand for Welcome to the Data Analytics Toolkit PowerPoint presentation on data governance. The complexity of healthcare delivery, the exploding demand for actionable information, pressure for greater public accountability,

More information

Town of Bradford West Gwillimbury. Asset Management Strategy and Plan Project. Asset Management and IT Strategy Executive Summary

Town of Bradford West Gwillimbury. Asset Management Strategy and Plan Project. Asset Management and IT Strategy Executive Summary Town of Bradford West Gwillimbury Asset Management Strategy and Plan Project Asset Management and IT Strategy Executive Summary March 2012 Table of Contents Introduction 1 Project Objectives 1 The Town

More information

The Integrated Planning and Performance Framework

The Integrated Planning and Performance Framework The Integrated Planning and Performance Framework Issue This briefing note provides an overview of the City's Integrated Planning Multi-Year Budgeting and Performance Framework and addresses four major

More information

Essentials to Building a Winning Business Case for Tax Technology

Essentials to Building a Winning Business Case for Tax Technology Essentials to Building a Winning Business Case for Tax Technology The complexity of the tax function continues to evolve beyond manual and time-consuming processes. Technology has been essential in managing

More information

Project, Program & Portfolio Management Help Leading Firms Deliver Value

Project, Program & Portfolio Management Help Leading Firms Deliver Value in collaboration with Project, Program & Portfolio Help Leading Firms Deliver Value Managing Effectively & Efficiently Through an Enterprise PMO Program & Portfolio : Aligning IT Capabilities with Business

More information

Chapter 8: Common Treatment Facilities, Programs, Operational Improvements and Policies for the Recommended Plan

Chapter 8: Common Treatment Facilities, Programs, Operational Improvements and Policies for the Recommended Plan Chapter 8: Common Treatment Facilities, Programs, Operational Improvements and Policies for the Recommended Plan 8.1 Introduction The purpose of this chapter is to document the variety of treatment-related

More information

Information Technology Master Plan

Information Technology Master Plan Information Technology Master Plan Building the base for continued reliable service and products El Dorado Irrigation District Serving people, agriculture, businesses and the environment since 1925 Information

More information

ENTERPRISE PROJECT MANAGEMENT OFFICE

ENTERPRISE PROJECT MANAGEMENT OFFICE ENTERPRISE PROJECT MANAGEMENT OFFICE QUALITY MANAGEMENT SYSTEM ISO 9001:2008 STATE CHIEF INFORMATION OFFICER CHRIS ESTES DEPUTY STATE CHIEF INFORMATION OFFICER AARON WIENSHIENK DEPARTMENT MANAGER JAMES

More information

Capital Improvement Program: Public Input and the Need for a Multi-year Plan

Capital Improvement Program: Public Input and the Need for a Multi-year Plan Attachment 1 OFFICE OF THE INDEPENDENT BUDGET ANALYST REPORT Date Issued: September 21, 2012 IBA Report Number: 12-39 Budget and Finance Committee Docket Date: September 26, 2012 Item Number: 8 OVERVIEW

More information

Begin Your BI Journey

Begin Your BI Journey Begin Your BI Journey As part of long-term strategy, healthcare entities seek opportunities for continuous improvement in order to meet the changing needs of their patients while also maintaining compliance

More information

Kansas City s Overflow Control Program

Kansas City s Overflow Control Program Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Technical Management Strategic Capabilities Statement. Business Solutions for the Future

Technical Management Strategic Capabilities Statement. Business Solutions for the Future Technical Management Strategic Capabilities Statement Business Solutions for the Future When your business survival is at stake, you can t afford chances. So Don t. Think partnership think MTT Associates.

More information

WHAT DO YOU KNOW? HOW TO GET THE BEST INFORMATION OUT OF YOUR SYSTEM AND THE FOLKS THAT RUN IT.

WHAT DO YOU KNOW? HOW TO GET THE BEST INFORMATION OUT OF YOUR SYSTEM AND THE FOLKS THAT RUN IT. WHAT DO YOU KNOW? HOW TO GET THE BEST INFORMATION OUT OF YOUR SYSTEM AND THE FOLKS THAT RUN IT. ABSTRACT Steve Shoaf, City Of Asheville Nicholas Dierkes, Brown and Caldwell Understanding how well our Utilities

More information

Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified.

Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified. Asset management Your asset is your business. The more challenging the economy, the more valuable the asset becomes. Decisions are magnified. Risk is amplified. Data is about more than numbers. It tells

More information

Title: Lucent s ITSM Journey Session #: 299 Speaker: Sheila Bridge Company: Lucent Technologies, Inc.

Title: Lucent s ITSM Journey Session #: 299 Speaker: Sheila Bridge Company: Lucent Technologies, Inc. Title: Lucent s ITSM Journey Session #: 299 Speaker: Sheila Bridge Company: Lucent Technologies, Inc. Presentation Outline q Background q Foundation to Support Successful ITSM Implementation q ITSM Project

More information

Mergers and Acquisitions: The Data Dimension

Mergers and Acquisitions: The Data Dimension Global Excellence Mergers and Acquisitions: The Dimension A White Paper by Dr Walid el Abed CEO Trusted Intelligence Contents Preamble...............................................................3 The

More information

Audit of the Management of Projects within Employment and Social Development Canada

Audit of the Management of Projects within Employment and Social Development Canada Unclassified Internal Audit Services Branch Audit of the Management of Projects within Employment and Social Development Canada February 2014 SP-607-03-14E Internal Audit Services Branch (IASB) You can

More information

Client Onboarding Process Reengineering: Performance Management of Client Onboarding Programs

Client Onboarding Process Reengineering: Performance Management of Client Onboarding Programs KNOWLEDGENT INSIGHTS volume 1 no. 4 September 13, 2011 Client Onboarding Process Reengineering: Performance Management of Client Onboarding Programs In the midst of the worst economic environment since

More information

Guide on Developing a HRM Plan

Guide on Developing a HRM Plan Guide on Developing a HRM Plan Civil Service Branch June 1996 Table of Contents Introduction What is a HRM Plan? Critical Success Factors for Developing the HRM Plan A Shift in Mindset The HRM Plan in

More information

PUTTING IT ALL TOGETHER: INTEGRATING MASTER PLANNING WITH ASSET MANAGEMENT

PUTTING IT ALL TOGETHER: INTEGRATING MASTER PLANNING WITH ASSET MANAGEMENT PUTTING IT ALL TOGETHER: INTEGRATING MASTER PLANNING WITH ASSET MANAGEMENT Jeffrey B. Stillman, P.E., Practice Leader (Main Author/Presenter) Kevin T. Laptos, P.E., Regional Planning Leader Kent A. Lackey,

More information

How To Implement An Enterprise Resource Planning Program

How To Implement An Enterprise Resource Planning Program ERP Implementation Program Key phases of ERP implementation: Analysis of the company existing or designing new business process descriptions Inventory of the company s existing formal workflows or designing

More information

Roadmap to Energy Efficiency. for. Water and Wastewater Utilities

Roadmap to Energy Efficiency. for. Water and Wastewater Utilities Roadmap to Energy Efficiency for Water and Wastewater Utilities Prepared by: Howard Steiman, P.E. (hsteiman@rwbeck.com) and Paul Doran, P.E. (pdoran@rwbeck.com) R. W. Beck, Inc. 550 Cochituate Road Meditech

More information

CONSULTING SERVICES Managed IT services

CONSULTING SERVICES Managed IT services CONSULTING SERVICES Managed IT services CONSULTING SERVICES Organizations around the globe face an array of critical issues in today s business environment. Economic conditions are requiring significant

More information

Town of Greenwich. Strategic Technology Plan

Town of Greenwich. Strategic Technology Plan Town of Greenwich Strategic Technology Plan Executive Summary May 6, 2013 Prepared for: Town of Greenwich 101 Field Point Road Greenwich, CT 06830 PaSFge ihttp:// http://www.berrydunn.com/gcg Acknowledgements

More information

IBM 2010 校 园 蓝 色 加 油 站 之. 商 业 流 程 分 析 与 优 化 - Business Process Management and Optimization. Please input BU name. Hua Cheng chenghua@cn.ibm.

IBM 2010 校 园 蓝 色 加 油 站 之. 商 业 流 程 分 析 与 优 化 - Business Process Management and Optimization. Please input BU name. Hua Cheng chenghua@cn.ibm. Please input BU name IBM 2010 校 园 蓝 色 加 油 站 之 商 业 流 程 分 析 与 优 化 - Business Process Management and Optimization Hua Cheng chenghua@cn.ibm.com Agenda Why BPM What is BPM What is BAM How BAM helps optimization

More information

Business Intelligence and Corporate Performance Management Strategy Theory Of Constraints

Business Intelligence and Corporate Performance Management Strategy Theory Of Constraints HITACHI CONSULTING Business Intelligence and Corporate Performance Management Strategy Theory Of Constraints Prakash Jha, Hitachi Consulting 5/1/2008 This page intentionally left blank Page: 2 of 9 Contents

More information

[project.headway] Integrating Project HEADWAY And CMMI

[project.headway] Integrating Project HEADWAY And CMMI [project.headway] I N T E G R A T I O N S E R I E S Integrating Project HEADWAY And CMMI P R O J E C T H E A D W A Y W H I T E P A P E R Integrating Project HEADWAY And CMMI Introduction This white paper

More information

PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020

PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 PUBLIC WORKS DEPARTMENT STRATEGIC PLAN 2015 2020 1 Purpose of Strategic Plan This document serves as the road map for the Public Works Department. It identifies where we are going and how we are going

More information

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM

DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM DEVELOPMENT OF BEST MANAGEMENT PRACTICES TO EXECUTE A SUCCESSFUL CAPITAL IMPROVEMENT PROGRAM 2015 Business Plan Chapter 3, Water Facilities Focus Area, Goal Number 4 June 2011 CAPITAL IMPROVEMENT PROGRAM

More information

MANUSCRIPT THE DETROIT WATER AND SEWERAGE DEPARTMENT S PERFORMANCE AND DASHBOARD SYSTEM (PADS): STRATEGIES, ACTIONS, AND MEASURES FOR OPTIMAL RESULTS

MANUSCRIPT THE DETROIT WATER AND SEWERAGE DEPARTMENT S PERFORMANCE AND DASHBOARD SYSTEM (PADS): STRATEGIES, ACTIONS, AND MEASURES FOR OPTIMAL RESULTS ABSTRACT MANUSCRIPT THE DETROIT WATER AND SEWERAGE DEPARTMENT S PERFORMANCE AND DASHBOARD SYSTEM (PADS): STRATEGIES, ACTIONS, AND MEASURES FOR OPTIMAL RESULTS Authors: Ryan W. Nagel, Senior Consultant,

More information

SEWER CLEANING, INSPECTION AND ASSESSMENT

SEWER CLEANING, INSPECTION AND ASSESSMENT 3.1 OVERVIEW Chapter 3 SEWER CLEANING, INSPECTION AND ASSESSMENT Preventive maintenance protects the investment of the sanitary sewer collection system infrastructure. Higher frequency cleaning of gravity

More information

P3M3 Portfolio Management Self-Assessment

P3M3 Portfolio Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction

More information

Capital Improvement Program Monthly Status Report for June 2014

Capital Improvement Program Monthly Status Report for June 2014 Capital Improvement Program Monthly Status Report for June 2014 August 7, 2014 This report provides a summary of the progress and accomplishments of the Capital Improvement Program (CIP) for the San José-Santa

More information

Audit of the Test of Design of Entity-Level Controls

Audit of the Test of Design of Entity-Level Controls Audit of the Test of Design of Entity-Level Controls Canadian Grain Commission Audit & Evaluation Services Final Report March 2012 Canadian Grain Commission 0 Entity Level Controls 2011 Table of Contents

More information

REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE

REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE REQUEST FOR PROPOSALS SANITARY SEWER MAINTENANCE SERVICES FOR THE TOWN CENTER SEWER ASSESSMENT DISTRICT WITHIN THE TOWN OF WOODSIDE Submit Proposals to: Town of Woodside Public Works Department 2955 Woodside

More information

e-training Transition Project

e-training Transition Project e-training Transition Project Phase II e-training Communications Guide August 24, 2005 National Aeronautics and Space Administration Communications Guide for the Phase II e-training Transition August 24,

More information

Seven Ways To Help ERP IN 2014 AND BEYOND

Seven Ways To Help ERP IN 2014 AND BEYOND Seven Ways To Help Data Migration During Implementation SPECial REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION 3 Develop a Data MigraTION Plan 4 PerfORM a ThOROUgh Gap Analysis 6 COMMIT ResOURCes

More information

Department of Finance and Deregulation 2011/004 Portfolio Panels for IT Services ATTACHMENT A

Department of Finance and Deregulation 2011/004 Portfolio Panels for IT Services ATTACHMENT A 2011/004 Portfolio Panels for IT Services Definition of IT Services The definition for IT Services supports the Portfolio Panel Policy and reflects the Victorian eservices model. Key Service Category Management

More information

Effectively Managing EHR Projects: Guidelines for Successful Implementation

Effectively Managing EHR Projects: Guidelines for Successful Implementation Phoenix Health Systems Effectively Managing EHR Projects: Guidelines for Successful Implementation Introduction Effectively managing any EHR (Electronic Health Record) implementation can be challenging.

More information

Information Technology Project Management (ITPM)

Information Technology Project Management (ITPM) FUNCTIONAL AREA 10 Project Management (ITPM) Incumbents in this functional area direct information technology system solution and/or improvement projects for cost, time, scope, risk, and quality. They

More information

FWEA Utility Council Sanitary Sewer Overflow (SSO) Enforcement Policy Recommendations

FWEA Utility Council Sanitary Sewer Overflow (SSO) Enforcement Policy Recommendations FWEA Utility Council Sanitary Sewer Overflow (SSO) Enforcement Policy Recommendations Purpose and Objective The FWEA Utility Council formed the SSO Sub-Workgroup to provide a venue to discuss the increase

More information

The Top Five EHR Implementation and Integration Imperatives

The Top Five EHR Implementation and Integration Imperatives The Top Five EHR Implementation and Integration Imperatives How to Identify Them and Achieve Success Introduction Since the push to deploy electronic health records (EHRs) began in earnest with passage

More information

ASSET MANAGEMENT PLAN Published January 2009

ASSET MANAGEMENT PLAN Published January 2009 San Diego County Water Authority 2 0 1 1 ASSET MANAGEMENT PLAN Published January 2009 4677 Overland Avenue San Diego, CA 92123 858-522-6600 www.sdcwa.org This page intentionally left blank. Table of Contents

More information

Solutions Master Data Governance Model and Mechanism

Solutions Master Data Governance Model and Mechanism www.pwc.com Solutions Master Data Governance Model and Mechanism Executive summary Organizations worldwide are rapidly adopting various Master Data Management (MDM) solutions to address and overcome business

More information

CMMS/EAM. Maintenance Solutions

CMMS/EAM. Maintenance Solutions CMMS/EAM Maintenance Solutions Superior Functionality. Fully Integrated Solution. Maximum System Support. Maximize Critical Assets Maintenance Software Solutions For nearly 40 years, CHAMPS has remained

More information

COST EFFICIENCIES/PRODUCTIVITY

COST EFFICIENCIES/PRODUCTIVITY Updated: 0-0-0 EB-0-0 Schedule Page of 0 COST EFFICIENCIES/PRODUCTIVITY.0 INTRODUCTION Hydro One has updated this exhibit to improve the information on Cost Efficiencies and Productivity initiatives and

More information

Assessment of NCTD Program Management Framework for Positive Train Control Program

Assessment of NCTD Program Management Framework for Positive Train Control Program Assessment of NCTD Program Management Framework for Positive Train Control Program Subtask 2: Analysis Gap Analysis Prepared for: Brad Hansen, M.S., PMP Director, PMO Capital Projects May 2013 0 icfi.com/transportation

More information

EMA Service Catalog Assessment Service

EMA Service Catalog Assessment Service MORE INFORMATION: To learn more about the EMA Service Catalog, please contact the EMA Business Development team at +1.303.543.9500 or enterpriseit@enterprisemanagement.com The IT Service Catalog Aligning

More information

Overview of EAM Services. A Fully Integrated Global EAM Service Provider

Overview of EAM Services. A Fully Integrated Global EAM Service Provider A Fully Integrated Global EAM Service Provider Table of Contents Strategy & Process Services Overview... p. 3 Asset Reliability Services Overview... p. 4 Systems & Technology Services Overview... p. 7

More information

PERFORMANCE MANAGEMENT

PERFORMANCE MANAGEMENT PERFORMANCE MANAGEMENT integrated software solutions 01 EXECUTIVE SUMMARY SOLUTION OVERVIEW Concerto provides a secure, web-based solution incorporating complete project and programme performance management

More information

An Oracle White Paper August 2014. Oracle Hyperion Project Financial Planning: Aligning Financial and Project Plans

An Oracle White Paper August 2014. Oracle Hyperion Project Financial Planning: Aligning Financial and Project Plans An Oracle White Paper August 2014 Oracle Hyperion Project Financial Planning: Aligning Financial and Project Plans Introduction... 2 Project Financial Planning... 3 What Type of Project?... 3 Adding a

More information

Environmental Data Management, Analysis, and Compliance Systems - Rethinking the Creation and Use of Emissions Data by the Regulated Community

Environmental Data Management, Analysis, and Compliance Systems - Rethinking the Creation and Use of Emissions Data by the Regulated Community Environmental Data Management, Analysis, and Compliance Systems - Rethinking the Creation and Use of Emissions Data by the Regulated Community Robert Emigh, Ph.D. & Connie Prostko-Bell Windsor Technologies,

More information

IT Governance Overview

IT Governance Overview IT Governance Overview Contents Executive Summary... 3 What is IT Governance?... 4 Strategic Vision and IT Guiding Principles... 4 Campus-Wide IT Strategic Vision... 4 IT Guiding Principles... 4 The Scope

More information

ATTACHMENT B PROGRAM MANAGEMENT SERVICES BEXAR COUNTY FY 2007 - FY 2017 FLOOD CONTROL PROJECTS

ATTACHMENT B PROGRAM MANAGEMENT SERVICES BEXAR COUNTY FY 2007 - FY 2017 FLOOD CONTROL PROJECTS ATTACHMENT B PROGRAM MANAGEMENT SERVICES BEXAR COUNTY FY 2007 - FY 2017 FLOOD CONTROL PROJECTS The following scope of services for program management is an effort to provide an encompassing but not all

More information

PHASE 5: DESIGN PHASE

PHASE 5: DESIGN PHASE PHASE 5: DESIGN PHASE During the Design Phase, the system is designed to satisfy the requirements identified in the previous phases. The requirements identified in the Requirements Analysis Phase are transformed

More information

SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND

SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND SEVEN WAYS THAT BUSINESS PROCESS MANAGEMENT CAN IMPROVE YOUR ERP IMPLEMENTATION SPECIAL REPORT SERIES ERP IN 2014 AND BEYOND CONTENTS INTRODUCTION 3 EFFECTIVELY MANAGE THE SCOPE OF YOUR IMPLEMENTATION

More information

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES

2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES 2012 2016 Capital Improvement Plan City of Houston WASTEWATER TREATMENT FACILITIES The Wastewater Treatment System (System)

More information

Assessing Your Information Technology Organization

Assessing Your Information Technology Organization Assessing Your Information Technology Organization Are you running it like a business? By: James Murray, Partner Trey Robinson, Director Copyright 2009 by ScottMadden, Inc. All rights reserved. Assessing

More information

Durango Migrates its Infrastructure GIS to an Asset Management System

Durango Migrates its Infrastructure GIS to an Asset Management System Durango Migrates its Infrastructure GIS to an Asset Management System Rick Szmajter, GISP City of Durango Colorado ESRI International User Conference San Diego, CA July 22, 2015 rick.szmajter@durangogov.org

More information