The Inkosi Albert Luthuli Hospital. Cairo, May 25 26, 2008
|
|
|
- Stephanie Phillips
- 10 years ago
- Views:
Transcription
1 The South Africa PPP Program The Inkosi Albert Luthuli Hospital Transaction Cairo, May 25 26,
2 USAID Support ( ) to: Establish the PPP Unit (2000) Develop the policy/regulatory y framework for PPP Prepare guidelines and manuals on the regulatory requirements Establish a Project Development Fund to improve quality of PPP Build a portfolio of transactions Launch a highly effective stakeholder awareness campaign to educate the public and private sector in procurement requirements 2
3 The National Treasury's PPP Unit Develops, formulates, and promotes PPP policy Evolve as a dynamic and sustainable center of excellence for PPPs: Ensures that international best practice for PPP are followed Drives the flow of PPP deals Gives technical assistance to public institutions through project feasibility, procurement, and management Promotes an enabling environment for PPPs by: facilitating certainty in a regulatory framework developing best practices guidelines: National Treasury PPP Manual ; Standardized provisions of PPP/agreements providing training for both the public and private sectors disseminating reliable information driving black economic empowerment in PPPs 3
4 Regulatory framework for PPP 1999: Public Finance Management Act (PFMA): A Strategic Framework for Delivering Public Services through PPP National/provincial dep. accountable for value-for-money decisions and delivery National Treasury maintains budget oversight, guidance 2000: Treasury Regulation 16 for PPPs national departments provincial departments 2003: Municipal Finance Management Act: Provides for municipal PPPs and requires Treasury view and recommendations on their feasibility 2004: Code for BEE in PPPs provides for a BEE scorecard in each project, with targets in the private party's: Equity/Management and employment Subcontracting 4
5 Regulatory framework for PPPs Reg 16 A PPP is defined in South African law as: A contract between government institution and private party Private party performs an institutional function and/or uses state property in terms of output specifications for a significant period of time Substantial project risk (financial, technical, operational) transferred to the private party Private party benefits through: unitary payments from government budget and/or user fees The public sector retains a major role either as main purchaser of the services or as main enabler of the project. 5
6 Key PPP regulatory features Regulation 16 requires all PPP deals to obtain Treasury Approval (TA) for: Affordability Value-for-money Appropriate allocation of Risk Applied within set PPP project cycle: Inception Feasibility Procurement PPP agreement management 6
7 Several years ago the main issue in the PPP market was that too few deals had been closed. This has changed dramatically with eighteen successfully concluded PPP deals in the market. However, with new successes also come new challenges which need to be met head on. Today, one of the key challenges facing PPPs is ensuring that the concluded deals are successfully implemented 7 according to the terms of the final agreement Dec
8 PPP projects as of December Inception: 18 Feasibility: 26 Procurement: 6 Negotiations: 3 Closed deals since Treasury PPP Reg. in May 2000: 18 8 closed PPP deals prior to Treasury PPP Reg.: (N3 and N4 toll roads, two prisons, SANParks) 8
9 The Inkosi Albert Luthuli Hospital Sponsor: Kwa Zulu Natal Department of Health (DoH) A 846-bed, tertiary care, referral-only hospital situated in Durban Opened in June
10 The Inkosi Albert Luthuli Hospital The first hospital in South Africa to enter into a PPP for the delivery of all its non-clinical services It was also the first South African PPP to be conducted according to Treasury Regulation 16 and the first at the Provincial level The hospital provides highly specialized services for the entire population of KwaZulu Natal and half of the Eastern Cape Province (Population 12.5 million) The hospital is fully computerized and works on paperless principles. It uses leading-edge medical equipment, from MRIs to surgical instruments 10
11 Project Context Create a central hospital that was comparable to the best in the world, with the following constraints/needs in the public sector: Limited it funding within the KZN DoH for replacement of equipment; Lack of expertise within the public sector in facilities management; Lack of expertise within the public sector to sustain the IT systems; A public sector hospital management skills shortage, which made it desirable to outsource non-core functions so that the department could focus on the core medical functions of the hospital Need to ensure cutting edge technology 11
12 Scope of the PPP Project 15 year PPP/concession for the delivery of all the hospital s nonclinical services: supply of state-of-the-art the art equipment and information management and technology (IM&T) systems and replacing the equipment and IM&T systems so as to ensure that they remain state-of-the-art; supply and replacement of medical equipment; provision of all services necessary to manage the hospital s s assets in accordance with best industry practice; maintenance and replacement of the departmental assets in the hospital; provision or procurement of utilities and consumables and surgical instruments; and provision of facilities management (FM) services The hospital was built under a separate contract. However, the Project Company was responsible for the remedial works 12
13 Concessionaire Obligations Service levels based on outputs specification Outputs for medical equipment and IM&T had to be produced using state of the art equipment and industry best practices five-year replacement schedules for medical equipment three-year replacement schedules for IM&T The FM services have to be provided according to detailed output-based t specifications A complex and rigorously designed and essentially selfmonitoring penalty system ensures that any deviation from full service provision by the concession company is reflected in a series of payment deductions A help desk for effective end user contact, call logging, and service performance measurement tracking was required 13
14 Extensive IM&T facilities An electronic patient record; order-communications; on-line results reporting; electronic prescribing and recording of drug administration; theatre and out-patient scheduling systems; digital imaging; incorporated as a principle near-patient computing to support near patient testing. This required computer access at the bedside; IM&T links with secondary care (Other government hospitals) to facilitate direct bookings; and Started actively exploring the potential of tele-medicine 14
15 Risk Transfer Medical Equipment and IM&T Technology refreshment Obsolescence replacement Purchase cost including exchange and taxation risks Equipment performance/availability Maintenance costs Life of Equipment Hospital Buildings and Infra-structure Condition and availability of the IALCH building fabric/services and its required FM services performance upon commencement and during the term of the Project Agreement Whole life FM costs to include asset maintenance and replacement and FM service delivery in capital and revenue terms Condition of the IALCH buildings and infrastructure at the end Project 15
16 Project Costs Capital Investment (NPV): R1,560.5 m R947 m in the first year Operating Costs (NPV): R1,460 m Value for Money: R370 million over the Public Sector Comparator (PSC) constructed during the feasibility study stage 16
17 PPP Award Contract award in March 2001 to Impilo Consortium Treasury approval in line with the PFMA regulations was given in October 2001 Financial closure followed in early November 2001 Contract signed in December 2001 First patients on June
18 African PPP/Healthcare Deal of 2002 Monthly (FM) Service Payment R M/year Ithala Finance Corporation IMPILO Shareholders Quarterly (Capital Costs) 15-year PPP Contract R 360 M Int. free loan ROE R60 M Equity R326 M unsecured loan facility IMPILO Consortium Special Purpose Company Deferred Shares Cowslip Inv. (SPV) Payments (i + p) Lender: RAND MERCHANT BANK Provision of non-clinical services Inkosi Albert Luthuli Hospital
19 Financial Structure Upfront Payment = Once-off amount of R360m (including VAT). This amount was not adjusted for inflation; Interest-free loan from the KZN DoH (made via Cowslip, a special purpose vehicle created to channel the funds to the project from the government s Ithala Finance Corporation) The agreement specifies that the KZN DoH should have first ranking security over the assets Cowslip took a special class of equity, which allows it to take control of the Concessionaire in the event of default, thus ensuring immediate control over the assets for the continuance of clinical service provision. 19
20 Financial Structure Service Payment= R304.9m per annum (including VAT and in March 2002 terms), to escalate by CPIX and payable in: Monthly installments to cover FM costs Quarterly installments to cover capital refurbishment and replacement costs The fact that the escalation in the quarterly fee for the purchasing, replacement, and maintenance of IM&T and medical equipment is linked to CPIx means that, although there is a significant import component on equipment, both initially and during replenishment, the government did not accept any foreign currency risk 20
21 The Inkosi Albert Luthuli Hospital First PPP project to close in terms of the Public Finance Management Act PPP regulations; First of its scale and complexity to achieve financial close less than a year after announcement of the preferred bidder; and First project where investors and banks have had to take aepo provincial cagoe government e ced credit risk, s, without ouay any reliance on national government, other than the approval procedures as set out in the regulations 21
22 Thank You! 22
23 PPP Closed Transactions 23
24 Chapman s Peak Drive toll road Benefit to government: R450 million in capex and operations Signed: May 2003 Term: 30 years BEE: equity 30%; construction subcontract 10%; ops and maintain subcontract 50% 24 24
25 Free State social grants Value to government: R260 million Signed: April 2004 Term: 3 years BEE: equity 40%; subcontracting first year 30%, second year 35%, third year 45% 25 25
26 Department of Trade & Industry campus Value to government: R870 million Signed: Aug 2003 Term: 25 years BEE: equity 55%; construction subcontract 43%; facilities management 50% 26 26
27 Toll roads: N3, N4 east, N4 west Term: 30 years each N3 signed: May 1999; value: R3.5bn N4 east signed: Dec 1997; value: R3.0bn N4 west signed: Aug 2001; value: R 3.2bn 27 27
28 Department of Labour IT Value to government: R1.5 billion Signed: Dec 2002 Term: 10 years BEE: equity 30%; subcontracting 25% 28 28
29 Universitas and Pelonomi Hospitals Term: 16,5 years Signed: Nov 2002 BEE: equity 40%; subcontracting 40% 29 29
30 SANParks concessions Eleven concessions in four national parks Signed: 2001 to 2002 Terms: 20 years each Value: R270 million in fixed capital assets; NPV concession fees R253 million BEE: equity 20% plus; subcontracting 30% plus; 620 new jobs 30 30
31 Project inception Register the PPP with the relevant treasury; Inform the relevant treasury of the expertise within that institution to proceed with a PPP; Appoint a project officer from within or outside the institution; and Appoint a transaction advisor if the relevant treasury so requests PSC: R4.8 bill. Risk Adjusted PSC: 5.4 bill.
32 Lessons from project inception Learn from international expertise, especially if none is available locally Ensure that the transaction advisor is multi-disciplinary and contains experts in all fields necessary to the project PSC: R4.8 bill. Risk Adjusted PSC: 5.4 bill. 32
33 Traditional payment mechanism Example: Government office accommodation Government Payment Overruns CAPEX Construction/ ti development Delay costs Overruns Budgeted OPEX Time (years) 33
34 PPP payment Example: Government office accommodation Government Payment PPP unitary payment Construction Period No payment Operational period Payment against service delivery, linked to CPI-X Time (years) 34
35 35
36 Treasury s PPP feasibility approach Affordability limit 36
37 Agenda The South Africa PPP Unit South Africa s Regulatory framework for PPPs Generic PPP Project Life Cycle The Inkosi Albert Luthuli Hospital Transaction 37
38 Inkosi Albert Luthuli Hospital Value to government: R4.5 billion Signed: Dec 2001 Term: 15 years BEE: equity 40%; subcontracting 40% 38 38
39 PPP Objectives for KZN Department of Health Improved value for money by choosing Services on the basis of whole life costs Make service payments based on service availability Ensure that payments fall within the parameters of the KwaZulu-Natal Government's budget. The project had to be affordable Establish a replacement program for all equipment Transfer risk to the Project Company Ensure that DoH s commitment to BEE and development were met 39
PPP UNIT OF THE NATIONAL TREASURY. The Public Private Partnership between the
PPP UNIT OF THE NATIONAL TREASURY The Public Private Partnership between the KwaZulu Natal Department of Health and Impilo Consortium in Inkosi Albert Luthuli Central Hosptial Document Comparison by Wits
CODE OF GOOD PRACTICE. for BLACK ECONOMIC EMPOWERMENT PUBLIC-PRIVATE PARTNERSHIPS
NATIONAL TREASURY CODE OF GOOD PRACTICE for BLACK ECONOMIC EMPOWERMENT in PUBLIC-PRIVATE PARTNERSHIPS Following public consultation and incorporation of comments, the Code of Good Practice for Black Economic
BLOEMFONTEIN, SOUTH AFRICA. Case Study (Healthcare) Project Summary:
BLOEMFONTEIN, SOUTH AFRICA Case Study (Healthcare) Project Summary: The Republic of South Africa has a population of 48 million people, living in nine provinces. Since the abolition of apartheid in the
Public-Private Partnerships
Authors: Shadrack Shuping i Sipho Kabane ii 10 Public-Private Partnerships A Case Study of the Pelonomi and Universitas Hospital Co-Location Project Abstract Whilst there has been an increase in the number
Hospital Co-location, Bloemfontein, South Africa
1 Hospital Co-location, Bloemfontein, South Africa P R O J E C T S U M M A R Y The Republic of South Africa has a population of 48 million people living in nine provinces. Since the abolition of apartheid
2009 Ghana PPP Conference
2009 Ghana PPP Conference Public-Private Partnership for Social Services and Infrastructure 10 September 2009 An Authorised Financial Services Provider Agenda: Introduction to Rand Merchant Bank Debt &
Public Sector Comparator for Highway PPP Projects. Henry Kerali Lead Transport Specialist
Public Sector Comparator for Highway PPP Projects Henry Kerali Lead Transport Specialist Presentation Outline Purpose and Definition of PSC Basis for comparison between Public v. Private Valuing risk Characteristics
Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit
Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL XXXXX PPP Unit Chief Executive Officer Job Description: The CEO is tasked with the establishment of a PPP Unit for the Government
PUBLIC-PRIVATE PARTNERSHIP (PPP)
PUBLIC-PRIVATE PARTNERSHIP (PPP) Virginia Tan, Allen & Overy Type: Published: Last Updated: Keywords: Legal guide June 2012 June 2012 PPP, infrastructure assets, public and private sectors This document
Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending
Click to edit Master title style Infrastructure Ontario Borrowing Today for the City of Tomorrow Session #1 Steve Rohacek, Vice President, Municipal Business Development & Lending www.infrastructureontario.ca
T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities
PPP Modalities Types and characteristics of PPP are presented in several sections of the Toolkit: refer Types of PPP in Key Issues. This section provides some consideration of which modality, or which
PPP GLOSSARY. Availability. Base Case. Bidder BOOT BOT. Business Case. Commercial Operations Date (COD) Concession
PPP GLOSSARY Availability Base Case Bidder Bond BOOT BOT Term Business Case Capex Commercial Operations Date (COD) Concession Meaning The period when the facility (or the relevant part thereof) is able
NATIONAL TREASURY STRATEGIC PLAN 2011/14
NATIONAL TREASURY STRATEGIC PLAN 2011/14 PRESENTATION TO PARLIAMENTARY FINANCE COMMITTEES Presenter: Lungisa Fuzile Director General, National Treasury 31 May 2011 TREASURY AIMS AND OBJECTIVES Chapter
TERMS OF REFERENCE For the Provision of Long Term Advisor Services To the Government Technical Advisory Centre
TERMS OF REFERENCE For the Provision of Long Term Advisor Services To the Government Technical Advisory Centre Tender reference: GTAC : 004/2015 Contracting authority Name of project Accounting officer
1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution
Reducing Bid Costs for Outcome-Based Procurements in NSW Infrastructure and Structured Finance Unit: Partnering to Create Partnerships December 2015 1. Evolution of infrastructure procurement in NSW 2.
Public Private Partnerships
Office of the Comptroller General Practice Guideline 1 Public Private Partnerships Ministry of Finance May 2009 I. INTRODUCTION... 3 II. THE SUBSTANCE OF THE ARRANGEMENT... 7 III. FUNDING ANALYSIS... 9
PPP Seminar : Health Royal Liverpool Hospital Case study
PPP Seminar : Health Royal Liverpool Hospital Case study Gavin Quantock Deloitte Corporate Finance 23 July 2014 Case study Royal Liverpool hospital PPP and Health Background Deloitte involvement Structure
Governments implement PPP programmes in the healthcare sector for one or more of a number of reasons:
UNECE Healthcare PPP Project Team Project Brief Introduction This is a very active time globally for the healthcare sector as demand for services continues to grow exponentially, driven by rising life
PUBLIC PRIVATE PARTNERSHIP HANDBOOK
PUBLIC PRIVATE PARTNERSHIP HANDBOOK VERSION 2 March 2012 1 CONTENTS Section 1: Introduction to Public Private Partnerships... 3 1.1 What is Public Private Partnership?... 4 1.2 Typical PPP Delivery Models...
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
The Corporation of the City of London Quarterly Report on Internal Audit Results
www.pwc.com/ca The Corporation of the City of London Quarterly Report on Internal Audit Results - Corporate Services - IT: Project Management and System Prioritization February 13, 2014 Agenda Rating Scale
Introduction to Public-Private Partnerships (P3s)
Introduction to Public-Private Partnerships (P3s) Today s Instructor Patrick DeCorla-Souza P3 Program Manager Office of Innovative Program Delivery Program Development Team Course Outline Slide 2 Lesson
Infrastructure Development Funding and Financing
Infrastructure Development Funding and Financing 09 December 2013 2 Presentation outline 1. Role of infrastructure development 2. Public sector infrastructure investment 3. Funding options i. Recent airport
SUPPLEMENTARY GREEN BOOK GUIDANCE
SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance
PROJECT FINANCE & PPPs
PROJECT FINANCE & PPPs EIB Presentation, BOAD, 40 th Anniversary 1 14 November 2013 Definition of PPPs 1) An agreement between a government and one or more private partners whereby the private partner(s)
Financing PPPs: Project Finance June 2006
Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:
GAUTENG DEPARTMENT OF HEALTH
GAUTENG DEPARTMENT OF HEALTH CPSI HEALTH-SPECIFIC INNOVATIVE SOLUTIONS WORKSHOP 24 NOVEMBER 2015 DR. M.R. BILLA CEO: HELEN JOSEPH HOSPITAL Introduction OBJECTIVE: - Provide an overview on the TeleRadiology
Public Private Partnership in Hospitals
Public Private Partnership in Hospitals Presentation to the International Health Seminar Brazil - Canada October 20, 2010 2008 The Canadian Council for Public-Private Partnerships Overview Healthcare in
CONTRACT MANAGEMENT POLICY POLICY ADOPTED BY COUNCIL ON???? AT ITEM C.????
CONTRACT MANAGEMENT POLICY POLICY ADOPTED BY COUNCIL ON???? AT ITEM C.???? 1 1. PRE-AMBLE All transactions undertaken by the Cape Winelands District Municipality involves a contract whether explicitly
ASEAN Bilateral Program 2012
ASEAN Bilateral Program 2012 Presentation on PPP Financial Structures 30 October 2012 Contents Introduction Our PPP Experience Key Elements of a PPP Project Risk Allocation The Payment Mechanism Financing
Emerging Farmer Support Services
Emerging Farmer Support Services In order to make a success of his/her new farming venture, an emerging farmer requires the following support structures: a) Access to land and related resources like water;
for Central and Local Public Sector Bodies in Relation to the Procedures in the Agency for Public Private Partnership
for Central and Local Public Sector Bodies in Relation to the Procedures in the Agency for Public Private Partnership TWINNING LIGHT PROJECT HR/2007/IB/FI/03TL PPP Guide for Central and Local Public Sector
PUBLIC-PRIVATE PARTNERSHIP IN INFRASTRUCTURE
A GUIDEBOOK ON PUBLIC-PRIVATE PARTNERSHIP IN INFRASTRUCTURE ECONOMIC AND SOCIAL COMMISSION FOR ASIA AND THE PACIFIC This Guidebook was developed by Mr. Abdul Quium of the Transport Division of ESCAP. Its
The WA Experience: Public Private Partnerships (PPPs) March 2014
B The WA Experience: Public Private Partnerships (PPPs) March 2014 Dr D J Russell-Weisz Chief Executive Fiona Stanley Hospital Commissioning Delivering a Healthy WA PPPs Objectives are to motivate the
ACCOUNTING OFFICERS CHIEF FINANCIAL OFFICERS HEADS OF PROCUREMENT GUIDELINE FOR BID COMMITTEE MEMBERS
ACCOUNTING OFFICERS CHIEF FINANCIAL OFFICERS HEADS OF PROCUREMENT GUIDELINE FOR BID COMMITTEE MEMBERS Supply Chain Management Office Practice Note Number SCM-03 of 2005 1 Context The Public Finance Management
DBSA RENEWABLE ENERGY FINANCING
DBSA RENEWABLE ENERGY FINANCING Development Bank of Southern Africa Presented by Madalo Minofu Project Preparation Specialist: DBSA Project Preparation Funds Division 2 June 2014 1 DBSA s Product Offering
Defining Contract Management
Defining Contract Management Government must anticipate the contract management needs over the contract period. The main aspect to be emphasized under contract management is that this vital activity must
PPP Experience on the Canada Line
PPP Experience on the Canada Line International Practicum on Innovative Transit Funding & Financing June 13, 2014 Fred Cummings, P.Eng. President and General Manager BC Rapid Transit Co. Outline TransLink
P3 Business Case Development Guide
P3 Business Case Development Guide Improving the delivery of public infrastructure through public-private partnerships PPP Canada 100 Queen Street, Suite 630 Ottawa, Ontario K1P 1J9 Canada Tel: 613.947.9480
OTHER POSTS POST 20/37 : ASSISTANT DIRECTOR: HUMAN RESOURCES DEVELOPMENT, REF NO: MISA 15/2016
ANNEXURE I MUNICIPAL INFRASTRUCTURE SUPPORT AGENT The Municipal Infrastructure Support Agent (MISA) is a Government Component within the Ministry for Cooperative Governance and Traditional Affairs. It
PPP Basics and Principles of a PPP Framework
Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership
4.03. Brampton Civic Hospital Public-private Partnership Project. Chapter 4 Section. Background. Follow-up on VFM Section 3.03, 2008 Annual Report
Chapter 4 Section 4.03 Brampton Civic Hospital Public-private Partnership Project Follow-up on VFM Section 3.03, 2008 Annual Report Background In 2001, the then Minister of Finance announced that public
SPECIAL CONDITIONS OF CONTRACT RT20-2015
SPECIAL CONDITIONS OF CONTRACT RT20-2015 THE APPOINTMENT OF A PANEL OF PROFESSIONAL SERVICE PROVIDERS FOR FINANCIAL MANAGEMENT AND RELATED SERVICES FOR THE STATE PERIOD 1 SEPTEMBER 2015 TO 31 AUGUST 2018
The vision of the Department of Safety and Security is: A safe and secure environment for the people in KwaZulu-Natal.
VOTE 9 Safety and Security To be appropriated by Vote R16 355 000 Statutory amount Nil Total R16 355 000 Responsible MEC Minister of Safety and Security 1 Administrating department Department of Safety
Agreements, bonds and guarantees
Agreements, bonds and guarantees SPV Formation The Special Project Vehicle (SPV) may take a variety of forms, including a corporation, limited liability company, general partnership, limited partnership,
Supply Chain Management Policy September 2005
Supply Chain Management Policy September 2005 MUNICIPAL SUPPLY CHAIN MANAGEMENT POLICY LOCAL GOVERNMENT: MUNICIPAL FINANCE MANAGEMENT ACT, 2003 This policy was adopted by the Council of the ethekwini Municipality
Course Brochure. New York. Doha
Course Brochure LONDON New York Dubai Hong Kong Singapore Johannesburg Doha Aberdeen abuja kuala lumpur Table of contents Background page 3 Oil & Gas Faculty pages 5-8 Mining Faculty pages 9-11 Public
An Introduction to Public Private Partnerships. Updated June 2003
An Introduction to Public Private Partnerships Updated June 2003 Introduction Public private partnerships (P3s) are a key part of British Columbia s strategy to provide affordable infrastructure that meets
Public Private Partnerships
07 Public Private Partnerships 02 03 Healthcare UK: innovative approaches to extend healthcare services The UK was the first country in the world to develop the concept of public private partnerships (PPPs)*
Inkosi Albert Luthuli Central Hospital
HEALTH KWAZULU-NATAL Inkosi Albert Luthuli Central Hospital HEALTH KWAZULU-NATAL Inkosi Albert Luhuli Central Hospital 800 Bellair Road Cato Manor 4058 Tel: (031) 240 1000 Fax: (031) 240 1050 Email: [email protected]
ADVERTISEMENT DATE 3 December 2014 Marketing & Communications RFQ NUMBER JCPZ/RFQ/MKT14 2014 DATE)
QUOTATIONS ARE HEREBY REQUESTED IN ACCORDANCE WITH THE SCM REGULATIONS SECTION 18 OF THE LOCAL GOVERNMENT MUNICIPAL FINANCE MANAGEMENT ACT 56 OF 2003, FOR THE PURCHASE OF ITEM/S THAT COULD BE ABOVE R30
ANNUAL RESULTS for the year ended 30 June 2015
ANNUAL RESULTS for the year ended 30 June 2015 STRATEGIC & OPERATIONAL OVERVIEW Hyde Park Corner, Johannesburg, Gauteng 2 1 FINANCIAL HIGHLIGHTS 30 June 2015 30 June 2014 Change Distribution 543,0 cps
PREFERENTIAL PROCUREMENT POLICY FRAMEWORK ACT NO. 5 OF 2000
PREFERENTIAL PROCUREMENT POLICY FRAMEWORK ACT NO. 5 OF 2000 [View Regulation] [ASSENTED TO 2 FEBRUARY, 2000] [DATE OF COMMENCEMENT: 3 FEBRUARY, 2000] (English text signed by the President) ACT To give
Social Services for Victims of Domestic Violence: The Role of the Department of Social Development in the Implementation of the Domestic Violence Act
Social Services for Victims of Domestic Violence: The Role of the Department of Social Development in the Implementation of the Domestic Violence Act S. Sipamla 1. Introduction Following public hearings
DoE Supply Chain Management Processes
DoE Supply Chain Management Processes 16 September 2015 Presented by: Boitumelo Musi 1 Presentation overview Legislation and prescripts governing SCM in the Public Sector Supplier database registration
Values customer needs and works well within tight time deadlines. Commercially oriented to solve complex tax matters in a very efficient manner.
TAX Values customer needs and works well within tight time deadlines. Commercially oriented to solve complex tax matters in a very efficient manner. CHAMBERS GLOBAL 2015 PRACTICE OVERVIEW In a complex
Alberta Schools Alternative Procurement (ASAP) Projects. Public School Construction Program September 19, 2011 Baltimore, USA
Alberta Schools Alternative Procurement (ASAP) Projects Public School Construction Program September 19, 2011 Baltimore, USA Presentation Outline P3 s in Alberta - An Overview Alberta Schools (ASAP) Projects
SUPPLY CHAIN MANAGEMENT UNIT PROCUREMENT POLICY
SUPPLY CHAIN MANAGEMENT UNIT PROCUREMENT POLICY Signed by acting HOD wef 8 December 2008 PURPOSE 1. The purpose of the departmental procurement policy is to provide guidance within the Department regarding
PUBLIC FINANCE MANAGEMENT ACT, 1999: DRAFT TREASURY REGULATIONS
STAATSKOERANT, 30 NOVEMBER 2012 No. 35939 3 GENERAL NOTICE NOTICE 1005 OF 2012 NATIONAL TREASURY PUBLIC FINANCE MANAGEMENT ACT, 1999: DRAFT TREASURY REGULATIONS The draft Treasury Regulations are set out
Presentation to the KZN Exporter Week
Presentation to the KZN Exporter Week Chris Thirion Stakeholder Management & Marketing 17 November 2014 ECIC Environment Self-sustained state-owned public entity registered as a Schedule 3 (b) business
Value for Money Assessment Guidance: Capital Programmes and Projects
Value for Money Assessment Guidance: Capital Programmes and Projects October 2011 Value for Money Assessment Guidance: Capital Programmes and Projects Foreword This guidance has been prepared and issued
Guide on Hourly Fee Rates for Consultants
Guide on Hourly Fee Rates for Consultants Department of Public Service and Administration January 2003 Table of Contents 1 INTRODUCTION...3 2 SCOPE AND CONCEPT CLARIFICATION...4 3 METHOD FOR DETERMINING
CRITICALITY LEVEL: LOW MEDIUM HIGH RISK ASSESSMENT TYPE: INFORMAL/FORMAL TEAM/INDIVIDUAL BASED COMPILED BY DESIGNATION SIGNATURE DATE
PREFERENTIAL PROCUREMENT POLICY POLICY FOR THE PREFERENTIAL PROCUREMENT OF GOODS, SERVICES AND EQUIPMENT IN SUPPORT OF LOCAL PROCUREMENT AND BLACK ECONOMIC EMPOWERMENT INITIATIVES CUSTODIAN : HEAD: SA
Case Study Royal Children s Hospital
Philippine-Australia PPP Policy Dialogue Case Study Royal Children s Hospital Tony Lubofsky Project Director Victorian Comprehensive Cancer Centre RCH Project Scope Construction
Request for Quotation: Hosting and Pay Per Click Campaign: Shisa Solar
ENERGY OFFICE 19th Floor, 75 Dr Langalibalele Dube Street, Durban, 4001 P O Box 1014, Durban 4000 Tel: +27 31 311 1139, Fax; +27 31 311 1089 Email: [email protected] www.durban.gov.za 30 th September
Please send your responses via email, to: [email protected]. Respondent details. Mark Redhead. Head of Policy
REFORM OF THE PRIVATE FINANCE INITIATIVE RESPONSE Please send your responses via email, to: [email protected] The deadline for responses is Friday 10 February 2012. Respondent details Your
PPP Practioner s Notes
PPP Practioner s Notes Capacity Challenges in PPP Program and Contract Management Mariana Abrantes de Sousa PPP DAYS 2012 UNECE Geneva Key issues in PPP program and contract management Functions of the
PRO FORMA FINANCIAL EFFECTS
SIBANYE GOLD LIMITED (Incorporated in the Republic of South Africa) (Registration number 2002/031431/06) Share code: SGL ISIN: ZAE000173951 Issuer code: SGL ("Sibanye" or "the Company") WESTONARIA [15
PROJECT FINANCE UNCDF October 2014 Dar Es Salaam
Project Finance PROJECT FINANCE UNCDF October 2014 Dar Es Salaam AGENDA History and Definition Structure of Project Finance Transactions Key Players Milestones Role of Debt in PF transactions Risk Management
Report of the Auditor-General of South Africa to Parliament on a performance audit of the infrastructure delivery process at the provincial
Report of the Auditor-General of South Africa to Parliament on a performance audit of the infrastructure delivery process at the provincial departments of Education and Health August 2011 Report of the
Gary Cooke, Cabinet Member for Corporate and Democratic Services. Rebecca Spore, Director of Infrastructure
From: Gary Cooke, Cabinet Member for Corporate and Democratic Services Rebecca Spore, Director of Infrastructure To: Subject: Classification: The Policy and Resources Cabinet Committee Total Facilities
African Bank Investments Limited Strategies to grow in the mass market
African Bank Investments Limited Strategies to grow in the mass market June 2007 Presentation agenda Who we are Our target market A transforming business Is this a good time to be in this market? Outlook
VACANCY. PORTFOLIO MANAGER (SOCIAL INFRASTRUCTURE) x1 JOB LEVEL: 5 PORTFOLIO:
VACANCY POSITION: DURATION REGION: PORTFOLIO: PORTFOLIO MANAGER (SOCIAL INFRASTRUCTURE) x1 3 YEAR CONTRACT KWAZULU NATAL DSU JOB LEVEL: 5 PURPOSE: To manage regional operations, direct regional portfolio
Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships
EMAIL [email protected] WEB www.fosterinfrastructure.com Comparative Study of Frameworks to protect the Long Term Interests of Pension Funds Investing in Public-Private Partnerships Pty
ADVERTISEMENT DATE 04 December 2013 CRM & Customer Interface Management DATE)
QUOTATIONS ARE HEREBY REQUESTED IN ACCORDANCE WITH THE SCM REGULATIONS SECTION 18 OF THE LOCAL GOVERNMENT MUNICIPAL FINANCE MANAGEMENT ACT 56 OF 2003, FOR THE PURCHASE OF ITEM/S THAT COULD BE ABOVE R30
RULES AND REGULATIONS FOR FINANCING PROJECTS AND COMMERCIAL ACTIVITIES
Page 1 of 8 Section 1. Purpose These Rules and Regulations are adopted by the Board of Governors pursuant to Article 13.3. of the Agreement Establishing the Black Sea Trade and Development Bank (Establishing
Asia s infrastructure trends and Case Study discussions
www.pwc.com Asia s infrastructure trends and Case Study discussions Lee Seng Chee Partner Capital Projects and Infrastructure October 2014 Contents Section 1: Asia s infrastructure trends and the Singapore
MANAGING RISK IN EMERGING MARKETS OUR CORE BUSINESS
MANAGING RISK IN EMERGING MARKETS OUR CORE BUSINESS Fiscal Year 2014 PROVEN TRACK RECORD 58 Years of profitable investments in emerging markets $67b $51.7b $15.3b $22.4b $17.3b $5.1b $1.5b Diversified
Guidelines on the preparation of Quarterly Reports for Public Entities. and Constitutional Institutions
Guidelines on the preparation of Quarterly Reports for Public Entities and Constitutional Institutions CONTENTS 1. INTRODUCTION 3 2. BACKGROUND 4 2.1. Current requirements for quarterly reporting... 4
Addressing Risk in Partner / Contractor Selection and Onboarding. Michael Davidson VP Quality Systems and Compliance March 2014
Addressing Risk in Partner / Contractor Selection and Onboarding Michael Davidson VP Quality Systems and Compliance March 2014 Industry Trends Pfizer Overview Pfizer s Approach Risk Based Robust Due Diligence
DEPARTMENT OF TRANSPORT
ANNEXURE L DEPARTMENT OF TRANSPORT Department of Transport is an equal opportunity, affirmative action employer with clear employment equity targets. Women and people with disabilities are encouraged to
PPP in Australia: Hospital Sector Case Study
PPP in Australia: Hospital Sector Case Study Richard Foster Executive Manager, Partnerships Victoria Kylee Anastasi Consultant, World Bank Institute Knowledge Sharing on Infrastructure - Public Private
private finance initiative
private finance initiative Lessons Learned We recently held a series of PFI Roundtable Discussions in collaboration with Trowers & Hamlins LLP. Finance managers from throughout the UK were invited to share
City of Cape Town. Supply Chain Management
City of Cape Town Supply Chain Management Processes Presented by: Leonard Shnaps A Walk Through Legal Framework SCM Conceptualised Demand Planning Supplier Management Tenders Procurement Website Unsolicited
DEVELOPMENT OF A NATIONAL EHEALTH STRATEGY FOR SOUTH AFRICA
DEVELOPMENT OF A NATIONAL EHEALTH STRATEGY FOR SOUTH AFRICA WHO-ITU MEETING, NATIONAL ehealth STRATEGY DEVELOPMENT: COUNTRY EXPERIENCE AND NEXT STEPS 24-26 JULY 1 2 1. BACKGROUND (1) The National Department
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2
FOR USE WITH PPP PROJECTS 1 SAMPLE GUIDELINES FOR PRE-QUALIFICATION AND COMPETITIVE BIDDING PROCESS 2 1. PRE-QUALIFICATION 1.1 The requirements for pre-qualifications will be reasonable and efficient and
MUNICIPAL SUPPLY CHAIN MANAGEMENT POLICY
MUNICIPAL SUPPLY CHAIN MANAGEMENT POLICY This Municipal Supply Chain Management Policy is based on the model policy made available by the National Treasury: MFMA Circular 22 dated 25 August 2005. NOTE:
Gebze Izmir Motorway & Izmit Bay Crossing Project
Gebze Izmir Motorway & Izmit Bay Crossing Project F.Mehmet Coşan CFO Haluk BÜYÜKBAŞ Secretary General, TCA Gebze Orhangazi Izmir Project is the landmark transaction for the infrastructure sector in Turkey
HICL Infrastructure Company Limited. Case Study. Queen Alexandra Hospital. September 2010. www.hicl.com 1
HICL Infrastructure Company Limited Case Study Queen Alexandra Hospital September 2010 www.hicl.com 1 Queen Alexandra Hospital ( QAH ) a PFI project case study Queen Alexandra Hospital ( QAH ) PFI project
