Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs
|
|
|
- Donald Rich
- 9 years ago
- Views:
Transcription
1 Buildings 01,, 0-1; doi:10.90/buildings000 Review OPEN ACCESS buildings ISSN Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs Nuhu Braimah Civil Engineering Department, School of Engineering and Design, Brunel University, Uxbridge, Middlesex UB8 PH, UK; [email protected]; Tel.: ; Fax: Received: 8 May 01; in revised form: 1 July 01 / Accepted: 18 July 01 / Published: July 01 Abstract: The time for performance of a project is usually of the essence to the employer and the contractor. This has made it quite imperative for contracting parties to analyse project delays for purposes of making right decisions on potential time and/or cost compensation claims. Over the years, existing delay analysis techniques (DATs) for aiding this decision-making have been helpful but have not succeeded in curbing the high incidence of disputes associated with delay claims resolutions. A major source of the disputes lies with the limitations and capabilities of the techniques in their practical use. Developing a good knowledge of these aspects of the techniques is of paramount importance in understanding the real problematic issues involved and their improvement needs. This paper seeks to develop such knowledge and understanding (as part of a wider research work) via: an evaluation of the most common DATs based on a case study, a review of the key relevant issues often not addressed by the techniques, and the necessary improvements needs. The evaluation confirmed that the various techniques yield different analysis results for the same delay claims scenario, mainly due to their unique application procedures. The issues that are often ignored in the analysis but would also affect delay analysis results are: functionality of the programming software employed for the analysis, resource loading and levelling requirements, resolving concurrent delays, and delay-pacing strategy. Improvement needs by way of incorporating these issues in the analysis and focusing on them in future research work are the key recommendations of the study. Keywords: delay analysis; construction claims; extension of time; scheduling; damages
2 Buildings 01, Introduction The duration of contract performance has a direct effect on the profitability of construction projects from the perspective of all stakeholders [1,]. For project owners, lost profits or benefits stem from being unable to make use of the project at the agreed date whilst to the contractor, extra cost will be incurred due to prolonged stay on site. Most standard forms of contract thus have provisions that anticipate delay brought about by the actions and/or inactions of the contractor, the owner or are outside the control of both parties. The contractor is often excused from the consequences and/or allowed compensation for any costs due to delays resulting from events or circumstances that are beyond its control. Contractual provisions also allow the owner to recover liquidated damages from the contractor for failure to deliver the project within the contract performance period. Liquidated damages clauses entitle the owner to recovery of a specified sum of money for each day or week of culpable delay. In both instances, a detailed schedule analysis is required to investigate the events that have actually caused the project to overrun. Over the years, owners and contractors have used various Delay Analysis Techniques (DATs) to achieve this. However, in the vast majority of cases, the parties are not able to settle delay claims amicably resulting in costly disputes after project completion [ ]. Consequently, delay claims are now a major source of conflict in the construction industry and also one of the most difficult to resolve [ 8]. This has generated considerable initiatives from researchers and industry practitioners aimed at enhancing the application of existing DATs (see for example, [,9 1]) and the development of good practice documents for providing guidance to practitioners on what the best application of the various techniques entails and the circumstances that dictate their proper use. Of such documents, the most notable are the Delay and Disruption Protocol [7] developed by the UK s Society of Construction Law and Recommended Practice on Forensic Schedule Analysis by the Association for Advancement of Cost Engineering International [1] of the USA. In spite of the many contributions, proper analysis of delay claims which take into consideration the effect of a number of scheduling and delay issues is often lacking in practice [8,1,17]. Therefore, the need for greater awareness and incorporation of these issues in delay analysis is crucial to ensuring fairness and amicable resolution of delay claims. As part of a wider study aimed at addressing these issues, the purpose of this paper is to: discuss the most common existing DATs, as well as review the issues that are often missed in the analysis, and the required improvement needs. The scope of this wider study involves investigating the techniques applications (in theory and in practice) thoroughly with the view to developing an appropriate framework for enhancing their proper usage, in order to help reduce the frequent delay claims resolution difficulties. This paper s presentation on DATs, as detailed in the next section, was done based on a hypothetical case study so as to clearly demonstrate the application processes of the techniques and their weaknesses in presenting (or defending) delay claims.. Existing Delay Analysis Techniques The objective of delay analysis is to calculate the project delay and work backwards to try to identify how much of it is attributable to each party (contractor, owner, or neither) so that time and/or cost compensation can be decided. Questions that need to be answered here often include [,18]:
3 Buildings 01, 08 what was supposed to happen? what did actually happen? what were the variances? how did they affect the project schedule? The various DATs have varying capabilities in providing sound answers to these questions. The techniques can be grouped under non-critical Path Method (CPM)-based techniques and CPM-based techniques. They have been reported by different authors in the literature using different names, with the most common techniques being: as-planned vs. As-built, impacted as-planned, as-planned but for, collapsed as-built, window analysis, and time impact analysis (see, for example, [ 8,19 ]).. A Case Study Project To critically evaluate the existing techniques, a simple case study has been designed and simulated with various delay scenarios. The case study project involves the construction of a small garage with the necessary approach drive-in, as shown in the network diagram of Figure 1, adopted from Pilcher []. Figure 1. Arrow diagram of the case-study project. The as-planned programme of this project (in bar chart format for clarity) is as shown in Figure, indicating a total project duration of 0 days. The as-planned critical path, indicated in red bars, flows through activities of the garage structure, with a -day float on the path of drive-in activities. The project started as scheduled but progress was affected by three main types of delay events: (1) Events for which the contractor assumes the risks of costs and the time consequences involved, which are often categorised as Nonexcusable Noncompensable delays (NN); () events for which the contractor is entitled to both time extensions and recovery of extra cost consequential upon the delay [ Excusable Compensable delays (EC)]; and finally, () those events for which no party has control over or bears the risks involved, (e.g., acts of God and strikes), which are often termed as Excusable Non-compensable (EN) delays.
4 Buildings 01, 09 Figure. As-planned schedule. Act. ID Activity Description Original duration Days GARAGE G1 Excavate foundation G G G Concrete foundation Brickwork to 1m high Brickwork to roof level 1 Completion date G Concrete to floor slab G Fix roof structure G7 Waterproof roof G8 Fix doors G9 Paint and clean up DRIVE-IN D1 Clear and excavate for drive-in 1 D Hardcore base to drive 10 D Tarmacadam to drive-in Table 1 below defines the delay scenarios encountered in the hypothetical project. The as-built schedule, which includes all delays that occurred during construction of the project, had total project duration of 1 days and a critical path along the drive-in activities (see Figure ). To distinguish between the various delays, EC delays are indicated in dark horizontal strips and NN delays in dark diagonal strips. Apart from the delays, there were also changes in the planned sequence between some of the activities. The as-built programme thus shows start start logic with lag of days between the first two activities of the garage instead of the originally planned finish start relationship. Similar logic with a lag of days exists between the first two activities of the drive-in. Figure. As-built schedule. Act. ID Activity Description Actual duration Days GARAGE G1 Excavate foundation G Concrete foundation G Brickwork to 1m high G Brickwork to roof level 17 G G G7 Concrete to floor slab Fix roof structure Waterproof roof Actual completion date G8 Fix doors G9 Paint and clean up DRIVE-IN D1 Clear and excavate for drive-in D Hardcore base to drive 19 D Tarmacadam to drive-in 9
5 Buildings 01, 10 Activity As planned duration Chronology of delays Table 1. Delays events that affected the sample project. Delay information Description Type Start date (day) End date (day) Concrete Contractor had a labour problem 1 foundations (G) so it took days extra to complete activity G. NN 9 Clear and excavate Contractor encountered unforeseen adverse ground 1 for drive-in (D1) condition during excavation of the drive-in. EC Activity G did not start immediately Brickwork to 1 after completion of its predecessor as-planned roof level (G) due to 1-day delay by the contractor s brick supplier. NN Contractor advised the owner on the Concrete to need to increase the thickness of the floor slab. This floor slab (G) change required 1 extra day to accomplish. EC After days of working on activity D, the owner Hardcore base 10 suspended works for days as a decision on the suitability to drive-in (D) of the hardcore material was being made. EC 8 The owner ordered the contractor to Brickwork to 1 add an extra window after the completion of G. roof level (G) This design change caused -day delay. EC 0 A quality control test revealed that certain sections of the Hardcore base 10 7 drive-in base were poorly constructed. This defective to drive-in (D) work resulted in days of rework by the contractor. NN 1 There was a -day delay by the owner Tarmacadam to 8 in making available to the contractor an drive-in (D) owner-furnished equipment for activity D EC 8 Waterproof roof (G7) 9 It took the contractor more days to complete activity G. NN 0 Fix doors (G8) 10 The owner changed his mind on the type of door used for the garage so ordered the contractor to make changes. This caused extra days of work. EC 0 Duration (days)
6 Buildings 01, 11. Project Delay Analysis Using the Various Techniques.1. As-Planned vs. As-Built Under this method, all delaying events (EC, EN and NN delays) encountered on the project are depicted on the as-built schedule. The difference between the as-planned and as-built completion dates is the amount of time for which the claimant will request for compensation. The critical path is determined once in the as-planned and again in the as-built schedule [8,]. This technique and the net impact technique utilising bar chart are similar in that they all show the net effect of all claimed delays. By the approach of Stumpf [], the following illustrates the allocation of delay responsibility between the owner and the contractor for the sample project. Sum of contractor-caused delays (NN) = ΣNN i = = 1 days (see Table 1); Sum of owner-caused delays (EC) = ΣEC i = = 1 days (see Table 1). From the above, the assumption is that concurrent delay due to both parties is 1 days ( i.e., the lower of the above two types of delays). Therefore, net project delays for which the owner is responsible = 1 1 = 9 days; From Figures and, the net total project delay = 1 0 = 11 days, the balance is the contractor responsibility, which is 11 9 = days. The limitations of this methodology are: it does not scrutinize delay types and this makes it easy for it to be manipulated and distorted to reflect either the position of the claimant or the defendant; it ignores the dynamic nature of the critical path and any changes in schedule logic [0,,]; no attempt is made to determine the individual impact of each delay on the project completion. All delays, including delays on non-critical path, were summed up and their net effect calculated. Figure. As-built schedule with delays. Act. ID Activity Description Planned Delay duration duration GARAGE G1 G G G G G G7 G8 G9 Excavate foundation Concrete foundation Brickwork to 1m high Brickwork to roof level Concrete to floor slab Fix roof structure Waterproof roof Fix doors Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in Days NN= EC=7 NN=1 EC=1 EC= EC= NN= NN= EC= EC= Actual completion date
7 Buildings 01, 1.. Impacted As-Planned This method measures the impact of the delays on the contractor s as-planned CPM schedule. The various delays are formulated as activities and added to the as-planned network in a chronological order showing the effect of each delay at a time and demonstrating how the project is being delayed [7]. The amount of delay equals the difference in completion dates between the schedules before and after the impacts. The technique can be used for analysis of delay during and after project completion. Delay analysis of the sample project using this technique was carried out by sequential addition of the delays to the as-planned schedule. The impact of each delay is as shown in Figures 1 below. Figure. Impact of first delay. Act. ID Activity Description Planned Delay duration duration GARAGE Days G1 G Excavate foundation Concrete foundation As-planned completion G G G Brickwork to 1m high Brickwork to roof level Concrete to floor slab 1 G G7 Fix roof structure Waterproof roof Delay=days G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in 1 10 Figure. Impact of second delay. Act. ID Activity Description Planned Delay duration duration GARAGE Days G1 Excavate foundation G Concrete foundation G G G G Brickwork to 1m high Brickwork to roof level Concrete to floor slab Fix roof structure 1 delay =0 (completion date same as previous schedule) G7 Waterproof roof G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in
8 Buildings 01, 1 Figure 7. Impact of third delay. Act. ID Activity Description Planned Delay duration duration GARAGE Days G1 G Excavate foundation Concrete foundation Previous completion date G G G Brickwork to 1m high Brickwork to roof level Concrete to floor slab 1 1 Delay = 1day G Fix roof structure G7 Waterproof roof New completion date G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in Figure 8. Impact of fourth delay. Act. ID Activity Description Planned Delay duration duration GARAGE G1 Excavate foundation Days G G G G G Concrete foundation Brickwork to 1m high Brickwork to roof level Concrete to floor slab Fix roof structure Completion date same as previous schedule Delay = 0 G7 Waterproof roof G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in
9 Buildings 01, 1 Figure 9. Impact of fifth delay. Act. ID Activity Description Planned Delay duration duration GARAGE G1 Excavate foundation G Concrete foundation G Brickwork to 1m high G Brickwork to roof level 1 1 G Concrete to floor slab 1 Days previous completion date Delay = 1 day 0 0 G G7 Fix roof structure Waterproof roof New completion date G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in Figure 10. Impact of sixth delay. Act. ID Activity Description Planned Delay duration duration GARAGE G1 Excavate foundation G Concrete foundation G Brickwork to 1m high G Brickwork to roof level 1 1+ G Concrete to floor slab 1 Days previous completion date 0 0 Delay = 1 day G G7 Fix roof structure Waterproof roof New completion date G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in
10 Buildings 01, 1 Figure 11. Impact of seventh delay. Act. ID Activity Description Planned Delay duration duration GARAGE G1 Excavate foundation G Concrete foundation G Brickwork to 1m high G Brickwork to roof level 1 1+ G Concrete to floor slab 1 Days previous completion date 0 0 Delay = days G G7 Fix roof structure Waterproof roof New completion date G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in Figure 1. Impact of eighth delay. Act. ID Activity Description Planned Delay duration duration GARAGE G1 Excavate foundation G Concrete foundation G Brickwork to 1m high G Brickwork to roof level 1 1+ G Concrete to floor slab 1 Days previous completion date 0 0 Delay = days G G7 Fix roof structure Waterproof roof New Completion date G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in
11 Buildings 01, 1 Figure 1. Impact of ninth and tenth delays. The first delay (NN = ) was on the critical path, G1-G-G-G-G-G7-G8-G9 so it caused days of slippage to the as-planned programme. The second, fourth, ninth and tenth delays were on non-critical paths so their impacts did not cause any slippage. The impacts of fifth, seventh and eighth delays caused project slippage on the critical path, D1-D-D-G9. A summary of the results obtained are as shown in Table. Table. Impacted as-planned results. Chronology of delays Activity Delay Type Duration (days) Impact (days) 1 G NN D1 EC 7 0 G NN 1 1 G EC 1 0 D EC 1 G EC 1 7 D NN 8 D EC 9 and 10 G7 and G8 NN and EC and 0 From Table, the owner is responsible for six days of delay to the project whilst the contractor is responsible for 8 days. The sum of these delays is greater than the actual project delay of 11 delays because of the failure of this technique to consider any changes in the as-planned programme, which is by maintaining the original finished start relationship of all activities in the analyses. The limitations of this method include the following: it uses fixed as-planned schedule to analyse delays out of context and time [,];
12 Buildings 01, 17 the original baseline programme may not be a realistic model on which to base the whole analysis; it has the potential of failing to consider the delays of all parties especially that of the claimant ( i.e., being one-sided); potential disputes over the adequacy of the as-planned schedule because it is not economically possible, nor does it makes sense, to schedule the entire project in detail at its inception []... As-Planned But for This method entails injecting the as-planned schedules with all the delays of a particular party to form an adjusted schedule. The completion date of this adjusted as-planned schedule compared with the actual completion date gives the amount of delay for which the other party is responsible [8,19,]. A contractor using this method would identify and add all non-excusable delays to the as-planned schedule, whereas the owner would add all excusable delays. The advantage of this method is that it can be performed quickly because there is no need to consider actual progress of the work. This technique is applied to the sample project first for contractor s point of view and then for owner s point of view. Contractor s point of view: Under this, all the contractor-caused delays were impacted on the as-planned schedule. This resulted in an adjusted as-planned schedule with completion date as day 7 and G1-G-G-G-G-G7-G8-G9 as the critical path (see Figure 1 below). With the actual completion date as day 1, the owner is responsible for days project delay, which could be charged as compensable delay. The amount of delay for which the contractor is responsible is 7 0 = 7 days, where 0 is the original as-planned completion date. Figure 1. As-planned schedule impacted with contractor s delays. Owner s point of view: Under this, all the owner-caused delays were impacted on the as-planned schedule. This resulted in an adjusted as-planned schedule with completion date as day 9
13 Buildings 01, 18 and D1-D-D-G9 as the critical path (see Figure 1 below). With actual completion date as day 1, the contractor is responsible for days project delay, which could be charged for liquidated damages by the owner. The owner is then responsible for the difference between the adjusted schedule and the original completion date, i.e., 9 0 = 9 days. Figure 1. As-planned schedule impacted with owner s delays. The limitations of this method include the following: it does not take into account any changes in the critical path schedule during the course of the project [19]; it assumes that the planned construction sequence remains valid during the project duration []; owner s point of view and contractor s point of view may yield different results resulting in disputes (as this case shows)... Collapsed As-Built In principle, this method is a form of but for which does not use the as-planned as a baseline schedule, but rather uses the as-built schedule (and thus also referred to as as-built but for technique). It involves removing the delays of each party from the as-built network so that the resulting schedule will give the completion date of the project but for the delays of the other party [18,]. Like the previous technique, this technique is applied to the sample project first for contractor s point of view and then for owner s point of view as follows: Contractor s point of view: Under this, all owner-caused delays were subtracted from the as-built schedule resulting in a collapsed as-built schedule of completion date as day and critical path G1-G-G-G-G-G7-G8-G9 (see Figure 1).
14 Buildings 01, 19 Figure 1. As-built schedule with owner s delays subtracted. With actual completion date as day 1, the owner is responsible for days of the (1 ) project delay, which could be charged as compensable delay. Comparing the collapsed as-built schedule with the original schedule gives 0 = days project delay, as caused by the contractor. Owner s point of view: Under this, all contractor-caused delays were subtracted from the as-built schedule resulting in a collapsed as-built schedule of completion date as day and critical path D1-D-D-G9 (see Figure 17). With actual completion date as day 1, the contractor is responsible for days of project delay, which could be charged for liquidated damages. Comparing the collapsed as-built schedule with the original schedule gives 0 = days project delay as that caused by the owner. Figure 17. As-built schedule with contractor s delays subtracted. This technique and the as-planned but for could give similar results if the planned logic remains unchanged in the course of the project. The perceived advantage of this technique is that it is based on actual events on the project, making it one of the techniques of high credibility []. However, its shortcomings include the following:
15 Buildings 01, 0 in collapsing the schedule, the analyst is typically forced to insert after-the-fact logic ties which may not reflect the thinking of the executor of the schedule during actual performance []; the removal of the delays from the schedule could result in an unrealistic as-built but-for schedule, particularly when the schedule sequence has been so much impacted by those delays; adjusting the collapsed schedule to suit what the contractor is likely to follow requires experience and sound judgement beyond the capability of most analysts [18]; it ignores the circumstances at the time of the delay and the dynamic nature of the critical path; the identification of the as-built critical path requires great deal of effort on judgement and schedule manipulation [0]; the use of as-built information to prepare the as-built schedule is subjective and highly amenable to manipulation [7]... Window Analysis This technique involves interim assessment of delay on updated schedules at specific periods of the project. This is similar to the snapshot technique described by Alkass [19] and contemporaneous period analysis described by Schumacher []. First, the total project duration is divided into a number time periods (windows or snapshots) usually based on major changes in planning or major project milestones [,8]. The schedule within each window is updated to reflect the actual durations and sequence at the time of the delay while the remaining as-planned schedule beyond the window period is maintained. Analyses are performed to determine the critical path and new completion date. This new completion date is compared with the as-planned completion date prior to this analysis to give the amount of delay during that window period. Applying this technique to the sample project, the total contract period was first broken into discrete time periods at days 10, 1,, 0 and 1, resulting in window periods. Analysis was carried out for each window successively at the various updates as shown in Figures 18 below. Figure 18. Updated schedule on day 10.
16 Buildings 01, 1 Figure 19. Updated schedule on day 1. Figure 0. Updated schedule on day. Delay Act. duratio ID Activity Description Planned Delay duration duration n GARAGE G1 G G Excavate foundation Concrete foundation Brickwork to 1m high G Brickwork to roof level G Concrete to floor slab G Fix roof structure G7 Waterproof roof G8 Fix doors G9 Paint and clean up DRIVE-IN D1 D Clear and excavate for drive-in Hardcore base to drive D Tarmacadam to drive-in rd Window Days completion date at start of window completion date
17 Buildings 01, Figure 1. Updated schedule on day 0. Figure. Updated schedule on day 1. Act. ID Activity Description Planned Delay duration duration GARAGE G1 Excavate foundation G Concrete foundation G Brickwork to 1m high Brickwork to roof G level G Concrete to floor slab G Fix roof structure G7 Waterproof roof G8 Fix doors G9 Paint and clean up DRIVE-IN Clear and excavate D1 for drive-in Hardcore base to D drive Tarmacadam to D drive-in Days th Window Completion date at start of window completion date There was 1-day slippage at the end of the 1st window due to days delay by the contractor on the critical path G1-G-G-G-G-G7-G8-G9. The updated schedule at the end of the nd window showed 1 day slippage due to 1-day delay by the contractor on the critical path. There was days of project delay at the end of the rd window as a result of days delay by the owner on the critical path. The critical path changed to D1-D-D-G9 at the end of the th window, resulting in days slippage. By but for analysis, the contractor s delay responsibility within this window is days while that of the owner is days. At the end of the last window, further days slippage was caused by the owner along the critical path, D1-D-D-G9. Table below gives a summary of the results of this analysis.
18 Buildings 01, Table. Window analysis results. Window number Schedule update (day No.) Completion date (day No.) Delays in window EC NN 0 (start) (completion) Total 7 Thus the contractor is responsible for delays to the project whilst the owner is responsible for 7 days delay. A major advantage of this method is that it divides a complicated network into a manageable one and also takes into account the dynamic nature of the critical path. This method offers a very effective approach to analysing delays and the more snapshots or windows used the better the accuracy of the results. However, the limitations of this technique include: it is time consuming and costly to operate and also demands complete project records, which are often not available; differences in the time periods (or windows ) can produce different results [1]; periodic updates may not be existing which may then require the analyst to perform a highly laborious analysis of project records to create updates... Time Impact Analysis This technique is a variant of the window technique described above, with the difference being that the time impact technique concentrates on a specific delay or delaying event but not on time periods containing delays or delaying events [19]. A stop-action picture of the project is developed each time it experiences a major delay situation. The schedule is then updated at this delay period and the effect of the delay is analysed to establish a new completion date. The difference between the new completion date and the date prior to the exercise gives the delay caused by that particular impact. A fragnet or subnetworks are sometimes prepared to depict the impact of the delay event, e.g., change orders on the schedule. It is an effective technique because the delays are analysed using real time CPM. It is also applicable to use during project duration and after completion. However its limitations include: it may not be practical or realistic to use if there are an overwhelming number of delay causing events [8]; periodic updates may not be existing which may then require the analyst to perform highly laborious analysis of project records to creates updates; the analysis requires intensive effort and is time consuming. Because of the close similarity of the time impact analysis and the window analysis, the former was not applied to the sample project.
19 Buildings 01, Table below summarises the results of delay responsibilities of the parties as given by the various the techniques. Table. Summary of delay analysis results for the case study. Delay analysis methodology Delay EC NN As-planned vs. As-built 9 Impacted As-planned 8 As-planned But for (a) contractor s point of view 7 (b) owner s point of view 9 Collapsed As-built Window Analysis 7.7. Reflection on the Different Results DATs Generate Clearly, the main reason responsible for the different results is the different modes of application the various techniques employ. Not only are there wide differences in their applications, the delaying events experienced by real-life projects are often extensive and more complex to deal with [7,19] than the example of this case study portrays. Thus, the analysis results from DATs for real-life cases tend to be staggeringly different and bear a significant amount of time and cost compensations, as well [17,]. The different modes of application also require varying levels of analysis details in the delay assessment process. DATs that analyse a programme(s) directly as it is, without any major modifications of the programme(s) (e.g., as-planned vs. as-built), are often considered simplistic methods [0]. On the other hand, those that involve extensive programme modifications, including running of additive and subtractive simulations (e.g., collapsed as-built and time impact analysis), are termed sophisticated methods [0]. Although the latter group require more expense, time, skills, resources and project records to operate, they tend to give more accurate results than the former partly due to the detailed/rigorous analysis they entail [,0]. In terms of which techniques are favoured by claim parties, the impacted as-planned, as-planned but-for, and collapsed as-built are often preferred by contractors or owners, since these techniques are capable of easily establishing the amount of project delays that could be attributable to the actions or inactions (delays) of a particular party, through just by inserting or removing such delays from relevant programmes [,]. In view of the aforementioned differences, the general view amongst practitioners regarding use of DATs is that no single technique is suitable for all delay claims situations and that the most appropriate one for any case is dictated by a number of factors or criteria [7,17]. The need to determine and make use of this appropriate technique is increasingly becoming a crucial issue. For example, in the UK case of Balfour Beatty Construction Ltd vrs The Mayor and Burgesses of the London Borough of Lambeth [8], the defendant challenged the adjudicator s decision for, in alia, not given any opportunity to the parties to comment on the appropriateness of the technique adopted by the adjudicator for determining time extensions and to seek their observations as to its use. The defendant s position was upheld by the judge, who regarded the adjudicator s inaction as a serious
20 Buildings 01, omission. The following sections discuss the factors often mentioned in the literature as being the key criteria that parties need to consider in deciding on the most appropriate technique. Availability and accuracy of project records have a major influence on the suitability of a technique since the various techniques employ different programming information sources. If a good as-planned network programme exists but has not been updated with progress due to lack of as-built records, etc., then impacted as-planned analysis may be appropriate [8]. Conversely, where there are good as-built records but no as-planned programme or the as-planned programme is not adequately prepared, then the collapsed as-built method may be appropriate []. The time of performing delay analysis is an important factor, since some techniques (e.g., time impact analysis, impacted as-planned) are suitable for performing forward or contemporaneous assessment (termed prospective analysis ), whilst others (e.g., collapsed as-built) can only be used for hindsight assessment (retrospective analysis) [,7]. The prospective analysis seeks to establish the effect of delays during the currency of the project, particularly when the contract provides that the contractor is entitled to relief from liquidated damages if completion is likely to be delayed. Retrospective analysis, on the other hand, is carried out after the fact (i.e., at the end of the project), where analysts usually have full benefit of hindsight [8,17]. The type of delay claims in dispute influences the type of DAT to be employed. The more theoretical techniques like impacted as-planned are helpful for instances where a party is concerned with proving delay time only [8]. Nevertheless, when the claim involves money as well, an approach based on the analysis of what actually transpired on the project (e.g., using Collapse As-built ) is warranted [8]. The cases McAlpine Humberoak Ltd vrs McDermott International Inc. [9] and Ascon Contracting Ltd vrs Alfred McAlpine Construction Isle of Man Ltd. [0] have both confirmed that wholly theoretical calculations are unlikely to succeed. The availability of resources for the analysis is also a relevant issue of consideration [7]. As noted earlier, the sophisticated techniques require more time and resources to use than the simplistic ones and hence the latter group may be suitable for small/medium size projects where management resources are limited and the records are usually inadequate. On the other hand, larger-scale projects with sufficient management resources warrant a more sophisticated method such as the time impact analysis and window analysis [7,17].. Relevant Issues not Addressed by Existing DATs In addition to the different results that existing DATs produce when applied to the same set of delay claims data, there are other relevant issues that have the potential of affecting the results but are often not taken into consideration in the techniques applications. These issues include: functionality of the programming software employed, resource loading and levelling requirements, resolving concurrent delays, and delay pacing strategies..1. Functionality of the Analysis Software Packages Not only do current construction programming software packages have different functionalities and capabilities [1,], they also lack transparency on certain scheduling operations [,]. For instance, when it comes to dealing with programming issues of relevance to delay analysis, such as project
21 Buildings 01, calendars, rescheduling activities with lags, handling of statuses/updates (progress override or retain logic settings) and resource allocation, the packages have different settings and ways of handling them [ 7]. As a result of these features, different software are likely to produce different results when used to analyse a particular delay claim [8] and therefore further exacerbating the difficulties often surrounding the amicable resolution of the delay claims. A possible solution to this issue is to convert the programme being used for the analysis from one software package into another, but this does not offer a viable solution either, as the conversion process is characterised by difficulties and information distortion problems [8]. A notable recommendation for dealing with the software problem is for the disputing parties to agree on a common software for undertaking the delay claims assessment [7], unless the project contract specifies otherwise... Resource Loading and Levelling Requirements The basic assumption underpinning traditional CPM programme that resources are unlimited does not hold in reality as resources tend to be limited in most practical situations [8,9]. It is thus quite important for baseline programmes to be resource-loaded so as to ensure both reliable task duration and network logic, especially when many tasks require the same resources at the same time [0]. Without such loading, the programme to be used for delay analysis would not show realistic float values in its non-critical activities, and would thus affect the outcome of the analysis, especially for cases involving time extensions claims resolutions [1,]. Therefore, resource loading or levelling considerations in delay analyses is quite crucial to ensuring accurate and trustworthy results [8,1], except for the collapse as-built technique as it does not rely on baseline programmes. It is noteworthy that the need for analysts to take resource allocations into account in their delay analyses is becoming an increasingly vital requirement. For instance, in the UK case of McAlpine Humberoak vrs McDermott International [9], the judge disapproved of the plaintiff s delay claim submissions on the basis of not giving consideration on how resource usage was planned for and how they were actually utilized during construction. Wickwire [] also reviewed legal decisions in the US and noted that in any analysis of project delays, the contractor is required to take into account realistic resource levelling. Although the incorporation of resource loading effects in the analysis represents a more accurate and rigorous assessment of delay claims, there is very little research on how this consideration can be incorporated in the existing techniques. There is thus the need for further research into this aspect of programming to help enhance the resolution of delay claims in practice... Resolving Concurrent Delays The identification and apportionment of concurrent delays remains a contentious technical subject [7]. More debilitating is the fact that there is no uniformly accepted definition among practitioners as to what it concurrent delay itself means [7]. A reliable approach for analysing concurrent delays would involve using dynamic multiple time periods or windows, as this is capable of tracing changes in the critical path [7,1,]. However, in such mode of analysis, identifying the concurrency and the type of concurrent delays within a given period will be dependent on the length of time chosen for the analysis period. Therefore analysts using different time intervals are bound to interpret a given concurrent delay situation differently. To enhance amicable settlement of claims,
22 Buildings 01, 7 analysts would have to agree on the analysis time interval to be used, which can either be based on dates at which programme updating occurred or the occurrence of key project events such as project milestone or major changes in the programme. The legal aspects of concurrent delays concerning the kind of remedies to be offered to parties have also continued to remain a highly contentious issue. Scott et al. [], for example, found that UK practitioners hold dissenting views to the SCL s recommended remedies [7], which stipulate that, for employer and contractor delays occurring concurrently, the parties should share the responsibility between them and extension of time without costs also awarded. In addition, existing case laws that could offer some guidance on the remedies do not speak in harmony []. This lack of consensus or clearly defined rules/methods for dealing with remedies of concurrent delay types poses great difficultly to practitioners in delay claims resolution. There is therefore the need for research into the underlying principles that govern the legal resolution of concurrent delays to establish clear guidelines for dealing with all possible concurrency situations. Employers may subsequently incorporate these in their contracts for it to guide claim parties during delay claims resolutions... Pacing Delays Zack [] defined this as deceleration of the project work, by one of the parties to the contract, due to a delay to the end date of the project caused by the other party, so as to maintain steady progress with the revised overall project schedule. The thinking behind pacing delay is that it is sensible for a party to slow down the working pace if a delay by other party makes it unnecessary for hard or fast working, as often memorably argued, why hurry up and wait. It enables the contractor or the employer to mitigate or avoid cost that otherwise would have been incurred had the work been done faster. However, there are difficulties in exercising the right to pace delays, which can affect the delay analysis process. For instance, float ownership, will determine whether a particular contractor-caused delay could be a potential employer s defence of concurrent delay or otherwise. Furthermore, as argued by Zack [], pacing delays tends to minimise compensable delay and this makes it imperative to consider its effect in delay analysis process to ensure fairness in the apportionment of delay responsibility. Further studies are thus needed to offer assistance on how to resolve these issues.. Conclusions Delay claims are now a major source of conflict in the construction industry and also one of the most difficult to resolve. Inspired by this, academic researchers and practitioners alike have made numerous attempts by way of developing DATs and good practice documents for guiding practitioners on the proper analyses and resolution of the claims. The knowledge of the application of these techniques is of paramount importance to understanding their limitations and capabilities in practice and areas of improvement needs. As part of a wider research work, this paper seeks to develop such knowledge and understanding via: an evaluation of the most common DATs based on a case study, a discussion of the key relevant issues often not addressed by the techniques and their improvement needs. The evaluation of the techniques confirmed that the various DATs give different allocations of delay responsibilities when applied to the same set of delay claims data, reinforcing the common notion that the most appropriate technique for any claims situation depends on the claims circumstances
23 Buildings 01, 8 and the project. The different results stem mainly from the unique set of requirements and application procedures each technique employs. In addition, there are a number of issues such as: functionality of the programming software employed for the analysis, resource loading and levelling requirements, concurrent delay and delay pacing, which are all vital to ensuring accurate and reliable analysis results but are not addressed by the DATs. Current programming software packages for analysis delay claims are characterised by different functionalities and capabilities. They also lack transparency on some crucial scheduling operations and employ different settings for dealing with key scheduling issues that affects delay analysis process such as project calendars, rescheduling activities with lags and status updates. These features increase the chance of claimants and defendants at arriving at different delay claim results and thus make it more difficult for amicable settlement of the delay claim disputes. This justifies the need for disputing parties to agree on a common acceptable software package for the analysis and how it should be applied appropriately. To ensure a more reliable delay analysis results, it is important to use resource-loaded and levelled baseline programmes, as such programmes provide for reliable task duration, network logic, and realistic float values in non-critical activities. Without taking such programming requirements into account in the analysis, the baseline programme would not adequately reflect the plan of work as dictated by the true intent of resource usage in practice, thereby leading to results that are not accurate and trustworthy. Although taking account of resource loading ensures reliable analyses and results thereby contributing to successful claims resolution, there is very little research done on how this consideration can best be incorporated in DATs. This limitation thus calls for the need for further research studies in this area. Resolving concurrent delays is still considered one of the most difficult issues to address, partly because existing DATs do not take them into account in the analyses. The best approach to handling this challenge is for the analyst to employ dynamic multiple time periods or windows, so as to be able to trace changes in the critical path. Using different time intervals would however produce different results as the extent and type of concurrency are bound to yield difference situations and effect. It is therefore important for disputing parties to agree on the most appropriate time interval to be used for the analysis, either based on status dates or the occurrence of key/milestone project events. Delay pacing strategy is a relatively new defence strategy often argued by both owners and contractors to demonstrate that their delay was not the dominant or controlling delay. Although each party has the right to pace delays, the process is fraught with difficulties similar to those of concurrent delays and float ownership issue. For instance, the latter will determine whether a particular contractor-caused delay could be a potential employer s defence of concurrent delay or otherwise. In general, this paper offers valuable insights into the applications of existing DATs, which have important implications for the resolution of construction delay claims and its improvement needs. First, parties involved in such claims should not only be aware of the limitations and capabilities of the techniques, but need to examine the above-highlighted issues as well so as to, as far as possible, take them into account in the analysis. This consideration will hopefully increase the rigour and transparency in the claims analysis, and hence reduce the chances of disputes in the claims settlement. Secondly, the highlighted issues have, however, received very little awareness and research attention thus far, as evidenced by delay analysis literature. Future research thus needs to focus more on these
24 Buildings 01, 9 relatively overlooked issues, in order to extend the limited knowledge and understanding that exist about them such as how best they can be addressed appropriately in delay analysis. Whilst the case study used was based on a hypothetical project, the proposed claims scenarios largely reflect that of a typical construction delay claims settings, both in relevance and context. However, to strengthen this study, it is recommended that a similar study be undertaken in the future based on real-life project data to validate the case study findings. Conflict of Interest The authors declare no conflict of interest. References 1. Akintoye, A.S.; Skitmore, R.M. Profitability of UK construction contractors. J. Constr. Manag. Econ. 1991, 9, 11.. Majid, M.Z.A.; McCaffer, R. Factors of non-excusable delays that influence contractors performance. J. Constr. Eng. Manag. ASCE 1998, 1, 9.. Schumacher, L. Quantifying and apportioning delay on construction projects. J. Cost Eng. 199, 7, Ng, S.T.; Skitmore, M.; Deng, M.Z.M.; Nadeem, A. Improving existing delay analysis techniques for the establishment of delay liabilities. Constr. Innov. 00,, 17.. Lovejoy, V.A. Claims schedule development and analysis: Collapsed as-built scheduling for beginners. J. Cost Eng. 00,, Finke, M.R. Window analysis of compensable delays. J. Constr. Eng. Manag. ASCE 1999, 1, Society of Construction Law (SCL). Protocol for Determining Extensions of Time and Compensations for Delay and Disruption; SCL: Burbage, UK, 00. Available online: (accessed on 19 July 01). 8. Pickavance, K. Delay and Disruption in Construction Contracts, th ed.; Sweet & Maxwell: London, UK, Kartam, S. Generic methodology for analysing delay claims. J. Constr. Eng. Manag. ASCE 1999, 1, Bordoli, D.W.; Baldwin, A.A. A methodology for assessing construction project delays. J. Constr. Manag. Econ. 1998, 1, Gothand, K.D. Schedule delay analysis: Modified windows approach. J. Cost Eng. 00,, Lee, H.; Ryu, H.; Yu, J.; Kim, J. Method for calculating scheduling delay considering lost productivity. J. Constr. Eng. Manag. ASCE 00, 11, Mbabazi, A.; Hegazy, T.; Saccomanno, F. Modified but-for method for delay analysis. J. Constr. Eng. Manag. ASCE 00, 11, Hegazy, T.; Zhang, K. Daily window delay analysis. J. Constr. Eng. Manag. ASCE 00, 11, 0 1.
25 Buildings 01, 0 1. Ibbs, W.; Nguyen, L.D. Schedule analysis under the effect of resource allocation. J. Constr. Eng. Manag. ASCE 007, 1, Association for the Advancement of Cost Engineering International (AACEI). Recommended Practice No. 9R-0, Forensic Schedule Analysis; AACEI: Morgantown, WV, USA, Peters, T.F. Performing forensic delay analyses from deep within the black tent. AACE Int. Trans. 007,, CDR.01.1 CDR Wickwire, J.M.; Groff, M.J. Update on CPM proof of delay claims. Sched. Update-Project Manag. Instit. Coll. Sched. 00, 1, Alkass, S.; Mazerolle, M.; Harris, F. Construction delay analysis techniques. J. Constr. Manag. Econ. 199, 1, Zack, J.G. But-for schedules Analysis and defense. J. Cost Eng. 001,, Alkass, S.; Mazerolle, M.; Tribaldos, E.; Harris, F. Computer-aided construction delay analysis and claims preparation. J. Constr. Manag. Econ. 199, 1,.. Pinnell, S. How to Get Paid for Construction Changes: Preparation, Resolution Tools and Techniques; McGraw-Hill Companies, Inc.: New York, NY, USA, Bubshait, A.A.; Cunningham, M.J. Comparison of delay analysis methodologies. J. Constr. Eng. Manag. ASCE 1998, 1, 1.. Stumpf, G.R. Schedule delay analysis. J. Cost Eng. 000,,.. Pilcher, R. Principles of Construction Management, rd ed.; McGraw-Hill International Limited: Maidenhead, UK, Lucas, D.E. Schedule Analyser Pro An aid in the analysis of delay time impact analysis. J. Cost Eng. 00,, Trauner, J.T. Construction Delays-Documenting Causes: Wining Claims, Recovering Costs; R.S. Means Company Inc.: Kingston, MA, USA, Balfour Beatty Construction Ltd vrs The Mayor and Burgesses of the London Borough of Lambeth; Building Law Report. Available online: (accessed on 17 July 01). 9. McAlpine Humberoak Ltd vrs McDermott International Inc.; 8 Building Law Report 1; Addison Wesley Longman Limited: London, UK, Ascon Contracting Ltd vrs Alfred McAlpine Construction Isle of Man Ltd.; Technology and Construction Court: London, UK, Conlin, J.; Retik, A. The applicability of project management software and advanced IT techniques in construction delay mitigation. Int. J. Proj. Manag. 1997, 1, Kelsey, J.; Winch, G.; Penn, A. Understanding the Project Planning Process: Requirements Capture for the Virtual Construction Site; Bartlett Research Paper 1; University College London: London, UK, Sanders, M. Transparent CPM. AACE International Transactions, PS.08; AACE International: Morgantown, WV, USA, 00.. Winter, R. Making CPM more transparent. AACE Int. Trans. 00, 1, p.10.1 p Maroto, C.; Tormos, P. Project management: An evaluation of software quality. Int. Trans. Op. Res. 199, 1, 09 1.
26 Buildings 01, 1. Kastor, A.; Sirakoulis, K. The effectiveness of resource levelling tools for resource constraint project scheduling problem. Int. J. Proj. Manag. 009, 7, Winter, R. MS Project for Construction Schedulers. In Proceedings of the AACE International th Annual Meeting, Anaheim, CA, USA, 19 June Forensic Claims Analysis. Available online: (accessed on 19 July 01). 9. Woodworth, B.M.; Shanahan, S. Identifying the critical sequence in a resource-constrained project. Int. J. Project Manag. 1988,, Kuhn, A.J. Artificial resource loading for schedule review. AACE Int. Trans. 007,, PS.17.1 PS Nosbisch, M.R.; Winter, R.M. Managing resource levelling. J. Cost Eng. 00, 8,.. Carmichael, S.; Murray, M. Record keeping for contemporaneous delay analysis: A model for effective event management. Constr. Manag. Econ. 00,, Wickwire, J.M. Standards of Proof for Contractor Time Delay Claims Case in Point. In Cause & Effect, News from CPMI on Construction Claims Analysis and Resolution, Issue 1; Springer: Berlin, Germany, 00; p... Scott, S.; Harris, R.A.; Greenwood, D. Assessing the new United Kingdom protocol for dealing with delay and disruption. J. Prof. Issues Eng. Educ. Pract. ASCE 00, 10, Martin, J. Concurrent Delay. In Proceedings of the Society of Construction Law, London, UK, February 00.. Zack, J.G. Pacing delays The practical effect. J. Cost Eng. 000,, by the authors; licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution license (
Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs
Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs Nuhu Braimah, Lecturer of Construction/Infrastructure Management, Civil Engineering Department, School of Engineering
Open Access Review of Delay Analysis Methods: A Process-Based Comparison
The Open Construction and Building Technology Journal, 2009, 3, 81-89 81 Open Access Review of Delay Analysis Methods: A Process-Based Comparison Jyh-Bin Yang*,1 and Chih-Kuei Kao 2 1 Department of Construction
How To Perform An As-Built But For Schedule Delay Analysis
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
Schedule Analysis under the Effect of Resource Allocation
Schedule Analysis under the Effect of Resource Allocation William Ibbs 1 and Long D. Nguyen 2 Abstract: The construction industry has employed various schedule analysis techniques to support delay claims.
FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment
AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment Acknowledgments: Kenji P. Hoshino, PSP CFCC (Author) Robert B. Brown, PE
Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
Method for Calculating Schedule Delay Considering Lost Productivity
Method for Calculating Schedule Delay Considering Lost Productivity Hyun-Soo Lee, M.ASCE 1 ; Han-Guk Ryu 2 ; Jung-Ho Yu 3 ; and Jae-Jun Kim, M.ASCE 4 Abstract: A delay claim often occurs when a difference
BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses
BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction
Scheduling Best Practices
RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding
WELCOME Best Practices for Managing Construction Delay and Interference Claims
WELCOME Best Practices for Managing Construction Delay and Interference Claims Kenneth A. Slavens 314.345.6419 Husch Blackwell LLP Topics to be covered Delay Acceleration Disruption Delay Impact on Project
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
Construction Delay Analysis under Multiple Baseline Updates
Construction Delay Analysis under Multiple Baseline Updates By Wail Menesi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Schedule and Delay Analysis Methodologies Richard J.
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
AACE International Recommended Practices
AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,
Schedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table
Construction Bonds. Vanessa S. Werden 604.408.2033 [email protected]
Construction Bonds Vanessa S. Werden 604.408.2033 [email protected] What is a bond? A bond is a special form of contract whereby one party guarantees the performance by another party of certain obligations. A
PRACTICALITIES OF DELAY ANALYSIS: RETROSPECTIVE ANALYSIS
PRACTICALITIES OF DELAY ANALYSIS: RETROSPECTIVE ANALYSIS Christopher A. Gorse 1, Mike Bates 1 and Aaron Hudson-Tyreman 2 1 Scchool of the Built Environment, Leeds Metropolitan University, Queen Square
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
The Principles of Schedule Impact Analysis
College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
Delay analysis Methodology in UAE construction Projects: Delay Claims, Literature Review 1. Saad Hegazy
Delay analysis Methodology in UAE construction Projects: 1 Saad Hegazy Introduction UAE is one of the pioneers among developing economies in the Middle East and the core for its development depends on
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in
Technology A Risk Prevention / Mitigation Tool
Technology A Risk Prevention / Mitigation Tool by Belden Premaraj 1 This paper highlights the possible use of various technological advancements as a tool to prevent or mitigate risk rather than merely
In initial planning phases In monitoring and execution phases
Project management What is it? Project management is a framework for a range of tools for helping plan and implement development and change projects. A range of tools exist, including: Gantt charts (bar
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Construction Schedules
CONSTRUCTION CLAIMS EDITION EDITION NO. 15 September 2013 Construction Schedules Recovery Schedules And Constructive Acceleration Protect Yourself From Pitfalls By Christopher M. Burke Partner, Watt, Tieder,
Scheduling Best Practices. Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group
Scheduling Best Practices Proper Use of Milestones and Constraints By Paul Brough, Vice President of Warner s Scheduling Group Paul Brough has experience in multiple phases of project management, including
PROGRAMMING TECHNIQUES. Chapter 5(Part 2)
PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate
CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT. JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK
CLAIMS UNDER THE NEW FIDIC CONDITIONS OF CONTRACT JOHN PAPWORTH FRICS, FCIArb, MInstCES, MACostE Managing Director, John Papworth Limited, UK SUMMARY The FIDIC Conditions are used extensively on international
OUT-OF-COURT RESTRUCTURING GUIDELINES FOR MAURITIUS
These Guidelines have been issued by the Insolvency Service and endorsed by the Bank of Mauritius. OUT-OF-COURT RESTRUCTURING GUIDELINES FOR MAURITIUS 1. INTRODUCTION It is a generally accepted global
ROSSENDALE BOROUGH COUNCIL SUNDRY DEBT MANAGEMENT - POLICY STATEMENT
ROSSENDALE BOROUGH COUNCIL SUNDRY DEBT MANAGEMENT - POLICY STATEMENT 1. Introduction 1.1. The principal objective for any debt recovery policy must be the maximum conversion of outstanding debt into cash
PLANNING & FORENSIC DELAY ANALYSIS
PLANNING & FORENSIC DELAY ANALYSIS Experts in international construction & engineering disputes 01 www.gtfairway.com Fairway Fairway is an internationally recognised company that provides expert analysis
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
IMCPM04 Project Scheduling and Cost Control. Course Outline
IMCPM04 Project Scheduling and Cost Control Course Outline January 2012 Project Scheduling and Cost Control Course Aim Project Scheduling and Cost Control is a five-day (5 day) course which provides participants
2 COMMENCEMENT DATE 5 3 DEFINITIONS 5 4 MATERIALITY 8. 5 DOCUMENTATION 9 5.1 Requirement for a Report 9 5.2 Content of a Report 9
PROFESSIONAL STANDARD 300 VALUATIONS OF GENERAL INSURANCE CLAIMS INDEX 1 INTRODUCTION 3 1.1 Application 3 1.2 Classification 3 1.3 Background 3 1.4 Purpose 4 1.5 Previous versions 4 1.6 Legislation and
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS
SECTION 01 32 00 - PROJECT PLANNING AND SCHEDULING PART 1: GENERAL 1.1 DEFINITIONS A. The term Baseline Schedule, as used throughout the contract documents, shall refer to a fixed projection of the project
Scope management can be defined as controlling what is and what is not a part of the project.
Scope Management Scope management can be defined as controlling what is and what is not a part of the project. According to the 2004 PMBOK scope management: Includes the processes required to ensure that
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
How To Use P6 For A Project Scheduling System
Managing Assets Through Enterprise - Wide Scheduling Scott Lowe, P.E. Principal, Trauner Consulting Services, Inc. Scott Lowe, Principal, Trauner Consulting Services CPM Scheduler Claims Analyst Expert
Environment Committee 11 January 2016
Environment Committee 11 January 2016 Title Whole Life Costing of Footway Maintenance Treatments and Scheme Prioritisation Report of Wards Status Urgent Key Enclosures Commissioning Director, Environment
ISSUES OF CONTRACTUAL CHAIN AND SUB- CONTRACTING IN THE CONSTRUCTION INDUSTRY
ISSUES OF CONTRACTUAL CHAIN AND SUB- CONTRACTING IN THE CONSTRUCTION INDUSTRY Wai Fan Wong and Charles Y.J. Cheah School of Civil and Environmental Engineering, Nanyang Avenue, Nanyang Technological University,
Producing a programme under the NEC form of contract
Proceedings of the Institution of Civil Engineers Management, Procurement and Law 163 May 2010 Issue MP2 Pages 59 64 doi: 10.1680/mpal.2010.163.2.59 Paper 900033 Received 02/05/09 Accepted 19/08/09 Keywords:
Who pays the Money for the Time?
Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Construction Project Scheduling: Keys to Success
View the online version at http://us.practicallaw.com/0-574-8625 Construction Project Scheduling: Keys to Success KELLY M. HEUER AND JAMES G. ZACK, JR., NAVIGANT CONSULTING, INC., WITH PRACTICAL LAW REAL
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)
01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other
Risks in International Consultancy Appointments: The FIDIC White Book
Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction
Linear Schedules for Tunnel Projects
Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear
REPORTING ACCOUNTANTS WORK ON FINANCIAL REPORTING PROCEDURES. Financing Change initiative
REPORTING ACCOUNTANTS WORK ON FINANCIAL REPORTING PROCEDURES consultation PAPER Financing Change initiative inspiring CONFIdENCE icaew.com/financingchange ICAEW operates under a Royal Charter, working
Scheduling Best Practices
In this article, as part of a continuing series of articles regarding critical path method (CPM) scheduling, Warner reviews various facets of the process of preparing, analyzing and utilizing schedules
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication
CDR.07. CPM Scheduling and How the Industry Views Its Use
CDR.07 CPM Scheduling and How the Industry Views Its Use Ms. Patricia D. Galloway, PE D elivering a project on time does not just mean signing a contract and hoping that the required completion date will
Contract Management. Brief 22. Public Procurement. September 2011
Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This
Hijacked by Ulterior Motives:
Hijacked by Ulterior Motives: The Manipulation of the Mandatory Mediation Process in Ontario By: Bruce Ally B.A., M.A., PhD., OCPM., & Leah Barclay B.A. Adv. The use of mediation as a method of conflict
EXAM EXEMPLAR QUESTIONS
Level 6 Professional Diploma in Procurement and Supply PD5 - Programme and project management EXAM EXEMPLAR QUESTIONS QUESTIONS AND INDICATIVE ANSWER CONTENT Page 1 of 10 QUALIFICATIONS 2013 QUESTIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
DCMA 14-Point Assessment Metrics
DCMA 14-Point Assessment Metrics The integrity of a CPM schedule is one of the critical factors in improving a project s likelihood of success 1! There is a well-established correlation between the quality,
An Introduction to the Management Principles of Scheduling
College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923
A Guidance Note to. Conditions of Contract for Consultancy Services (2005)
A Guidance Note to Conditions of Contract for Consultancy Services (2005) This Guidance Note is based on a document prepared by the Auckland Region Contract Group, and verified by ACENZ, in February 2005.
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE
Volume.02, Issue. 06, June 2014 ISSN (online): 2348 7550 APPLICATION OF PROJECT MONITORING TOOLS FROM OWNER S PERSPECTIVE 1 Dr. V. M. Topkar, 2 Pise Akshay H. 1,2 Civil and Environmental Engineering Department,
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement
Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the
CALCULATION DIFFERENCES WHEN IMPORTING FROM INTO ORACLE PRIMAVERA P6 VERSION 7 PAUL E HARRIS EASTWOOD HARRIS
CALCULATION DIFFERENCES WHEN IMPORTING FROM MICROSOFT PROJECT 2003-2010 INTO ORACLE PRIMAVERA P6 VERSION 7 BY PAUL E HARRIS OF EASTWOOD HARRIS TABLE OF CONTENTS 1 INTRODUCTION 3 2 AIM 3 3 SUMMARY 3 4 LEVELS
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
Collection of Tax Debts
Collection of Tax Debts The Collector-General outlines Revenue s approach Introduction Revenue, as the Irish tax and customs administration, plays a critical role in securing and delivering most of the
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Contract Administration
Chapter 5 Contract Administration Section 3 Change Orders 5-301 General 5-302 Change Order Policy 5-303 Purpose of Change Orders 5-304 Initiation of Change Orders 5-305 Preliminary Considerations 5-306
Builder s Risk Structuring the Right Coverage, Avoiding and Resolving Disputes
Builder s Risk Structuring the Right Coverage, Avoiding and Resolving Disputes American Bar Association (ABA) Section of Litigation Insurance Coverage Tucson, Arizona March 6, 2015 Builder s Risk Speakers
Protocol for the Instruction of Experts to give Evidence in Civil Claims
Protocol for the Instruction of Experts to give Evidence in Civil Claims June 2005 amended October 2009 CONTENTS Page No. 1. Introduction... 3 2. Aims of Protocol... 3 3. Application 4 Limitation. 4 4.
GN5: The Prudential Supervision outside the UK of Long-Term Insurance Business
GN5: The Prudential Supervision outside the UK of Long-Term Insurance Business Classification Recommended Practice MEMBERS ARE REMINDED THAT THEY MUST ALWAYS COMPLY WITH THE PROFESSIONAL CONDUCT STANDARDS
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
Insurance claims and losses in Spain. Procedural aspects of the Spanish legal system
Insurance claims and losses in Spain. Procedural aspects of the Spanish legal system Further information If you would like further information, please contact a person mentioned below or the person with
PRACTICE DIRECTION NUMBER 11 OF 2012 SUPREME COURT OF QUEENSLAND SUPERVISED CASE LIST
PRACTICE DIRECTION NUMBER 11 OF 2012 SUPREME COURT OF QUEENSLAND SUPERVISED CASE LIST 1. Practice Direction No 6 of 2000 is hereby repealed. 2. This Practice Direction is intended to (a) provide some explanation
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
Litigation schemes and proof of debt schemes: Managing conflicts of interest
REGULATORY GUIDE 248 Litigation schemes and proof of debt schemes: Managing conflicts of interest April 2013 About this guide This guide sets out our approach on how a person who provides a financial service
NSW COURT OF APPEAL DECISION SUPPORTS LITIGATION FUNDING MARKET
NSW COURT OF APPEAL DECISION SUPPORTS LITIGATION FUNDING MARKET Introduction 1. The New South Wales Court of Appeal, in a unanimous Judgment on Thursday 31 March 2005, sent some clear messages to legal
THE POSSIBILITIES FOR PRIVATE ENFORCEMENT OF THE COMPETITION RULES IN THE NETHERLANDS
THE POSSIBILITIES FOR PRIVATE ENFORCEMENT OF THE COMPETITION RULES IN THE NETHERLANDS A survey commissioned by the Dutch Ministry of Economic Affairs - EXECUTIVE SUMMARY - Amsterdam, 3 November 2005 Mr.
Business-critical Insurance
Business-critical Insurance Identifying those insurances that support the business and its strategy Guide 2015 Contents Introduction... 4 Categories of insurance... 5 Determining which insurance covers
Limitation of Liability
Limitation of Liability Submission to the Attorney-General (Western Australia) July 2000 The Institution of Engineers, Australia Institution of Engineers, Australia 11 National Circuit, Barton, ACT, 2604
Devising new Software Project Risk Management Model: MARUNA
Devising new Software Project Risk Management Model: MARUNA Bekim Fetaji South East European University, Computer Sciences, Ilindenska bb, 00 Tetovo, Macedonia Abstract The focus of this research is the
Terms & Conditions Verder B.V. (02031806) Filed at the Chamber of Commerce on 29-01-2015
Terms & Conditions Verder B.V. (02031806) Filed at the Chamber of Commerce on 29-01-2015 1. General 1.1 These terms and conditions use the following terms and definitions: Product: items, as well as services
// Benchmarking Project Schedules
// Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...
Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations
Waste Transfer Pricing Methodology for the disposal of higher activity waste from new nuclear power stations December 2011 Contents Contents... i Introduction... 1 Executive Summary... 1 Background...