Schedule Analysis under the Effect of Resource Allocation
|
|
|
- Timothy Hancock
- 10 years ago
- Views:
Transcription
1 Schedule Analysis under the Effect of Resource Allocation William Ibbs 1 and Long D. Nguyen 2 Abstract: The construction industry has employed various schedule analysis techniques to support delay claims. Paradoxically, resourcerelated issues are frequently ignored even though they can affect project completion time, too. The research presented here shows that delay analysis without resource allocation practice substantially affects results of schedule analysis. Some delay can cause unrealistic resource allocation in downstream work, which in turn may further delay the project. The effect of resource allocation can either add to or reduce the severity of some delaying event. Apportionment of delay responsibility may be inaccurate unless resource allocation practice is considered in the analysis. Practical and necessary steps are proposed to enhance the existing window analysis technique. A case study is presented to compare the enhanced window analysis with the existing window analysis. This research enables practitioners to make delay analyses and claims more practical and reliable. Further studies are needed to improve the usability, credibility, and acceptability of schedule analysis considering resource allocation. DOI: / ASCE :2 131 CE Database subject headings: Scheduling; Resource management; Claims; Delay time; Construction management. Introduction Project schedules are invariably dynamic and uncertain. Various controllable and uncontrollable factors can adversely affect the project schedule and cause delays. As a result, the identification and analysis of delays become essential Finke They are however, onerous tasks. Contractors are prone to view most delays as the responsibility of the owner while owners frequently attempt to tag delays as contractor caused, third party caused, or concurrent Zack Consequently, delays may lead to some form of dispute resolution alternatives, from negotiation to litigation, which may be expensive and a crapshoot. Responding to such challenge, the industry has created and employed many schedule analysis techniques. The level of acceptability of each technique depends on its credibility and the court or board ruling the corresponding delay claims. However, resource-related issues such as constraints, availability, or in broader term resource allocation can cause delays yet their effects are typically neglected in those techniques. It should be noted that although a number of studies have focused on scheduling with resource allocation e.g., Wiest 1967; Davis 1974; Willis 1985; Fondahl 1991; Bowers 1995; Hegazy 1999; Kim and de la Garza 2003, 2005; Chua and Shen 2005, none of them addressed resource allocation in after-the-fact schedule delay analysis. 1 Professor of Construction Management, Dept. of Civil and Environmental Engineering, Univ. of California, Berkeley, CA 94720; formerly, President, The Ibbs Consulting Group, Inc. corresponding author. [email protected] 2 Ph.D. Candidate, Dept. of Civil and Environmental Engineering, Univ. of California, Berkeley, CA [email protected] Note. Discussion open until July 1, Separate discussions must be submitted for individual papers. To extend the closing date by one month, a written request must be filed with the ASCE Managing Editor. The manuscript for this paper was submitted for review and possible publication on December 5, 2005; approved on September 6, This paper is part of the Journal of Construction Engineering and Management, Vol. 133, No. 2, February 1, ASCE, ISSN /2007/ /$ The objectives of this research are threefold: 1 prove that effects of resource allocation should not be neglected in schedule analysis via a motivating case; 2 propose practical and necessary steps for dealing with resource allocation and embed them in the most acceptable technique window analysis; and 3 compare the enhanced window analysis with the existing window analysis for a simple case study. The benefit of this research is that project parties will make schedule analysis more credible and practical. This research also raises issues that need further studies to improve credibility of schedule analysis. Delays Delays are acts or events that extend the time necessary to finish activities under a contract Stumpf They are classified in several ways. The classification can be based on origin, compensability, and timing of these delays Kartam In terms of responsibility, delays can be owner-, contractor-, or third partycaused delays. As their names suggest, an owner-caused contractor-caused delay is within the control of, is the fault of, or is due to the negligence of the owner contractor Sweet and Schneier The third party caused delay is attributable to neither the owner nor contractor Kraiem and Diekmann Liability for a certain delay is normally stipulated by contractual terms. Identification of which delays are the responsibility of the owner relies significantly upon the language of the contract itself Hughes and Ulwelling In general, compensable, inexcusable, and excusable delays correspond to owner-, contractor-, and third party-caused delays, respectively. However, there are some exceptions that are imposed by contract clauses, for example no-damage-for-delay clauses. This leads to the fact that several excusable delays may be caused by the owner Bartholomew Also, some inexcusable delays may not be attributable to the contractor. Bartholomew 1989 claimed that the event may have been unforeseen, or due to no fault or negligence of the contractor, yet not necessarily qualify as an excusable delay. Apportionment of delays will be more complicated when JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007 / 131
2 concurrent delays exist. Discussion of concurrent delays is beyond the scope of this paper. Discussion of no-damage-fordelay clauses can be found elsewhere e.g., Lesser and Wallach 2003; Thomas and Messner Schedule Analysis Process of Schedule Analysis Schedule analysis is a formidable challenge. It is the analytical process through which a professional employs the critical path method CPM, together with a forensic review of project documentation and other pertinent data, to evaluate and apportion the effects of delays and other impacts on the project schedule Holloway There are some typical steps for schedule analysis. Al-Saggaf 1998 describes a formal schedule analysis procedure with the following five steps: 1 data gathering; 2 data analysis; 3 identification of the root cause; 4 classification of the type of delay; and 5 assigning responsibility. Additionally, selecting an expert witness can be another earlier step Pinnell Kartam 1999 proposes a generic methodology for analyzing delay claims. The window analysis or contemporaneous period analysis technique is the only delay analysis method recommended in that methodology since the data are assumed or perceived sufficient. In general, CPM schedules play a critical role in success or failure of schedule analysis. Use of CPM schedules to prove construction claims became the standard Wickwire and Smith A CPM analysis is one of the best ways to fulfill courts and mediators who want to hear in the simplest possible terms what really occurred day to day on the project Frost Though its success is varied, CPM has been widely used for supporting delay and disruption claims in the early 1970s such as in Chaney & James Construction Co. v. United States, 190 Ct. Cl. 699, 421 F.2d and Continental Consolidated Corp. v. United States, 17 CCF 81, Schedule Analysis Techniques Major schedule analysis techniques include: 1 total time or asplanned versus as-built; 2 what-if or impacted as-planned; 3 but-for or collapsed as-built; 4 window, snapshot, or contemporaneous period analysis; and 5 time impact analysis. Each technique may have several variants. Different techniques may yield different results for a same circumstance Alkass et al. 1996; Stumpf Also, the same technique may provide inconsistent results Hegazy and Zhang Detailed descriptions, advantages, and disadvantages of these techniques are available in previous studies e.g., Alkass et al. 1996; Finke 1999; Wickwire and Ockman 1999; Stumpf 2000; Niesse 2004; Lovejoy 2004; Kim et al Inspired by the sometimes inexact and inconsistent results yielded by these techniques, both researchers and practitioners have attempted to either improve the existing techniques or propose new methods for schedule analysis. Alkass et al proposed a new method called isolated delay type which utilizes advantageous attributes of the three techniques; namely butfor, window analysis, and time impact analysis. Unfortunately, there is no successful case using that method reported during the last 10 years. Shi et al proposed a computation method using as-planned schedules as a basis of analysis and not based on the criticality of activities. Those premises in concert with other limitations can hamper its acceptability in the real world. Hegazy and Zhang 2005 developed a spreadsheet to facilitate daily window analysis for small and medium-size projects. From a practical viewpoint, however, daily window analysis tends to be too much work. Lee et al present a delay analysis method considering lost productivity. Unclear differentiation between delay and disruption as well as between their claims may really challenge its applicability. Discussion of delay versus disruption can be found elsewhere e.g., Finke Kim et al proposed a method using delay section, which addresses the two limitations of available methods, namely ambiguity in the analysis of concurrent delays and inadequate consideration of time-shortened activities. As the authors point out the method requires much effort and time in project records, updates, and analyses. Mbabazi et al interestingly employ a Venn diagram to eliminate such drawbacks of the but-for method as its narrow focus on the viewpoint of a single party and its inability to accurately consider concurrent delays. However, the other drawbacks of the but-for method still exist. For instance, the context of when delays arose is not addressed when modifying the but-for method. This is especially important when effects of resource allocation are taken into account during delay analysis. Motivating Case Fig. 1. Schedules of motivating example Fig. 1 illustrates the as-planned, as-built, and collapsed as-built schedules of the motivating case. The as-planned duration is 7 weeks. The contractor will only be able to allocate two backhoes on this site. Numbers denoted in each activity bar indicate the number of backhoes needed for that activity. During the course of work there are two 2-week delays by the owner and the contractor on two activities, namely excavation trench 1 and excavation trench 2, respectively Fig. 1 b. The project is therefore de- 132 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007
3 layed 1 week. Similar to Hegazy and Zhang 2005, the o or c denoted in the bar indicates the owner-caused or contractorcaused delay in that activity. The but-for method is used to analyze the delays. Fig. 1 c shows the collapsed as-built schedule, which results from removing the owner delay in the as-built schedule. The difference in time between the completion date on the as-built and collapsed as-built schedules is the amount of owner-caused delays Schumacher Thus, the owner solely caused the 1-week delay. Note that a window analysis with day-by-day window sizes also yields the same result. The effect of resource allocation actually reverses the above result. The collapsed as-built schedule indicates that the contractor would have completed the project in 7 weeks but for the owner-caused delay. However, this is not true and practical. At the fourth week the work would have required three backhoes for simultaneously performing the three excavation activities Fig. 1 c. This contradicts the fact that the contractor could have been able to allocate only two backhoes on this site. That is, the contractor would still have delayed paced the project 1 week even if the owner had not caused the delay. The 1-week compensable delay yielded from available schedule analyses is therefore misleading. In other words, the owner has to be responsible for what he or she does if the effect of resource allocation is not taken into consideration in this circumstance. This example case demonstrates that resource allocation practice may substantially affect the credibility of schedule analysis and therefore should not be neglected. The need for reflecting and capturing the practice of resource allocation in schedule analysis is apparent and imperative. Many existing and new techniques pay little or no attention to this crucial issue. This paper adopts window analysis as a current technique for improvement. The reasons are twofold. First, courts and boards as well as practitioners and researchers generally agree that window analysis is the best available option Finke 1999; Kartam 1999; Stumpf 2000; Hegazy and Zhang Second, a mechanism that incorporates resource allocation is more feasible, practical, and ready to use. Enhanced window analysis considering resource allocation includes additional steps compared to the current window analysis. Seven steps of current window analysis are adopted from Stumpf Basically, Steps 2, 3, 5, and 6 between current and enhanced window analyses are similar. The enhanced window analysis introduces Step 0 which emphasizes that technical and resource constraints, and resource availability and allocation practice should be documented, disseminated, and obtained a consensus between the contractor and owner. This ensures that schedule analysis considering the effect of resource allocation is legally enforceable thereafter. For instance, the contractor must inform the owner at the beginning that he or she will only be able to allocate two backhoes on the site in the case described above. Resource allocation practices can change and/or be changed over time when more information from the project or the project parties is available. This reflects in Step 7, which includes updating Step 0 and repeats the procedure from Steps 2 to 6 for each window period to the end of the project. Step 1 is to prepare and periodically update the as-planned CPM schedule under technical and resource constraints, and resource availability and allocation practices from Step 0. Step 4 of the current window analysis is subdivided into Steps 4a and 4b. Step 4b is the same between the two analyses. By including Step 4a, the enhanced analysis stresses rescheduling and resequencing the not-yet-completed and not-yet-started activities, which reflects technical and resource constraints, and resource availability and allocation practice. Delays not only change critical path s but also disorganize planned resource allocation practices. This appears to be disregarded in current window analysis. Finally, existing CPM scheduling with resource constraints, resource-constrained scheduling, and resource leveling in commercial scheduling software packages can facilitate Steps 1 and 4a. The answer to which one is chosen depends upon various factors such as contractual stipulations, availability of those scheduling techniques and/or software packages, and reliability of their underlying algorithms. Discussion of this issue is also beyond the scope of this paper. Although several steps in the enhanced and current window analyses are similar, the enhanced method will result in more reliable delay analysis. As the motivating case suggests, resource allocation practice can significantly affect delay analysis. Unfortunately, the current method barely weighs resource allocation. The enhanced window analysis presented herein fundamentally solves this problem. It ensures how resource allocation practice should be embedded during delay analysis so that its effects in apportionment of delay responsibility can be captured in an equitable manner. As such, an answer to the question who really caused delays is more reasonable and potentially less disputable. Window Analysis under Effect of Resource Allocation Case Study Case Overview Fig. 2 presents the as-planned schedule of the case study adopted from a resource-constrained CPM schedule Kim and de la Garza The original planned contract duration was 13 days. The maximum available resource limits were two and one unit s per day for resource Types A and B, respectively Fig. 2. Both the as-planned and as-built schedules met the resource limits. The actual contract duration was 16 days as shown on the hypothesized as-built schedule Fig. 3. The project was thus delayed 3 days. There were four delays during the course of contract work. Like Mbabazi et al. 2005, these delays are directly inserted in the corresponding delayed activities Fig. 3. Responsibility of this 3-day delay needs analyzing and apportioning. Analysis of Delays This section presents a window analysis for the case study. For comparison purposes, both current and enhanced window analyses described above are presented simultaneously. Microsoft MS Project is used for the analyses. As previously discussed, enhanced window analysis can employ existing CPM scheduling with resource constraints, resource-constrained scheduling, or resource leveling in commercial scheduling software packages for Steps 1 and 4a. In this case study, we use CPM scheduling and resource leveling in MS Project for the analyses. Step 0: Dissemination and Consensus of Resource Allocation Practice Resource allocation practice was simply to meet the resource limits for both resource Types A and B. This practice and other tech- JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007 / 133
4 Fig. 2. As-planned resource-constrained schedule nical constraints e.g., precedence relationships remained unchanged during the course of work. The parties agreed on these issues. Step 1: Development of As-Planned CPM Schedule Considering Resource Allocation Practice The as-planned resource-constrained CPM schedule was developed based on Kim and de la Garza 2003 Fig. 2. The contract duration was 13 days. Step 2: Selection of Meaningful Window Sizes Both existing window analysis and enhanced window analysis use similar window periods. Based on the as-built schedule Fig. 3, the project is divided into four windows. Windows 1, 2, 3, and 4 are Days 1 5, Day 6, Day 7, and Days 8 16, respectively. Guidelines for defining reasonable windows can be found in Finke Steps 3 7: Apportionment of Delays The windows method is a repetitive process. To avoid unnecessary redundancy in presentation, we describe the analyses from Steps 3 to 7 in the same section. Schedule analysis of Windows 1 and 2 has graphical illustrations for representative purposes. Also, only resource allocation graphs that do not satisfy resource allocation practices will be presented and embedded in the corresponding schedule windows. Since the enhanced window analysis Fig. 3. Hypothesized as-built schedule 134 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007
5 Fig. 4. Traditional window analysis: window No. 1 ensures proper resource allocation for the remaining work after a window period, resource allocation graphs are not encompassed in that window. Figs. 4 and 5 display results of the first window by traditional and enhanced window analyses, respectively. Traditional window analysis shows a 1-day compensable delay in this window period Days 1 5. However, the resource Type A would be overallocated at Days 7 and 8. This implies that compensable delays in this period not only delayed the project 1 day but also made the initial resource allocation for remaining work impractical. Enhanced window analysis shows a 2-day compensable delay in the same period. Compared to the traditional window analysis, the actual compensable delay is 1 more day 2 versus 1. The analysis is similar for the other windows. Figs. 6 and 7 depict the traditional and enhanced window analyses for the second window, respectively. There is a 1-day concurrent delay compensable and inexcusable in this period under traditional analysis. Again, the resource Type A would be overallocated at Days 7 9. In contrast, the enhanced window analysis shows that the project did not suffer any delay due to the delays in this window. The excusable and inexcusable delays on Activities C and D, respectively, in the third window actually did not cause project delay by both traditional and enhanced window analyses. However, the traditional analysis results in resource overallocation on Days Both the traditional and enhanced analyses for the fourth and last window yield the same results, which show a 1-day inexcusable delay. Table 1 summarizes results of the two schedule analyses. Compensable, concurrent compensable and inexcusable, and inexcusable delays are 1, 1, and 1 days, respectively, under traditional window analysis. Enhanced window analysis results in 2 days and 1 day for compensable and inexcusable delays, respectively. Comparing the traditional analysis to the enhanced analysis, we see that there is a 1-day delay shift from the concurrent delay category to the compensable delay category. It should be noted that contractors are normally entitled to time extensions for concurrent delays. Consequently, the contractor would be penalized if resource allocations were neglected in this case study. Discussion This paper proves that practice of resource allocation significantly affects results of schedule delay analysis and apportionment of delay responsibility. This raises several interesting issues for practitioners and researchers as follows. Fig. 5. Enhanced window analysis: window No. 1 JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007 / 135
6 Fig. 6. Traditional window analysis: window No. 2 Possible Extended Effect of Delays Traditional schedule analysis evaluates whether an event, several, or all events prolong the critical path s of the project. This paper shows that some delay can make unrealistic resource allocation in downstream work, which in turn may further delay the project. Available schedule analysis methods do not readily capture this possible extended effect of the delay. In other words, a schedule delay analysis that considers resource allocation is able to evaluate the forward effects of some delay. This results in a more trustworthy apportionment of delay responsibilities. Delay analysis aims at measuring the time difference between the actual project completion date and when the project would have ended but-for the owner-caused delays Zack Unfortunately, the answer to when the project would have ended but-for the ownercaused delays will be unreasonable unless the effect of resource allocation is addressed in that delay analysis. Future research may develop systematic algorithms that can readily identify whether a certain delaying event causes an extended effect and effectively quantify it, if any. Table 1. Schedule Analysis Summary Window number Window period date Completion duration days Fig. 7. Enhanced window analysis: window No. 2 Delays day Compensable Excusable Inexcusable Concurrent a a Results of enhanced window analysis existing window analysis. 136 / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007
7 Positive/Negative Effect of Resource Allocation on Delay Responsibility The effect of adding resource allocation considerations to a traditional schedule analysis can either add or reduce the impact of a delaying event. That is, either owners i.e., in the motivating case or contractors i.e., in the case study may face disadvantages in apportionment of delays under existing schedule analysis. The key question is under what delay circumstances will contractors or owners face such disadvantages? We are continuing to research this issue. Legal Acceptability Available schedule analysis techniques have frequently not incorporated the effects of resource allocation. Nevertheless, courts and review boards have supported delay claims based upon rigorous analysis techniques, especially the schedule window analysis method. We believe the methodology presented herein is logical and rigorous and will, over time, be acceptable to such bodies. Implications of Applying Enhanced Window Analysis Undoubtedly, the enhanced method potentially yields more reliable results. It however requires much more information from the project under dispute. Data collection for traditional window analyses is already an arduous task. Together with project records regarding delays i.e., weather, change orders, etc. as in the traditional method, the enhanced method further requires project records regarding practices of resource allocation. Although initial agreed resource allocation is important for the analysis, actual resource allocation also needs recording and using in the enhanced method. The reason is that some planned resource allocation practices have to be changed to accommodate uncertainties including delay occurrences that manifest during project execution. The other allocation practices may rarely change over time such as spatial resource constraints for a given activity. Work methods can lead to change resource allocation. For example, a shift from a labor-intensive method to an equipmentintensive one and vice versa may result in radical changes in both resource allocation practices and project completion time. This raises an interesting issue that unrealistic resource allocation in downstream work in certain circumstance can be caused by either current delays as previously discussed or by current changes in work methods. Thus, the status of work methods, especially when differing from original approved plans, has to be recorded and addressed during delay analysis. The analysis also needs to separate changes in resource allocation due to delays from those due to work method changes. This further emphasizes the importance of collecting pertinent project records under the contexts of delays. Recording project data for the enhanced window analysis can be less burdensome if resource allocation practices are selectively collected. Only critical resources which likely affect the project schedule need tracking and gathering their allocation practices. They include, but are not limited to, manpower, scarce and longlead materials, and major equipment and plants. Their status consists of availability, delivery issues, technical and market constraints, planned versus actual allocations, and so forth. A computer-aided tool such as a spreadsheet program may facilitate tracking these resource allocation practices. Conclusions Resource allocation substantially influences project time performance. Impractical allocation may account for the project delay. Unfortunately, current schedule analysis often does not consider a project s resource allocation. This paper illustrates that resource allocation can affect the results of a delay analysis. Performing a schedule analysis without considering resource allocations may increase the owner s or contractor s risk of assuming delay responsibility which is not his or her fault. This paper has proposed steps to ensure that delay analysis considers impacts of resource allocation. They are embedded in the window analysis, which is currently the most acceptable schedule analysis technique, to enhance its credibility. A case study was used to compare the analyses and results of the traditional and enhanced schedule window analysis methods. A delay analysis that includes the resource allocation used on the project is more trustworthy. As such, this research is useful to both industry professionals and researchers. The research enables more reliable schedule analysis. Future research may focus on issues to increase the usability, credibility, and acceptability of delay analysis considering resource allocation by project stakeholders. References Alkass, S., Mazerolle, M., and Harris, F Construction delay analysis techniques. Constr. Manage. Econom., 14 5, Al-Saggaf, H. A The five commandments of construction project delay analysis. Cost Eng., 40 4, Bartholomew, S. H Discussion of Concurrent delays in construction projects. J. Constr. Eng. Manage., 115 2, Bowers, J. A Criticality in resource-constrained networks. J. Oper. Res. Soc., 46 1, Chaney & James Construction Co. v. United States Ct. Cl. 699, 421 F.2d 728. Chua, D. K. H., and Shen, L. J Key constraints analysis with integrated production scheduler. J. Constr. Eng. Manage., 131 7, Continental Consolidated Corp. v. United States, 17 CCF 81, Davis, E. W Networks: Resource allocation. J. Industrial Engineering, 6 4, Finke, M. R Window analyses of compensable delays. J. Constr. Eng. Manage., 125 2, Finke, M. R Schedule density as a tool for pricing compensable float consumption. Cost Eng., 42 6, Fondahl, J. W The development of the construction engineer: past progress and future problems. J. Constr. Eng. Manage., 117 3, Frost, D CPM scheduling in resolving delay claims The big picture. Construction Law and Business, 2 6, 1 2. Hegazy, T Optimization of resource allocation and leveling using genetic algorithms. J. Constr. Eng. Manage., 125 3, Hegazy, T., and Zhang, K Daily windows delay analysis. J. Constr. Eng. Manage., 131 5, Holloway, S Introductory concepts in delay claims. Construction Law and Business, 2 6, 3 6. Hughes, F. J., and Ulwelling, J. K True concurrent delays and a proposed rule of law for apportioning damages for delay arising therefrom. Francis J. Hughes, Calif. Kartam, S Generic methodology for analyzing delay claims. J. Constr. Eng. Manage., 125 6, Kim, K., and de la Garza, J. M Phantom float. J. Constr. Eng. Manage., 129 5, JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007 / 137
8 Kim, K., and de la Garza, J. M Evaluation of the resourceconstrained critical path method algorithms. J. Constr. Eng. Manage., 131 5, Kim, Y., Kim, K., and Shin, D Delay analysis method using delay section. J. Constr. Eng. Manage., , Kraiem, Z. I., and Diekmann, J. E Concurrent delays in construction projects. J. Constr. Eng. Manage., 113 4, Lee, H. S., Ryu, H. G., Yu, J. H., and Kim, J. J Method for calculating schedule delay considering lost productivity. J. Constr. Eng. Manage., , Lesser, S. B., and Wallach, D. L Risky business: The active interference exception to no-damage-for-delay clauses. Constr. Lawyer, 23 4, 26 31, Lovejoy, V. A Claims schedule development and analysis: Collapsed as-built scheduling for beginners. Cost Eng., 46 1, Mbabazik, A., Hegazy, T., and Saccomanno, F Modified but-for method for delay analysis. J. Constr. Eng. Manage., , Niesse, D. P Forum: Determining after-the-fact time-related damages caused by changes. J. Profl. Issues Eng. Educ. Pract., 130 1, Pinnell, S. S Construction scheduling disputes: Proving entitlement. Constr. Lawyer, 12 1, Schumacher, L Quantifying and apportioning delay on construction projects. Cost Eng., 37 2, Shi, J. J., Cheung, S. O., and Arditi, D Construction delay computation method. J. Constr. Eng. Manage., 127 1, Stumpf, G. R Schedule delay analysis. Cost Eng., 42 7, Sweet, J., and Schneier, M. M Legal aspects of architecture, engineering, and the construction process, 7th Ed., Thomson- Engineering, Toronto. Thomas, H. R., and Messner, J. I No-damages-for-delay clause: Evaluating contract delay risk. J. Profl. Issues Eng. Educ. Pract., 129 4, Wickwire, J. M., and Ockman, S Use of critical path method on contract claims Constr. Lawyer, 19 4, Wickwire, J. M., and Smith, R. F The use of critical path method techniques in construction claims. Public Contract Law Journal, 7 1, Wiest, J. D A heuristic model for scheduling large projects with limited resources. Manage. Sci., 13 6, B359 B377. Willis, R. J Critical path analysis and resource constrained project scheduling Theory and practice. Eur. J. Oper. Res., 21 2, Zack, J. G Pacing delays The practical effect, Cost Eng., 42 7, Zack, J. G Calculation and recovery of home office overhead. AACE Int. Trans., CDR / JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT ASCE / FEBRUARY 2007
Open Access Review of Delay Analysis Methods: A Process-Based Comparison
The Open Construction and Building Technology Journal, 2009, 3, 81-89 81 Open Access Review of Delay Analysis Methods: A Process-Based Comparison Jyh-Bin Yang*,1 and Chih-Kuei Kao 2 1 Department of Construction
Construction Delay Analysis under Multiple Baseline Updates
Construction Delay Analysis under Multiple Baseline Updates By Wail Menesi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree of Master of Applied
Method for Calculating Schedule Delay Considering Lost Productivity
Method for Calculating Schedule Delay Considering Lost Productivity Hyun-Soo Lee, M.ASCE 1 ; Han-Guk Ryu 2 ; Jung-Ho Yu 3 ; and Jae-Jun Kim, M.ASCE 4 Abstract: A delay claim often occurs when a difference
BIM.03. Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses
BIM.03 Leveraging the Power of 4D Models for Analyzing and Presenting CPM Schedule Delay Analyses Mr. Kevin Coyne, PE PSP T his paper explores the use of 4D models, which provide a virtual construction
Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2
Criticality of Schedule Constraints Classification and Identification Qui T. Nguyen 1 and David K. H. Chua 2 Abstract In construction scheduling, constraints among activities are vital as they govern the
Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs
Buildings 01,, 0-1; doi:10.90/buildings000 Review OPEN ACCESS buildings ISSN 07-09 www.mdpi.com/journal/buildings/ Construction Delay Analysis Techniques A Review of Application Issues and Improvement
How To Perform An As-Built But For Schedule Delay Analysis
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs
Construction Delay Analysis Techniques A Review of Application Issues and Improvement Needs Nuhu Braimah, Lecturer of Construction/Infrastructure Management, Civil Engineering Department, School of Engineering
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY
ALGORITHM FOR DETERMINING CONTROLLING PATH CONSIDERING RESOURCE CONTINUITY By Mohammad A. Ammar 1 and Emad Elbeltagi 2 ABSTRACT: Scheduling of construction projects that have multiple units, wherein activities
Linear Schedules for Tunnel Projects
Mun Wei Leong Jacobs Associates Seattle, WA Linear Schedules for Tunnel Projects Daniel E. Kass, P.E. Jacobs Associates San Francisco, CA ABSTRACT: Tunneling projects lend themselves to the use of linear
Scheduling Best Practices
RECOVERY SCHEDULES By Mark I. Anderson, Executive Vice President and Chief Operating Officer of Warner Construction Consultants, Inc. In this article, as part of a continuing series of articles regarding
ALGORITHM FOR SCHEDULING WITH MULTISKILLED CONSTRAINED RESOURCES
ALGORITHM FOR SCHEDULING WITH MULTISKILLED CONSTRAINED RESOURCES By Tarek Hegazy, 1 Member, ASCE, Abdul Karim Shabeeb, 2 Emad Elbeltagi, 3 and Tariq Cheema 4 ABSTRACT: Scheduling with constrained resources,
Who pays the Money for the Time?
Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency
PROJECT CHANGE MANAGEMENT SYSTEM
PROJECT CHANGE MANAGEMENT SYSTEM By C. William Ibbs, 1 Clarence K. Wong, 2 and Young Hoon Kwak 3 ABSTRACT: Changes in projects are common and may be deleterious or beneficial whether you see a change as
Delay analysis Methodology in UAE construction Projects: Delay Claims, Literature Review 1. Saad Hegazy
Delay analysis Methodology in UAE construction Projects: 1 Saad Hegazy Introduction UAE is one of the pioneers among developing economies in the Middle East and the core for its development depends on
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Schedule and Delay Analysis Methodologies Richard J.
CDR.07. CPM Scheduling and How the Industry Views Its Use
CDR.07 CPM Scheduling and How the Industry Views Its Use Ms. Patricia D. Galloway, PE D elivering a project on time does not just mean signing a contract and hoping that the required completion date will
Project Control. 1. Schedule Updating
Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table
Construction Project Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical Models and Critical Path Method
Construction Project Scheduling with Time, Cost, and Material Restrictions Using Fuzzy Mathematical Models and Critical Path Method Daniel Castro-Lacouture, A.M.ASCE 1 ; Gürsel A. Süer 2 ; Julian Gonzalez-Joaqui
The Principles of Schedule Impact Analysis
College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923
METHODOLOGIES FOR DETERMINING CONSTRUCTION CONTRACT TIME AND EVALUATING CONTRACT TIME EXTENSIONS FINAL REPORT
METHODOLOGIES FOR DETERMINING CONSTRUCTION CONTRACT TIME AND EVALUATING CONTRACT TIME EXTENSIONS FINAL REPORT SCDOT Research Project 652: Construction Contract Time/Construction Contract Time Extension
OPTIMIZATION MODEL OF EXTERNAL RESOURCE ALLOCATION FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEMS
OPTIMIZATION MODEL OF EXTERNAL RESOURCE ALLOCATION FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING PROBLEMS Kuo-Chuan Shih Shu-Shun Liu Ph.D. Student, Graduate School of Engineering Science Assistant Professor,
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program
Engineering and Construction Contract Management Certificate Program (ECCM Workshops 1, 2, 3, 4, 5, 6) Certified Program 458 برنامج إدارة العقود الھندسية وعقود التشييد المتكامل معتمد عالميا 10 October
AACE International Recommended Practices
AACE International Recommended Practice No. 52R-06 TIME IMPACT ANALYSIS AS APPLIED IN CONSTRUCTION TCM Framework: 6.4 Forensic Performance Assessment, 7.2 Schedule Planning and Development, 10.2 Forecasting,
THE FUTURE OF FORENSIC SCHEDULE DELAY ANALYSIS
CONSTRUCTION THE FUTURE OF FORENSIC SCHEDULE DELAY ANALYSIS JOHN LIVENGOOD Managing Director 415.356.7137 [email protected] Navigant.com About Navigant Navigant Consulting, Inc. (NYSE: NCI) is
After major construction
Anderson Kill & Olick, P.C. REAL ESTATE & CONSTRUCTION A D V I S O R www.andersonkill.com Summer 2012 Ten Tips for Pursuing Insurance and Bond Claims After Construction Accidents By Finley Harckham Finley
Stanford University Guest Lecturer, Professor s Assistant, 1999-2004 Advanced Construction Issues and Claims, Civil Engineering Department
Current Position PKR CONSULTING, INC. Founder and Chief Executive Officer, 2004 Present Provides construction consulting, dispute resolution and expert witness services to owners, contractors, subcontractors,
Construction Scheduling Using Critical Path Analysis with Separate Time Segments
Construction Scheduling Using Critical Path Analysis with Separate Time Segments by Wail Menesi A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree
Scheduling Best Practices
The eighth article in the Scheduling Best Practices series is How to Handle the Weather. Our colleague Beth Blair, a managing consultant in Warner s Disputes Resolution Group, has over 20 years of experience
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, Claims & Counterclaims
The Practical Techniques on Contract Administration, Site Management, Scheduling, Budgeting, 469 (ECCM Workshops 3, 4 & 5) Certified Program التقنيات العملية في إعداد الجدول الزمني والمالي اإلدارة الموقعية
Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
PLANNING & FORENSIC DELAY ANALYSIS
PLANNING & FORENSIC DELAY ANALYSIS Experts in international construction & engineering disputes 01 www.gtfairway.com Fairway Fairway is an internationally recognised company that provides expert analysis
WELCOME Best Practices for Managing Construction Delay and Interference Claims
WELCOME Best Practices for Managing Construction Delay and Interference Claims Kenneth A. Slavens 314.345.6419 Husch Blackwell LLP Topics to be covered Delay Acceleration Disruption Delay Impact on Project
Constraint-Directed Scheduling for Multi-Storey Building Projects
Constraint-Directed Scheduling for Multi-Storey Building Projects Pasit Lorterapong* and Osama Moselhi** ** Department of Civil Engineering, King Mongkut ' s Institute of Technology Thonburi, Pracha u-tid
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM)
Major Characteristics and Functions of New Scheduling Software Beeliner Based on the Beeline Diagramming Method (BDM) Seon-Gyoo Kim Abstract The construction environment has been changing rapidly over
Construction Schedules
CONSTRUCTION CLAIMS EDITION EDITION NO. 15 September 2013 Construction Schedules Recovery Schedules And Constructive Acceleration Protect Yourself From Pitfalls By Christopher M. Burke Partner, Watt, Tieder,
Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects
Development of Resource-Driven Scheduling Model for Mass Housing Construction Projects Ar. A. Cindrela Devi and K. Ananthanarayanan Abstract Resource continuity is a key issue for Mass housing construction
A Critical Review of the AACEI Recommended Practice for Forensic Schedule Analysis
CONTRACT FORMS AND CONTRACT DRAFTING/PROJECT DELIVERY A Critical Review of the AACEI Recommended Practice for Forensic Schedule Analysis By Judah Lifschitz, Evans M. Barba, and Alexis M. Lockshin Judah
Bills of Quantity. D. Atkinson December 2000. Nature of Bills
Bills of Quantity D. Atkinson December 2000 Nature of Bills Bills of Quantities comprise a list of items of work which are briefly described. The Bills also provide a measure of the extent of work and
LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980
LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
Schedule Impact Analysis Using CPM Schedules
College of Engineering VDOT-VT Partnership for Project Scheduling Charles Edward Via, Jr. Department of Civil and Environmental Engineering 200 Patton Hall (0105) Blacksburg, Virginia 24061 540/231-0923
108-C-215 CRITICAL PATH METHOD SCHEDULE. (Revised 03-24-10)
CRITICAL PATH METHOD SCHEDULE (Revised 03-24-10) The Standard Specifications are revised as follows: SECTION 108, BEGIN LINE 177, INSERT AS FOLLOWS: 108.04.1 Critical Path Method Schedule (a) General Requirements
A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS
A SIMULATION MODEL FOR RESOURCE CONSTRAINED SCHEDULING OF MULTIPLE PROJECTS B. Kanagasabapathi 1 and K. Ananthanarayanan 2 Building Technology and Construction Management Division, Department of Civil
Construction Bonds. Vanessa S. Werden 604.408.2033 [email protected]
Construction Bonds Vanessa S. Werden 604.408.2033 [email protected] What is a bond? A bond is a special form of contract whereby one party guarantees the performance by another party of certain obligations. A
Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011)
Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011) Construction projects are usually complex undertakings with numerous participants, linked by a web
FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment
AACE International Recommended Practice No. 29R-03 FORENSIC SCHEDULE ANALYSIS TCM Framework: 6.4 Forensic Performance Assessment Acknowledgments: Kenji P. Hoshino, PSP CFCC (Author) Robert B. Brown, PE
TUPE 2006 Detailed Analysis
that activity is central or ancillary. Under existing case law this can include an organised group of one person! TUPE 2006 Detailed Analysis The TUPE 2006 Regulations completely replace the 1981 Regulations
A genetic algorithm for resource allocation in construction projects
Creative Construction Conference 2015 A genetic algorithm for resource allocation in construction projects Sofia Kaiafa, Athanasios P. Chassiakos* Sofia Kaiafa, Dept. of Civil Engineering, University of
Improved Schedule Analysis Considering Rework Impact and Optimum Delay Mitigation
Improved Schedule Analysis Considering Rework Impact and Optimum Delay Mitigation by Mohamed Said A thesis presented to the University of Waterloo in fulfillment of the thesis requirement for the degree
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
ASSESSMENT OF THE USE OF RESOURCE SCHEDULING FACILITIES IN PROJECT MANAGEMENT SOFTWARE PACKAGES FOR LARGE CONTRACTORS
ASSESSMENT OF THE USE OF RESOURCE SCHEDULING FACILITIES IN PROJECT MANAGEMENT SOFTWARE PACKAGES FOR LARGE CONTRACTORS Godfaurd John Department of Built and Natural Environment, University of Central Lancashire,
American College of Real Estate Lawyers Tucson, Arizona March 18, 2005. FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W.
American College of Real Estate Lawyers Tucson, Arizona March 18, 2005 FORCE MAJEURE IN BUILD-TO-SUIT LEASES By: Charles W. Trainor An excusable delay, or force majeure, clause is an important element
Construction Claims in
Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial
ATTORNEY GENERAL'S DEPARTMENT OF NSW & THE DEPARTMENT OF PREMIER AND CABINET
NSW GOVERNMENT REVIEW OF THE DUST DISEASES CLAIMS RESOLUTION PROCESS ISSUES PAPER DECEMBER 2008 ATTORNEY GENERAL'S DEPARTMENT OF NSW & THE DEPARTMENT OF PREMIER AND CABINET Issues Paper: Review of the
A. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: [email protected]
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA SECOND APPELLATE DISTRICT DIVISION TWO
Filed 8/27/14 Tesser Ruttenberg etc. v. Forever Entertainment CA2/2 NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying
Builder s Risk Structuring the Right Coverage, Avoiding and Resolving Disputes
Builder s Risk Structuring the Right Coverage, Avoiding and Resolving Disputes American Bar Association (ABA) Section of Litigation Insurance Coverage Tucson, Arizona March 6, 2015 Builder s Risk Speakers
MS PROJECT FOR CONSTRUCTION SCHEDULERS
MS PROJECT FOR CONSTRUCTION SCHEDULERS Copyright January 25, 2011 by Ron Winter, PSP F. Burak Evrenosoglu, PE CCE PSP Presented at The AACE International 55 th Annual Meeting June 22, 2011 Disneyland Hotel,
OPTIMIZATION OF RESOURCE ALLOCATION AND LEVELING USING GENETIC ALGORITHMS
OPTIMIZATION OF RESOURCE ALLOCATION AND LEVELING USING GENETIC ALGORITHMS By Tarek Hegazy, 1 Member, ASCE ABSTRACT: Resource allocation and leveling are among the top challenges in project management.
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613
IJSRD - International Journal for Scientific Research & Development Vol. 3, Issue 10, 2015 ISSN (online): 2321-0613 Planning, Scheduling and Resource Optimization for A Villa by using Ms-Project 2010 Mr.
Object-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
Resource Allocation and Scheduling
90 This section is about the general overview of scheduling and allocating resources. Assigning people and machines to accomplish work (work on tasks). Resource Allocation: Time-Constrained. Assigning
SYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University
AGREEMENT AMERICAN TRANSLATORS ASSOCIATION GUIDE TO A TRANSLATION SERVICES AGREEMENT
THE FOLLOWING GUIDE DOES NOT RESTRICT ANYONE FROM CONTRACTING FOR SERVICES ON TERMS AND CONDITIONS DIFFERENT FROM THOSE BELOW. THE USE OF ANY CLAUSE IS STRICTLY VOLUNTARY. NEITHER THE AMERICAN TRANSLATORS
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?
EXECUTIVE SUMMARY PURPOSE: This paper is a comparison and contrast of two project management planning and execution methodologies: critical path methodology (CPM) and the critical chain project management
Avant welcomes the opportunity to provide input into the Productivity Commission s draft report on Access to Justice Arrangements.
21 May 2014 Access to Justice Productivity Commission GPO Box 1428 Canberra City ACT 2601 Access to Justice Arrangements Draft Report Avant welcomes the opportunity to provide input into the Productivity
the loss. The insured may possess a claim in addition to the subrogation claim if the policy
JOINT PURSUIT OF RECOVERY WITH AN INSURED: ISSUES FOR THE SUBROGATING CARRIER TO CONSIDER By: Barrett Kiernan The subrogation claim of an insurance carrier does not always include all the damages incurred
The Roles of Functional and Cross-functional Planning in Managing the Enterprise Elliot Chocron Matthew Steigerwald Introduction
The Roles of Functional and Cross-functional Planning in Managing the Enterprise Elliot Chocron Matthew Steigerwald Introduction In 2003, General Motor s GVDP Operations Planning & Scheduling group responded
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
Contract Management. Brief 22. Public Procurement. September 2011
Brief 22 September 2011 Public Procurement Contract Management C O N T E N T S The process of contract management Contract management in practice Post contract performance review www.sigmaweb.org This
Project Management. Synopsis. 1. Introduction. Learning Objectives. Sections. Learning Summary
Synopsis Project Management 1. Introduction By the time you have completed Module 1 you should understand: what is meant by a project; the concept of project management; how project management can be structured
Indemnification Clauses, Part 1* Discussion from a/e ProNet's Risk Management and Contract Guide. J. Kent Holland, Jr., Esq.
Indemnification Clauses, Part 1* Discussion from a/e ProNet's Risk Management and Contract Guide J. Kent Holland, Jr., Esq. Issue: Indemnification provisions in contracts may require the design professional
Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education
OPEN ACCESS Engineering Leaders Conference 2014 Application of Critical Path Method scheduling to research plan and management of graduate students research project in engineering education M.O. Daramola
Schedule analytics tool
Schedule analytics tool As capital project spend increases and aggressive deadlines are built into project schedules, the reliance on accurate, transparent and meaningful schedule practices is growing.
March 30, 2007 CHAPTER 4
March 30, 07 CHAPTER 4 SUPPORTING PLANNING AND CONTROL: A CASE EXAMPLE Chapter Outline 4.1 Background What was the cause of the desperation that lead to the development of the Program Evaluation and Review
Construction Litigation: How to stay in the black and out of the Courtroom. Kenneth W. Movat. Certified Specialist in Construction Law
Construction Litigation: How to stay in the black and out of the Courtroom Kenneth W. Movat Certified Specialist in Construction Law This publication is intended for general information purposes only and
UNIFIED FACILITIES GUIDE SPECIFICATIONS ************************************************************************** SECTION TABLE OF CONTENTS
USACE / NAVFAC / AFCEC / NASA UFGS-01 32 16.00 20 (February 2015) Change 2-11/15 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 32 16.00 20 (November 2009) UNIFIED FACILITIES
MODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
IMPROVING THE DESIGN-CONSTRUCTION INTERFACE
Improving the Design-Construction Interface IMPROVING THE DESIGN-CONSTRUCTION INTERFACE Luis F. Alarcón 1 and Daniel A. Mardones 2 ABSTRACT In building projects customer requirements, constructive aspects
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE
SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in
Actuarial Standard of Practice No. 23. Data Quality. Revised Edition
Actuarial Standard of Practice No. 23 Data Quality Revised Edition Developed by the General Committee of the Actuarial Standards Board and Applies to All Practice Areas Adopted by the Actuarial Standards
JOURNAL OF OBJECT TECHNOLOGY
JOURNAL OF OBJECT TECHNOLOGY Online at www.jot.fm. Published by ETH Zurich, Chair of Software Engineering JOT, 2006 Vol. 5. No. 8, November-December 2006 Requirements Engineering Tasks Donald Firesmith,
Impacts on the construction industry of the new revenue standard
IFRS Impacts on the construction industry of the new revenue standard September 2014 kpmg.com/ifrs Contents The devil is in the detail 1 1 Critical judgements at contract inception 2 1.1 Pre-contract costs
GOODS AND SERVICES AGREEMENT BETWEEN SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY AND COMPANY/CONTRACTOR NAME
GOODS AND SERVICES AGREEMENT BETWEEN SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY AND COMPANY/CONTRACTOR NAME This GOODS AND SERVICES AGREEMENT ("Agreement") is entered into and effective [DATE], by and
MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
California Senate Bill 474 Impact on Owners & Contractors
California Senate Bill 474 Impact on Owners & Contractors Beginning January 1, 2013, project owners, general contractors ( GC ), construction managers ( CM ) and any lower tier contractor who employs subcontractors
The effectiveness of resource levelling tools for Resource Constraint Project Scheduling Problem
Available online at www.sciencedirect.com International Journal of Project Management 27 (2009) 493 500 www.elsevier.com/locate/ijproman The effectiveness of resource levelling tools for Resource Constraint
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without