ERPP (17) FALL PROTECTION RESCUE INFORMATION AND PROCEDURES
|
|
|
- Ella Horton
- 9 years ago
- Views:
Transcription
1 ERPP (17) FALL PROTECTION RESCUE INFORMATION AND PROCEDURES FALL PROTECTION RESCUE REQUIREMENTS Always consult the work jurisdictions OHS Regulations/codes when developing fall protection plans, carrying out fall protection training, preparing rescue plans, etc. For all jobs where fall hazards over 10ft (3 metres) exist, fall protection rescue procedures should be planned and communicated to workers; Workers using fall protection systems used/set-up by CCMET must follow the relevant Safe Work Practices and s. Practice drills and rescue procedures (with Prime Contractor, Client, Fire Department, etc.) should be completed/reviewed with workers; In the event recue from a fire department is necessary, CCMET must ensure an agreement is drafted and implemented as per the work jurisdictions OHS Regulations. The agreement should be updated as necessary when work operations change. INDUSTRIAL HIGH-ANGLE ROPE RESCUE BRITISH COLUMBIA (as taken from the WSBC Occupational Health and Safety Regulation Guidelines) Rescue of a worker at a high elevation can be effectively done in a variety of ways, depending on the circumstances at the workplace. For example, on a construction site, the personnel hoist may be used, or a "dedicated emergency platform" (DEP) hoisted by a tower or mobile crane may be used to remove an injured worker. Some work activities, for example window washing, swing stage work and tower crane operation result in a need for high angle rescue capability to rescue or remove a stranded or injured worker. An employer may develop its own high angle rescue capability, and this requires specialized equipment and training and practice. As an alternative, for a workplace located in an area serviced by a fire/rescue department, and where the local department has high angle rescue capabilities, the employer may be able to arrange for the local fire department to provide rescue services for the employer's operation. The following municipal fire/rescue departments have developed high angle (rope) rescue capability using techniques and equipment acceptable to the WSBC for workplace rescue. (The initiative to develop this capability was in part sponsored by the WSBC): City of Burnaby City of Port Alberni City of Coquitlam City of Port Coquitlam City of Delta City of Port Moody City of Kamloops District of Powell River City of Kelowna City of Prince George City of Kitimat Regional District of Kootenay Boundary City of Prince Rupert City of Richmond City of Saanich Page 1 of 14
2 City of Nanaimo City of Surrey City of Nelson City of Vancouver City of New Westminster City of West Vancouver City of North Vancouver Village of Whistler District of North Vancouver City of White Rock City of Penticton If a workplace is located outside the service area of a municipal fire/rescue department providing high angle rescue service, the employer has to provide for any necessary high angle rescue requirements by other acceptable means. If an employer wants to use the local municipal fire/rescue department as a high angle (rope) rescue service provider, the employer must notify the department in advance, and ensure the department is capable and prepared to provide the required services. CCMET Construction will utilize the "NOTICE OF WORK AT HEIGHT" standard WSBC form, to notify the fire department.. For projects that will have a longer term need for high angle rescue capability, CCMET will utilize the WSBC s High-Angle Rope Rescue written agreement. This agreement will be established between CCMET Construction and the Fire Department. A copy of this written agreement will be available at the workplace as an attachment to the fall protection evaluation and written work plan. In the event of being notified of the request for potential high-angle rope rescue services, The fire/rescue department may: visit the project site to determine site suitability for rescue purposes, request additional and reasonable provisions to assist rescue capabilities, and refuse to enter into an agreement to provide rescue services if all reasonable requirements are not fulfilled. VARIOUS FALL PROTECTION RESCUE PROCEDURES AND INFORMATION The below noted STANDARD fall protection rescue procedures can be used in CCMET s written Fall Protection Plans for specific job sites and adapted as required. WORKING BELOW BRIDGE DECK ABOVE DECK RESCUE Written procedures must be prepared on how to set up the tripod rescue system. The procedures should outline the complete rescue process and reviewed with workers; If using a tripod rescue system, all workers using the system must be trained on how to use the system Inspect rescue systems and related equipment on a daily basis, before set-up, and formally monthly; In the event of a fall below bridge deck, workers will erect a tripod system on the bridge deck, spreading the bridge ties, and activating the system. Page 2 of 14
3 Rescue systems must comply with applicable work jurisdictions OHS Regulations/Codes; The above is acceptable, for quick rescue, provided the following steps have been taken: The bridge deck hardware has been removed over the working area (to facilitate the moving of ties) The tripod system is available and in good working order No bridge traffic is evident. WORKING BELOW BRIDGE DECK BELOW DECK RESCUE Written procedures must be prepared on how to set up the tripod rescue system. The procedures should outline the complete rescue process and reviewed with workers; Inspect rescue systems and related equipment on a daily basis, before set-up, and formally monthly, etc. Workers using rescue system must be trained in its safe use; If using a snooper truck, hoisting equipment with a suspended work platform/man basket, elevating man lift or scissor lift, these systems may be used to aid fallen/suspended workers Ensure equipment box and remote hook is on a pier or close to the working area. Wrap cable around brace frame, lateral brace or bridge tie and connect eyes with shackle Install hook onto shackle and lower cable to person requiring rescue (rescue hook can be connected into back of d-ring either by worker requiring rescue or by means of a telescoping hook from above. Once cable is hooked into shock absorber or d-ring, commence lifting. Tripod systems must comply with applicable work jurisdictions OHS Regulations. SUSPENDED WORK PLATFORMS (MAN BASKETS) USING CRANE OR OTHER HOISTING DEVICE Using a suspended work platform/man basket for rescue or general work purposes is considered a critical lift. The appropriate SWPs, SJPs, rescue procedures/emergency response procedures and paperwork for using this system must be adhered to and completed in addition to following the work jurisdictions OHS Regulations. Written procedures must be prepared in the fall protection plan on how utilize a suspended work platform / man basket to carry out fall protection rescues. The procedures should outline the complete rescue process and reviewed with workers; Ensure the suspended work platform /man basket and related rigging is located close to the bridge/hoisting equipment and easily accessible to workers and crane; Inspect suspended work platform / man basket and related rigging & hardware daily /before use, including fall protection PPE etc.; Ensure suspended work platform/ man basket is engineered, with the correct Page 3 of 14
4 placard /information and capable of carrying out rescue work as required; Suspended Work Platforms / Man baskets, rigging, hardware, etc. must comply with applicable work jurisdictions OHS Regulations. Suspended Work Platforms / Man baskets, rigging, etc. must be tested, serviced and inspected as per manufacturer specifications, work jurisdictions OHS Regulations and CCMET s Equipment and Maintenance Program. WATER RESCUE VESSELS / LIFE PRESERVERS Whenever possible, guard against falls into water by using a fall protection system ideally guardrails should be used. If they cannot be used another fall protection system (follow hierarchy of fall protection controls) should be adopted and implemented. Water Rescues (Swift Water) may be coordinated through the local Fire Departments. Contact the Fire Department when preparing the rescue plan. Always consult the work jurisdictions OHS Regulations when preparing water rescue procedures. Written procedures must be prepared on how to deploy rescue water vessel /Life preserver ring in the event of an emergency. The procedures should outline the complete rescue process and reviewed with workers; Rescue water vessels, such as skiffs, aluminum crew boats, life preserver rings/ life line rope and jet skis should be inspected daily before work commences to ensure vessels / equipment are operational and free of damage. The vessels, equipment, etc. should be serviced according to manufacturer s specifications, applicable government regulations/ohs Regulations and CCMET s Equipment and Maintenance Program. Only workers with a pleasure craft operators ticket may run water rescue vessels. Where the waters are navigable, a rescue water vessel (boat) may need to be provided, as per the Work Contract. (Rescue vessel may be required as part of project s fall protection rescue plan.) For more information refer to WATER VESSEL EMERGENCY, RESCUE INFORMATION AND PROCEDURES in this Manual. Always have the appropriate type of personal protective equipment for working along the water and/or to assist with a water rescue (i.e. personal flotation devices, harnesses, lanyards). PFDs must be inspected daily before use and worn by the rescuers as well as the rescued worker. ELEVATING WORK PLATFORMS Instead of using a Suspended Work Platform or High-Angle Rescue system, an elevating man lift or scissor lift may be used instead. Always consult the work jurisdictions OHS Regulations when preparing fall protection rescue plans using an elevating man lift. Written procedures must be prepared on how to implement the rescue in the event Page 4 of 14
5 of an emergency. The procedures should outline the rescue process and be reviewed with workers. Elevating work platforms should be inspected before use on a daily basis. Results should be documented in the Equipment log book. Elevating work platforms should be tested, inspected, serviced and maintained in accordance with Manufacturers specifications, the work jurisdictions OHS Regulations and CCMET s Equipment and Maintenance Program. Only trained/qualified workers may operate elevating work platforms and other related equipment For more information, review the safe work practices for elevating work platforms. RESCUE ADVICE FOR FALLEN/SUSPENDED WORKER Everybody who is suspended in a safety harness runs the risk of shock and unconsciousness due to blood flow insufficiency. Unconsciousness can become life threatening after only a few minutes. Shock, caused by a lack of blood flow, is due to the blood accumulating in the lower parts of the body as a result of the musculature of the legs relaxing and the so-called muscle pump stopping. In order to maintain this function in good order, the victim of a fall must be made to keep his or her legs moving. In this way, blood circulation can be activated and the accumulation of blood in the legs prevented. The victim of a fall must be released from the suspended situation as quickly as possible. Important! The accident victim must never be laid down after being rescued from the suspended position, not even in the stable side position. The victim should be positioned with the upper body very well raised, i.e. seated, or possibly squatting in crouched posture. All restrictive belts and clothing should be unfastened. Follow the Serious Injury procedures as outlined in the Emergency Preparedness Section of the General Environmental, Health and Safety Plan or in the Emergency Response Plan created for the project. Laying the victim down horizontally could be life threatening. The blood that has accumulated in the legs flows abruptly into the heart creating risk of heart failure due to overstrain. Transfer to a horizontal posture should take place only gradually. Continuous monitoring of the respiration and circulation of the victim is necessary. In the event of unconsciousness, the air passages should be kept open. Page 5 of 14
6 SUSPENDED WORK PLATFORM/ MAN BASKET RESCUE PROCEDURES Tools/Equipment Required: Material(s) Required: Personal Protective Equipment: Designated Rescue man basket / suspended work platform (800lb capacity), rigging & hardware, first aid kit & Hard hat, personal flotation devices (PFDs, if working over water), fall protection harness & lanyard, steel toe boots, high visibility vest/gear equipment/other rescue equipment, radios / emergency communication devices, fall protection system equipment, Crane 1 Worker has fallen is suspended from bridge No way to rescue worker no suspended work platform /man basket on site or cannot reach worker, crane not on site, worker succumbs to injuries due to lengthy wait time for rescue No rescue procedure & emergency response plan in place to address fallen workers All workers on site must be trained on the fall protection plan (sign off as required) & emergency response plan. Site safety orientation before starting work. Develop & implement both plans. Only experienced /trained workers to be working from heights Wear & Inspect fall protection PPE (harness, lanyard, etc.) before use each day. Monthly formal inspections. Inspect fall protection system to be used by workers each day. Monthly formal inspections. Ensure primary & back-up first aid attendant on site, first aid kit/equipment also readily available Ensure rescue equipment, crane, rigging, is in good condition, readily available & accessible on site 2 Crew member radio crane operator to assist with rescue, crew members rig suspended work platform/man basket to crane No rigging or incorrect rigging available, Crew members don t know how to rig, platform is not easily accessible, no radios /emergency communication devices, no crane or crane operator on site Radios readily available on site, charged daily & distributed to first aid attendant, crane operator, workers, etc. Only trained/experienced workers to rig suspended work platform /man basket to crane Ensure rescue equipment, crane, rigging, is readily available, in good condition & accessible on site Suspended work platform must be NDT inspected/certified every 3 years & be used in accordance with OHS Regulations & CSA Standards, placard on basket & engineering records readily available on site Ensure appropriate rigging available for suspended work platform/man basket (design factor of 10 or higher, inspect rigging before use/ monthly Page 6 of 14
7 3 Designated crew member No way to rescue worker no (ideally a first aid suspended work platform /man attendant) gets into basket on site or cannot reach suspended work platform/ fallen worker, crane not on site, man basket worker succumbs to injuries due to lengthy wait time for rescue Crew member on ground with assistance of worker in suspended work platform/man basket instructs crane operator to lift suspended work platform/ basket to fallen workers location No rescue procedure & emergency response plan in place to address fallen workers No rigging or incorrect rigging available, Crew members don t know how to rig, platform is not easily accessible, no radios /emergency communication devices, no crane or crane operator on site. Worker in suspended work platform / man basket falls out of man basket Designate crew members to be first aid attendants, rescue workers for the work site upon job start up. Same recommended procedures in step #1 Same recommended procedures in step #2 Worker, must be equipped with radio in suspended work platform & wear fall protection PPE & must be tied off above the hook 4 Crane Operator flies suspended work platform/ man basket & worker to fallen worker suspended from bridge 5 Worker in suspended work platform /man basket reaches and removes lanyard attached to fallen workers harness and attaches new lanyard to fallen worker No way to rescue worker no suspended work platform /man basket on site or cannot reach fallen worker, crane not on site, worker succumbs to injuries due to lengthy wait time for rescue No rescue procedure & emergency response plan in place to address fallen workers no radios /emergency communication devices, no crane or crane operator on site. Worker in suspended work platform / man basket falls out of man basket Crane operator error swings into adjacent structure No way to rescue worker no suspended work platform /man basket on site or cannot reach fallen worker, crane not on site, worker succumbs to injuries due to lengthy wait time for rescue No rescue procedure & emergency response plan in place to address fallen workers Same recommended procedures in step #1 Same recommended procedures in step #2 Same recommended procedures in step #3 Only trained crane operators to operate crane, follow applicable Safe Work practices for operating cranes. Crane operator to communicate via radio to rescue worker in suspended work platform. Same recommended procedures in step #1 Same recommended procedures in step #2 Same recommended procedures in step #3 Rescue worker must be tied off at all times above the hook while assisting fallen worker into suspended work platform/ man basket. Bring extra lanyard for fallen worker so that they can be tied off to suspended work platform/ man basket above the hook when they get on Page 7 of 14
8 5 no radios /emergency Con't communication devices, no crane or crane operator on site. Rescue Worker in suspended work platform / man basket falls out of man basket. Fallen worker falls from suspended location to ground below 6 Fallen worker gets into suspended work platform / man basket. Rescue worker begins first aid treatment and instructs crane operator to take suspended work platform / man basket to safe unloading area No way to rescue worker no suspended work platform /man basket on site or cannot reach fallen worker, crane not on site, worker succumbs to injuries due to lengthy wait time for rescue No rescue procedure & emergency response plan in place to address fallen workers no radios /emergency communication devices, no crane or crane operator on site. Rescue Worker in suspended work platform / man basket falls out of man basket. Fallen worker falls from suspended location to ground below No safe unloading area for fallen worker inside suspended work platform No first aid equipment on site, no primary or back-up first aid attendants designated for site Bring first aid equipment/kit on to suspended work platform/man basket if serious injuries sustained to fallen worker. Begin administering first aid in basket as required. Extra worker (back-up first aid attendant) in suspended work platform/ man basket if necessary due to fallen worker injuries Same recommended procedures in step #1 Same recommended procedures in step #2 Same recommended procedures in step #3 Same recommended procedures in step #5 Ensure there is an adequate area for the suspended work platform /man basket to land, free of obstructions & hazards. Practice regular housekeeping/ clean-up of the work areas. Safe landing area should be on the town/camp side of the bridge If the fallen worker is injured, Contact first responders for ambulance/medevac while rescue is underway. Have a worker meet first responders/medevac & escort them to suspended work platform landing area If ETV on site (as required by OHS Regulations), Another worker to drive ETV to safe landing area for suspended work to get the worker to medical treatment Ensure ETV is clean & in good working order, inspect daily, straps in ETV to secure worker as required 7 Crew members on ground assist fallen worker out of suspended work platform/ man basket and begin/continue providing first aid No way to rescue worker no suspended work platform /man basket on site or cannot reach fallen worker, crane not on site, worker succumbs to injuries due to lengthy wait time for rescue No rescue procedure & emergency response plan in place to address fallen workers Same recommended procedures in step #1 Same recommended procedures in step #2 Same recommended procedures in step #3 Same recommended procedures in step #5 Page 8 of 14
9 7 no radios /emergency Con't communication devices, no crane or crane operator on site. Rescue Worker in suspended work platform / man basket falls out of man basket. Fallen worker falls from suspended location to ground below Same recommended procedures in step #6 Dispose fall protection PPE and system used by fallen worker No safe unloading area for fallen worker inside suspended work platform No first aid equipment on site, no primary or back-up first aid attendants designated for site ELEVATING MAN LIFT/ AERIAL WORK PLATFORM RESCUE PROCEDURES Tools/Equipment Required: Elevating man lift/aerial work platform, first aid kit & equipment/other rescue equipment, radios / emergency communication devices, fall protection system equipment, spill kit, fire extinguisher Material(s) Required: Fuel Personal Protective Equipment: Hard hat, fall protection harness & lanyard, steel toe boots, high visibility vest/gear 1 Worker has fallen is No way to rescue worker no suspended from bridge / elevating work platform on site or work area cannot reach worker (boom is not long enough), worker succumbs to injuries due to lengthy wait time for rescue No rescue procedure & emergency response plan in place to address fallen workers All workers on site must be trained on the fall protection plan (sign off as required) & emergency response plan. Site safety orientation before starting work. Develop & implement both plans. Only experienced /trained workers to be working from heights Wear & Inspect fall protection PPE (harness, lanyard, etc.) and basic PPE before use each day. Monthly formal inspections. Inspect fall protection system (including elevating man lifts) to be used by workers each day. Monthly formal inspections. Ensure primary & back-up first aid attendant on site, first aid kit/equipment also readily available Ensure rescue equipment, elevating man lift is in good condition, readily available & accessible on site. Boom must be long enough to carry out work in all areas Page 9 of 14
10 2 Crew member radio Elevating man lift cannot access elevating man lift operator rescue location due to uneven to assist with rescue, ground / poor ground conditions, crew members on ground Crew members don t know how to assist with rescue operate elevating work platform, elevating work platform is not easily accessible, Elevating man lift failure, no radios /emergency communication devices, no operator on site 3 Designated crew member (ideally a first aid attendant) gets into elevating work platform. Another worker to operate elevating work platform & drive to fallen worker location Elevating man lift hits workers /equipment on ground Elevating man lift cannot access rescue location due to uneven ground / poor ground conditions, Crew members don t know how to operate elevating work platform, elevating work platform is not easily accessible, no radios /emergency communication devices, no operator on site Radios readily available on site, charged daily & distributed to first aid attendant, elevating man lift operator, workers, etc. Only trained/experienced workers to operate elevating work platform Ensure rescue equipment, elevating work platform is readily available, in good condition & accessible on site Elevating work platform must be NDT inspected/certified & be used in accordance with OHS Regulations & CSA Standards, log book completed daily before use & readily available on site Site must have cleared access/egress routes, workers on ground must maintain a safe distance Follow applicable Safe Work practices for using & working around elevating man lifts/aerial work platforms Use 3-point contact when getting into & out of equipment Follow the recommended procedures in step #1 Follow the recommended procedures in step #2 Workers in the elevating man lift must be tied off to the guardrails/anchor points on the machine at all times. Elevating man lift hits workers /equipment on ground No first aid attendants on site Workers in elevating work platform fall off of platform 4 Once at the fallen worker location, 2 workers in elevating man lift to assist fallen worker & help them into the elevating man lift Worker #1 in elevating man lift removes lanyard attached to fallen workers harness and attaches new lanyard to fallen worker Elevating man lift cannot access rescue location due to uneven ground / poor ground conditions, Crew members don t know how to operate elevating work platform, elevating work platform is not easily accessible, Elevating man lift failure, no radios /emergency communication devices, no operator on site Follow the recommended procedures in step #1 Follow the recommended procedures in step #2 Follow the recommended procedures in step #3 If the fallen worker is injured, Contact first responders for ambulance/medevac while rescue is underway. Have a worker meet first responders/medevac & escort them to site Page 10 of 14
11 4 Con't If fallen worker is injured, begin administering first aid Boom makes contact with obstructions / adjacent structures Fallen worker falls from location or from elevating man lift If ETV on site (as required by OHS Regulations), Another worker to drive ETV to safe landing area for suspended work to get the worker to medical treatment Ensure ETV is clean & in good working order, inspect daily, straps in ETV to secure worker as required 5 Once the elevating man lift has travelled to the unloading area, the operator booms down to get the fallen worker onto the ground - continue to provide first aid Boom makes contact with obstructions / adjacent structures Elevating man lift failure, no radios /emergency communication devices, no operator on site Fallen worker sustains further injury getting out of elevating man lift Follow the recommended procedures in step #1 Follow the recommended procedures in step #2 Follow the recommended procedures in step #3 Follow the recommended procedure in step #4 Dispose fall protection PPE and system used by fallen worker WORKING ON TOP OF CONCRETE BATCH PLANT ELEVATING MAN LIFT RESCUE PROCEDURES Tools/Equipment Required: Elevating man lift/aerial work platform, first aid kit & equipment (transport basket) rescue equipment, radios / emergency communication devices, fall protection system equipment, spill kit, fire extinguisher, ropes and hardware Material(s) Required: Fuel Personal Protective Equipment: Hard hat, fall protection harness & lanyard, steel toe boots, high visibility apparel, safety glasses, eye protection, hand protection 1 Injury occurs or Workers ensure of how to maintenance worker initiate emergency response falls from work area and rescue plan 2 Ground crew notified first aid and man lift operator Radios /emergency communication devices don t work. First aid attendants or man lift operator cannot be found. No one trained on how to operate man lift. Review fall protection and rescue plans with personnel. Perform mock drill to test rescue plan. Ensure workplace parties are notified of maintenance being performed on batch plant. Ensure first aid attendants on standby during operations Determine maintenance schedule and communicate dates to primary and back-up FA attendants, Ensure first aid attendants on standby during operations. Inspect radios before use each day. Ensure at least 2 workers are trained on how to run man lifts on scheduled maintenance days. Page 11 of 14
12 First aid attendants Injured worker sustains 3 arrive on site, primary additional injury as a result of first aid attendant takes removing lanyard from worker. over situation. Continued on next page Primary First Aid attendant to determine movement of injured worker or removal of lanyards. Continued on next page Determine if: - Transport basket required - First Aid to ascent tower to address injured worker - Man lift required to transport injured worker to ground - Further medical attention required (i.e. medical evacuation by helicopter, transportation to hospital by ambulance/ ETV or crew truck.) Transport Basket Required 4 Man lift operator to travel man lift to height of injured or fallen worker. (FA kit and transport basket in on man lift secured) Primary First Aid Attendant climbs up tower to access worker Elevating man lift is not working correctly. First aid kit cannot be found/ transport basket not available Primary first aid attendant falls Complete pre-use inspection of elevating man lift on a daily basis. Carry out regular servicing and maintenance of man basket. Inspect first aid kit and rescue equipment on a regular basis. Store in designated area. 100% tie off when accessing tower / injured worker location 5 Primary First Aid Attendant performs first aid and secures injured worker in transport basket. Risk of falling (injured worker, transport basket, injured worker) Ensure fall protection plan is implemented and adhered to. Regular inspection of fall protection equipment. Transport basket will be tied off to man lift. Under direction of Primary First Aid Attendant, the transport basket will be transferred to the tower and tied off to the tower safety railings Continued on next page Page 12 of 14
13 693 Sequence of Steps Potential Accidents or 5 Con t Injured worker will be transferred to the transport basket and secured and slid back into the elevating man lift basket. 6 Elevating man lift operator lowers injured worker and primary first aid attendant down to ground Maintenance person #2 climbs down tower Remove from elevating man lift basket and Perform additional first aid to injured worker and coordinate transportation to medical treatment Elevating man lift is not working correctly. First aid kit cannot be found/ transport basket not available Primary first aid attendant falls Risk of falling (injured worker, transport basket, injured worker) Transport basket, injured worker, elevating man lift operator and Primary First Aid Attendant to be tied off at all times. Follow safe job procedure steps #4 through #6 During the rescue process, the back-up first aid attendant can take instructions from the ground from the primary first aid attendant and make arrangements for medical evacuation. (i.e. medical evacuation or ETV/ Ambulance Transportation) First Aid to Ascend Tower without Transport Basket Primary first aid attendant ascends tower using elevating man lift run by elevating man lift operator to access injured/ fallen worker Primary first aid attendant treats injured/ fallen worker assists worker from fallen position Injured /fallen worker enters elevating man lift with assistance and is transported to the ground by the elevating man lift operator. Same hazards apply in steps #1 through #6 Same hazards apply in steps #1 through #6 Same hazards apply in steps #1 through #6 Same safe job procedures apply in steps #1 through #6 Same safe job procedures apply in steps #1 through #6 Same safe job procedures apply in steps #1 through #6 10 Elevating man lift operator returns to remove primary first aid attendant & maint. worker #2 to the ground Same hazards apply in steps #1 through #6 Same safe job procedures apply in steps #1 through #6 Page 13 of 14
14 Emergency Contact List Ambulance 911 Fire Department 911 Police 911 British Columbia BC Air Ambulance 24 Hour Emergency BC Ambulance 24 Hour Emergency Forest Fire Reporting 24 Hour Emergency Oil and Gas Commission Poison Control 24 Hour Emergency WCB BC Environmental Spills/Complaint 24 Hour Emergency Radiation Emergency Alberta Poison Centre 24 Hour Emergency Environmental Spills/Complaint 24 Hour Emergency Stars Emergency Link Centre 24 Hour Emergency Atco Electric 24 Hour Emergency Atco Gas 24 Hour Emergency OH&S (serious incident fatality) 24 Hour Emergency Page 14 of 14
Fall Protection System: A system put in place to protect workers from falling. (i.e. installation of guardrails, fall arrest, fall restraint, etc.
SWP (6) FALL PROTECTION PROGRAM The following information on Fall Protection has been based around the BC OHS Regulations, standards, policies and guidelines. Prior to starting work outside of BC, the
Fall Protection Guidelines
OCT 2015 1 of 6 Fall Protection Guidelines 1.0 PURPOSE To establish the requirements and procedures to protect employees and other persons conducting work from hazards associated with falling from one
SITE SPECIFIC FALL PROTECTION PLAN
1 THIS PLAN IS SPECIFIC TO: PROJECT & ADDRESS 1.1 THIS PLAN IS SPECIFIC TO THE FOLLOWING AREA(S) ON SITE: Parkade level: Typical level: Other: Between G/L: 1.2 THIS PLAN IS APPLICABLE TO THE FOLLOWING
SG19:10 NASC. A Guide to Formulating a Rescue Plan. NOTE: Scaffolders who need to use a harness should never work alone. 1 of 8 1.
SG19:10 A Guide to Formulating a Rescue Plan 1. INTRODUCTION The legal requirement for rescue is specified in the Work at Height Regulations 2005 and require every employer in selecting work equipment
Sample Fall Rescue Plan for Bridge Work
This document is intended to provide guidance for developing fall rescue plans for bridge contractors. The Occupational Safety and Health Administration s (OSHA) regulation 29 CFR 1926.502(d)(20) states:
Slips, Trips and Falls. AR 2012 DMME Division of Mineral Mining
Slips, Trips and Falls AR 2012 DMME Division of Mineral Mining It Doesn t Take Much Since the beginning of 2008, 14 miners have died from injuries sustained in falls at M/NM mines. Several were wearing
Names and Contact Numbers of Competent Rescuers Assigned to Job (Please print)
Emergency Plan For Rescue from Heights Department of Facilities Management Occupational Health and Safety Shop Performing Work Date Work Order No. Job Location Job Description Height of work platform /
EMERGENCY PREPAREDNESS
EMERGENCY PREPAREDNESS Page 1 SECTION 11 EMERGENCY PREPAREDNESS CONSIDERATIONS FOR APPROPRIATE EMERGENCY PREPAREDNESS...3 EMERGENCY PREPAREDNESS POLICY Emergency Preparedness Policy - Sample...5 EMERGENCY
Guide to Fall Protection Regulations
Guide to Fall Protection Regulations Produced by: Workers Compensation Board of PEI PO Box 757 Charlottetown PE C1A 7L7 902-368-5697 or 1-800-237-5049 website: www.wcb.pe.ca Revised June 2013 Guide to
Health and Safety Resources Caution to Users
Health and Safety Resources Caution to Users Many of the resources in this archive were originally prepared by WSN s predecessor organizations for use by industry clients. While much of the information
BCIT. CNST 1100 Construction Safety Officer Training. Lesson Plan
BCIT CNST 1100 Construction Safety Officer Training Lesson Plan BCIT Two Week Outline- CNST 1100 (Please note there may be adjustments made to this outline) Monday- Day #1 Week #1 0730 Paperwork Introductions
The Work At Height Safety Association
The Work At Height Safety Association Technical Guidance Note 5 Guidance on rescue during work at height A series of informative notes for all industries involved with work at height or rescue. The information
Programme-Based Engagement (ProBE) for Fall From Heights. Statistics
Programme-Based Engagement (ProBE) for Fall From Heights Statistics For the past ten years, falling from height has been the number one cause of death in workplaces in Singapore. It has accounted for 34%
The Tomato Plant Company Ltd. Method Statement and Risk Assessment Loads requiring lifting
The Tomato Plant Company Ltd Method Statement and Risk Assessment Loads requiring lifting Generic method statement & risk assessment for the removal of portable accommodation units and/or shipping containers
EMPLOYEE FALL PROTECTION
EMPLOYEE FALL PROTECTION You can fall from any height and be seriously injured or killed. In the construction industry, as well as any other industry, when falls from heights happen, they are usually very
FALL PROTECTION PROGRAM
FALL PROTECTION PROGRAM Page 2 of 15 Table of Contents Applicability... 3 Overview... 3 Definitions... 3 Responsibilities... 5 Risk Assessment... 6 Risk Management... 7 Roof Access Procedure 10 Rescue
Working at Heights and Fall Protection
Standard Operating Procedures Working at Heights and Fall Protection Last Modified: JAN 2013 1 of 6 Working at Heights and Fall Protection I Purpose Serious accidents can result from falls. All employees
FALL PROTECTION PROGRAM RESCUE PLAN
GLOBAL LEADER IN FALL PROTECTION Capital Safety 95 Derby Street Silverwater, NSW 2128 Tel: 02 8753 7600 Fax: 02 8753 7603 FALL PROTECTION PROGRAM RESCUE PLAN IMPORTANT: This document is intended to provide
This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor.
Big Four Construction Hazards: Fall Hazards This material was produced under grant number SH-17792-08-60-F-48 Occupational Safety and Health Administration, U.S. Department of Labor. It does not necessarily
PORT HEDLAND PORT AUTHORITY
PORT HEDLAND PORT AUTHORITY Working at Heights Procedure PR-OHS021 Document Users : All Contractors All Port Users Port Hedland Port Authority Position Responsible For Keeping Document Current : Safety
CHAPTER 2 GENERAL SAFETY REQUIREMENTS
Bridge Inspection Handbook 2-1 2.1 INTRODUCTION CHAPTER 2 GENERAL SAFETY REQUIREMENTS Safety is everyone's business. As an employer, MassDOT is obligated to promote job safety and furnish safe tools, equipment,
FALLING OBJECTS EXCESSIVE NOISE CHAINSAW & CHIPPER WORK AT HEIGHTS MANUAL HANDLING
JOB NO: PROJECT: DATE: SWMS NO: SWMS 001.1 PREPARED BY: Ian Hartley REVISED BY: Nick Bragg & Cameron McNeil ACTIVITY: TREE REMOVAL & PRUNING SIGNED BY: REVISION DATE: December 2015 MINIMUM PERSONAL PROTECTIVE
Job safety analysis Installing wall frames and roof trusses on-site
Job safety analysis Installing wall frames and roof trusses on-site 1. Taking delivery: - unloading the truck - moving materials manually to the work area Body sprains and strains from lifting materials
Fall Protection and Fall Prevention. San José State University Environmental Health and Safety Facilities Development & Operations
Fall Protection and Fall Prevention San José State University Environmental Health and Safety Facilities Development & Operations Learning Objectives To understand the hazards of falls To understand when
Working at Height Risk of suspension trauma and rescue plan
Working at Height Risk of suspension trauma and rescue plan Risk of suspension trauma and rescue plan page 1 V1 November 2010 1: Working at height Loading and unloading of trucks for Ineos O&P downstream
Work at Height. John Frontczak Construction Manager Facilities Engineering. 2011 Chevron Corporation. All rights reserved.
Today Work at Height John Frontczak Construction Manager Facilities Engineering Agenda Definition and Requirements Fall Prevention Scaffolding Safety Fall Protection Fall-Arrest System Rescue Plan Training
COURSE INFORMATION SHEET
Course ID: HGT - WRKHT COURSE OVERVIEW WORKING AT HEIGHTS Working at Heights is an approved Ontario Ministry of Labour (MOL) program (Approved Training Program ID # WAH56789). This program was designed
Tremline Pty Ltd trading as The Hills Bark Blower
JSA No: Rev: 10011 Date: 10010 ABN 1 07 880 6 Website: wwwbarkblowercomau Job Number Start Time: Vehicle : Max Length Hose Date: Company Name: Product: Quantities Depth Job site address: Description of
INTRODUCTION... 3. 1.0 Purpose... 4. 2.0 Policy... 4. Exception for Short-Term Workplace Visits... 4. Relevant Legislation and Regulations...
March 2006 INTRODUCTION... 3 1.0 Purpose... 4 2.0 Policy... 4 Exception for Short-Term Workplace Visits... 4 Relevant Legislation and Regulations... 5 Definitions... 5 Contractor Safety Coordination Overview...
Good Practice Guide. The Selection of Access Methods to Install and Dismantle Safety Netting
Good Practice Guide The Selection of Access Methods to Install and Dismantle Safety Netting FASET is the trade association for the safety net rigging and temporary safety systems industry. This document
EMERGENCY PREPAREDNESS & RESPONSE PROCEDURE
1 of 12 DOCUMENT REVISION HISTORY Revision No. Date DESCRIPTION OF CHANGES Pages Affected By 00 01/07/2003 Draft Issued For Comment All HSEQ Dept. 01 01/09/2003 Total Change First Approved Issue All HSEQ
Gotcha! rescue. Stranded in an aerial work platform
Gotcha! Following on from last month s article on harnesses and lanyards, Ed Darwin looks at points to consider when rescuing those trapped at height and stresses the need for contingency planning. When
Company Name Company Address Company Phone Number Company Fax Number
Job Hazard Analysis Plumbing Company Name Company Address Company Phone Number Company Fax Number Job/Task Plumbing fixture and piping Date Prepared: 08.04.2010 installation Project Name: Project Name
Fall Protection Equipment
Fall Protection Equipment Quick Tips #130 Introduction Before you can begin a fall protection program, you must identify the potential fall hazards in your workplace. Any time a worker is at a height of
WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document Fall Protection in Residential Construction Table of Contents Executive Summary... 1 Introduction... 1
Working at a height of two metres or more while carrying out general work activities or construction works
1. Working at Heights 2. Scope / Description of Job Working at a height of two metres or more while carrying out general work activities or construction works 3. Critical Safety Issues A fall from any
June 22, 2013. Steve Johnson Operation Manager Best Roofing, Inc. 7002 N. 288th St. Sioux City, IA 68064. Booker Elementary Safety Survey Omaha, NE
June 22, 2013 Steve Johnson Operation Manager Best Roofing, Inc. 7002 N. 288th St. Sioux City, IA 68064 Re: Booker Elementary Safety Survey Omaha, NE Steve Johnson, This report is in follow-up to the safety
Fall Protection Program
Fall Protection Program Policy: It is the policy of our company to provide fall protection for employees exposed to fall hazards greater than 7 ½ feet. Fall hazards include but, are not limited to; work
WORKING AT HEIGHT & ITS WOES
WORKING AT HEIGHT & ITS WOES Capital Safety EMEA HOW FAR WILL A PERSON FALL IN...? TIME seconds DISTANCE metres 1 4.9 2 19.6 3 44.1 4 78.4 ABSOLUTELY ZERO MARGIN FOR ERROR! 2FT?!? 6FT?!? 50FT?!?! COMMON
Powered Industrial Truck Safety Program
Powered Industrial Truck Safety Program TABLE OF CONTENTS Forklift Safety Program 1.0 Overview... 3 2.0 Policy.....3 3.0 Requirements 3 4.0 Purpose. 3 5.0 Scope......4 6.0 Forklift Procedures 4 6.0 Responsibilities.....6
GN-008. Mast and Tower Rescue Guidance for Radio and Rigging Teams working on Radio Structures
GN-008 Mast and Tower Rescue Guidance for Radio and Rigging Teams working on Radio Structures Issue 1.0 Review date : November 2015 MATS Group Guidance Note Mast and Tower Rescue Guidance for Radio and
Working at Heights. Understanding the Requirements of Fall Protection. 29 CFR 1926 Subpart M Fall Protection
Working at Heights Understanding the Requirements of Fall Protection 29 CFR 1926 Subpart M Fall Protection When is Fall Protection Required? Fall Protection is required for employees who are working: 1.
Fall Protection Susan Harwood Grant Training Program 2013 Fall Arrest. OSHA Susan Harwood Training - AGC
Fall Protection Susan Harwood Grant Training Program 2013 Fall Arrest Learning Objectives Identify the components of a proper personal fall arrest system (PFAS) Understand how to calculate total fall distance
RESCUE PLAN FALL PROTECTION PROGRAM
RESCUE PLAN IMPORTANT: This document is intended to provide guidance only for developing site-specific rescue plans for working at heights. GLOBAL LEADER IN FALL PROTECTION RESCUE PLAN This document is
SECTION 2 HAZARDOUS WORK. CLASSIC STANDARD 2.04 Working at Heights
SECTION 2 HAZARDOUS WORK CLASSIC STANDARD 2.04 Working at Heights 1 Purpose The purpose of this standard is to document Rio Tinto Aluminium Mining & Refining Weipa s requirements to minimise, and where
Level 1 Award in Health and Safety in a Construction Environment
Level 1 Award in Health and Safety in a Construction Environment Student notes (sample) www.britsafe.org Membership Training Qualifications Audit and Consultancy Audit and Policy Consultancy and Opinion
7. PRINCIPAL STEPS 8. POTENTIAL HAZARDS 9. RECOMMENDED CONTROLS
ACTIVITY HAZARD ANALYSIS (AHA) 1. Contract Number: 2. Contractor Name: 3. Date prepared: 4. Title/Activity Performed: FIXED SCAFFOLDING 5. Location: 6. Estimated Date of Completion: 7. PRINCIPAL STEPS
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY
THE UNIVERSITY OF SHEFFIELD WORK AT HEIGHT POLICY CONTENTS Page No 1 INTRODUCTION 2 2 LEGISLATION 2 3 HIERARCHY OF CONTROL 2 4 WORK AT HEIGHT POLICY 3 5 ROLES AND RESPONSIBILITIES 3 6 RISK ASSESSMENTS
PRE-COURSE ASSIGNMENT
FALL PROTECTION POLICY ASRETEC is committed to ensure that, for all in-house courses, site trainings, demonstrations and operational projects, we maintain the highest level of Work-at-Height Safety, providing
ELEVATED WORK POLICY
ELEVATED WORK POLICY 1.0 BACKGROUND The purpose of this program is to prevent accidents and injuries to workers from falls and to provide employees with the information for the safe use of fall protection
Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014
Workplace Incident Fatalities Accepted by the Workers Compensation Board in 2014 Workplace Incident Fatalities Year to date, numbers as of December 31, 2014 Workplace Incident fatalities are cases where
ELECTRICAL SAFETY & ARC FLASH Handbook
Electricity Forum Handbooks Electrical Safety and Arc Flash Handbook Series ELECTRICAL SAFETY & ARC FLASH Handbook Volume 10 Reprinted by permission of the publisher, Hurst Communications, from the Electrical
POTENTIAL HEALTH & SAFETY HAZARDS
Number: OH&S 18.27.1 Revision Date: 2014.01.28 Crane Safety Procedures 1. PURPOSE 1.1. These procedures provide the University requirements for the operation and management of overhead travelling cranes
Method Statement. Risk Assessment
Method Statement Risk Assessment Client: Location: Page 1 of 6 Health and Safety Method Statement and Risk Assessment Customer & Address: Site Address: Description of Works: Method Statement: Risk Assessment:
RISK RATING SAFE WORK METHOD STATEMENT 1 HIGH 2 MEDIUM 3LOW. I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager
RISK RATING 1 HIGH 2 MEDIUM 3LOW SAFE WORK METHOD STATEMENT Title: : Working at Height above 2trs Ref No: 1 I approve the use of this Safe Work Method Statement: NAME: POSITION: Department Manager SIGNATURE:
WORK AT HEIGHT UNIT 4
WORK AT HEIGHT UNIT 4 WHAT IS WORKING AT HEIGHT? The Working At Height Regulations 2005 define working at height as:- Any work above or below ground level where a fall would result in personal injury.
Incident Investigations Handbook
Incident Investigations Handbook The following agencies may respond to an incident (insert phone numbers of your location) Police Fire/rescue Ambulance Coroner WorkSafeBC BC Safety Authority ICBC BC Hydro
Section 2 Hazard Assessment and Risk Control Table of Contents
Section 2 Hazard Assessment and Risk Control Table of Contents 2.1 INTRODUCTION... 2 Class A Hazard... 3 Class B Hazard... 3 Class C Hazard... 3 Class D Hazard... 3 2.2 HAZARD ASSESSMENT... 4 2.2.1 Hazard
CHAPTER 10. FALL PROTECTION PROGRAM
CHAPTER 10. FALL PROTECTION PROGRAM 1000 GENERAL. This chapter establishes policy for developing fall protection programs to protect all Federal Aviation Administration (FAA) personnel working at elevated
Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, 1926.500, 1926.501, 1926.502, and1926.
STANDARDS Fall Protection, Title 29 Code of Federal Regulations (CFR) Part 45, Subpart M, Fall Protection, 1926.500, 1926.501, 1926.502, and1926.503 1.0 Purpose This document meets the requirements outlined
Chapter 3: Fall Protection/ Scaffolding Safety
Chapter 3: Fall Protection/ Scaffolding Safety Learning Objectives In this chapter you will learn to: recognize the hazards commonly associated with work on or around scaffolds; be aware of common scaffold-related
MA FACE Occupational Fatality Report
MA FACE Occupational Fatality Report Arborist Dies in Fall from a Tree after being Hoisted by a Crane to the Tree - Massachusetts Release Date: September 25, 2013 Investigation: # 11-MA-031-01 Massachusetts
The University of Texas at Austin. Lift Safety Plan
The University of Texas at Austin Lift Safety Plan August 2012 President s Environmental Health and Safety Statement of Commitment The University of Texas at Austin is committed to protecting the health
OCCUPATIONAL SAFETY AND HEALTH RECORDS
Occupational Safety Records Occupational Safety OCCUPATIONAL SAFETY AND HEALTH RECORDS Numbers listed below refer to the applicable part from the WorkSafeBC Occupational Health and Safety Regulation and/or
Contractor s Safe Working Agreement
Contractor s Safe Working Agreement This statement provides details on how I/we, the Trade Contractor will manage the health and safety hazards associated with my/our work. ASSESSING WORKPLACE HEALTH AND
PART 2.11 SERVICE NL WORKPLACE HEALTH AND SAFETY INSPECTIONS
PART 2.11 SERVICE NL WORKPLACE HEALTH AND SAFETY INSPECTIONS Executive Summary Service NL (the Department) through its Occupational Health and Safety (OHS) Branch (the Branch) has a mandate to maintain
What the OHS Act says about the training responsibilities of constructors, employers, and supervisors
REQUIRED Pull-out chart TRAINING Construction Health and Safety in Ontario The Occupational Health and Safety Act (OHS Act) requires constructors and employers to provide worker training. Specific requirements
notes Video User s s Guide Accident Involving Radioactive Material
Emergency Response to a Transportation Accident Involving Radioactive Material DISCLAIMER Viewing this video and completing the enclosed printed study material do not by themselves provide sufficient skills
Information. on Workplace Health and Safety. Information. for Workers
Information on Workplace Health and Safety Information for Workers This guide is designed to provide basic information about workplace health and safety as required by the Occupational Health and Safety
Civil Engineering Sector Labour-Management Health and Safety Committee
PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION SITES Civil Engineering Sector Labour-Management Health and Safety Committee July 2008 PROCEDURE FOR THE STORAGE AND HANDLING OF FUEL ON CONSTRUCTION
Introduction to Fall Protection
Introduction to Fall Protection with John Evinger CRSP (204)228-8277 INSERT YOUR LOGO HERE Expected results of the day Today I will provide you with information to make you realize that you don t have
Fall Protection Rescue Plan. Presented by: Bruno Gagné
Fall Protection Rescue Plan Presented by: Bruno Gagné 1 Workshop Objectives By the end of this workshop, the participant will understand: 1. The importance of having a rescue plan 2. What happens to a
Directorate of Estates and Facilities Management. Health and Safety Policy for Working at Height. Code of Practice
Directorate of Estates and Facilities Management Health and Safety Policy for Working at Height Code of Practice Created December 2011 Revision date Revision number 1 1.0 Introduction 1.1 The Work at Height
Walking/Work Surfaces Fall Protection Program
Reviewed: 10-2006 Walking/Work Surfaces Fall Protection Program It is the responsibility of all supervisors and/or administrators to implement this safety program. Their responsibility includes yearly,
PLEASE NOTE. For more information concerning the history of these regulations, please see the Table of Regulations.
PLEASE NOTE This document, prepared by the Legislative Counsel Office, is an office consolidation of this regulation, current to June 9, 2012. It is intended for information and reference purposes only.
CODE OF PRACTICE FOR FALL PROTECTION/WORK AT HEIGHT
CODE OF PRACTICE FOR FALL PROTECTION/WORK AT HEIGHT Section: Date of Issue: November 29, 2007 Issued By: Environmental Health &Safety Part: Revision #: -- Revision Date: August 11, 2009 Pages: 63 Revised
Brief Analysis of Site Accident Cases
Brief Analysis of Site Accident Cases This publication is produced by the Occupational Safety and Health Branch of the Labour Department This edition February 2013 Brief Analysis of Site Accident Cases
Fall Protection Rescue
Page 1 of 8 I. INTRODUCTION This paper provides an overview of the present state-of-the art in fall protection rescue. Decades of experience in protecting workers exposed to fall hazards has resulted in
Walking and Working Surface Checklist:
Walking and Working Surfaces Purpose: This information is presented to improve the level of safety in our operations, and to inform you that we will comply with the OSHA Standard 29 CFR 1910.23. Responsibility:
Elkhorn Construction, Inc. Safety Manual Title: Fall Protection Policy Effective Date: 03-01-2000
1. General Requirements (OSHA References: OSHA 29 CFR 1926.503) 1.1 Elkhorn Construction, Inc. employee-owners and subcontractors are required to use fall protection equipment or systems when an assessment
Working at Height Rescue Plan Risk Assessment - Method Statement
Company Logo Company Name Working at Height Rescue Plan Risk Assessment - Method Statement Document...Revision... Site Address:.. Rescue Plan Ref. No:...... Location/area:. JOB TASK: Reference No.: Work
Activity Hazard Analysis (AHA)
Activity Hazard Analysis (AHA) Activity/Work Task: Scaffolding Erection Overall Risk Assessment Code (RAC) (Use highest code) Project ocation: 1010 W. Snow Blind Street, Ft. Nowhere, Alaska Contract Number:
FALL PROTECTION WORK PLAN
FALL PROTECTION WORK PLAN INSTRUCTIONS A written fall protection work plan must be implemented by each employer on a job site where a fall hazard of 10 feet or greater exists, in accordance with OSHA Standards.
Safety Manual For Overhead Crane Operators
Safety Manual For Overhead Crane Operators Contents Forward ---------------------------------------------------------------1 Qualifications---------------------------------------------------------1 Certification
Work at Height / Falling Objects
Introduction This information sheet gives employers and employees practical advice on work at height and falling objects and how to eliminate or reduce the risk of harm or damage occurring. It will assist
METHOD STATEMENT CRANE HIRE PROVIDING A CONTRACT LIFT SERVICE IN COMPLIANCE WITH BS7121 PARTS 1 & 3 AND LOLER REGULATIONS
METHOD STATEMENT CRANE HIRE PROVIDING A CONTRACT LIFT SERVICE IN COMPLIANCE WITH BS7121 PARTS 1 & 3 AND LOLER REGULATIONS CLIENT: Elliott Group CONTACT: Maurice Kennett SITE: Lympstone Church Ring School,
MATERIAL HANDLING PROGRAM (Section 10)
MATERIAL HANDLING PROGRAM (Section 10) OVERVIEW (WMI Facility) (1) Only certified personnel will operate powered industrial lifts. (2) Training will be provided to those who require to be certified or
SURVIVING THE FALL: The Proper Use Of Your Personal Fall Arrest System
SURVIVING THE FALL: The Proper Use Of Your Personal Fall Arrest System This easy-to-use Leader s Guide is provided to assist in conducting a successful presentation. Featured are: INTRODUCTION: A brief
OSHA 1910.66 Remove impacted systems and components. Inspect systems prior to use.
Q: When do I remove my harness from service? A: ANSI (American National Standards Institute) A10.32-2004 states the service life of fall protection equipment manufactured of synthetic fiber shall be 5
Working at Height. A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use.
A printed or saved copy is an UNCONTROLLED copy. Check that it is the latest available version before use. Title: Number: WORKING AT HEIGHT GM-11-031-02 Version Number: 22.0 Date Revised: 03 September
Safety and Environmental Information for External Companies Koehler Oberkirch
and al and at Work 1. Delivery, Notice, Signature After receiving the following information sheets, the team leader from every external company is required to read through them, explain them to their employees,
Contractor s Injury Management Toolbox RISK CONTROL
Contractor s Injury Management Toolbox managing job site accidents and injuries RISK CONTROL Your Role in Workplace Safety As a superintendent or foreman, you play an important role in helping our company