Storm Water Runoff from Natural Gas Well Sites in North Texas: Sampling, Modeling, and Management Options
|
|
|
- Clare Joanna Anderson
- 9 years ago
- Views:
Transcription
1 Storm Water Runoff from Natural Gas Well Sites in North Texas: Sampling, Modeling, and Management Options Kenneth E. Banks David J. Wachal City of Denton, Texas David Wachal is now with ESRI Professional Services Research demonstrated within this presentation was partially financed through grants from the U.S. Environmental Protection Agency US Natural Gas Development end of 2010 Texas through 2011: 100,966 I yr. increase of 5952, ~6.3% Source: The U.S. Energy Information Administration (EIA) Number of Producing Gas Wells Release date : 4/30/2012 1
2 Study Area Denton, Texas Population ~117,000 Denton City Limits ~160 sq km Denton ETJ ~207 sq km Rainfall averages 99 cm / yr In top 10 list of fastest growing cities in the nation 2
3 Cumulative disturbance area for wells drilled Study Area 3
4 Sediment 4
5 Heavy Metals Petroleum Hydrocarbons 5
6 Gas well concerns intensify in urban settings Concerns include air emissions, surface contamination, groundwater, noise and light pollution, safety, road damage, property values, effects on soil stability, etc.. NIMBY now includes NUMBY in the urban setting. Research Questions Is storm water runoff from natural gas well development sites impacted? If so, what impacts exist and to what extent? Can impacts be modeled? Can impacts be mitigated? Do impacts indicate runoff from these sites should be regulated? 6
7 Research Objectives 1. Characterize storm water runoff Sediment Petroleum Hydrocarbons Heavy Metals Water Chemistry 2. Evaluate modeling approaches 3. Develop model parameters using rainfall simulation 4. Evaluate Best Management Practices (BMPs) (modeling-economics) Study Design and Data Collection 7
8 Natural Gas Well Site Monitoring Point Pad Site Cut Slope Runoff Intake Pressure Transducer 8
9 9
10 10
11 Discretion is the better part of valor, Act 1 Valor > discretion Discretion is the better part of valor, Act 2 Discretion > Valor 11
12 Sampled Events n=17 n= Site 2 Rainfall (mm) n=11 n=5 n=5 Site 3 Site 4 Site 2R 40 Site 3R mm = 1 inch Parameters Analyzed Water Chemistry Metals Petroleum Hydrocarbons Sediment Alkalinity Arsenic TPH TSS Calcium Cadmium BTEX Turbidity Chlorides Chromium Conductivity Copper Hardness Iron ph Lead TDS Manganese Nickel Zinc 12
13 Wilcoxon Rank-Sum and Ratio of Medians (Provided for those with an adequate number of samples above detection) Parameter n/n p-value Ratio Alkalinity 40/10 < Chlorides 40/ Conductivity 40/10 < Hardness 40/10 < ph 40/10 < TDS 40/ Calcium 36/8 < TSS 39/8 < Turbidity 37/9 < Iron 36/8 < Manganese 36/8 < Nickel 36/ Metals Previous Research Hudak and Banks (2006) Urban Watersheds Gas Well Site Metals Reference Site Metals Kayhanian et al. (2001) Highway Construction Sites Gas Well Site Metals Reference Site Metals = 13
14 Wilcoxon Rank-Sum and Ratio of Medians Parameter n/n p-value Ratio Alkalinity 40/10 < Chlorides 40/ Conductivity 40/10 < Hardness 40/10 < ph 40/10 < TDS 40/ Calcium 36/8 < TSS 39/8 < Turbidity 37/9 < Iron 36/8 < Manganese 36/8 < Nickel 36/ Sediments and Petroleum Hydrocarbons Sediment yields at gas well sites in this study ranged from 29 to 41 t/ha/yr TPH was below detection limits for all samples BTEX was detected in a few gas well sample but EMCs were below the detection limit BTEX was detected in all samples at reference site 2R TPH / BTEX did not exceed State WQ Standards 14
15 How much is 41 tonnes?? = 2.24 loads Sediment Concentration (mg/l) Wolman and Schick (1967) Daniel et al. (1979) Madison et al. (1979) Schueler and Lugbill (1990) Nelson (1996) USGS (2000) Kayhanian et al. (2001) EMC Range COD - Hickory Creek Reference Sites Gas Well Sites , ,000 15
16 City Of Denton Quarterly Sampling Summary Petroleum Hydrocarbons were not prevalent in storm water runoff at gas well sites Metals at gas well sites were: higher than at reference sites higher than local urban storm water similar to highway construction sites Total Suspended Sediment at gas well sites were: 157 times higher than at reference sites 36 times higher than at the outlet of the Hickory Creek Watershed Similar to other types of construction sites 16
17 Evaluation of Runoff and Sediment Yield Predictions Evaluate WEPP predictions of runoff and sediment Why monitoring data is limited can be used to develop what if scenarios provide defendable information for local decision making Allowed modeling of cut and fill slopes as a system Steps in Model Calibration Set parameters (management conditions; soil conditions, etc.) Input slope information Input climate information Run the model Compare observed and predicted values Error = Observed minus Predicted Evaluate error results using goodness-of-fit indicators Adjust parameters and rerun the model 17
18 Performance Ratings (Moriasi et al., 2007) NSE = Nash Sutcliffe efficiency (NSE) RSR = ratio of RMSE(root mean square errors) to standard deviation Percent bias (PBIAS) = describes the average tendency of simulated data to be larger or smaller than their observed counterparts. NSE ranges between negative infinity and 1.0, with NSE = 1 being the optimal value. RSR varies from an optimal value of 0 (which indicates zero RMSE) to a large positive value. The better the model simulation performs, the lower the RMSE, and therefore the lower the RSR score. Model Validation (17 events) NSE = Very Good RSR = Very Good PBIAS = Good/Very Good NSE =.90 RSR =.28 PBIAS =15 NSE =.86 RSR =.38 PBIAS =-11 NSE =.99 RSR =.12 PBIAS =-2 NSE =.86 RSR =.38 PBIAS =16 18
19 Summary The results demonstrate that WEPP can effectively model runoff and sediment from natural gas well sites Therefore, the model can be used to Evaluate potential sediment impacts Evaluate management alternatives to minimize impacts Work suggested future rainfall simulation study to better parameterize the pad portion of the site. From a storm water perspective, the pad is quite complex. Rainfall Simulation Study Design Dry Run - 58 mm/hr on existing soil conditions Wet Run - 58 mm/hr, applied 24 hours after dry run Very Wet Run - 58 mm/hr increased to 104 mm/hr decreased to 58 mm/hr Applied 30 minutes after wet run 19
20 20
21 Data Collection Modeling Used WEPP to model runoff and sediment from plot area for each plot and each run type (18 runs) Input calculated K i values (interrill erodibility (mass-time/length 4 )) Adjusted K ef (effective conductivity) until predicted runoff equaled observed runoff NSE =.90 = very good RSR =.30 = very good PBIAS = 13.7 = very good 21
22 Modeling Continued WEPP was run in continuous simulation mode (30-years) Predicted annual average sediment yields for pad sites (t/ha/yr) Ranged from 5.0 to 11.0 Average of 7.4 Results Interrill Erodibility (K i ) parameter for gas well pad sites = mean of 681,699 kg s/m 4 Hydraulic Conductivity (K ef ) parameter = mean of 30 mm/hr Sediment yield from the pad portion of a gas well site ranges from 5.0 to 11.0 t/ha/yr 22
23 Modeling Erosion and Sediment Control BMPs Evaluate the effectiveness of six BMPs specifically for natural gas well sites Demonstrate a practical approach for quantitatively evaluating BMP alternatives based on Soil type Slope condition Site management goals Implementation cost Methodology For each slope and soil combination sediment yields were modeled with and without BMPs BMP Efficiencies were calculated accordingly: ER = (SY without BMP SY withbmp )/ SY without BMP ER = (50 tons 10 tons) / 50 tons = 80% efficiency Mulching Filter Strip Silt Fence 23
24 Percent Slope Modeled Site Slopes % Slope 2.9% Slope 1.8% Slope Each slope was simplified to 9 slope segment for modeling
25 Methodology For each slope and soil combination sediment yields were modeled with and without BMPs BMP Efficiencies were calculated accordingly: ER = (SY without BMP SY withbmp )/ SY without BMP ER = (50 tons 10 tons) / 50 tons = 80% efficiency Results Sediment Yield without BMPs (tonnes/ha/yr) 1.8% slope 2.9% slope 4.5% slope K-factor 0.17 Sandy Loam K-factor 0.32 Clay Loam K-factor 0.43 Silty Clay Loam
26 BMP Cost / Efficiency Example (Moderate Slope/Moderate Erodibility) BMP Site Cost Site Management Goal $9,000 $8,000 $7,000 $6,000 $5,000 $4,000 $3,000 $2,000 $1,000 $0 Seeding Mulching Erosion Blanket BMP Site Cost Effeciency Efficiency Silt Fence Filter Strip Sediment Basin Site Management Goal measure of the acceptable level of reduced sediment yield through erosion prevention and sediment removal ER Findings With BMPs, sediment yields can be reduced by 50 to over 90 percent according to model results Soils and slope both influence BMP efficiency Methodology can be used to assist in the selection of BMPs according to various site factors and BMP site costs. Note: The Reasonable and Prudent Practices for Stabilization (RAPPS) of Oil and Gas Construction Sites document used portions of this research to establish decision trees of management practices based on slope, rainfallrunoff erosivity factor (R), and soil characteristics 26
27 Conclusions Sediment yields at gas well sites in this study ranged from 29 to 41 t/ha/yr Metal concentrations were higher at gas well sites compared to reference sites and local urban watersheds WEPP was able to effectively model runoff and sediment yield from gas well sites Parameters were specifically developed for gas well pad sites modeled average sediment yields from the pad site were 7.4 t/ha/yr over 30 year period Best Management Practices could reduce sediment yields by 50 to 90% for entire site Recommendations Municipal / state governments should consider implementing erosion and sediment control provisions for natural gas development Types of erosion and sediment controls should be selected according to site-specific conditions. Selections can be refined by considering costs and efficiencies of BMPs Future research should focus on additional rainfall simulation studies and gas well site BMPs slope K factor Management options 27
28 Additional information Wachal, D.J. and K.E. Banks and D.H. Hunter Collecting Stormwater at Small Gas Well Exploration and Production Sites. Published in the Watershed and Wet Weather Technical Bulletin 11(6):10-15 Banks, K.E and D.J. Wachal "Water Quality and Land Use: Analyzing relationships among multiple watersheds using contingency analysis". Stormwater: January / February Wachal, D.J. and K.E. Banks Application of WEPP to Natural Gas Exploration and Production Sites. Published in Proceedings of the American Society of Agricultural and Biological Engineers (ASABE): Fourth Conference on Watershed Management to Meet Water Quality and TMDL Issues: Solutions and Impediments to Watershed Management and TMDLS. March Wachal, D.J. and K.E. Banks Sediment Impacts from Natural Gas Exploration and Production Sites. Published in the proceedings of 2007 Annual International Meeting of the American Society of Agricultural and Biological Engineers (ASABE). June 17-20, 2007, Minneapolis, Minnesota. Wachal, D.J. and K.E. Banks Integrating GIS and Erosion Modeling: A Tool for Watershed Management. Published in the proceedings of the Twenty-Seventh Annual ESRI International User Conference June 18-22, 2007, San Diego, California. Williams, H.F.L., D.L.Havens, K.E. Banks, and D.J. Wachal Field-Based Monitoring of Sediment Runoff from Natural Gas Well Sites in Denton County, Texas, USA. Environmental Geology DOI /s Wachal, D.J., R.D. Harmel, K.E. Banks and P.F. Hudak Evaluation of WEPP for Runoff and Sediment Yield Prediction on Natural Gas Well Sites. Transactions of ASABE 51(6): Wachal, D.J., K.E. Banks, P.F. Hudak and R.D. Harmel. Modeling Erosion and Sediment Control Practices with RUSLE 2.0: A Management Approach for Natural Gas Well Sites in Denton County, Texas, USA. Environmental Geology. DOI /s Havens, D.L Assessment of Sediment Runoff from Natural Gas Well Development Sites. Masters Thesis, University of North Texas, Denton, Texas. More information about WEPP can be found at (USDA Agricultural Research Service) Contact Information Kenneth Banks, Ph.D. City of Denton Phone: (940) [email protected] 28
TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN
1. GENERAL TERMS OF REFERENCE FOR THE RAPID EIA STUDY FOR SHIVKAR LIGNITE BLOCK, DIST. BARMER, RAJASTHAN The main objective of the EIA study is to assess the positive and negative impacts likely to accrue
Impact of utilised bottom ash
Impact of utilised bottom ash Raul Grönholm, MSc, Sysav Jan Hartlén, PhD, JH Geoconsulting 24 januari 2012 1 Agenda SYSAV BOTTOM ASH FROM WASTE INCINERATION USE OF BOTTOM ASH MONITORING AND ESTIMATION
STATEMENT OF ACKNOWLEDGMENT
General Permit for the Discharge of Stormwater and Dewatering Wastewaters from Construction Activities, issued 8/21/13, effective 10/1/13 Stormwater Monitoring Report SITE INFORMATION Permittee: BNE Energy
CONSTRUCTION GENERAL PERMIT RISK ASSESSMENT R-FACTOR CALCULATION NOTIFICATION
CONSTRUCTION GENERAL PERMIT RISK ASSESSMENT R-FACTOR CALCULATION NOTIFICATION NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) GENERAL PERMIT FOR STORM WATER DISCHARGES ASSOCIATED WITH CONSTRUCTION
Field Performance of Two Stormwater Bioretention Filtration Design Configurations
Field Performance of Two Stormwater Bioretention Filtration Design Configurations Andrew Anderson, E.I.T. North Carolina State University Department of Biological & Agricultural Engineering 2013 Annual
Innovative Removal of Agricultural Related Water Pollutants in the Chesapeake Bay Watershed
Innovative Removal of Agricultural Related Water Pollutants in the Chesapeake Bay Watershed William E. Roper, Kelly P. Rock, and Howard E. Sorber III Micronic Technologies, Wise, VA National Capital Regional
Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides
Compost-Based Stormwater Best Management Practices Using Compost to Improve Stormwater Management and Erosion Control On Roadsides Chris Newman US EPA Region 5 Chicago, IL Compost-Based BMPs Compost-based
URBAN STORMWATER GUIDELINES AND BEST MANAGEMENT PRACTICES FOR PROTECTION OF FISH AND FISH HABITAT DRAFT DISCUSSION DOCUMENT
URBAN STORMWATER GUIDELINES AND BEST MANAGEMENT PRACTICES FOR PROTECTION OF FISH AND FISH HABITAT DRAFT DISCUSSION DOCUMENT Contacts: Barry Chilibeck (666-3765) or Megan Sterling (666-2322) Revision 4
TARP Section 2.2 Stormwater BMP Screening for Validation
Requirements for Final Certification of Manufactured Treatment Devices for Total Suspended Solids Removal Based on Field Testing Amendments to TARP Protocol DRAFT April 28, 2009 The New Jersey Stormwater
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS
DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection
ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND
ROSE CREEK WATERSHED HYDROLOGIC, HYDRAULIC, SEDIMENT TRANSPORT, AND GEOMORPHIC ANALYSES TASK 1 EXISTING DATA AND INFORMATION SUMMARY REPORT BACKGROUND The Rose Creek Watershed (RCW) consists of three planning
Improper storage of potential pollutants will increase the risk of water pollution that may occur because of spills.
WQ-3 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design and Operation Standards Section 1. Introduction According to the EPA, the majority of water pollution
Life After Getting a BS and MS Degree Working as a Professional in PA
Life After Getting a BS and MS Degree Working as a Professional in PA Presented by: Mr. Brian Oram, PASEO Soil Scientist Professional Geologist B.F. Environmental Consultants Inc. 15 Hillcrest Drive Dallas,
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements
City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting
A San Antonio Case Study on the Water Quantity and Quality Benefits of LID Development
A San Antonio Case Study on the Water Quantity and Quality Benefits of LID Development Chad Richards PE, CFM, CPSWQ Brett Sachtleben PE, CFM Agenda Purpose Water Quality Processes LID Components and their
Low Impact Development
Low Impact Development for Linear Transportation Projects Disclaimer This project was developed through an Assistance Agreement under the U.S. EPA Office of Water 104 b(3) Program. It is intended for use
WEPP MODEL APPLICATIONS FOR EVALUATIONS OF BEST MANAGEMENT PRACTICES
WEPP MODEL APPLICATIONS FOR EVALUATIONS OF BEST MANAGEMENT PRACTICES D.C. FLANAGAN 1, W.J. ELLIOT 2, J.R. FRANKENBERGER 3, C. HUANG 4 1 USDA-Agricultural Research Service, National Soil Erosion Research
Lessons Learned from the Expert BMP Panel Process That May Apply to MTDs. Tom Schueler Chesapeake Stormwater Network
Lessons Learned from the Expert BMP Panel Process That May Apply to MTDs Tom Schueler Chesapeake Stormwater Network Recent Expert Panels 1. Stormwater Retrofit Practices 2. New State Performance Standards
BHARAT PETROLEUM CORPORATION LIMITED
TERMS OF REFERENCE (TOR) FOR CARRYING OUT ENVIRONMENT IMPACT ASSESSMENT (EIA) FOR BPCL- KOCHI REFINERY MS BLOCK PROJECT AT KOCHI, KERALA PROPONENT: BHARAT PETROLEUM CORPORATION LIMITED 1.0 INTRODUCTION
BMP 6.7.3: Soil Amendment & Restoration
BMP 6.7.3: Soil Amendment & Restoration Soil amendment and restoration is the process of improving disturbed soils and low organic soils by restoring soil porosity and/or adding a soil amendment, such
The International Stormwater BMP Database Part 1: Summary of Database
Land Development Brief: February 2013 The Pennsylvania Housing Research Center The International Stormwater BMP Database Part 1: Summary of Database Katherine L. Blansett, Ph.D., P.E. INTRODUCTION This
Pervious Pavers: Where is the Perviousness?
Pervious Pavers: Where is the Perviousness? Elizabeth (Betsy) Pappas Research Hydraulic Engineer Chi-hua Huang Soil Scientist United States Department of Agriculture Agricultural Research Service National
1.7.0 Floodplain Modification Criteria
1.7.0 Floodplain Modification Criteria 1.7.1 Introduction These guidelines set out standards for evaluating and processing proposed modifications of the 100- year floodplain with the following objectives:
Universal Soil Erosion Equation
Author: Laura Swantek Time: 50 minute class period Grade Level: 9-12 Background: Soil is created by the weathering of rock and the decomposition of organic materials. Soils are classified according to
MBJ Environmental Programmes
MBJ Airports Limited Environmental Policy The following is MBJ Airports Limited s (MBJ) Environmental Policy for Sangster International Airport (SIA): Integrate environmental management measures with planning,
Construction Site Inspection. Inspecting to Keep You in Compliance
Construction Site Inspection Inspecting to Keep You in Compliance Inspection/Monitoring/Reporting Know if your plan is working Document corrective actions Ketchikan A Contractor that destroys their site
Sewerage Management System for Reduction of River Pollution
Sewerage Management System for Reduction of River Pollution Peter Hartwig Germany Content page: 1 Introduction 1 2 Total emissions 3 3 Discharge from the wastewater treatment plants 4 4 Discharge from
Total Suspended Solids: The Hows & Whys of Controlling Runoff Pollution
New State Storm Water Rules: WHAT MUNICIPALITIES NEED TO KNOW Total Suspended Solids: The Hows & Whys of Controlling Runoff Pollution Stormwater management by Wisconsin municipalities is under scrutiny.
Improper storage of fuel on construction sites will increase the risk of water pollution that may occur as a result of leaks or spills.
WQ-10 Best Management Practice (BMP) Water Quality Protection Guideline Secondary Containment Design Standards Fuel Storage on Construction Sites According to the EPA, the majority of water pollution in
Watershed-Wide Modeling for TMDL/MS4 Permit Compliance. Greg Wilson, Barr Engineering
Watershed-Wide Modeling for TMDL/MS4 Permit Compliance Greg Wilson, Barr Engineering Acknowledge City of Golden Valley Eric Eckman Heather Hegi Laura Jester and BCWMC Technical Advisory Committee members
BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT
Harmony Creek subwatershed Harmony Creek subwatershed BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT April 2011 TABLE OF CONTENTS 1.0 INTRODUCTION...
4. Environmental Impacts Assessment and Remediation Targets
4. Environmental Impacts Assessment and Remediation Targets 4.1 Environmental Impacts Significant additional development in the Alder Creek watershed is not anticipated at this time; however, there are
Ginger Paige and Nancy Mesner University of Wyoming Utah State University
Effective Water Quality BMP Monitoring Tools Ginger Paige and Nancy Mesner University of Wyoming Utah State University Overview BMP Monitoring Guidance Document for Stream Systems Lessons learned CEAP
stormwater BMP Total Cost Analysis
Cost and Pollutant Removal of Storm-Water Treatment Practices Peter T. Weiss, M.ASCE 1 ; John S. Gulliver, F.ASCE 2 ; and Andrew J. Erickson, S.M.ASCE 3 Abstract: Six storm-water best management practices
Rational Method Hydrologic Calculations with Excel. Rational Method Hydrologic Calculations with Excel, Course #508. Presented by:
Rational Method Hydrologic Calculations with Excel, Course #508 Presented by: PDH Enterprises, LLC PO Box 942 Morrisville, NC 27560 www.pdhsite.com Calculation of peak storm water runoff rate from a drainage
Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans
Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans OVERVIEW The objective of a Combined Sewer Overflow (CSO) Facility Plan is to abate CSO discharges
SE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
PRIVATE TREATMENT CONTROL BMP OPERATION AND MAINTENANCE VERIFICATION FORM BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS
BIORETENTION FACILITIES, VEGETATED SWALES & HIGHER RATE BIOFILTERS Check here for Address or phone number change the fiscal year (July 1 June 30), and date(s) maintenance was performed. Under Inspection,
WHISKY CREEK DEMONSTRATION PROJECT
WHISKY CREEK DEMONSTRATION PROJECT OCC Tasks 16 and 17 FY 1990 319(h) Sub-Task 200(A) EPA Grant # C9-006704-90-0 Submitted by: Oklahoma Conservation Commission Water Quality Division 413 NW 12 th Oklahoma
Retention/Irrigation. Design Considerations. Soil for Infiltration Area Required Slope Environmental Side-effects
Description Retention/irrigation refers to the capture of stormwater runoff in a holding pond and subsequent use of the captured volume for irrigation of landscape of natural pervious areas. This technology
Active Treatment Systems
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
A water quality monitoring network for environmental management of port areas An example from the Port of Venice
A water quality monitoring network for environmental management of port areas An example from the Port of Venice Nicola Torricella ([email protected]), Marta Citron ([email protected])
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.
BMP: SUBSURFACE DRAIN Definition A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. PurRoses 1. To prevent sloping soils from becoming
Final Report of the Town Owned Lands Improvement Project for the Town of Brentwood, NH
Final Report of the Town Owned Lands Improvement Project for the Town of Brentwood, NH Project Background In November of 2013 the Green Infrastructure for Sustainable Coastal Communities (GISCC) project
Agua Hedionda Creek Flood Plain Information; Department of Army, Los Angeles District,
Bibliography Agua Hedionda Creek Flood Plain Information; Department of Army, Los Angeles District, California and Maps. US Army Corps of Engineers July 1973 pg. 24 Aqua Hedionda Lagoon Foundation Framework
Chapter 2 Treatment Facility Menus
Chapter 2 Treatment Facility Menus This chapter identifies the treatment facility menus. The menus in this chapter are as follows: Oil Control Menu, Section 2.1 Phosphorus Treatment Menu, Section 2.2 Enhanced
Costs for Green Infrastructure and Stormwater Retention Practices
Costs for Green Infrastructure and Stormwater Retention Practices Bob Newport U.S. EPA December 9, 2014 Topics to be Covered EPA data collection and cost analysis focused on postconstruction stormwater
Waste Handling & Disposal
Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Improper storage and handling of solid wastes can allow toxic compounds, oils and greases, heavy metals, nutrients, suspended
A Developer s Guide: Watershed-Wise Development
A Developer s Guide: Watershed-Wise Development Environmental Protection What is a watershed? It does not matter how far away you build from a creek, lake, or the ocean, you are in a watershed. Another
IMPROVING SOUTH FORK PEACHTREE CREEK WATERSHED USING THE TRIPLE BOTTOM LINE DEKALB COUNTY, GEORGIA
IMPROVING SOUTH FORK PEACHTREE CREEK WATERSHED USING THE TRIPLE BOTTOM LINE DEKALB COUNTY, GEORGIA David Chastant AUTHORS:DeKalb County, 330 West Ponce De Leon Ave, Decatur, Georgia 30030 REFERENCE:Proceedings
Storm Water Runoff. Managing. A Self-Assessment Guide for Wisconsin Businesses. Storm water runoff is coming. This guide provides businesses
Managing Storm Water Runoff A Self-Assessment Guide for Wisconsin Businesses Storm water runoff is coming under increasing scrutiny as both a source of pollutants to our lakes and streams, and as a cause
LOW INTEREST LOANS FOR AGRICULTURAL CONSERVATION
LOW INTEREST LOANS FOR AGRICULTURAL CONSERVATION LILAC MANUAL LOW INTEREST LOANS FOR AGRICULTURAL CONSERVATION TABLE OF CONTENTS Introduction... 3 General Eligibility... 4 Specific Eligibility Criteria
Greater Los Angeles County Region
Attachment 6 Greater Los Angeles County Region IRWM Implementation Grant Proposal Monitoring, Assessment, and Attachment 6 consists of the following items: Monitoring, Assessment, and. The purpose of this
Appendix I: BMP Inspection Form CASQA SWPPP Template 91 January2011 BMP INSPECTION REPORT Date and Time of Inspection: Date Report Written: Inspection Type: (Circle one) Weekly Complete Parts I,II,III
Spill Prevention, Control & Cleanup SC-11
Objectives Cover Contain Educate Reduce/Minimize Product Substitution Description Spills and leaks, if not properly controlled, can adversely impact the storm drain system and receiving waters. Due to
D R A F T. Best Management Practices Plan (Surface Water, Sediment & Erosion Control) West Carleton Environmental Centre. May 2014
Best Management Practices Plan (Surface Water, Sediment & Erosion Control) West Carleton Environmental Centre D R A F T Prepared for: Waste Management of Canada Corporation 2301 Carp Road Ottawa, Ontario
STORMWATER MONITORING: POLLUTANTS, SOURCES, AND SOLUTIONS
RICHLAND COUNTY STORMWATER MANAGEMENT DIVISION STORMWATER MONITORING: POLLUTANTS, SOURCES, AND SOLUTIONS As part of the federal government s National Pollutant Discharge Elimination System Permit (NPDES)
Part B Integrated Monitoring Design for Comprehensive Assessment and Identification of Impaired Waters Contents
Part B Integrated Monitoring Design for Comprehensive Assessment and Identification of Impaired Waters Contents Chapter 10. Selecting Metrics or Indicators of WQS Attainment... 10-2 Chapter 11. Monitoring
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE
CONSTRUCTION STORMWATER POLLUTION PREVENTION PLAN TEMPLATE The following template may be used as a general guide for development of a Stormwater Pollution Prevention Plan (SWPPP) for construction activities.
TCEQ TPDES CGP EPA NPDES GCP Inspection of Controls Report
TCEQ TPDES CGP EPA NPDES GCP Inspection of Controls Report Complete this form every seven days and after every rain event of 0.5" or greater and retain in your SWP3. General Information Name of Project:
City of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
Burnsville Stormwater Retrofit Study
Burnsville Stormwater Retrofit Study Prepared for City of Burnsville June 2006 4700 West 77 th Street Minneapolis, MN 55435-4803 Phone: (952) 832-2600 Fax: (952) 832-2601 Burnsville Stormwater Retrofit
SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION
SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 104-1 Description. Provide erosion control measures on the project and in areas outside the right-of-way where work is accomplished
Estimating Potential Reduction Flood Benefits of Restored Wetlands
Estimating Potential Reduction Flood Benefits of Restored Wetlands Kenneth W. Potter University of Wisconsin Introduction Throughout the summer of 1993 a recurring question was the impact of wetland drainage
NC STATE UNIVERSITY PERMEABLE PAVEMENT RESEARCH AND CHANGES TO THE STATE OF NC RUNOFF CREDIT SYSTEM
NC STATE UNIVERSITY PERMEABLE PAVEMENT RESEARCH AND CHANGES TO THE STATE OF NC RUNOFF CREDIT SYSTEM William F. Hunt, III and Eban Z. Bean William F. Hunt, Biological and Agricultural Engineering, NC State
Use of Green Roofs to Meet New Development Runoff Requirements. Greg Davis Nov. 8, 2007
Use of Green Roofs to Meet New Development Runoff Requirements Greg Davis Nov. 8, 2007 Why green roof? Absorption of precipitation Increased insulation Reduced urban heat island effect Pollutant removal
Good? Bad? Why? http://uncultured.com/2007/09/20/notre-dame-and-watering-sidewalks/ Training Module 4
Good? Bad? Why? http://uncultured.com/2007/09/20/notre-dame-and-watering-sidewalks/ Solution Sprinklers should be directed at lawn areas Spraying water on pavement increases runoff Look for more water-efficient
Swamp Area Passive Treatment System Kettle Creek Watershed, Clinton County, PA
Swamp AMD Chemistry Swamp Area Passive Treatment System Kettle Creek Watershed, Clinton County, PA A Technical Report for Trout Unlimited and the Kettle Creek Watershed Association Prepared by Hedin Environmental
Land Application of Drilling Fluids: Landowner Considerations
SCS-2009-08 Land Application of Drilling Fluids: Landowner Considerations Mark L. McFarland, Professor and Extension State Water Quality Specialist Sam E. Feagley, Professor and Extension State Environmental
Stormwater Management in Chicago waterways :Basement Flooding and its prevention Kyungmin Kim
Stormwater Management in Chicago waterways :Basement Flooding and its prevention Kyungmin Kim CE 394K GIS in Water Resources - David R. Maidment. Dec 4th 2015 Motivation and Objective Recently, Chicago
National Pollutant Removal Performance Database
National Pollutant Removal Performance Database Version 3 September, 2007 8390 Main Street, 2 nd Floor Ellicott City, MD 21043 410.461.8323 FAX 410.461.8324 www.cwp.org www.stormwatercenter.net The National
Scheduling Maintenance for Infiltration Basins and Trenches
Visual Inspection for Infiltration Practices Visual inspection is a rapid assessment procedure for qualitatively evaluating the functionality of a stormwater best management practice (BMP). Visual inspections
Activity Yes No N/A Notes
CE 2020 (Rev. 12/11) Page 1 of 5 PROJECT NAME AND SITE ADDRESS: CONTRACT NUMBER: ORACLE NUMBER: WDID NUMBER: CONTRACTOR NAME AND ADDRESS: PROJECT SITE RISK LEVEL: Risk Level 1 Risk Level 2 Risk Level 3
BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION
COLORADO DEPARTMENT OF TRANSPORTATION STORMWATER FIELD INSPECTION REPORT - ACTIVE CONSTRUCTION (1) Project Name: (2) Project Contractor: (3) Erosion Control Supervisor/SWMP Administrator: (4) CDOT Project
Beseck Switching Station Inspection
Page 1 of 5 Docket No. 272 Development and Management Plan Inspection The Connecticut Light and Power Company Certificate of Environmental Compatibility and Public Need for the construction of a new 345-kV
NAPA COUNTY WATERSHED SYMPOSIUM
Planning, Building, and Environmental Services NAPA VALLEY GROWTH NAPA COUNTY WATERSHED SYMPOSIUM Plunging Forward May 15, 2015 1 YOU CAN T CROSS THE SEA MERELY BY STANDING AND STARING AT THE WATER. Rabindranath
Virginia Street Tree Box Filters Demonstration Project
Virginia Street Tree Box Filters Demonstration Project HARVESTING WATER IN THE LANDSCAPE: IMPLEMENTING LOW IMPACT DEVELOPMENT November 16, 2007 Chris Conway, CPSWQ, Kennedy/Jenks Consultants E. Terri Svetich,
Green Streets, Places, and Spaces
Thursday October 23, 2014 Green Streets, Places, and Spaces Green Streets reduce stormwater runoff and improve a street s ecological performance. Often, strategies for sustainable stormwater management
Understanding Erosion. Revised Universal Soil Loss Equation
Understanding Erosion with the Revised Universal Soil Loss Equation Towards a Better Understanding of the What, Why & How Erosion is a process of detachment and transport of soil particles by erosive forces.
Web-based GIS Application of the WEPP Model
Web-based GIS Application of the WEPP Model Dennis C. Flanagan Research Agricultural Engineer USDA - Agricultural Research Service National Soil Erosion Research Laboratory West Lafayette, Indiana, USA