1 July 2015 Oklahoma Capitol Restoration Project Interior Rehabilitation Monthly Progress Report
2 TABLE OF CONTENTS Design-Builder Progress Summary... TAB 1 Design Progress Summary... TAB 2 Project Schedule... TAB 3
3 1. Design-Builder Progress Summary 1 P a g e
4 WORK IN PROGRESS & NOTABLES Best Practices of Capitol Management In mid-july, several members of the Interior Rehabilitation Team met with the Architect of the U.S. Capitol (AOC), Mr. Stephen T. Ayers, FAIA, Leed AP. Manhattan Construction Company also constructed the U.S. Capitol Visitor Center Project in Washington, D.C. This experience and expertise has provided a valuable opportunity to further study best practices of Capitol management beyond the restoration process. Mr. Ayers answered specific questions regarding Management and Oversight, Budget and Finance, Maintenance and Improvement Projects, as well as Communications revolving around the U.S. Capitol operations. Mr. Ayers is the 11th Architect of the Capitol and has served since May 12, Mr. Ayers is responsible for the facilities maintenance and operation of the historic U.S. Capitol Building, the care and improvement of more than 553 acres of grounds and the operation and maintenance of 17.4 million square feet of buildings including: the House and Senate Congressional Office Buildings, the Capitol Visitor Center, the Library of Congress Buildings, the U.S. Supreme Court Building, the Thurgood Marshall Federal Judiciary Building and other facilities. He is responsible for the care of all works of art in the Capitol under the direction of the Joint Committee on the Library and is responsible for the maintenance and restoration of murals, outdoor sculpture and other architectural elements throughout the Capitol complex. He also serves as Acting Director of the U.S. Botanic Garden and the National Garden. The Architect of the Capitol has approximately 2,300 employees and an annual budget of nearly $600 million. 2 P a g e
5 Images below: Members of the Interior Rehabilitation Team meeting with Mr. Stephen T. Ayers, FAIA, Leed AP, Architect of the Capitol in the U.S.Capitol on July 16, P a g e
6 Working Sessions One of the most important aspects of the design process is the sharing and development of ideas. Seldom does a first draft of anything see the light of day without planning and revision. To that extent, the Interior Rehabilitation Team has been participating in a process of working sessions aimed to provide a consistent approach throughout the schematic development process. These working sessions have thus far concentrated on: i. Defining priorities associated with the Scope of Work Priority Matrix within the construction cost limitations associated with the project. ii. Historic Preservation Zones and defining specifications and terminology associated with Preservation, Restoration, Rehabilitation and Adaptive Reuse. iii. Preliminary Master Plans for Mechanical, Electrical, Plumbing and Fire Protection Systems to be implemented through the Interior Rehabilitation Project. iv. Programming efforts required to adhere to the Oversight Committee s goal to improve historic aesthetics and establish a master place for efficient use of space. Image below: Members of the Interior Rehabilitation Team in a Working Session reviewing the Preliminary Master Plan for MEP & FP Systems on July 21, P a g e
7 Image below: Members of the Interior Rehabilitation Team in a Working Session reviewing the Historic Preservation Zones and Methodology on July 21, Risk Assessment & Management Plan The ability to define risks associated with a project is often a living document developed over the course of a project. It is only fully understood once all project stakeholders acknowledge the multitude of risks associated with a design-build project of this caliber. The entire project team has expended exhaustive efforts towards risk identification which is crucial to the overall project success strategy. Defining risks with a desired outcome to mitigate said risks is paramount. Risk management and mitigation plans are being analyzed by the entire project team for adoption within the project. 5 P a g e
8 Priority Matrix We are actively working with the Owner Project Team to refine and evaluate the Scope of Work Priority Matrix. This process is providing clarification of the scope of work that can be included within the existing funding parameters ($91.6MM). This is a process of identifying priorities in relation to project goals and criteria adopted by the State Capitol Repair Expenditure Oversight Committee (SCREOC). The scope of work being evaluated includes building repairs, restoration, betterments and functional enhancements. Coordination: Oklahoma State Fire Marshal s Office - Our team is engaged with coordinating initial plans for the Interior Rehabilitation with the Oklahoma State Fire Marshal s Office (OSFM). Future improvements will upgrade Life Safety Systems within the historic structure. We are extremely appreciative of the efforts and involvement from the OSFM to facilitate a project of this caliber. Photo below: Our team is shown meeting with Mr. Luke Tallant with the Oklahoma State Fire Marshal s Office to review initial analysis and implementation of Life Safety Systems and code requirements for the Oklahoma Capitol Restoration on July 14, P a g e
9 Design Assist Strategy Collaboration and planning lead to a successful design-build strategy. Major renovations, such as the Oklahoma Capitol Restoration, can be complex in design and scope development, therefore presenting the challenge of maintaining a fully operational facility during construction. We have a proven recipe for success from delivering multiple projects in and around The State Capitol. Our experience has produced not only a team of Oklahoma s very best, but a world class team to undertake this project. We have partnered with the highest quality team of Oklahoma-based talent in the country to ensure cost control measures are in place and actively maintained as well as expediting resources and procurement opportunities. Photo below: MEP & FP master planning sessions with our design-assist partners shown in progress. 7 P a g e
10 LOOKING AHEAD Milestones & Deliverables Schematic development efforts are rapidly being completed as plans are being expedited to start Phase 1 Prerequisites for the Interior Restoration. Phase 1 will start the Single-Move Strategy by creating space to vacate portions of the basement slated for Phase 2 Renovations. In addition, Phase 1 allows for intrusive investigations to begin exposing concealed conditions so that we can identify hazardous materials. In addition, Phase 1 spaces serve as a laboratory for historic preservation analysis. Our historic preservation consultants are analyzing original paint colors, finishes, performing testing required to restore original marble floors, and taking core samples to properly identify original flooring materials. 8 P a g e
11 2. Design Progress Summary 9 P a g e
12 Monthly Project Status Report Frankfurt Short Bruza Architects Engineers Planners Date: July 30, 2015 Project: 15151DB Capitol Interior Restoration To: From: Name Company/Position Phone Kyle Nelson Manhattan Construction Co Steve Scovel, Architect / Project Manager Re: Monthly Project Status Report July 2015 This project status report is being provided to you to in order to document our current status on the subject project as required by OMES. The following is a summary of our contracted work broken down by project SOW and Status: BIM MODEL FSB has continued to update the model to incorporate refined assessment information. The BIM model will include the existing architectural, mechanical, electrical and fire protection systems in the Capitol as observed in the room-by-room and system assessments CONDITIONS ASSESSMENT All of the room-by-room assessments have been completed and information is being loaded into the model (as stated above). The building assessment information is currently being compiled utilizing the Field 360 program implemented during the assessments. BUILDING SYSTEMS ASSESSMENT The building systems assessments have been completed and information has continued to be loaded into the model. PROGRAMMING All of the preliminary programming with the Capitol agencies has been completed. Programming information which was gathered from each agency during the programming meetings is being edited for final draft. FSB has been working in conjunction with SJK, Inc. to establish the Preservation Zones in regard to Historic Preservation as part of the final 35% deliverable package. In addition, work has taken place regarding Historic Preservation as it relates to the pre-requisite remodeling for the 1 st floor House of Representative and the 3 rd floor Senate spaces. DESIGN STANDARDS FSB continues to build upon the design standards as set forth in the preliminary report by Mass Architects. FSB has meet with OMES staff in several meetings to review the preliminary architectural interiors, MEP/FP systems and Historic Preservation zones as they relate to the 35% deliverable package Broadway Extension, Suite 500, Oklahoma City, Oklahoma Telephone (405) Facsimile (405) Website Page 1 of 1
13 3. Progress Schedule 10 P a g e
14 Activity ID Activity Name Cost % Compl Master Plan Preconstruction / Schematic Design Preconstruction Deliverables & Milestones Orig Rem Dur Dur PRE % SCREOC Presentation Jun-15 A PRE-700 Phase 1 Contract Completion Milestone-35% Deliverable Oct-15* Start Finish May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct 20% SCREOC Presentation Phase 1 Contract Completion Milestone-35% Deliverable Schematic Development % SCREOC Deliverable - HAMMOCK Apr-15 A 31-Aug Preservation Zoning $75, % Apr-15 A 31-Aug Room By Room Conditions Assessment $535, % Apr-15 A 31-Aug Programming Development $175, % Apr-15 A 31-Aug Scope of Work Definitions $65, % Apr-15 A 30-Oct Priority Scope Matrix $90, % Apr-15 A 31-Aug % SD Deliverable - HAMMOCK Apr-15 A 31-Aug Risk Management Plan $25, % Jun-15 A 31-Aug Risk Assessment $25, % Jun-15 A 31-Aug % SD's & Specifications $240, % Jun-15 A 31-Aug Cost Modeling $80, % Jun-15 A 31-Aug Phasing Approach & Definition $25, % Apr-15 A 31-Aug-15 20% SCREOC Deliverable - HAMMOCK Preservation Zoning $75, Room By Room Conditions Assessment $535, Programming Development $175, Scope of Work Definitions $65, Priority Scope Matrix $90, % SD Deliverable - HAMMOCK Risk Management Plan $25, Risk Assessment $25, % SD's & Specifications $240, Cost Modeling $80, Phasing Approach & Definition $25, Start Date 23-Feb-15 Finish Date 07-Mar-16 Data Date 29-Jul-15 Run Date 03-Aug-15 Page 1 of 1 OCRI-04 Actual Level of Effort Actual Work Remaining Work Suspension Remaining LOE Critical Remaining Work Milestone Critical Milestones Oklahoma Capitol Restoration-Interior Rehabiliation Oklahoma City, Oklahoma MCC Project #3707 TASK filters: 2 Month Back + All Remaining, Master Plan Only.
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
Analysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
Enhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
Every Student I Every Day I Every Possibility
For the Facilities Master Plan March 4, 2015 1 Introduction This has been prepared to describe a proposed process to be implemented in order to develop comprehensive Facility Master Plans for all schools
PROJECT: DLS Website Redesign STATUS REPORT May-June 2015
PROJECT: DLS Website Redesign STATUS REPORT May-June 2015 Key Project Roles Project Sponsor: Karen Johnson Executive Director, DLS Project Advisor: Vanessa Salway Program Manager: Project Manager: Steve
Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital
Request for Proposal East Tower Nursing Unit and Infrastructure Upgrade Grossmont Hospital June 21, 2007 The Grossmont Healthcare District (GHD) will accept proposals for Architectural and Engineering
Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre
Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal To change the opening hours of the Revenues & Benefits Call Centre to 9am until 5pm Monday to Friday with effect
Ashley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
Walton Centre. Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt. Monitoring & Audit
Page 1 Walton Centre Monitoring & Audit Document History Date Version Author Changes 01/10/2004 1.0 A Cobain L Wyatt Page 2 Table of Contents Section Contents 1 Introduction 2 Responsibilities Within This
Computing & Telecommunications Services Monthly Report March 2015
March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex [email protected] www.wright.edu/cats/ Last Modified
STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION
STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS PFRC MEETING #1 APRIL 15, 2015 INTRODUCTIONS 1 PROJECT TEAM - John Chadwick Assistant Superintendent, Facilities & Operations -
CENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR
JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf
2012 CBECS: Preliminary Results and Timeline for Data Release
2012 CBECS: Preliminary Results and Timeline for Data Release Joelle Michaels, CBECS Survey Manager Interagency Sustainability Working Group September 18, 2012 Washington, DC U.S. Energy Information Administration
May 2014 Texas School Bond Elections
May 2014 Texas School Bond Elections What are the individual districts needs? New facilities Renovations Technology Central facilities How much tax revenue can the district generate? Depends on district
Delivering Major Crown Projects Long Term Vision and Plan for the Parliamentary Precinct
Delivering Major Crown Projects Long Term Vision and Plan for the Parliamentary Precinct November 2014 Long Term Vision and Plan The main focus of the LTVP is the rehabilitation of the Centre, West and
FY 2015 Schedule at a Glance
Coaching and Mentoring for Excellence Oct 21 23, 2014 $2,950 Residential Coaching and Mentoring for Excellence Apr 7 9, 2015 $2,400 Non-residential Coaching and Mentoring for Excellence May 27 29, 2015
Bb Upgrade Timeline. Oct Nov Dec Jan 2011 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2012. PDFmyURL.com
Bb Upgrade Timeline Oct Nov Dec Jan 2011 Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan 2012 Technology Create a training plan for Bb early adopters and mentors Conduct Transitioning to Bb 9.1 training
Employers Compliance with the Health Insurance Act Annual Report 2015
Employers Compliance with the Health Insurance Act Annual Report 2015 ea Health Council Health Council: Employers Compliance with the Health Insurance Act 1970 Annual Report 2015 Contact us: If you would
2016 Examina on dates
Please note the following informa on: The following exams are available throughout the year: Please click on the exam for which you wish to see the dates. When you have finished, you can select to return
City & County of San Francisco Permit & Project Tracking System
City & County of San Francisco Permit & Project Tracking System PPTS Sneak Preview March 20, 2013 Welcome & Opening Statements AGENDA 1. Opening Statements Department Directors 2. Project Background 3.
2015 Examination dates
Please note the following information: The following exams are available throughout the year: BULATS Paper-based: Please click on the exam for which you wish to see the dates. When you have finished, you
EXHIBIT 2-2-C PROGRESS SCHEDULES
EXHIBIT 2-2-C PROGRESS SCHEDULES PART 1 GENERAL 1.01 SUMMARY A. The work specified in this section consists of furnishing transportation, labor, materials, equipment and incidentals necessary for preparation,
Annexure B: Planning, Budgeting and Performance Management Programme
Annexure B:, Budgeting Programme The following are key activities that need take place in more detail than Time frame Nature Period referred Start Finish 2012/09/01 /08/31 /or September /09/01 /09/26 August
Request for Proposal Campus Master Planning Consultant
Request for Proposal Campus Master Planning Consultant Institution Institution URL for Additional Information about this Project (Optional) Project Name Type of Services Project Manager : Western Carolina
From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Steve Berberich, Vice President of Technology and Corporate Services and Chief Financial Officer Date: September
Design Development Quality Management Phase Checklist Project Phase Checklist Series
Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA
CPSC ITDS/RAM Pilot System: PGA Message Set
CPSC ITDS/RAM Pilot System: PGA Message Set Electronic Certificate Filing Test March 27, 2015 This presentation has not been reviewed or approved by the Commission and may not reflect its views CPSC Background
1. Introduction. 2. User Instructions. 2.1 Set-up
1. Introduction The Lead Generation Plan & Budget Template allows the user to quickly generate a Lead Generation Plan and Budget. Up to 10 Lead Generation Categories, typically email, telemarketing, advertising,
2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc
July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
Project Management Planning
The Project Plan Template The Project Plan The project plan forms the basis for all management efforts associated with the project. A project plan template is included in this document. The information
CONSTRUCTION MANAGEMENT REPORT NO. 2
CONSTRUCTION MANAGEMENT REPORT NO. 2 Expansion and Renovation Prepared for: HOLLAND PUBLIC SCHOOLS BOARD OF EDUCATION Date: October 31, 2011 HOLLAND PUBLIC SCHOOLS HIGH SCHOOL EXPANSION AND RENOVATION
ESTABLISHMENT OF A NEW BUSINESS
ESTABLISHMENT OF A NEW BUSINESS ATTENTION BUSINESS OWNERS Certificate of Occupancy Permit Requirements & Application Prior to any materials associated with your business being moved into the property that
CAFIS REPORT 2015.10
CAFIS REPORT 2015.10 INDEX Message CAFIS Inbound 03-06 07-08 CAFIS Arch 09-10 CAFIS Brain 11-12 CAFIS Global 13-14 What We Do 15-16 About CAFIS 17-18 Services for Member Stores 19-34 Services for Card
Request for Qualifications 2015-162
Kitsap County Human Services Department Request for Qualifications 2015-162 Architectural and Project Management Services - Kitsap County Work Release Facility Remodel Response Deadline: November 17, 2015
Implementation Plan: Development of an asset and financial planning management. Australian Capital Territory
Implementation Plan: Development of an asset and financial planning management framework for TAMS Australian Capital Territory NATIONAL PARTNERSHIP AGREEMENT TO SUPPORT LOCAL GOVERNMENT AND REGIONAL DEVELOPMENT
Supervisor Instructions for Approving Web Time Entry
Supervisor Instructions for Approving Web Time Entry Time Approval Deadlines by Category Local 2110 Members members submit time by NOON on Monday of the pay week. Time should be approved no later than
Consumer ID Theft Total Costs
Billions Consumer and Business Identity Theft Statistics Business identity (ID) theft is a growing crime and is a growing concern for state filing offices. Similar to consumer ID theft, after initially
Architectural Services Data Summary March 2011
Firms Typically Small in Size According to the latest U.S. Census Survey of Business Owners, majority of the firms under the description Architectural Services are less than 500 in staff size (99.78%).
GTA Board of Directors September 4, 2014
GTA Board of Directors September 4, 2014 Our Strategic Vision Our Mission A transparent, integrated enterprise where technology decisions are made with the citizen in mind To provide technology leadership
Discussion Outline. A. KPIs Defined. B. Why KPIs Matter. C. KPI Menu. D. Implementation. E. Example KPIs. F. Pitfalls
Discussion Outline A. KPIs Defined B. Why KPIs Matter C. KPI Menu D. Implementation E. Example KPIs F. Pitfalls 1 Key Performance Indicators (KPI s) Defined Periodic assessment of an organization, business
P/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014
2014-2015 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2014 TERM Key: P/T = Part of Term P/T Description
P/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013
2013-2014 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2013 TERM Key: P/T = Part of Term P/T Description
Roles: Scrum Master & Project Manager
Roles: Scrum Master & Project Manager Scrum Master: Facilitate collaborative meetings Track team performance Remove impediments (Risk, Issue) Validate team alignment to Agile framework and scope Drive
P/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015
2015-2016 SPECIAL TERM ACADEMIC CALENDAR For Scranton Education Online (SEOL), Masters of Business Administration Online, Masters of Accountancy Online, Health Administration Online, Health Informatics
Media Planning. Marketing Communications 2002
Media Planning Marketing Communications 2002 Media Terminology Media Planning - A series of decisions involving the delivery of messages to audiences. Media Objectives - Goals to be attained by the media
The Interagency Security Committee and Security Standards for Federal Buildings
Order Code RS22121 Updated November 23, 2007 The Interagency Security Committee and Security Standards for Federal Buildings Summary Stephanie Smith Analyst in American National Government Government and
GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4
GOVERNING BODY MEETING held in public 29 July 2015 Agenda Item 4.4 APPENDIX A Strategic Planning Process 2016/17 Strategic Planning Process 2016/17 Interlocking processes 5 Year strategic process: reviewed
Release of the Draft Cybersecurity Procurement Language for Energy Delivery Systems
Release of the Draft Cybersecurity Procurement Language for Energy Delivery Systems Energy Sector Control Systems Working Group Supporting the Electricity Sector Coordinating Council, Oil & Natural Gas
A Resource for Free-standing Mathematics Units. Data Sheet 1
Data Sheet 1 Regular Expenses Item Estimate of Cost When Petrol/Diesel 10p per mile As needed Oil 12 for can of oil and filter Once or twice per year Air Filter 10 Once a year MOT 25-30 (excluding repairs)
Request for Proposal for Architectural Services Scope of Work and Design Documents for
10400 Detrick Avenue Kensington, Maryland 20895-2484 Telephone (240) 627-9786 Fax (301) 949-1286 www.hocmc.org RFP #1968 Request for Proposal for Architectural Services Scope of Work and Design Documents
An Introduction to the. Society Program Portfolio Management Process
An Introduction to the Society Program Portfolio Management Process Presentation Topics What is Society Program Portfolio Management or SPPM? What is the Goal of SPPM? Who Oversees SPPM? Who Participates
Coordination and air quality monitoring during emergencies. Colin Powlesland Environment Agency
Coordination and air quality monitoring during emergencies Colin Powlesland Environment Agency Contents h Introduction h What do we want to achieve? h Implementation programme h Incident timeline h Proposed
Florida s Private Rebuilt Vehicle Inspection Program. Pilot Program Report January 30, 2015. Terry L. Rhodes, Executive Director
Florida s Private Rebuilt Vehicle Inspection Program Pilot Program Report January 30, 2015 Terry L. Rhodes, Executive Director Florida s Private Rebuilt Vehicle Inspection Program Pilot Program Report
Business Idea Development Product production Services. Development Project. Software project management
Page 1, 1/20/2003 Ivica Crnkovic Mälardalen University Department of Computer Engineering [email protected] Development Project Product Lifecycle Business Idea Development Product production Services
Independent Accountants Report on Applying Agreed-Upon Procedures
Independent Accountants Report on Applying Agreed-Upon Procedures Board of Trustees We have performed the procedures, as discussed below, with respect to the employer contributions remitted by to the in
ATLANTA, April 19, 2004 Swan House, a Neoclassical style home-turned-historic house
News Release FOR IMMEDIATE RELEASE Contact: Ken Higa Lord, Aeck & Sargent 404-253-6732 [email protected] or Ann Kohut Kohut Communications Consulting 770-913-9747 [email protected] Swan House
5-Minute Primer for Commercial Building Energy Audits
5-Minute Primer for Commercial Building Energy Audits Why Energy Audits? Because an energy audit is the first step to saving energy at your facility. Putting together an energy project can be like finding
TECH. Tracking Progress. Project Schedule PHASE 1 STEP 1 ACTIVITY 1.1. Activity and Milestone STEP 1 STEP 2 : ACTIVITY 2.2 : ACTIVITY 1.
CH03 Planning and Managing the Project * Tracking Progress * Project Personnel * Effort Estimation * Risk Management * The Project Plan * Process Models and Project Management Tracking Progress Questions
US Army Corps of Engineers. Vision Statement. Be the premier stewards of entrusted hydropower resources
Vision Statement Be the premier stewards of entrusted hydropower resources Mission Statement Provide reliable hydroelectric power services at the lowest possible cost, consistent with sound business principles,
2017 Budget and Grid Management Charge Initial Stakeholder Meeting
2017 Budget and Grid Management Charge Initial Stakeholder Meeting June 16, 2016 Page 1 Agenda Topic 2017 Budget Process & GMC Rate Outlook Managing Employee Compensation Presenter(s) Ryan Seghesio & April
Training Calendar 2015. GTC Energy: Training Calendar / 165
Training Calendar 2015 GTC Energy: Training Calendar / 165 166 / GTC Energy: Training Calendar January Project Cost Estimation and Cost Control Houston 26 Jan 2015 1 Week 2 Weeks 127 February Advanced
Detailed guidance for employers
April 2015 3 Detailed guidance for employers Appendix A: Pay reference periods This document accompanies: Detailed guidance no. 3 Assessing the workforce Pay reference period calendars where the definition
Consulting Services for Enterprise Resource Planning Project Planning and RFP Development Government Finance Officers Association
Volusia County Schools Consulting Services for Enterprise Resource Planning Project Planning and RFP Development Government Finance Officers Association May 12, 2016 Agenda o Introductions o Approach &
Executive Branch IT Reorganization Project Plan
Office of Information Resource Management Executive Branch Project Plan Work Program Funded by for IT Appropriations Reorganization 2007, 2009 and Five Small Projects Date: August 2009 Version: 1.3 Revision
Implementing Carbon Reduction Without Impacting Working Capital. Presented by Dylan Crompton
Implementing Carbon Reduction Without Impacting Working Capital Presented by Dylan Crompton Evolution of a Carbon Strategy Proactive organisations are on a journey to reduce carbon emissions. Marginal
Stephen Doune HRIS Project Manager Plan International
Stephen Doune HRIS Project Manager Plan International Content 1. About Plan International 2. The Challenge 3. The Vision 4. About Assima 5. The Projects 6. The Timeline 7. Partner Selection 8. Key 1st
AgriLife Information Technology IT General Session January 2010
AgriLife Information Technology IT General Session January 2010 Agenda Topics Year in Review Enterprise IT Services Update FirstCall Overview and Next Steps Sophos Antivirus Initiative Update Information/
Choosing a Cell Phone Plan-Verizon
Choosing a Cell Phone Plan-Verizon Investigating Linear Equations I n 2008, Verizon offered the following cell phone plans to consumers. (Source: www.verizon.com) Verizon: Nationwide Basic Monthly Anytime
State Annual Report Due Dates for Business Entities page 1 of 10
State Annual Report Due Dates for Business Entities page 1 of 10 If you form a formal business entity with the state, you may be required to file periodic reports on the status of your entity to preserve
Managing Projects with Practical Software & Systems Measurement PSM
Managing Projects with Practical Software & Systems Measurement PSM Mauricio Aguiar PSM Qualified Instructor TI Métricas Ltda. Av. Rio Branco 181/1910 Rio de Janeiro, RJ Brazil 20040-007 www.metricas.com.br
In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including:
Enterprise Risk Management Process and Procedures Scope In accordance with risk management best practices, below describes the standard process for enterprise risk management (ERM), including: Risk identification
Capital Project Delivery Handbook
Capital Project Delivery Handbook Volume One Facilities Planning & Construction 1 FACILITIES PLANNING & CONSTRUCTION 3/8/09 2 FACILITIES PLANNING & CONSTRUCTION 1. WELCOME TO FACILITIES PLANNING & CONSTRUCTION...
Department of Public Welfare (DPW)
Department of Public Welfare (DPW) Office of Income Maintenance Electronic Benefits Transfer Card Risk Management Report Out-of-State Residency Review FISCAL YEAR 2012-2013 June 2013 (March, April and
Pre-Existing Structures at the Site Project Duration Type of Structure Under Construction Any Other Entities with Interests in the Property
Speakers: Vice President, Global Risk Management & Insurance Starwood Hotels & Resorts Worldwide Senior Vice President - National Director National Property Claims - Strategic Outcomes Practice Willis
Accident & Emergency Department Clinical Quality Indicators
Overview This dashboard presents our performance in the new A&E clinical quality indicators. These 8 indicators will allow you to see the quality of care being delivered by our A&E department, and reflect
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance
RBC Insurance Fetes Online Auto/Home Insurance Growth
Case Studies, K. Harris Research Note 29 October 2002 RBC Insurance Fetes Online Auto/Home Insurance Growth RBC Insurance's e-business successes are generating greater than $3 million in premiums per month.
Maximising Ability, Reducing Disability. Dr. Áine Carroll Clinical Lead Valerie Twomey Programme Manager
Rehabilitation Medicine Programme Maximising Ability, Reducing Disability Dr. Áine Carroll Clinical Lead Valerie Twomey Programme Manager 1 Quality, Access and Cost Quality: Reduce morbidity: Reduced pressure
Volume II- Project Development Processes
Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required
The principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
Sage ERP MAS 90, 200, 200 SQL, and Sage ERP MAS 500. Supported Versions
Sage ERP MAS 90, 200, 200 SQL, and Sage ERP MAS 500 Supported Versions Current Document: 2012... Page 1 Earlier Documents: 2011... Page 2 2010... Page 3 2009... Page 4 2008... Page 5 Sage ERP MAS 90, 200,