TOTAL ASSET MANAGEMENT. Life Cycle Costing Guideline
|
|
|
- Maud Felicia McCoy
- 9 years ago
- Views:
Transcription
1 TOTAL ASSET MANAGEMENT Life Cycle Costing Guideline September 2004 TAM04-10
2 Life Cycle Costing Guideline September 2004 TAM04-10 ISBN X (set) ISBN Asset management New South Wales. 2. Capital Investment. 3. Public administration New South Wales I. Title. (Series : TAM 2004) This work is copyright. Apart from any use as permitted under the Copyright Act 1968, no part may be reproduced by any process without written permission from the NSW Treasury. Requests and inquiries concerning reproduction and rights should be addressed to: NSW Treasury The Executive Officer, Level 27 Governor Macquarie Tower 1 Farrer Place Sydney NSW 2000 General inquiries concerning this document should be initially directed to: Arthur Megaloconomos (Tel: or [email protected]) of NSW Treasury. This publication can be accessed from the Treasury s Office of Financial Management Internet site [ For printed copies contact the Publications Officer on Tel: Set consists of: ISBN ISBN ISBN ISBN ISBN ISBN ISBN ISBN Asset Information Guideline TAM04-7 Demand Management Guideline TAM04-8 Heritage Asset Management Guideline TAM04-9 Life Cycle Costing Guideline TAM04-10 Post Implementation Review Guideline TAM04-11 Risk Management Guideline TAM04-12 Sustainable Development Guideline TAM04-13 Value Management Guideline TAM04-14 Further publications are also available in this series on the following topics: ISBN ISBN ISBN X ISBN ISBN ISBN Asset Strategy Planning TAM04-1 Capital Investment Strategic Planning TAM04-2 Asset Maintenance Strategic Planning TAM04-3 Asset Disposal Strategic Planning TAM04-4 Office Accommodation Strategic Planning TAM04-5 Total Asset Management Template TAM04-6 Additional publications also available in this series on the following topics: ISBN ISBN X ISBN ISBN 07313c Total Asset Management Capability Tool TAM04-15 Total Asset Management Capability Tool - Snapshot Capability Review TAM04-16 Total Asset Management Capability Tool - The Guide to Conducting a Full Capability Review TAM04-17 Total Asset Management Capability Tool- The Capability Review Report Kit TAM04-18
3 TABLE OF CONTENTS 1. Introduction Why use Life Cycle Costing What is Life Cycle Costing Distribution of assets over the asset life cycle Linkages with Total Asset Management Modelling life cycle costs Life Cycle Costing models Life Cycle Costing breakdown into asset cost elements Estimating asset cost elements 4 3. The Life Cycle Costing process Overview 6 Appendix A The concept of discounting and its application 13 TAM Life Cycle Costing Guideline i
4 LIFE CYCLE COSTING - GUIDELINE 1 Introduction 1.1 Why use Life Cycle Costing? The determination of costs is an integral part of the asset management process and is a common element of many of the asset manager s tools, particularly Economic Appraisal, Financial Appraisal, Value Management, Risk Management and Demand Management. In the past, comparisons of asset alternatives, whether at the concept or detailed design level, have been based mainly on initial capital costs. Growing pressure to achieve better outcomes from assets means that ongoing operating and maintenance costs must be considered as they consume more resources over the asset s service life. For example, the operating costs of a hospital consume an equivalent of the capital cost every two to three years and can continue to do so for forty years or more. The operating costs of a school can consume the equivalent of its capital cost every four to five years and remain in service for a century. Both the capital and the ongoing operating and maintenance costs must be considered wherever asset management decisions involving costs are made. This is the Life Cycle Cost approach. Life Cycle Costing is a process to determine the sum of all the costs associated with an asset or part thereof, including acquisition, installation, operation, maintenance, refurbishment and disposal costs. It is pivotal to the asset management process as an input to the evaluation of alternatives via Economic Appraisal, Financial Appraisal, Value Management, Risk Management and Demand Management. There is an Australian Standard on Life Cycle Costing (AS4536) that includes examples of the application of Life Cycle Costing in its appendices. 1.2 What is Life Cycle Costing? The Life Cycle Cost (LCC) of an asset is defined as: " the total cost throughout its life including planning, design, acquisition and support costs and any other costs directly attributable to owning or using the asset". Life Cycle Costing adds all the costs of alternatives over their life period and enables an evaluation on a common basis for the period of interest (usually using discounted costs). This enables decisions on acquisition, maintenance, refurbishment or disposal to be made in the light of full cost implications. Life cost planning Life Cost Planning concerns the assessment and comparison of options/alternatives during the design/ acquisition phase. It utilises similar techniques as those for Economic Appraisal in that future, nominal costs are discounted to today's dollar Discounted Cost. The application of Discounted Cost analyses to Life Cost Planning differs from that in Economic Appraisal in that Life Cost Planning generally: considers all cost components within asset options over the asset s life TAM Life Cycle Costing Guideline 1
5 does not directly consider benefits or revenue streams that are generally assumed to be equal among the options being compared (benefits and revenues are considered in the evaluation of options). Life cost analysis Life Cost Analysis enables the creation, operation and disposal costs of a selected alternative to be monitored throughout its life to enable accurate and timely decision-making as to how these costs can be minimised. Where ownership of the asset changes over time, each owner, takes responsibility for decisions required during the period of ownership only. Life Cost Analysis is used as the basis for monitoring and management of costs over an asset s life. It is essentially a financial management tool costs are generally not expressed as real or discounted costs but as nominal costs (ie. estimated costs that are to be paid when due) to enable a comparison of the predicted cost and the actual cost. This enables better prediction and adjustment of the Life Cycle Costing model (LCC). Appendix A provides a summary of the discounting concept along with an explanation of the differences between real, discounted and nominal costs. 1.3 Distribution of costs over the asset life cycle Life Cycle Costing can be carried out during any or all phases of an asset's life cycle. It can be used to provide input to decisions regarding asset design, manufacture, installation, operation, support and disposal. By the end of the concept and definition phases of acquisition, more than half of the asset s life costs may be committed by decisions made with respect to asset features, performance, reliability, technology, and support resources. By the end of design and development phases, even more of the asset's life costs may be fixed. The interaction between potential savings and asset costs is shown in Figure 1 - Potential Savings and Cost Relationship. Early identification of acquisition and ownership costs enables the decision-maker to balance performance, reliability, maintainability, maintenance support and other goals against life cycle costs. Decisions made early in a asset's life cycle have a much greater influence on Life Cycle Costing than those made late in a asset's life cycle, leading to the development of the concept of discounted costs. Figure 1 Potential Savings and Cost Relationship Cost Cost of making changes Time Potential for making savings TAM Life Cycle Costing Guideline 2
6 1.4 Linkages with Total Asset Management TAM reflects priorities for whole-of-life asset management, extended planning requirements for new works, and new relationships between services planning and asset procurement activities. Costs may change and accumulate as a program or project progresses. Initial provisions made to manage whole-of-life costs should be evaluated and updated before committing to one alternative. A LCC model provides a mechanism to compare these costs. TAM Life Cycle Costing Guideline 3
7 2 Modelling life cycle costs 2.1 Life Cycle Costing models LCC model is an accounting structure containing terms and factors which enable estimation of an asset's component costs. a number of commercially available models can be used for LCC analysis. However, in some cases it may be appropriate to develop a model for a specific application. In either case, the LCC model should: represent the characteristics of the asset being analysed including its intended use environment, maintenance concept, operating and maintenance support scenarios and any constraints or limitations be comprehensive enough to include and highlight the factors relevant to the asset LCC be easily understood to allow timely decision- making, future updates and modification provide for the evaluation of specific LCC elements independently of other elements. Before selecting a model, the purpose of the analysis and the information it requires should be identified. The model should also be reviewed with respect to the applicability of all cost factors, empirical relationships, constants, elements and variables. 2.2 LCC breakdown into asset cost elements Estimating the total LCC requires breakdown of the asset into its constituent cost elements over time. The level to which it is broken down will depend on the purpose and scope of the LCC study and requires identification of: significant cost generating activity components the time in the life cycle when the work/activity is to be performed relevant resource cost categories such as labour, materials, fuel/energy, overhead, transportation/travel and the like. Costs associated with LCC elements may be further allocated between recurring and non-recurring costs. LCC elements may also be estimated in terms of fixed and variable costs. To facilitate control and decision-making and to support the Life Cycle Costing process, the cost information should be collected and reported in a manner consistent with the defined LCC breakdown structure. 2.3 Estimating asset cost elements The method used to estimate asset cost elements in LCC calculations will depend on the amount of information needed to: establish asset use patterns and operational characteristics and hence expected asset life understand the technology employed in the asset. Sources of cost data By definition, detailed cost data will be limited in the early stages of the asset life, particularly during the design/acquisition phase. Cost data during these early stages will need to be based on the cost performance of similar asset components currently in operation. Where new technology is being employed, data can only be based on estimated unit cost parameters such as $/construction unit, construction unit/labour hours, specified or suggested by the technology. TAM Life Cycle Costing Guideline 4
8 More information on asset component costs will become available during use of the asset, enabling more complete and descriptive costs to be defined. Methods of analyses One or more of the following methods for analysing cost data should be used. Engineering cost method The Engineering Cost Method is used where there is detailed and accurate capital and operational cost data for the asset under study. It involves the direct estimation of a particular cost element by examining the asset component-by-component. It uses standard established cost factors (eg. firm engineering and/or manufacturing estimates) to develop the cost of each element and its relationship to other elements (known as Cost Element Relationships - CER). Analogous cost method This method provides the same level of detail as the Engineering Cost Method but draws on historical data from components of other assets having analogous size, technology, use patterns and operational characteristics. Parametric cost method The Parametric Cost Method is employed where actual or historical detailed asset component data is limited to known parameters. This available data from existing cost analyses is used to develop a mathematical regression or progression formula that can be solved for the cost estimate required. AS 4536 contains an example of regression analyses to find the cost per vehicle to undertake new delivery routes based on known delivery costs and known route distances. A formula of the form y=a+bx is then solved for the required route. (y is vehicle costs, a is a transport constant, b is the slope of the regression line and x is the route distance) TAM Life Cycle Costing Guideline 5
9 3 The Life Cycle Costing process Plan Analysis Select/ Develop Model Apply Model Document and Review Results Prepare Life Cost Analysis Implement and Monitor Life Cost Analysis Life Cost Planning Life Cost Analysis 3.1 Overview As shown in the attached diagram, Life Cycle Costing is a six-staged process. The first four stages comprise the Life Cost Planning phase with the last two stages incorporating the Life Cost Analysis phase. The six stages are: Stage 1: Plan LCC Analysis Stage 2: Select/Develop LCC Model Stage 3: Apply LCC Model Stage 4: Document and Review LCC Results Stage 5: Prepare Life Cost Analysis Stage 6: Implement and Monitor Life Cost Analysis All stages may be performed iteratively as needed. Assumptions made at each stage should be rigorously documented to facilitate such iterations and to aid in interpretation of the results of the analysis. LCC analysis is a multi-disciplinary activity. An analyst should be familiar with the philosophy, which underlies Life Cycle Costing (including typical cost elements, sources of cost data and financial principles), and should have a clear understanding of the methods of assessing the uncertainties associated with cost estimation. Depending upon the scope of the analysis, it will be important to obtain cost inputs from individuals who are familiar with each of the phases of the asset life cycle. This may include representatives of both the supplier(s) and the user(s). TAM Life Cycle Costing Guideline 6
10 Stage 1 Plan LCC analysis Plan Analysis The Life Cycle Costing process begins with development of a plan, which addresses the purpose, and scope of the analysis. The plan should: define the analysis objectives in terms of outputs required to assist management decisions. Typical objectives are:! determination of the LCC for an asset in order to assist planning, contracting, budgeting or similar needs! evaluation of the impact of alternative courses of action on the LCC of an asset (such as design approaches, asset acquisition, support policies or alternative technologies)! identification of cost elements which act as cost drivers for the LCC of an asset in order to focus design, development, acquisition or asset support efforts. delineate the scope of the analysis in terms of the asset(s) under study, the time period (life cycle phases) to be considered, the use environment and the operating and maintenance support scenario to be employed. Identify any underlying conditions, assumptions, limitations and constraints (such as minimum asset performance, availability requirements or maximum capital cost limitations) that might restrict the range of acceptable options to be evaluated. Identify alternative courses of action to be evaluated. The list of proposed alternatives may be refined as new options are identified or as existing options are found to violate the problem constraints. Provide an estimate of resources required and a reporting schedule for the analysis to ensure that the LCC results will be available to support the decision-making processes for which they are required. The plan should be documented at the beginning of the Life Cycle Costing process to provide a focus for the rest of the work. Intended users of the analysis results should review the plan to ensure their needs have been correctly interpreted and clearly addressed. TAM Life Cycle Costing Guideline 7
11 Stage 2 Select/develop LCC model Select/ Develop Model Stage 2 is the selection or development of an LCC model that will satisfy the objectives of the analysis. The model should: create or adopt a cost breakdown structure (CBS) that identifies all relevant cost categories in all appropriate life cycle phases. Cost categories should continue to be broken down until a cost can be readily estimated for each individual cost element. Where available, an existing cost breakdown structure may provide a useful starting point for development of the LCC breakdown structure (see Section 2.2). identify those cost elements that will not have a significant impact on the overall LCC of the asset(s) under consideration or those that will not vary between alternatives. These elements may be eliminated from further consideration select a method (or methods) for estimating the cost associated with each cost element to be included in the model (see Section 2.3). determine the data required to develop these estimates, and identify sources for the data. identify any uncertainties that are likely to be associated with the estimation of each cost element. integrate the individual cost elements into a unified LCC model, which will provide the LCC outputs required to meet the analysis objectives. review the LCC model to ensure that it is adequate to address the objectives of the analysis. the LCC model including all assumptions should be documented to guide and support the subsequent phases of the analysis process. TAM Life Cycle Costing Guideline 8
12 Stage 3 Apply LCC model Identify the demand Application of the LCC Model involves the following steps: obtain data and develop cost estimates and their timing for all the basic cost elements in the LCC model. validate the LCC model with available historical data if possible. obtain the LCC model results from each relevant combination of operating and support scenarios defined in the analysis plan. identify cost drivers by examining LCC model inputs and outputs to determine the cost elements that have the most significant impact on the LCC of the asset(s). quantify any differences (in performance, availability or other relevant constraints) among alternatives being studied, unless these differences are directly reflected in the LCC model outputs. categorise and summarise LCC model outputs according to any logical groupings, which may be relevant to users of the analysis results (eg. fixed or variable costs, recurring or nonrecurring costs, acquisition or ownership costs, direct or indirect costs). conduct sensitivity analyses to examine the impact of variations to assumptions and cost element uncertainties on LCC model results. Particular attention should be focused on cost drivers, assumptions related to asset usage and different discount rates. review LCC outputs against the objectives defined in the analysis plan to ensure that all goals have been fulfilled and that sufficient information has been provided to support the required decision. If the objectives are not met, additional evaluations and modifications to the LCC model may be required. the LCC analysis (including all assumptions) should be documented to ensure that the results can be verified and readily replicated by another analyst if necessary. TAM Life Cycle Costing Guideline 9
13 Stage 4 Document and review LCC results Document and Review Results The results of the LCC analysis should be documented to allow users to clearly understand both the outcomes and the implications of the analysis along with the limitations and uncertainties associated with the results. The report should contain the following. Executive Summary: a brief synopsis of the objectives, results, conclusions and recommendations of the analysis. Purpose and Scope: a statement of the analysis objective, asset description including a definition of intended asset use environment, operating and support scenarios, assumptions, constraints and alternative courses of action considered. LCC Model Description: a summary of the LCC model, including relevant assumptions, the LCC breakdown structure and cost elements along with the methods of estimation and integration. LCC Model Application: a presentation of the LCC model results including the identification of cost drivers, the results of sensitivity analyses and the output from any other related analyses. Discussion: discussion and interpretation of the results including identification of uncertainties or other issues which will guide decision makers and users in understanding and using the results. Conclusions and Recommendations: a presentation of conclusions related to the objectives of the analysis and a list of recommendations along with identification of any need for further work or revision of the analysis. A formal review of the analysis process may be required to confirm the correctness and integrity of the results, conclusions and recommendations presented in the report. If such a requirement exists someone other than the original analysts should conduct the review (to ensure objectivity). The following elements should be addressed in the review: the objectives and scope of the analysis to ensure that they have been appropriately stated and interpreted the model (including cost element definitions and assumptions) to ensure that it is adequate for the purpose of the analysis the model evaluation to ensure that the inputs have been accurately established, the model has been used correctly, the results (including those of sensitivity analysis) have been adequately evaluated and discussed and that the objectives of the analysis have been achieved all assumptions made during the analysis process to ensure that they are reasonable and that they have been adequately documented. TAM Life Cycle Costing Guideline 10
14 Stage 5 Prepare life cost analysis Prepare Life Cost Analysis The Life Cost Analysis is essentially a tool, which can be used to control and manage the ongoing costs of an asset or part thereof. It is based on the LCC Model developed and applied during the Life Cost Planning phase with one important difference: it uses data on nominal costs. The preparation of the Life Cost Analysis involves review and development of the LCC Model as a "real-time" cost control mechanism. This will require changing the costing basis from discounted to nominal costs. Estimates of capital costs will be replaced by the actual prices paid. Changes may also be required to the cost breakdown structure and cost elements to reflect the asset components to be monitored and the level of detail required. Targets are set for the operating costs and their frequency of occurrence based initially on the estimates used in the Life Cost Planning phase. These targets may change with time as more accurate data is obtained, either from the actual asset operating costs or from benchmarking with other similar assets. TAM Life Cycle Costing Guideline 11
15 Stage 6 Implement and monitor life cost analysis Implement and Monitor Life Cost Analysis Implementation of the Life Cost Analysis involves the continuous monitoring of the actual performance of an asset during its operation and maintenance to identify areas in which cost savings may be made and to provide feedback for future life cost planning activities. For example, it may be better to replace an expensive building component with a more efficient solution prior to the end of its useful life than to continue with a poor initial decision. TAM Life Cycle Costing Guideline 12
16 Appendix A The Concept of discounting and its application A1 The discount rate and its components Since asset component costs for differing options occur at varying times throughout the asset life cycle, they can only be compared by reducing them to costs at a common base date. This is achieved through the well-known process of discounting that reflects the net changes in the real value of an asset component as a result of: decreases in value due to inflation increases in value due to the (potential) interest earned if the money expended on the asset component was otherwise invested. The discounting of costs takes account of three elements: the interest rate available from long term investment in bank or government bonds the interest rate that business would expect as a return for risk the inflation rate that would affect the purchasing power of the currency. The real discount rate makes allowance for A and B. The nominal discount rate makes allowance for A, B and C. Discounting does not incorporate changes due to price movements as a result of changes in efficiency, technology, etc. since these are in essence real changes in value. The discount rate reflects the net changes in real value due to the compounding effect of interest (potentially) earned on money and the discounting effects of inflation as expressed in the following formula. The Discount Rate reflects the real rate of interest at which money is borrowed or lent ie. the absolute (or nominal) interest rate at which money is borrowed or lent discounted for the effects of inflation. Consequently, the terms discount rate and real interest rate are synonymous. A2 Nominal, real and discounted costs For the purposes of discounting, there are three relevant expressions of asset component costs. These are: Nominal Cost, C N The expected price that will be paid when a cost is due to be paid (ie. including inflation and price movements due to changes in efficiency, technology, etc.) Real Cost, CR The cost expressed in values of the base date excluding inflation but including price movements due to changes in efficiency, technology, etc. Discounted Cost, CD The Real Cost discounted by the Real Discount Rate which is equivalent to the Nominal Cost discounted by the Nominal Interest (or Discount) Rate. The Discounted Cost is thus often referred to as the Net (or Discounted) Present Value. TAM Life Cycle Costing Guideline 13
17 Therefore, for an asset component having a Nominal Cost, C N in Year n, then the Real Cost (or Present Value), C R at the base date (Year 0) is given by: ( 1 ) n CR= CN + f and the Discounted Cost (or Net Present Value), C D at the base date (Year 0) is thus: n C = C 1+ d D R ( ) ( 1 n ) ( 1 ) n ( 1+ i) ( 1 f ) ( 1+ f ) ( 1 n i) = C + f + d N = C + N = C + N ( ) 1 + d = d = ( ) 1 + i ( 1 + f) ( ) 1 + i ( 1 f) n n n where d = (Real) D iscount Rate i = Nominal Interest (or Discount) Rate f = Inflation Rate For this reason, i is often referred to as the Nominal Discount Rate since it is the rate applied when discounting Nominal Costs. TAM Life Cycle Costing Guideline 14
Total Asset Management Capability Tool
TOTAL ASSET MANAGEMENT Total Asset Management Capability Tool September 2004 TAM04-15 TAM Total Asset Management Capability Tool i Total asset management capability tool September 2004 TAM04-15 ISBN 0
TOTAL ASSET MANAGEMENT. Risk Management Guideline
TOTAL ASSET MANAGEMENT Risk Management Guideline September 2004 TAM04-12 Risk Management Guideline September 2004 TAM04-12 ISBN 0 7313 3325 X (set) ISBN 0 7313 32849 1. Asset management New South Wales.
december 08 tpp 08-5 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper
december 08 Guidelines for Capital Business Cases OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The NSW Government is committed to the ongoing improvement of public services by ensuring
Project Evaluation Guidelines
Project Evaluation Guidelines Queensland Treasury February 1997 For further information, please contact: Budget Division Queensland Treasury Executive Building 100 George Street Brisbane Qld 4000 or telephone
LIFE CYCLE COSTING BETTER PRACTICE GUIDE
LIFE CYCLE COSTING BETTER PRACTICE GUIDE December 2001 Auditor-General s Foreword This Better Practice Guide is intended to assist APS managers responsible for decisions relating to acquiring, owning,
Strategic Asset Management Framework
STRATEGIC ASSET MANAGEMENT Strategic Asset Management Framework (Second Edition) Achieving better value for South Australians from our investment in State assets Government of South Australia First edition
Summary of GAO Cost Estimate Development Best Practices and GAO Cost Estimate Audit Criteria
Characteristic Best Practice Estimate Package Component / GAO Audit Criteria Comprehensive Step 2: Develop the estimating plan Documented in BOE or Separate Appendix to BOE. An analytic approach to cost
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP)
AIPM PROFESSIONAL COMPETENCY STANDARDS FOR PROJECT MANAGEMENT PART B CERTIFIED PRACTISING PROJECT PRACTITIONER (CPPP) Copyright: Australian Institute of Project Management Document Information Document
Financial Sustainability Information Paper 8. Long-term Financial Plans
Financial Sustainability Information Paper 8 Long-term Financial Plans Revised January 2012 Introduction This Information Paper is one of a series of Information Papers about Financial Sustainability and
TEC Capital Asset Management Standard January 2011
TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining
Total Asset Management Manual
Total Asset Management Manual This document is a snapshot of the NSW Government Total Asset Management Manual dated August 2003 see the TAM Manual Web Site for current documents. The Total Asset Management
Long Term Financial Planning
Long Term Financial Planning Framework and Guidelines Long Term Financial Planning Framework and Guidelines for Western Australian Local Governments p1. Contents Foreword 4 1. Introduction 7 2. Purpose
TOTAL ASSET MANAGEMENT. Post Implementation Review Guideline
TOTAL ASSET MANAGEMENT Post Implementation Review Guideline September 2004 TAM04-11 Post Implementation Review Guideline September 2004 TAM04-11 ISBN 0 7313 3325 X (set) ISBN 0 7313 3278 4 1. Asset management
1.1 Objective 4. 1.2 Competencies and resources required 4. 1.3 Scope 4. 1.4 Related documents 5. 3.1 Defining the objectives and scope of projects 7
Contents 1.0 Introduction 3 1.1 Objective 4 1.2 Competencies and resources required 4 1.3 Scope 4 1.4 Related documents 5 2.0 Project evaluation 5 3.0 Project feasibility 7 3.1 Defining the objectives
Developing and Managing Internal Budgets. top-down. embed. hasing variation. allocation. forecasting. bottom-up
Developing and Managing Internal Budgets top-down embed hasing variation forecasting allocation bottom-up Better Practice Guide June 2008 ISBN No. 0 642 81021 4 Commonwealth of Australia 2008 COPYRIGHT
july 07 tpp 07-4 Commercial Policy Framework: Guidelines for Financial Appraisal OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper
july 07 Commercial Policy Framework: Guidelines for Financial Appraisal OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface The Guidelines for Financial Appraisal is a policy document prepared
PROJECT COST MANAGEMENT
7 PROJECT COST MANAGEMENT Project Cost Management includes the processes required to ensure that the project is completed within the approved budget. Figure 7 1 provides an overview of the following major
Project Cost Management
Project Skills Team FME www.free-management-ebooks.com ISBN 978-1-62620-982-9 Copyright Notice www.free-management-ebooks.com 2014. All Rights Reserved ISBN 978-1-62620-982-9 The material contained within
Treasury Circular. Payment of Accounts
Payment of Accounts Treasury Circular NSW TC 11/12 14 July 2011 This Circular specifies the Government s payment of accounts policy, including new requirements, effective from 14 July 2011, for agencies
The RCM Analyst - Beyond RCM
The RCM Analyst - Beyond RCM About the Author: Daryl Mather was originally trained in RCM in 1991, after which he was involved in the application of the method through a range of capital-intensive industries.
Organisational Performance Measurement and Reporting Guide
Organisational Performance Measurement and Reporting Guide Australian Capital Territory, Canberra, April 2013 This work is copyright. Apart from any use permitted under the Copyright Act 1968, no part
Guide for the Development of Results-based Management and Accountability Frameworks
Guide for the Development of Results-based Management and Accountability Frameworks August, 2001 Treasury Board Secretariat TABLE OF CONTENTS Section 1. Introduction to the Results-based Management and
NSW SENIOR EXECUTIVE SERVICE
NSW SENIOR EXECUTIVE SERVICE NSW DEPARTMENT OF EDUCATION AND TRAINING Position Description POSITION DETAILS Position Title: Reports to: Location: Directorate: Chief Financial Officer Deputy Director-General,
A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division
A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose
NSW BOARDING ACCOMODATION CALCULATOR USER GUIDELINES
NSW BOARDING ACCOMODATION CALCULATOR USER GUIDELINES ORIGINALLY PREPARED FOR NSW DEPARTMENT OF HOUSING IN MAY 2007 BY HILL PDA. AMENDED JULY 2010 BY HOUSING NSW 1 WHAT IS THE BOARDING ACCOMMODATION CALCULATOR?
IUCN Project Budgeting Guidelines
IUCN Project Budgeting Guidelines Version: 14 February 2014 Issued by: Chief Financial Officer Contents 1. Definition... 2 2. Purpose... 2 3. Budget principles :... 2 4. Budget types... 3 5. Budget structure...
New car. Lower tax. CarePLUS. novated. a salary packaging option. for healthcare and emergency services employees
New car. Lower tax. CarePLUS. novated car leasing a salary packaging option for healthcare and emergency services employees a message from the managing director Thank you for taking the time to find out
Capitalisation of Software
The Auditor-General Audit Report No.14 2010-11 Performance Audit Australian Bureau of Statistics Civil Aviation Safety Authority IP Australia Australian National Audit Office Commonwealth of Australia
The Transport Business Cases
Do not remove this if sending to pagerunnerr Page Title The Transport Business Cases January 2013 1 Contents Introduction... 3 1. The Transport Business Case... 4 Phase One preparing the Strategic Business
SUPPLEMENTARY GREEN BOOK GUIDANCE
SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance
CAPITAL PLANNING GUIDELINES
CAPITAL PLANNING GUIDELINES 1. INTRODUCTION... 2 2. EXTENSION OF EXISTING INFRASTRUCTURE PROJECTS... 2 3. NEW CAPITAL PROJECTS... 2 4. MINIMUM INFORMATION REQUIRED... 3 5. PREPARATORY WORK... 3 5.1 NEEDS
Management of Business Support Service Contracts
The Auditor-General Audit Report No.37 2004 05 Business Support Process Audit Management of Business Support Service Contracts Australian National Audit Office Commonwealth of Australia 2005 ISSN 1036
A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF WHOLE-OF-LIFE COSTING
A QUICK REFERENCE GUIDE FOR ELECTED OFFICIALS AND STAFF WHOLE-OF-LIFE COSTING A This booklet is a quick reference guide to help you to: nn understand the purpose and benefits of applying the fundamental
INTERNATIONAL STANDARD
INTERNATIONAL STANDARD IEC 60300-3-3 Second edition 2004-07 Dependability management Part 3-3: Application guide Life cycle costing IEC 2004 Copyright - all rights reserved No part of this publication
2 COMMENCEMENT DATE 5 3 DEFINITIONS 5 4 MATERIALITY 8. 5 DOCUMENTATION 9 5.1 Requirement for a Report 9 5.2 Content of a Report 9
PROFESSIONAL STANDARD 300 VALUATIONS OF GENERAL INSURANCE CLAIMS INDEX 1 INTRODUCTION 3 1.1 Application 3 1.2 Classification 3 1.3 Background 3 1.4 Purpose 4 1.5 Previous versions 4 1.6 Legislation and
1 JULY 2015. Investment Guide INDUSTRY, CORPORATE AND PERSONAL DIVISIONS
1 JULY 2015 Investment Guide INDUSTRY, CORPORATE AND PERSONAL DIVISIONS Your investment choice TWUSUPER was established in 1984 as the Industry SuperFund for people in transport and logistics. By understanding
The Gateway Review Process
The Gateway Review Process The Gateway Review Process examines programs and projects at key decision points. It aims to provide timely advice to the Senior Responsible Owner (SRO) as the person responsible
All staff dealing with fixed assets must comply with the policies and procedures that relate to fixed assets.
Fixed Assets Policy Purpose The purpose of the policy is to define fixed assets, the policy of capitalising expenditure at fair value and effectively controlling such assets (including contributed assets).
Managing construction procurement risks
CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: [email protected]
HELP Interest Rate Options: Equity and Costs
HELP Interest Rate Options: Equity and Costs Bruce Chapman and Timothy Higgins July 2014 Abstract This document presents analysis and discussion of the implications of bond indexation on HELP debt. This
Asset Liability Management for Australian Life Insurers Anton Kapel Zac Roberts
Asset Liability Management for Australian Life Insurers Anton Kapel Zac Roberts Copyright 2006, the Tillinghast Business of Towers Perrin. All rights reserved. A licence to publish is granted to the Institute
Chapter 7. (PMBOK Guide)
Chapter 7 Project Cost Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case
The Human Capital Management Systems Business Case A Checklist to assist agencies developing a business case Final version for release Human Capital Management See more at psc.nsw.gov.au/hcm Index - Business
Registrar of Community Housing 5. Financial Viability
5. Financial Viability Version 2.0 WWW.RCH.NSW.GOV.AU The Registration Process 1 Published by The 2010 This work is copyright. It may be produced in whole or in part for study or training purposes subject
COMPOUND INTEREST AND ANNUITY TABLES
COMPOUND INTEREST AND ANNUITY TABLES COMPOUND INTEREST AND ANNUITY TABLES 8 Percent VALUE OF AN NO. OF PRESENT PRESENT VALUE OF AN COM- AMORTIZ ANNUITY - ONE PER YEARS VALUE OF ANNUITY POUND ATION YEAR
Implementing an Electronic Document and Records Management System. Checklist for Australian Government Agencies
Implementing an Electronic Document and Records Management System Checklist for Australian Government Agencies Acknowledgments The checklist for implementing an electronic document and records management
Time Value of Money. Critical Equation #10 for Business Leaders. (1+R) N et al. Overview
Time Value of Money Critical Equation #10 for Business Leaders (1+R) N et al. Overview The time value of money is fundamental to all aspects of business decision-making. Consider the following: Would you
1. The purpose of this paper is to discuss the assessment of whether a contract contains a lease and does not discuss:
IASB Agenda ref 3A STAFF PAPER May 2014 REG FASB IASB Meeting Project Paper topic Leases Definition of a Lease CONTACT(S) Sarah Geisman [email protected] +44 (0)20 7246 6464 Patrina Buchanan [email protected]
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Project Assessment Framework Cost-benefit analysis
Project Assessment Framework Cost-benefit analysis July 2015 Component of the Project Assessment Framework (PAF) This document forms part of the Project Assessment Framework, as outlined below. Overarching
Transportation Asset Management
Transportation Asset Management The Role of Engineering Economic Analysis Presented by: Eric Gabler Economist, Office of Asset Management Federal Highway Administration Introduction The mission of the
UNSOLICITED PROPOSALS
UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY
9. GOVERNANCE. Policy 9.8 RECORDS MANAGEMENT POLICY. Version 4
9. GOVERNANCE Policy 9.8 RECORDS MANAGEMENT POLICY Version 4 9. GOVERNANCE 9.8 RECORDS MANAGEMENT POLICY OBJECTIVES: To establish the framework for, and accountabilities of, Lithgow City Council s Records
MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question.
Survey of Macroeconomics, MBA 641 Fall 2006, Quiz 4 Name MULTIPLE CHOICE. Choose the one alternative that best completes the statement or answers the question. 1) The central bank for the United States
Capital Works Management Framework
POLICY DOCUMENT Capital Works Management Framework Policy for managing risks in the planning and delivery of Queensland Government building projects Department of Public Works The concept of the asset
Project Management Guidebook
METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple
Standard 1. Governance for Safety and Quality in Health Service Organisations. Safety and Quality Improvement Guide
Standard 1 Governance for Safety and Quality in Health Service Organisations Safety and Quality Improvement Guide 1 1 1October 1 2012 ISBN: Print: 978-1-921983-27-6 Electronic: 978-1-921983-28-3 Suggested
LIFE INSURANCE AND WEALTH MANAGEMENT PRACTICE COMMITTEE AND GENERAL INSURANCE PRACTICE COMMITTEE
LIFE INSURANCE AND WEALTH MANAGEMENT PRACTICE COMMITTEE AND GENERAL INSURANCE PRACTICE COMMITTEE Information Note: Discount Rates for APRA Capital Standards Contents 1. Status of Information Note 3 2.
SEER for IT Detailed Overview
SEER for IT Detailed Overview Andy Robinson Galorath SEER : Empowering Estimation, Planning and Control Since 1988 Outline SEER for IT brief overview Estimation Features Demonstration Reporting with SEER
APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES
APPENDIX B: FINANCIAL PLANNING AND CONTROL OF RESOURCES 1 PERFORMANCE PLANS 1.1 The key controls for performance plans are: (a) to ensure that all relevant plans are produced and that they are consistent
ICT Benchmarking: Better Practice Roadmap
ICT Benchmarking: Better Practice Roadmap PART 1 VERSION 1.0 ICT Benchmarking: Better Practice Roadmap 1 Licensing The Department of Finance and Deregulation is licensed to use, reproduce, adapt, modify,
CHAPTER 4. The Time Value of Money. Chapter Synopsis
CHAPTER 4 The Time Value of Money Chapter Synopsis Many financial problems require the valuation of cash flows occurring at different times. However, money received in the future is worth less than money
FINANCIAL SERVICES TRAINING PACKAGE FNB99
FINANCIAL SERVICES TRAINING PACKAGE FNB99 This is Volume 12 of a 13-volume set. This volume should not be used in isolation but in the context of the complete set for the Financial Services Training Package.
Annex 10: Financial proposal template. Table of contents
UNFCCC/CCNUCC Page 1 Annex 10: Financial proposal template Table of contents Annex 10... 2 10.1 Financial proposal... 2 10.1.1 Vendor s name... 3 10.1.2 Type of engagement... 3 10.1.3 Validity of proposal...
Audit of Sydney Catchment Authority s Asset Management System
Independent Pricing and Regulatory Tribunal Audit of Sydney Catchment Authority s Asset Management System Report to the Minister Water Licensing Compliance Report April 2009 Audit of Sydney Catchment
Capital Planning Guidelines
Capital Planning Guidelines Contents Capital Planning Guidelines... 1 1. INTRODUCTION... 3 2. CAPITAL PROJECTS EVALUATION PROCESS... 3 3. APPRAISAL PROCESS UNDERTAKEN BY DEPARTMENTS... 4 3.1 Extension
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology
2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our
The 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
HKAS 36 Revised June November 2014. Hong Kong Accounting Standard 36. Impairment of Assets
HKAS 36 Revised June November 2014 Hong Kong Accounting Standard 36 Impairment of Assets HKAS 36 COPYRIGHT Copyright 2014 Hong Kong Institute of Certified Public Accountants This Hong Kong Financial Reporting
Small business guide to trade practices compliance programs. April 2006
Small business guide to trade practices compliance programs April 2006 Commonwealth of Australia 2006 ISBN 1 920702 93 8 This work is copyright. Apart from any use permitted under the Copyright Act 1968
Financial Planner of the Year 2015. Financial Plan Guide
Financial Planner of the Year 2015 Financial Plan Guide TABLE OF CONTENTS INTRODUCTION 3 PROFESSIONAL SKILLS 3 PROFESSIONAL RESPONSIBILITY 4 PRACTICE 4 COMMUNICATION 4 COGNITIVE 4 PROFESSIONAL AND LEGAL
GOVERNMENT EXPENDITURE & REVENUE SCOTLAND 2013-14 MARCH 2015
GOVERNMENT EXPENDITURE & REVENUE SCOTLAND 2013-14 MARCH 2015 GOVERNMENT EXPENDITURE & REVENUE SCOTLAND 2013-14 MARCH 2015 The Scottish Government, Edinburgh 2015 Crown copyright 2015 This publication is
AMP CAPITAL BALANCED GROWTH FUND ARSN 089 594 623 DIRECTORS' REPORT AND FINANCIAL REPORT FOR THE FINANCIAL YEAR ENDED 31 DECEMBER 2015
ARSN 089 594 623 DIRECTORS' REPORT AND FINANCIAL REPORT AMP Capital Funds Management Limited 33 Alfred Street, Sydney, NSW 2000 ACN 159 557 721 TABLE OF CONTENTS Page Directors' Report 1-2 Auditor's Independence
9. Time Value of Money 1: Present and Future Value
9. Time Value of Money 1: Present and Future Value Introduction The language of finance has unique terms and concepts that are based on mathematics. It is critical that you understand this language, because
GUIDANCE MATERIAL GUIDANCE ON THE USE OF POSITIVE PERFORMANCE INDICATORS TO IMPROVE WORKPLACE HEALTH AND SAFETY
GUIDANCE MATERIAL GUIDANCE ON THE USE OF POSITIVE PERFORMANCE INDICATORS TO IMPROVE WORKPLACE HEALTH AND SAFETY Office of the Australian Safety and Compensation Council NOVEMBER 2005 IMPORTANT NOTICE The
TAX & SUPERANNUATION:
SECURING RETIREMENT INCOMES TAX & SUPERANNUATION: BENCHMARKING AUSTRALIA AGAINST THE WORLD S BEST RETIREMENT SAVINGS SYSTEMS FEBRUARY 2013 CONTENTS 1 Executive Summary 2 Introduction 3 The variety of retirement
august09 tpp 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper
august09 09-05 Internal Audit and Risk Management Policy for the NSW Public Sector OFFICE OF FINANCIAL MANAGEMENT Policy & Guidelines Paper Preface Corporate governance - which refers broadly to the processes
Retained Fire Fighters Union. Introduction to PRINCE2 Project Management
Retained Fire Fighters Union Introduction to PRINCE2 Project Management PRINCE2 PRINCE stands for: PRojects IN Controlled Environments and is a structured method which can be applied to any size or type
Management Accounting (F2/FMA) September 2015 (for CBE exams from 23 September 2015) to August 2016
Management Accounting (F2/FMA) September 2015 (for CBE exams from 23 September 2015) to August 2016 This syllabus and study guide are designed to help with teaching and learning and is intended to provide
Education about and for S u s ta i n a b i l i t y i n A u s t r a l i a n B u s i n e s s
Education about and for S u s ta i n a b i l i t y i n A u s t r a l i a n B u s i n e s s Schools STAGE 3 An action research program EXECUTIVE SUMMARY The full report explores the outcomes and discusses
Summary of Chapters. Preparation of Lease Determination Worksheet Part B
Summary of Chapters Chapter 1: Chapter 2: Chapter 3: Chapter 4: Chapter 5: Introduction Purpose of this handbook Background information on capital and operating leases Laws and regulations that govern
National Commission for Academic Accreditation & Assessment
National Commission for Academic Accreditation & Assessment Standards for Quality Assurance and Accreditation of Higher Education Programs Evidence of Performance Judgments about quality based on general
A client guide to business valuation engagements and reports.
A client guide to business valuation engagements and reports. Disclaimer This guide is distributed with the understanding that the author, publisher and distributor are not rendering legal, accounting
Investing Report. Comparing 10, 20 and 25 year performance of various investments to December 2010 FULL REPORT / JUNE 2011
Long-Term Investing Report Comparing 10, 20 and 25 year performance of various investments to December 2010 FULL REPORT / JUNE 2011 A research study issued by the ASX and Russell Investments About Us As
THE PROJECT MANAGEMENT KNOWLEDGE AREAS
THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human
University of New South Wales Group. Group leader: John Piggott
University of New South Wales Group Group leader: John Piggott Contributing members: Hazel Bateman, Suzanne Doyle, Sachi Purcal Executive summary - January 2002 One of the economic imperatives of the new
MSD Supply Chain Programme Strategy Workshop
MSD Supply Chain Programme Strategy Workshop Day 2 APPENDIX Accenture Development Partnerships Benchmarking MSD s Current Operating Supply Chain Capability 1.0 Planning 2.0 Procurement 3.0 Delivery 4.0
Guide to Integrated Strategic Asset Management
Guide to Integrated Strategic Asset Management Issue date: 14 November 2011 Acknowledgements This guide is based on the Australasian Procurement and Construction Council Inc. s (APCC) publication, Asset
Managing IT Projects. Chapter 2 The PMI Framework
Managing IT Projects Chapter 2 The PMI Framework The PMI Framework The Project Management Institute,USA is an internationally acclaimed organization Devoted to Creation & sharing of knowledge in the area
