1 Subject: SUBMITTAL OF CONVEYANCE INSTALLATION/ALTERATION PLANS Reference: Denver Fire Code Section Approved: Joseph L. Gonzales, Division Chief, Fire Prevention Division Number: Effective Date: July 1, 2013 Page 1 of 6 GENERAL INFORMATION This policy outlines the requirements for shop/layout drawing submittal for any conveyance installation or alteration in the City and County of Denver. Prior to commencing work, a licensed elevator contractor is required to submit plans for approval and shall obtain an Installation or Alteration Permit from the Denver Fire Department (DFD). WHAT TO SUBMIT New Conveyance Installations The following items must be included in the plan review submittal to the DFD: 1. A completed Application for Plan Review. (See the following pages for specific requirements on different types of applications) 2. Two Complete Sets of Layout Drawing(s). Drawings must be submitted in one (1) hard-copy format and one (1) electronically in PDF format. All drawings must bear the signature and seal of the architect and/or engineer responsible for the conveyance design. Layout drawings shall be dimensional and indicate that the conveyance meets the requirements set out in ASME A or ASME A Any drawings not indicating the proper code edition will be returned immediately to the contractor. Approved layout drawings are the property of the building owner and shall remain on site at all times. The elevator contractor shall provide documentation that the current fire alarm panel is capable of fire recall or that a #3A permit to alter-install a new fire alarm panel has been issued. Documentation stating that material for the car enclosure, enclosure linings and floor coverings (other than metal or glass) conform to the following: a) ASTM E 84, ANSI/UL 723, NFPA 252 for car enclosure and the enclosure lining with a flame spread rating of 0 to 75, and smoke development of 0 to 450. b) ASTM E 648 with a critical radiant flux of not less than 0.45 W/cm 2 for floor covering and underlayment.
2 Number: Effective Date: July 1, 2013 Page 2 of 6 If, at the time of application, the interior car material is unknown, DFD may issue an Initial Installation Permit to install the conveyance. An Alteration Permit must be obtained before the car interior is installed. Layout drawings shall also include the following: (The following code references are to ASME A17.1 current adopted edition): All Elevators (including LU/LA s, dumbwaiters/material lifts): a) Building name, address and conveyance State registration number b) Required clearances and basic dimensions c) Indicate whether a Fire Command Center is present d) Layout of the elevator annunciator panel (if Fire Command Center is present) e) Indicate whether elevator(s) are operational on emergency power (generator); also indicate the sequence of operation and how many elevators can be operated simultaneously f) Primary and alternate floor locations (as determined by DFD) g) Indicate that the Flashing Fire Hat signal conforms to Denver Fire Code amendments h) Indicate that the Fire Emergency Operation conforms to Denver Building Code amendments for pressurized shafts i) Maximum bracket spacing (see 2.23 or 3.23) j) Estimated maximum vertical forces on the guide rails on application of the safety or other retarding device (see 2.23 and or 3.23) k) In the case of freight elevators for Class B or C loading (see ), the horizontal forces on the guiderail faces during loading and unloading, and the estimated maximum horizontal forces in a post-wise direction on the guiderail faces on the application of the safety device (see 2.23 or 3.23) l) Size and linear weight kg/m (lb/ft) of any rail reinforcement, where provided (see 2.23 or 3.23) m) Total static and impact loads imposed on machinery and sheave beams, supports, and floors or foundations (see 2.9) n) Impact load on buffer supports due to buffer engagement at the maximum permissible speed and load (see 8.2.3) o) Total static and dynamic loads from the governor, ropes, and tension system p) Horizontal forces on the building structure stipulated by and
3 Number: Effective Date: July 1, 2013 Page 3 of 6 q) Rated speed and operating speed in the down direction r) Identification of welding in conjunction with work. Hot work permit is required (other than for tack welds) or include in elevator permit scope s) Identification if hoistway is pressurized Electric Elevators (including LU/LA s, dumbwaiters/material lifts): a) Where compensation tie-down is applied (see ), the load on the compensation tie-down supports b) Maximum upward movement (see 2.4.6) Hydraulic Elevators (including LU/LA s, Dumbwaiters/Material Lifts): a) Net vertical load from the elevator system, which includes the total car weight and rated load; plunger, cylinder, and oil; and any structural supports b) Outside diameter and wall thickness of the cylinder, plunger and piping, and the working pressure c) Minimum grade of pipe (ASTM or recognized standard) required to fulfill the installation requirements for pressure piping, or in lieu of a specific grade of pipe, the minimum tensile strength of pipe to be used for the installation (see 3.19) d) Length of the plunger and cylinder e) Clearance between the bottom of the plunger and the bottom head of the cylinder as required by Escalators/Moving Walks Layout drawings shall, in addition to other data, indicate the following: (All references are to ASME A17.1 current adopted edition) a) Building name, address and State registration number b) Whether escalator to be installed indoors or outdoors c) Maximum speed (escalators 100 fpm; moving walks up to 180 fpm depending on angle of inclination) d) Angle of inclination (escalators not to exceed 30 o ; moving walks not to exceed 12 o ) e) Rise and length
4 Number: Effective Date: July 1, 2013 Page 4 of 6 Vertical Platform Lift (VPL) and Inclined Platform Lift (IPL) Layout drawings shall, in addition to other data, indicate the following: (All references are to ASME A18.1 current adopted edition) a) Building name, address and State registration number b) Number for landings (stops). c) Whether the lift is to be installed indoors or outdoors d) Type of drive e) Total travel (not to exceed 14ft, VPL) f) Speed (not to exceed 30ft/min) g) Capacity (not to exceed 750lbs) h) Clear platform width and length (not to exceed 18ft 2 for VPL and 12ft 2 for IPL) i) Type of lift controls j) Power supply Altered Conveyances (all conveyances): A detailed list of the components that are to be altered. A scope of work shall be attached to the permit application form. If the scope of work includes altering of Fire Emergency Operation, the elevator contractor shall provide documentation that the current fire alarm panel is capable of fire recall or that a #3A permit to alter/install a new fire alarm panel has been issued. If the scope of work includes the interior of the car enclosure, documentation as stated above shall be provided. 3. Equipment Manufacturer s Specification Sheets showing that all equipment is listed and labeled for the intended application If any of the above items are missing or incomplete, the review of the plans will not begin until complete information is received. Repair Work Requiring a Permit The following repair work will require a permit and an inspection for the following: (Code references are to ASME A17.1, except item f ) a) Repair a of Speed Governor b) Repair of a Releasing Carrier
5 Number: Effective Date: July 1, 2013 Page 5 of 6 c) Replacement of Suspension Rope(s) d) Replacement of a Speed Governor e) Shortening of Suspension Ropes f) ASME A Replacement of Steel Coated Belt(s) g) Replacement of Governor Rope h) Replacement of Listed/Certified Devices (Devices that may fall under this requirement are included but not limited to hoistway door locking devices and electric contacts, car door contacts and interlocks, hydraulic control valves, escalator steps, fire doors, and electrical equipment.) i) Replacement of a Door Reopening Device j) Repair/Replacement of Hydraulic Valves and Piping k) Replacement of car/counterweight safeties l) Replacement of Brake Components m) Hydraulic Flexible Hoses and Fittings n) Installation/Alteration of hall call fixtures (need to verify that the fire service key switch on the call station and COP match) o) Addition of a security system to control access to floors (need to verify that Fire Emergency Operation will bypass security) Temporary Certificate of Operation If a Temporary Certificate of Operation has been issued a Work Permit must be obtained before the following work can begin: a) Any work involving Fire Service components b) Failed/Witnessed Testing c) Past Due Safety Tests d) Electrical protective safety devices e) Repair/Replacement of 2-way communication system (phone, intercom etc.) f) Suspension Means monitoring device g) Repair/Installation of Door restrictors (where required) Repair permit Temporary Certificate of Operation plans required within 30 days
6 Number: Effective Date: July 1, 2013 Page 6 of 6 FEES New Installations/Replacements $300 per conveyance $350 per conveyance Alterations $150 per conveyance $175 per conveyance Re-Submittal Fees New Installations/Replacements $300 per conveyance $350 per conveyance Alterations $150 per conveyance $175 per conveyance 2nd and subsequent Re-Submittal Fees New Installations/Replacements Alterations Repair Permit Fees $450 per conveyance $250 per conveyance $175 per conveyance Fee for work without a permit Double permit fee All permit fees will be collected when plans are submitted no exceptions. Permit fees are non-refundable. Make checks payable to Manager of Finance. Permit fees cover plan review, QCQA inspection, initial inspection for fire service operation and processing and issuance of certificate of operation. Re-inspection fees for failed fire service operation shall be determined by DFD Systems Acceptance Testing unit. All permit fees will be collected when plans are submitted no exceptions. Permit fees are non-refundable. Make payment to Manager of Finance. WHERE TO SUBMIT All plan documents shall be submitted to: Denver Fire Department Fire Prevention 2 nd Floor 745 W. Colfax Avenue Denver CO TURNAROUND TIME Denver Fire Department s goal for completion of the plan review process is no more than 20 working days; however, we reserve the option of a longer completion time depending upon the complexity and size of the project being reviewed. Remember, the review process does not begin until all components of the submittal are received and complete. END OF DOCUMENT
DEPARTMENT OF CORRECTIONS
Elevator Consulting, LLC. Post Office Box 464 Mequon, WI 53092-0464 Voice/Fax: 262-242-3077 Mobile No: 262-853-1054 E-mail: PerformElevCons@wi.rr.com DEPARTMENT OF CORRECTIONS MILWAUKEE SECURE DETENTION
More informationP.A.L. S SPECIFICATIONS
PART 1- GENERAL 1.1 SCOPE To furnish all labor, materials and equipment necessary or required to complete the installation of the lift as indicated on the Drawings and Specifications. This specification
More informationCOMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES
COMMERCIAL COOKING HOODS, VENTILATION & FIRE SUPPRESSION SYSTEM GUIDELINES AND PROCEDURES These guidelines are to be used for ALL commercial cooking hoods, ventilation systems and related fire suppression
More informationRoped Hydraulic Residential Elevator Specifications
January 1, 2004 Roped Hydraulic Residential Elevator Specifications P.O. Box 749, 5191 Stump Rd., Plumsteadville, PA 18949 Toll Free: 888-443-2800, Phone: 215-766-3380, Fax: 215-766-3385 CONTENTS Part
More informationElevating and Amusement Devices Safety Division Elevating Devices Code Adoption Document - Amendment
Elevating and Amusement Devices Safety Division Elevating Devices Code Adoption Document - Amendment Ref. No.: Date: Rev. No.: 261-13 1 May 1, 2013 Date: September 15, 2013 IN THE MATTER OF: Technical
More informationSECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
More informationSuffolk County Department of Health Services. Division of Environmental Quality
Suffolk County Department of Health Services Division of Environmental Quality Guidelines For the Construction of Storage Areas for Portable Containers ~~~~ Clare B. Bradley, M.D., M.P.H. Suffolk County
More informationWINDOW AND DOOR REPLACEMENT REQUIREMENTS
WINDOW AND DOOR REPLACEMENT REQUIREMENTS Should you have any questions after reading the following information, please call the Building Inspection Department at 651-439-4439 to discuss the topics of concern.
More informationInterfacing Elevators with Fire Alarm and Sprinklers
Interfacing Elevators with Fire Alarm and Sprinklers IEEE Atlanta Chapter May 15, 2006 Brian K Fabel, PE Agenda Today s Codes NFPA, ASME, IBC/IFC Conflicts/Issues Tomorrow s Codes? Applicable Codes NFPA
More informationMODIFIED INDUSTRY STANDARDS FOR ELEVATORS AND CONVEYING SYSTEMS
MODIFIED INDUSTRY STANDARDS FOR ELEVATORS AND CONVEYING SYSTEMS CHAPTER K1 MODIFICATIONS TO ASME A17.1-2000, SAFETY CODE FOR ELEVATORS AND ESCALATORS K101.1 General. As referenced by Chapter 30 of the
More informationV1504 Vertical Platform Lift OWNER S MANUAL
V1504 Vertical Platform Lift OWNER S MANUAL (To Be Retained by Owner After Installation by Authorized Savaria Dealer) Part No. 000692 03-m12-2013 2 IMPORTANT Ensure that only an authorized Savaria Dealer
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More informationSECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
More informationMERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS
MERCER ISLAND FIRE DEPARTMENT FIRE COMMERCIAL SPRINKLER STANDARDS COMMERCIAL FIRE SPRINKLER SYSTEMS Page 1-5 SCOPE: Fire sprinkler systems in the City of Mercer Island shall meet the criteria as set forth
More informationHow To Make A House Safe
1 RESIDENTIAL Screen Enclosures Orange County Residential Code Compliance Alternative design method for screen enclosures R301.2.1.1.3 PLAN REVIEW Engineered plans must state that the Alternative Design
More informationSECTION 14 20 10 - FREIGHT & PARKING GARAGE ELEVATORS PART I - GENERAL
SECTION 14 20 10 - FREIGHT & PARKING GARAGE PART I - GENERAL 1.1 SECTION INCLUDES [NOTE to AE: The following lists requirements that are specific to freight elevators. These requirements are in addition
More informationV1504 Vertical Platform Lift OWNER S MANUAL
V1504 Vertical Platform Lift OWNER S MANUAL (To Be Retained by Owner After Installation by Authorized Savaria Dealer) Part No. 000692 01-m03-2016 2 IMPORTANT Ensure that only an authorized Savaria Dealer
More informationFIRE ALARM SYSTEM PLAN SUBMITTAL CHECKLIST
FIRE ALARM SYSTEM PLAN SUBMITTAL CHECKLIST All fire alarm system plan submittals must include this Fire Alarm System Plan Submittal Checklist. PLAN APPROVAL - No work shall be performed until plans are
More informationSECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS
SECTION 08360 SECTIONAL OVERHEAD DOORS 521 SERIES ALUMINUM SECTIONAL OVERHEAD DOORS Display hidden notes to specifier by using Tools / Options / View / Hidden Text. On newer versions of Microsoft Word
More informationHYDRAULIC FREIGHT ELEVATOR PACKAGES
HYRAULIC FRIGHT LVATOR PACKAGS Leistritz offers its customers a complete selection of freight elevators to meet a wide range of heavy-duty, freight handling applications. In addition to the cylinders,
More informationMOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION
MOBILE FIRE - RESCUE DEPARTMENT FIRE CODE ADMINISTRATION Fire Pump Plan Review 2009 International Fire Code and NFPA 20 Date of Review / / BLD201 - Project Address: Project Name: Contractor s Business
More informationServices Enclosures and Protected Shafts - Maintaining Compartmentation
Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping
More informationPlanning Information. Passenger and Freight Elevators.
A company of ThyssenKrupp Elevator Thyssen Aufzüge tk This planning information will give you an overview of the most important planning criteria of passenger and freight elevators. However you should
More informationFire Pump Plan Review March 2010
Fire Pump Plan Review March 2010 Date of Review: / / Permit Number: Business/Building Name: Address of Project: Designer Name: Designer s Phone: Contractor: Contractor s Phone: Occupancy Classification:
More informationrpsa FIRE PROTECTION ENGINEERS www.rpsa-fire.com
www.-fire.com R.P. SCHIFILITI ASSOCIATES, INC. P.O. Box 297 Reading, MA 01867-0497 USA 781.944.9300 Fax / Data 781.942.7500 Telephone Elevator Fire Safety: Elevator Recall and Elevator Power Shutdown Disclaimer:
More informationThe replacement or modification of existing windows shall comply with the following requirements:
City of La Habra Heights Building Division 1245 N. Hacienda Road La Habra Heights, CA 90631 Office: (562) 694-6302 ext. 228 Fax: (562) 690-5010 WINDOW REPLACEMENT 2010 CALIFORNIA RESIDENTIAL CODE (CRC)
More informationLighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering
More informationRecommendations to improve the safety of existing lifts
Recommendations to improve the safety of existing lifts Lift & Escalator Industry Association Lift Safety an introduction Lifts are amongst the very few modes of transport available for continuous unsupervised
More information2014 Limited Plan Submittal Checklist
City of Aurora Public Works Department WET AND DRY CHEMICAL HOOD SUPPRESSION SYSTEM 2014 Limited Plan Submittal Checklist Building Division 15151 E. Alameda Parkway, Ste 2400 Aurora, CO 80012 303-739-7420
More informationOur professional elevator support staff and emergency elevator repair technicians are available to serve you 24 hours a day, seven days a week.
Applied Elevator Service, Sales and Installation Applied Elevator delivers unparalleled customer service, proactive maintenance programs and dependability that will exceed your expectations. With more
More informationCLARK COUNTY FIRE DEPARTMENT Fire Hazard & Prevention Services
CLARK COUNTY FIRE DEPARTMENT Fire Hazard & Prevention Services 575 E. Flamingo Road, Las Vegas, NV 89119 (702) 455-7316 FAX (702) 455-7347 105.8a-6.1 TITLE: FIRE ALARM SYSTEM REQUIREMENTS SCOPE: This guideline
More informationLOADING DOCK EQUIPMENT. A. Section 03100 - Concrete Forms and Accessories: Placement of anchors into concrete.
LOADING DOCK EQUIPMENT PART 1 GENERAL 1.1 SECTION INCLUDES A. Loading dock equipment of the following types: 1. Dock lifts. 2. Control stations. 1.2 RELATED SECTIONS A. Section 03100 - Concrete Forms and
More informationSECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)
SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2
More informationSingle Family Residential Basement Finish
How to Use This Guide Building Guide Pottawattamie County Planning & Development Department Building & Safety Division Single Family Residential Basement Finish Provide two (2) sets of plans and complete
More informationMechanical Installation
Page -1-1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and precommissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer s
More informationLIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc.
LIFE SAFETY UPDATE FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. The purpose of this update is as follows: Remind all state
More informationAssessment of Elevator and Escalator Maintenance & Repair Program Final Elevator Audit Submission Bethesda Station - Escalator A09X04 (Station)
Bethesda Station - Escalator A09X04 (Station) Ride Quality Test Results The Parametricoder is a time and displacement encoding system that measures mechanical performance characteristics on escalators.
More informationFinance and Administration Department 907 Billy Mitchell Blvd. P: (210) 228-1022 Fire Alarm Permit Application
PERMIT FEE: $ Finance and Administration Department 907 Billy Mitchell Blvd. P: (210) 228-1022 Fire Alarm Permit Application PAYMENT TYPE: Check Credit Card Charge to Job #: (Please complete all of the
More informationGeneral Fire Code Requirements Within Commercial Tenant Spaces
FIRE DEPARTMENT in cooperation with Scope: General Fire Code Requirements Within Commercial Tenant Spaces This handout is designed to assist owners, architects, contractors and others in understanding
More informationSpray Booth Guideline
Department of Development Service 135 North D Street, Perris CA. 92570 Phone: (951) 443-1029 Fax: (951) 943-3293 PURPOSE The intent of this guideline is to provide the information necessary to ensure that
More informationCity of Bettendorf Fire Alarm System Requirements
City of Bettendorf Fire Alarm System Requirements Section 907 of the 2009 Edition of the International Fire Code (IFC) and Section 10-7-3 of the Municipal Code provide fire alarm requirements. IFC Section
More informationPLAN SUBMITTAL REQUIREMENTS FOR SPRAY BOOTHS AND SPRAYING ROOMS EXTINGUISHING SYSTEMS
January 1997 PLAN SUBMITTAL REQUIREMENTS FOR SPRAY BOOTHS AND SPRAYING ROOMS EXTINGUISHING SYSTEMS 1.0 PERMIT 1.1 After receipt of a Building Permit from the City of San Jose Building Department, submit
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationWalking and Working Surface Checklist:
Walking and Working Surfaces Purpose: This information is presented to improve the level of safety in our operations, and to inform you that we will comply with the OSHA Standard 29 CFR 1910.23. Responsibility:
More informationSECTION 807 PUMP STATION REHABILITATION
SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but
More informationCode of Standard Practice for Timber Frame Structures
TFEC 2-2013 Code of Standard Practice for Timber Frame Structures August 2013 Preface This Code is intended to represent a reasonable consensus of what constitutes ordinary and acceptable practice within
More informationCardok Sàrl CP37 CH-1295 Tannay Switzerland Phone: 0041 22 77 66 051 info@cardok.com
CARDOK CARLIFT Fast access to underground garages Fast, Silent, Discreet, Design, High-Tech Installation to replace an access ramp on private property Dimensions: (Built to measure, all dimensions can
More informationFIRE ALARM SYSTEMS PERMIT APPLICATION, PLAN SUBMITTAL, DESIGN, INSTALLATION AND INSPECTION REQUIREMENTS Effective Date: January, 2011
Office of the Fire Marshal 1.0 PERMITS FIRE ALARM SYSTEMS PERMIT APPLICATION, PLAN SUBMITTAL, DESIGN, INSTALLATION AND INSPECTION REQUIREMENTS Effective Date: January, 2011 1.1 To acquire an installation
More informationCity of Columbus Department of Building and Zoning Services
City of Columbus Department of Building and Zoning Services Introduction This manual is designed to provide you, the contractor, owner or design professional with a step-by-step guide to our process, beginning
More informationSTANDARD FOR NON-FIRE RATED ROLLING DOORS
ANSI/DASMA 203-2004 AMERICAN NATIONAL STANDARD STANDARD FOR NON-FIRE RATED ROLLING DOORS Door & Access Systems Manufacturers Association, International Sponsor: 1300 Sumner Ave Cleveland, Ohio 44115-2851
More informationRancho Cucamonga Fire Protection District Prevention Bureau Standard
Rancho Cucamonga Fire Protection District Prevention Bureau Standard Title: Fire Alarm and Monitoring Systems Standard # 9-3 Effective: May 2002 Number of Pages: 7 Revised: January 2014 INTENT The intent
More informationLoss Prevention Standard
Loss Prevention Standard : ISSUE 3.0 Requirements for the LPCB Approval and Listing of Companies Undertaking the Maintenance and Repair of Doorsets, Shutters, and Active Smoke/Fire Barriers This standard
More informationEXCAVATOR SAFETY TRAINING
EXCAVATOR SAFETY TRAINING INSPECTION CHECKLIST INSPECTION AREA INSPECTION RESULTS Sat. Unsat. N/A Comments Carrier & Car Body Rotation system Tracks Rollers Frame, welds, bolts Drive system Upper Structure
More informationCLEAR-DIVISIONS CENTERFOLD
CLEAR-DIVISIONS CENTERFOLD Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS CENTERFOLD moveable The yellow highlighted areas in
More informationITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
More informationEXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS
EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS 1. SCOPE 1.1 This specification covers the type, physical properties and dimensions of Expanded Polystyrene Insulation Board intended for use
More information2880 International Circle Colorado Springs, CO 80910 Telephone 719-327-2880. Executive Summary. 2011 Pikes Peak Regional Building Code Revisions
2880 International Circle Colorado Springs, CO 80910 Telephone 719-327-2880 Web address www.pprbd.org Executive Summary 2011 Pikes Peak Regional Building Code Revisions October 21 st 2015 This document
More informationProduct Guide Specification
Reef Industries, Inc. 9209 Almeda Genoa Rd. Houston, Texas 77075 Toll Free (800) 231-6074 Phone (713) 507-4251 Fax (713) 507-4295 Web Site www.reefindustries.com E-Mail ri@reefindustries.com Product Guide
More informationSWIMMING POOL, SPA, & HOT TUB GUIDELINES
SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015
More informationRESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS
RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional
More informationCLEAR-DIVISIONS VARIOFOLD
CLEAR-DIVISIONS VARIOFOLD Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS VARIOFOLD moveable The yellow highlighted areas in the
More informationThe Passenger and Freight Elevator Regulations, 2003
PASSENGER AND FREIGHT ELEVATOR, 2003 P-4 REG 2 1 The Passenger and Freight Elevator Regulations, 2003 being Chapter P-4 Reg 2 (effective January 1, 2004) as amended by Saskatchewan Regulations 80/2008.
More informationPIPELINE / WIRE LINE PROCESS INSTRUCTIONS
PIPELINE / WIRE LINE PROCESS INSTRUCTIONS Licensing Process: 1. Once the application package is received by Jones Lang LaSalle Brokerage, Inc. (JLL), the application and drawing will be forwarded to the
More informationFIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.
Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's
More informationArapahoe County Residential Water Heater Installation and Inspection Guide
Arapahoe County Residential Water Heater Installation and Inspection Guide The attached handout is designed to be a general permit submittal and inspection guide covering most installation instances, however
More informationSECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM
SECTION 23 81 03 - PACKAGED ROOFTOP AIR CONDITIONING UNITS NON-CUSTOM PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Packaged rooftop air conditioning unit (5 tons and smaller). 2. Roof curb. 1.2
More informationHERNANDO COUNTY FIRE ALARM GUIDELINES
HERNANDO COUNTY FIRE ALARM GUIDELINES To be used for all commercial building fire alarm system plan review. The procedures set forth in this document are the minimum requirements necessary to ensure a
More informationThis handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.
Basement Finishing Guide Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org
More informationMedicine Hat Fire Department. Special Event Requirements. medicinehat.ca/fire. August 2012
Medicine Hat Fire Department Special Event Requirements August 202 medicinehat.ca/fire The following is a standard guide for event organizers to ensure occupant safety and compliance with the Alberta Fire
More informationCLEAR-DIVISIONS APERTO
CLEAR-DIVISIONS Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS moveable glass wall system. The yellow highlighted areas in the
More informationCCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
More informationCOMMISSIONING OF FIRE ALARM SYSTEMS
COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference
More informationArea of Rescue Assistance Communication System ADA Code Applicable excerpts:
Area of Rescue Assistance Communication System ADA Code Applicable excerpts: CONTENTS (Guidelines and Definitions) Page 1 Area of Rescue Assistance Requirements Page 2 Emergency Communication Equipment
More informationProject Report. Structural Investigations Hotel del Sol Yuma, Arizona
Project Report Structural Investigations Yuma, Arizona Prepared by: 2619 Spruce Street Boulder, CO 80302 303-444-3620 Prepared for: Principle Engineering Group, Inc. 833 East Plaza Circle, Suite 100 Yuma,
More informationQuality Control and Quality Assurance Guide
Quality Control and Quality Assurance Guide Bridge Division, Design Section October 2013 Table of Contents Chapter 1 About this Guide... 3 Chapter 2 Goals and Objectives... 5 Chapter 3 Participants...
More informationBuilding Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11
Building Construction and Development in Norristown: A User s Guide to the Land Development and Building Permit Process 1/25/11 Introduction Constructing new commercial or residential space can be a complicated
More informationSmall Business Permit Service
Small Business Permit Service Building Permit Requirements For a Unit Finish or Interior Alteration Industrial, Commercial or Institutional Occupancies Building Permit Application The following documents
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationCity of San Diego, CWP Guidelines
PART 1 -- GENERAL SECTION 08520-1.1 WORK OF THIS SECTION City of San Diego, CWP Guidelines A. The WORK of this Section includes providing aluminum windows with frames, bracing, glazing attachments, screens,
More informationC I T Y O F S E L M A F I R E D E P A R T M E N T
C I T Y O F S E L M A F I R E D E P A R T M E N T Informational Bulletin Regarding Residential Fire Sprinkler Systems for One and Two Family Homes: Frequently Asked Questions ADMINISTRATIVE PROVISIONS:
More informationLOUISVILLE FIRE PROTECTION DISTRICT 895 West Via Appia, Louisville, Colorado 80027 303-666-8809
LOUISVILLE FIRE PROTECTION DISTRICT 895 West Via Appia, Louisville, Colorado 80027 303-666-8809 Contractor s Checklist and Installation Guide TABLE OF CONTENTS Fire Protection Narrative........... 3 Fire
More informationKITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS
St. Louis County Department of Public Works Division of Code Enforcement KITCHEN AND BATH REMODELING BUILDING PERMIT REQUIREMENTS This guideline is intended to provide the homeowner/contractor with the
More informationDIAMOND Retractable Rodding Robot Model SPRAYROD-R
2004-12-21 2 1 (23) DIAMOND Retractable Rodding Robot Model SPRAYROD-R 2004-12-21 2 2 (23) Table of contents 1 TECHNICAL DESCRIPTION...4 1.1 MAIN DETAILS...5 1.2 COMPONENTS DESCRIPTION...5 1.2.1 Pneumatic
More informationSARATOGA FIRE DISTRICT EARLY WARNING FIRE ALARM SYSTEM STANDARDS AND REQUIRMENTS CONTENTS
SARATOGA FIRE DISTRICT EARLY WARNING FIRE ALARM SYSTEM STANDARDS AND REQUIRMENTS CONTENTS I. APPLICATION AND DEFINITIONS 1.01 Authorization for Standards 1.02 Application of Standards 1.03 Definitions
More informationHAWAII ADMINISTRATIVE RULES TITLE 12 DEPARTMENT OF LABOR AND INDUSTRIAL RELATIONS SUBTITLE 8 DIVISION OF OCCUPATIONAL SAFETY AND HEALTH CHAPTER 232
HAWAII ADMINISTRATIVE RULES TITLE 12 DEPARTMENT OF LABOR AND INDUSTRIAL RELATIONS SUBTITLE 8 DIVISION OF OCCUPATIONAL SAFETY AND HEALTH CHAPTER 232 PERSONNEL HOISTS 12-232-1 Definitions 12-232-2 General
More informationBold items are particular to the City of Euless
EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 2/12 Fire Chief Wes Rhodes Fire Marshal Paul Smith EFD-FMO 3-2 2009 International Fire & Building Code as Amended NFPA Standards Adopted
More informationExcerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationMETHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationCITY AND COUNTY OF DENVER
CITY AND COUNTY OF DENVER DEPARTMENT OF GENERAL SERVICES P URCHASING D IVISION www.denvergov.org/purchasing WELLINGTON E. WEBB MUNICIPAL OFFICE BUILDING 201 WEST COLFAX AVE., DEPT. 304 DENVER, CO 80202
More informationHealth Chapter 420-5-22 ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE
Health Chapter 420-5-22 ALABAMA STATE BOARD OF HEALTH ALABAMA DEPARTMENT OF PUBLIC HEALTH ADMINISTRATIVE CODE CHAPTER 420-5-22 SUBMISSION OF PLANS AND SPECIFICATIONS FOR HEALTH CARE FACILITIES TABLE OF
More informationRAPID RESPONSE Model RSV-1 Residential Shut-Off Valve, 1 Inch and 2 Inch (DN25 and DN50) for Dual-Purpose Residential Water Supply General Description
Worldwide Contacts www.tyco-fire.com RAPID RESPONSE Model RSV-1 Residential Shut-Off Valve, 1 Inch and 2 Inch (DN25 and DN50) for Dual-Purpose Residential Water Supply General Description The TYCO RAPID
More informationMinistry of the Environment Decree on accessible building
F1 THE FINNISH BUILDING REGULATIONS 1 Barrier-free Building Regulations and 2005 Ministry of the Environment Decree on accessible building adopted in Helsinki on the 1 st of October 2004 In accordance
More informationcity of edmonds development information
#B17 city of edmonds development information Commercial Kitchen Hood & Hood Fire Suppression System Permit Submittal Requirements PERMIT REQUIRED: CODES: FEES: A Commercial Kitchen Hood Mechanical Permit
More informationTopics of the Presentation
Drill Rig Safety Topics of the Presentation Personnel safety and monitoring PPE Health (Drugs and Alcohol) Drill Rig operation Safe set up procedures Safe operation of machine Safety related accidents
More informationCONSTRUCTION FIRE SAFETY PLANNING GUIDELINES
CONSTRUCTION FIRE SAFETY PLANNING GUIDELINES Review the following information pertaining to Construction Fire Safety Planning: B.C. Building Code Sections 8.1 up to and including Subsection 8.2.3 B.C.
More informationDoes Wall Township require an inspection by the building department on resale of a home?
Selling your home Does Wall Township require an inspection by the building department on resale of a home? No. We do not require a Certificate of Continued Occupancy on the resale of home. A Smoke Detector,
More informationCITY OF PHILADELPHIA DEPARTMENT OF LICENSES AND INSPECTIONS ANNUAL CERTIFICATION FOR FIRE ALARM SYSTEMS
CITY OF PHILADELPHIA DEPARTMENT OF LICENSES AND INSPECTIONS ANNUAL CERTIFICATION FOR FIRE ALARM SYSTEMS PROPERTY ADDRESS (BRT Address Required) TESTING CONTRACTOR (Name and Address) License No. ANNUAL
More informationBUILDING SAFETY UNIT
POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential
More information