SESSION 4 PLANNING THE PROJECT PROJECT PLANNING DEFINITIONS
|
|
|
- Luke Jacobs
- 9 years ago
- Views:
Transcription
1 SSSION 4 PLNNIN TH PROJT PROJT PLNNIN Scope planning Time planning ost planning Human resource planning Procurement planning Quality planning ommunication planning INITIONS The project plan is a list of activities that need to be accomplished to meet the project objectives. The project schedule is the project plan plotted against a timeline. n event is an identifiable single point in time in the project life cycle. milestone is a significant event in the project life cycle.
2 TOOLS THT SSIST IN PLNNIN Historical Reports xperience Handbooks Standards and procedures hecklists Model plans PLNNIN THNIQUS Manual barcharts ritical path analysis Line of balance Last schedule ritical chain MNUL RHRTS () asy to read Shows the time scale Shows the activities on a single barchart asy to monitor and schedule Manual updating is required No logic links are shown on the barchart ifficult to maintain and update on large projects ifficult to track changes on the barchart
3 MNUL RHRTS () RITIL PTH NLYSIS () The method of planning and controlling projects by recording their interdependence in a diagrammatic form. Two methods are commonly used namely: ctivity on arrow ctivity on node/precedence diagramming method RITIL PTH NLYSIS () With the arrow on node system the activity is shown by arrows, with a node at each end (normally a circle). The length and direction of the arrow have no meaning. The arrow only implies logic. ummy activities must be added to complete logic. 3
4 RITIL PTH NLYSIS (3) With the activity on node system the activity is represented by boxes or nodes. The length and direction of the arrow have no meaning. The arrow only implies logic. Relationships or lags can be included in the logic diagram. RITIL PTH NLYSIS (3) ctivity on arrow xcavation oundation ctivity on node xcavation oundation RITIL PTH NLYSIS (4) The default relationship that is normally shown on the precedence diagram is finish to start. The following relationships can however also be taken into account: Start to start inish to finish Start to finish 4
5 RITIL PTH NLYSIS (6) Start to start xcavation oundation n example would be the excavation and placing of concrete. You do not have to complete all the excavations before casting the concrete. In this instance the start to start lag could be e.g. 3 days after you have started on the excavation you would pour start pouring concrete. RITIL PTH NLYSIS (7) inish to finish ommissioning section ommissioning section n example would be the commissioning of a number of sections. The important issue is not when the commissioning is started but when they are completed and you would e.g. have these happening 3 days after each other. RITIL PTH NLYSIS (5) Start to finish Install chillers Install pumps n example would be when a specific time frame has been determined for a set of activities like for example the period a crane will be on site. That implies that activity will start when the crane arrives but that activity must be completed by the time the crane leaves site. 5
6 VNTS O USIN P Shows the interdependency between activities Prevents unrealistic planning Identifies the critical activities on the project etermines the shortest time to completion Shows available float for non-critical activities llows what if scenarios P TRMINOLOY () arly start the earliest possible time an activity can begin based on network logic. arly finish the earliest possible time an activity can finish based on network logic. Late start the latest possible time an activity can begin without delaying project completion. Late finish the latest possible time an activity can finish without delaying project completion. P TRMINOLOY () ritical path is the longest path through the network which determines the shortest time in which the project can be completed. Total float is the amount of free time that is allocated to a string of activities. ree float is the amount of time an activity can use up without delaying the project. 6
7 LIN O LN This is a planning technique that is suited for repetitive projects like mass housing, road construction, pipe line installation of rail installation. The number of units are plotted on one axis and the duration of the project on the other. LIN O LN LN PROUTION THNIQUS The concept of lean production which originated within the production environment is being adopted and applied within the construction industry. This method of production has however lead to a different approach to planning and has lead to the development of new planning techniques like last planner and critical chain. 7
8 PRPR TH PROJT TIM SHUL USIN P () ormulate the project scope statement stablish the project phases evelop the work breakdown structure Identify the project activities etermine the activity duration alculate the resources required to complete the activities PRPR TH PROJT TIM SHUL USIN P () etermine the logic links and cconstruct the logic diagram Verify the logic diagram etermine the project duration Verify the project duration onstruct a resource histogram pply resource scheduling ORMULT TH PROJT SOP STTMNT This step was covered in detail in the session on scope planning. The outcome of this step is to clearly identify what needs to be delivered. 8
9 STLISH TH PROJT PHSS () This is also referred to as determining the project life cycle. The project can be broken down into smaller manageable sections which link together like activities. The titles given to these phases will vary from project to project and industry to industry. The generic titles given to these phases are initiation phase, implementation phase and closeout phase. STLISH TH PROJT PHSS () The phases commonly used on built environment projects are feasibility phase, design phase, procurement phase, construction phase, commissioning phase and operational phase. Traditionally these phases were sequenced in series however project managers have been overlapping these phases due to time constraints placed on projects by clients. VLOP TH WORK RKOWN STRUTUR The development of the WS can follow a number of conventions but should however ensure that it allows for easy project integration. The different project plans cannot be considered in isolation and therefore need to be integrated against a common basic structure. The work breakdown structure is the most suited techniques to use within the project environment. 9
10 INTIY TH PROJT TIVITIS () Project activities can be identified from the WS. This information can also be obtained from historical reports, experience or the people who will be carrying out the activities. Once identified the activities should be listed in an activity list. Once an activity list has been developed it can also serve as the default list for future project. INTIY TH PROJT TIVITIS - TIVITY LIST () ode ctivity epend uration Resources Remarks Wake up in the morning Have a shower Make coffee Make breakfast at and drink breakfast et dressed Leave varsity for INTIY TH PROJT TIVITIS (3) The level of detail decided on for each activity is important at this stage. This is were the WS can be useful..g. making coffee can be broken down into four smaller activities namely get ingredients, add to cup, add water and stir. It is also important to identify whether any other methods are available to complete the activity. In construction a method statement is normally drawn up to document these alternatives. 0
11 TRMIN TH TIVITY URTION The activity duration is a prediction based on current knowledge at the time the activity is expected to take place under normal circumstances. The duration can be calculated based on known industry specific production outputs..g. a bricklayer can lay 800 bricks in one day. If we know we that bricks are in the project we can determine that the project will take 00 days to complete. LULT TH RSOUR RQUIRMNTS () Resources relate to material, manpower, equipment etc. Initially we need to assume that we have unlimited resources available for the project. We do however need to find out what the resource availability is to determine the realistic duration for an activity. If e.g. 5 bricklayers are available we can reduce the duration from 00 days to 0 days. LULT TH RSOUR RQUIRMNTS () Normal resource production outputs need to be considered initially. nticipated absenteeism also needs to be considered. ll existing commitments need to be taken into account. Space limitations need to be considered diminishing returns. apacity of equipment needs to be considered.
12 TRMIN TH PROJT LOI () This step requires the application of strict logic as all we are trying to determine is what is standing in the way of the commencement of an activity. It is therefore necessary to question standard practices to determine whether new or alternatives ways of carrying out the activity are available. TRMIN TH PROJT LOI () ode ctivity epend uration Resources et out of bed Start 5 minutes Have a shower 5 minutes Make coffee 3 minutes Make breakfast minutes at and drink breakfast et dressed, 0 minutes 6 minutes Leave for varsity, 5 minutes ONSTRUT TH LOI IRM
13 VRIY TH LOI IRM The logic diagram must be check to ensure the logic built into it is correct. It is possible that certain project constraints might have been overlooked when focusing on specific activities. Once the verification process has been completed you can move on to the next step and calculate the project duration. These steps are normally integrated when using a PM planning package. TRMIN TH PROJT URTION () We use the term forward pass to define the process of calculating the early start and early finish dates for all activities. arly start + activity duration = early finish We use the term backward pass to define the process of calculating the late start and late finish dates for all activities. Late finish - activity duration = late start TRMIN TH PROJT URTION TIVITY LOK () Late start Late finish escription loat arly start uration arly finish 3
14 TRMIN TH PROJT URTION - TH ORWR PSS LULTION (3) TRMIN TH PROJT URTION - TH KWR PSS (4) TRMIN TH PROJT URTION - TH RITIL PTH (6) You will notice that path - -has no free time. This therefore implies that this path has no float and is called the critical path. The critical path can and will change over the duration of the project. It is important to check the critical path after each update the master programme. It is possible to have more that one critical path on the project. 4
15 TRMIN TH PROJT URTION - TH RLY STRT RHRT (7) VRIY TH PROJT URTION t this stage you can verify whether the project time objective will be achieved. You can also verify whether all of the milestone dates will be achieved. ll other key operations need to be verified at this stage to ensure that the times calculated nee the project objectives. s you can see it is much easier to verify the project duration using a barchart. ONSTRUT TH RSOUR HISTORM () 3 3 5
16 6 ONSTRUT TH RSOUR HISTORM () ONSTRUT TH RSOUR HISTORM (3) ONSTRUT TH RSOUR HISTORM (4) 3
17 ONSTRUT TH RSOUR HISTORM (5) The amount of free float available needs to be considered. omplexity of tasks need to be considered as you do not want to delay an activity and then find it running late. The number of resources available need to be considered. The impact of the change on other activities. LLOTIN TH LNR Once the project duration has been calculated it needs to be superimposed on the project calendar. The calendar can be a 5, 6 or even 7 day working week. When allocating the calendar holidays and other non working days need to be taken into account. ertain PM packages allow for the use of multicalendars on a project. UPTIN TH SHUL Project progress must be monitored on a regular basis. This can be weekly monthly or even daily. Progress is recorded as percentage work complted or percentage of work still to be complted. The actual work completed must be compared with the work scheduled for the period and any deviation must be analysed to determine the impact of the change on the project. revised schedule must be produced and distributed to all concerned. 7
18 PROJT PRORSS T N O PRIO ctivity Scheduled 00% 60% 00% 00% 0% 0% 0% ctual 00% 40% 00% One day late 0% 0% 0% UPTIN TH SHUL UPTIN TH SHUL 8
19 PROJT PRORSS T N O PRIO ctivity Scheduled 00% 60% 00% 00% 0% 0% 0% ctual 00% 40% One day late One day late Not started 0% 0% ONSTRUT LOI NTWORK () ctivity uration ependency Start Start 4 3, SOLUTION XMPL STRT
20 ONSTRUT LOI NTWORK () ctivity uration ependency Start , SOLUTION XMPL 0 S T R T I N I S H SOLUTION XMPL 3 0
21 RINS IN LIRRY () urke, (Rory), Project management planning and control techniques, Promatec International, 999. ooke, (rian), onstruction planning, programming and control / 998 Lockyer. K..(Keith erald) Project management and project network techniques / 996. Woodgate, Harry Samuel Planning by network : 977 Hoare, Henry Ronald Project management using network analysis / 973 urman. RINS IN LIRRY () Peter J. Precedence networks for project planning and control / 97 Ogander, Mats. The practical application of project planning by network techniques / 97 International ongress for Project Planning by Network nalysis(969 :msterdam, Netherlands) Project planning by network analysis / 969 Moder, Joseph J. Project management with PM and PRT / 964 RRNS urke, (Rory), Project management planning and control techniques, Promatec International, 999. Scheduling systems with focus on practical concerns in repetitive projects, I-Tung Yang & P.. Ioannou, onstruction Managemenent and conomics, July 004, Volume.
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM)
PROJECT EVALUATION REVIEW TECHNIQUE (PERT) AND CRITICAL PATH METHOD (CPM) Project Evaluation Review Technique (PERT) and Critical Path Method (CPM) are scheduling techniques used to plan, schedule, budget
Project Scheduling. Introduction
Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total
Project Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
Project Planning Tools. GANTT Chart. Chapter 7 Project Planning. GANTT Chart (Figure 7.3) CPM Chart (Figure 7.12) PERT Chart (Figure 7.
Project Planning ools hapter 7 Project Planning Lecture 2 Project Planning nd Management ools GN hart (Figure 7.) PM hart (Figure 7.2) P hart (Figure 7.5) GN: eveloped by Henry Gantt PM: ritical Path Method
12 CRITICAL PATH ANALYSIS
1 RTL PT NLYSS hapter 1 ritical Path nalysis Objectives fter studying this chapter you should be able to construct activity networks; be able to find earliest and latest starting times; be able to identify
Resources Management
Resources Management. Introduction s we have seen in network scheduling, the basic inputs to criticalpath analysis are the individual project activities, their durations, and their dependency relationships.
Use project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
Goals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
Project Scheduling by PERT/CPM
Project Scheduling by PERT/PM Reference ooks: nderson, Sweeney, and Williams, N INTROUTION TO MNGEMENT SIENE, QUNTITTIVE PPROHES TO EISION MKING, th edition, West Publishing ompany,99 Hamdy. Taha, OPERTIONS
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Large Scale Systems Design G52LSS
Large Scale Systems esign 52LSS Lecture 6 Project Scheduling With PRT Project Scheduling PRT iagrams onstructing Pert iagrams Learning outcomes: describe the purpose and steps of project scheduling within
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
Systems Analysis and Design
Systems Analysis and Design Slides adapted from Jeffrey A. Hoffer, University of Dayton Joey F. George, Florida State University Joseph S. Valacich, Washington State University Modern Systems Analysis
Mastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
Critical Path Analysis & PERT Charts (taken from www.business.com.
Critical Path Analysis & PERT Charts (taken from www.business.com. - Planning and scheduling more complex projects Critical Path Analysis and PERT are powerful tools that help you to schedule and manage
02 Project planning. There are two approaches to identifying the components of a project: productbased and work- or activity-based.
C H A P T E R T W O 02 Project planning LEARNING OUTCOMES When you have completed this chapter you should be able to demonstrate an understanding of the following: project deliverables and intermediate
Operational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
PERFORMANCE REPORTING USING SCHEDULE COMPRESSION INDEX
PROR RPORT US SU OPRSSO X *ahaa ussein and **Osama oselhi epartment of uilding, ivil, nvironmental ngineering, oncordia University 1455 e aisonneuve lvd. W. ontreal, Q anada 3 18 (*orresponding author:
Programmes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
Time Planning and Control
TOBIC 4 TIM SCLD NTWORK 1 June 3013 Time Planning and Control Time-Scaled Network G404 NGINRING MNGMNT 1 TOBIC 4 TIM SCLD NTWORK 1 June 3013 Processes of Time Planning and Control 1. Visualize and define
Notes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS
33 CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS 4.1 BASICS OF LINEAR SCHEDULING The LSM is a graphical technique in which the locations or the length of the linear project is indicated
CRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
Problems, Methods and Tools of Advanced Constrained Scheduling
Problems, Methods and Tools of Advanced Constrained Scheduling Victoria Shavyrina, Spider Project Team Shane Archibald, Archibald Associates Vladimir Liberzon, Spider Project Team 1. Introduction In this
Precedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
CRITICAL-PATH ANALYSIS FOR NETWORK SCHEDULING
CRITICAL-PATH ANALYSIS FOR NTWORK SCHULING From studying this section, you will be able to: - Perform CPM and PM analyses for AOA and AON networks; - Calculate the early / late times that an activity can
Chapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
NE-50413B Mastering Microsoft Project 2010
NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Mastering Microsoft Project 2013
Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals
8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days
3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: [email protected] Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:
CPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP [email protected] Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led
Mastering Microsoft Project 2010 50413B; 3 days, Instructor-led Course Description This three-day instructor-led course provides students with the knowledge and skills plan and manage projects using Microsoft
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
Test Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
Time Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
Basic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Topic: The easiest way to calculate Critical Path, Total Float, Free Float, Early Start, Early Finish, Late Start, and Late Finish.
Hot Topics & hallenges Time Management Topic: The easiest way to calculate ritical Path, Total Float, Free Float, Early, Early, Late, and Late. Presenter: Sohel khter, PMP, N,ISMS PMP and Six Sigma instructor,
Leaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
Test Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
Time Management. Herb Pollard III
Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas
CHAPTER FIVE THE PROJECT SCHEDULE
CHAPTER FIVE THE PROJECT SCHEDULE THE 2012 ULTIMATE PROJECT MANAGEMENT MANUAL HERE S WHAT YOU LL LEARN Primary reasons for scheduling the project Ten characteristics of a good schedule Common scheduling
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S
SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...
Module 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
Leaving Certificate Technology. Project Management. Student Workbook
Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage
MnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
WORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Module 11. Software Project Planning. Version 2 CSE IIT, Kharagpur
Module 11 Software Project Planning Lesson 29 Staffing Level Estimation and Scheduling Specific Instructional Objectives At the end of this lesson the student would be able to: Identify why careful planning
PROGRAMMING TECHNIQUES. Chapter 5(Part 2)
PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate
Project Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
MATERIALS: The Contractor shall provide the latest version of Primavera SureTrak software.
DESCRIPTION: '108-01, Start and Progress of Work, is hereby amended to require that the Contractor furnish and participate in a computerized CPM (critical path method) network scheduling system. The purpose
Software Development & Education Center. Microsoft Office 2010. (Microsoft Project 2010)
Software Development & Education Center Microsoft Office 2010 (Microsoft Project 2010) Mastering Microsoft Project 2010 About This Course This three-day instructor-led course provides students with the
Errata. 133 Figure 5-15 Corrected the output for 8.3 Control Quality to read verified deliverables
Errata NOTE: The following errata only pertain to the first printing of the PMBOK Guide Fifth Edition. In order to verify the print run of your book (or PDF), refer to the bottom of the copyright page
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
Chapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
The Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
Cambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
Critical Path Analysis
Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe
LECTURE 5: SOFTWARE PROJECT MANAGEMENT. Software Engineering Mike Wooldridge
LECTURE 5: SOFTWARE PROJECT MANAGEMENT Mike Wooldridge 1 Introduction The software crisis of the 1960s and 1970s was so called because of a string of high profile software project failures: over budget,
Basic Concepts. Project Scheduling and Tracking. Why are Projects Late? Relationship between People and Effort
Basic s Project Scheduling and Tracking The process of building a schedule for any case study helps really understand how it s done. The basic idea is to get across to break the software project into well-defined
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
Collaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
SECTION 01311 - CONSTRUCTION SCHEDULE B. Part 1 - General... 1. 1.01 Work Included... 1. 1.02 Related Requirements... 1. 1.03 Reference Standards...
SECTION 01311 - CONSTRUCTION SCHEDULE B CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement
Dashboards and Reporting for Program Management
MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
Priori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Spec. Standard: 11/27/06 01310-1 Revision: 11/27/06
SECTION 01310 CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. Construction Progress Schedule: The CONTRACTOR shall submit a detailed work progress schedule showing all work in a graphic format suitable
Guidance on Critical Path Analysis
Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
SE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
Project Management Dr. James A. Bednar
Project Management Dr. James A. Bednar [email protected] http://homepages.inf.ed.ac.uk/jbednar SAPM Spring 2006: Project Management 1 Project Management A project is a temporary endeavour to produce
Project Planning. Lecture Objectives. Basic Reasons for Planning. Planning. Project Planning and Control System. Planning Steps
Project Planning What are you going to do in the project? Lecture Objectives To discuss the tasks in planning a project To describe the tools that can be used for developing a project plan To illustrate
Scheduling 101 CPM Basics. Phoenix Project Management Systems, LLC www.phoenixcpm.com
Scheduling 101 CPM Basics Phoenix Project Management Systems, LLC www.phoenixcpm.com Scheduling 101 CPM Basics Getting Started with CPM This guide is intended as an introduction to the Critical Path Method
MnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE
PN 107-01/16/2009 - CRITICAL PATH METHOD PROGRESS SCHEDULE A. General. The progress schedule required for this project is the critical path method schedule (CPM schedule). The Contractor shall designate
Mastering Microsoft Project 2013
This three-day, instructor-led course is intended for individuals who are interested in expanding their knowledge base and technical skills about Microsoft Project. The course begins with the basic concepts
Practical Aspects of Construction Scheduling
Practical Aspects of Construction Scheduling AACE Atlanta, GA April 16, 2013 Mark G Cundiff, PSP Vice President, Hill International The Preparation of the Estimate involves planning and consideration of
Resource Planning and Scheduling. CSTM 462 Resource Loading Fall 2012
Resource Planning and Scheduling CSTM 462 Resource Loading Fall 2012 Schedule October 01/02- Resource Loading Lecture October 03/04- ASiMI Lab Week of October 08- No Class Download Software-Download instructions
Figure out the early start and early finish. Early start. Early finish
Figure out the early start and early finish oming up with the float for each activity is useful, but you can actually do better! When you have a long critical path, but the other paths in your network
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.
Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June
5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
MSc Project Planning
MSc Project Planning Dr Paul Brunn 4 th February 2009 Project Planning and Control Intro to General Methods Some simple examples How to plan and complete an MSc Dissertation project EPS Graduate Education
ME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
added to the task, using Project, it will automatically calculate the schedule each time a new resource is added.
Chapter 3 Effort Driven Task Type By now, you will be getting sick of my repetition of the effort driven formula: Resource Units X Duration = Work I make no apologies, as it needs to be engraved in the
Should I Resource Load My Schedule?
Should I Resource Load My Schedule? th Annual International Integrated Program Management Conference November -, Copyright All Rights Reserved The Goals Of Project Management: to make the most effective
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
