DEFINING %COMPLETE IN MICROSOFT PROJECT
|
|
|
- Marshall Gaines
- 10 years ago
- Views:
Transcription
1 CelersSystems DEFINING %COMPLETE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP, PMI-SP, MVP For Addtonal Informaton about Earned Value Management Systems and reportng, please contact: CelersSystems, Inc East Mra Loma Ave, Sute 43 Anahem, CA Unted States Telephone: or E 3 V 8 M 6 S 7 [Intentonally Blank]
2 CelersSystems Contents Table of Contents Introducton Background Percent Complete Calcuaton Types Percent Complete Percent Work Complete Physcal Percent Complete Analyss Duraton Analyss (Detal Tasks)... 7 Equatons Equaton Duraton Based Percent Complete... 3 Equaton 2 Percent Work Complete... 5 Equaton 3 Physcal Percent Complete... 6 Fgures Fgure Percent Complete Screen Shot... 4 Fgure 2 Resource Sheet... 4 Fgure 3 Resource Loaded Schedule Showng Total Work... 4 Fgure 4 Work Profle (Task Usage Vew)... 4 Fgure 5 Percent Work Complete Screen Shot... 5 Fgure 6 Costed Resource Loadng... 5 Fgure 7 Physcal Percent Complete Screen Shot... 6 Fgure 8 Graphcal Illustratons of Three Methods of Percent Complete... 7 Tables Table Expected Values of Percent Complete... 7
3 CelersSystems INTRODUCTION The key to understandng percent complete s to recognze the value s a fracton. To obtan a fracton, dvde two numbers. Ths mples the user knows whch two numbers to dvde: Brcks lad dvded by total brcks requred, wages pad dvded by total budget, work hours spent dvded by total work hours estmated. Wthout knowng whch two numbers to dvde, a percent complete s just a number for msnterpretaton by others. The real questons here are: If I am on schedule, how many brcks should I have lad? How many dollars n wages should I have pad? How many work hours should have been expended? How much cost should I have ncurred? 2 BACKGROUND Mcrosoft Project contans three measures of %Complete. Many users of the software want to know: If they are on schedule, what should be the values calculated by each of the measures of percent complete. The three measures are: Percent Complete (%Complete), Percent Work Complete (%Work Complete), and Physcal % Complete. Addtonal measures are avalable f created by the user. 3 PERCENT COMPLETE CALCUATION TYPES 3. Percent Complete The default method of measurng %Complete by Mcrosoft Project s based on actvty duraton, a 0 day actvty s 40% Complete at the close of busness on the 4 th work day from the start date of the actvty. Mcrosoft Project wll ndcate ths task s late f the value for %Complete s less than the expected value as of the status date. Ths nformaton s vewable n ether the status ndcator or status columns. The formula to roll up %Complete for summary level tasks, and eventually the entre project s gven by: = tasks = % Complete * Duraton = task = Duraton Equaton Duraton Based Percent Complete Usng Fgure below, Mcrosoft Project wll calculate the percent complete as follows: Page 3 of CelersSystems Telephone
4 CelersSystems Fgure Percent Complete Screen Shot %Complete = [(50%*(5 days) + 30%*(7 days) + 65%*(3 days)]/(5 days + 7 days + 3 days) %Complete = % Mcrosoft Project wll round to the nearest whole nteger, 44%. 3.2 Percent Work Complete Percent complete based on the number of work hours completed s another measure calculated by Mcrosoft Project. For ths purpose, two resources wll be loaded to the tasks wth work as shown. Fgure 2 Resource Sheet Fgure 3 Resource Loaded Schedule Showng Total Work The man-hour profle for work-hours s loaded wth the majorty of the work n the frst three days: Fgure 4 Work Profle (Task Usage Vew) Percent work complete s calculated n accordance wth an effort based weghtng: Page 4 of CelersSystems Telephone
5 CelersSystems % WorkComplete = tasks % WorkComplete * Work = = = tasks Equaton 2 Percent Work Complete Usng the same percentages as the orgnal example, the calculaton becomes: %Work Complete= [50%*(40) + 30%*(4) + 65%*(2)]/[40+4+2] %Work Complete=48.48% Mcrosoft Project confrms the calculaton: = Work Fgure 5 Percent Work Complete Screen Shot 3.3 Physcal Percent Complete When the desred unt of measure s Physcal Percent Complete, a baselne s requred and the calculaton s based on the dollar costs nvolved. In ths case, the cost of the project s spread as shown below: Fgure 6 Costed Resource Loadng For the moment, the Project Status Date wll be set far nto the future, past the last day of the project. In ths case, although any measure of the three measures of percent complete should ndcate a behnd schedule condton, the Physcal % Complete appears n the fgure below: Page 5 of CelersSystems Telephone
6 CelersSystems Fgure 7 Physcal Percent Complete Screen Shot The equaton used by Mcrosoft Project depends on the dollar value of the work budgeted and s shown below: Physcal% Complete = tasks Physcal% Complete * BAC = = = tasks Equaton 3 Physcal Percent Complete Note: BAC s Budget At Complete, Total Cost, or Baselne Cost. The detals of the calculaton are: Physcal Percent Complete = [50%($3,440)+30%($204)+65%(228)]/[$4872] Physcal Percent Complete = 46% Further analyss regardng calculaton of Physcal % Complete s n a later secton of ths paper. Specfcally, what happens when the status date s before or durng the perod of performance of tasks? 4 ANALYSIS The prevous secton descrbes three methods of determnng percent complete. In each case, the value clamed for percent complete was numercally dentcal for the three dscrete tasks (50%, 30% and 65%, respectvely). The weghted value of the calculaton produced a dfferent result n each case at the summary level. In the example, the values are close. However, consder what mght happen f there was a large dscrepancy n the amount of work assgned to the tasks, or, f the costs of the resources were vastly dfferent from each other. Further, the measures of percent complete (Duraton, Work, and Physcal) all represent dfferent thngs. Although the possblty does exst that the measures could theoretcally be equal under certan crcumstances, the general case s the measures wll not be numercally equal. If a project marches along on schedule the table below wll show the cumulatve % Complete for each calculaton type: = BAC Page 6 of CelersSystems Telephone
7 CelersSystems Table Expected Values of Percent Complete Method vs. Day %Complete %Work Complete Physcal % Complete Graphcally the results are dfferent for each method of percent complete as a functon of tme: %Complete %Work Complete Physcal % Complete Fgure 8 Graphcal Illustratons of Three Methods of Percent Complete 4. Duraton Analyss (Detal Tasks) By defnton, the duraton percent complete of a task grows only wth the passage of tme and s always on schedule. Snce t s duraton based measurement, unless the task has not started and needs to be delayed, the user should always clam the tasks to be as scheduled when updatng the duraton based percent complete. Where the calculaton wll vary s when the user makes updates to the remanng work and remanng duraton felds. Ths author has no understandng of the concept a user can clam any duraton based %complete and then provde remanng duraton estmates that are nconsstent wth the percent complete provded. In the case of Page 7 of CelersSystems Telephone
8 CelersSystems duraton based percent complete, t s best to adjust remanng duraton (or remanng work) and let the software calculate the percent complete. If the user provdes remanng work or duraton greater than calculated by the program, the %Complete value wll regress. If the user revses the remanng duraton/work to be less than calculated by the program, the %Complete ncreases. Dependng on the reportng rules n place on the program, t may be a volaton of reportng rules to allow the percent complete to decrease from a pror reportng perod. If an estmator beleves t wll take three days to pant 24 feet of fence, the planned profle wll be 33% per day. If at the end of the frst day the panter clams four addtonal days are needed, then the job s /5 = 20% duraton complete ( day of actual duraton, 4 days of remanng duraton). What the user really wants to know s how the 20% complete calculaton compares to the 33% complete that s expected (the baselne). Indeed, what duraton percent complete s expected for the purpose of ths comparson as of the status date (end of day )? The answer s 33% and the panter met 20/33=6% of expectaton (39% behnd schedule). What can be done n a case such as ths? If the task s orgnally assgned as fxed unts wth one resource, then management needs to decde how to recover from the gven stuaton. There appears to be several choces: Clearly the panter has re-estmated the job, perhaps because of ncreased ntellgence ganed durng the performance of Day. The panter provdes a revsed estmate to complete so the cost of the job ncreases (from 24 hours to 40 hours). Management must decde f the addtonal cost wll be absorbed or passed on to the customer, and, f the addtonal duraton s acceptable to all the stakeholders. Substtute a resource and assgn the task to someone who can complete the job wthn the remanng baselne duraton (2 remanng days). Ths may change costs. Change technology, perhaps the panter can use spray equpment as opposed to a brush and complete on the baselne fnsh day (Day 3). Ths may also mpact cost. Man-load the task wth addtonal workers (perhaps at ncreased cost) to save the baselne duraton, or at least compress duraton. It s a matter for management to reconcle estmatng practces that 24 manhours were estmated for the job when the performng organzaton provded a hgher estmate once the task was underway and more nformaton was known. Of course ths scenaro that sooner or later Page 8 of CelersSystems Telephone
9 CelersSystems the maxmum amount of productve resources wll have already been added to the job and addng more resources wll decrease productvty. Page 9 of CelersSystems Telephone
10 For nformaton regardng Earned Value Management Systems, Program Offce functonalty and schedulng management, please contact: CelersSystems 3335 East Mra Loma Ave, Sute 43 Anahem, Calforna Toll Free n the Unted States ext 706 Outsde the Unted States: CelersSystems
An Alternative Way to Measure Private Equity Performance
An Alternatve Way to Measure Prvate Equty Performance Peter Todd Parlux Investment Technology LLC Summary Internal Rate of Return (IRR) s probably the most common way to measure the performance of prvate
benefit is 2, paid if the policyholder dies within the year, and probability of death within the year is ).
REVIEW OF RISK MANAGEMENT CONCEPTS LOSS DISTRIBUTIONS AND INSURANCE Loss and nsurance: When someone s subject to the rsk of ncurrng a fnancal loss, the loss s generally modeled usng a random varable or
Time Value of Money Module
Tme Value of Money Module O BJECTIVES After readng ths Module, you wll be able to: Understand smple nterest and compound nterest. 2 Compute and use the future value of a sngle sum. 3 Compute and use the
Simple Interest Loans (Section 5.1) :
Chapter 5 Fnance The frst part of ths revew wll explan the dfferent nterest and nvestment equatons you learned n secton 5.1 through 5.4 of your textbook and go through several examples. The second part
Module 2 LOSSLESS IMAGE COMPRESSION SYSTEMS. Version 2 ECE IIT, Kharagpur
Module LOSSLESS IMAGE COMPRESSION SYSTEMS Lesson 3 Lossless Compresson: Huffman Codng Instructonal Objectves At the end of ths lesson, the students should be able to:. Defne and measure source entropy..
THE DISTRIBUTION OF LOAN PORTFOLIO VALUE * Oldrich Alfons Vasicek
HE DISRIBUION OF LOAN PORFOLIO VALUE * Oldrch Alfons Vascek he amount of captal necessary to support a portfolo of debt securtes depends on the probablty dstrbuton of the portfolo loss. Consder a portfolo
Can Auto Liability Insurance Purchases Signal Risk Attitude?
Internatonal Journal of Busness and Economcs, 2011, Vol. 10, No. 2, 159-164 Can Auto Lablty Insurance Purchases Sgnal Rsk Atttude? Chu-Shu L Department of Internatonal Busness, Asa Unversty, Tawan Sheng-Chang
Solution: Let i = 10% and d = 5%. By definition, the respective forces of interest on funds A and B are. i 1 + it. S A (t) = d (1 dt) 2 1. = d 1 dt.
Chapter 9 Revew problems 9.1 Interest rate measurement Example 9.1. Fund A accumulates at a smple nterest rate of 10%. Fund B accumulates at a smple dscount rate of 5%. Fnd the pont n tme at whch the forces
Traffic-light a stress test for life insurance provisions
MEMORANDUM Date 006-09-7 Authors Bengt von Bahr, Göran Ronge Traffc-lght a stress test for lfe nsurance provsons Fnansnspetonen P.O. Box 6750 SE-113 85 Stocholm [Sveavägen 167] Tel +46 8 787 80 00 Fax
APPLICATION OF PROBE DATA COLLECTED VIA INFRARED BEACONS TO TRAFFIC MANEGEMENT
APPLICATION OF PROBE DATA COLLECTED VIA INFRARED BEACONS TO TRAFFIC MANEGEMENT Toshhko Oda (1), Kochro Iwaoka (2) (1), (2) Infrastructure Systems Busness Unt, Panasonc System Networks Co., Ltd. Saedo-cho
To manage leave, meeting institutional requirements and treating individual staff members fairly and consistently.
Corporate Polces & Procedures Human Resources - Document CPP216 Leave Management Frst Produced: Current Verson: Past Revsons: Revew Cycle: Apples From: 09/09/09 26/10/12 09/09/09 3 years Immedately Authorsaton:
M-applications Development using High Performance Project Management Techniques
M-applcatons Development usng Hgh Performance Project Management Technques PAUL POCATILU, MARIUS VETRICI Economc Informatcs Department Academy of Economc Studes 6 Pata Romana, Sector, Bucharest ROMANIA
A DYNAMIC CRASHING METHOD FOR PROJECT MANAGEMENT USING SIMULATION-BASED OPTIMIZATION. Michael E. Kuhl Radhamés A. Tolentino-Peña
Proceedngs of the 2008 Wnter Smulaton Conference S. J. Mason, R. R. Hll, L. Mönch, O. Rose, T. Jefferson, J. W. Fowler eds. A DYNAMIC CRASHING METHOD FOR PROJECT MANAGEMENT USING SIMULATION-BASED OPTIMIZATION
Depreciation of Business R&D Capital
Deprecaton of Busness R&D Captal U.S. Bureau of Economc Analyss Abstract R&D deprecaton rates are crtcal to calculatng the rates of return to R&D nvestments and captal servce costs, whch are mportant for
The Development of Web Log Mining Based on Improve-K-Means Clustering Analysis
The Development of Web Log Mnng Based on Improve-K-Means Clusterng Analyss TngZhong Wang * College of Informaton Technology, Luoyang Normal Unversty, Luoyang, 471022, Chna [email protected] Abstract.
INVESTIGATION OF VEHICULAR USERS FAIRNESS IN CDMA-HDR NETWORKS
21 22 September 2007, BULGARIA 119 Proceedngs of the Internatonal Conference on Informaton Technologes (InfoTech-2007) 21 st 22 nd September 2007, Bulgara vol. 2 INVESTIGATION OF VEHICULAR USERS FAIRNESS
CHOLESTEROL REFERENCE METHOD LABORATORY NETWORK. Sample Stability Protocol
CHOLESTEROL REFERENCE METHOD LABORATORY NETWORK Sample Stablty Protocol Background The Cholesterol Reference Method Laboratory Network (CRMLN) developed certfcaton protocols for total cholesterol, HDL
How To Understand The Results Of The German Meris Cloud And Water Vapour Product
Ttel: Project: Doc. No.: MERIS level 3 cloud and water vapour products MAPP MAPP-ATBD-ClWVL3 Issue: 1 Revson: 0 Date: 9.12.1998 Functon Name Organsaton Sgnature Date Author: Bennartz FUB Preusker FUB Schüller
Section 5.4 Annuities, Present Value, and Amortization
Secton 5.4 Annutes, Present Value, and Amortzaton Present Value In Secton 5.2, we saw that the present value of A dollars at nterest rate per perod for n perods s the amount that must be deposted today
Number of Levels Cumulative Annual operating Income per year construction costs costs ($) ($) ($) 1 600,000 35,000 100,000 2 2,200,000 60,000 350,000
Problem Set 5 Solutons 1 MIT s consderng buldng a new car park near Kendall Square. o unversty funds are avalable (overhead rates are under pressure and the new faclty would have to pay for tself from
Section 5.3 Annuities, Future Value, and Sinking Funds
Secton 5.3 Annutes, Future Value, and Snkng Funds Ordnary Annutes A sequence of equal payments made at equal perods of tme s called an annuty. The tme between payments s the payment perod, and the tme
Institute of Informatics, Faculty of Business and Management, Brno University of Technology,Czech Republic
Lagrange Multplers as Quanttatve Indcators n Economcs Ivan Mezník Insttute of Informatcs, Faculty of Busness and Management, Brno Unversty of TechnologCzech Republc Abstract The quanttatve role of Lagrange
Traffic State Estimation in the Traffic Management Center of Berlin
Traffc State Estmaton n the Traffc Management Center of Berln Authors: Peter Vortsch, PTV AG, Stumpfstrasse, D-763 Karlsruhe, Germany phone ++49/72/965/35, emal [email protected] Peter Möhl, PTV AG,
IMPACT ANALYSIS OF A CELLULAR PHONE
4 th ASA & μeta Internatonal Conference IMPACT AALYSIS OF A CELLULAR PHOE We Lu, 2 Hongy L Bejng FEAonlne Engneerng Co.,Ltd. Bejng, Chna ABSTRACT Drop test smulaton plays an mportant role n nvestgatng
Joe Pimbley, unpublished, 2005. Yield Curve Calculations
Joe Pmbley, unpublshed, 005. Yeld Curve Calculatons Background: Everythng s dscount factors Yeld curve calculatons nclude valuaton of forward rate agreements (FRAs), swaps, nterest rate optons, and forward
Small pots lump sum payment instruction
For customers Small pots lump sum payment nstructon Please read these notes before completng ths nstructon About ths nstructon Use ths nstructon f you re an ndvdual wth Aegon Retrement Choces Self Invested
Activity Scheduling for Cost-Time Investment Optimization in Project Management
PROJECT MANAGEMENT 4 th Internatonal Conference on Industral Engneerng and Industral Management XIV Congreso de Ingenería de Organzacón Donosta- San Sebastán, September 8 th -10 th 010 Actvty Schedulng
Using Series to Analyze Financial Situations: Present Value
2.8 Usng Seres to Analyze Fnancal Stuatons: Present Value In the prevous secton, you learned how to calculate the amount, or future value, of an ordnary smple annuty. The amount s the sum of the accumulated
Calculation of Sampling Weights
Perre Foy Statstcs Canada 4 Calculaton of Samplng Weghts 4.1 OVERVIEW The basc sample desgn used n TIMSS Populatons 1 and 2 was a two-stage stratfed cluster desgn. 1 The frst stage conssted of a sample
The OC Curve of Attribute Acceptance Plans
The OC Curve of Attrbute Acceptance Plans The Operatng Characterstc (OC) curve descrbes the probablty of acceptng a lot as a functon of the lot s qualty. Fgure 1 shows a typcal OC Curve. 10 8 6 4 1 3 4
Updating the E5810B firmware
Updatng the E5810B frmware NOTE Do not update your E5810B frmware unless you have a specfc need to do so, such as defect repar or nstrument enhancements. If the frmware update fals, the E5810B wll revert
Reporting Forms ARF 113.0A, ARF 113.0B, ARF 113.0C and ARF 113.0D FIRB Corporate (including SME Corporate), Sovereign and Bank Instruction Guide
Reportng Forms ARF 113.0A, ARF 113.0B, ARF 113.0C and ARF 113.0D FIRB Corporate (ncludng SME Corporate), Soveregn and Bank Instructon Gude Ths nstructon gude s desgned to assst n the completon of the FIRB
How Much to Bet on Video Poker
How Much to Bet on Vdeo Poker Trstan Barnett A queston that arses whenever a gae s favorable to the player s how uch to wager on each event? Whle conservatve play (or nu bet nzes large fluctuatons, t lacks
7.5. Present Value of an Annuity. Investigate
7.5 Present Value of an Annuty Owen and Anna are approachng retrement and are puttng ther fnances n order. They have worked hard and nvested ther earnngs so that they now have a large amount of money on
Answer: A). There is a flatter IS curve in the high MPC economy. Original LM LM after increase in M. IS curve for low MPC economy
4.02 Quz Solutons Fall 2004 Multple-Choce Questons (30/00 ponts) Please, crcle the correct answer for each of the followng 0 multple-choce questons. For each queston, only one of the answers s correct.
ANALYZING THE RELATIONSHIPS BETWEEN QUALITY, TIME, AND COST IN PROJECT MANAGEMENT DECISION MAKING
ANALYZING THE RELATIONSHIPS BETWEEN QUALITY, TIME, AND COST IN PROJECT MANAGEMENT DECISION MAKING Matthew J. Lberatore, Department of Management and Operatons, Vllanova Unversty, Vllanova, PA 19085, 610-519-4390,
Extending Probabilistic Dynamic Epistemic Logic
Extendng Probablstc Dynamc Epstemc Logc Joshua Sack May 29, 2008 Probablty Space Defnton A probablty space s a tuple (S, A, µ), where 1 S s a set called the sample space. 2 A P(S) s a σ-algebra: a set
Staff Paper. Farm Savings Accounts: Examining Income Variability, Eligibility, and Benefits. Brent Gloy, Eddy LaDue, and Charles Cuykendall
SP 2005-02 August 2005 Staff Paper Department of Appled Economcs and Management Cornell Unversty, Ithaca, New York 14853-7801 USA Farm Savngs Accounts: Examnng Income Varablty, Elgblty, and Benefts Brent
The Current Employment Statistics (CES) survey,
Busness Brths and Deaths Impact of busness brths and deaths n the payroll survey The CES probablty-based sample redesgn accounts for most busness brth employment through the mputaton of busness deaths,
How To Get A Tax Refund On A Retirement Account
CED0105200808 Amerprse Fnancal Servces, Inc. 70400 Amerprse Fnancal Center Mnneapols, MN 55474 Incomng Account Transfer/Exchange/ Drect Rollover (Qualfed Plans Only) for Amerprse certfcates, Columba mutual
Multiple-Period Attribution: Residuals and Compounding
Multple-Perod Attrbuton: Resduals and Compoundng Our revewer gave these authors full marks for dealng wth an ssue that performance measurers and vendors often regard as propretary nformaton. In 1994, Dens
What is Candidate Sampling
What s Canddate Samplng Say we have a multclass or mult label problem where each tranng example ( x, T ) conssts of a context x a small (mult)set of target classes T out of a large unverse L of possble
8.4. Annuities: Future Value. INVESTIGATE the Math. 504 8.4 Annuities: Future Value
8. Annutes: Future Value YOU WILL NEED graphng calculator spreadsheet software GOAL Determne the future value of an annuty earnng compound nterest. INVESTIGATE the Math Chrstne decdes to nvest $000 at
The Use of Analytics for Claim Fraud Detection Roosevelt C. Mosley, Jr., FCAS, MAAA Nick Kucera Pinnacle Actuarial Resources Inc.
Paper 1837-2014 The Use of Analytcs for Clam Fraud Detecton Roosevelt C. Mosley, Jr., FCAS, MAAA Nck Kucera Pnnacle Actuaral Resources Inc., Bloomngton, IL ABSTRACT As t has been wdely reported n the nsurance
IT09 - Identity Management Policy
IT09 - Identty Management Polcy Introducton 1 The Unersty needs to manage dentty accounts for all users of the Unersty s electronc systems and ensure that users hae an approprate leel of access to these
2008/8. An integrated model for warehouse and inventory planning. Géraldine Strack and Yves Pochet
2008/8 An ntegrated model for warehouse and nventory plannng Géraldne Strack and Yves Pochet CORE Voe du Roman Pays 34 B-1348 Louvan-la-Neuve, Belgum. Tel (32 10) 47 43 04 Fax (32 10) 47 43 01 E-mal: [email protected]
Causal, Explanatory Forecasting. Analysis. Regression Analysis. Simple Linear Regression. Which is Independent? Forecasting
Causal, Explanatory Forecastng Assumes cause-and-effect relatonshp between system nputs and ts output Forecastng wth Regresson Analyss Rchard S. Barr Inputs System Cause + Effect Relatonshp The job of
How Large are the Gains from Economic Integration? Theory and Evidence from U.S. Agriculture, 1880-2002
How Large are the Gans from Economc Integraton? Theory and Evdence from U.S. Agrculture, 1880-2002 Arnaud Costnot MIT and NBER Dave Donaldson MIT, NBER and CIFAR PRELIMINARY AND INCOMPLETE August 15, 2011
RESEARCH ON DUAL-SHAKER SINE VIBRATION CONTROL. Yaoqi FENG 1, Hanping QIU 1. China Academy of Space Technology (CAST) yaoqi.feng@yahoo.
ICSV4 Carns Australa 9- July, 007 RESEARCH ON DUAL-SHAKER SINE VIBRATION CONTROL Yaoq FENG, Hanpng QIU Dynamc Test Laboratory, BISEE Chna Academy of Space Technology (CAST) [email protected] Abstract
Brigid Mullany, Ph.D University of North Carolina, Charlotte
Evaluaton And Comparson Of The Dfferent Standards Used To Defne The Postonal Accuracy And Repeatablty Of Numercally Controlled Machnng Center Axes Brgd Mullany, Ph.D Unversty of North Carolna, Charlotte
SUPPLIER FINANCING AND STOCK MANAGEMENT. A JOINT VIEW.
SUPPLIER FINANCING AND STOCK MANAGEMENT. A JOINT VIEW. Lucía Isabel García Cebrán Departamento de Economía y Dreccón de Empresas Unversdad de Zaragoza Gran Vía, 2 50.005 Zaragoza (Span) Phone: 976-76-10-00
Lecture 3: Force of Interest, Real Interest Rate, Annuity
Lecture 3: Force of Interest, Real Interest Rate, Annuty Goals: Study contnuous compoundng and force of nterest Dscuss real nterest rate Learn annuty-mmedate, and ts present value Study annuty-due, and
Prediction of Disability Frequencies in Life Insurance
Predcton of Dsablty Frequences n Lfe Insurance Bernhard Köng Fran Weber Maro V. Wüthrch October 28, 2011 Abstract For the predcton of dsablty frequences, not only the observed, but also the ncurred but
How To Calculate The Accountng Perod Of Nequalty
Inequalty and The Accountng Perod Quentn Wodon and Shlomo Ytzha World Ban and Hebrew Unversty September Abstract Income nequalty typcally declnes wth the length of tme taen nto account for measurement.
Tuition Fee Loan application notes
Tuton Fee Loan applcaton notes for new part-tme EU students 2012/13 About these notes These notes should be read along wth your Tuton Fee Loan applcaton form. The notes are splt nto three parts: Part 1
The Application of Fractional Brownian Motion in Option Pricing
Vol. 0, No. (05), pp. 73-8 http://dx.do.org/0.457/jmue.05.0..6 The Applcaton of Fractonal Brownan Moton n Opton Prcng Qng-xn Zhou School of Basc Scence,arbn Unversty of Commerce,arbn [email protected]
Design and Development of a Security Evaluation Platform Based on International Standards
Internatonal Journal of Informatcs Socety, VOL.5, NO.2 (203) 7-80 7 Desgn and Development of a Securty Evaluaton Platform Based on Internatonal Standards Yuj Takahash and Yoshm Teshgawara Graduate School
Luby s Alg. for Maximal Independent Sets using Pairwise Independence
Lecture Notes for Randomzed Algorthms Luby s Alg. for Maxmal Independent Sets usng Parwse Independence Last Updated by Erc Vgoda on February, 006 8. Maxmal Independent Sets For a graph G = (V, E), an ndependent
PSYCHOLOGICAL RESEARCH (PYC 304-C) Lecture 12
14 The Ch-squared dstrbuton PSYCHOLOGICAL RESEARCH (PYC 304-C) Lecture 1 If a normal varable X, havng mean µ and varance σ, s standardsed, the new varable Z has a mean 0 and varance 1. When ths standardsed
Conversion between the vector and raster data structures using Fuzzy Geographical Entities
Converson between the vector and raster data structures usng Fuzzy Geographcal Enttes Cdála Fonte Department of Mathematcs Faculty of Scences and Technology Unversty of Combra, Apartado 38, 3 454 Combra,
Kiel Institute for World Economics Duesternbrooker Weg 120 24105 Kiel (Germany) Kiel Working Paper No. 1120
Kel Insttute for World Economcs Duesternbrooker Weg 45 Kel (Germany) Kel Workng Paper No. Path Dependences n enture Captal Markets by Andrea Schertler July The responsblty for the contents of the workng
ASSESSMENT OF STEAM SUPPLY FOR THE EXPANSION OF GENERATION CAPACITY FROM 140 TO 200 MW, KAMOJANG GEOTHERMAL FIELD, WEST JAVA, INDONESIA
ASSESSMENT OF STEAM SUPPLY FOR THE EXPANSION OF GENERATION CAPACITY FROM 14 TO 2 MW, KAMOJANG GEOTHERMAL FIELD, WEST JAVA, INDONESIA Subr K. Sanyal 1, Ann Robertson-Tat 1, Chrstopher W. Klen 1, Steven
Load Settlement System. Procedures and Methods
Procedures and Methods Effectve January 01 TABLE OF CONTENTS 1. NTRODUCTON... 1. STE TO SETTLEMENT ZONE MAPPNG.... LOAD PROFLNG... LOAD RESEARCH SAMPLES... SAMPLNG ACCURACY REQUREMENTS... HSTORC CLASS
Nordea G10 Alpha Carry Index
Nordea G10 Alpha Carry Index Index Rules v1.1 Verson as of 10/10/2013 1 (6) Page 1 Index Descrpton The G10 Alpha Carry Index, the Index, follows the development of a rule based strategy whch nvests and
A Novel Methodology of Working Capital Management for Large. Public Constructions by Using Fuzzy S-curve Regression
Novel Methodology of Workng Captal Management for Large Publc Constructons by Usng Fuzzy S-curve Regresson Cheng-Wu Chen, Morrs H. L. Wang and Tng-Ya Hseh Department of Cvl Engneerng, Natonal Central Unversty,
Uncrystallised funds pension lump sum payment instruction
For customers Uncrystallsed funds penson lump sum payment nstructon Don t complete ths form f your wrapper s derved from a penson credt receved followng a dvorce where your ex spouse or cvl partner had
Chapter 4 ECONOMIC DISPATCH AND UNIT COMMITMENT
Chapter 4 ECOOMIC DISATCH AD UIT COMMITMET ITRODUCTIO A power system has several power plants. Each power plant has several generatng unts. At any pont of tme, the total load n the system s met by the
A Secure Password-Authenticated Key Agreement Using Smart Cards
A Secure Password-Authentcated Key Agreement Usng Smart Cards Ka Chan 1, Wen-Chung Kuo 2 and Jn-Chou Cheng 3 1 Department of Computer and Informaton Scence, R.O.C. Mltary Academy, Kaohsung 83059, Tawan,
DISCLOSURES I. ELECTRONIC FUND TRANSFER DISCLOSURE (REGULATION E)... 2 ELECTRONIC DISCLOSURE AND ELECTRONIC SIGNATURE CONSENT... 7
DISCLOSURES The Dsclosures set forth below may affect the accounts you have selected wth Bank Leum USA. Read these dsclosures carefully as they descrbe your rghts and oblgatons for the accounts and/or
Overview of monitoring and evaluation
540 Toolkt to Combat Traffckng n Persons Tool 10.1 Overvew of montorng and evaluaton Overvew Ths tool brefly descrbes both montorng and evaluaton, and the dstncton between the two. What s montorng? Montorng
Dynamic Scheduling of Emergency Department Resources
Dynamc Schedulng of Emergency Department Resources Junchao Xao Laboratory for Internet Software Technologes, Insttute of Software, Chnese Academy of Scences P.O.Box 8718, No. 4 South Fourth Street, Zhong
J. Parallel Distrib. Comput.
J. Parallel Dstrb. Comput. 71 (2011) 62 76 Contents lsts avalable at ScenceDrect J. Parallel Dstrb. Comput. journal homepage: www.elsever.com/locate/jpdc Optmzng server placement n dstrbuted systems n
Trivial lump sum R5.0
Optons form Once you have flled n ths form, please return t wth your orgnal brth certfcate to: Premer PO Box 2067 Croydon CR90 9ND. Fll n ths form usng BLOCK CAPITALS and black nk. Mark all answers wth
www.olr.ccli.com Introducing Online Reporting Your step-by-step guide to the new online copy report Online Reporting
Onlne Reportng Introducng Onlne Reportng www.olr.ccl.com Your step-by-step gude to the new onlne copy report Important nformaton for all lcence holders No more software to download Reportng as you go...
Efficient Project Portfolio as a tool for Enterprise Risk Management
Effcent Proect Portfolo as a tool for Enterprse Rsk Management Valentn O. Nkonov Ural State Techncal Unversty Growth Traectory Consultng Company January 5, 27 Effcent Proect Portfolo as a tool for Enterprse
Linear Circuits Analysis. Superposition, Thevenin /Norton Equivalent circuits
Lnear Crcuts Analyss. Superposton, Theenn /Norton Equalent crcuts So far we hae explored tmendependent (resste) elements that are also lnear. A tmendependent elements s one for whch we can plot an / cure.
VRT012 User s guide V0.1. Address: Žirmūnų g. 27, Vilnius LT-09105, Phone: (370-5) 2127472, Fax: (370-5) 276 1380, Email: info@teltonika.
VRT012 User s gude V0.1 Thank you for purchasng our product. We hope ths user-frendly devce wll be helpful n realsng your deas and brngng comfort to your lfe. Please take few mnutes to read ths manual
A Performance Analysis of View Maintenance Techniques for Data Warehouses
A Performance Analyss of Vew Mantenance Technques for Data Warehouses Xng Wang Dell Computer Corporaton Round Roc, Texas Le Gruenwald The nversty of Olahoma School of Computer Scence orman, OK 739 Guangtao
Statistical Methods to Develop Rating Models
Statstcal Methods to Develop Ratng Models [Evelyn Hayden and Danel Porath, Österrechsche Natonalbank and Unversty of Appled Scences at Manz] Source: The Basel II Rsk Parameters Estmaton, Valdaton, and
1. Measuring association using correlation and regression
How to measure assocaton I: Correlaton. 1. Measurng assocaton usng correlaton and regresson We often would lke to know how one varable, such as a mother's weght, s related to another varable, such as a
Master s Thesis. Configuring robust virtual wireless sensor networks for Internet of Things inspired by brain functional networks
Master s Thess Ttle Confgurng robust vrtual wreless sensor networks for Internet of Thngs nspred by bran functonal networks Supervsor Professor Masayuk Murata Author Shnya Toyonaga February 10th, 2014
CHAPTER 14 MORE ABOUT REGRESSION
CHAPTER 14 MORE ABOUT REGRESSION We learned n Chapter 5 that often a straght lne descrbes the pattern of a relatonshp between two quanttatve varables. For nstance, n Example 5.1 we explored the relatonshp
8.5 UNITARY AND HERMITIAN MATRICES. The conjugate transpose of a complex matrix A, denoted by A*, is given by
6 CHAPTER 8 COMPLEX VECTOR SPACES 5. Fnd the kernel of the lnear transformaton gven n Exercse 5. In Exercses 55 and 56, fnd the mage of v, for the ndcated composton, where and are gven by the followng
Mathematics of Finance
CHAPTER 5 Mathematcs of Fnance 5.1 Smple and Compound Interest 5.2 Future Value of an Annuty 5.3 Present Value of an Annuty; Amortzaton Revew Exercses Extended Applcaton: Tme, Money, and Polynomals Buyng
Risk Model of Long-Term Production Scheduling in Open Pit Gold Mining
Rsk Model of Long-Term Producton Schedulng n Open Pt Gold Mnng R Halatchev 1 and P Lever 2 ABSTRACT Open pt gold mnng s an mportant sector of the Australan mnng ndustry. It uses large amounts of nvestments,
SPECIALIZED DAY TRADING - A NEW VIEW ON AN OLD GAME
August 7 - August 12, 2006 n Baden-Baden, Germany SPECIALIZED DAY TRADING - A NEW VIEW ON AN OLD GAME Vladmr Šmovć 1, and Vladmr Šmovć 2, PhD 1 Faculty of Electrcal Engneerng and Computng, Unska 3, 10000
Texas Instruments 30X IIS Calculator
Texas Instruments 30X IIS Calculator Keystrokes for the TI-30X IIS are shown for a few topcs n whch keystrokes are unque. Start by readng the Quk Start secton. Then, before begnnng a specfc unt of the
Methodology to Determine Relationships between Performance Factors in Hadoop Cloud Computing Applications
Methodology to Determne Relatonshps between Performance Factors n Hadoop Cloud Computng Applcatons Lus Eduardo Bautsta Vllalpando 1,2, Alan Aprl 1 and Alan Abran 1 1 Department of Software Engneerng and
Feature selection for intrusion detection. Slobodan Petrović NISlab, Gjøvik University College
Feature selecton for ntruson detecton Slobodan Petrovć NISlab, Gjøvk Unversty College Contents The feature selecton problem Intruson detecton Traffc features relevant for IDS The CFS measure The mrmr measure
METHODOLOGY TO DETERMINE RELATIONSHIPS BETWEEN PERFORMANCE FACTORS IN HADOOP CLOUD COMPUTING APPLICATIONS
METHODOLOGY TO DETERMINE RELATIONSHIPS BETWEEN PERFORMANCE FACTORS IN HADOOP CLOUD COMPUTING APPLICATIONS Lus Eduardo Bautsta Vllalpando 1,2, Alan Aprl 1 and Alan Abran 1 1 Department of Software Engneerng
Chapter 8 Group-based Lending and Adverse Selection: A Study on Risk Behavior and Group Formation 1
Chapter 8 Group-based Lendng and Adverse Selecton: A Study on Rsk Behavor and Group Formaton 1 8.1 Introducton Ths chapter deals wth group formaton and the adverse selecton problem. In several theoretcal
