1 RECENT FAILURES OF LARGE CORRUGATED METAL PIPE SPILLWAYS Harald W. Van Aller,P.E. Geotechnical Engineer Maryland Dam Safety Division ABSTRACT Many new stormwater management dams in Maryland have been constructed with large diameter corrugated metal pipe (CMP) spillways. Several of these dams, all dry ponds that impound water only during storms, have recently failed by piping of embankment soils along the outside of the conduit or through leaky joints. Random inspections have revealed serious deficiencies in many of the structures. Inadequate construction inspection of critical items has contributed to the failures. Several case histories are discussed. INTRODUCTION During the lastten years,more than 400 stormwater management ponds have been designed and built in Maryland with large (48-inches and larger in diameter) pipe conduits. In general, these ponds are low hazard structures less than 30 feet high. As such, they are exempt from Maryland s waterway construction permit requirements if the design is approved by a local Soil Conservation District. Although such local approval requires adherence to minimum design and construction standards that were developed by the USDA Soil Conservation Service, detailed construction inspection by a qualified engineer is often neglected, Approximately 200 of these ponds have spillways constructed of large diameter corrugated metal (steel) pipe, with some more than eight feet in diameter. In the last two years, the Dam Safety Division has investigated more than a dozen failures of these structures. The failures range in severity from complete failure of the dam and loss of the pool to leaking joints and indications that piping of embankment soils has been initiated. During the same period of time, about 170 ponds were designed with large diameter reinforced concrete pipe spillways. Only two failures of RCP spillways have been investigated by the Dam Safety Division. One of these had leaking joints that were repaired by injection of hydrophilic grout. The other structure required complete removal and replacement of the spillway conduit. INSPECTION PROGRAM The Dam Safety Division recently inspected more than a dozen small dams constructed with CMP spillway conduits. Some of these inspections were conducted with a local CMP manufacturer in order to determine if there are inherent problems with CMP spillways or whether the problems are construction related. In addition, after numerous deficiencies were noted, we enlisted the help of local publics works officials to perform inspections of 341
2 additional dams. In all, more than 40 new dams with large CMP spillways have been inspected, and more inspections are in progress. Two complete dam failures were investigated. These resulted in loss of impounded stormwater and severe environmental damage below the dams. Both structures were apparently constructed by installation of the conduits into near vertical trenches cut into the partially completed embankment fill and/or foundation soils. Both failures resulted from loss of embankment soil from along the outside of the conduit by seepage flow, a process termed piping. We found that very few installations of large CMP conduits are in accordance with generally accepted criteria for pipes through dams, Many of the problems we observed are most likely due to poor installation, such as: 1, Poor compaction of fill under the haunches of the pipe. Unlike rigid (concrete) pipes which are designed to support external loads with minimal deformation, CMP conduits are flexible, and are designed to deform slightly which allows the surrounding soil to provide most of the support for the embankment fill above the conduit. In practice, it is very difficult to obtain adequate compaction under the haunches of the pipe to provide the necessary support, especially with large diameter pipes. If the contractor is overzealous in his efforts to compact the soil in this zone, there is a possibility that the relatively lightweight pipe will be lifted from the subgrade soils, leaving an open void under the conduit, Inadequate support under the haunches of the pipe will likely result in eventual failure of the conduit. In addition, voids in the fill under the pipe are avenues for seepage flow, increasing the possibility of a piping failure. 2, Pipe was installed in trench with near-vertical sides cut through partially completed embankment fill. Some contractors contend that it is more cost effective to place the majority of embankment fill with large equipment and to cut a trench through the fill and install the pipe. However this can result in poor compaction of the pipe backfill because much of the work is hand labor in a confined area, especially in the haunch area as described above, and thin fill layers are necessitated by the use of lightweight compaction equipment. In addition, there is a potential for transverse cracking of the dam embankment due to differential settlement between the hand placed backfill and embankment fill placed with heavy equipment, increasing the possibility of a piping failure. Also, pipe backfill placed in a trench tends to reduce loads on the pipe by a process known as arching. While desireable from a structural standpoint for design of the pipe, this phenomenon may result in low soil pressures near the pipe. If the soil pressures are less than the anticipated hydrostatic loading, there is a potential for the pond water to cause serious cracking of the embankment by a process termed hydraulic fracturing. 3. Watertight joints were not obtained. Our experience indicates that watertight joints are difficult to obtain in the field. This can result from: Damaged pipe ends which prevent proper alignment of pipe sections. 342
3 Gaskets notinstalled joints, wrong type of gaskets used, or gaskets not lubricated properly which causes uneven gasket contact. Helically corrugated pipe ends not re-rolled to provide concentric channels for proper gasket contact. Incorrect joint connecting bands installed. Dimple or narrow hugger bands do not provide the desired level of joint integrity. Construction inspection was performed on some, but not all, of these structures while they were being built. However, the inspector was often a soils technician, with limited dam construction experience, retained by the contractor to simply test the fill for compliance with the project specifications. The inspector was usually not on site full-time, so that certain critical items, such as joint construction, gasket details, compaction of the fill under the haunches of the pipe, etc. were not observed, Interviews with construction and inspection personnel for some of the projects indicates that there is sometimes a lack of communication between the inspectors and the engineers, often because the inspector worked for another company and was not under the direct supervision of the design engineer, Also, since most of the inspectors were on site to simply observe and document construction techniques, the inspector had no control over the project, In one instance, the inspector duly noted in his report that the contractor was installing incorrect gasket materials into the joints. However, this problem was not corrected at the time of construction and several years later the pipe is in the process of failure due to loss of fill material by piping into the leaky joints. RECOMMENDATIONS Sowers (1974) observed that the most common failures of dams are those of small reservoirs, in part because the owners of these structures are /rj/ed into complacency by the very insignificance of their structures. /t is difficu/t for them to realize the damaging effects of the fai/ure of sma// reservoirs. He further states that those responsible for design... of such reservoirs are interested primari/y in the [function) of the reservoir rather than with the structure (itse/f]. They... are rarely dam designers and builders. Therefore, the smaller dams often are not given the benefit of experienced design, adequate construction supervision... The consequences are disastrous. Itis obvious that detailed construction inspection by qualified geotechnical engineers is essential for proper construction of small dams. The construction industry needs to have better trained, full-time construction inspection under the direction of the design engineer. The designer should be a geotechnical engineer experienced in dam design and construction. In addition to soil compaction specifications, the inspector should be familiar with pipe specifications and should be able to reject deficient installations on the spot. Too often, inspector is under contract only to observe and document installation and problems that are documented in daily reports are not forwarded to the engineer until too late to remedy. 343
4 Use fly-ash based controlled low strength material or flowable fill to backfill under the haunches and sides of the pipe. Flowable fill is a low strength material that can be delivered to the job site in a standard ready-mix concrete truck. It can be formulated to have compressive strengths in the range of 30 to 1200 psi. Flowable fill in the range of 30 to 150 psi has characteristics similar to that of compacted fill, and can easily be removed by common excavation techniques at a later date if needed. The material is self-levelling, and is simply poured into an excavation, where it fills the voids under the pipe with no compactive effort.itisrecommended thatitbe placedtoa leveltoatleasthalfwayup the sides of the pipe, Due to the potential for significant shrinkage, it is recommended that the flowable fill be placed in two pours, with sufficient time between then to allow the first pour to cure. The pipe conduit must be anchored to prevent flotation. Compact the fill that will be under the haunches of the pipe before installing the pipe, and use a special excavator bucket to conform the bottom of the trench to the contour of the conduit. This may reduce the possibility voids under the pipe. Better inspection during construction to ensure that joints are watertight, from the time the joints are made through completion of filling operations. Since watertight joints are essential for a safe conduit through a dam embankment or its foundation, pressure testing of each joint before continuing with installation may be warranted. This is commonly done for sewer installations. Improve joint design. Soil Conservation Service pond construction standards in Maryland now requires that pipes with a diameter of 24-inches or more be connected by a 24 long annular corrugated band using rods and lugs. A 12 wide by 3/8 thick closed cell circular neoprene gasket is to be installed on the end of each pipe for a total of 24. Perhaps the use flanged joints instead of connector bands and o-ring gaskets should be considered. Have pipe manufacturers match mark pipe sections. CMP manufacturers in Maryland typically custom fabricate pipe for pond projects in one continuous section which is then cut into lengths that can be shipped to the job site. Since the cuts are not always perpendicular to the pipe axis, misalignment of the joints is inevitable if the same two pieces are not installed adjacent to each other. This is more of a problem with large diameters, since a small cutting error translates to a sizeable alignment error. Match marks will help with alignment of joints in field and result in a greater likelihood of watertight joints. Eliminate anti-seep collars and use filter diaphragms to control seepage and piping along the conduit. It is interesting to note that the two structures that failed completely were built with anti-seep collars which did not prevent loss of soil by piping. It is a common misconception that the collars will prevent seepage along the conduit. Thus, there is a temptation to skimp on compaction of backfill material and to rely on the collars to prevent failure. Properly designed filter diaphragms, on the other hand, will control seepage that may occur along the outside of the conduit. A filter diaphragm is a zone of filter material (sand and gravel) that completely surrounds the pipe. It is generally located near the downstream end of the conduit. (SCS 1985) The filter must be designed in accordance with standard soil mechanics filter criteria. (Talbot 1985, 1990) 344
5 CONCLUSIONS A large number of pond and dam failures can be attributed to problems with the conduit. Since all of the failures that we observed were located along the spillway pipe, consideration should also be given to eliminating conduits through dam embankments and foundations wherever possible, perhaps by utilizing weir structures instead of conduits, If large CMP spillways are to continue to be used in dam construction, new standards need to be developed. These could include: elimination of anti-seep collars and use of filter diaphragms to control seepage that may develop along the outside of the conduits; better joint design to ensure watertightness; shaping the bottom of the trench to precisely fit the circumference of pipe to improve the support of the pipe haunches; and the use of flowable fill material for pipe backfill. In addition, installation of pipes in vertical trenches excavated through partially completed dam embankments contribute toward failure potential and the technique should be avoided, REFERENCES American Concrete Pipe Association, (1992) Design Stormwater Pipelines, Greenbelt, Maryland Genstar Stone Products Company, (1990) Ready Mixed Life Seminar, Buried Wastewater and Flowable Fill, Hunt Valley, Maryland. Manzi, Joseph E,, (1984) Construction Inspection: Improvin the Benefits Received, Professional Inspection of Construction, edited by Stephen 6, Quinn, AS 8 E, New York, p, Martin, Ray E., (1989), Seepage Control Along Conduits Penetrating Embankment Dams, presented at the 1989 Southeastern Association of State Dam Safety Officials Conference National Ready Mixed Concrete Association (1989), CIP 17: Flowable Fill Materials, Silver Spring, Maryland Shields, David R,, (1985) Geotechnical Inspection for Small Dams: How Small is Too Small?, Hvdro Review Maqazine, Fall issue. Sowers, George F., (1974) Dam Safety Legislation: A Solution or a Problem, Proceedings of Engineering Foundation Conference at New England College, ASCE, New York, p Talbot, J. R. and Ralston, D. C. (1985), Earth Dam Seepage Control, SCS Experience, SeeDaGe and Leakaqe from Darns and Impoundments, ASCE Geotechnical Engineering Symposium, edited by R.L. Volpe and W.E, Kelly, New York, p Talbot, James R., (1990) SCS Filter Studies, Design Procedures and Experiences with Filter Diaphragmsn, Association of State Dam Safety Officials Mid-Atlantic Regional Technical Seminar on Seepacre in Dam Safetv: Evaluation and Remediation, Baltimore, Maryland USDA Soil Consewation Service, (1992) MD-378, Standards and Specifications for Ponds, Annapolis, Maryland USDA Soil Conservation Service, (1985), Technical Release No. 60 (TR-60), Earth Dams and Reservoirs, Washington, DC, p. 6-7 through 6-9 USDA Soil Conservation Service, South National Technical Center, (1985), Technical Note 7091 Dimensioning of Filter Drainaqe Diaphragms for Conduits Accordina to TR-60, Fort Worth, Texas Van Aller, Harald W., (1990) Filter Diaphragm Design Considerations, Association of State Dam Safety Officials Mid-Atlantic Regional Technical Seminar on Seepaue in Dam Safetv: Evaluation and Remediation, Baltimore, Maryland 345
6 PARTIAL SUMMARY OF CMP PIPE INVESTIGATIONS Insp. Dam Site Dam Pipe ~~e ~ ~ Comments 4/93 <1 yr AML Complete failure and severe environmental damage to creek below dam. Poor compaction; leaky jointsj installed m trench cut through partially completed fill. Conduit to be replaced with concrete pipe. 5/89 4yr LFM Complete failure and severe environmental damage to trout stream. Poor compaction; installed in trench cut through partially completed fill. 10/90 5yr SSS Leaky joints; sinkholes; extensive piping in regress. Breach excavated through dam to alleviate pubhc sa fety hazard, 2/91 5yr VHL Leaky joints; sinkholes in fill due to piping, 10/92 2yr CST Deformation of conduit noted to be about 7-inches; leaky joints; missing o-ring gaskets. Embankment was removed, joints were repaired with concrete collars and dam was rebuilt, 4/91 4yr MRN Wet pond with 6 foot normal pool depth. Leaking joints; pi ing in progress. Ongoing investigation for repair alternatives. Eam is only access to a housing subdivision, and major utilities (electric, water: sewer, telephone) in the embankment make pipe replacement dtficult. 4/91 2yr BWC Leaking joints; piping. Sinkhole at upstream end. Pipe replaced. 5/93 3yr CGY No askets installed during construction. Internal joint rings instaf led after the fact do not appear watertight. 11/92 6yr TMR Leaking joints; wrong connecting bands; pipe ends not re-rolled; pig;:fationin progress; pipe damaged by utility contractors after 3/93 3yr HSM Leaking joints;repairattempted with mastic but jointsnot watertight. 2/92 2yr CVY Leakage along outsides of five parallel spillway pipe conduits. Repaired by injection of cement grout into voids in embankment. 4/92 3yr RTP Leaking joints; excessive deformation. Pipe replaced. 7/93 2yr MKS Open joints; large voids under pipe; piping in progress. 5/91 2yr UP Voids and see a e along pipe; settlement profile indicates that l % pipe was insta Ie in trench through dam. 5/91 <1 yr FOX Joints separated up to 2. Exposed flat, neoprene gasket leaking. Voids under haunches. 5/93 2yr SRP Excellent alignment; nearly all joints appear watertight. 4/91 e2yr HBC Voids under haunches; more flow under the pipe than through it; infiltration noted at all joints; deflection of pipe noted at center of dam. 346
7 Complete failure of 25 foot high dam for dry end, viewed from the pool area. The structure does not normally impound water. f he 72-inch barrel pipe was apparently installed in a vertical trench cut through nearly completed embankment fill. Failure occurred during a storm that filled pool to just below enlarged top of riser. Detail of above, looking downstream along pipe from riser. Note collapse of 14-foot square anti-seep collar and the near vertical trench wall parallel to pipe in center of picture. 347
8 Complete failure of 25 foot hi h dam as viewed from downstream end of 54-inch pipe, TI his pipe was ap arently instal f ed in a vertical trench cut through partially complet ed embankment fill, Loss of soil support due to piping of surrounding backfill resulted in collapse of pipe and catastrophic release of flood waters. Man emb joint 3W ch 348
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard
Stormwater/Wetland Pond Construction Inspection Checklist
: Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials
Wastewater Capital Projects Management Standard Construction Specification
CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
REHABILITATION OF FAILED CORRUGATED METAL PIPE SPILLWAYS PRESENTED AT JUNE 1996 REGIONAL CONFERENCE MID-ATLANTIC COUNCIL FOR SAFE DAMS
REHABILITATION OF FAILED CORRUGATED METAL PIPE SPILLWAYS PRESENTED AT JUNE 1996 REGIONAL CONFERENCE MID-ATLANTIC COUNCIL FOR SAFE DAMS by Harald W. Van Aller, PE Geotechnical Engineer, Maryland Dam Safety
Section 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
SUBDRAINS AND FOOTING DRAIN COLLECTORS. A. Construct subdrains, subdrain cleanouts and outlets, and footing drain collectors.
SUBDRAINS AND FOOTING DRAIN COLLECTORS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subdrains B. Subdrain Cleanouts and Outlets C. Footing Drain Collectors D. Storm Sewer Service and Connections 1.02 DESCRIPTION
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
DIVISION 4300 STORM DRAINAGE
DIVISION 4300 STORM DRAINAGE SECTION 4305 STORM SEWER PART 1 - GENERAL 1.01 SCOPE This section covers the construction of storm sewers for the collection and transport of stormwater runoff. 1.02 REFERENCES
Moving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
Storm Sewer Trenchless Upgrade Alternatives and Recommendations
Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL
DIVISION 2 - SEWERAGE AND DRAINAGE SECTION 02720 - STORM DRAIN SYSTEMS PART 1 - GENERAL 1.01 DESCRIPTION A. Furnish and install all storm drains, including manholes, inlets, service lines and other appurtenant
SECTION 02612 NONREINFORCED CONCRETE SEWER PIPE
SECTION 02612 PART 1 GENERAL 1.1 SUMMARY A. Section Includes: Furnishing and installing nonreinforced concrete sewer pipe. Provide concrete sewer pipe less than 12 inches in diameter, and in other sizes
The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS
SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING
San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.
Small Dam Repair The Stone Lake Dam Story Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. 29601 1 Historical background of Stone Lake A series of three
San Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
Section 02702 SEWER PIPE INSTALLATION AND TESTING
PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete
Protecting Your Pools Crack Treatments
1 Protecting Your Pools Crack Treatments Scuba Pool Repair Inc. 800 Cristich Lane Campbell, CA 95008 Phone: 408-866-1945 Fax: 408-866-1931 Email: [email protected] www.scubapoolrepair.com Scuba
SECTION 02630 STORM DRAINAGE SYSTEM
SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE
Meeting the Challenge of Pipeline Emergency Repair
Meeting the Challenge of Pipeline Emergency Repair Michael R. McReynolds, PE, SE 1 Tao Peng, PE, SE 2 ABSTRACTS The Metropolitan Water District of Southern California (MWD) is the nation s largest provider
Emergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200
STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete
SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)
Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks
SECTION 02400 - STORM DRAIN SYSTEM
SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And
SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE
SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel
Appendix B.1. NRCS-MD Code No. 378 Pond Standards/Specifications
Appendix B.1 NRCS-MD Code No. 378 Pond Standards/Specifications Pond MD-378-1 USDA NATURAL RESOURCES CONSERVATION SERVICE MARYLAND CONSERVATION PRACTICE STANDARD POND CODE 378 (Reported in No.) DEFINITION
SECTION 724 PIPE CULVERTS
SECTION 724 PIPE CULVERTS 724.1 Description. This work shall consist of providing pipe or pipe arch of the diameter or shape designated, laid upon a firm bed and backfilled as specified. Where appropriate
Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL
7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction
STANDARD SPECIFICATIONS & CONSTRUCTION DETAILS MANUAL SECTION 5 - STORM DRAINAGE. 5.01 Design
SECTION 5 - STORM DRAINAGE 5.01 Design Storm drainage facilities shall be designed in accordance with the goals and guidelines set forth in the Unified Development Ordinance. The goal shall be to collect
53.03 MATERIALS FOR SEWER LINER PIPE AND FITTINGS: The following materials are approved for installation in sanitary sewer lines:
Division 53: Slip-Lining of Existing Sewer Line 53.01 GENERAL: This section includes all labor, materials, transportation, equipment necessary to rehabilitate by means of Instituform deteriorated sections
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
C. Section 014510 TESTING LABORATORY SERVICE.
SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe
TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,
Baton Rouge Foundation Repair
Baton Rouge Foundation Repair 13822 Florida Blvd Bldg 3 Baton Rouge, LA 70819 Baton Rouge Foundation Repair offers services to correct the settlement of both Slab foundations and Pier & Beam foundations
Installation of Large Diameter Buried Pipes
Installation of Large Diameter Buried Pipes Sullivan (Sully) Curran P. E., Executive Director I. Introduction and Scope There is an ongoing need to provide designers, specifiers, engineers, consultants
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872
STORMWATER MANAGEMENT CHECKLIST
STORMWATER MANAGEMENT CHECKLIST *This checklist must be completed and part of the Land Disturbing Permit submittal for review if the acreage disturbed is one (1) acre or more: I. SUPPORTING DATA Narrative
SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE
6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction
A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.
PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,
CHAPTER 6 - SANITARY SEWER
CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings
CONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION
BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION GENERAL Rehabilitation of culverts with pipe liners is one of several methods available for extending the life of an existing culvert. It is often cost
NRCS Overview. National Dam Safety Program Technical Workshop #19 February 22-23, 2012
NRCS Overview National Dam Safety Program Technical Workshop #19 February 22-23, 2012 Thomas Brown National Design, Construction, and Soil Mechanics Center (NDCSMC) Fort Worth, Texas NRCS Dam Inventory
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS
SIDE SEWER CONDITION ASSESSMENT AND REPAIR RECOMMENDATIONS Introduction City of Tacoma property owners are responsible for the construction, maintenance and repair of private side sewers, which connect
SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority
Sewer Pipe Lining An Economic Solution for Pipe Rehabilitation By Tawana Albany Nicholas, Virgin Islands Waste Management Authority Abstract The United States Virgin Islands Waste Management Authority
Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
Minimum Design Criteria for the permitting of Gravity Sewers
Minimum Design Criteria for the permitting of Gravity Sewers Adopted by the Division of Water Quality on February 12, 1996 Updated to 15A NCAC 2T Regulations on March 2008 1,400 copies of this document
PVC PIPE PERFORMANCE FACTORS
PVC PIPE PERFORMANCE FACTORS PVC pipe, like all flexible pipe products, is very dependent on the surrounding soil for its structural capacity, in addition, the pipe material must have sufficient inherent
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in
SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES
SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with
Specifications for Residential Property Owners Connection to New Public Sewer
Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the
Foundation Water Problems. An Overview and Discussion of some Causes and Cures for Water Infiltration into Basements and Foundation Structures
Foundation Water Problems An Overview and Discussion of some Causes and Cures for Water Infiltration into Basements and Foundation Structures This presentation was prepared and presented by Dwight Walker
SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING
SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent
Exhibit A. Rules and Regulations for House Connections and Sewer Extensions
The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and
SECTION 3 SANITARY SEWER DESIGN
SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary
817 - PIPE CULVERTS, EROSION PIPE, STORM SEWERS, SANITARY SEWERS & END SECTIONS SECTION 817
SECTION 817 PIPE CULVERTS, EROSION PIPE, STORM SEWERS, SANITARY SEWERS AND END SECTIONS 817.1 DESCRIPTION Install the size and type of pipe culvert, erosion pipe, storm sewer, sanitary sewer, end section
CONCRETE SEGMENTAL RETAINING WALL SYSTEM
CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)
Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.
ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical
SECTION 03400 PRECAST CONCRETE STRUCTURES
PART 1 GENERAL 1.01 SCOPE OF WORK A. Furnish all labor, materials, and equipment required to install precast concrete manholes, sanitary leaching rings, pump station, valve chamber, structures, frames,
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY
Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Policy: This policy will replace all previous policies regarding the selection of pipe material for cross drains, drive pipe, drop pipe, storm
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS
SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE
NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without
1.3.2 Method of construction and restoration of existing water service connections. This shall include:
1.0 GENERAL 1.1 DESCRIPTION: This specification shall cover the rehabilitation of existing water lines using the GRUNDOCRACK PIPE BURSTING SYSTEM. Pipe bursting is a system by which the pneumatic bursting
Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps
Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure
X Planning X Quality X Maintenance & Operations
Delaware Department of Transportation Division of Transportation Solutions Design Guidance Memorandum Memorandum Number 1-20 Revised 1. Road Design Manual 2. Bridge Design Manual 3. Utilities Design Manual
SECTION 7- STORM SEWER
SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...
CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS
CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection
FY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION
STANDARD AND SPECIFICATIONS FOR STORM DRAIN INLET PROTECTION Design Criteria Drainage Area The drainage area for storm drain inlets shall not exceed one acre. The crest elevations of these practices shall
FY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT
SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,
February 4, 2011. [email protected]. Report Recommendations and NIPSCO Responses. 4.3 Maintaining and Controlling Vegetation Growth
February 4, 2011 VIA E-MAIL AND CERTIFIED MAIL #7010 0290 0002 0577 6226 Mr. Stephen Hoffman US Environmental Protection Agency (5304P) 1200 Pennsylvania Avenue, NW Washington, DC 20460 [email protected]
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control
Town of Elkton & Cecil Soil Conservation District Checklist for Joint Agency Review Stormwater Management / Erosion and Sediment Control Project Name: Tax Map Parcel: Acreage: Plat: ADC Map & Grid Engineering
BEST MANAGEMENT STANDARDS FOR FOUNDATION REPAIR MARCH 2003 REVISED JUNE 13, 2012
BEST MANAGEMENT STANDARDS FOR FOUNDATION REPAIR MARCH 2003 REVISED JUNE 13, 2012 Prepared in cooperation with the Building Inspectors Association of Southeastern Wisconsin www.biasew.net 1 BEST MANAGEMENT
SECTION 02763 POINT REPAIRS TO SANITARY SEWERS. A. Repairs to existing sewer lines by replacing short lengths of failed pipe.
SECTION 02763 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Repairs to existing sewer lines by replacing short lengths of failed pipe. 1.02 UNIT PRICES A. Measurement for point repairs is on a unit price
ENGINEERED SOLUTIONS. A2 Liner Pipe for Trenchless Technology
ENGINEERED SOLUTIONS A2 Liner Pipe for Trenchless Technology A2 Liner Pipe Restores Deteriorated Sewers Cost-Effective Rehabilitation The increasing rate of sanitary and storm sewer deterioration requires
Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
PIPE INSPECTION AND REPAIR. Larry Ritchie
PIPE INSPECTION AND REPAIR Larry Ritchie February 23, 2010 PIPE INSPECTION AND REPAIR The Florida Department of Transportation builds and maintains hundreds of miles of underground infrastructure as part
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES. 1. Trenching, Backfilling and Compacting: 02223
STANDARD SPECIFICATIONS SECTION 02701 INSTALLATION OF GRAVITY SEWER PIPELINES PART 1 - GENERAL A. Description This section describes the installation of gravity sewer pipelines fabricated of vitrified
Local Road Assessment and Improvement Drainage Manual
Local Road Assessment and Improvement Drainage Manual Donald Walker, T.I.C. Director, author Lynn Entine, Entine & Associates, editor Susan Kummer, Artifax, design Transportation Information Center University
SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or
Section 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
SECTION 9. All sewer laterals shall tie into the sewer main lines unless approved by the City Engineer.
SECTION 9 SEWER/DRAINAGE LINES 9.1 GENERAL This section covers the requirements for piping materials and installation in the Cedar Hills City sewer and drainage collection system. All materials and workmanship
Safe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
CLIFTY CREEK PLANT MADISON, INDIANA
2015 DAM AND DIKE INSPECTION REPORT GERS-15-018 CLIFTY CREEK PLANT MADISON, INDIANA PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Annual Dam and Dike Inspection
Waste Collection Systems
Waste Collection Systems System Maintenance and Repair Maintenance and Repair Training Objectives To gain an understanding of: System Maintenance and Repair vocabulary System Maintenance and Repair techniques