Project Plan. 1.0 Introduction. 2.0 Roles and Responsibilities. 3.0 Project Development Model
|
|
|
- Jennifer Andrews
- 10 years ago
- Views:
Transcription
1 Project Plan 1.0 Introduction This docum ent seeks to outline the planning, resources, scheduling and approach that will be used throughout the development of the VisiNet project. 2.0 Roles and Responsibilities Our project team consists of three Final year degree students:, Karwan Miran and Jam ie Macgill. Due to the lim ited size of our group each m em ber will be involved in m any different aspects of the project. Although each m em ber will be involved in m ore then role we have decided that each part of the project should be overseen by a single individual. A list of these oversight roles are given below. Project Management & Scheduling Richard Analysis of Requirements - Jamie System Design & Specification - Kar Interface Design & Specification - Jamie Administrative Management - Kar Quality Assurance & Version Management Richard All the rem aining roles within the project will be distributed between the group members allowing each m em ber to contribute. A list of the rem aining roles is given below. System Implementation & Coding System Testing Evaluation & Review Process - ALL - ALL - ALL This m ethod of resource m anagem ent will allow each m em ber to be involved and share ideas and concepts to the benefit of all aspects of the project. I t will also allow the group to operate with great flexibility, enabling group m em bers to interoperate and work together more efficiently. 3.0 Project Development Model Every software developm ent project undertaken is always constrained in som e way by a num ber of different factors placed on the project. One of the m ain Project Plan Page 1 of 7
2 constraints for our project is the am ount of tim e that we have available for the project. For this reason we have decided that the best approach is to use an iterative developm ent m odel, allowing a software solution to be developed early on and then refined by further iterations. We believe that if the process was not iterative then possible problem s with the analysis, specification or design would not becom e apparently until the latter im plem entation parts of the project. This could represent a significant risk to the success of the project and have dram atic affects on the timing constraints of the project. The iterative developm ent m odel we have chosen for this project is Evolutionary prototyping. The Evolutionary prototyping m odel as shown in Figure 1 allows us to grow a solution thru iterations of development. Figure 1 Evolutionary Prototyping Model We have identified that we have approxim ately twenty weeks of developm ent time in order to apply the Evolutionary prototyping m odel m ost effectively we have decided to carry out two iterations. We have decided that the iterations will last approximately eight weeks, this will give us an overall flexibility of four weeks allowing us to adapt to yet unforeseen problem s that m ay occur during the project. The iteration will be started with a clear list of target requirem ents for the iteration. And will be concluded with a review of the iteration and an evaluation of its success against the initial requirements. Project Plan Page 2 of 7
3 3.1 Requirements Stage This stage involves researching and analysing the requirem ents for the project to develop a specification and form al list of requirem ents that the project. I t will involve looking at several previous projects to establish the key aspects of functionality that we wish to incorporate into our own project. 3.2 Analysis and Design Stage After the requirem ents stage is com plete the requirem ents will be analysed and an initial design will be created. I n the early stages of the project the design will be rather flexible concentrating m ainly on the sim ulation aspects of the project developm ent. Later on we anticipate that design will becom e m ore detailed as iteration 1 is com pleted and giving us a stable fram ework for the extension to visualisation in iteration Implementation Stage I m plem entation is the stage where the physical design of the program is translated into code. Each specification developed during the last stage will be im plem ented into the overall program structure. I f any problem s with the design are discovered the project will return to the design stage and create a revised design. The process will then continue checking that each of the previously implemented features can be satisfied within the new design framework. 3.4 Testing Stage During the testing stage each function im plem ented in the im plem entation stage is checked against its specification to ensure that it perform s the correct action. More detailed testing will also be carried out details of the testing procedures can be found our project Test plan. 3.5 Evaluation Stage This stage will be used to exam ine whether the prototype that has been developed fulfils all the requirem ents of the project. I f the prototype doesn t fulfil these requirem ents the process will continue with a further iteration. I f the prototype fulfils all the requirem ents then it will stop the cycle of iteration and continue onto the next stage. The evaluation stage also gives us the opportunity to gauge the progress over the past iteration to determ ine the am ount of tim e taken and to adjust the tim e schedule accordingly. Also the evaluation process will also allow us to assess how well the iteration was executed and to identify any key areas of improvement. Project Plan Page 3 of 7
4 3.6 Deployment Stage Deploym ent is the process in which the program has reached com pletion and is ready for deploym ent into its prospective environm ent. Deploym ent will also involve the creation of a project review that will look at each aspect of the project determ ining how successful each part was and to suggest im provem ents for the future. Project Plan Page 4 of 7
5 4.0 Project Scheduling and Estim ation The m ost influential constraint on our project is the am ount of tim e available for developm ent. For this reason it is im portant to schedule events in the project to ensure that tim e is properly m anaged and that tasks are perform ed efficiently. The am ount of tim e that certain event will take in the project is in precise. To allow scheduling to take place estim ation will have to be used to determ ine the probably length of tim e that each stage will require. Gantt charts containing our actual Gantt time plan can be found below: ID Task Name Duration Start Finish Predecessors 4 Interview with module lecturer 1 day Tue 30/09/03 Tue 30/09/03 5 Analysis of Existing Solutions 3 days Wed 01/10/03 Fri 03/10/ NeVis 3 days Wed 01/10/03 Fri 03/10/03 7 Macachino 3 days Wed 01/10/03 Fri 03/10/03 8 PellyDeprez 3 days Wed 01/10/03 Fri 03/10/03 9 AJM 3 days Wed 01/10/03 Fri 03/10/03 10 Evaluation of Existing Solutions 2 days Mon 06/10/03 Tue 07/10/ Human Computer Interaction 4 days Tue 30/09/03 Fri 03/10/03 12 Project requirements 2 days Wed 08/10/03 Thu 09/10/03 10,11 13 Project Success Criteria 2 days Fri 10/10/03 Mon 13/10/ Iteration 1 42 days Tue 14/10/03 Wed 10/12/03 15 Design Stage 10 days Tue 14/10/03 Mon 27/10/ Basic Diagrams 5 days Tue 14/10/03 Mon 20/10/03 17 Advanced Diagrams 5 days Tue 21/10/03 Mon 27/10/ Implementation Stage 22 days Tue 28/10/03 Wed 26/11/ Testing Stage 5 days Thu 27/11/03 Wed 03/12/ Evaluation Stage 5 days Thu 04/12/03 Wed 10/12/ Iteration 2 49 days Thu 11/12/03 Tue 17/02/ Review Requirements 5 days Thu 11/12/03 Wed 17/12/03 23 Design Stage 15 days Thu 11/12/03 Wed 31/12/03 24 Review & Evolve Diagrams 9 days Thu 11/12/03 Tue 23/12/03 25 Graphic User Interface Design 6 days Wed 24/12/03 Wed 31/12/ Implementation Stage 22 days Thu 01/01/04 Fri 30/01/ Testing Stage 7 days Mon 02/02/04 Tue 10/02/ Evaluation Stage 5 days Wed 11/02/04 Tue 17/02/ Deployment 1 day Wed 18/02/04 Wed 18/02/ Evaluation of Project 14 days Thu 19/02/04 Tue 09/03/04 29 Figure 2 Estimated Project Gantt chart As the project progresses the Gantt chart will continue to be updated with actually timings and revised estimations. A copy of the revised Gantt chart will be available in the Project Folder. Project Plan Page 5 of 7
6 After lengthy discussion the decision was taken to should break up the requirem ents into two m ain sections: Sim ulation and Visualisation. Each section will then be implemented iteratively. Iteration 1 This iteration will aim to develop the m ain core of the sim ulator with just a single protocol: CSMA/ CD. This will allow us to test the basic functionality of the sim ulator before the additional protocols are added. The iteration will also involve a form of console based control and a textual output. An outline of the features to be implemented and there priority can be found below: 1. Create Basic Simulator with Simulation, Bus and Station 2. Create a control class to control the Simulation 3. Create a textual representation of a simulation state 4. Expand Simulation to additional protocols Iteration 2 The key aim s of this iteration are to develop the Visualisation part of the project. We will start by transferring control of the sim ulation to a graphic user interface with buttons and controls. The sim ulation will then be attached to a graphical representation or visualisation of the state of the sim ulation. When both of these functions have been com pleted in there basic m ost form we shall continue to evolve the design of the Visualisation incorporating m ore features until the requirements are met. 1. Create a graphical control for the simulation 2. Develop a Visualisation panel to display the simulation state 3. Integrate all of the components into a form with a layout component 4. Continue to evolve the visualisation to incorporate anim ation and interactive help tools. 5. Expand the control to support the loading and saving of simulation data 6. Implement any additional visualisation requirements 5.0 Technical Planning and CASE Tools The project will be im plem ented using the Java program m ing language. We decided to use java because every group m em ber has very good knowledge of java. Other languages such as C and C+ + were considered but were unsuitable because only two m em bers had an acceptable knowledge of the languages. We Project Plan Page 6 of 7
7 shall be using the current m ost Java Software Developm ent Kit (SDK) Version To assist in the developm ent of this project we shall be using several different case tools below is a list of case tools we shall be using and there role within the project: TogetherSoft 6 Used in the design process to develop various UML Diagrams. Concurrent Version System (CVS) Used for code access control, synchronisation and version management. TextPad / EditPlus / PFE Editors used during the im plem entation process to develop code. JUnit Used during testing process to help write and control unit and integration tests. Microsoft Project Used for scheduling and tim ing of entire project process. Project Plan Page 7 of 7
Law, Ka Yee (2009) CRM adoption and its impact on organisational performance. PhD thesis, University of Nottingham.
Law, Ka Yee (2009) CRM adoption and its impact on organisational performance. PhD thesis, University of Nottingham. Access from the University of Nottingham repository: http://eprints.nottingham.ac.uk/10787/6/5-chapter_1.pdf
7 A MANAGEMENT MODEL STUDY
7.1 Aim s and Objectives of the Management Model Study Positive Solutions is part of the consultant team and is w orking on the governance and m anagem ent model to ensure appropriate operating arrangements
TEXAS BOARD OF NURSING 3.4.1.a. EDUCATION GUIDELINE Approval Process for a New Dean/Director/Coordinator, or New Interim Dean/Director/Coordinator
TEXAS BOARD OF NURSING 3.4.1.a. EDUCATION GUIDELINE Approval Process for a New Dean/Director/Coordinator, or New Interim Dean/Director/Coordinator Revised: 01/02/2013 Rule 214.6 sets forth the requirements
i-pro M anagem ent Software ASC970 system Explanation of new functions for Ver. 8.0
i-pro M anagem ent Software ASC970 system Explanation of new functions for Ver. 8.0 Security System s B usiness D ivision Panasonic System N etw orks Co., Ltd. 2 ASE901 function (Option software for ASM
Member Profile. Deposit Insurance Agency (Russia)
SHARING DEPOSIT INSURANCE EXPERTISE WITH THE WORLD Member Profile Deposit Insurance Agency (Russia) The deposit insurance system of the Russian Federation was established on 27 Decem ber 2003, based on
Report of Follow-Up Survey Visit Wayland Baptist University in San Antonio, Texas Baccalaureate Degree Nursing Education Program
Agenda Item: 3.2.14. Prepared by: J. Hooper; S. Emerson Board Meeting: April 2013 Report of Follow-Up Survey Visit Wayland Baptist University in San Antonio, Texas Baccalaureate Degree Nursing Education
INTRODUCTION TO SOA GATEWAYS: BEST PRACTICES, BENEFITS & REQUIREMENTS
INTRODUCTION TO SOA GATEWAYS: BEST PRACTICES, BENEFITS & REQUIREMENTS Learn best practices and common deployment scenarios of SOA Gateways and why they are an essential component of a secure, robust and
Guide to Intel Rapid Storage
Guide to Intel Rapid Storage Overview I ntel Rapid Storage Technology provides new levels of protection, perform ance, and expandability for desktop and m obile platform s. Whether using one or m ultiple
Number of First Time Candidates (Passed/Total) 2011 83.08% 54/65 Full with W arning January 2012. 2010 78.95% 75/95 Conditional April 2011
Agenda Item: 3.2.8.b. Prepared by: J. Hooper Board Meeting: April 2013 Consideration for Change in Approval Status from Full with Warning to Full Valley Grande Institute in Weslaco, Texas Vocational Nursing
Penetration Testing. Module 20
Penetration Testing Module 20 Ethical Hacking and Countermeasures Penetration Testing P e n e t r a t i o n T e s t i n g M o d u le 2 0 Engineered by Hackers. Presented by Professionals. C E H E t h i
An Evaluation of the Performance Management System In an Irish Pharmaceutical Company
An Evaluation of the Performance Management System In an Irish Pharmaceutical Company By Siobhan Kennedy A dissertation submitted in partial fulfillment For a BA (Hons) in Human Resource Management National
Project Management Plan Outline ITSC
Project Management Plan Outline ITSC Date: 02/28/2012 Introduction At start of each project vendors must create a project management plan for ITSC approval, including, at a minimum, the sections described
Java Security Concepts Within I nsecure Networks
Diplom a Thesis Java Security Concepts Within I nsecure Networks I n the case of the SASI I project Author: Jürgen Leitner Markt 328 3184 Türnitz Examiner: Prof. Mag. Otto Reichel Period: September 2001
The personal records database:
The personal records database: for the authorities and for you The Municipal Personal Records Database 2 The personal records database: for the authorities and for you The Municipal Personal Records Database
Process Improvement. Process improvement. Process improvement stages. Understanding, Modelling and Improving the Software Process
Process Improvement Understanding, Modelling and Improving the Software Process Ian Sommerville 1995 Software Engineering, 5th edition. Chapter 31 Slide 1 Process improvement Understanding existing processes
Proposal to Establish A New Nursing Education Program South University in Austin, Texas Baccalaureate Degree Nursing Education Program
Proposal to Establish A New Nursing Education Program South University in Austin, Texas Baccalaureate Degree Nursing Education Program Agenda Item: 3.2.6.c. Prepared by: J. Hooper Board m eeting: July
LAUREA MAGISTRALE - CURRICULUM IN INTERNATIONAL MANAGEMENT, LEGISLATION AND SOCIETY. 1st TERM (14 SEPT - 27 NOV)
LAUREA MAGISTRALE - CURRICULUM IN INTERNATIONAL MANAGEMENT, LEGISLATION AND SOCIETY 1st TERM (14 SEPT - 27 NOV) Week 1 9.30-10.30 10.30-11.30 11.30-12.30 12.30-13.30 13.30-14.30 14.30-15.30 15.30-16.30
V2Soft Viki Software
V2Soft Viki Software Project Name: RAS-2005 (Restaurant Automation System) Project Id: 1 Document Name: RAS-2005 INITIAL DESIGN REPORT Document Id: 1-ID01 Document release: 1-ID01-1 Document Description:
Software Process Models. Xin Feng
Software Process Models Xin Feng Questions to Answer in Software Engineering? Questions to answer in software engineering What is the problem to be solved? Definition What are the characteristics of the
MindView Advanced Training Guide (PC)
MindView Advanced Training Guide (PC) How can MindView be used as a Study Skill tool by students? MindView is a mind mapping solution which can genuinely help students with their studies. Students using
Material Design and Production subprocess - 1/12
Material Design and Production subprocess - 1/12 MATERIAL DESIGN AND PRODUCTION MODELS M aterial design and production general m odel MATERIAL DESIGN MATERIAL PRODUCTION D1 P1 Specific processes of each
Session 6. Microsoft Project. Emanuele Della Valle. http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza
Session 6 Microsoft Project Emanuele Della Valle http://home.dei.polimi.it/dellavalle Lecturer: Dario Cerizza Credits 2 This slides are largely based on CEFRIEL s slides for PMI Certification and Prof.
(Refer Slide Time: 01:52)
Software Engineering Prof. N. L. Sarda Computer Science & Engineering Indian Institute of Technology, Bombay Lecture - 2 Introduction to Software Engineering Challenges, Process Models etc (Part 2) This
A bsenteeism and the Effectiveness o f A bsence M anagem ent Strategies - A study w ithin B ausch and Lom b. By Theresa Farrell
A bsenteeism and the Effectiveness o f A bsence M anagem ent Strategies - A study w ithin B ausch and Lom b By Theresa Farrell A dissertation submitted in part fulfilment of the B.A. (Hons) in Human Resource
Pr ojec t Por t folio Mana gem ent. and Progress Tracking. using Microsoft Project
Pr ojec t Por t folio Mana gem ent and Progress Tracking using Microsoft Project DOCUMENT TITLE: DOCUMENT IDENTIFIER: Project Portfolio Management & Progress Tracking using Microsoft Project.doc DOCUMENT
TABLE OF CONTENTS ABSTRACT ACKNOWLEDGEMENT LIST OF FIGURES LIST OF TABLES
TABLE OF CONTENTS ABSTRACT ACKNOWLEDGEMENT LIST OF FIGURES LIST OF TABLES ii iii x xiv CHAPTER 1: INTRODUCTION 1 1.0 Background 1 1.1 Research Motivation 4 1.2 Research Objectives 5 1.3 Project Scope 6
L iechtenstein L aw G azette
961.1 L iechtenstein L aw G azette Y ear 2006 N o. 125 published on 30 June 2006 L aw of 17 M ay 2006 on Insurance M ediation (Insurance M ediation A ct;im A ) I hereby grant m y consent to the follow
BANKRUPTCY EXEMPTION GUIDE - CALIFORNIA
BANKRUPTCY EXEMPTION GUIDE - CALIFORNIA Prepared By DAHL LAW, ATTORNEYS AT LAW 2304 N St, Sacram ento, CA 95816-5716 Tel: 916 446-8800 W eb: www.dahllaw.net 1999-2014 Disclaimer: This Bankruptcy Exem ption
The theory of environmental policy SECOND EDITION
The theory of environmental policy SECOND EDITION WILLIAM J. BAUMOLand WALLACE E. OATES The theory of environmental policy Second edition William J. Baumol Princeton and N ew York Universities Wallace
Unit R081 Pre-production skills. Work Plans and Production Schedules
Unit R081 Pre-production skills Work Plans and Production Schedules Instructions and answers for Teachers These instructions should accompany the OCR resource Work Plans and Production Schedules Activity,
To introduce software process models To describe three generic process models and when they may be used
Software Processes Objectives To introduce software process models To describe three generic process models and when they may be used To describe outline process models for requirements engineering, software
Software Engineering. Software Processes. Based on Software Engineering, 7 th Edition by Ian Sommerville
Software Engineering Software Processes Based on Software Engineering, 7 th Edition by Ian Sommerville Objectives To introduce software process models To describe three generic process models and when
CURRICULUM DEVELOPER
CURRICULUM DEVELOPER Job Description/ Specification (As-Needed/ Temporary Assignment) BASI C FUN CT I ON S Design s and develops curriculum content, training materials, training m od ules, teaching aids,
Project Management for Web-based Course Development
Project Management for Web-based Course Development Dong Li Rick Shearer Penn State University Project Management for Web-based Course Development Transferring face-to-face courses into Web-based courses
Overseas E-learning and Vocational Education in Au Stralia
InternationalDevelopm ents invocational Pathways: Lessons for Au stralia Phillip M ckenzie ACER and Monash University ACER Centre for the Econom ics of Educationand Training Presentationto the Conference
How To Work At Cornerstone Behavioral Health
CORNERSTONE Behavioral Health Mental Health and Substance Abuse Programs Client Handbook Revised: May 2012 Introduction W elcom e to Cornerstone Behavioral Health. Our m ission is to provide individual,
The Software Lifecycle. Software Lifecycles
The Software Lifecycle Examining the phases of large-scale software development projects Jeff Stephenson Software Lifecycles Software Engineering vs. Programming What you have done for our past assignments
Software Engineering. Project Management. Based on Software Engineering, 7 th Edition by Ian Sommerville
Software Engineering Project Management Based on Software Engineering, 7 th Edition by Ian Sommerville Objectives To explain the main tasks undertaken by project managers To introduce software project
MSc Project Planning
MSc Project Planning Dr Paul Brunn 4 th February 2009 Project Planning and Control Intro to General Methods Some simple examples How to plan and complete an MSc Dissertation project EPS Graduate Education
Organizing, planning and scheduling software projects
Project management Organizing, planning and scheduling software projects Ian Sommerville 1995 Modified by Spiros Mancoridis 1998 Software Engineering, 5th edition. Chapter 3 Slide 1 Objectives To introduce
Part-time Diploma in InfoComm and Digital Media (Information Systems) Certificate in Information Systems Course Schedule & Timetable
Certificate in Information Systems Course Schedule & Timetable Module Code Module Title Start Date End Date Coursework Final Exam PTDIS010101 Management Information Tue, April 16, 2013 Tue, 2 April 2013
Version 1.0. 2012 Devolutions inc.
Version 1.0 2 Remote Desktop Manager Server (Version 1.0) Table of Contents Foreword Part I Getting Started 0 4 1 What is... Remote Desktop Manager Server? 4 2 Features... 5 3 System... Requirements 6
Contents. Introduction and System Engineering 1. Introduction 2. Software Process and Methodology 16. System Engineering 53
Preface xvi Part I Introduction and System Engineering 1 Chapter 1 Introduction 2 1.1 What Is Software Engineering? 2 1.2 Why Software Engineering? 3 1.3 Software Life-Cycle Activities 4 1.3.1 Software
Proposal to Establish A New Nursing Education Program Chamberlain College of Nursing in Houston, Texas Baccalaureate Degree Nursing Education Program
Proposal to Establish A New Nursing Education Program Chamberlain College of Nursing in Houston, Texas Baccalaureate Degree Nursing Education Program Agenda Item: 3.2.11.b. Prepared by: V. Ayars/R. Caldwell
Software Engineering. Software Development Process Models. Lecturer: Giuseppe Santucci
Software Engineering Software Development Process Models Lecturer: Giuseppe Santucci Summary Modeling the Software Process Generic Software Process Models Waterfall model Process Iteration Incremental
Requirements Analysis Concepts & Principles. Instructor: Dr. Jerry Gao
Requirements Analysis Concepts & Principles Instructor: Dr. Jerry Gao Requirements Analysis Concepts and Principles - Requirements Analysis - Communication Techniques - Initiating the Process - Facilitated
Case 1:15-cr-20296-JEM Document 15 Entered on FLSD Docket 06/11/2015 Page 1 of 6 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA
Case 1:15-cr-20296-JEM Document 15 Entered on FLSD Docket 06/11/2015 Page 1 of 6 UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF FLORIDA CA SE NO. 15-CR-20296-JEM UNITED STATES OF AMERICA 5'S. JEFFREY
HR s Role in Maintaining Employee Engagement during a Merger, Acquisition or Demerger. Emily Pierse. Masters in Human Resource Management
HR s Role in Maintaining Employee Engagement during a Merger, Acquisition or Demerger Emily Pierse Masters in Human Resource Management National College of Ireland MAHRM National College of Ireland 2012
Chapter 1 - Forzip at a Glance
Chapter 1 - Forzip at a Glance Forzip is the software designed to enhance card production quality and volumes, adding constantly evolving technologies demanded by production bureaus and providing management
ProGUM-Web: Tool Support for Model-Based Development of Web Applications
ProGUM-Web: Tool Support for Model-Based Development of Web Applications Marc Lohmann 1, Stefan Sauer 1, and Tim Schattkowsky 2 1 University of Paderborn, Computer Science, D 33095 Paderborn, Germany {mlohmann,sauer}@upb.de
Software Quality Requirements and Evaluation, the ISO 25000 Series
Pittsburgh, PA 15213-3890 Software Quality Requirements and Evaluation, the ISO 25000 Series PSM Technical Working Group February 2004 Dave Zubrow Sponsored by the U.S. Department of Defense Background
Life Cycle Models. V. Paúl Pauca. CSC 331-631 Fall 2013. Department of Computer Science Wake Forest University. Object Oriented Software Engineering
Life Cycle Models V. Paúl Pauca Department of Computer Science Wake Forest University CSC 331-631 Fall 2013 Software Life Cycle The overall framework in which software is conceived, developed, and maintained.
Microsoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
UML-based Test Generation and Execution
UML-based Test Generation and Execution Jean Hartmann, Marlon Vieira, Herb Foster, Axel Ruder Siemens Corporate Research, Inc. 755 College Road East Princeton NJ 08540, USA [email protected] ABSTRACT
Peach State Reserves 40 1(k) and 457 Plans
Peach State Reserves 40 1(k) and 457 Plans W hy save w ith Peach State Reserves? (PSR) Answer: 25% of your life could be spent in retirem ent You could leave em ploym ent with the state before you re vested
PROPOSAL TO ESTABLISH A NEW VOCATIONAL NURSING EDUCATIONAL PROGRAM MEDVANCE INSTITUTE - GRAND PRAIRIE VOCATIONAL NURSING EDUCATIONAL PROGRAM
Agenda Item: 3.2.5 Prepared by: P. W aller/ R. Gibbs Board Meeting: October 2009 PROPOSAL TO ESTABLISH A NEW VOCATIONAL NURSING EDUCATIONAL PROGRAM MEDVANCE INSTITUTE - GRAND PRAIRIE VOCATIONAL NURSING
Consideration for Change of Approval Status from Initial to Full Approval RGV Careers in Pharr, Texas Vocational Nursing Education Program
Prepared by: V. Ayars Board Meeting: April 2012 Consideration for Change of Approval Status from Initial to Full Approval RGV Careers in Pharr, Texas Vocational Nursing Education Program Summary of Request:
Organising, planning and scheduling software projects. Software management distinctions
Project management Organising, planning and scheduling software projects Software management distinctions The product is intangible The product is uniquely flexible Software engineering is not recognized
CHAPTER 1 INTRODUCTION
CHAPTER 1 INTRODUCTION 1.1 Overview Web Content Management Systems (WCMS) consist of applications used to create, manage, store and deploy content on the Web, including text, graphics, video or audio,
Module 2. Software Life Cycle Model. Version 2 CSE IIT, Kharagpur
Module 2 Software Life Cycle Model Lesson 3 Basics of Software Life Cycle and Waterfall Model Specific Instructional Objectives At the end of this lesson the student will be able to: Explain what is a
SLIM Estimate and Microsoft Project Best Practices
SLIM Estimate and Microsoft Project Best Practices There are many activities to perform during the life of a software development project. No single tool provides all of the functionality or data that
INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9
Contents Contents INTRODUCTION 5 COLLABORATION RIBBON 5 SELECT THE UPDATING METHOD 6 MAKE YOUR PROJECT COLLABORATIVE 8 PROCESSING RECEIVED TASK UPDATES 9 IMPORT UPDATES 12 CUSTOM TEXT FIELDS MAPPING 13
How To Use Rittal'S Rizone
RiZone Data Centre Infrastructure Management Enclosures Power Distribution Climate Control IT INFRASTRUcTURe SOFTWARE & SERVICEs RiZone Data Centre Infrastructure Management What can the RiZone Data Centre
Maureen A. Madden RN MSN PCCNP FCCM Pediatric Critical Care Nurse Practitioner Bristol- Myers Squibb Children s s Hospital Assistant Professor of
Maureen A. Madden RN MSN PCCNP FCCM Pediatric Critical Care Nurse Practitioner Bristol- Myers Squibb Children s s Hospital Assistant Professor of Pediatrics UMDNJ- Robert Wood Johnson Medical School New
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
CANADIAN FOOD INSPECTION AGENCY (CFIA) AUTOMATED IMPORT SYSTEM (AIS) PARTICIPANTS INFORMATION DOCUMENT (PID)
CANADIAN FOOD INSPECTION AGENCY (CFIA) AUTOMATED IMPORT SYSTEM (AIS) PARTICIPANTS INFORMATION DOCUMENT (PID) Release Date: January 2007 TABLE OF CONTENTS 1.0 INTRODUCTION... 1 1.1 Contact List... 2 2.0
Assignment 2: Microsoft Project Toolset. Eric Palmer & Mahindra Bheodari. Kennesaw State University. IS 8100 Spring 2015
Assignment 2: Microsoft Project Toolset 1 Assignment 2: Microsoft Project Toolset Eric Palmer & Mahindra Bheodari Kennesaw State University IS 8100 Spring 2015 Assignment 2: Microsoft Project Toolset 2
Process Methodology. Wegmans Deli Kiosk. for. Version 1.0. Prepared by DELI-cious Developers. Rochester Institute of Technology
Process Methodology for Wegmans Deli Kiosk Version 1.0 Prepared by DELI-cious Developers Rochester Institute of Technology September 15, 2013 1 Table of Contents 1. Process... 3 1.1 Choice... 3 1.2 Description...