1 Optimizing Mega Project Execution with Integrated Interface Management and Project Scheduling By: Sandra MacGillivray VP, Product & Marketing

2 Introduction In today s mega projects, implementing a collaborative interface management program is critical to achieving alignment between project stakeholders and to reduce interface-related project risk. Best practices have been established for the systematic identification of interface points and interface agreements (see Figure 1), and the collaboration between contractors for the management of interfaces throughout the project lifecycle. Similarly, project controls for interface management have matured such that a project owner and each of the major contractors involved in an integrated interface management program can easily monitor scope, progress, quality and change requests. The next level of maturity for a collaborative interface management program is to achieve systematic monitoring of schedule impact by all project stakeholders. The best strategy to achieve this level of control is to enable each project stakeholder to integrate high risk interface points, managed in the Interface Management Solution (IMS), as milestone activities within its respective organization s project schedule. Properly executed, this ensures Figure 1: Interface Elements Managed Throughout the Project Lifecycle that interface-related schedule risk can more easily be identified by each contractor and the project owner, and that an efficient process exists to resolve interface-related schedule issues. This strategy also standardizes the project controls used to monitor unresolved interface-related schedule issues by Interface Managers and Project Planners at each stakeholder s organization. This paper will outline how interface management programs and project scheduling can come together to significantly reduce interface-related project risk. The Problem The contracting strategy used by project owners of today s mega projects normally results in the multiple scope packages being awarded to multiple contractors that are geographically dispersed. This is executed with the objective of minimizing both technical and delivery risk to the overall project. Consider a deepwater gas field project as outlined in Figure 2. The main scope packages typically include: Topsides development of the superstructure of the production facility Subsea hookup of subsea installations, tiebacks, risers, etc Onshore facilities Offshore Pipelines Figure 2: Example of Deepwater Gas Field Project 1 Page 2

3 Interface Management in mega projects starts with the identification of interface points early in the project life cycle, and identifying these project interfaces for each scope package. These may be physical, commercial or environmental in nature. Interface points can be internal to a scope package, or external (existing between different contractors and scope packages). External iterface points normally represent higher risk to the project because of the increased coordination required to establish and execute the associated interface agreements. Therefore, external interface points should normally be tracked in a project schedule. A master project schedule is managed by either the project owner, or commonly by a project management consultant (PMC) representing the owner, who is experienced in managing mega projects with international contractors. Despite significant advances in integrated project management practices, separate project schedules are almost always maintained by every contractor involved in the mega project. This increases the complexity of identifying the schedule impact of interface points, since schedule issues could arise in the master project schedule, or in any of the contractors involved with an interface point. Without a strategy that allows each stakeholder to easily integrate their interface points into their respective project schedule, and communicate interface-related schedule risk with other project stakeholders, substantial reduction in interface-related risk through schedule integration is difficult to achieve. The Solution If the project owner adopts one system of record for their Interface Management program that is shared by the contractors responsible for all major scope packages, high risk interface points can be identified, and schedule risk can be easily monitored by each stakeholder that is impacted. For maximum impact, every project stakeholder maintaining a project schedule with dependencies on interfaces should follow this general process: 1. Identify High Risk Interface Points. Throughout the project life-cycle, each impacted stakeholder (the project owner or PMC and all contractors) will monitor their interface points and may at any time flag an interface point as high-risk. A typical interface breakdown structure (IBS) includes: Level 1 - the interface point Level 2 - the project phase (e.g. design, procurement, construction, commissioning) Level 3 - the interface agreement that rolls up to an interface point, and relates to a specific phase of the project. Interface Manager Project Planner Integrating Interface Management & Project Scheduling Identify High Risk IPs Export IP Schedule Import IP Schedule New IP Milestones? No Yes Identify IP Milestone Dependencies Create IP Milestone dependencies Perform Critical Path Analysis Legend IP Need Date Changes Required? Review Schedule Variance Report Activity Changes Required? Update Activity Details Scheduling Software Figure 3: Integration of Interface Management & Project Scheduling Solutions Create Change Requests Monitor IP s with rejected change requests Monitor activities & milestones with schedule issues Interface Management Software While there is no universal agreement on how the levels of a project work breakdown structure (WBS) are defined, in general, level two of the IBS aligns well with level three of the WBS in a project schedule. This means monitoring the forecasted finish date of an interface point for a specific phase in the project schedule. Focusing on interface agreements would require integration at a level five or six in the project WBS, with substantially more maintenance to integrate your IMS and your project schedule. Page 3

4 2. Export Interface Point Schedule from the IMS. On a regular basis, each stakeholder s Interface Manager exports their high risk interface point list, along with the interface point s forecasted finish date by phase. This is provided to the stakeholder s Project Planner. 3. Import Interface Point Schedule into the Project Schedule. On a regular basis, each stakeholder s Project Planner will import the interface point schedule updates and perform the following: a. Add new milestones for interface point phases. Any new milestones created are reviewed with their Interface Manager to identify dependencies with other project activities (Figure 4). b. Update interface point milestones in the project schedule. The interface point s phase forecasted finish date is assigned as the milestone finish date. c. Assess impact to the critical path. As part of the Project Planner s regular analysis of the critical path, any impact cause by an interface point, or impacting an interface point is identified, assessed and reported back to their Interface Manager. Figure 4: IP Milestone Schedule 4. Identify Project Schedule Issues. The stakeholder s Interface Manager must evaluate options to avoid or mitigate the schedule impact of an interface point discrepancy with their project schedule. This starts by drilling down in the IMS to understand the specific interface agreements within the project phase that are impacted, or into the project schedule to understand the specific project activities that are impacted. The stakeholder s Interface Manager will attempt to resolve schedule issues within their internal project team. 5. Initiate a Change Request in the IMS. When interface-related schedule issues cannot be resolved by the contractor, their Interface Manager will initiate a request to change the interface agreements need date in the IMS to align with their project schedule (being maintained separately from the project s master schedule). If the change request is approved by the other contractor, the interface agreement need date is updated. If it is rejected, the interface agreement need date remains unchanged, but the schedule risk is fully disclosed to all parties, and the risk can easily be monitored in the IMS. 6. Monitor Schedule Discrepancies in the IMS. Each stakeholder s Interface Manager uses the IMS dashboard to monitor all rejected change requests that pose risk to their organization s project schedule. 7. Monitor Schedule Issues in Project Schedule. Each contractor s project planner will monitor interface points, by phase, with unresolved schedule issues such that interface-related risk is reported and stewarded in the standard project schedule reports. Page 4

5 The Impact The following two scenarios represent typical interfaces in an industrial mega project. Both demonstrate the positive impact of collaboration on interfaces between contractors, as well as the value of integrating high risk interface points with each stakeholder s project schedule. 1. Design Phase Interface Scenario During design phase, the delay in completion of a key interface agreement impacts a critical path activity for another contractor. Interface Breakdown Structure Level 1 Interface Point Level 2 Phase Level 3 Interface Agreement An interface point is being managed for a terminating pipe that spans two scope packages. Two contractors are involved one for each scope package that the pipe spans. Design A key interface agreement is created for Contractor A to confirm their specifications for the high pressure titanium piping material for Contractor B. A need date is agreed upon early in the design phase. The interface agreement s need date is the latest in the phase indicating the forecasted date of completion for the interface point s design phase. If Contractor A does not complete the interface agreement by the need date, Contractor B s Interface Manager is automatically notified by the IMS. The Project Planner for Contractor B can identify the schedule slippage related to the interface point through the IP Schedule update and determine the impact on dependent project activities including procurement of the long lead time titanium piping. Impact Without integration of Contractor A s interface point milestone dates into Contractor B s project schedule, and identification of the dependencies at the interface point, Contractor B s project planner would never have been aware of the schedule impact of this subtle, but critical Interface agreement to confirm piping specifications. By immediately identifying a delay, Contractor B s Project Planner can notify their Procurement contact of this schedule impact on procurement of the long lead time titanium. Procurement can contact their Interface Manager to discuss how to expedite completion of the interface point with Contractor A. 2. Commissioning Phase Interface Scenario During commissioning phase, the delay in material delivery for Contractor A results in a delay of an interface point that impacts Contractor B. Scenario An interface point between two scope packages at a flanged joint is identified as high risk in the IMS by both Contractor A and Contractor B. The Interface Managers for both contractors have worked with their respective project planners to add this as a milestone into their organization s project schedule. Late in the construction phase, the delivery of required piping material is delayed for Contractor A. The schedule variance report created by Contractor A identifies that this delay will impact the interface point milestone and reports the issue Interface Breakdown Structure Level 1 Interface Point Level 2 Phase Level 3 Interface Agreement An interface point is being managed for testing of a flanged joint on piping between two scope packages. Two contractors are involved one for each scope package the pipe spans. (Figure 5) Commissioning Several interface agreements are created for the commissioning phase, including one where Contractor A and Contractor B agree upon the need date and details of how each contractor will complete commissioning tightness testing for the flanged joint. Page 5

6 to their Interface Manager. Contractor A s Interface Manager investigates this issue and identifies the specific interface agreement that will be impacted and requests the change to the need, including details of the procurement delay that is driving the change request. Contractor B s Interface Manager reviews the change request, approves and the interface agreement s need is updated. Figure 5: Piping interface Impact Without integration of the IMS and the contractor s project schedule, Contractor A would not have even been aware of the impact on the Interface Agreement in time to initiate a change request and disclose the schedule issue Contractor B. Conclusion Significant reduction in interface-related project risk in mega projects can be achieved by integration of your interface management and project scheduling solutions. However, it requires the commitment of all stakeholders. The critical success factors to achieve this goal include: Alignment of all project stakeholders on the importance of identifying high risk interface points, monitoring for interface-related schedule issues, and collaborating to resolve these. Integration with all project schedules - the project owner or PMC, and each major contractor. Selecting a manageable level of integration between your projects IBS and each stakeholders WBS. Creating a standard operating procedure on how an Interface Manager and Project Planner work collaboratively to monitor and resolve interface-related schedule issues. About Coreworx A proven web-based enterprise software system, Coreworx enables EPCs and owner-operators to automate best practices, mitigate business risk and improve performance to budget throughout the entire project lifecycle. Coreworx solutions integrate with existing systems for accelerated project stand up to quickly ensure the controlled distribution of information, management of asset integrity, design control and configuration management. Real-time analysis ensures accurate, predictive project data to keep projects on schedule, accurate and within scope. Founded in 1997, Coreworx services a portfolio of projects valued at over $500 billion across more than 50 countries, on more than 600 capital projects with nearly 70,000 users and offices in Kitchener, Calgary, Halifax, Houston (USA) and Perth (Australia). CWXPS 2013/03 Page 6

Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry

Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry By: Arash Shahi Senior Product Manager, Coreworx 519-772-3181 Contents Executive Summary 3 Background 4

More information

Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas

Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas Industry Solutions Oil and Gas Engineering Document Control and Project Collaboration Solutions for Oil and Gas Industry Solutions Managing the complexity of major capital projects in today s oil and gas

More information

ORACLE PROJECT MANAGEMENT

ORACLE PROJECT MANAGEMENT ORACLE PROJECT MANAGEMENT KEY FEATURES Oracle Project Management provides project managers the WORK MANAGEMENT Define the workplan and associated resources; publish and maintain versions View your schedule,

More information

OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc.

OTC 12979. Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. OTC 12979 Managing the Cost & Schedule Risk of Offshore Development Projects Richard E. Westney Westney Project Services, Inc. Copyright 2001, Offshore Technology Conference This paper was prepared for

More information

ORACLE PROJECT PLANNING AND CONTROL

ORACLE PROJECT PLANNING AND CONTROL ORACLE PROJECT PLANNING AND CONTROL (Formerly Oracle Project Management) KEY FEATURES COLLABORATIVE PROJECT PLANNING Define a project work breakdown structure to align plans to execution Coordinate financial

More information

HEDCO Total Management Solution

HEDCO Total Management Solution HEDCO Total Management Solution Project Management & Control Document Management Procurement Management Construction Management In HEDCO We Believe in IT INFORMATION MANAGEMENT & SOFTWARE APPLICATIONS

More information

Planet LifeCycle Integrated Platform for Achieving Research and Development Program Management Excellence. www.dataformsoftware.

Planet LifeCycle Integrated Platform for Achieving Research and Development Program Management Excellence. www.dataformsoftware. Planet LifeCycle Integrated Platform for Achieving Research and Development Program Management Excellence www.dataformsoftware.com Planet allows cross-functional pharmaceutical R&D teams to achieve agility

More information

Industry Solutions Process Manufacturing Flexible and Agile Engineering Document Control for Efficient, Safe and Compliant Plants

Industry Solutions Process Manufacturing Flexible and Agile Engineering Document Control for Efficient, Safe and Compliant Plants Industry Solutions Process Manufacturing Flexible and Agile Engineering Document Control for Efficient, Safe and Compliant Plants Industry Solutions Key Challenges Facing Process Manufacturing High energy

More information

project portfolio management Effectively plan, manage, and control projects and resources Planview Enterprise Planview Project Portfolio Management

project portfolio management Effectively plan, manage, and control projects and resources Planview Enterprise Planview Project Portfolio Management project portfolio management Effectively plan, manage, and control projects and resources Planview Project Portfolio Management gives you the tools you need to effectively manage projects and resources

More information

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter

5.1 4.1 4.2 4.3 PROCESS GROUP: PLANNING PROCESS GROUP: INITIATION. Oracle Projects. PMBOK Oracle Mapping. Scope Planning. Develop Project Charter Develop Project Charter Develop Preliminary Project Scope Statement Develop Project Management Plan Scope Planning PROCESS GROUP: INITIATION 4.1 The project charter serves as the input document for the

More information

See What's Coming in Oracle Project Portfolio Management Cloud

See What's Coming in Oracle Project Portfolio Management Cloud See What's Coming in Oracle Project Portfolio Management Cloud Release 9 Release Content Document Table of Contents GRANTS MANAGEMENT... 4 Collaborate Socially on Awards Using Oracle Social Network...

More information

An Oracle White Paper August, 2010. Enhancing the Construction Process for Energy Companies to Increase ROI & Improve Cash Flow

An Oracle White Paper August, 2010. Enhancing the Construction Process for Energy Companies to Increase ROI & Improve Cash Flow An Oracle White Paper August, 2010 Enhancing the Construction Process for Energy Companies to Increase ROI & Improve Cash Flow Executive Overview An increasingly complex and volatile business environment

More information

Project Management Certificate (IT Professionals)

Project Management Certificate (IT Professionals) Project Management Certificate (IT Professionals) Whether your field is architecture or information technology, successful planning involves a carefully crafted set of steps to planned and measurable goals.

More information

BROCHURE ECOSYS EPC. Full Lifecycle Project Cost Controls

BROCHURE ECOSYS EPC. Full Lifecycle Project Cost Controls BROCHURE ECOSYS EPC Full Lifecycle Project Cost Controls ECOSYS EPC EcoSys EPC is a next generation planning and cost controls software solution delivering best practices for full lifecycle project cost

More information

Industry Solutions Construction Project Collaboration and Document Control Solutions for the Construction Sector

Industry Solutions Construction Project Collaboration and Document Control Solutions for the Construction Sector Industry Solutions Project Collaboration and Document Control Solutions for the Sector Industry Solutions McLaren Software Setting Standards New Opportunities, New Challenges Whether it be architects,

More information

Technology based Project Management Consulting (T-PMC): Innovate to Reduce Costs

Technology based Project Management Consulting (T-PMC): Innovate to Reduce Costs Technology based Project Management Consulting (T-PMC): Innovate to Reduce Costs Graham Freeth, North African Oil and Gas Summit, Tunis, Tunisia October 2009 J P Kenny Offices World Wide Aberdeen Stavanger

More information

Data Governance Center Positioning

Data Governance Center Positioning Data Governance Center Positioning Collibra Capabilities & Positioning Data Governance Council: Governance Operating Model Data Governance Organization Roles & Responsibilities Processes & Workflow Asset

More information

Evolution of Information Management & Strategies for Tomorrow

Evolution of Information Management & Strategies for Tomorrow Houston, 2 June 2010 Evolution of Information Management & Strategies for Tomorrow Stephen Airey MBA in Project Management (Cranfield), Chartered Engineer Today s Agenda Information Management What is

More information

SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING. Mikhail Hanna Janaka Y. Ruwanpura

SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING. Mikhail Hanna Janaka Y. Ruwanpura Proceedings of the 2007 Winter Simulation Conference S. G. Henderson, B. Biller, M.-H. Hsieh, J. Shortle, J. D. Tew, and R. R. Barton, eds. SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING

More information

Migration Planning and Execution:

Migration Planning and Execution: WHITE PAPER: FDCCI INDUSTRY DAY MIGRATION PLANNING AND EXECUTION Migration Planning and Execution: CA Technologies Services for Effective Data Center Consolidation SEPTEMBER 2011 Table of Contents Executive

More information

Enterprise Solutions for Engineering Consultancy Firms

Enterprise Solutions for Engineering Consultancy Firms Professional Services Enterprise Solutions for Engineering Consultancy Firms The business processes within consultancies that provide multi-disciplinary engineering and technical services to their clients

More information

Total Subsea Solutions

Total Subsea Solutions Total Subsea Solutions Total Subsea Solutions Developing new energy reserves, managing, and improving producing fields means an unprecedented number of technical challenges. In partnership with our customers,

More information

PMO Metrics Recommendations

PMO Metrics Recommendations Introduction The purpose of this document is to recommend metrics to be used by the Project Management Office (PMO) to measure and analyze their project and PMO success. The metrics are divided into Project

More information

EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies

EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies EST.491 Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies Nicolas Alexander Hall and Sarah Delille, PE ABSTRACT Usually, when a company has a history of successfully planning

More information

Analytics for Oil & Gas

Analytics for Oil & Gas Analytics for Oil & Gas Table of Contents Project Delivery. 3 Sales & Operations. 5 Resources. 8 Finance. 10 Contact Us. 14 2 Are you tracking and maximizing the profitability of every project? Don t let

More information

SOLUTION BRIEF: CA CLARITY PPM ON DEMAND. How can I quickly deploy applications across a complex enterprise?

SOLUTION BRIEF: CA CLARITY PPM ON DEMAND. How can I quickly deploy applications across a complex enterprise? SOLUTION BRIEF: CA CLARITY PPM ON DEMAND How can I quickly deploy applications across a complex enterprise? CA Clarity PPM On Demand is a SaaS-based Project and Portfolio Management (PPM) solution that

More information

Using the Proxy NPV Model for Value-Based Strategic Decisions

Using the Proxy NPV Model for Value-Based Strategic Decisions Using the Proxy NPV Model for Value-Based Strategic Decisions January 2011 Westney Consulting Group, Inc. www.westney.com The Importance of Value-Based Development Decisions The Influence Curve has long

More information

The power to consider all of your organization s projects and investments in terms of the common objective: Achieving your business goals.

The power to consider all of your organization s projects and investments in terms of the common objective: Achieving your business goals. The power to consider all of your organization s projects and investments in terms of the common objective: Achieving your business goals Mariner by As one of the earliest and largest users of Mariner

More information

Bringing Control to Global Supply Management Business Process Management (BPM) and Advanced Project Management Practices

Bringing Control to Global Supply Management Business Process Management (BPM) and Advanced Project Management Practices Bringing Control to Global Supply Management Business Process Management (BPM) and Advanced Project Management Practices Jason Klemow, CTP, Partner The JK Group 301/948-2134; Jason@TheJKGroup.com Francine

More information

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT)

OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) OPERATIONAL PROJECT MANAGEMENT (USING MS PROJECT) 3 DAY COURSE INTRODUCTION The principles of project management are generic and therefore can be applied to all projects regardless of business sector.

More information

Transforming Enterprise

Transforming Enterprise Transforming Enterprise OpenERP Solutions www.apagen.com About Apagen Appearance Apagen Solutions, head office is based out of Delhi Apagen is a sister concern of Enventa Group Track record of world class

More information

PRIMAVERA CONTRACT MANAGEMENT

PRIMAVERA CONTRACT MANAGEMENT PRIMAVERA CONTRACT MANAGEMENT Completing projects on schedule and within budget demands complete project control. Primavera Contract Management from KEY FEATURES NEW: Updated User Interface NEW: Content

More information

Seven Reasons to Use PlanView for Timesheets

Seven Reasons to Use PlanView for Timesheets Seven Reasons to Use PlanView for Timesheets Background Business professionals often face the tough job of choosing the right timesheet system for their enterprise. The wrong system can lead to lost productivity,

More information

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE

SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE SECTION 01310 COST LOADED CRITICAL PATH SCHEDULE 1.0 General 1.1 Description The Work specified in this Section consists of developing and maintaining an accurate cost loaded critical path schedule in

More information

Introductory Certificate. The APM Project Fundamentals Qualification

Introductory Certificate. The APM Project Fundamentals Qualification The syllabus provides a summary of the coverage of the qualification, the details are then found in the learning outcomes and assessment criteria. Both the syllabus and the learning outcomes and assessment

More information

Effective Materials Management

Effective Materials Management WHITE PAPER Effective Materials Management Reducing Costs and Improving Procurement Efficiency Contents 1. Introduction... 1 2. Industry Challenges... 2 3. Business Benefits... 3 3.1 Managing Reference

More information

PeopleSoft Program Management

PeopleSoft Program Management PeopleSoft Program Management Large enterprises and project-based organizations have long recognized the value of leveraging project knowledge across multiple projects. Yet today, 50 percent of IT projects

More information

CA Clarity Project & Portfolio Manager

CA Clarity Project & Portfolio Manager CA Clarity Project & Portfolio Manager Project Management User Guide v12.1.0 This documentation and any related computer software help programs (hereinafter referred to as the "Documentation") are for

More information

SOLUTION BRIEF: CA CLARITY GRANTS MANAGER. CA Clarity Grants Manager

SOLUTION BRIEF: CA CLARITY GRANTS MANAGER. CA Clarity Grants Manager SOLUTION BRIEF: CA CLARITY GRANTS MANAGER CA Clarity Grants Manager Q: How Can I Manage the Entire Grants Lifecycle and Meet My Reporting and Transparency Requirements? A: CA Clarity Grants Manager helps

More information

E X C E RPT I D C M a r k e tscape: Project Portfolio M a nagement Solutions in the Worldwide O i l a n d Gas Industry

E X C E RPT I D C M a r k e tscape: Project Portfolio M a nagement Solutions in the Worldwide O i l a n d Gas Industry E X C E RPT I D C M a r k e tscape: Project Portfolio M a nagement Solutions in the Worldwide O i l a n d Gas Industry I D C E n e r g y I n s i g h t s : W o r l d w i d e O i l a n d G a s I T S t r

More information

NE-50413B Mastering Microsoft Project 2010

NE-50413B Mastering Microsoft Project 2010 NE-50413B Mastering Microsoft Project 2010 Summary Duration Vendor 3 Days Microsoft Audience This course is intended for both novice and experienced Project Managers and project support personnel who need

More information

INFORMATION CONNECTED

INFORMATION CONNECTED INFORMATION CONNECTED Business Solutions for the Utilities Industry Primavera Project Portfolio Management Solutions Achieve Operational Excellence with Robust Project Portfolio Management Solutions The

More information

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS

TECHNIQUES FOR MANAGING COMPLEX PROJECTS WITH PLANNING AND SCHEDULING SOFTWARE PAUL E HARRIS EASTWOOD HARRIS P.O. Box 4032 EASTWOOD HARRIS PTY LTD Tel 61 (0)4 1118 7701 Doncaster Heights ACN 085 065 872 Fax 61 (0)3 9846 7700 Victoria 3109 Project Management Systems Email: harrispe@eh.com.au Australia Software

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

Earned Value Management and Professional Services Automation

Earned Value Management and Professional Services Automation Earned Value Management and Professional Services Automation Prepared by: Frances B. Craig Unanet Technologies www.unanet.com 1 of 5 Earned Value Management and Professional Services Automation Earned

More information

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE

ITRM Guideline CPM 110-01 Date: January 23, 2006 SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE PROJECT MANAGEMENT GUIDELINE SECTION 4 - PROJECT EXECUTION AND CONTROL PHASE Table of Contents Introduction... 3 Project Execution and Control Phase Overview... 3 Activities and Documents in the Execution

More information

Monitoring capital projects and addressing signs of trouble

Monitoring capital projects and addressing signs of trouble /01 / Leadership Series 6 PROJECT ADVISORY Monitoring capital projects and addressing signs of trouble Leadership Series 6 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards

More information

SALES AND OPERATIONS PLANNING BLUEPRINT BUSINESS VALUE GUIDE

SALES AND OPERATIONS PLANNING BLUEPRINT BUSINESS VALUE GUIDE Business Value Guide SALES AND OPERATIONS PLANNING BLUEPRINT BUSINESS VALUE GUIDE INTRODUCTION What if it were possible to tightly link sales, marketing, supply chain, manufacturing and finance, so that

More information

Interface Management. Effective information exchange through improved communication. ABB Value Paper Series

Interface Management. Effective information exchange through improved communication. ABB Value Paper Series Interface Management Effective information exchange through improved communication ABB Value Paper Series Interface Management Effective information exchange through improved communication by Josh Caglar,

More information

Mastering Microsoft Project 2013

Mastering Microsoft Project 2013 Course 55054: Mastering Microsoft Project 2013 Page 1 of 9 Mastering Microsoft Project 2013 Course 55054: 2 days; Instructor-Led Introduction This two-day, instructor-led course is intended for individuals

More information

Reducing Risk in Large-scale Process Automation Projects

Reducing Risk in Large-scale Process Automation Projects White Paper Reducing Risk in Large-scale Process Automation Projects Author: Harald Konermann, Vice President Global Delivery & Vice President EMEA What s Inside: 1. Clear delineation of roles and responsibilities

More information

Time Management. Herb Pollard III

Time Management. Herb Pollard III Time Management A Small Business Perspective Herb Pollard III Project Manager for Time Management - Pollard PMI Slide 1 Introduction: Time Management - Pollard PMI Slide 2 Project Phases and the Areas

More information

Asta Powerproject POWERFUL PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOFTWARE. www.astadev.com

Asta Powerproject POWERFUL PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOFTWARE. www.astadev.com Asta Powerproject POWERFUL PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOFTWARE www.astadev.com WHY INVEST IN A PROJECT, PORTFOLIO AND RESOURCE MANAGEMENT SOLUTION? Today s management challenges need innovative

More information

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days

Mastering Microsoft Project 2013 Course: 55054A Course Length: 3 Days 3 Riverchase Office Plaza Hoover, Alabama 35244 Phone: 205.989.4944 Fax: 855.317.2187 E-Mail: rwhitney@discoveritt.com Web: www.discoveritt.com Mastering Microsoft Project 2013 Course: 55054A Course Length:

More information

Technip Data Management Journey. IPMA Italy. Jean-Luc Brunat VP, Business Support Functions & Group Data Systems Group IT. Rome, December 3 rd 2013

Technip Data Management Journey. IPMA Italy. Jean-Luc Brunat VP, Business Support Functions & Group Data Systems Group IT. Rome, December 3 rd 2013 Technip Data Management Journey IPMA Italy Jean-Luc Brunat VP, Business Support Functions & Group Data Systems Group IT Rome, December 3 rd 2013 1 Sezione Informatica This is Business Intelligence! 2 What

More information

Dashboards and Reporting for Program Management

Dashboards and Reporting for Program Management MnDOT Project Management Office Presents: Dashboards and Reporting for Program Management Presenter: Jonathan McNatty Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will

More information

O I L & G A S L O G I S T I C S

O I L & G A S L O G I S T I C S OIL & GAS LOGISTICS OIL & GAS LOGISTICS THE OIL AND GAS INDUSTRY DEMANDS THE HIGHEST STANDARDS IN LOGISTICS MANAGEMENT. THE COMPLEXITY AND SCALE OF THE PROJECTS, IN SOME OF THE WORLD S MOST DIFFICULT

More information

Engineering and technologies Floating LNG

Engineering and technologies Floating LNG Engineering and technologies Floating LNG Major contracts confirm Technip's leadership Technip at a glance Technip is a world leader in project management, engineering and construction for the oil and

More information

MNLARS Project Audit Checklist

MNLARS Project Audit Checklist Audit Checklist The following provides a detailed checklist to assist the audit team in reviewing the health of a project. Relevance (at this time) How relevant is this attribute to this project or audit?

More information

PROCUREMENT, FABRICATION & CONSTRUCTION

PROCUREMENT, FABRICATION & CONSTRUCTION SmartPlant Enterprise PROCUREMENT, FABRICATION & CONSTRUCTION 2 Balancing Act PROCUREMENT, FABRICATION, AND CONSTRUCTION represent a complex balancing act between profit-making and risk-taking that requires

More information

One trusted platform. All your project information.

One trusted platform. All your project information. One trusted platform. All your project information. The most trusted and widely used online collaboration platform for engineering and construction projects. New York City Hall Reconstruction New York

More information

ORACLE S PRIMAVERA CONTRACT MANAGEMENT, BUSINESS INTELLIGENCE PUBLISHER EDITION

ORACLE S PRIMAVERA CONTRACT MANAGEMENT, BUSINESS INTELLIGENCE PUBLISHER EDITION ORACLE S PRIMAVERA CONTRACT MANAGEMENT, BUSINESS INTELLIGENCE PUBLISHER EDITION KEY FEATURES NEW: Oracle BI Publisher NEW: UPK Support NEW: Technology Enhancements NEW: Web Services Powerful dashboards

More information

Our business approach Technip PMC

Our business approach Technip PMC Our business approach Technip PMC Project Management Consultancy Services: Ensuring Safe and Successful Execution of Your Projects Technip at a glance Technip is a world leader in project management, engineering

More information

Turnaround / Shutdown Management with SAP Enterprise Asset Management Dean Fitt

Turnaround / Shutdown Management with SAP Enterprise Asset Management Dean Fitt Turnaround / Shutdown Management with SAP Enterprise Asset Management Dean Fitt SAP AG A collaboration of: What I ll Cover SAP Enterprise Asset Management can be used to manage the whole lifecycle of a

More information

GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices

GAO MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices GAO United States Government Accountability Office Report to Congressional Addressees March 2013 MAJOR AUTOMATED INFORMATION SYSTEMS Selected Defense Programs Need to Implement Key Acquisition Practices

More information

Making Every Project Business a Best-Run Business

Making Every Project Business a Best-Run Business SAP Functions in Detail SAP Business Suite SAP Commercial Project Management Making Every Project Business a Best-Run Business Table of Contents 3 Quick Facts 4 Facilitating Optimal Project Delivery for

More information

CA Clarity PPM. Business Objects Universe Developer Guide. v13.0.00

CA Clarity PPM. Business Objects Universe Developer Guide. v13.0.00 CA Clarity PPM Business Objects Universe Developer Guide v13.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation

More information

CA Clarity PPM. Project Management User Guide. v13.0.00

CA Clarity PPM. Project Management User Guide. v13.0.00 CA Clarity PPM Project Management User Guide v13.0.00 This documentation, which includes embedded help systems and electronically distributed materials, (hereinafter referred to as the Documentation )

More information

Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects)

Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects) Business Success through Excellence in Project Management (Better, Cheaper, Faster and Safer Projects) Process and Tools that Enable Project Teams to Achieve World-Class Performance and thereby Improve

More information

Develop Project Charter. Develop Project Management Plan

Develop Project Charter. Develop Project Management Plan Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs

More information

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3

Stakeholder management and. communication PROJECT ADVISORY. Leadership Series 3 /01 PROJECT ADVISORY Stakeholder management and communication Leadership Series 3 kpmg.com/nz About the Leadership Series KPMG s Leadership Series is targeted towards owners of major capital programmes,

More information

WelcomRisk. For organizations looking to improve project performance through proactive risk management.

WelcomRisk. For organizations looking to improve project performance through proactive risk management. Welcom For organizations looking to improve project performance through proactive risk management. Improved Project Performance Through Better Management. All projects are exposed to varying degrees of

More information

The Challenges of Managing Public Infrastructure Projects

The Challenges of Managing Public Infrastructure Projects PRIMAVERA The Challenges of Managing Public Infrastructure Projects A discussion paper from Oracle Success factors in Public Infrastructure Project Management Public infrastructure projects drive a country

More information

MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices

MAJOR AUTOMATED INFORMATION SYSTEMS. Selected Defense Programs Need to Implement Key Acquisition Practices United States Government Accountability Office Report to Congressional Committees March 2014 MAJOR AUTOMATED INFORMATION SYSTEMS Selected Defense Programs Need to Implement Key Acquisition Practices GAO-14-309

More information

A Leading Provider of Engineering Information Management Solutions and Services. Facilitating multi-office, multi-contractor execution strategies

A Leading Provider of Engineering Information Management Solutions and Services. Facilitating multi-office, multi-contractor execution strategies A Leading Provider of Engineering Information Management Solutions and Services Facilitating multi-office, multi-contractor execution strategies Engineering projects are increasingly becoming more complex

More information

Auditing Engineer-Procure-Construct (EPC) Projects

Auditing Engineer-Procure-Construct (EPC) Projects Auditing Engineer-Procure-Construct (EPC) Projects Baker Tilly refers to Baker Tilly Virchow Krause, LLP, an independently owned and managed member of Baker Tilly International. 2012 Baker Tilly Virchow

More information

Mastering Microsoft Project 2010

Mastering Microsoft Project 2010 Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project

More information

Australian Renewable Energy Agency s (ARENA s) 2015-16 Corporate Plan

Australian Renewable Energy Agency s (ARENA s) 2015-16 Corporate Plan Australian Renewable Energy Agency s (ARENA s) 2015-16 Corporate Plan Introduction As the accountable authority of the Australian Renewable Energy Agency (ARENA), the ARENA Board presents the 2015-16 ARENA

More information

Service Portfolio Management PinkVERIFY

Service Portfolio Management PinkVERIFY -11-G-001 General Criteria Does the tool use ITIL 2011 Edition process terms and align to ITIL 2011 Edition workflows and process integrations? -11-G-002 Does the tool have security controls in place to

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

Professionals in oil, gas and power projects LEADING IN OIL, GAS AND POWER PROJECTS

Professionals in oil, gas and power projects LEADING IN OIL, GAS AND POWER PROJECTS Professionals in oil, gas and power projects LEADING IN OIL, GAS AND POWER PROJECTS More successful with STAR, the expert in Oil, Gas and Power Projects Projects in Oil, Gas and Power generating industries

More information

INFORMATION MANAGED. Project Management You Can Build On. Primavera Solutions for Engineering and Construction

INFORMATION MANAGED. Project Management You Can Build On. Primavera Solutions for Engineering and Construction INFORMATION MANAGED Project Management You Can Build On Primavera Solutions for Engineering and Construction Improve Project Performance, Profitability, and Your Bottom Line Demanding owners, ineffective

More information

THE PROJECT MANAGEMENT KNOWLEDGE AREAS

THE PROJECT MANAGEMENT KNOWLEDGE AREAS THE PROJECT MANAGEMENT KNOWLEDGE AREAS 4. Project Integration Management 5. Project Scope Management 6. Project Time Management 7. Project Cost Management 8. Project Quality Management 9. Project Human

More information

CMMI: Specific Goals and Practices

CMMI: Specific Goals and Practices Software Engineering for Outsourced & Offshore Development CMMI: Specific Goals and Practices PeterKolb Software Engineering CMMI Process Areas for R&D Projects Slide 2 Content Management in Projects Project

More information

Bringing Safe and Cost Effective Products to Market

Bringing Safe and Cost Effective Products to Market Industry Solutions Life Sciences Engineering, Project Collaboration, Document Control and Facilities Management Solutions across the Life Sciences Value Chain Industry Solutions Life sciences companies

More information

Planning, Building, and Commissioning Assets

Planning, Building, and Commissioning Assets Solution in Detail Oil and Gas Executive Summary Contact Us Planning, Building, and Commissioning Assets 2013 2014 SAP SE or an SAP affiliate company. Effective Management of Asset Development Managed

More information

Adoption of a PPM Solution Using An Agile Approach. Andy Robinson

Adoption of a PPM Solution Using An Agile Approach. Andy Robinson Adoption of a PPM Solution Using An Agile Approach Andy Robinson 1 Agenda Drivers for using a Portfolio and Project Management system Organisational maturity Where to start Planning, delivery, realisation

More information

Life-of-Field. seabed-to-surface

Life-of-Field. seabed-to-surface Life-of-Field seabed-to-surface Global capabilities Life-of-Field {LOF} definition: Assurance of asset integrity throughout the operational life cycle, enabled by a suite of services including integrity

More information

What Are the Key Components of a PFB System?

What Are the Key Components of a PFB System? Software Selection for Project-Focused Businesses White Paper 180 SYSTEMS 2010 Authored by: Michael Burns Software Selection for Project-Focused Businesses White Paper Business software systems are similar

More information

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo

Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management. Introduction. Alfred Sankara, DigiBridge TelCo Application of Standard Project Management Processes in Fiber Optic Cable Plant Project Management Alfred Sankara, DigiBridge TelCo Introduction The Project Management Institute (PMI) is the world's leading

More information

Microsoft Project Server 2013

Microsoft Project Server 2013 Project Server 2013 Project Server 2013 is a flexible on-premises solution for project portfolio management (PPM) and everyday work. Team members, project participants, and business decision makers can

More information

Industry Solutions Mining Engineering Document Control and Project Collaboration Solutions for the Mining Industry Provide Flexibility and Simplicity

Industry Solutions Mining Engineering Document Control and Project Collaboration Solutions for the Mining Industry Provide Flexibility and Simplicity Industry Solutions Mining Engineering Document Control and Project Collaboration Solutions for the Mining Industry Provide Flexibility and Simplicity Industry Solutions The Great Dilemma In the facing

More information

SCHEDULE AND BUDGETING

SCHEDULE AND BUDGETING PROJECT CONTROLS The right combination of software management tools, proper initial project set-up, timely and accurate data input, continuous tracking of progress, a meaningful reporting structure, strong

More information

Release Management: Effective practices for IT delivery

Release Management: Effective practices for IT delivery Release Management: Effective practices for IT delivery Introduction Today s health plans face a unique combination of technology challenges due to their complex IT environments. These environments serve

More information

National Research Council Canada IP Prosecution and IP License Management Solution Project

National Research Council Canada IP Prosecution and IP License Management Solution Project National Research Council Canada IP Prosecution and IP License Management Solution Project Appendix 1 Statement of Work Version 6.0, 10 December 2013 ii Table of Contents 1. Instructions to Bidders...

More information

Assessment guide. Certificate IV in Project Management BSB41507

Assessment guide. Certificate IV in Project Management BSB41507 Assessment guide Certificate IV in Project Management BSB41507 First produced August 2010. Cayenne Resources. All rights reserved. All materials produced by Cayenne Resources, regardless of format, are

More information

Wilhelmenia Ravenell IT Manager Eli Lilly and Company

Wilhelmenia Ravenell IT Manager Eli Lilly and Company Wilhelmenia Ravenell IT Manager Eli Lilly and Company Agenda Introductions The Service Management Framework Keys of a successful Service management transformation Why transform? ROI and the customer experience

More information

Effective reporting for construction projects: increasing the likelihood of project success

Effective reporting for construction projects: increasing the likelihood of project success PROJECT ADVISORY Effective reporting for construction projects: increasing the likelihood of project success Thought Leadership Series 13 kpmg.com/nz About the Leadership Series KPMG s Leadership Series

More information

Civil Engineering & Construction

Civil Engineering & Construction RoadWorks Civil Infrastructure WaterWorks Contract Services Site Preparation Building Construction Track and Rails Works Concrete Works General contracting Civil Engineering & Construction for Microsoft

More information

EPM Live Presentation. EPM Live Solution Overview

EPM Live Presentation. EPM Live Solution Overview Presentation Solution Overview Social Project & Work Management Social Project Management Product Focus Area Customers interested in an Enterprise Project and Social Project Management application to manage

More information