INNOVATION EMPOWERS. CONSTRUCTABILITY AND CONSTRUCTION PLANNING BY ADOPTING STATE OF THE ART ENGINEERING AND CAD TECHNOLOGY

Size: px
Start display at page:

Download "INNOVATION EMPOWERS. CONSTRUCTABILITY AND CONSTRUCTION PLANNING BY ADOPTING STATE OF THE ART ENGINEERING AND CAD TECHNOLOGY"

Transcription

1 INNOVATION EMPOWERS. CONSTRUCTABILITY AND CONSTRUCTION PLANNING BY ADOPTING STATE OF THE ART ENGINEERING AND CAD TECHNOLOGY MAURIZIO M. GRANATA BUSINESS DEVELOPMENT EXECUTIVE PROCESS POWER MARINE DIVISION

2 Innovation discussion: Innovation is a change in the thought process for doing something, or "new stuff that is made useful". [1]!"# Max McKeown, (2008). The Truth About Innovation. London, Prentice Hall

3 Agenda Drivers leading past technology improvements Competitive Environment and current Challenges Innovation available today

4 1 - Bring simple but powerful computing capabilities to Site Construction can be at times considered as stand alone world No information / data exchange from Home Office Basic construction needs: Warehouse management: MRR, MIR, Inventory Sub-contractors accountability Planning and Schedule $ %& '()*+,-.

5 2 - Improve data availability at Site Construction brings information from up stream work processes Bill of Materials from engineering and design PO data Planning Construction works New concepts in Construction Managements SMH, work efficiency, regional / local K factors construction DB $ %/ '()*+,-.

6 3 - Engineering visibility at Site: re-use design data The paperless dream Review 3D model at Site Revise Isometric drawings electronically Electronic As built 2D ½ - 3D Iso / Spool Management Tools for SITE Materials Issuing Report against Iso BoM Printed Collecting Notes / Collecting Vouchers $+%0 '()*+,-.

7 4 - Improve Procurement visibility at Site Full Tracking It empowers erection / fabrication feasibility Construction Forecast considers Supply Chain Events Maximize efficiency of fabricators to save time and cost EPCs fully control sub-contractors Tracking also QA/QC documents Materials Quality Certifications Heat Numbers OSD reports $ %" '()*+,-.

8 Agenda Drivers leading past technology improvements Competitive environment and current challenges Innovation available today

9 Competitive environment Mega Projects with global recession in between From Lack of resources to Volatile availability Risks increase Restlessly searching round for: Efficiency, more productive work, doing More with Less Do not overrun CAPEX budgets!

10 There is no single cause for overruns: Underpinning causes: The numbers are from Construction Owners Association of Alberta COAA. poor information integration, and CII - Construction Industry Institute - has run a similar study and found that direct work in the projects they studies varied from 20% to 33%, with an average of 27% direct work. availability and lack of coordinated and timely communications between all involved departments The 33% figure is a generous number.

11 Current challenges: EPCs Increase Direct work Reduce Waiting & Idle by 1. Sharing Engineering vision to Construction since front end planning 2. Providing Construction Management with clear, concise, and reliable data 3. Making Construction planning, sequencing and visualisation easier 4. Delivering the ability to understand impact of changes Concrete Carpenter General Heavy Equip Op Painters Inspectors Riggers Pipe Fitters Welders Week

12 Current challenges: EPCs and technology providers Make or Buy Internal development was a must. those days are gone Competitive paradigm shift Contractors work together Providing technology providers with common / basic / key requirements the standards software will address Need using standard software better than competitors Effective answers to EPC needs Real breakthrough, not easy improvement!

13 Agenda Drivers leading past technology improvements Competitive environment and current challenges Innovation available today

14 Construction: project execution internal client Point-to-Point Link between project systems: 3D CAD, Scheduling system, Materials management weak, yet possible option

15 Construction: project execution internal client 1(23 Work processes oriented integration is The answer "776 Bridge the gap in between who uses - who defines infos Provide Construction with appropriate data Single re-use of information: no re-create, re-define Easily sharing of information among stake-holders: Foreman, Project Controller, Expediter, Engineer, Designer Real teamwork between all Dept. and Disciplines 4-. No garbage In : No garbage Out! 56

16 Innovation empowers Constructability Review Meetings Effective Constructability starts from Smart Layout Engineering & Construction seats together to define smartest layout 3D technology is available to: Simulating layout and construction operations Test and trial Evaluating options, feasibility, potential delivery constraints, and relevant costs See more at :

17 Innovation empowers Proactive Construction Management Work with Owner teams to balance Systems Turnover perspective and Commissioning / Start-Up with EPC goals Prevent Engineering efficiency to drive priorities and sequence of work Construction organizations to think in terms of the most optimal bulk build or area Construction approaches Prevent Procurement strategies to be whip sawed by these competing perspectives

18 Innovation empowers Workface Planning Traditional approach New approach Projects are typically planned to result in designs Construction implies breaking the design down into planned tasks Field supervisors assign tasks to crew and ensure availability of required information and resources prior to work starting Organize and deliver all elements before work is done Break project into manageable Work Packages enable craft persons to perform quality work in a safe, effective and efficient manner Owner driven initiative Integrates design, construction and operations See more at :

19 Innovation empowers Workface Planning One Goal, One Team: it aids in communication and coordination between Operations & Maintenance (Commissioning Team), Construction and Engineering Teams (Contractor Teams) It facilitates alignment, balance and optimization across the full EPC and Start-Up continuum It prevents sub-optimization of any single stage from compromising overall objectives

20 Innovation empowers CWPs + DPs Balancing together: Construction Execution Plan Construction Work Packages Engineering Delivery Strategy Delivery Packages Construction Sequence to drive consistent planning for: Issued For Construction of Engineering deliverables Relevant Materials availability In-line with overall Project Schedule Early identification of issues with sequencing

21 Innovation empowers Easy handling of Priority changes What if next Delivery Package is missing? or not IFC yet? What if materials for next Work Package is suddenly delayed? System shall support remedial / recovery actions, by looking into all available 3D, 2D design, procurement, and planning data And quick re-definition of Work Packages

22 Developed by Construction Professionals for Construction Users Several Premier Partners provided Intergraph with input (1) CTCI Taiwan Fluor Global Keiwit USA Ledcor Canada Nexen Canada Technip Global URS Washington Div. USA (1) Alphabetic order

23 What our partners say about Intergraph s approach to Construction management Technip : SmartPlant Construction opens the door to new possibilities in project execution on any scale URS Washington Group : SmartPlant Enterprise s cutting-edge attributes will make us more efficient and add value to our customer s projects CTCI Corporation : This application has the potential to introduce a step change in the way we do business and lead to improvements in our projects See more at :

24 Business Benefits for all Players Risk reduction and capital cost containment, by Construction efficiency and productivity Cash flow optimization by Long Lead Procurement priorities Rework minimization / unplanned shifts in priorities by efficient planning and use of Engineering resources Revenue generating opportunities, by more efficient Turnover Taking 600 M project, and assuming Construction is 25% of Total Cost, 5% of saving in Construction costs means approximately 7.5 M

25 Grazie Maurizio M. Granata Skype: mmgranata

PROCUREMENT, FABRICATION & CONSTRUCTION

PROCUREMENT, FABRICATION & CONSTRUCTION SmartPlant Enterprise PROCUREMENT, FABRICATION & CONSTRUCTION 2 Balancing Act PROCUREMENT, FABRICATION, AND CONSTRUCTION represent a complex balancing act between profit-making and risk-taking that requires

More information

Procurement and Supply Chain In a Work Face Planning Environment

Procurement and Supply Chain In a Work Face Planning Environment Procurement and Supply Chain In a Work Face Planning Environment COAA Workface Planning Forum Calgary, Alberta December 1 2010 Presented by: Bill Somerville Overview Scope of Discussion Owners and Contractors

More information

intergraph Procurement, Fabrication & Construction seminar

intergraph Procurement, Fabrication & Construction seminar intergraph Procurement, Fabrication & Construction seminar agenda Integrating Enterprises to Support Smarter and Leaner Construction Execution Procurement, fabrication, and construction represent a complex

More information

Effective Materials Management

Effective Materials Management WHITE PAPER Effective Materials Management Reducing Costs and Improving Procurement Efficiency Contents 1. Introduction... 1 2. Industry Challenges... 2 3. Business Benefits... 3 3.1 Managing Reference

More information

Solution. SmartPlant. Procurement, Fabrication & Construction

Solution. SmartPlant. Procurement, Fabrication & Construction Solution SmartPlant Enterprise Procurement, Fabrication & Construction BALANCING ACT Procurement, fabrication, and construction represent a complex balancing act between profi t-making and risk-taking

More information

CAD/CAE systems and cost engineering

CAD/CAE systems and cost engineering CAD/CAE systems and cost engineering The purpose of this article is to explain how total life-cycle solutions can help engineering procurement and construction and plant owner companies meet today s business

More information

SMARTPLANT ENTERPRISE

SMARTPLANT ENTERPRISE INDUSTRY SMARTPLANT ENTERPRISE For the Metals and Mining Industry INDUSTRY CHALLENGES Metals and mining facilities are increasingly complex and large in scope, with mega-projects becoming the norm. There

More information

Importance of Construction Management in Project Execution

Importance of Construction Management in Project Execution Importance of Construction Management in Project Execution ARC Twelfth India Forum, Bangalore 10-11 July, 2014 Industry in Transition: The Information Driven Enterprise in a Connected World Rainer Lamping

More information

ARC Industry Forum, Orlando 2/13/2014. Overview. Martin Swaine 4D Program Manager, Shell P&T (Projects & Technology) Shell International

ARC Industry Forum, Orlando 2/13/2014. Overview. Martin Swaine 4D Program Manager, Shell P&T (Projects & Technology) Shell International ARC Industry Forum, Orlando 2/13/2014 Overview Martin Swaine 4D Program Manager, Shell P&T (Projects & Technology) Shell International 2001, CII Formed Fiatech Realize Best of What Is! Realize Best of

More information

Process, Power and Marine Division

Process, Power and Marine Division Process, Power and Marine Division SmartPlant Enterprise for Owner Operators (SPO) Adrian Park, Global Technical Director, Owner Operator Solutions P2C2 Scandinavia, 16th October 2007 The Owner Operator

More information

RULES OF CREDIT FOR EWP S WHY GO THERE??? Presenter Glen Warren Co-Chair COAA WFP Committee

RULES OF CREDIT FOR EWP S WHY GO THERE??? Presenter Glen Warren Co-Chair COAA WFP Committee RULES OF CREDIT FOR EWP S WHY GO THERE??? Presenter Glen Warren Co-Chair COAA WFP Committee AGENDA 1. Why is progressing EWP important in AWP / WFP Strategy? 2. What is happening now and why? 3. Example

More information

1.040 Project Management

1.040 Project Management MIT OpenCourseWare http://ocw.mit.edu 1.040 Project Management Spring 2009 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms. Fred Moavenzadeh Spring 2009

More information

WHITE PAPER. Lean Construction. Technology Advances in Lean Construction

WHITE PAPER. Lean Construction. Technology Advances in Lean Construction WHITE PAPER Lean Construction Technology Advances in Lean Construction Contents 1. Introduction... 1 2. Origins of Lean Construction... 2 3. Lean Construction Principles... 4 4. Advancements in Lean Construction

More information

WORKFACE PLANNING CONFERENCE WFP IS MAKING IT HAPPEN. PROJECT PLANNING A CASE STUDY Wayne Cusitar, P.Eng., MBA

WORKFACE PLANNING CONFERENCE WFP IS MAKING IT HAPPEN. PROJECT PLANNING A CASE STUDY Wayne Cusitar, P.Eng., MBA CONSTRUCTION OWNERS ASSOCIATION of ALBERTA WORKFACE PLANNING CONFERENCE WFP IS MAKING IT HAPPEN Glenmore Inn Hotel and Convention Centre Calgary, Alberta - November 17-18, 2009 PROJECT PLANNING A CASE

More information

Engineering, Procurement and Construction (EPC) Projects

Engineering, Procurement and Construction (EPC) Projects Engineering, Procurement and Construction (EPC) Projects Opportunities for Improvements through automation Presented by Robert N. Fox Summary Clarify distinctions between EPC and AEC State EPC Challenges

More information

Product Lifecycle Management. Diane Ryan Siemens PLM Software

Product Lifecycle Management. Diane Ryan Siemens PLM Software Product Lifecycle Management Diane Ryan Siemens PLM Software Discussion Topics Challenges in Manufacturing and Lifecycle Maintenance Product Lifecycle Management Communication and Collaboration Standardized

More information

Building Contractor Management Excellence

Building Contractor Management Excellence Building Contractor Management Excellence For several years, companies have been under relentless pressure to control costs. That is especially true of industrial and assetintensive companies, and in response,

More information

Project Materials Control

Project Materials Control Project Management the smart way Project Materials Control QMS Materials Management System for Projects Track Materials with QMS Introducing QMS In an ideal world, materials control should be easy. Once

More information

Challenges & Trends. Differentiate & Innovate the Business Model. Optimize and streamline the Operations

Challenges & Trends. Differentiate & Innovate the Business Model. Optimize and streamline the Operations Consulting Challenges & Trends Differentiate & Innovate the Business Model Optimize and streamline the Operations The constantly evolving market context, increasingly driven by technological developments,

More information

Siemens PLM Software. Energy and utilities. PLM solutions for tough industry challenges and sustained business growth. siemens.

Siemens PLM Software. Energy and utilities. PLM solutions for tough industry challenges and sustained business growth. siemens. Siemens PLM Software Energy and utilities PLM solutions for tough industry challenges and sustained business growth siemens.com/plm Global megatrends in energy Demographic change, resource scarcity and

More information

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS)

PROJECT CONTROL PROCEDURE (PROJECT STANDARDS AND SPECIFICATIONS) TABLE OF CONTENTS Page 1 of 18 PURPOSE 2 SCOPE 2 DEFINITION 2 ORGANIZATION AND RESPONSIBILITIES 2 Organization and Function 2 Integration of Control Functions 5 7 Introduction 7 Planning and Scheduling

More information

Factors Affecting Construction Labor Productivity

Factors Affecting Construction Labor Productivity WHITE PAPER Factors Affecting Construction Labor Productivity Managing Efficiency in Work Planning Contents 1. Introduction... 1 2. Labor Impacts on Construction Planning... 2 3. Unique Projects... 3 4.

More information

Technip Data Management Journey. IPMA Italy. Jean-Luc Brunat VP, Business Support Functions & Group Data Systems Group IT. Rome, December 3 rd 2013

Technip Data Management Journey. IPMA Italy. Jean-Luc Brunat VP, Business Support Functions & Group Data Systems Group IT. Rome, December 3 rd 2013 Technip Data Management Journey IPMA Italy Jean-Luc Brunat VP, Business Support Functions & Group Data Systems Group IT Rome, December 3 rd 2013 1 Sezione Informatica This is Business Intelligence! 2 What

More information

RT319 Validating Advanced Work Packaging as a Best Practice A Game Changer

RT319 Validating Advanced Work Packaging as a Best Practice A Game Changer RT319 Validating Advanced Work Packaging as a Best Practice A Game Changer Michael Bankes, Fluor Joel Gray, Coreworx William O Brien, University of Texas at Austin Jim Rammell, Wood Group Mustang, Inc.

More information

HEDCO Total Management Solution

HEDCO Total Management Solution HEDCO Total Management Solution Project Management & Control Document Management Procurement Management Construction Management In HEDCO We Believe in IT INFORMATION MANAGEMENT & SOFTWARE APPLICATIONS

More information

SMARTMARINE ENTERPRISE

SMARTMARINE ENTERPRISE SOLUTION SMARTMARINE ENTERPRISE Improving the Complete Marine Structure Life Cycle InDUstry forecasts The marine industry is changing quickly. Industry leaders agree on a number of factors they predict

More information

PLANT DESIGN AT YOUR FINGERTIP

PLANT DESIGN AT YOUR FINGERTIP intergraph Cadworx & analysis Solutions PLANT DESIGN AT YOUR FINGERTIP Introduction The use of intelligent plant design tools is an obvious choice for most medium- and large-sized engineering companies

More information

The Supply Chain Management Process

The Supply Chain Management Process article The Supply Chain Management Process D r N e va n W r i g h t, A U T U n i v e r s i t y, N e w Z e a l a n d, e - m a i l : N e va n. w r i g h t @ a u t. a c. n z The primary purpose of this introductory

More information

The "Smart" Implementation Intergraph s Latest Approach and Strategy to Support Successful System Implementations

The Smart Implementation Intergraph s Latest Approach and Strategy to Support Successful System Implementations The "Smart" Implementation Intergraph s Latest Approach and Strategy to Support Successful System Implementations Vivek Mokashi Executive Manager SmartPlant 3D Services Intergraph Norway 2008 12 th Nov

More information

SMARTPLANT ENTERPRISE

SMARTPLANT ENTERPRISE SOLUTION SMARTPLANT ENTERPRISE 3D Modeling & Visualization INDUSTRY CHALLENGES Plant owner operators (O/Os) and engineering, procurement, and construction (EPC) companies alike are under continued pressure

More information

ICG Team. ICG Solutions: Your challenges and seeing them through. software solutions for oil & Gas companies

ICG Team. ICG Solutions: Your challenges and seeing them through. software solutions for oil & Gas companies WHAT'S INSIDE Product Catalog, Software Solutions for Oil & Gas companies ICG Team INNOVATION CENTRIC GROUP ICG Solutions: Your challenges and seeing them through. Designing custom software solutions for

More information

SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING. Mikhail Hanna Janaka Y. Ruwanpura

SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING. Mikhail Hanna Janaka Y. Ruwanpura Proceedings of the 2007 Winter Simulation Conference S. G. Henderson, B. Biller, M.-H. Hsieh, J. Shortle, J. D. Tew, and R. R. Barton, eds. SIMULATION TOOL FOR MANPOWER FORECAST LOADING AND RESOURCE LEVELING

More information

How to successfully manage your mega-project

How to successfully manage your mega-project How to successfully manage your mega-project Part I Early planning and organizing for success kpmg.com 2 Building, Construction & Real Estate How to successfully manage your mega-project A three-part series

More information

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013

JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 JAGAN RAO ADELAIDE, TUESDAY, 3 DECEMBER 2013 Relate to this? Outline 1. Safety & Housekeeping 2. Aim 3. Introduction SKM and Jagan Rao 4. Project Controls Overview 5. Cost Estimating 6. Planning & Scheduling

More information

Five Steps to Building a Successful Procurement Strategy. SIG Webinar May 2013

Five Steps to Building a Successful Procurement Strategy. SIG Webinar May 2013 Five Steps to Building a Successful Procurement Strategy SIG Webinar May 2013 Our Subject Matter Experts Today: John Evans Grant Dearborn Managing Partner Denali Group 530.550.8306 [email protected]

More information

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University.

Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. Linbeck Construction used the Last Planner system of production control on a $22 million remodel of the Chemistry Building at Rice University. This was one of four innovative practices was described by

More information

Real Estate Lifecycle Management

Real Estate Lifecycle Management Solution in Detail Enterprise Asset Management Executive Summary Contact Us Real Estate Lifecycle Management Boost Your Real Estate Portfolio Portfolio Management Optimized Management Managing corporate

More information

SUPPLY CHAIN SERVICES

SUPPLY CHAIN SERVICES EB-0-0 Exhibit F Schedule Page of SUPPLY CHAIN SERVICES INTRODUCTION Supply Chain supports THESL asset management plans by ensuring that all required goods and services are available when needed. Strong

More information

Plan to Pay (P2P) Optimize your process to Manage your Contractors with Oracle Primavera July, 2012

Plan to Pay (P2P) Optimize your process to Manage your Contractors with Oracle Primavera July, 2012 Plan to Pay (P2P) Optimize your process to Manage your Contractors with Oracle Primavera July, 2012 Agenda Oracle View of Plan to Pay (P2P) Composite Process Component Review Project Planning & Portfolio

More information

Engineering g Procurement. 02-Feb-2015

Engineering g Procurement. 02-Feb-2015 Engineering g Procurement Construction & Operation Capability Presentation About Pyramid E&C Est. 1995, professionally managed Company Over 500 projects executed till date Employs over 600 Engineers and

More information

Project Execution Planning: The Key to Successful Pharmaceutical Project Delivery

Project Execution Planning: The Key to Successful Pharmaceutical Project Delivery Reprinted from PHARMACEUTICAL ENGINEERING THE OFFICIAL TECHNICAL MAGAZINE OF ISPE MARCH/APRIL 2014, VOL 34, NO 2 Copyright ISPE 2014 www.pharmaceuticalengineering.org facilities and equipment : The Key

More information

S&OP i dagligvarubranschen affärsplanering för ökat konsumentvärde. Henrik Hjalmarsson Findus Sverige AB

S&OP i dagligvarubranschen affärsplanering för ökat konsumentvärde. Henrik Hjalmarsson Findus Sverige AB S&OP i dagligvarubranschen affärsplanering för ökat konsumentvärde Henrik Hjalmarsson Findus Sverige AB Agenda What are the challenges in business planning? Why Sales & Operations Planning (S&OP)? The

More information

Knowledge is the food of the soul ~Plato. Knowledge Transferred Transferencia del Saber

Knowledge is the food of the soul ~Plato. Knowledge Transferred Transferencia del Saber Knowledge is the food of the soul ~Plato Knowledge Transferred Transferencia del Saber Unlocking your organization s workforce potential with customized key solutions Saber Academy Capacity Building Program

More information

Project driven supply chain in complex MRO services Oracle e-business suite

Project driven supply chain in complex MRO services Oracle e-business suite Global Sponsor Project driven supply chain in complex MRO services Oracle e-business suite Session: CON11132 Date: Monday, September 29 Time: 11:45 a.m. - 12:30 p.m. Venue: Intercontinental Intercontinental

More information

Turnaround and Maintenance Services

Turnaround and Maintenance Services Turnaround and Maintenance Services Reliably providing quality turnaround and maintenance services safely Matrix Safe a cultural mindset For us, safety is more than a core value. It s a way of life. We

More information

Risk Management. Policy

Risk Management. Policy Policy Risk Management Endorsed: 26 February 2014 Brief description The GPC Risk Management Policy and its supporting standards and procedures provide a framework to ensure that risks arising from our

More information

Improving Offshore Supply Chain by Predictive Asset Management Making Smarter Business Decisions

Improving Offshore Supply Chain by Predictive Asset Management Making Smarter Business Decisions Improving Offshore Supply Chain by Predictive Asset Management Making Smarter Business Decisions Aberdeen, 28 November 2013 Agenda: Asset Management as the front office of the offshore supply chain Impact

More information

5 Unexpected Ways Continuous Improvement With Lean Six Sigma Can Improve Your Company

5 Unexpected Ways Continuous Improvement With Lean Six Sigma Can Improve Your Company A Whitepaper from Juran Global The Source for Breakthrough Lean Six Sigma 5 Unexpected Ways Continuous Improvement With Lean Six Sigma Can Improve Your Company 0 Juran Global Our expertise has been developed

More information

Mergers and Acquisitions: The Data Dimension

Mergers and Acquisitions: The Data Dimension Global Excellence Mergers and Acquisitions: The Dimension A White Paper by Dr Walid el Abed CEO Trusted Intelligence Contents Preamble...............................................................3 The

More information

Amajor benefit of Monte-Carlo schedule analysis is to

Amajor benefit of Monte-Carlo schedule analysis is to 2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to

More information

Solution. Smartplant. Reducing CAPEX and Improving ROCE

Solution. Smartplant. Reducing CAPEX and Improving ROCE Solution Smartplant Enterprise Reducing CAPEX and Improving ROCE Industry Pressures Significant growth especially in economic hot-spots such as China and India will continue to drive global demand for

More information

Pipeline Engineering. Natural Gas Distribution

Pipeline Engineering. Natural Gas Distribution R Pipeline Engineering Natural Gas Distribution Gas Distribution Engineering Services Our team of professionals at EN Engineering has been designing, upgrading and maintaining distribution system assets

More information

Track 1 Business & Entrepreneurship Education

Track 1 Business & Entrepreneurship Education Track 1 Business & Entrepreneurship Education iexec The course provides ICT related business education that enables learners to develop new strategies to transform their organization and business through

More information

SAP Supply Chain Management Elinor Castell Solution Owner Transportation, SAP SE

SAP Supply Chain Management Elinor Castell Solution Owner Transportation, SAP SE SAP Supply Chain Management Elinor Castell Solution Owner Transportation, SAP SE 2014 SAP SE or an SAP affiliate company. All rights reserved. 1 SAP Extended Supply Chain Management Solution Strategy 2

More information

Saving Troubled Projects

Saving Troubled Projects Saving Troubled Projects 2012 Instructor and Developer Mark Waldof Mark Waldof Consulting Retired Lockheed Martin University of Minnesota Instructor CCE Business Improvements Consultant Project Management

More information

Business Challenges. Customer retention and new customer acquisition (customer relationship management)

Business Challenges. Customer retention and new customer acquisition (customer relationship management) Align and Optimize Workflows with Lean Dan Marino Marino Associates, LLC Strategic and tactical planning Information systems integration Customer retention and new customer acquisition (customer relationship

More information

Introduction to Construction Project/Jobsite Management

Introduction to Construction Project/Jobsite Management Introduction to Construction Project/Jobsite Management Hal Johnston April 23, 2014 Professor Emeritus Construction Management California Polytechnic State University San Luis Obispo, California, US Visiting

More information

BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi

BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value. Professor Mustafa Alshawi BIM Best Practice to Cut Capital and Operational Expenditure: Maximizing Business Value Professor Mustafa Alshawi Improving Project Performance Current Project Portfolio 1.83 B UAED ($500M) Award Winning

More information

Shipbuilding and Repair. Career Path Design for Job Entry and Succession Planning. Larry Gebhardt Dale Jermyn Dawn Wilson

Shipbuilding and Repair. Career Path Design for Job Entry and Succession Planning. Larry Gebhardt Dale Jermyn Dawn Wilson Shipbuilding and Repair Career Path Design for Job Entry and Succession Planning Larry Gebhardt Dale Jermyn Dawn Wilson What Is a Career Path? The Defined Track a Person Follows in the Pursuit of Professional

More information

Construction Project Saves $11 Million in 24 Months Using RFID Enabled Material Control

Construction Project Saves $11 Million in 24 Months Using RFID Enabled Material Control Construction Project Saves $11 Million in 24 Months Using RFID Enabled Material Control Project located in the Canadian Oil Sands Realizes 467% ROI in the First Two Years of Implementation www.atlasrfid.com

More information

Strategic Key Account Management

Strategic Key Account Management Strategic Key Account Management Page 1 How Economic and Technological Changes Have Made Key Account Management a Strategic Imperative In the 1970s, companies like Xerox and IBM started to address their

More information

Materials Management:

Materials Management: Materials Management: Damodara U. Kini, P.E. OFTEN OVERLOOKED AS A COST SOLUTION, SUCCESSFULLY MANAGING MATERIALS CAN LEAD TO GREATER SAVINGS. Damodara U. Kini is procurement manager at Raytheon, Engineers

More information

ENTERPRISE ASSET MANAGEMENT (EAM) The Devil is in the Details CASE STUDY

ENTERPRISE ASSET MANAGEMENT (EAM) The Devil is in the Details CASE STUDY ENTERPRISE ASSET MANAGEMENT (EAM) The Devil is in the Details CASE STUDY 1 EXECUTIVE SUMMARY Enterprise Asset Management (EAM) is a strategy to provide an optimal approach for the management of the physical

More information

AVEVA NET Accesses and Manages the Digital Asset. Executive Overview... 3. Project Risk: Inaccessible, Unreliable Information... 4

AVEVA NET Accesses and Manages the Digital Asset. Executive Overview... 3. Project Risk: Inaccessible, Unreliable Information... 4 ARC WHITE PAPER By ARC Advisory Group JUNE 18, 2013 AVEVA NET Accesses and Manages the Digital Asset Executive Overview... 3 Project Risk: Inaccessible, Unreliable Information... 4 AVEVA NET Focuses on

More information

How To Work At Propak

How To Work At Propak Build Your Career at Propak Challenge yourself and expand your skills by joining our multi-disciplinary team. Work with us to design and build industry-leading oil and gas processing facilities for installation

More information

How To Use The Standard Database For Smartplant Reference Data

How To Use The Standard Database For Smartplant Reference Data WHITE PAPER Standard Database for SmartPlant Reference Data Contents 1. Introduction... 2 2. SmartPlant Reference Data... 3 3. Standard Database for SmartPlant Reference Data... 4 3.1 Out-of-the-box Productivity...

More information

Reduce Capital Cost Overruns with Repeatable Engineering Designs

Reduce Capital Cost Overruns with Repeatable Engineering Designs WHITE PAPER Reduce Capital Cost Overruns with Repeatable Engineering Designs by Ron Beck, Industry Marketing Director, Aspen Technology, Inc. The use of standardized and modular designs to reduce engineering

More information

Strategies to successfully manage your major project

Strategies to successfully manage your major project PROJECT ADVISORY Strategies to successfully manage your major project Whitepaper 1 Thought Leadership Series 10 kpmg.com/nz About this whitepaper KPMG s Project Advisory thought leadership series is aimed

More information

Steel supply chain transformation challenges Key learnings

Steel supply chain transformation challenges Key learnings IBM Global Business Services White Paper Industrial Products Steel supply chain transformation challenges Key learnings 2 Steel supply chain transformation challenges Key learnings Introduction With rising

More information

Oliver Wight Sales & Operations Planning and Demand Management as a Competitive Differentiator

Oliver Wight Sales & Operations Planning and Demand Management as a Competitive Differentiator Oliver Wight Sales & Operations and Demand Management as a Competitive Differentiator James Small Oliver Wight 1 Business Drivers and Benefits of Integrated Business (S&OP) % Respondents -- Business Drivers

More information

Siemens PLM Software. Electronics Manufacturing Services. Using PLM to accelerate and optimize the production process. siemens.

Siemens PLM Software. Electronics Manufacturing Services. Using PLM to accelerate and optimize the production process. siemens. Siemens PLM Software Electronics Manufacturing Services Using PLM to accelerate and optimize the production process siemens.com/plm We not only rearranged our manufacturing planning, we also reached better

More information

14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution

14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution 2015 ERP GUIDE 14 TRUTHS: How To Prepare For, Select, Implement And Optimize Your ERP Solution Some ERP implementations can be described as transformational, company-changing events. Others are big disappointments

More information

Supply Chain Strategy. Edition 01-2014

Supply Chain Strategy. Edition 01-2014 Supply Chain Strategy Edition 01-2014 Contents Executive Summary Mutual Benefits of the Supply Chain 01 04 Subcontractor Relations Guidelines 05 Levels of Engagement 07 Introduction Tiered Supply The Chain

More information

JD Edwards EnterpriseOne One View Reporting Functional Content Overview

JD Edwards EnterpriseOne One View Reporting Functional Content Overview JD Edwards EnterpriseOne One View Reporting Functional Content Overview October 2012 2 Agenda ERP Reporting Business Issues Benefits of One View Reporting One View Reporting Across The Enterprise Functional

More information

Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry

Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry Best Practices for the Planning and Execution of Turnaround Projects in the Oil and Gas Industry By: Arash Shahi Senior Product Manager, Coreworx 519-772-3181 Contents Executive Summary 3 Background 4

More information

OPTIMIZING PRODUCTION

OPTIMIZING PRODUCTION REAL WORLD SCENARIOS Volume 2 Cases 7-12 OPTIMIZING PRODUCTION SQUEEZE MORE OUT OF PRODUCTION OPTIMIZING SCHEDULING PRODUCTION FLOW IMPROVEMENTS INTEGRATED MAINTENANCE PLANNING INTEGRATED PROJECT MANAGEMENT

More information

Training Programs for Enterprise-Wide Change

Training Programs for Enterprise-Wide Change Training Programs for Enterprise-Wide Change Top Five Requirements for Programs that Deliver Prepared by VisionCor, Inc. 1 Contents Summary... 3 Before We Get Started... 3 Program Principles... 4 Business

More information

UNLOCKING MAJOR COST SAVINGS ON OIL & GAS PROJECTS

UNLOCKING MAJOR COST SAVINGS ON OIL & GAS PROJECTS UNLOCKING MAJOR COST SAVINGS ON OIL & GAS S $ RESPONDING TO A LOW-PRICE OIL ENVIRONMENT THE BENEFITS OF EARLY INVOLVEMENT: In our experience early involvement on a project is key when it comes to securing

More information

Quality Management Principles and Guidelines on their Application

Quality Management Principles and Guidelines on their Application Document: ISO/TC 176/SC 2/N 376 Secretariat of ISO/TC 176/SC 2 Our ref: 97/402545 Date: 30 June 1997 To the Members of ISO/TC 176/SC 2 - Quality Management and Quality Assurance/ Quality Systems (TC176/SC2/WG15/N133)

More information

Corporate Procurement and Supply Services

Corporate Procurement and Supply Services Corporate Procurement and Supply Services CORPORATE SERVICES Branch Manager: Dan Lajeunesse 16 CORPORATE PROCUREMENT AND SUPPLY SERVICES 2016 2018 BUSINESS PLAN Table of Contents INTRODUCTION Our Branch

More information

Operations Management and the Integrated Manufacturing Facility

Operations Management and the Integrated Manufacturing Facility March 2010 Page 1 and the Integrated Manufacturing Facility This white paper provides a summary of the business value for investing in software systems to automate manufacturing operations within the scope

More information

WESTAC 2015 Fall Member Forum Paul Bingham, Economic Development Research Group. Calgary, Alberta November 10, 2015

WESTAC 2015 Fall Member Forum Paul Bingham, Economic Development Research Group. Calgary, Alberta November 10, 2015 WESTAC 2015 Fall Member Forum Paul Bingham, Economic Development Research Group Calgary, Alberta November 10, 2015 Operations and planning for the freight transport system is fragmented reflecting the

More information

EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies

EST.491. Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies EST.491 Cost Estimation Challenges and Uncertainties Confronting Oil and Gas Companies Nicolas Alexander Hall and Sarah Delille, PE ABSTRACT Usually, when a company has a history of successfully planning

More information

Guidelines For A Successful CRM

Guidelines For A Successful CRM Guidelines For A Successful CRM Salesboom.com Many organizations look to CRM software solutions to address sales or maybe customer service deficiencies or to respond to pressures from outside sources in

More information

Turn Your Business Vision into Reality with Microsoft Dynamics SL

Turn Your Business Vision into Reality with Microsoft Dynamics SL Turn Your Business Vision into Reality with Microsoft Dynamics SL You have worked hard to build a vision for your business. With Microsoft Dynamics SL, you can turn that vision into reality with a solution

More information

Guidelines for a PROJECT EXECUTION PLAN

Guidelines for a PROJECT EXECUTION PLAN Guidelines for a PROJECT EXECUTION PLAN 1. OBJECTIVES The objectives of this guideline are: To provide a standard template for Project Execution Plans (PEP); To identify the critical items which need to

More information

The 2011 Global Supply Chain Agenda Market and demand volatility drives the need for supply chain visibility

The 2011 Global Supply Chain Agenda Market and demand volatility drives the need for supply chain visibility The 2011 Global Supply Chain Agenda Market and demand volatility drives the need for supply chain visibility Cover-Reference Number The Supply Chain agenda in 2011 2 The 2011 Global Supply Chain Agenda

More information

10 Keys to Successful Software Projects: An Executive Guide

10 Keys to Successful Software Projects: An Executive Guide 10 Keys to Successful Software Projects: An Executive Guide 2000-2006 Construx Software Builders, Inc. All Rights Reserved. www.construx.com Background State of the Art vs. State of the Practice The gap

More information

DISCRETE MANUFACTURING

DISCRETE MANUFACTURING DISCRETE MANUFACTURING 1 Our research and development strategy: to be the most innovative IT solutions integrator Prodware s software development strategy is centred around the leading ERP platform, Microsoft

More information