CARDIFF COUNCIL AGENDA ITEM: 3 CYNGOR CAERDYDD

Size: px
Start display at page:

Download "CARDIFF COUNCIL AGENDA ITEM: 3 CYNGOR CAERDYDD"

Transcription

1 CARDIFF COUNCIL AGENDA ITEM: 3 CYNGOR CAERDYDD ENVIRONMENTAL SCRUTINY COMMITTEE: 17 th May 2011 PRELIMINARY FLOOD RISK ASSESSMENT Purpose of report 1. To provide Members with information of the Preliminary Flood Risk Assessment currently being developed for Cardiff. Background 2. A European Directive introduced the Flood Risk Regulations which came into force on 10 December These imposed strict timetables on member states for the completion of three elements of work which will finally culminate in the publication of Flood Risk Management Plans for River Basin districts, of which there are 11 in England and Wales, and river catchments, which number 77 in England and Wales. There are 9 river catchments in Wales and those that are relevant to Cardiff are the Taff/ Ely and the Rhymney / Ebbw catchments. 3. The Regulations identify the Environment Agency and Local Authorities as lead authorities to work with partners such as water companies to manage flood risk and to reduce the consequences of flooding on human health, economic activity, cultural heritage and the environment. The Regulations set out a 6 year cycle of assessment and production of mapping and plans with the Environment Agency assigned responsibility for main river, the sea and reservoirs and lead Local Flood Authorities (all councils in Wales), responsible for all other sources of flooding including surface water runoff, ground water and ordinary watercourse flooding. 4. The Flood Risk Regulations impose dates for the completion of 3 separate elements of work for the management of risk associated with flooding to be completed as follows Preliminary Flood Risk Assessment by 22 December 2011 Flood Risk and Flood Hazard Map by 22 December

2 Flood Risk Management Plans by 22 December The Environment Agency Wales is tasked with collating the 22 Preliminary Flood Risk Assessment s covering the whole of Wales and they must submit a summary Preliminary Flood Risk Assessment by the above deadline. In order that they have sufficient time to meet their deadline they in turn have imposed their own deadline of 22 June 2011 for Lead Local Flood Authorities to submit reports. 6. The report on Cardiff's Preliminary Flood Risk Assessment is due for submission to the Environment Agency by the 22 June The Environment Agency has produced a guidance document which has been used by all local authorities to draft their Preliminary Flood Risk Assessment s. It should be noted that the scope of the Preliminary Flood Risk Assessment covers only local flood risk, that of tributaries, surface water run off and feeder streams and therefore excludes flooding risk from the main rivers, the sea and large raised reservoirs. Those watercourse risks are being assessed by the Environment Agency and a consolidated report covering both is to be produced by the Environment Agency by the Welsh Assembly Government prescribed deadlines. 8. The Council has engaged a consultant, Hyder Consulting Ltd, to prepare its Preliminary Flood Risk Assessment and the draft version of this document is attached as Appendix 1. The document consists of: A text document prepared to a standard format. A map of the county showing the area of significant flood risk. A schedule of known flood events that have occurred in the past. 9. The costs of preparing the Assessment have been met from a 22,000 grant assigned to Cardiff from the Welsh Assembly Government from which all authorities in Wales benefited. The potential for future additional funding for further aspects of work associated with the Flood Risk Regulations is not know at this time. Liaison with the Welsh Assembly Government officials will continue to understand and develop the next stage of the process. 2

3 10. Environment Agency Wales supplied all Lead Local Flood Authorities with maps of their areas showing Indicative Flood Risk areas based on a national methodology which has been stipulated by the Assembly Government. To ensure a consistent and proportionate approach Environment Agency Wales have identified 1 km squares above the flood risk threshold using the Flood Map for Surface Water. The 1 km squares identify areas where more than 200 people, or more than one critical service or more than 20 nonresidential properties are predicted to be flooded to a depth greater than 0.3m under the 0.5% annual probability surface water event. With this as a starting point the consultant has drawn on all available information from many sources (as set out in Appendix 2) some internal to the Council and others external to assess whether the indicative flood risk map is an accurate representation of the actual flood risk. 11. In undertaking a review of the maps supplied by Environment Agency Wales there has been an analysis of all known historical flooding events both small and large and also potential future flooding based on a 1 in 100 year event. The Preliminary Flood Risk Assessment in Appendix 1 is the conclusion of this analysis. 12. The analysis identified three new 1km squares that should have been included but these have not increased the area covered by the original indicative flood risk area proposed by Environment Agency Wales. Two of the new squares cover the Whitchurch Brook and members will be aware that European funding has already been allocated to a project aimed to reduce the flood risk posed by the Brook. The project is currently awaiting match funding from the Assembly before it can proceed. 13. It should also be noted that in analysing the future flood risk the consultants have reviewed information available from Strategic Flood Consequence Assessments which have been undertaken to support proposals contained within the Local Development Plan. Further flood assessment work in relation to the Local Development Plan is ongoing but is unaffected by the conclusions of the Preliminary Flood Risk Assessment. 14. The Preliminary Flood Risk Assessment report is a high-level screening exercise which must consider flooding which has or could have a significant harmful consequence for human health, economic activity, the environment and cultural heritage and the map illustrating the area of flood risk will have to be refined with further study. The Plan presents a summary of potential consequences noting; the number of people and 3

4 critical services at risk, impacts on roads or rail infrastructure, that a number of Sites of Special Scientific Interest, Scheduled Monuments and Listed Buildings. 15. The next stage stipulated by the Regulations will be a more detailed and comprehensive analysis to prepare flood hazard maps and flood risk maps which will be used to develop the Councils Flood Risk Management Plan that must be submitted to the Environment Agency by the 22 June 2015, progress and delivery on this stage will be the subject of a future report to the Executive. Issues 16. Councillor Delme Bowen, Executive Member for Traffic & Transportation has been invited to attend the meeting. At the meeting officers representing City Services will be in attendance to deliver a presentation and answer Member questions. Way Forward 17. Members may wish to consider whether there are any issues or comments on this item which they would like to pass on to the Executive. Members may also wish to consider if and when this issue should be reconsidered by the Committee. Legal Implications 18. The Scrutiny Committee is empowered to enquire, consider, review and recommend but not to make policy decisions. As the recommendations in this report are to consider and review matters there are no direct legal implications. However, legal implications may arise if and when the matters under review are implemented with or without any modifications. Any report with recommendations for decision that goes to Executive/Council will set out any legal implications arising from those recommendations. All decisions taken by or on behalf the Council must (a) be within the legal powers of the Council; (b) comply with any procedural requirement imposed by law; (c) be within the powers of the body or person exercising powers of behalf of the Council; (d) be undertaken in accordance with the procedural requirements imposed by the Council e.g. Scrutiny Procedure Rules; (e) be fully and properly informed; (f) be properly motivated; (g) be taken having regard to the Council's fiduciary duty to its taxpayers; and (h) be reasonable and proper in all the circumstances. 4

5 Financial Implications 19. The Scrutiny Committee is empowered to enquire, consider, review and recommend but not to make policy decisions. As the recommendations in this report are to consider and review matters there are no direct financial implications at this stage in relation to any of the work programme. However, financial implications may arise if and when the matters under review are implemented with or without any modifications. Any report with recommendations for decision that goes to Executive/Council will set out any financial implications arising from those recommendations. RECOMMENDATIONS The Committee is recommended to: 1. Take account of the information received at the meeting, and; 2. Report any comments to the Executive for their consideration. Mike Davies Head of Service Scrutiny, Performance & Improvement 11 th May

6 Cardiff Council PRELIMINARY FLOOD RISK ASSESSMENT DRAFT REPORT

7 Hyder Consulting (UK) Limited HCL House Fortran Road St Mellons Business Park St Mellons Cardiff CF3 0EY United Kingdom Tel: +44 (0) Fax: +44 (0) Cardiff Council PRELIMINARY FLOOD RISK ASSESSMENT DRAFT REPORT Author S Hooton Checker R Green Approver N Evans Report No 5000-UA NE-R-01 Date 5 May 2011 This report has been prepared for Cardiff Council in accordance with the terms and conditions of appointment for the Preliminary Flood Risk Assessment dated February Hyder Consulting (UK) Limited ( ) cannot accept any responsibility for any use of or reliance on the contents of this report by any third party. Hyder Consulting (UK) Limited Page 2

8 Executive Summary This report has been prepared by Hyder Consulting (UK) Limited on behalf of Cardiff Council to help manage local flood risk and deliver the requirements of the Flood Risk Regulations 2009 ( the Regulations ). Cardiff Council is defined as a Lead Local Flood Authority (LLFA) under the Regulations. The Preliminary Flood Risk Assessment (PFRA) which comprises this document, the supporting spreadsheets and GIS layer, meets the first stage of the requirements of the Regulations. The PFRA process is aimed at providing a high level overview of flood risk from local flood sources, including surface water, groundwater and ordinary watercourses. As a LLFA, Cardiff Council must submit the PFRA to Environment Agency Wales (EAW) for review by the 22 June The methodology for producing the PFRA has been based on EAW guidance (EAW, 2010) and guidance provided by the Department of Environment, Food and Rural Affairs (DEFRA) and the Welsh Assembly Government (WAG) (DEFRA/WAG, 2010). EAW has used a national methodology, which has been set out by WAG, to identify indicative Flood Risk Areas in Wales. Of the eight indicative Flood Risk Areas that have been identified nationally, one is located within the Cardiff Council boundary. Within the finalised Flood Risk Area, the Regulations require Cardiff Council to produce Flood Risk and Hazard Maps and Flood Risk Management Plans by June 2013 and June 2015 respectively. In order to develop a clear overall understanding of the flood risk across Cardiff, flooding information and records of historical events have been collected from a range of key stakeholders, including the Council, Emergency Services, Dwr Cymru Welsh Water and Community Councils. Records relating to over 1000 flood events caused by flooding from local sources were collected and analysed. Each historical flood record has been analysed. However, no historical flood events are judged to have met the significant harmful consequences criteria which are defined in this report as a flood event which local resources were insufficient to manage and which made national headline news and could occur again. This PFRA has also reviewed the future flood risk to Cardiff, by analysing various local and national data sets. Based on this it is considered that there is no justification for the refinement of the EAW indicative Flood Risk Area for Cardiff. However, the review has highlighted that the boundary of the EAW indicative Flood Risk Area for Cardiff extends into the Vale of Glamorgan Council area and an indicative Flood Risk Area for part of Rhonda Cynon Taff extends into the Cardiff Council area. It is recommended that the indicative Flood Risk Areas are refined along administrative boundary lines. Consultations with the Vale of Glamorgan and Rhonda Cynon Taff Councils are ongoing in order to gain formal agreement to these changes and agree consistency across LLFA PFRAs.

9

10 Contents 1 Introduction General Aims and Objectives Study Area LLFA Responsibilities Introduction LLFA Responsibilities Stakeholder Engagement Public Engagement Further Responsibilities Methodology and Data Review Overview Data Collection Process Data Collected Data Limitations Licensing and Restrictions Past Flood Risk Overview Description of Past Historical Floods Significant Harmful Consequences Future Flood Risk Locally Agreed Surface Water Information Ordinary Watercourses Groundwater Other Sources of Flooding Local Drainage Capacity Consequences of Future Floods Climate Change and Long Term Developments Review of Indicative Flood Risk Areas Overview EAW Identified Blue Squares Review of Blue Squares Consultations with adjacent LLFAs Identification of Flood Risk Areas Hyder Consulting (UK) Limited

11 8 Next Steps References Figures Figure 1-1 Cardiff Council Administrative Area... 2 Figure 3-1 Data Collection Pro forma... 6 Figure 4-1 Summary Map showing locations of Historical Flood Events (yellow dots)... 9 Figure 5-1 Locally agreed surface water information (FMfSW) Figure 6-1 1km squares where the flood risk has been assessed to be above the threshold Figure 6-2 Proposed additional 1km squares that are above the flood risk threshold Figure 6-3 Proposed 1km squares that are above the flood risk threshold Figure 7-1 EAW indicative Flood Risk Area Figure 7-2 EAW indicative Flood Risk Area with blue squares Figure 7-3 Proposed Flood Risk Area Tables Table 2-1 Key Stakeholders... 3 Table 3-1 Timeline for PFRA Completion... 5 Table 3-2 Summary of Historic Data Received... 6 Table 3-3 Additional Data from Stakeholders... 7 Table 4-1 Summary of Historical Flooding Records Table 5-1 Summary of Information on future floods that has been reviewed Table 5-2 Summary of the consequences of flooding on human health Table 5-3 Summary of the consequences of flooding on economic activity Table 5-4 Summary of the consequences of flooding on environmental criteria Table 6-1 Summary of flood risk in blue squares Table 6-2 Details for the three additional 1km squares Hyder Consulting (UK) Limited Page ii

12 Annexes Annex 1 Records of past floods and their significant consequences Annex 2 Records of future floods and their consequences Annex 3 Records of Flood Risk Areas and their rationale Annex 4 Review Checklist Annex 5 GIS layer of Flood Risk Area Hyder Consulting (UK) Limited

13

14 1 Introduction 1.1 General Cardiff Council has commissioned Hyder Consulting (UK) Limited to undertake this Preliminary Flood Risk Assessment (PFRA). Under the Flood Risk Regulations 2009 ( the Regulations ), Lead Local Flood Authorities (LLFAs) are responsible for undertaking a Preliminary Flood Risk Assessment (PFRA) to provide an evidence base with which to identify areas of significant flood risk (Flood Risk Areas) from local sources such as surface runoff, groundwater and ordinary watercourses. Under the Regulations there is a six year flood risk management planning cycle based on a four stage process of: undertaking a PFRA; identifying Flood Risk Areas; preparing flood hazard and risk maps for Flood Risk Areas preparing flood risk management plans for Flood Risk Areas. This PFRA report and annexes form the first two stages of the process. The scope of the PFRA only covers local flood risk and therefore excludes flooding from main rivers, the sea and large raised reservoirs. This study therefore only considers flooding from surface runoff, groundwater and ordinary watercourses and any interaction these have with drainage systems and other sources of flooding including sewers, the sea and main rivers. A definition of these sources of flooding is as follows: Surface runoff rainwater (including snow and other precipitation) which is on the surface of the ground and has not entered a watercourse, drainage system or public sewer. Groundwater water which is below the surface of the ground and in direct contact with the ground or subsoil. Ordinary Watercourses stream, brook, ditch or non-public sewer which is not a main river. 1.2 Aims and Objectives The PFRA is a high level screening exercise which aims to identify areas where there is a significant flood risk. The PFRA involves: Collecting information from relevant organisations regarding past and potential future floods within the study area; Assembling the information into the PFRA report; Reviewing and amending, if necessary, the existing EAW Flood Risk Areas. The PFRA also aims to inform and support the local flood risk management strategy which is required to be produced under the Flood and Water Management Act Hyder Consulting (UK) Limited Page 1

15 1.3 Study Area The study area, shown in Figure 1-1, is the administrative boundary of Cardiff Council which is an area of approximately 158 km 2 and contains a population of around 336,200. The information collated for this PFRA is for areas located within the Cardiff study area. Cardiff falls within the Ely, Taff and Rhymney main river catchments. Two Catchment Flood Management Plans (CFMPs) cover the Cardiff area: the Taff and Ely CFMP (EAW, 2009) and the Eastern Valleys CFMP (EAW, 2009), which includes the River Rhymney. In Cardiff there are estimated to be 148,109 residential properties, 8,011 non-residential properties and 1,341 critical services (hospitals, nursing/care/retirement homes, electricity sub stations, schools, Police, Fire and Ambulance Stations, prisons and sewerage treatment works). This information has been obtained from the EAW National Receptor Database (NRD), a dataset which contains a number of GIS layers categorised into themes of information. Figure 1-1 Cardiff Council Administrative Area Hyder Consulting (UK) Limited Page 2

16 2 LLFA Responsibilities 2.1 Introduction The preparation of a PFRA is just one of several responsibilities of LLFAs under the new legislation. This section provides a brief overview of the responsibilities Cardiff Council are obliged to fulfil under their role as a LLFA. 2.2 LLFA Responsibilities During the review of the summer 2007 flooding, Sir Michael Pitt stated that the role of local authorities should be enhanced so that they take on responsibility for leading the coordination of flood risk management in their areas. As the designated LLFA, Cardiff Council is therefore responsible for leading local flood risk management across Cardiff. 2.3 Stakeholder Engagement Meetings have been held with representatives attending from Strategic Planning, Emergency Management and Drainage Management departments within Cardiff Council along with WAG, DCWW and IDB. The importance of working together is reflected in Regulation 35 of the Regulations and Section 13 of the Flood and Water Management Act. Table 2-1 lists the key stakeholders that were contacted during the preparation of the PFRA: Table 2-1 Key Stakeholders 1 EAW Stakeholder 2 British Waterways 3 Network Rail 4 Dwr Cymru Welsh Water 5 Caldicot and Wentlooge Levels Internal Drainage Board 6 South Wales Fire Service 7 South Wales Police 8 Tongwynlais Community Council 9 St Mellons Community Council 10 Radyr and Morganstown Community Council 11 Pentyrch Community Council 12 Lisvane Community Council 13 Welsh Assembly Government 2.4 Public Engagement Local public knowledge is also considered valuable and information has been documented by Cardiff Council and community councils. Public meetings attended by Cardiff Council have been held following local flood events and the Council has provided Hyder Consulting with Hyder Consulting (UK) Limited Page 3

17 relevant information (such as meeting minutes and plans) for use in the preparation of the PFRA. 2.5 Further Responsibilities Aside from forming partnerships and coordinating and leading on local flood management, there are a number of other key responsibilities that have arisen for LLFAs from the Flood & Water Management Act and the Flood Risk Regulations. These responsibilities include: Investigating flood incidents LLFAs have a duty to investigate and record details of significant flood events within their area. This duty includes identifying which authorities have flood risk management functions and what they have done or intend to do with respect to the incident, notifying risk management authorities where necessary and publishing the results of any investigations carried out. Asset Register LLFAs also have a duty to maintain a register of structures or features which are considered to have an effect on flood risk, including details on ownership and condition as a minimum. The register must be available for inspection and the Secretary of State will be able to make regulations about the content of the register and records. SuDS Approving Body LLFAs are designated the SuDS Approving Body (SAB) for any new drainage system, and therefore must approve, adopt and maintain any new sustainable drainage systems (SuDS) within their area. Local Strategy for Flood Risk Management LLFAs are required to develop, maintain, apply and monitor a local strategy for flood risk management in its area. The local strategy will build upon information such as national risk assessments and will use consistent risk based approaches across different local authority areas and catchments. This PFRA will be a key resource when developing the Local Flood Risk Management Strategy for Cardiff. Works powers LLFAs have powers to undertake works to manage flood risk from surface runoff and groundwater, consistent with the local flood risk management strategy for the area. Designation powers LLFAs, as well as district councils and the EA have powers to designate structures and features that affect flooding or coastal erosion in order to safeguard assets that are relied upon for flood or coastal erosion risk management. Hyder Consulting (UK) Limited Page 4

18 3 Methodology and Data Review 3.1 Overview The PFRA is based on existing and readily derivable data. Table 3-1 shows the key stages of the PFRA process. Table 3-1 Timeline for PFRA Completion Activity Indicative Completion Date 1 Set up governance & develop partnerships February Determine appropriate data systems February Collate information on past & future floods and their consequences March - April Determine locally agreed surface water information April Complete preliminary assessment report document May Record information on past & future floods with significant consequences in spreadsheet May Illustrate information on past and future floods May Review indicative Flood Risk Areas May Identify Flood Risk Areas May Record information including rationale May Data Collection Process The key stakeholders listed in Table 2-1 were consulted to obtain any relevant data that they hold. Figure 3-1 shows a sample of the pro forma spreadsheet that was issued to the Community Councils, Network Rail, Fire Service and the Police to assist in the collection of historic data. Hyder Consulting (UK) Limited Page 5

19 Figure 3-1 Data Collection Pro forma 3.3 Data Collected A brief summary of the historic flooding data received from the various organisations is shown in Table 3-2. Any gaps in this data have also been summarised in this table. The data sets were compared with each other and where several organisations had recorded the same event duplications were removed to ensure that double counting did not occur. Table 3-2 Summary of Historic Data Received Organisation Summary of Data Provided Type of flooding Gaps in data DCWW 814 records of internal and external sewer flooding in Cardiff. Sewer flooding as a result of hydraulic overload of the system. This includes 466 internal (DG5) flooding records and 348 external flooding records. Flooding details limited to just internal or external flooding. No information on flood duration. Cardiff Council 26 flooding records for properties affected in Rhiwbina in June Fluvial from an ordinary watercourse. Limited information on flood extent and total number of properties affected. Historical flooding record for Whitchurch Brook (between 1990 and 2009).10 known events. Fluvial from an ordinary watercourse. Flooding record is relatively recent. No detailed information on the duration, extent and number of properties affected. 145 historical flooding locations/events. Surface water and fluvial from an ordinary watercourse. No information on duration, cause and number of properties affected. Relatively recent and frequent events. Hyder Consulting (UK) Limited Page 6

20 WAG 26 flooding records for historic sewer flooding. 604 properties and 3 schools affected. Sewer. No information on duration or date of event. No details of cause. 13 flooding records for historic surface water flooding. 267 properties affected. Surface Water No information on duration or date of event. No details of cause. Fire Service Police Service Network Rail British Waterways IDB Tongwynlais Community Council St Mellons Community Council Radyr and Morganstown Community Council Pentyrch Community Council Lisvane Community Council 107 records. Records have been screened and, where needed, removed due to some records relating to domestic burst pipes etc. Significant events appear to have occurred on 1 September 2008 and 6 June No data received. No data received. No data received. No historical flooding records within the Council boundary. Groundwater, surface water, fluvial and sewer. 3 commercial properties flooded. Fluvial from an ordinary watercourse. 5 locations of regular flooding identified. Surface water. 4 locations of regular flooding identified. 2 properties flooded. Surface water and fluvial from an ordinary watercourse. 1 property flooded. Surface water. 3 locations of regular flooding identified. Surface water, sewerage and fluvial from an ordinary watercourse. Limited record only going back to August No information has been provided on the duration or details of number of people affected. Limited number of events and events recorded are relatively recent. Mainly minor road and nuisance flooding. Limited information on the dates of the events. Along with the historic data detailed in Table 3-2 additional information, as outlined in Table 3-3, was provided by Cardiff Council and EAW. Table 3-3 Additional Data from Stakeholders Information 1 Cardiff Strategic Flood Consequences Assessment (SFCA) Source Cardiff Council 2 National Receptor Dataset EAW 3 Indicative Flood Risk Areas EAW 4 Areas Susceptible to Surface Water Flooding (AStSWF) EAW 5 Flood Map for Surface Water (FMfSW) EAW 6 Historic Flood Map EAW Hyder Consulting (UK) Limited Page 7

21 7 Areas Susceptible to Groundwater Flooding EAW 8 Cluster Boundaries EAW 9 Flood Zone 3 Map EAW 10 Taff and Ely Catchment Flood Management Plan (CFMP) EAW 11 Eastern Valleys CFMP EAW 12 Severn Estuary Flood Risk Management Strategy EAW 3.4 Data Limitations The PFRA is limited to a certain extent by the quality of the data that has been received. In general the historical flooding information is only for relatively recent events and there is significant variation in the quality, accuracy and detail of the data from the different organisations. Some key gaps in the data sets have been highlighted in Table 3-2. A large proportion of the data was not available in a geo-referenced format, this data was subsequently geo-referenced relying on location descriptions and postcodes to try and accurately allocate the National Grid Reference. Cardiff Council do not currently have a formal database for documenting flood records. It is understood that records from some past events may have been lost or destroyed and held with individuals rather than in formal datasets. In the future it is proposed to develop a GIS system which will record all flooding and drainage geo-referenced data collected as part of the PFRA. This GIS system will enable the LLFA to access and interrogate existing information on past and future floods as well as create new flooding records. 3.5 Licensing and Restrictions The use of some of the data provided by EAW and DCWW is restricted to Cardiff Council in the preparation of the PFRA. Hyder Consulting (UK) Limited Page 8

22 4 Past Flood Risk 4.1 Overview The flood information received from the various stakeholders, detailed in Table 3-2, resulted in over 1000 historic flood records within the study area. The data was reviewed and a master spreadsheet of the appropriate information was compiled. This master data set was then loaded into GIS software to enable the historic flood event data to be viewed in its graphical location along with the National Receptor Database. Analysing the information in its GIS format enabled a logical assessment of the overall flood risk. This section summarises the findings of the review of the historical flooding records in order to extract relevant information on past events with significant harmful consequences. 4.2 Description of Past Historical Floods General A summary map showing the locations of known historical flooding is provided in Figure 4-1 and Table 4-1 provides an overview of the historical flooding records by receptor type. Figure 4-1 Summary Map showing locations of Historical Flood Events (yellow dots) Hyder Consulting (UK) Limited Page 9

23 Table 4-1 Summary of Historical Flooding Records Receptor Type Number of recorded events Residential Properties 341 Critical Services (schools) 9 Non- Residential Properties 156 Open areas (gardens, parks, roads etc) Surface Water Flooding Surface water flooding can occur when heavy rainfall overwhelms the drainage capacity of local areas. The historic records show that localised surface water flooding is widely distributed throughout Cardiff, which is consistent with the general topography of the area Ordinary Watercourses Flooding from ordinary watercourses occurs when a channel cannot cope with the water draining into it from the surrounding land. This can happen, for example, when heavy rain falls on an already waterlogged catchment. A key historic flooding event occurred in June 2009 when 29 residential properties, 5 non-residential properties and 1 critical service (school) were inundated across Cardiff. In addition to the reported property flooding there were 71 records of flooding of open areas. In this event the flooding was predominantly in the area of the Whitchurch Brook located in the northern area of the city. The flooding that occurred in this event was shown to be caused by the flow capacity of this ordinary watercourse being exceeded as a result of a rainfall event with an annual probability of between 3.33% and 5% Groundwater Flooding Groundwater flooding occurs when water levels in the ground rise above surface levels. It is most likely to occur in areas underlain by permeable rocks, called aquifers. These can be extensive, regional aquifers, such as chalk or sandstone, or may be more local sand or river gravels in valley bottoms underlain by less permeable rocks. There is no information on historic groundwater flooding which suggests that the risk of groundwater flooding is low in Cardiff Sewer Flooding Sewers can become overwhelmed by heavy rainfall which can cause flooding. The likelihood of flooding depends on the capacity of the local sewerage system. Land and property can be flooded with water contaminated with raw sewage as a result. Rivers can also become polluted by sewer overflows. A key sewer flooding event occurred in July 2001 with 230 residential properties, 129 non-residential properties and 3 critical services (schools) inundated across Cardiff. The records for this event were received from DCWW s DG5 register but, due to lack of information dating back to 2001, no other details, apart from summary information in the Cardiff Strategic Flood Consequences Assessment (SFCA) (Atkins, 2009), were available for this event. In addition to the reported property flooding there were 177 records of flooding of open areas. The flooding Hyder Consulting (UK) Limited Page 10

24 that occurred in this event was shown to be caused by hydraulic overload of the sewers as a result of a 1.67% annual probability rainfall event which exceeded the design capacity of the sewers (generally designed to a 3.33% annual probability standard). Once a property has been identified on DCWW s DG5 register, it typically means that the water company can put funding in place to take it off the DG5 register and, as such, a recurrence of a similar flood event is unlikely. 4.3 Significant Harmful Consequences National guidance issued by WAG sets thresholds for defining Flood Risk Areas where the risk of flooding is deemed to be significant. No guidance has been issued for defining locally significant harmful consequences as it is up to each LLFA to set its own definition. As agreed with Cardiff Council in this PFRA significant harmful consequences have been defined as the consequences of a flood event which local resources were insufficient to manage and which made national headline news and could occur again. For the localised surface water flooding and both the July 2001 and June 2009 flood events, Cardiff Council has confirmed that local resources were able to cope with the flooding experienced. Therefore, in line with the definition above, the PFRA has confirmed that there are no known past floods which are considered to have had significant harmful consequences. Therefore, no events with significant harmful consequences have been recorded in Annex 1. Hyder Consulting (UK) Limited Page 11

25 5 Future Flood Risk This section summarises all relevant information on future floods. Table 5-1 outlines the relevant information on future flooding that has been reviewed as part of the PFRA. Table 5-1 Summary of Information on future floods that has been reviewed No Information Source Use in Study 1 Flood Map for Surface Water (FMfSW) 2 Flood Zone 3 Map (excluding main river extents) 3 Areas Susceptible to Groundwater Flooding 4 Cardiff Strategic Flood Consequences Assessment (SFCA) 5 Extracts of the Whitchurch Brook Project Appraisal Report (PAR) EAW EAW EAW LLFA LLFA Assess future flood risk associated with surface water flooding Assess future flood risk associated with flooding from ordinary watercourses Assess future flood risk associated with groundwater flooding In the SFCA simplistic assessments have been undertaken to assess the flood risk from surface water and from ordinary watercourses. These assessments are mainly related to future developments. The Flood Map for Surface Water is considered to be more accurate for defining the future flood risk associated with surface water flooding and therefore the SFRA predictions on future flooding have only been used to provide background information. Only summary extracts of the findings of the PAR have been obtained. No detailed information to quantify the future flood risk associated with the Whitchurch Brook has been provided. 5.1 Locally Agreed Surface Water Information No strategic studies have been undertaken to specifically assess the flood risk from surface water in Cardiff. In the Cardiff SFCA (Atkins, 2009) reference has been made to known past surface water flooding locations, however no surface water flood maps have been produced. EAW has produced a national assessment of surface water flood risk in the form of two national mapping datasets. The first generation national mapping, Areas Susceptible to Surface Water Flooding (AStSWF) contains three susceptibility thresholds for a rainfall event that has a 0.5% annual probability of occurrence. The national methodology has since been updated to produce the Flood Map for Surface Water (FMfSW), a revised model with two flood events (3.33% and 0.5% annual probabilities) and two depth thresholds (greater than 0.1m and greater than 0.3m deep). The 0.5% event and 0.3m deep threshold has been used by the EA to produce indicative Flood Risk Areas and adopted by the LLFA to identify properties and critical services at future risk of surface water flooding. As no local information has been produced the FMfSW national dataset forms the locally agreed surface water information. The AStSWF dataset was not adopted as it was viewed to be less Hyder Consulting (UK) Limited Page 12

26 accurate, as the estimates of surface water flows did not consider infiltration and the effects of sewers. In addition the FMfSW dataset takes into account buildings which were not represented in the AStSWF dataset. The locally agreed surface water information is shown in Figure 5-1 and illustrates areas that are predicted to flood to a depth greater than 300mm associated with a 0.5% annual probability rainfall event. Figure 5-1 Locally agreed surface water information (FMfSW) 5.2 Ordinary Watercourses There are four key ordinary watercourses in Cardiff: the Whitchurch Brook, Fairwater Stream, Roath Brook and Nant Glandulas. Although designated as ordinary watercourses the EAW Flood Map covers these watercourses from the point at which their catchment areas exceed 3km². As these four watercourses are an important source of flooding in Cardiff the main river sections from the flood map have been removed in order to derive information about flooding from ordinary watercourses (see Section 5.6). A number of other ordinary watercourses are present in the area, many of which are partly culverted under the densely developed areas of the city. The Dock Feeder runs from an offtake from the River Taff at Blackweir to Bute Dock though sections of open canalised channels and culverts. It is understood that no flood studies have been undertaken for this watercourse. The Wentlooge Levels within the Cardiff Council boundary extends from the Rhymney River in the west to St Mellons Business Park in the East. The Wentlooge Levels comprise an area of reclaimed land. As part of the reclamation and subsequent management, an extensive system of ditches (reens) exists to drain the low lying land. A high level study was undertaken as part of the Cardiff SFCA (Atkins, 2009) to indicatively assess the risk of flooding from the reen system. This assessment only predicted significant flooding of low lying areas outside the Cardiff Council boundary. Therefore, in addition to the active management and regular maintenance of the reen system by the IDB, it is considered that there is no significant risk of flooding from the reens within the Cardiff Council boundary. Hyder Consulting (UK) Limited Page 13

27 5.3 Groundwater It is understood through consultations with key stakeholders that there is no local information on future groundwater flooding for Cardiff. The risk of groundwater flooding is considered to be low, and this is confirmed by the Taff and Ely CFMP (EAW, 2009) which states that groundwater flooding is not considered to be a significant issue within the catchment. The EAW map showing Areas Susceptible to Groundwater Flooding has been used in conjunction with the future Surface Water Flood Map (as this identifies potential areas of ponding due to topographical depressions) to assess the consequences of future groundwater flooding. The results of these are outlined in Section Other Sources of Flooding No local information on other sources of future flooding has been obtained for the Cardiff area. 5.5 Local Drainage Capacity Cardiff has both separate and combined foul and surface drainage systems. No specific information has been obtained on the capacity of highway drainage within the Cardiff area. In addition, although DCWW historical flood records are given a risk category based on a prescribed methodology (a combination of frequency of flooding and storm return periods), no specific information has been obtained on the capacity of sewer systems within the Cardiff area In line with national design standards and information on past floods in Cardiff, the capacity (surcharged conditions) of highway drainage networks and sewers is likely to be exceeded in rainfall events with an annual probability in the order of 3.33%. 5.6 Consequences of Future Floods Detailed records of future floods and their possible consequences are provided in Annex Human Health Table 5-2 summarises the consequences of flooding on human health using the indicators of the number of people and critical services affected. Table 5-2 Summary of the consequences of flooding on human health Criteria Surface Runoff Ordinary Watercourses Number of People Groundwater 4,287 2, Number of Critical Services The number of people at risk of flooding has been calculated by multiplying the number of properties at risk by There are different methods for calculating the number of properties and in this study the address point data rather than the Flood Map for Surface Water Property Hyder Consulting (UK) Limited Page 14

28 Count Method has been used. In the early stages of the project the use of the Flood Map for Surface Water Property Count Method was not feasible due to the combination of the large amount of reformatting of the OS building layer and the study deadline. It is likely that the use of the address point data will slightly under predict the number of people and critical services affected. However, given the high level screening nature of the PFRA and the high level of uncertainty associated with the flood data sets the use of the address point data is considered to be acceptable Economic Activity Table 5-3 summarises the consequences of flooding on economic activity in Cardiff. The predicted consequences of flooding of road infrastructure, although included in Table 5-3, is not considered to be adverse as alternative routes are available due to the dense road network throughout Cardiff. In addition the surface water flood maps are believed to over predict the flood risk to this infrastructure. Table 5-3 Summary of the consequences of flooding on economic activity Criteria Surface Runoff Ordinary Watercourses Groundwater Number of nonresidential properties Infrastructure network (e.g. length of roads and rail flooded) M4-0.9km A48 1.3km A km A km No adverse consequences identified No adverse consequences identified Environment Table 5-4 summarises the consequences of flooding on the environment in Cardiff. The information has been obtained by interrogating NRD data against the associated flood extent. The consequences of the predicted flooding of environmental assets is not considered to be adverse. Hyder Consulting (UK) Limited Page 15

29 Table 5-4 Summary of the consequences of flooding on environmental criteria Criteria Surface Runoff Ordinary Watercourses Pollution Prevention and Control (PPC) sites Groundwater Control of Major Accident Hazard (COMAH) sites No Data Provided Special Areas of Conservation (SAC) Special Protection Areas (SPA) Ramsar Sites Sites of Special Scientific Interest (SSSI) World Heritage Sites Scheduled Monuments Listed Buildings Registered parks and gardens Climate Change and Long Term Developments The Evidence There is clear scientific evidence that global climate change is happening now. It cannot be ignored. Over the past century around the UK we have seen sea level rise and more of our winter rain falling in intense wet spells. Seasonal rainfall is highly variable. It seems to have decreased in summer and increased in winter, although winter amounts changed little in the last 50 years. Some of the changes might reflect natural variation, however the broad trends are in line with projections from climate models. Greenhouse gas (GHG) levels in the atmosphere are likely to cause higher winter rainfall in future. Past GHG emissions mean some climate change is inevitable in the next years. Lower emissions could reduce the amount of climate change further into the future, but changes are still projected at least as far ahead as the 2080s. Hyder Consulting (UK) Limited Page 16

30 We have enough confidence in large scale climate models to say that we must plan for change. There is more uncertainty at a local scale but model results can still help us plan to adapt. For example we understand rain storms may become more intense, even if we can t be sure about exactly where or when. By the 2080s, the latest UK climate projections (UKCP09) are that there could be around three times as many days in winter with heavy rainfall (defined as more than 25mm in a day). It is plausible that the amount of rain in extreme storms (with a 1 in 5 annual chance, or rarer) could increase locally by 40% Key Projections for Severn River Basin District If emissions follow a medium future scenario, UKCP09 projected changes by the 2050s relative to the recent past are Winter precipitation increases of around 12% (very likely to be between 2 and 26%) Precipitation on the wettest day in winter up by around 9% (very unlikely to be more than 22%) Relative sea level at Bristol very likely to be up between 10 and 40cm from 1990 levels (not including extra potential rises from polar ice sheet loss) Peak river flows in a typical catchment likely to increase between 9 and 18% Increases in rain are projected to be greater at the coast and in the south of the district Implications for Flood Risk Climate changes can affect local flood risk in several ways. Impacts will depend on local conditions and vulnerability. Wetter winters and more of this rain falling in wet spells may increase river flooding along the Severn and its tributaries. More intense rainfall causes more surface runoff, increasing localised flooding and erosion. In turn, this may increase pressure on drains, sewers and water quality. Storm intensity in summer could increase even in drier summers, so we need to be prepared for the unexpected. Drainage systems in the district have been modified to manage water levels and could help in adapting locally to some impacts of future climate on flooding, but may also need to be managed differently. Rising sea or river levels may also increase local flood risk inland or away from major rivers because of interactions with drains, sewers and smaller watercourses. Where appropriate, we need local studies to understand climate impacts in detail, including effects from other factors like land use. Sustainable development and drainage will help us adapt to climate change and manage the risk of damaging floods in future Adapting to Change Past emission means some climate change is inevitable. It is essential we respond by planning ahead. We can prepare by understanding our current and future vulnerability to flooding, developing plans for increased resilience and building the capacity to adapt. Regular review and adherence to these plans is key to achieving long-term, sustainable benefits. Although the broad climate change picture is clear, we have to make local decisions against deeper uncertainty. We will therefore consider a range of measures and retain flexibility to adapt. This approach, embodied within flood risk appraisal guidance, will help to ensure that we do not increase our vulnerability to flooding. Hyder Consulting (UK) Limited Page 17

31 5.7.5 Long Term Developments It is possible that long term developments might affect the occurrence and significance of flooding. However current planning policy aims to prevent new development from increasing flood risk. In Wales, Technical Advice Note 15 (TAN15) on development and flood risk sets out a precautionary framework to guide planning decisions. The overarching aim of the precautionary framework is "to direct new development away from those areas which are at high risk of flooding." Adherence to Government policy ensures that new development does not increase local flood risk. However, in exceptional circumstances the Local Planning Authority may accept that flood risk can be increased contrary to Government policy, usually because of the wider benefits of a new or proposed major development. Any exceptions would not be expected to increase risk to levels which are "significant" (in terms of the Government's criteria). Consultation with Cardiff Strategic Planning department has confirmed that there are no new or proposed major developments which may increase local flood risk within Cardiff Local Information Concerning Climate Change Impacts on Flood Risk No local information has been made available regarding climate change impacts on future flood risk. Hyder Consulting (UK) Limited Page 18

Preliminary Flood Risk Assessment:

Preliminary Flood Risk Assessment: Preliminary Flood Risk Assessment: 15 th March 2011 Reference Status Date of Issue TX400010 1 st Issue for 04/03/11 The Environment Agency Prepared by Checked by Approved by Ellen Campbell & Brendan Stone

More information

London Borough of Merton Local Flood Risk Management Strategy

London Borough of Merton Local Flood Risk Management Strategy Local Flood Risk Management Strategy Summary 2014-2020 Introduction In response to the severe flooding across large parts of England and Wales in summer 2007, the Government has recently enacted the Flood

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT Appendix 1 PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF SOUTHWARK Quality Management Quality Management DOCUMENT INFORMATION Title: London Borough of Southwark PFRA Owner: John Kissi

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF RICHMOND UPON THAMES Quality Management Quality Management DOCUMENT INFORMATION Title: Owner: Version: Status: Project Number: File Name:

More information

Warwickshire County Council. Peter Bones petebones@warwickshire.gov.uk 01926 412 826 TO COMPLETE. Documents submitted. EA date received LLFA

Warwickshire County Council. Peter Bones petebones@warwickshire.gov.uk 01926 412 826 TO COMPLETE. Documents submitted. EA date received LLFA LLFAs should complete the pale blue sections with the relevant information, and send to their Environment Agency Local Area Contact along with the Preliminary Assessment Report and Annexes. Yellow and

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF SUTTON Quality Management Quality Management DOCUMENT INFORMATION Title: Owner: Version: Status: Project Number: File Name: London Borough

More information

2 ND SEPTEMBER 2014. Report of the Bi-Borough Executive Director for Transport and Technical Services

2 ND SEPTEMBER 2014. Report of the Bi-Borough Executive Director for Transport and Technical Services London Borough of Hammersmith & Fulham COMMUNITY SAFETY, ENVIRONMENT & RESIDENTS SERVICES POLICY & ACCOUNTABILITY COMMITTEE 2 ND SEPTEMBER 2014 SURFACE WATER MANAGEMENT PLAN (SWMP) Report of the Bi-Borough

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF LAMBETH Executive Summary Quality Management DOCUMENT INFORMATION Title: London Borough of Lambeth PFRA Owner: Owen Davies Version: 1.0

More information

Wiltshire SWMP Project Governance Framework

Wiltshire SWMP Project Governance Framework Wiltshire SWMP Project Governance Framework Final Framework Prepared on behalf of This document has been prepared in accordance with the scope of Scott Wilson's appointment with its client and is subject

More information

London Borough of Croydon Local Flood Risk Management Strategy

London Borough of Croydon Local Flood Risk Management Strategy London Borough of Croydon Local Flood Risk Management Strategy Summary 2014-2020 Introduction In response to the severe flooding across large parts of England and Wales in summer 2007, the Government has

More information

Newbiggin House Farm,

Newbiggin House Farm, Newbiggin House Farm, Near Waberthwaite Flood Investigation Report 32 Flood Event 30/8/2012 Cumbria County Council Version Undertaken by Reviewed by Approved by Date Preliminary Colin Parkes Anthony Lane

More information

Bolton s Flood Risk Management Strategy

Bolton s Flood Risk Management Strategy Bolton s Flood Risk Management Strategy www.bolton.gov.uk Public Summary Bolton s Flood Risk Management Strategy Public Summary Introduction Over 5.5 million properties in England and Wales are at risk

More information

Homes and Environment Scrutiny Committee. (Environment & Transport)

Homes and Environment Scrutiny Committee. (Environment & Transport) REPORT TO: REPORT NO: Homes and Environment Scrutiny Committee HHPPE/89/15S DATE: 9 September 2015 LEAD MEMBER: Councillor David A Bithell (Environment & Transport) CONTACT OFFICER: Neil Taunt (Tel: 729734)

More information

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document

London Borough of Waltham Forest LOCAL FLOOD RISK MANAGEMENT STRATEGY. Summary Document LOCAL FLOOD RISK MANAGEMENT STRATEGY Summary Document October 2013 Local Flood Risk Management Strategy Summary 1 Introduction 2 Partner responsibilities 3 What do we know about flooding in the borough?

More information

PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON

PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF WANDSWORTH Quality Management Quality Management DOCUMENT INFORMATION Title: London Borough of Wandsworth PFRA Owner: Adam Hutchings Version:

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF HARROW DOCUMENT INFORMATION Title Preliminary Flood Risk Assessment Preliminary Assessment Report Owner Version 01 Status Final Project

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF ISLINGTON Document Information Document Information Title: Preliminary Flood Risk Assessment for London Borough of Islington Owner: Bevan

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF NEWHAM Revision Schedule Revision Schedule DOCUMENT INFORMATION Title: PFRA for London Borough of Newham Owner: John East Version: 1.1 Status:

More information

Essex County Council Flood Investigation Report

Essex County Council Flood Investigation Report Essex County Council Stock City of Chelmsford Rev Date Details Author Checked and Approved By 01 February 2015 Draft report for stakeholder consultation Ed Clarke Flood Investigation Engineer Lucy Shepherd

More information

FLOOD RISK RECENT TRENDS AND POLICY RESPONSES

FLOOD RISK RECENT TRENDS AND POLICY RESPONSES FLOOD RISK RECENT TRENDS AND POLICY RESPONSES DEVELOPING WESTMINSTER S LOCAL PLAN Booklet No. 2 LDF Consultation - CMP Revision November 2013 INTRODUCTION CLLR ROBERT DAVIS Westminster is at risk of flooding

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF CROYDON Quality Management Quality Management DOCUMENT INFORMATION Title: Owner: Version: Status: Project Number: File Name: London Borough

More information

Creating the environment for business

Creating the environment for business 1. Introduction 1.1 Introduction to Water Cycle Strategies (WCS) 1.1.1 Background The water cycle describes the pathways and processes through which water moves through the natural and built environment,

More information

Strategic Flood Risk Assessment

Strategic Flood Risk Assessment local development framework Strategic Flood Risk Assessment LOCAL DEVELOPMENT FRAMEWORK ROYAL BOROUGH OF KINGSTON UPON THAMES Level 1 and 2 April 2011 Contents Executive Summary 5 Part 1 - Aiding Planning

More information

Groundwater Flooding: a UK Perspective

Groundwater Flooding: a UK Perspective Groundwater Flooding: a UK Perspective David Macdonald British Geological Survey Maclean Building Crowmarsh Gifford Wallingford OX10 8BB Tel 01491 838800 NERC All rights reserved Talk outline Definition

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF MERTON 0BQuality Management Quality Management DOCUMENT INFORMATION Title: London Borough of Merton PFRA Owner: Lee Baldwin Version: 1.0

More information

Brighton & Hove City Council

Brighton & Hove City Council Brighton & Hove City Council On behalf of Project Ref: 23301/005 Rev: E Date: April 2014 Office Address: Caversham Bridge House, Waterman Place, Reading, Berkshire RG1 8DN T: +44 (0)118 950 0761 F: +44

More information

SURFACE WATER MANAGEMENT PLAN

SURFACE WATER MANAGEMENT PLAN SURFACE WATER MANAGEMENT PLAN DRAIN LONDON LONDON BOROUGH OF RICHMOND UPON THAMES Quality Management Quality Management DOCUMENT INFORMATION Title: Owner: Version: Status: Project Number: File Name: Surface

More information

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers

Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Flood Risk Assessment and Drainage Impact Assessment: Planning Guidance for Developers Development and Regeneration Services Glasgow City Council 229 George Street Glasgow G1 1QU May 2011 1. Introduction...-

More information

SURFACE WATER MANAGEMENT PLAN Volume 1

SURFACE WATER MANAGEMENT PLAN Volume 1 SURFACE WATER MANAGEMENT PLAN Volume 1 DRAIN LONDON LONDON BOROUGH BRENT OF Hyder Consulting (UK) Limited 2212959 Aston Cross Business Village 50 Rocky Lane Aston Birmingham B6 5RQ United Kingdom Tel:

More information

Managing flood risk in Camden The London Borough of Camden flood risk management strategy

Managing flood risk in Camden The London Borough of Camden flood risk management strategy Managing flood risk in Camden The London Borough of Camden flood risk management strategy Contents 1. Foreword 3 2. Executive summary 4 3. Glossary 6 4. Introduction 8 4.1 Strategy objectives 8 4.2 Guiding

More information

SURFACE WATER MANAGEMENT PLAN Volume 1

SURFACE WATER MANAGEMENT PLAN Volume 1 SURFACE WATER MANAGEMENT PLAN Volume 1 DRAIN LONDON LONDON BOROUGH OF HARROW Quality Page DOCUMENT INFORMATION Title Surface Water Management Plan Owner AECOM Ltd Version 02 Status Final Project Number

More information

Contents... 2. Foreword... 5. Introduction... 6

Contents... 2. Foreword... 5. Introduction... 6 Havering Local Flood Risk Management Strategy 2015 Contents Contents... 2 Foreword... 5 Introduction... 6 Structure of Strategy... 6 Review of the Strategy... 7 Annual Plans... 7 Guiding principles...

More information

Introduction. The vision of the West Yorkshire Combined Authority (WYCA) Flood Risk Partnership

Introduction. The vision of the West Yorkshire Combined Authority (WYCA) Flood Risk Partnership WYCA SuDS Guidance Introduction As part of the government s continuing commitment to protect people and property from flood risk, the Department for Communities and Local Government and the Department

More information

Vital Earth Composting Facility Flood Risk and Drainage Statement

Vital Earth Composting Facility Flood Risk and Drainage Statement Vital Earth Flood Risk and Drainage Statement Final December 2011 Prepared for Vital Earth Ltd Revision Schedule Flood Risk and Drainage Statement December 2011 Rev Date Details Prepared by Reviewed by

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF HILLINGDON Revision Schedule Revision Schedule DOCUMENT INFORMATION Title: PFRA for London Borough of Hillingdon Owner: Ian Thynne Version:

More information

Flood Risk Management in Southwark

Flood Risk Management in Southwark Flood Risk Management in Southwark 1 Presented to Borough & Bankside Community Council 25 th April 2012 By Flood and Drainage Team Agenda Item 11 IN BRIEF Background Legislation What have we done? What

More information

SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY

SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY SUFFOLK COASTAL DISTRICT COUNCIL DOMESTIC FLOOD PROTECTION POLICY 1. Introduction 1.1 The Council recognises the threat to local communities from flooding following severe weather events and as a result

More information

FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES

FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES FLOOD RISK AND SURFACE WATER DRAINAGE ASSESSMENT HILLHOUSE RESTORATION SITE, OFF JAMESON ROAD, THORNTON CLEVELEYS ON BEHALF OF NPL ESTATES Integra Consulting Engineers Limited NS / 2543 Fountain House

More information

Community Services and Safety Scrutiny Sub-Committee 1 November 2011

Community Services and Safety Scrutiny Sub-Committee 1 November 2011 REPORT TO: Community Services and Safety Scrutiny Sub-Committee 1 November 2011 AGENDA ITEM: 6 SUBJECT: LEAD OFFICER: CABINET MEMBER: Flood Prevention Stephen McDonald Executive Director of Planning and

More information

Environment Agency 2014 All rights reserved. This document may be reproduced with prior permission of the Environment Agency.

Environment Agency 2014 All rights reserved. This document may be reproduced with prior permission of the Environment Agency. Flood and coastal erosion risk management Long-term investment scenarios (LTIS) 2014 We are the Environment Agency. We protect and improve the environment and make it a better place for people and wildlife.

More information

SUFFOLK FLOOD RISK MANAGEMENT JOINT SCRUTINY PANEL ANNUAL REPORT 2010. Working in Partnership with

SUFFOLK FLOOD RISK MANAGEMENT JOINT SCRUTINY PANEL ANNUAL REPORT 2010. Working in Partnership with SUFFOLK FLOOD RISK MANAGEMENT JOINT SCRUTINY PANEL ANNUAL REPORT 2010 Working in Partnership with Suffolk Flood Risk Management Joint Scrutiny Panel Foreword by Councillor Gary Green, Chairman of the Suffolk

More information

Sheffield Flood Risk Management Strategy. Draft Edition 1: Version 1

Sheffield Flood Risk Management Strategy. Draft Edition 1: Version 1 Sheffield Flood Risk Management Strategy Draft Edition 1: Version 1 Prepared by: Sheffield City Council Regeneration and Development Services For further information, please contact: Sheffield City Council

More information

A Guide to the Role of Community Flood Wardens

A Guide to the Role of Community Flood Wardens A Guide to the Role of Community Flood Wardens What is a Community Flood Warden Scheme? Community Flood Warden schemes are completely voluntary, and can consist of a single person or several people acting

More information

Flood Risk & Surface Water Management. Page 1 of 20

Flood Risk & Surface Water Management. Page 1 of 20 Page 1 of 20 Flood Risk & Surface Water Management Flood Risk & Surface Water Management and the Planning Process Introduction The purpose of this document is to increase awareness of the potential of

More information

London Borough of Hammersmith and Fulham. Updated Surface Water Management Plan. April 2015 UNITED KINGDOM & IRELAND.

London Borough of Hammersmith and Fulham. Updated Surface Water Management Plan. April 2015 UNITED KINGDOM & IRELAND. London Borough of Hammersmith and Fulham Updated Surface Water Management Plan UNITED KINGDOM & IRELAND Prepared for: 47065080 REVISION SCHEDULE Rev Date Details Prepared by Reviewed by Approved by 1 December

More information

Surface Water Management Plan Technical Guidance

Surface Water Management Plan Technical Guidance Surface Water Management Plan Technical Guidance March 2010 www.defra.gov.uk Publishing organisation Department for Environment, Food and Rural Affairs Flood Management Division, Ergon House, Horseferry

More information

London Borough of Bromley LEAD LOCAL FLOOD AUTHORITY UPDATE AND GRANT DRAW-DOWN

London Borough of Bromley LEAD LOCAL FLOOD AUTHORITY UPDATE AND GRANT DRAW-DOWN Report No. ES15041 London Borough of Bromley PART ONE - PUBLIC Decision Maker: Executive Date: 9 th September 2015 Decision Type: Non-Urgent Executive Non-Key Title: Contact Officer: Chief Officer: Ward:

More information

East Riding of Yorkshire Council

East Riding of Yorkshire Council East Riding of Yorkshire Council Lead Local Flood Authority Interim Standing Advice Revision A - April 2015 1. Introduction From April 2015 the Lead Local Flood Authority (LLFA) became a statutory consultee

More information

PRELIMINARY FLOOD RISK ASSESSMENT

PRELIMINARY FLOOD RISK ASSESSMENT PRELIMINARY FLOOD RISK ASSESSMENT DRAIN LONDON LONDON BOROUGH OF Ealing Revision Schedule Revision Schedule DOCUMENT INFORMATION Title: PFRA for London Borough of Ealing Owner: Sebastian Navaranjan Version:

More information

Flooding from groundwater

Flooding from groundwater Flooding from groundwater Improved flood warning service - frequently asked questions General 1 - What is flooding from groundwater? 2 - Who deals with flooding from groundwater? 3 - How do I find out

More information

06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH

06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH 06 - NATIONAL PLUVIAL FLOOD MAPPING FOR ALL IRELAND THE MODELLING APPROACH Richard Kellagher 1, Mike Panzeri 1, Julien L Homme 1, Yannick Cesses 1, Ben Gouldby 1 John Martin 2, Oliver Nicholson 2, Mark

More information

INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies

INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION. Infrastructure Flood Protection Remediation Policies INFRASTRUCTURE, FLOOD PROTECTION AND REMEDIATION Infrastructure Flood Protection Remediation Policies DRAFT POOLBEG PLANNING SCHEME 196 FIGURE 9.1: UTILITIES WAYLEAVES Electricity Cables 8m Wayleave for

More information

AGMA Policy for Investigating Flood Incidents

AGMA Policy for Investigating Flood Incidents AGMA Policy for Investigating Flood Incidents THE LEGISLATION Section 19 of the Flood and Water Management Act 2010 states that: (1) On becoming aware of a flood in its area, a lead local flood authority

More information

Action plans for hotspot locations - Ash Study

Action plans for hotspot locations - Ash Study Appendix 9 Action plans for hotspot locations - Ash Study Ash Vale North 1. Local evidence indicates the culvert could not discharge during December 2013 because the outlet was blocked on the western side

More information

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year

1 in 30 year 1 in 75 year 1 in 100 year 1 in 100 year plus climate change (+30%) 1 in 200 year Appendix C1 Surface Water Modelling 1 Overview 1.1 The Drain London modelling was designed to analyse the impact of heavy rainfall events across each London borough by assessing flow paths, velocities

More information

Wye and Usk Catchment Flood Management Plan. Summary Report January 2010. managing flood risk

Wye and Usk Catchment Flood Management Plan. Summary Report January 2010. managing flood risk Wye and Usk Catchment Flood Management Plan Summary Report January 2010 managing flood risk We are Environment Agency Wales. It s our job to look after your environment and make it a better place for you,

More information

SURFACE WATER MANAGEMENT PLAN

SURFACE WATER MANAGEMENT PLAN SURFACE WATER MANAGEMENT PLAN DRAIN LONDON LONDON BOROUGH OF LEWISHAM Document Information Document Information Title: Surface Water Management Plan for London Borough of Lewisham Owner: Bo Quatresols

More information

London Borough of Newham. Local Flood Risk Management Strategy

London Borough of Newham. Local Flood Risk Management Strategy London Borough of Newham Local Flood Risk Management Strategy Version 5, September 2015 Local Flood Risk Management Strategy for the London Borough of Newham Document Management: Version Control Title:

More information

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED

WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WEST LONDON PIPELINE AND STORAGE LIMITED AND UNITED KINGDOM OIL PIPELINES LIMITED WLPS BUNCEFIELD REBUILD Flood Risk Assessment Green Lane Hemel Hempstead Hertfordshire HP2 7HZ September 2009 Prepared

More information

Managing Surface Water Flooding in Paddock Wood Briefing note - June 2011

Managing Surface Water Flooding in Paddock Wood Briefing note - June 2011 Managing Surface Water Flooding in Paddock Wood Briefing note - June 2011 Information for Editors What is the reason for this initiative? 1. Legal Requirements The main drivers are the Flood Risk Regulations

More information

Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter

Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter Chapter 9: Water, Hydrology and Drainage Land West of Uttoxeter ENVIRONMENTAL STATEMENT: VOLUME 1 9.1 INTRODUCTION 9.1.1 This Chapter considers the effects of the Project on surface water and groundwater

More information

Strategic Flood Risk Assessment Update 2015

Strategic Flood Risk Assessment Update 2015 Strategic Flood Risk Assessment Update 2015 On behalf of Contents Glossary... iv Executive Summary... 1 1 Introduction... 4 1.1 Overview... 4 1.2 Future Development in Lewisham Borough... 5 2 SFRA Approach...

More information

Kirklees Surface Water Management Plan

Kirklees Surface Water Management Plan 2011 Kirklees Surface Water Management Plan An evidenced statement on the surface water flood risk in Kirklees and a delivery plan for reduction of the risk across the district Tom Ghee Kirklees Council

More information

FLOOD CONTINGENCY PLAN

FLOOD CONTINGENCY PLAN Unrestricted Copy DERBYSHIRE LOCAL RESILIENCE FORUM FLOOD CONTINGENCY PLAN Issued January 2013 Revised Flood Contingency Plan CONTENTS CONTENTS RECORD OF AMENDMENTS CIRCULATION LIST Page i iii iv 1 BACKGROUND

More information

(http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf

(http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf Possible Submission about Water and Flooding (See maps 3a and 3b) From Mole Valley Local Development Framework: Strategic Flood Risk Assessment Update 2012 (http://www.molevalley.gov.uk/media/pdf/c/r/srfa_-_updated_jnauary_2012.pdf

More information

River Flooding and the Grid-to-Grid Hydrological Model

River Flooding and the Grid-to-Grid Hydrological Model River Flooding and the Grid-to-Grid Hydrological Model Summary of Impacts Impact Mitigating the annual costs of damage from ordinary river flooding Mitigating the costs of damage from extreme river flooding

More information

SURFACE WATER MANAGEMENT PLAN

SURFACE WATER MANAGEMENT PLAN SURFACE WATER MANAGEMENT PLAN DRAIN LONDON LONDON BOROUGH OF CROYDON Executive Summary Executive Summary This document forms the Surface Water Management Plan (SWMP) for the London Borough of Croydon which

More information

Climate Change and Infrastructure Planning Ahead

Climate Change and Infrastructure Planning Ahead Climate Change and Infrastructure Planning Ahead Climate Change and Infrastructure Planning Ahead Infrastructure the physical facilities that support our society, such as buildings, roads, railways, ports

More information

Designed and produced by geo-graphicsdesign.com DP 300 3/02

Designed and produced by geo-graphicsdesign.com DP 300 3/02 Designed and produced by geo-graphicsdesign.com DP 300 3/02 Guidance for Developers and Regulators Purpose This booklet is produced on behalf of the North East Scotland Flooding Advisory Group and is intended

More information

Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by

Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by Guidance on the use of sustainable drainage systems (SUDS) and an overview of the adoption policy introduced by Easy guide to Sustainable drainage systems 02 Contents Page Introduction 05 Purpose of this

More information

Issue: 2 Adopted by Council: 20/02/07. Directorate of Environment and Regeneration Planning Services

Issue: 2 Adopted by Council: 20/02/07. Directorate of Environment and Regeneration Planning Services Issue: 2 Adopted by Council: 20/02/07 Directorate of Environment and Regeneration Planning Services LOCAL PLANNIING GUIIDANCE NOTE NO..19:: SUSTAIINABLE DRAIINAGE SYSTEMS Background The provision of adequate

More information

Local Flood Risk Management Strategy

Local Flood Risk Management Strategy Local Flood Risk Management Strategy Lewisham Local Flood Risk Management Strategy - June 2015 1 Foreword I am sure you will agree that flooding has been an issue for many over the past few years, particularly

More information

Summary of SFRA Data. Contribution to SFRA. Data Category Format Source. Licensing

Summary of SFRA Data. Contribution to SFRA. Data Category Format Source. Licensing Summary of Data Data Category Format Source Climate Change Scenarios for the United Kingdom: The UKCIP02 Scientific Climate Climate Change and London Transport Systems Climate London s Warming: A Climate

More information

1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies.

1.2 This technical note provides a preliminary investigation into the Flood Risk and provides outline drainage strategies. ODYSSEY MARKIDES TECHNICAL NOTE PROJECT : CHAILEY HOUSE, BLEWBURY JOB NO. : 14-216 NOTE TITLE : PRELIMINARY FLOODING AND DRAIANGE AUTHOR : STEVEN ROOTH APPROVED : ANDREAS MARKIDES DATE : 02/09/2014 1.0

More information

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details Appendix C - Risk Assessment: Technical Details Page C1 C1 Surface Water Modelling 1. Introduction 1.1 BACKGROUND URS Scott Wilson has constructed 13 TUFLOW hydraulic models across the London Boroughs

More information

Taylor Wimpey UK Ltd. December 2007

Taylor Wimpey UK Ltd. December 2007 Taylor Wimpey UK Ltd December 2007 QM Issue/revision Issue 1 Revision 1 Revision 2 Revision 3 Remarks Draft For Planning Date 3 August 2007 20 December 2007 Prepared by D Gooding P Barton Signature Checked

More information

Guidance Notes: GARDEN FLOODING

Guidance Notes: GARDEN FLOODING Page 1 of 7 Guidance Notes: GARDEN FLOODING If you are unsure about anything within these notes then please contact the Flood Risk Management (FRM) team using the details at the end of this document. Water

More information

Appendix B: SWMP Contact List

Appendix B: SWMP Contact List Appendix B: SWMP Contact List South Essex SWMP Working Group List, January 2011 Client Group Matthew Winslow Basildon BC Client SWMP Project Manager matthew.winslow@basildon.gov.uk Emmanuelle Meunier Basildon

More information

FLOOD RISKS IN LONDON

FLOOD RISKS IN LONDON Environment Committee FLOOD RISKS IN LONDON Summary of findings April 2014 About this summary 2 This is a summary of the findings of the Environment Committee s investigation into flood risk. In January

More information

Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015.

Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015. Product 4 (Detailed Flood Risk) for: Sam Murray (Amey) Site: Land at Kingsnorth Reference: KSL151125 KR79 Date: 30 th November 2015 Contents Flood Map Confirmation Flood Map Extract Model Output Data Data

More information

Objective 4: Enhanced community education, flood awareness and preparedness

Objective 4: Enhanced community education, flood awareness and preparedness Objective 4: Enhanced community education, flood awareness and preparedness Understanding the extent and full impacts of flooding is essential for planning for potential future pressures on the drainage

More information

Recommendations for future developments

Recommendations for future developments C Recommendations for future developments C.1 Reducing flood risk through site layout and design C.1.1 C.1.2 Flood risk should be considered at an early stage in deciding the layout and design of a site

More information

Preliminary Environmental Information Report: Appendix 16.C. Flood Warning and Evacuation Plan

Preliminary Environmental Information Report: Appendix 16.C. Flood Warning and Evacuation Plan Preliminary Environmental Information Report: Appendix 16.C Flood Warning and Evacuation Plan THIS PAGE IS LEFT INTENTIONALLY BLANK Page 2 of 30 Contents SUMMARY 1. INTRODUCTION... 9 1.1 Background...

More information

Draft New Museums Site Development Framework Supplementary Planning Document SUSTAINABILITY APPRAISAL SCREENING REPORT

Draft New Museums Site Development Framework Supplementary Planning Document SUSTAINABILITY APPRAISAL SCREENING REPORT Draft New Museums Site Development Framework Supplementary Planning Document SUSTAINABILITY APPRAISAL SCREENING REPORT MAY 2015 1 Contents 1 INTRODUCTION 3 2 DRAFT NEW MUSEUMS SITE SPD 4 3 STRATEGIC ENVIRONMENTAL

More information

How To Manage Flooding In The London Borough Of Hounslow

How To Manage Flooding In The London Borough Of Hounslow SURFACE WATER MANAGEMENT PLAN DRAIN LONDON LONDON BOROUGH OF HOUNSLOW Quality Management Quality Management DOCUMENT INFORMATION Title: Surface Water Management Plan for London Borough of Hounslow Owner:

More information

FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY

FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY FLOOD RISK ASSESSMENT AND DRAINAGE STRATEGY London Rd. WATERLOOVILE FOR McCarthy & Stone Ltd. July 2010 Such Salinger Peters Ltd 30558-1- Flood Risk Assessment & Drainage Strategy Contents Paragraph Page

More information

SURFACE WATER MANAGEMENT PLAN Evidence Base

SURFACE WATER MANAGEMENT PLAN Evidence Base SURFACE WATER MANAGEMENT PLAN Evidence Base DRAIN LONDON LONDON BOROUGH OF HILLINGDON Acknowledgements i Acknowledgements Acknowledgements A number of people and organisations outside Hillingdon Council

More information

New Brunswick s Flood Risk Reduction Strategy. Province of New Brunswick PO 6000, Fredericton NB E3B 5H1. www.gnb.ca

New Brunswick s Flood Risk Reduction Strategy. Province of New Brunswick PO 6000, Fredericton NB E3B 5H1. www.gnb.ca New Brunswick s Flood Risk Reduction Strategy i New Brunswick s Flood Risk Reduction Strategy Province of New Brunswick PO 6000, Fredericton NB E3B 5H1 2014 www.gnb.ca ISBN 978-1-4605-0533-5 (print edition)

More information

PPG21. Pollution Prevention Guidelines. pollution incident response planning: PPG 21. 1. Introduction

PPG21. Pollution Prevention Guidelines. pollution incident response planning: PPG 21. 1. Introduction PPG21 February 2004 Environmental Alliance working together Pollution Prevention Guidelines pollution incident response planning: PPG 21 These guidance notes have been drawn up to assist those developing

More information

JASPERS Networking Platform

JASPERS Networking Platform JASPERS Networking Platform Promoting climate change adaptation, risk prevention and management in the Water Sector UK Emergency Warning System Rachel Brisley, Technical Director & Sophie Dusting, Analyst

More information

SURFACE WATER MANAGEMENT PLAN

SURFACE WATER MANAGEMENT PLAN SURFACE WATER MANAGEMENT PLAN DRAIN LONDON LONDON BOROUGH OF NEWHAM FINAL DRAFT v2.0 Quality Management Quality Management DOCUMENT INFORMATION Title: Surface Water Management Plan for London Borough of

More information

SURFACE WATER MANAGEMENT PLAN

SURFACE WATER MANAGEMENT PLAN SURFACE WATER MANAGEMENT PLAN DRAIN LONDON LONDON BOROUGH OF WANDSWORTH Quality Management Quality Management DOCUMENT INFORMATION Title: SWMP for the London Borough of Wandsworth Owner: Adam Hutchings

More information

STAFF REPORT TO COMMITTEE OF THE WHOLE

STAFF REPORT TO COMMITTEE OF THE WHOLE STAFF REPORT TO COMMITTEE OF THE WHOLE DATE: November 7 2012 TO: FROM: SUBJECT: ATTACHMENT(S): COMMITTEE OF THE WHOLE GINA LAYTE-LISTON, SUPERVISOR, WASTEWATER Stormwater Management Funding Strategy None

More information

Carterton Drainage Strategy. Stage 1 - Initialise/Prepare

Carterton Drainage Strategy. Stage 1 - Initialise/Prepare Carterton Drainage Strategy Stage 1 - Initialise/Prepare Introduction Why sewer flooding Britain s first sewerage systems were constructed 150 years ago in the Victorian era, and have served us well for

More information

Flood and Coastal Erosion Risk Management Service Delivery Plan

Flood and Coastal Erosion Risk Management Service Delivery Plan Flood and Coastal Erosion Risk Management Service Delivery Plan Document Information Title Flood and coastal erosion risk management Service Delivery Plan Owner Sefton Council Version 1.2 Status Draft

More information

SECTION 3: MAIN CATCHMENTS, COASTAL AREAS & SURFACE WATER MANAGEMENT WITHIN OUTER HEBRIDES LOCAL PLAN DISTRICT

SECTION 3: MAIN CATCHMENTS, COASTAL AREAS & SURFACE WATER MANAGEMENT WITHIN OUTER HEBRIDES LOCAL PLAN DISTRICT SECTION 3: MAIN CATCHMENTS, COASTAL AREAS & SURFACE WATER MANAGEMENT WITHIN OUTER HEBRIDES LOCAL PLAN DISTRICT CHAPTER 4.5: SURFACE WATER FLOODING The purpose of this section is to identify the main surface

More information

PROPERTY RISK MANAGEMENT BUSINESS EMERGENCY, FLOOD PLANNING AND MITIGATION GUIDANCE

PROPERTY RISK MANAGEMENT BUSINESS EMERGENCY, FLOOD PLANNING AND MITIGATION GUIDANCE PROPERTY RISK MANAGEMENT BUSINESS EMERGENCY, FLOOD PLANNING AND MITIGATION GUIDANCE 1 The most common cause of flooding is when the river catchment area receives far greater amounts of water than normal,

More information

Report on. The Pitt Review

Report on. The Pitt Review Report to Cabinet Scrutiny 20 January 2009 Item No 7.2 Report on The Pitt Review Report by Head of Emergency Planning This report looks at the current situation with regard to the recommendations put forward

More information

Littleport Co-located Schools

Littleport Co-located Schools Littleport Co-located Schools February 2015 Morgan Sindall Littleport Co-located Schools 330763 BNI BSE 003 C P:\Cambridge\Murdoch\EST\PROJECTS\330763 Littleport Co-located Schools\12.0 Documents\12.2

More information