1 BASILDON BOROUGH COUNCIL Report to: Audit and Risk Committee 14 November 2012 CORPORATE RISK MANAGEMENT UPDATE Report by: Commissioning Director for Corporate Support Enquiries to: Paula Mills, Manager of Audit & Risk, on Enclosures: None EXECUTIVE SUMMARY: The purpose of this report is to update the Committee on the progress of work undertaken by the Corporate Risk Management Team and the Audit & Risk Committee s Risk Management Working Group. STRATEGIC IMPROVEMENT PLAN AIMS: Value for Money WARD(S): All Wards RECOMMENDATION: 1. That the progress of the Corporate Risk Management Team be noted; 2. That the progress of the Risk Management Working Group be noted; and 3. That the progress of the operational risk management projects and groups be noted. BACKGROUND The Terms of Reference for the Committee include a number of specific responsibilities in relation to risk including to review arrangements for Strategic Risk Management and monitor the key corporate risks. This report is part of a regular series presented to the Audit & Risk Committee to facilitate Members in fulfilling this aspect of their role, in addition to updating Members on the work of the Corporate Risk Management (CRM) Team, the Risk Management Working Group and the progress of operational risk management initiatives.

2 Risk Management Working Group At the meeting of the last Audit & Risk Committee on 26 July 2012 it was agreed that the Working Group would meet on three occasions over the course of the year to examine and bring challenge to a number of key risk areas. The final programme of risk areas to be reviewed was to be agreed at the first meeting, which would also have included a detailed risk management training session in order to prepare Members for the future challenge sessions. It is unfortunate that the two Working Group meetings planned for September and October were cancelled due to unforeseeable circumstances; however, these meetings will be reconvened in December 2012 and January Meanwhile, the CRM Team will continue to monitor the key risks accordingly and bring to the attention of the Working Group any concerns for further scrutiny when the group reconvenes. Due to the change in programme it will no longer be relevant for the Working Group to review the risks associated with the Pantomime, however, the Audit & Risk Committee can be assured that the CRM Team will work closely with the Manager of Leisure Services to manage the risks and opportunities associated with this event. Project & Partnership Risk Management The CRM Team is currently working closely with Regeneration Services to capture the key risks and opportunities associated with the Pitsea Regeneration Project and these will be added to the corporate risk register and monitored throughout the duration of the project. The CRM Team are also supporting the relevant service areas with the successful implementation and delivery of a new Human Resources IT system. This has been a large scale project involving several Council services and the external system provider Midlands. The CRM Team have been involved from the initial stages of the project and continue to provide support to the project board in managing and monitoring project risks and opportunities, this includes working closely with the provider to establish potential risks in relation to the contract and service provision. The Council s recently established Transformation Team is now fully established and as such, the CRM Team is continually liaising with them to embed risk management effectively within the services provided by the Transformation Team. The Manager of the Transformation Team has given assurance that risk management will be an integral part to all areas of the service and as such, the CRM Team is to be consulted on all proposed projects and initiatives. In addition to this the CRM Team will have full access to Verto, the new performance management system specifically procured for transformation related projects. Single Status has progressed significantly over recent months and the CRM Team has been heavily involved in this project from the initiation stages to date and have been monitoring project risks closely and will continue to work closely with the lead project officers to ensure the appropriate management of any new risks or issues that may arise. The CRM Team have recently developed, with the Community Safety Team, a risk profile which details the risks associated with the Council s involvement within the Community Safety Partnership. This risk profile is wide ranging and relates to many Council services.

3 Similarly, an additional risk profile will be developed for the Council s involvement within the Basildon Renaissance Partnership (BRP) and the CRM Team will work closely with the lead BRP officers to identify key risks and opportunities. Benchmarking During 2012/13 the Council again participated in the ALARM/CIPFA Risk Management Survey in order to benchmark the current level of service provided against other Local Authorities. In summary, the current year s results showed that for the majority of areas within risk management, Basildon is embedding and integrating risk management at all levels of the organisation and is above average or working at the same level as other Authorities, specifically in relation to leadership and management, policy and strategy, people, processes and outcomes and delivery. The Council are performing at the highest level and well above average in relation to partnerships, the use of joint risk registers with key partners being a major advantage in this area of risk. Scores were only below average with regard to risk handling and assurance; this may be due to the further work required by the CRM Team in ensuring that managers are confident in using risk management to deliver outcomes in an effective and cost effective manner. A detailed action plan will be completed, based on these results, which will address any areas for improvement, assist in driving the service forward and will also inform the 2013/14 Service Business Plan. Further updates on the action plan and outcomes of this year s survey will be brought to the Committee at future meetings. Covalent Covalent, the Council s corporate performance management system has been in place for a year and to date, has proved to be a very successful tool in managing the Council s corporate performance. Risk management is embedded within the quarterly Corporate Performance Reports which are reviewed at Departmental Management Team (DMT) challenge sessions, whereby Heads of Service and the service managers discuss the top level risks for their service area. Subsequent to these sessions a corporate performance report is produced and presented to the Corporate Management Team (CMT) which details the Council s corporate key risks for review and challenge. It is the intention of the CRM Team to attend future DMT meetings to further embed risk management effectively, whilst challenging Heads of Service and service managers on their key service risks. This will certainly assist in addressing the areas for improvement highlighted in the benchmarking exercise. The Council s Corporate Generic risk profile has been reviewed and updated at a recent Senior Management Team meeting which resulted in some minor amendments to the risk profile. These amendments have been reflected on Covalent and will be presented to the Risk Management Working Group in the New Year. To allow the CRM Team to be more sophisticated in the delivery of the service and to be involved in top level corporate projects, Managers have been encouraged through risk workshops and s to take a proactive role in the management of service risk profiles. In addition, the Manager of Audit & Risk discussed the importance of risk management at an Operational Management Team meeting and issued a briefing paper outlining the role of the CRM Team and reaffirm managers responsibilities in terms of risk management.

4 In general, managers are using Covalent successfully to update risk profiles. However, the CRM still have to encourage and support managers in this regard. Therefore, the CRM Team will continue to provide training and encourage managers to use Covalent more effectively. The recent corporate restructure required substantial changes to Covalent to ensure the risk information recorded on Covalent is reflective of the new structure and that each risk is under the ownership of the correct Head of Service and Service Manager. The CRM Team have completed this exercise and all risk information on Covalent is now recorded under the correct ownerships. Operational Risk Management Projects, Initiatives and Groups It was previously reported to the Committee that the Council has an annual Operational Risk Management budget of 50,000, which is used to fund operational projects that will reduce future risk to the Council. Departments are encouraged to bid for funding for such projects whilst identifying the areas of risk that will be reduced. The scheme is currently funding seventeen different initiatives across the Council relating to the prevention of a wide variety of risks, such as reducing the risk of employees injuring themselves to preventing system errors from occurring. Of these seventeen projects, five have been completed, with the remainder expecting to be completed by the end of the financial year. The Insurance and Corporate Risk Management Teams also facilitate officer working groups and specific operational risk projects; currently they are working closely with relevant departments to address the increase in motor vehicle claims. An initiative in relation to establishing improved inspection regimes for all Council owned land is also being undertaken, which will assist with the prevention of incidents occurring in the future and with the defence of any subsequent insurance claims. Further updates on the progress and outcomes of this work will be brought to the Committee at future meetings. LEGISLATION/POLICY There is an implicit statutory requirement for risk management and this is supported by the CIPFA/SOLACE Guidance on Corporate Governance upon which the Council s Member approved Code of Governance and Risk Management Policy & Strategy are based. GENERAL INFORMATION Financial Implications There are no financial implications arising from this report. The cost of funding operational risk management projects is covered by existing budgets. Risk Management Implications Relevant risks and opportunities in connection with this matter have been considered and are referred to in the body of the report, as appropriate.

5 Inclusion, Diversity and Community Cohesion Implications The Risk Management Policy & Strategy have been subject to a Service Impact Assessment. The concept of Risk Management and the implementation of robust Risk Management procedures serve to assist in the provision of positive outcomes to all sections of the community. Other Relevant Considerations All considerations are covered in the report. Background Papers None

council s Budget and Financial Planning Framework

council s Budget and Financial Planning Framework Basildon District Council Financial Planning Framework 1. Introduction The Financial Planning Framework underpins the Council s Medium Term Financial Strategy and sets out the financial planning processes

More information

Service Delivery Plan 2007/8 Template 1. Delivery plan

Service Delivery Plan 2007/8 Template 1. Delivery plan Delivery plan Theme Leisure & Environment Clean and safe streets and public places with the Council maintaining and enforcing high standards of cleanliness throughout the borough. 1. Deliver a proactive

More information

Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009.

Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009. Report to the Corporate Governance & Audit Committee. Report of the Assistant Director Strategy & Performance to the meeting of Corporate Governance & Audit Committee to be held on 20 March 2009. Subject:

More information

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers

RISK MANAGEMENT POLICY AND STRATEGY. Document Status: Draft. Approved by. Appendix 1. Originator: A Struthers. Updated: A Struthers Appendix 1 RISK MANAGEMENT POLICY AND STRATEGY Document Status: Draft Originator: A Struthers Updated: A Struthers Owner: Executive Director Corporate Services Version: 01.01.03 Date: 30/3/14 Approved

More information

Annual Governance Statement

Annual Governance Statement Annual Governance Statement 2014/15 1 Fareham Borough Council Civic Offices, Civic Way, Fareham PO16 7AZ Scope of Responsibility Fareham Borough Council is responsible for ensuring that its business is

More information

Shepway District Council Risk Management Policy

Shepway District Council Risk Management Policy Shepway District Council Risk Management Policy Contents Section 1 Risk Management Policy... 3 1. Updates and amendments... 3 2. Definition... 3 3. Policy statement... 3 4. Objectives... 3 Section 2 Risk

More information

The Risk Management strategy sets out the framework that the Council has established.

The Risk Management strategy sets out the framework that the Council has established. Derbyshire County Council Management Policy Statement The Authority adopts a proactive approach to Management to achieve Best Value and continuous improvement and is committed to the effective management

More information

Business Plan for Strategic Human Resources - March 2012 to 30 September 2013

Business Plan for Strategic Human Resources - March 2012 to 30 September 2013 Business Plan for Strategic Human Resources - March 2012 to 30 September 2013 1. Introduction 1.1 The Service s key responsibilities are to: 1.2 Context Design & deliver people and organisational development

More information

Review of Financial Planning and Monitoring. City of York Council Audit 2008/09 Date

Review of Financial Planning and Monitoring. City of York Council Audit 2008/09 Date Review of Financial Planning and Monitoring City of York Council Audit 2008/09 Date Contents Introduction and Background 3 Audit approach 4 Main conclusions 5 Financial Planning Findings 6 Financial Monitoring

More information

Area Manager - Head of Operational Policy & Assurance

Area Manager - Head of Operational Policy & Assurance JOB DESCRIPTION Job Title: Fleet Manager Department: Operational Assurance Location: FSHQ Post Number: Grade/Role: PM2 Special Allowances: Essential Car User Responsible to: Area Manager - Head of Operational

More information

MEMBERS CONSIDER THE RISK STRATEGY AND RECOMMEND APPROVAL TO COUNCIL.

MEMBERS CONSIDER THE RISK STRATEGY AND RECOMMEND APPROVAL TO COUNCIL. Agenda item: 8 Committee: Audit & Standards Committee Date of meeting: 19 th September 2011 Subject: Risk Management Strategy Lead Officer: Head of Finance Portfolio Holder: Resources - Councillor T Oliver

More information

SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012

SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012 SCRUTINY COMMITTEE ITEM 04 28 MARCH 2012 INTERNAL AUDIT PLAN Report of the: Director of Finance Contact: John Turnbull or Gillian McTaggart Urgent Decision?(yes/no) No If yes, reason urgent decision required:

More information

Version No: 2 Date: 27 July 2015. Data Quality Policy. Assistant Chief Executive. Planning & Performance. Data Quality Policy

Version No: 2 Date: 27 July 2015. Data Quality Policy. Assistant Chief Executive. Planning & Performance. Data Quality Policy Version No: 2 Date: 27 July 2015 Data Quality Policy Assistant Chief Executive Planning & Performance Data Quality Policy Contents 1. Summary Statement 2. Context 3. Purpose 4. Scope 5. Detail of the policy

More information

NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013

NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 APPENDIX 1 NORTH AYRSHIRE COUNCIL CORPORATE ASSET MANAGEMENT STRATEGY 2013-2023 JANUARY 2013 Page 1 of 10 1. INTRODUCTION It is widely recognised that asset management is a core component of effective

More information

External Performance Assessment Improvement Plan 2006/8 - Monitoring 6

External Performance Assessment Improvement Plan 2006/8 - Monitoring 6 Report title Agenda item External Performance Assessment Improvement Plan 2006/8 - Monitoring 6 Meeting Performance Management & Community Safety Panel 15 September 2008 Date Report by Document Number

More information

DATA QUALITY POLICY PORTFOLIO RESPONSIBILITY: CORPORATE, CUSTOMER SERVICES AND HUMAN RESOURCES CABINET 10 APRIL 2008

DATA QUALITY POLICY PORTFOLIO RESPONSIBILITY: CORPORATE, CUSTOMER SERVICES AND HUMAN RESOURCES CABINET 10 APRIL 2008 DATA QUALITY POLICY PORTFOLIO RESPONSIBILITY: CORPORATE, CUSTOMER SERVICES AND HUMAN RESOURCES CABINET 10 APRIL 2008 Wards Affected County-wide Purpose To approve the data quality policy. Key Decision

More information

Confident in our Future, Risk Management Policy Statement and Strategy

Confident in our Future, Risk Management Policy Statement and Strategy Confident in our Future, Risk Management Policy Statement and Strategy Risk Management Policy Statement Introduction Risk management aims to maximise opportunities and minimise exposure to ensure the residents

More information

HUNTINGDONSHIRE DISTRICT COUNCIL. Internal Audit Service: Annual Report. Meeting/Date: Corporate Governance Panel 15 July 2015

HUNTINGDONSHIRE DISTRICT COUNCIL. Internal Audit Service: Annual Report. Meeting/Date: Corporate Governance Panel 15 July 2015 Public Key Decision - No HUNTINGDONSHIRE DISTRICT COUNCIL Title: Internal Audit Service: Annual Report Meeting/Date: Corporate Governance Panel 15 July 2015 Executive Portfolio: Report by: Ward(s) affected:

More information

Performance Management Framework

Performance Management Framework Performance Management Framework Steve Harman Strategic Performance Manager Performance in a Nutshell BAD GOOD Introduction A Performance Management Framework (PMF) brings together the strategies, plans,

More information

Best Value toolkit: Information management

Best Value toolkit: Information management Best Value toolkit: Information management Prepared by Audit Scotland July 2010 Contents Introduction 2 The Audit of Best Value 2 The Best Value toolkits 4 Using the toolkits 4 Auditors evaluations 5 Best

More information

JOB DESCRIPTION. Performance Management Officer. Performance, Programme and Risk Manager

JOB DESCRIPTION. Performance Management Officer. Performance, Programme and Risk Manager JOB DESCRIPTION POST: SERVICE: SECTION: Performance Management Officer Audit and Governance Performance, Programme and Risk BAND: Band 5 REPORTS TO: RESPONSIBLE FOR: Performance, Programme and Risk Manager

More information

CHESHIRE EAST COUNCIL

CHESHIRE EAST COUNCIL CHESHIRE EAST COUNCIL REPORT TO: Staffing Committee Date of Meeting: 7 January 2010 Report of: Paul Bradshaw, Head of Human Resources & Organisational Development Subject/Title: HR Update Portfolio Holder:

More information

This Report is provided for: Decision Endorsement Assurance Information

This Report is provided for: Decision Endorsement Assurance Information Agenda item 12 Enclosure PAPER G Report to: Author: Presented by: SUBJECT: Trust Board 24 November 2014 John McIlveen, Trust Secretary John McIlveen, Trust Secretary Well-Led Framework for Governance reviews

More information

MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc

MARCH 2012. Strategic Risk Policy Update March 2012 v1.10.doc MARCH 2012 Version 1.10 Strategic Risk Policy Update March 2012 v1.10.doc Document History Current Version Document Name Risk Management Policy Statement and Strategic Framework Last Updated By Alan Till

More information

RISK AND OPPORTUNITY MANAGEMENT STRATEGY 2013-2014

RISK AND OPPORTUNITY MANAGEMENT STRATEGY 2013-2014 RISK AND OPPORTUNITY MANAGEMENT STRATEGY 2013-2014 Version 1.0 October 2013 Not protectively marked INDEX PAGE NO TITLE 3 Executive Summary 4 Our Shared Vision and Priorities 5 Outline of the Risk and

More information

Business Plan for Financial Management and Business Effectiveness Unit - May 2011 to 30 September 2013

Business Plan for Financial Management and Business Effectiveness Unit - May 2011 to 30 September 2013 1 Business Plan for Financial Management and Business Effectiveness Unit - May 2011 to 30 September 2013 1. Introduction 1.1 The Service s key responsibilities are: o The achievement of proper and effective

More information

Technology Review Feedback Vale of Glamorgan Council

Technology Review Feedback Vale of Glamorgan Council Technology Review Feedback Vale of Glamorgan Council Audit year: Annual Improvement Assessment 2011 Issued: October 2011 Document reference: 538A2011 Status of report The person who delivered the work

More information

REPORT 4 FOR DECISION. This report will be considered in public

REPORT 4 FOR DECISION. This report will be considered in public REPORT 4 Subject: Safety Readiness for the Summer 2013 Events Programme Agenda item: Public Item 7 Report No: 4 Meeting date: 28 May 2013 Report to: Board Report of: Mark Camley, Interim Executive Director

More information

Procurement and Contract Management Strategy 2013-2017

Procurement and Contract Management Strategy 2013-2017 Procurement and Contract Management Strategy 2013-2017 Title Owner Version 1 Distribution Procurement and Contract Management Strategy 2013 2017 Procurement and Performance Manager Corporate Issue date

More information

HR Corporate Objectives and Strategy Action Plan January 2013

HR Corporate Objectives and Strategy Action Plan January 2013 Reference Objective / Strategy Action Responsibility Target Date (CO1) By 2016 we will be in the top 20% of Acute Trusts as measured by the NHS National Staff Survey Embed the Trust values into reward

More information

Bedford Group of Drainage Boards

Bedford Group of Drainage Boards Bedford Group of Drainage Boards Risk Management Strategy Risk Management Policy January 2010 1 Contents 1. Purpose, Aims & Objectives 2. Accountabilities, Roles & Reporting Lines 3. Skills & Expertise

More information

Delivery Plan. Service Delivery Plan 2007/08 Template 1. Desired Outcome

Delivery Plan. Service Delivery Plan 2007/08 Template 1. Desired Outcome Delivery Plan Theme 1 Deliver Loughborough Eastern Gateway Project Director Apr 05 Mar 09 Balanced Scorecard Initiative Scheme approved Mar 07 Agreement with Network Rail Dec 06 Final agreement with preferred

More information

Highway Asset Management Strategy

Highway Asset Management Strategy 1. Introduction 1.1. Cheshire East Council (CEC) recognises the importance of its highway infrastructure and how an effectively maintained and managed network contributes to the achievement of its corporate

More information

LONDON BOROUGH OF HARROW. Overview & Scrutiny Committee

LONDON BOROUGH OF HARROW. Overview & Scrutiny Committee LONDON BOROUGH OF HARROW Meeting: Overview & Scrutiny Committee Date: 27 April 2004 Subject: Internal Audit Plan 2004/05 Key Decision: Responsible Chief Officer: No Executive Director, Business Connections

More information

3.1 There are eight grade two and two grade three recommendations contained within the detailed findings section and action plan of this report.

3.1 There are eight grade two and two grade three recommendations contained within the detailed findings section and action plan of this report. Internal Audit Section Appendix B5 Data Quality Audit Review 2009/10 Part One Executive Summary 1. Introduction 1.1 As part of the 2009/10 Internal Audit Plan, a systems based review has been undertaken

More information

iso20000templates.com

iso20000templates.com iso20000templates.com Public IT Limited 2011 IT Service Policy Document Ref. ITSM01001 Version: 1.0 Draft 1 Document Author: Document Owner: V 1.0 Draft 1 Page 1 of 11 Revision History Version Date RFC

More information

Provision of a Corporate Asset Management Software System

Provision of a Corporate Asset Management Software System MERTHYR TYDFIL COUNTY BOROUGH COUNCIL Civic Centre, Castle Street, Merthyr Tydfil, CF47 8AN Main Tel: 01685 725000 To: Chairman, Ladies and Gentlemen CABINET REPORT www.merthyr.gov.uk Date Written 7 th

More information

Best Value toolkit: Performance management

Best Value toolkit: Performance management Best Value toolkit: Performance management Prepared by Audit Scotland July 2010 Contents Introduction The Audit of Best Value The Best Value toolkits Using the toolkits Auditors evaluations Best Value

More information

Department of Health INFORMATION ASSURANCE SUMMARY REPORTS. The purpose and scope of this review

Department of Health INFORMATION ASSURANCE SUMMARY REPORTS. The purpose and scope of this review INFORMATION ASSURANCE SUMMARY REPORTS Department of Health The purpose and scope of this review 1 During the period September to December 2011, the National Audit Office (NAO) carried out an examination

More information

LONDON BOROUGH OF SOUTHWARK

LONDON BOROUGH OF SOUTHWARK APPENDIX 1 LONDON BOROUGH OF SOUTHWARK The annual report to the Audit & Governance Committee on Risk and Insurance for 2011/12, and the key corporate risks Presented to the Audit & Governance Committee

More information

How To Manage A Corporate Council

How To Manage A Corporate Council JOB DESCRIPTION POST: SERVICE: GRADE: Audit and Governance Manager Corporate Governance and Support SE1 MAIN PURPOSE The Governance Manager will form part of the Council s bronze level of management and

More information

Property & Terrier Team Leader. Office based hot desk/touch down worker

Property & Terrier Team Leader. Office based hot desk/touch down worker ROLE PROFILE Role profile Career Grades C, D & E Role Title Property & Terrier Officer (Level 1) Role Grade: GRADE C Role Reference: Reports to: Behavioural Competency Job Type: Work Style Definition Primary

More information

Supplier & Contract Management System (SCMS)

Supplier & Contract Management System (SCMS) Meeting of the Executive Member for Corporate Services and Advisory Panel 30 October 2007 Report of the Assistant Director Audit and Risk Management Supplier & Contract Management System (SCMS) Summary

More information

DATA QUALITY STRATEGY

DATA QUALITY STRATEGY DATA QUALITY STRATEGY If you or anybody you know requires this or any other council information in another language, please contact us and we will do our best to provide this for you. Braille, Audio tape

More information

Report Performance Board

Report Performance Board Report Board Part 1 Date: 29 th March 2016 Item No: Subject Purpose Data Quality Review To advise the Board of the findings from the Wales Audit Office s recent review of the Council s data quality. Author

More information

London Borough of Bromley. Executive & Resources PDS Committee. Disaster Recovery Plans for London Borough of Bromley

London Borough of Bromley. Executive & Resources PDS Committee. Disaster Recovery Plans for London Borough of Bromley Report No. DRR12/041 London Borough of Bromley PART 1 - PUBLIC Decision Maker: Executive & Resources PDS Committee Date: 4 th April 2012 Decision Type: Non-Urgent Non-Executive Non-Key Title: Disaster

More information

CABINET MEMBER DECISION RECORD SECTION 1 BASILDON SPORTING VILLAGE GRANT FUNDING AND MURRAYFIELD PAVILION

CABINET MEMBER DECISION RECORD SECTION 1 BASILDON SPORTING VILLAGE GRANT FUNDING AND MURRAYFIELD PAVILION CABINET MEMBER DECISION RECORD SECTION 1 BASILDON SPORTING VILLAGE GRANT FUNDING AND MURRAYFIELD PAVILION Report to: Report by: Councillor Turner Cabinet Member for Resources Regeneration Services Enquiries

More information

Bridgend County Borough Council. Corporate Risk Management Policy

Bridgend County Borough Council. Corporate Risk Management Policy Bridgend County Borough Council Corporate Risk Management Policy December 2014 Index Section Page No Introduction 3 Definition of risk 3 Aims and objectives 4 Strategy 4 Accountabilities and roles 5 Risk

More information

Bawden Contracting Services Ltd Job Profile. Contracts Manager. Purpose of the Job

Bawden Contracting Services Ltd Job Profile. Contracts Manager. Purpose of the Job Contracts Manager Purpose of the Job As Contracts Manager you will manage all aspects of the Grounds Maintenance contracting business safely and efficiently, maximising profitability through the completion

More information

Data Quality Review Newport City Council. Audit year: 2015-16 Issued: January 2016 Document reference: 703A2015

Data Quality Review Newport City Council. Audit year: 2015-16 Issued: January 2016 Document reference: 703A2015 Data Quality Review Newport City Council Audit year: 2015-16 Issued: January 2016 Document reference: 703A2015 Status of report This document has been prepared as part of work performed in accordance with

More information

Corporate Director Environment & Community Services

Corporate Director Environment & Community Services CABINET Meeting date: 23 July 2015 From: Corporate Director Environment & Community Services DIGITAL STRATEGY 1.0 EXECUTIVE SUMMARY 1.1 This paper presents Cabinet with a draft Digital Strategy for approval.

More information

JOB DESCRIPTION. Facilities Management PARTICIPATING JOB HOLDER(S): APPROVED BY: JOB HOLDERS: HEAD OF DEPARTMENT OR DIRECTOR: Zoological Director

JOB DESCRIPTION. Facilities Management PARTICIPATING JOB HOLDER(S): APPROVED BY: JOB HOLDERS: HEAD OF DEPARTMENT OR DIRECTOR: Zoological Director JOB DESCRIPTION JOB TITLE: SECTION: DIVISION: RESPONSIBLE TO: PARTICIPATING JOB HOLDER(S): Head of FM Facilities Management LONDON ZOO ZOOLOGICAL DIRECTOR VACANT APPROVED BY: JOB HOLDERS: HEAD OF DEPARTMENT

More information

Annual Governance Statement 2013/14

Annual Governance Statement 2013/14 31 Annual Governance Statement 2013/14 1. SCOPE OF RESPONSIBILITY ESPO is responsible for ensuring that its business is conducted in accordance with the law and proper standards, and that public money

More information

Corporate Risk Management Policy

Corporate Risk Management Policy Corporate Risk Management Policy Managing the Risk and Realising the Opportunity www.reading.gov.uk Risk Management is Good Management Page 1 of 19 Contents 1. Our Risk Management Vision 3 2. Introduction

More information

Delivering High Quality Compassionate Care

Delivering High Quality Compassionate Care Strategy 2015-17 Nursing Delivering High Quality Compassionate Care 1 Foreword Lincolnshire Partnership NHS Foundation Trust (LPFT) is the main provider of NHS mental health and wellbeing services in Lincolnshire,

More information

The SDNPA has agreed the following statement as an expression of the values that will govern the behaviour of its staff and Members:

The SDNPA has agreed the following statement as an expression of the values that will govern the behaviour of its staff and Members: Agenda Item 9 Appendix 1 DRAFT LOCAL CODE OF CORPORATE GOVERNANCE Introduction Corporate Governance has been defined 1 as being: how local government bodies ensure that they are doing the right things,

More information

Financial Resilience Assessment Bridgend County Borough Council. Audit year: 2015-16 Issued: March 2016 Document reference: 210A2016

Financial Resilience Assessment Bridgend County Borough Council. Audit year: 2015-16 Issued: March 2016 Document reference: 210A2016 Financial Resilience Assessment Bridgend County Borough Council Audit year: 2015-16 Issued: March 2016 Document reference: 210A2016 Status of report This document has been prepared as part of work performed

More information

People Strategy 2013/17

People Strategy 2013/17 D a t a L a b e l : P U B L I C West Lothian Council People Strategy 2013/17 Contents 1 Overview 2 2 Council Priorities 8 3 Strategy Outcomes 10 1 Engaging and motivating our employees 13 2 Recognised

More information

Waveney Lower Yare & Lothingland Internal Drainage Board Risk Management Strategy and Policy

Waveney Lower Yare & Lothingland Internal Drainage Board Risk Management Strategy and Policy Waveney Lower Yare & Lothingland Internal Drainage Board Risk Management Strategy and Policy Page: 1 Contents 1. Purpose, Aims & Objectives 2. Accountabilities, Roles & Reporting Lines 3. Skills & Expertise

More information

www.blackburn.gov.uk

www.blackburn.gov.uk Blackburn with Darwen Borough Council Data Quality Policy (Performance Data) Prepared by: The Policy and Performance Team (01254 585245) Revised: December 2012 Version: 1.0 Prepared by: Policy and Performance

More information

LEICESTERSHIRE COUNTY COUNCIL RISK MANAGEMENT POLICY STATEMENT 2011-2012

LEICESTERSHIRE COUNTY COUNCIL RISK MANAGEMENT POLICY STATEMENT 2011-2012 106 LEICESTERSHIRE COUNTY COUNCIL RISK MANAGEMENT POLICY STATEMENT 2011-2012 Leicestershire County Council believes that managing current and future risk, both opportunity and threat, is increasingly vital

More information

Aberdeen City Council. Performance Management Process. External Audit Report o: 2008/19

Aberdeen City Council. Performance Management Process. External Audit Report o: 2008/19 Aberdeen City Council Performance Management Process External Audit Report o: 2008/19 Draft Issued: 11 February 2009 Final Issued: 6 April 2009 Contents Pages Pages Management Summary Introduction 1 Background

More information

PERFORMANCE DATA QUALITY POLICY

PERFORMANCE DATA QUALITY POLICY PERFORMANCE DATA QUALITY POLICY 2007 / 08 Improvement Service May 10 th 2007 Data Quality Policy V7 10.05.07 1 INTRODUCTION / BACKGROUND Good quality performance data is accurate, valid, reliable, timely,

More information

Hertsmere Borough Council. Data Quality Strategy. December 2009 1

Hertsmere Borough Council. Data Quality Strategy. December 2009 1 Hertsmere Borough Council Data Quality Strategy December 2009 1 INTRODUCTION Public services need reliable, accurate and timely information with which to manage services, inform users and account for performance.

More information

HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK

HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK HARLOW COUNCIL PERFORMANCE MANAGEMENT FRAMEWORK July 2013 1 P age Contents Page 1.0 Definition 3 2.0 Context 3 3.0 Purpose and aim of the policy 4 4.0 Policy Statement 4 5.0 Framework for Performance Management

More information

Integrated Strategic Planning Process Service, Financial and Improvement Planning

Integrated Strategic Planning Process Service, Financial and Improvement Planning 7 Shropshire and Wrekin Fire Authority Strategy and Resources Committee 2 October 2007 Integrated Strategic Planning Process Service, Financial and Improvement Planning Report of the Chief Fire Officer

More information

Business Continuity Management Policy

Business Continuity Management Policy Governance: Business Committee Policy Owner: Chief Superintendent, Corporate Services Department: Corporate Services Policy Number: 002 Version: 3.0 Policy Writer: Business Continuity Co-ordinator Effective

More information

Homes and Environment Scrutiny Committee. (Environment & Transport)

Homes and Environment Scrutiny Committee. (Environment & Transport) REPORT TO: REPORT NO: Homes and Environment Scrutiny Committee HHPPE/89/15S DATE: 9 September 2015 LEAD MEMBER: Councillor David A Bithell (Environment & Transport) CONTACT OFFICER: Neil Taunt (Tel: 729734)

More information

Richmond-upon-Thames Performance Management Framework

Richmond-upon-Thames Performance Management Framework Richmond-upon-Thames Performance Management Framework Introduction Everyone at the Council has a role in Performance Management. It is therefore important that we all understand what is involved. This

More information

Charnwood Borough Council. Corporate Performance Management Framework

Charnwood Borough Council. Corporate Performance Management Framework Charnwood Borough Council Corporate Performance Management Framework Contents 1 Introduction... 1 2 Background... 1 3 Role of the Performance Team... 2 4 Charnwood Framework... 2 4.1 Corporate Plan...2

More information

Trust Board 8 May 2014

Trust Board 8 May 2014 Trust Board 8 May 2014 Title of the Paper: Quarter 4 (1 st January 2014 31 st March 2014) CLIPS Report Agenda item: 205/17 Author: Jackie Ardley, Interim Chief Nurse Trust Objective: 1) Achieving continuous

More information

Data Quality Policy. Appendix A. 1. Why do we need a Data Quality Policy?... 2. 2 Scope of this Policy... 2. 3 Principles of data quality...

Data Quality Policy. Appendix A. 1. Why do we need a Data Quality Policy?... 2. 2 Scope of this Policy... 2. 3 Principles of data quality... Data Quality Policy Appendix A Updated August 2011 Contents 1. Why do we need a Data Quality Policy?... 2 2 Scope of this Policy... 2 3 Principles of data quality... 3 4 Applying the policy... 4 5. Roles

More information

Committees Date: Subject: Public Report of: For Information Summary

Committees Date: Subject: Public Report of: For Information Summary Committees Audit & Risk Management Committee Finance Committee Subject: Cyber Security Risks Report of: Chamberlain Date: 17 September 2015 22 September 2015 Public For Information Summary Cyber security

More information

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 PAGE: 1 REPORT TO: SUBJECT: BY: AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 ASSET MANAGEMENT CHIEF FINANCIAL OFFICER 1. REASON FOR REPORT 1.1 To provide the Audit and Performance Review

More information

APPENDIX A. Integrated Performance Management Framework 2009/10 2012/13

APPENDIX A. Integrated Performance Management Framework 2009/10 2012/13 APPENDIX A Integrated Performance Management Framework 2009/10 2012/13 Table of Contents INTRODUCTION 3 SECTION 1: DELIVERY PLANNING 4 Diagram 1: Links between key strategies 4 Diagram 2: Planning cycle

More information

RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION

RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION RCT HOMES HOUSING ASSOCIATION JOB DESCRIPTION TITLE: REPORTING TO: RESPONSIBLE FOR: Financial Accountant Group Accountant Assistant Accountant 1. Overall Objectives 1.1. To provide the Financial Accounting

More information

WILTSHIRE POLICE FORCE POLICY

WILTSHIRE POLICE FORCE POLICY Template v4 WILTSHIRE POLICE FORCE POLICY BUSINESS CONTINUITY MANAGEMENT SYSTEMS (BCMS) Effective from: July 2013 Version: 2.0 Next Review Date: July 2015 POLICY STATEMENT Wiltshire Police has a statutory

More information

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT ARGYLL AND BUTE COUNCIL EXECUTIVE SUPPORT SERVICES REVIEW 15 DECEMBER 2011 SUMMARY REPORT 1.0 SUMMARY 1.1 The service reviews for Customer and Support Services, Improvement and HR and Strategic Finance

More information

Basildon Council - Motor Vehicle Claim Form

Basildon Council - Motor Vehicle Claim Form Basildon Council - Motor Vehicle Claim Form Please ensure you read the following information before completing this claims form and that you complete this form thoroughly, failure to complete the form

More information

Jenny Obee, Head of Information Management jenny.obee@barnet.gov.uk, Tel: 020 8359 4859. Micailah Fleming, IT Director micailah.fleming@capita.co.

Jenny Obee, Head of Information Management jenny.obee@barnet.gov.uk, Tel: 020 8359 4859. Micailah Fleming, IT Director micailah.fleming@capita.co. Performance and Contract Management Committee 7 January 2016 Title Report of Wards Status ICT Operations ITIL Methodology Assessment Chief Operating Officer All Public Urgent Key No No Enclosures None

More information

APPENDIX 50. Enterprise risk management - Risk management overview

APPENDIX 50. Enterprise risk management - Risk management overview APPENDIX 50 Enterprise risk management - Risk management overview Energex regulatory proposal October 2014 ENTERPRISE RISK MANAGEMENT Risk Management Overview (RMO) 06 11 2013 Table of Contents 1. INTRODUCTION...

More information

Performance Detailed Report. Date. Last saved: 12/10/2007 13:18:00. Property asset management. Bristol City Council. Audit 2006/07

Performance Detailed Report. Date. Last saved: 12/10/2007 13:18:00. Property asset management. Bristol City Council. Audit 2006/07 Performance Detailed Report Date Last saved: 12/10/2007 13:18:00 Property asset management Audit 2006/07 - Audit Commission descriptor to be inserted by Publishing- Document Control Author Filename Bob

More information

DATA QUALITY POLICY April 2010 Updated January 2015 1

DATA QUALITY POLICY April 2010 Updated January 2015 1 DATA QUALITY POLICY April 2010 Updated January 2015 1 Contents page 1. Introduction 3 2. Context and Purpose 3 3. Why is data quality important? 4 4. Characteristics of good quality data 5 5. Policy Objectives

More information

Appendix 2e. DIRECTORATE OF AUDIT, FF RISK AND ASSURANCE Internal Audit Service to the GLA. Follow up Review of Sickness Monitoring and Control

Appendix 2e. DIRECTORATE OF AUDIT, FF RISK AND ASSURANCE Internal Audit Service to the GLA. Follow up Review of Sickness Monitoring and Control Appendix 2e DIRECTORATE OF AUDIT, FF RISK AND ASSURANCE Internal Audit Service to the GLA Follow up Review of Sickness Monitoring and Control EXECUTIVE SUMMARY 1. Background 1.1 This audit follows up the

More information

Equality Impact Assessment (EIA) Highways Asset Management Plan

Equality Impact Assessment (EIA) Highways Asset Management Plan Equality Impact Assessment (EIA) Highways Asset Management Plan Equality impact, needs and requirements assessment form Please use this form to record your findings, proposed actions, equality objectives

More information

HISTORIC SCOTLAND BOARD MEETING 25-27 JUNE: ORKNEY HSB 10/06 HEALTH AND SAFETY ANNUAL REPORT FOR 2005 2006

HISTORIC SCOTLAND BOARD MEETING 25-27 JUNE: ORKNEY HSB 10/06 HEALTH AND SAFETY ANNUAL REPORT FOR 2005 2006 HEALTH AND SAFETY ANNUAL REPORT FOR 2005 2006 1 INTRODUCTION 1.1 Managing corporate risks is a key issue for all organisations. One key risk is the health and safety of our staff and others such as visitors

More information

Framework: Supporting transformation of government financial

Framework: Supporting transformation of government financial Performance Improvement Framework: Supporting transformation of government financial management services: Background DECK for workshop attendees State Services Commission, Room 10.3, No 2 The Terrace,

More information

AUDIT COMMITTEE 25 JUNE 2015

AUDIT COMMITTEE 25 JUNE 2015 AUDIT COMMITTEE 25 JUNE 2015 AGENDA ITEM 13 Subject: ANNUAL INTERNAL AUDIT REPORT 2014/15 Report by: AUDIT AND INVESTIGATIONS MANAGER Enquiries contact: Ray Joy (01245 606424) Email ray.joy@chelmsford.gov.uk

More information

Subject: Resource & Governance Business Plan 2014/15

Subject: Resource & Governance Business Plan 2014/15 CLACKMANNANSHIRE COUNCIL Report to Resource & Audit Committee THIS PAPER RELATES TO ITEM 10 ON THE AGENDA Date of Meeting: 19 June 2014 Subject: Resource & Governance Business Plan 2014/15 Report by: Senior

More information

Corporate Services Business Plan 20015/16- Day to Day Tasks. Corporate Services, Performance Management. Signed off: G Walsh 19.05.

Corporate Services Business Plan 20015/16- Day to Day Tasks. Corporate Services, Performance Management. Signed off: G Walsh 19.05. Corporate Services Business Plan 20015/16- Day to Day Tasks Directorate: Officer: Corporate Services, Performance Management Gary Walsh, Deputy Chief Fire Officer Signed off: G Walsh 19.05.2015 The purpose

More information

Technical Journal. Paper 142

Technical Journal. Paper 142 Technical Journal 09 Paper 142 142 Kevin Balaam Programme Manager Highways & Transportation Atkins The Area 6 MAC approach to planning and programme management Introduction Steve Dickinson Schemes Manager

More information

Hammersmith & Fulham Borough of Opportunity. Executive Support Officer. Community Services. Application Pack

Hammersmith & Fulham Borough of Opportunity. Executive Support Officer. Community Services. Application Pack Hammersmith & Fulham Borough of Opportunity Executive Support Officer Community Services Application Pack Job Description Designation: Executive Support Officer Post Number: P07286 Department: Community

More information

Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information

Royal Borough of Kensington and Chelsea. Data Quality Framework. ACE: A Framework for better quality data and performance information Royal Borough of Kensington and Chelsea Data Quality Framework ACE: A Framework for better quality data and performance information March 2010 CONTENTS FOREWORD 2 A CORPORATE FRAMEWORK FOR DATA QUALITY

More information

Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement

Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Recommendations That the Executive note CRM procurement will be put out to tender in 2010/11 and note the proposed phasing

More information

NHS Heywood, Middleton and Rochdale Community Health Care

NHS Heywood, Middleton and Rochdale Community Health Care NHS Heywood, Middleton and Rochdale Community Health Care Quality Account 2010-2011 Page 1 of 11 Contents Page Part 1 1.0 Statement from the Managing Director 3 Part 2 2.0 Priorities for Improvement and

More information

Corporate Parenting Advisory Panel Thursday 17 September 2015

Corporate Parenting Advisory Panel Thursday 17 September 2015 Corporate Parenting Advisory Panel Thursday 17 September 2015 Title Individual Savings Accounts - Corporate Parenting Advisory Panel 17/09/15 Report of Linda Burbidge, Finance Manager Wards All Status

More information

JOB DESCRIPTION. Programme & Project Assurance Officer. Performance, Programme and Risk Manager

JOB DESCRIPTION. Programme & Project Assurance Officer. Performance, Programme and Risk Manager JOB DESCRIPION POS: SERVICE: SECION: Programme & Project Assurance Officer Audit and Governance Performance, Programme and Risk Service BAND: Band 7 REPORS O: RESPONSIBLE FOR: Performance, Programme and

More information

Project Appraisal and Scrutiny Committee Recommendation. E-mail, file storage system and server upgrades

Project Appraisal and Scrutiny Committee Recommendation. E-mail, file storage system and server upgrades Cambridge City Council To: Report by: Scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources James Nightingale, Head of ICT Client Services Strategy and Resources

More information

Health and safety policy

Health and safety policy 1. General statement of intent The Company recognises and accepts its responsibilities as an employer to ensure, so far as is reasonably practicable, the health, safety and welfare of its employees and

More information

RISK & INSURANCE ANNUAL REPORT 2015

RISK & INSURANCE ANNUAL REPORT 2015 Committee and Date Item Audit Committee 17 th September 2015 RISK & INSURANCE ANNUAL REPORT 2015 Responsible Officer Angela Beechey e-mail: Angela.beechey@shropshire.gov.uk Tel: (01743) 252073 Fax (01743)

More information