Commissioning Fundamentals and a Practical Approach

Size: px
Start display at page:

Download "Commissioning Fundamentals and a Practical Approach"

Transcription

1 PDHonline Course P146 (2 PDH) Commissioning Fundamentals and a Practical Approach Instructor: Timothy D. Blackburn, MBA, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA Phone & Fax: An Approved Continuing Education Provider

2 Commissioning Fundamentals and a Practical Approach Timothy D. Blackburn, MBA, PE Introduction Have you ever had something not to work but only discovered long after start-up? Do you have an uneasy feeling that something might not be installed correctly, but don t know how to verify? Then try commissioning. Actually, Commissioning is nothing new. What good engineer would not confirm an installation works? But if commissioning is documented poorly, it is inadequate. If it is done improperly, it is inadequate. Projects routinely have problems. One part of the solution to minimizing project problems is to have a robust and documented Commissioning process (assuming the design is robust in the first place). However, we can go to far and judge success by the weight of the paper generated. How can Commissioning be implemented meaningfully in the real world? This course will attempt to answer this question. The Author has been a leader in the Pharmaceutical industry in the application of documented Commissioning to minimize the regulated paperwork required for Validation/Qualification. He shares his learned experience in this course in the practical application of commissioning, whether in a regulated industry or not. This course is to a general audience see separate material for specific applications to the Pharmaceutical industry. Course Content Why Commission? Commissioning is necessary to ensure facilities, equipment, and systems are installed and function properly, and are successfully turned over. A documented Commissioning approach offers traceable verification, and ensures a systematic approach that minimizes commissioning oversights. Effective Commissioning minimizes punchlist items, and improves startup by eliminating problems up-front. Further, certain Commissioning activities may be used to support documentation requirements for regulated industries. Commissioning Defined Commissioning is a well planned, documented, and managed engineering approach to the start-up and turnover of facilities, systems, and equipment to the End-User that results in a safe and functional environment that meets established design requirements and stakeholder expectations. i That is, Commissioning verifies what was specified was installed, that it functions properly, and it was successfully turned over to the user and reasonably ensures the next step verification for regulated industries will be successful. Given this definition, engineers have always commissioned projects to a degree. For example, when a new pump is installed, the proper rotation and flow rate is verified. Before it is installed, the model number and materials of construction are confirmed. Another example is an HVAC system. The airhandler is confirmed to be leveled and adjusted. The controls are tested. At the end, a test and balance contractor adjusts circuit setters for proper water flowrates, and to Page 1 of 13

3 adjust dampers for proper airflow. At the end of a project, the operators and maintenance staff are trained. To have a record of what was installed, as-built drawings and Operations and Maintenance manuals are developed. This is commissioning. All these activities can be summarized in distinct Commissioning categories: Pre-Commissioning activities, Setting-to-Work, Inspections, Testing, and Turnover. (Note: Setting to Work is a potential fourth category, but may be included under Inspection or Testing as needed.) Pre-Commissioning Pre-commissioning activities are Site Acceptance Tests (SAT) and Factory Acceptance Tests (FAT) as well as other similar activities. FAT s are useful in protecting the business aspect of an investment, by testing the equipment or system at the factory. This allows the system to be tested and deficiencies corrected in a manufacturing environment before it arrives on-site with surprises. The SAT verifies proper equipment and operation on-site. For many projects, especially those with single equipment systems, the SAT may constitute the majority if not all the Commissioning inspection and testing requirements. Further, SAT s (and FAT s with caution) may include elements sufficient for aspects of a regulated activity verification. If a FAT is provided, the SAT could be a reduced regimen. However, be careful in that changes made after the FAT in the factory (outside a controlled setting) could affect acceptable outcomes. The following are typical elements of FAT s/sat s, as applicable: Confirm fundamental scope definitions (or Acceptance Criteria) and Specifications Functionality operate equipment/systems during test Alarms and safeties PLC/Controls thorough checkout/challenge Utilities Maintenance needs Calibration Labeling Training and turnover Setting-to-Work Setting-to-work and other regulation and adjustments are needed prior to energizing the system or full startup. This could include factory representative start-up, calibration, and other considerations needed before fully operating the equipment and beginning other aspects of Commissioning. Inspection Inspection is the process by which the construction and installation is verified as in accordance with the detailed design, specified construction standards and materials and any relevant legal or regulatory demands related to these areas. ii From the examples above, confirm the pump model number and verifying the airhandler was properly leveled are Inspection activities. Inspection activities generally do not include testing, and often are better handled on forms separate from testing. (There are exceptions when for succinctness or clarity Inspection items are included with Tests.) Inspections are usually visual confirmations. The questions to ask when developing an Inspection checklist are, What needs observing to ensure the equipment is properly installed? Page 2 of 13

4 What needs inspecting to ensure project definition requirements, Acceptance Criteria and other regulatory issues are met? What inspections are needed to reasonably ensure any subsequent regulated verification will pass? How will Inspection activities be structured/documented so repetition during any regulated verification is not required? When these basic questions are answered, commonsense will prevail. There is no need to create volumes of documents of marginal value. Yet, documentation must be adequately thorough. The key is to be specific with Inspection line items to ensure documentation is traceable. Testing Testing is the process by which adjustments to, and regulation of, individual systems are demonstrated as within the required tolerances, system components are demonstrated as delivering the required capacity or duty, the functions of the systems are demonstrated as delivering the required capacity of duty, the functions of the system are demonstrated to be as specified and appropriate. iii Referring again to the commissioning examples earlier in the article, checking the pump s flow rate and performing test & balance on the HVAC system are all testing activities. Essentially, testing is needed on what was installed to ensure the equipment or system operates as specified and required. The questions to ask when determining test requirements are, What level of testing is needed to ensure the equipment is properly functioning as specified? What tests are needed to ensure fundamental design requirements, Acceptance Criteria, and other regulatory issues are met? What testing is needed to ensure (within reason) any required regulatory verification will pass? How can the testing be documented/structured so it will not need to be repeated during any regulated verification? As with Inspection, when the basic questions are answered, commonsense will prevail. There is no need to create volumes of useless test documents when the documentation is adequately thorough. As with Inspection, a documented paper trail is recommended to demonstrate (and document) that equipment and systems are adequately tested. The project is not fully commissioned until Turnover is also completed. Training, Project Closeout (documentation), and Commissioning Documentation are parts of a successful project turnover as follows: Training Unless staff are properly trained, they will be unable to safely and efficiently operate and maintain the facility, equipment, or system. The commonsense questions to ask before determining training requirements are: 1. On which equipment/systems is training required? 2. Who needs to be trained? 3. What training do they need? (Not everyone needs the same training). 4. How must training be recorded? 5. What are the required qualifications of the trainer? Page 3 of 13

5 Project Closeout, Documentation A project is not complete until all associated documentation is completed and turned over to appropriate individuals. This includes as-built drawings and specifications, Operations and Maintenance Manuals, etc. Commissioning Documentation Good commissioning is well documented commissioning. Commissioning documentation could be included in a Commissioning Report for more complex projects. For more complex projects, a formal Commissioning Plan is helpful to define the commissioning process. But before we discuss the elements for a higher documented Commissioning process, let s ensure we InVEST wisely in Commissioning. InVEST Wisely in Commissioning When establishing Commissioning requirements, it is important to remain focused on commonsense objectives to make the effort meaningful and cost effective. The acrostic InVEST is helpful in establishing the focus: Integrate: Integrate Commissioning with any other documentation required for a regulated industry if permitted. Don t automatically do things twice. Integrate also means to include commissioning activities in various vendors /subcontractors scope of work, as well as design documents. Verify: Ask: does the Commissioning activity adequately verify the equipment or system is what was specified and works as it should? Ensure Regulated Documentation Success: Ask: does the commissioning effort sufficiently ensure any regulated testing or inspection activities will be successful first time? Sensible: Do enough but don t over do it Traceable: Document it. Remember the saying, If you don t document it, you didn t do it. Establishing Commissioning and Documentation Requirements Before developing Commissioning Documentation, establish the extent of Commissioning needed, and design efficient and effective Commissioning around the needs of the project (hopefully as expressed in well-written and thorough project definition documentation. Typical Commissioning Documents may include the following, depending on project complexity. Overall Commissioning Plan for large and more complex projects, especially those in regulated environments this is a masterplan for Commissioning when the approach needs preplanning and structure. On smaller projects/single equipment, consider relying on Standard Operating Procedure (SOP) requirements rather than a separate overall Plan. Pre Commissioning: Includes Factory Acceptance Test (FAT), Site Acceptance Test (SAT), and possibly other early inspection/test activities. These are usually structured for individual systems, and can be included in or required by Commissioning Plan or Test Plans. These could be stand alone for individual equipment/systems, and/or include essential elements of the Commissioning Test/Inspection Plans Page 4 of 13

6 Commissioning Test and Inspection Plans: These could be stand alone for individual equipment/systems. These may also supplement areas not covered by FAT s/sat s. Further, self-contained Commissioning Checklists can be used for simple/small work. Don t create unnecessary volumes of documentation. Commissioning Checklists: For smaller/simpler projects, consider a single Commissioning Checklist in lieu of more extensive documentation above. These overall checklists may include the following: o Verify item specified was installed o Utility connection o Functionality checkout o Verify calibration completed o Verify closeout documentation completed o Verify training or orientation completed o CMMS (Computerized Maintenance Management System) entry o Other internal requirements Note: When sufficient Commissioning direction is provided in specifications or in drawings and for non-regulated applications, at a minimum consider developing a detailed checklist to ensure commissioning is completed, and documentation is turned over. This is especially useful in nonregulated applications where a high-level of documentation is not required. The following is a hierarchy diagram of typical commissioning documentation: Page 5 of 13

7 Commissioning Plan Commissioning Plan may include: -Basic scope of work -Record Keeping requirements -Signatory requirements -Reference any defined scope narratives and acceptance criteria -Equipment/System List/ Boundaries and Impact Assessment -Training Verification -Turnover Requirements -Change Management approach Pre Commissioning Activities (in or directed by Com. Plan) FAT SAT Other Commissioning Test Plans (in or directed by Com. Plan) Setting to Work, Initial Adjustments Inspections Testing Now that we ve reviewed the typical Commissioning documentation, we need to consider values to which we will Commission. When we perform Commissioning, we need to evaluate equipment and systems to specific quantifiable criteria. SMART Commissioning Acceptance Criteria/Ranges Another helpful acrostic is SMART, which should be considered when assigning values for Commissioning verification. Often, limits can be set that are not attainable by the installed equipment, nor are needed for the operation. The acrostic SMART as follows can assist us in making meaningful acceptance criteria: Sensible: Be practical when assigning commissioning acceptance ranges. Is the range really needed? What does the project really require? Can the equipment deliver this range consistently? Do the ranges also meet business/payback objectives? Energy efficiency? Maintainable: Will the range be maintained over time? Accurate: Is the range measurable? Are realistic tolerances considered? Can equipment consistently meet this target? Range: Is a reasonable range assigned? Rarely can point values be maintained. Design values must be well within commissioned ranges to minimize nuisance alarms. Traceable: Has/can the attainment of the range be verified and documented? Can it be verified later? Page 6 of 13

8 The International Society of Pharmaceutical Engineers (ISPE) Baseline Guides present Design, Normal Operating, and Operating Ranges. Design is the value to which the equipment or system is designed (see references). Normal Operating is the range, wider than Design, at which a pre-alert could occur for maintenance notification this could be the Commissioned range (or the Commissioning range could be tighter if needed.) Even wider is the Operating range useful for in regulated industries (the range in which safety is maintained or product tolerances are controlled.) It is crucial to have a less stringent Operating range than the Normal Operating range, both of which should be less stringent than the design range or value. For example, the desired Operating range of a filler may be 300 vials or bottles per minute, the Commissioned (Normal Operating) might be 320, and the Design 340. If the Operating range was set at the design value or range, occasional failures would likely occur. (For this example, don t forget to also check at the lower speed during Commissioning some equipment may not operate properly at slow speeds.) Buffers should be provided in these ranges. Remember, once Operating ranges are assigned, there could be a Quality intervention required when there are excursions obviously, this should be avoided. Ideally, acceptance criteria should be determined early, and be a part of the primary scope definition document against which final Commissioning documents are drafted. (Note: For some examples, the chart could be inverted.) So far, we have reviewed practical approaches to Commissioning, as well as its definition. The following section offers a few practical examples of how Commissioning might be applied. (Obviously, you will need to craft approaches specific to your applications.) Page 7 of 13

9 Specific Examples How do we Commissioning those typical systems? Obviously, any application could differ, requiring more or less of the listed considerations. But the following reflect practical experience of the Instructor. Given the complexity of the various systems or with some combinations of systems, overall Commissioning Plans should also be considered where needed. Computer/Controls Items to consider o Hardware/Software verification and testing o Security o Part 11 issues (for certain FDA regulated applications which includes such considerations as traceability, electronic signatures, security, etc.) o Functionality/challenge o Alarms o Trends o Data verification and integrity o Human interface/graphics o Backup o Input/output verification Include verification of items being controlled - somewhere! Commissioning vehicle: Most commissioning activities (inspections/tests) can be captured in FAT/SAT Packaging/Fill Equipment Items to consider o Verify specified equipment installed o Utility connections o Instrumentation/calibration o Controls interface o Proper installation/alignment o Materials of fabrication o Safeties/ergonomics o Additional for sterile o Run product! Line Speeds Labeling Tolerances Proper Product Encapsulation Finish Form Acceptance Criteria Cartoning Commissioning vehicle: o Most commissioning activities (inspections/tests) may be captured in FAT/SAT o Supplement with Commissioning Test Plans Process/Manufacturing Items to consider Page 8 of 13

10 o Verify specified equipment installed o Utility connections o Proper installation/alignment o Materials of fabrication, passivation o Operating parameters (flow rates, mixing, heating, cooling, vacuum, reactions) o Adjustments, balancing, tests (pressure, etc.) o Instrumentation/calibration o Safeties/ergonomics o Acceptable product Commissioning vehicle: Commissioning Plan, Commissioning Test Plans, and FAT/SAT on individual major equipment when needed. If the project essentially consists of a single equipment, FAT/SAT could satisfy most of (if not all) the Commissioning Test/Inspection activities. HVAC Items to consider o Temperature o Relative Humidity o Particle Counts o Differential Pressure o Air Change Rate o Laminar flow issues o Room Classifications Commissioning vehicles o Pre-Commissioning Activities (FAT/SAT): Airhandler (AHU) and Building Management System (BMS) o Major equipment factory start-up (Setting-to-work, etc.) o Commissioning Test Plan!"Sequence of Operation Challenge!"Standard Tests and Inspections (such as IO verification, Calibrations, etc.)!"test and balance!"hepa Filter certifications!"trends!"viable/non-viable counts!"inspection activities Purified Water Items to consider o TOC s o Conductivity o Production rates o Micro o Other Commissioning vehicles o FAT/SAT of equipment o Commissioning Test Plan:!"Challenge installed system to meet acceptance criteria, alarms, safeties, automatic operation, etc. Page 9 of 13

11 !"SCADA/PLC checkout!"trends!"inspection activities Compressed Air Items to consider o Viable and non-viable particle counts o Moisture (dew point) o Flow rate/pressure o Oil free?!" Commissioning vehicles o Pre-commissioning: SAT s of major equipment o Commissioning Test Plan!" Challenge installed system to meet acceptance criteria, alarms, safeties, automatic operation, etc.!" Trends!" Inspection activities Implementing Commissioning The first step in implementation is to draft a robust Commissioning Plan or have a predefined approach. For Commissioning to be successful, and more importantly, meaningful, the process must be properly defined. Start by assigning a single responsible individual, a Commissioning Team Leader. Establish a multidiscipline team to be a part of the commissioning documentation approval and development. But the Commissioning Team Leader (CTL) cannot do it by himself or herself. Even if time were not an issue, no one can have the technical expertise in all areas to develop meaningful tests and procedures. Much of the administrative aspects can be typical or require only minor modifications, and other templates/formats are useful. Including the development of Inspection Checklists and testing requirements in Architectural/Engineering consultant s or equipment integrator s scope of work can be effective financially and technically. The design engineers of record are most qualified to know what needs to be Inspected and Tested. However, the engineers of record must be familiarized on basic procedures as to how to develop proper formats for the specific Client, which can be accomplished by examples and written procedures. Much of the test requirements are routinely identified as part of the project specifications, which must be referenced or included in the Commissioning Plan or confirmed as part of a verification checklist. Writing the entire Commissioning documentation can be accomplished completely by outside consultants, but they must be adequately trained on the Owner s procedures. Complete outsource plan writing can be less effective than having an internal CTL at the Owner to at least develop the backbone of the document and coordinate/insert outsourced Inspections and Tests forms and requirements. Once the Commissioning documentation is written, who will do the Inspections and Tests? Again, the CTL cannot do all inspecting and testing (nor will be qualified to do so) by himself/herself. Assistance is needed. For Inspections, Construction Managers or integrators can provide cost effective support in this area. They often appreciate the opportunity to have Inspection checklists upfront, since it minimizes punch list items later. This approach usually adds minimal additional cost to the project. Most testing is typically performed by traditional testing agencies, such as geotechnical consultants, test and balancers, particulate monitoring companies, etc. as Page 10 of 13

12 routinely defined in a project s specifications. However, specialized tests often require extra assistance/guidance. A good example is a computerized system; it is often best to require the design engineer of record to write and witness the sequence challenge test. He or she best understands the acceptable outputs of the system and the logic needed. Commissioning for each project must be tailored to its needs, considering internal resource constraints. Another alternative (and usually more costly) is to outsource the complete commissioning implementation to a commissioning consultant. However, as with all outsourcing, careful scrutiny by qualified internal resources is needed to ensure Owner-specific requirements are met. Below is a graphic of an example of an efficient Commissioning Process that has worked well for building projects (there are others) which relies on the Engineering Consultant and Construction Manager (CM) to perform much of the Commissioning activities, while maintaining a CTL to coordinate the process (this example has a dedicated Commissioning Team Leader (CTL) who develops the Commissioning Plan and directs the Commissioning process, relies on the Engineering Consultant to produce Inspection and Testing requirements, and acquires Commissioning execution through the Contractor/Construction Manager. The approach is essentially a 5-stage process. 1. The consultant develops essential inspection and testing requirements for the CTL. 2. The CTL assembles the above and supplements as needed, completing other commissioning documents such as a Commissioning Plan if required. 3. Testing vendors provide standard test results to the CM. 4. The CM completes other Commissioning requirements, assembles 3 and 4, and forwards to the CTL. Outsourced Commissioning activities are under the direction of the CTL. 5. The CTL reviews, approves, and assembles the materials into a Commissioning Report. Page 11 of 13

13 Timing of Commissioning Sufficient scope detail should be included in Requests for Proposals/Quotes (RFP/Q s) to enable consultants and contractors to include scope and pricing in their quotations. At a minimum, a draft of the Commissioning Plan should be issued with bid documents. The cost of specialized tests or inspections will be less if captured under a competitively bid environment. A Commissioning Plan or other suitable documented commissioning directives should be approved by the Commissioning Team Members and issued prior to construction beginning. The implementation of Commissioning should begin concurrently with construction. There will be items on the Inspection Checklists and Test requirements that will be concealed by construction and cannot be viewed later. Course Summary Page 12 of 13

14 Commissioning is a worthwhile exercise. It minimizes punch lists and provides higher assurance of project success. Commissioning is an important exercise to ensure what we installed is what we specified, and it works as specified. However, commonsense should prevail. Do no more or no less than is needed, and your project will benefit. Remember to InVEST wisely (Integrate Commissioning with Qualification, Verify, Ensure Qualification Success, Sensible, Traceable/Document it) and set SMART Acceptance Criteria in the beginning (Sensible, Maintainable, Accurate, Range, Traceable). To get more information, see various trade organizations (ASHRAE, ISPE, etc.). Tried and tested Commissioning approaches and documents are available. But mostly, learn by doing it! References i Pharmaceutical Engineering Guides for New and Renovated Facilities Volume 5 Commissioning and Qualification ii Ibid iii Ibid Page 13 of 13

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY

Guide Specification SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY SECTION 23 08 00 - COMMISSIONING OF HVAC PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. HVAC Commissioning description. 2. HVAC Commissioning responsibilities. 1.2 REFERENCES A. American Society

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

COMMISSIONING OF FIRE ALARM SYSTEMS

COMMISSIONING OF FIRE ALARM SYSTEMS COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012)

Commissioning Plan Preparation Guide. Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) Commissioning Plan Preparation Guide Version 2.0 (Replaces Project Test Plans Preparation Guide, Version 1.0, September 2012) September 2013 Commissioning Plan Preparation Guide Contents 1.0 Introduction...

More information

Design Guidelines for Facilities Construction:

Design Guidelines for Facilities Construction: Engineering Division Facilities Management Department Design Guidelines for Facilities Construction: DESIGN GUIDELINE DG01-9 General Commissioning Requirements Part 1 - GENERAL 1.1 SUMMARY A. Section includes

More information

R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document.

R000. Revision Summary Revision Number Date Description of Revisions R000 Feb. 18, 2011 Initial issue of the document. 2 of 34 Revision Summary Revision Number Date Description of Revisions Initial issue of the document. Table of Contents Item Description Page 1. Introduction and Purpose... 5 2. Project Management Approach...

More information

Computer-Aided Facilities Management - A Logical Trend

Computer-Aided Facilities Management - A Logical Trend Computer-Aided Facilities Management - A Logical Trend Two major organisational changes are part of the modern pharmaceutical industry scene. Firstly, mergers as companies seek to consolidate resources

More information

Testing Automated Manufacturing Processes

Testing Automated Manufacturing Processes Testing Automated Manufacturing Processes (PLC based architecture) 1 ❶ Introduction. ❷ Regulations. ❸ CSV Automated Manufacturing Systems. ❹ PLCs Validation Methodology / Approach. ❺ Testing. ❻ Controls

More information

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan)

ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) ISO 9001: 2008 Construction Quality Management System Sample - Selected pages (not a complete plan) Part 1: Project-Specific Quality Plan Part 2: Company Quality Manual Part 3: Submittal Forms Part 4:

More information

pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2007 management for development series The Project Management Processes PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage

More information

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK

Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services PROJECT MANAGEMENT METHODOLOGY FRAMEWORK Facility Services Project Management Methodology Framework 1 - Executive Summary The purpose of this document is to introduce the University community

More information

Risk-Based Validation of Computer Systems Used In FDA-Regulated Activities

Risk-Based Validation of Computer Systems Used In FDA-Regulated Activities September 2, 2003 Risk-Based Validation of Computer Systems Used In FDA-Regulated Activities Purpose This document provides a summary of the requirements relating to use of computer-based systems in activities

More information

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary

Statement of Work. 3.0 Details of Service Pre Start-up. - 1 - Cooling Start-up Service. Installation Service. Table of Contents. 1.0 Executive Summary Installation Service Statement of Work - 1 - Cooling Start-up Service Cooling Start-up Service Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits 3.0 Details

More information

Monitoring manufacturing, production and storage environments in the pharmaceutical industry

Monitoring manufacturing, production and storage environments in the pharmaceutical industry Application Description AD/RandC/005-EN Monitoring manufacturing, production and storage environments in the pharmaceutical industry - Provides independent verification and validation of the manufacture,

More information

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2016 management for development series Project Scope Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Experience and Qualifications of PROCESS PLANTS CORPORATION

Experience and Qualifications of PROCESS PLANTS CORPORATION Experience and Qualifications of PROCESS PLANTS CORPORATION Table of Contents Section 1. Project Services pg 3-20 Engineering Services Project management Design engineering Design management Construction

More information

PROJECT MANAGEMENT BASICS

PROJECT MANAGEMENT BASICS PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the

More information

Classification and Qualification STANDARDS

Classification and Qualification STANDARDS Classification and Qualification STANDARDS HVAC Series Classification Title Class Code Date Established Date Revised Operating Engineer Building Service Engineer Air Conditioning/Refrigeration Mechanic

More information

Overview of Medical Device Design Controls in the US. By Nandini Murthy, MS, RAC

Overview of Medical Device Design Controls in the US. By Nandini Murthy, MS, RAC Overview of Medical Device Controls in the US By Nandini Murthy, MS, RAC 18 controls are a regulatory requirement for medical devices. In the US, compliance with the design controls section of 21 Code

More information

www.itilhelp.com ISO 9000 Quality Standard Background Information Quality Systems Implementation

www.itilhelp.com ISO 9000 Quality Standard Background Information Quality Systems Implementation ISO 9000 Quality Standard Background Information www.itilhelp.com There is a worldwide trend towards more stringent customer expectations with regard to quality. Accompanying this trend has been a growing

More information

OPERATIONAL STANDARD

OPERATIONAL STANDARD 1 of 11 1. Introduction The International Safe Transit Association (ISTA), a non-profit association whose objective is to prevent product damage and excess packaging usage within the distribution environment.

More information

P3M3 Portfolio Management Self-Assessment

P3M3 Portfolio Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction

More information

Construction Management Standards of Practice

Construction Management Standards of Practice Construction Management Standards of Practice 2010 Edition Advancing Professional Construction/ Program Management Worldwide. 7926 Jones Branch Drive, Suite 800 McLean, VA 22102-3303 USA 703.356.2622 703.356.6388

More information

Conducting a Gap Analysis on your Change Control System. Presented By Miguel Montalvo, President, Expert Validation Consulting, Inc.

Conducting a Gap Analysis on your Change Control System. Presented By Miguel Montalvo, President, Expert Validation Consulting, Inc. Conducting a Gap Analysis on your Change Control System Presented By Miguel Montalvo, President, Expert Validation Consulting, Inc. Standards, Regulations, Guidelines related to Change Control Management

More information

Minnesota Health Insurance Exchange (MNHIX)

Minnesota Health Insurance Exchange (MNHIX) Minnesota Health Insurance Exchange (MNHIX) 1.2 Plan September 21st, 2012 Version: FINAL v.1.0 11/9/2012 2:58 PM Page 1 of 87 T A B L E O F C O N T E N T S 1 Introduction to the Plan... 12 2 Integration

More information

Particle Monitoring Requirements in Pharmaceutical Cleanrooms

Particle Monitoring Requirements in Pharmaceutical Cleanrooms Particle Monitoring Requirements in Pharmaceutical Cleanrooms All drugs must be manufactured in accordance with the current Good Manufacturing Practice (cgmp) regulations. Pharmaceutical manufacturers

More information

Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents

Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents Haulsey Engineering, Inc. Quality Management System (QMS) Table of Contents 1.0 Introduction 1.1 Quality Management Policy and Practices 2.0 Quality System Components 2.1 Quality Management Plans 2.2 Quality

More information

On-Site GMP Training GMP COMPLIANCE TECHNICAL

On-Site GMP Training GMP COMPLIANCE TECHNICAL PharmaNet On-Site GMP Training GMP COMPLIANCE TECHNICAL 284 E Lake Mead Pkwy Suite C-278 Henderson, NV 89015 Phone: 702-558-0094 Fax: 702-558-0079 www.gmpseminars.com Key to Level of Program Level A: Program

More information

COMPLIANCE BY DESIGN FOR PHARMACEUTICAL QUALITY CONTROL LABORATORIES INSIGHT FROM FDA WARNING LETTERS

COMPLIANCE BY DESIGN FOR PHARMACEUTICAL QUALITY CONTROL LABORATORIES INSIGHT FROM FDA WARNING LETTERS COMPLIANCE BY DESIGN FOR PHARMACEUTICAL QUALITY CONTROL LABORATORIES INSIGHT FROM FDA WARNING LETTERS Primer CONTENTS INTRODUCTION...3 QUALITY AND COMPLIANCE IN QUALITY CONTROL LABORATORIES...5 Compliance

More information

Hazard Analysis and Critical Control Points (HACCP) 1 Overview

Hazard Analysis and Critical Control Points (HACCP) 1 Overview Manufacturing Technology Committee Risk Management Working Group Risk Management Training Guides Hazard Analysis and Critical Control Points (HACCP) 1 Overview Hazard Analysis and Critical Control Point

More information

GMP ANNEX 1 REVISION 2008, INTERPRETATION OF MOST IMPORTANT CHANGES FOR THE MANUFACTURE OF STERILE MEDICINAL PRODUCTS

GMP ANNEX 1 REVISION 2008, INTERPRETATION OF MOST IMPORTANT CHANGES FOR THE MANUFACTURE OF STERILE MEDICINAL PRODUCTS PHARMACEUTICAL INSPECTION CONVENTION PHARMACEUTICAL INSPECTION CO-OPERATION SCHEME PI 032-2 8 January 2010 RECOMMENDATION GMP ANNEX 1 REVISION 2008, INTERPRETATION OF MOST IMPORTANT CHANGES FOR THE MANUFACTURE

More information

Denver International Airport Data Center Commissioning Plan

Denver International Airport Data Center Commissioning Plan Denver International Airport Data Center Jefferson County School District Columbine High School Renovation Date July 25th, 2014 Prepared by Patrick Corrigan, QCxP Commissioning Engineer McKinstry McKINSTRY

More information

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE

PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE PROJECT MANAGEMENT METHODOLOGY SECTION 3 -- PLANNING PHASE Table of Contents Introduction...3-1 Overview...3-1 The Process and the Project Plan...3-1 Project Objectives and Scope...3-1 Work Breakdown Structure...3-1

More information

Using the ISPE s GAMP Methodology to Validate Environmental Monitoring System Software

Using the ISPE s GAMP Methodology to Validate Environmental Monitoring System Software Using the ISPE s GAMP Methodology to Validate Environmental Monitoring System Software TEST DOCUMENTS DETAILED DOCUMENTS FUNCTIONAL SPECS USER REQUIREMENTS Introduction Continuous Monitoring Systems (CMS)

More information

QUESTIONS TO ASK WHEN REPLACING YOUR HVAC TOGETHERWESAVE.COM

QUESTIONS TO ASK WHEN REPLACING YOUR HVAC TOGETHERWESAVE.COM QUESTIONS TO ASK WHEN REPLACING YOUR HVAC TOGETHERWESAVE.COM TOGETHERWESAVE.COM IS IT TIME TO REPLACE YOUR HVAC SYSTEM? If your heating and cooling system is 15 to 20 years old and is experiencing problems,

More information

Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc.

Your Software Quality is Our Business. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. INDEPENDENT VERIFICATION AND VALIDATION (IV&V) WHITE PAPER Prepared by Adnet, Inc. February 2013 1 Executive Summary Adnet is pleased to provide this white paper, describing our approach to performing

More information

How to Survive an FDA Computer Validation Audit

How to Survive an FDA Computer Validation Audit How to Survive an FDA Computer Validation Audit The Myth Within the pharmaceutical, biotech, and medical device industry there is much fear and concern over approaching FDA audits. The FDA strikes fear

More information

Impact Assessment in a Science & Risk Based Environment. R. Legland 11/04/11

Impact Assessment in a Science & Risk Based Environment. R. Legland 11/04/11 Impact Assessment in a Science & Risk Based Environment R. Legland 11/04/11 Background US GMP s EU GMP s Japan GMP s ICH Q8, Q9, Q10 Guidance ASTM Standard E2500-07 Science and Risk Based Approach to Determine

More information

Quality System: Design Control Procedure - Appendix

Quality System: Design Control Procedure - Appendix Quality System: Design Control Procedure - Appendix Page 1 of 10 Quality System: Design Control Procedure - Appendix CORP Medical Products Various details have been removed, indicated by [ ] 1. Overview

More information

Design, Construction, Commission, and Qualification of Critical Utility Systems: Part III

Design, Construction, Commission, and Qualification of Critical Utility Systems: Part III Design, Construction, Commission, and Qualification of Critical Utility Systems: Part III BY DAVID W. VINCENT AND HERBERT MATHESON HEATING, VENTILATION, AND AIR CONDITIONING (HVAC) SYSTEMS INTRODUCTION

More information

LIBRARY PLANNING. Every library shall develop, prepare and be guided by a long-range plan. (Planning for Library Excellence Revised [Draft])

LIBRARY PLANNING. Every library shall develop, prepare and be guided by a long-range plan. (Planning for Library Excellence Revised [Draft]) LIBRARY PLANNING Planning is the deliberate, preferred manner of preparing for library service in the future. It is the responsible means of fulfilling future community library needs. A long-range plan,

More information

Energy Management. System Short Guides. A Supplement to the EPA. Guidebook for Drinking Water and Wastewater Utilities (2008)

Energy Management. System Short Guides. A Supplement to the EPA. Guidebook for Drinking Water and Wastewater Utilities (2008) Energy Management System Short Guides A Supplement to the EPA Energy Management Guidebook for Drinking Water and Wastewater Utilities (2008) PREPARED BY GLOBAL ENVIRONMENT & TECHNOLOGY FOUNDATION (A 501(C)(3)

More information

Commissioning Your Data Center for Greater Availability, Safety and Efficiency While Reducing Costs Throughout the Life Cycle

Commissioning Your Data Center for Greater Availability, Safety and Efficiency While Reducing Costs Throughout the Life Cycle A White Paper from the Experts in Business-Critical Continuity TM Commissioning Your Data Center for Greater Availability, Safety and Efficiency While Reducing Costs Throughout the Life Cycle Executive

More information

unless the manufacturer upgrades the firmware, whereas the effort is repeated.

unless the manufacturer upgrades the firmware, whereas the effort is repeated. Software Validation in Accredited Laboratories A Practical Guide Gregory D. Gogates Fasor Inc., 3101 Skippack Pike, Lansdale, Pennsylvania 19446-5864 USA g.gogates@ieee.org www.fasor.com Abstract Software

More information

How many times have each of us asked ourselves if

How many times have each of us asked ourselves if EST.02 Transforming Historical Project Data into Useful Information Todd W. Pickett, CCC and Bruce G. Elliott, CCC How many times have each of us asked ourselves if I only had the chance to do that over

More information

Commercial Manufacturing - Qualification & Validation-related GMP Deficiencies and Other Lifecycle Considerations

Commercial Manufacturing - Qualification & Validation-related GMP Deficiencies and Other Lifecycle Considerations Commercial Manufacturing - Qualification & Validation-related GMP Deficiencies and Other Lifecycle Considerations Kevin O Donnell PhD Market Compliance Manager, IMB PDA / FDA Conference Pharmaceutical

More information

Information Technology Project Oversight Framework

Information Technology Project Oversight Framework State of California California Technology Agency Information Technology Project Oversight Framework SIMM Section 45 Revised April 2011 This Page Intentionally Left Blank California Technology Agency Table

More information

Improved Utilization of Self-Inspection Programs within the GMP Environment A Quality Risk Management Approach

Improved Utilization of Self-Inspection Programs within the GMP Environment A Quality Risk Management Approach Improved Utilization of Self-Inspection Programs within the GMP Environment A Quality Risk Management Approach Barbara Jeroncic Self-inspection is a well-established and vital part of the pharmaceutical

More information

Great Lakes National Program Office and Office of Water Quality Management Training Modules

Great Lakes National Program Office and Office of Water Quality Management Training Modules GLOSSARY Assessment - the evaluation process used to measure the performance or effectiveness of a system and its elements. As used here, assessment is an all-inclusive term used to denote any of the following:

More information

Manage Deliverables - Construction Step 6. July 12, 2012

Manage Deliverables - Construction Step 6. July 12, 2012 Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

What methods are used to conduct testing?

What methods are used to conduct testing? What is testing? Testing is the practice of making objective judgments regarding the extent to which the system (device) meets, exceeds or fails to meet stated objectives What the purpose of testing? There

More information

Top 10 Mistakes in Data Center operations:

Top 10 Mistakes in Data Center operations: Top 10 Mistakes in Data Center operations: Operating Efficient and Effective Data Centers By Lee Kirby Vice President, Business Development and Strategic Accounts Lee Technologies Top 10 Mistakes in Data

More information

SOFTWARE-IMPLEMENTED SAFETY LOGIC Angela E. Summers, Ph.D., P.E., President, SIS-TECH Solutions, LP

SOFTWARE-IMPLEMENTED SAFETY LOGIC Angela E. Summers, Ph.D., P.E., President, SIS-TECH Solutions, LP SOFTWARE-IMPLEMENTED SAFETY LOGIC Angela E. Summers, Ph.D., P.E., President, SIS-TECH Solutions, LP Software-Implemented Safety Logic, Loss Prevention Symposium, American Institute of Chemical Engineers,

More information

6500m HOV Project Stage 1: A-4500 HOV

6500m HOV Project Stage 1: A-4500 HOV 6500m HOV Project Stage 1: A-4500 HOV Systems Engineering, Integration & Testing Plan Document Control No.: 0000000 01-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control

More information

May 2005 Lear Corporation For use by Lear Corporation and its Suppliers only. Copies or reproduction for any other purpose is permitted only by prior

May 2005 Lear Corporation For use by Lear Corporation and its Suppliers only. Copies or reproduction for any other purpose is permitted only by prior ISO 14001:2004 Implementation Workbook For Facilities and Suppliers May 2005 Lear Corporation For use by Lear Corporation and its Suppliers only. Copies or reproduction for any other purpose is permitted

More information

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning

CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning CAN/ULC S1001-11 Integrated Systems Testing of Fire Protection and Life Safety Systems and Fire Protection Commissioning Presentation To: Canadian Fire Alarm Association (CFAA) Alberta Technical Seminar

More information

Annex 7 Application of Hazard Analysis and Critical Control Point (HACCP) methodology to pharmaceuticals

Annex 7 Application of Hazard Analysis and Critical Control Point (HACCP) methodology to pharmaceuticals World Health Organization WHO Technical Report Series, No. 908, 2003 Annex 7 Application of Hazard Analysis and Critical Control Point (HACCP) methodology to pharmaceuticals 1. Introduction Traditionally,

More information

A Guide to Renovation and Repair Contract Warranties

A Guide to Renovation and Repair Contract Warranties A Guide to Renovation and Repair Contract Warranties By Gerald A. Dalrymple, PE A fter being retained to review the merits of several major disputes involving the scope of warranties in renovation and

More information

Quality Management System Manual Revision L

Quality Management System Manual Revision L This Page 1 of 35 of the Quality Management System Manual If issued as a controlled copy, the serial number of this copy is Quality Management System Manual Certified to AS9100 Revision C Printed copies

More information

SECTION 15950 - TESTING, ADJUSTING, AND BALANCING

SECTION 15950 - TESTING, ADJUSTING, AND BALANCING SECTION 15950 - TESTING, ADJUSTING, AND BALANCING PART 1 - GENERAL 1.1 RELATED DOCUMENTS Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification

More information

If a heating, ventilating and air conditioning contractor s bid is too good to believe, don t..

If a heating, ventilating and air conditioning contractor s bid is too good to believe, don t.. If a heating, ventilating and air conditioning contractor s bid is too good to believe, don t.. 5 Q U E S T I O N S A S A V V Y C O N S U M E R S H O U L D A S K. Ask the right questions before you sign

More information

White Paper. Life Sciences Industry Solution Blueprint for Environmental Monitoring Systems (EMS) ISPE Guidance and Best Practices.

White Paper. Life Sciences Industry Solution Blueprint for Environmental Monitoring Systems (EMS) ISPE Guidance and Best Practices. White Paper Life Sciences Industry Solution Blueprint for Environmental Monitoring Systems (EMS) Author: Roberto Zerbi, Global Industries Solutions Life Sciences, Invensys What s Inside: 1. Introduction

More information

ACG COMMISSIONING GUIDELINE. For Building Owners, Design Professionals and Commissioning Service Providers

ACG COMMISSIONING GUIDELINE. For Building Owners, Design Professionals and Commissioning Service Providers ACG COMMISSIONING GUIDELINE For Building Owners, Design Professionals and Commissioning Service Providers ACG COMMISSIONING GUIDELINE For Building Owners, Design Professionals and Commissioning Service

More information

Audit of Contract Management Practices in the Common Administrative Services Directorate (CASD)

Audit of Contract Management Practices in the Common Administrative Services Directorate (CASD) Audit of Contract Management Practices in the Common Administrative Services Directorate (CASD) AUDIT REPORT Prepared for NSERC (Natural Sciences and Engineering Research Council) and SSHRC (Social Science

More information

Compact Monitoring Technology your environmental monitoring solution

Compact Monitoring Technology your environmental monitoring solution Compact Monitoring Technology your environmental monitoring solution Monitor your GxP environmental parameters and cut your validation costs. Solutions for Life Science and Hospitals www.siemens.com/cmt

More information

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects

Best Practices Statement Project Management. Best Practices for Managing State Information Technology Projects State of Arkansas Office of Information Technology 124 W. Capitol Ave. Suite 990 Little Rock, AR 72201 501.682.4300 Voice 501.682.4020 Fax http://www.cio.arkansas.gov/techarch Best Practices Statement

More information

Project Management Plan for

Project Management Plan for Project Management Plan for [Project ID] Prepared by: Date: [Name], Project Manager Approved by: Date: [Name], Project Sponsor Approved by: Date: [Name], Executive Manager Table of Contents Project Summary...

More information

Why Use Software for Calibration Management? Calibration White Paper. Beamex. INCLUDES CUSTOMER CASE STORY: Heineken España A.S.

Why Use Software for Calibration Management? Calibration White Paper. Beamex. INCLUDES CUSTOMER CASE STORY: Heineken España A.S. Beamex Calibration White Paper info@beamex.com Why Use Software for Calibration Management? INCLUDES CUSTOMER CASE STORY: Heineken España A.S. Calibration management software can benefit all sizes of process

More information

The Need for a Systems Engineering Approach For Measuring and Predicting the Degradation of Aging Systems And How It Can Be Achieved

The Need for a Systems Engineering Approach For Measuring and Predicting the Degradation of Aging Systems And How It Can Be Achieved The Need for a Systems Engineering Approach For Measuring and Predicting the Degradation of Aging Systems And How It Can Be Achieved William Robinson Gisele Welch Gary O Neill Georgia Tech Research Institute

More information

R214 SPECIFIC REQUIREMENTS: INFORMATION TECHNOLOGY TESTING LABORATORY ACCREDITATION PROGRAM

R214 SPECIFIC REQUIREMENTS: INFORMATION TECHNOLOGY TESTING LABORATORY ACCREDITATION PROGRAM The American Association for Laboratory Accreditation Document Revised: R214: Specific Requirements: Information Technology Testing Laboratory Accreditation July 13, 2010 Program Page 1 of 26 R214 SPECIFIC

More information

How To Decommission A Nuclear Plant

How To Decommission A Nuclear Plant International Atomic Energy Agency Decommissioning of Nuclear Facilities Management of Decommissioning Projects Lawrence E. Boing Manila, Philippines, October 2006 1 Lesson Objectives Understand the management

More information

10 common GMP challenges facing Maintenance departments in pharmaceutical plants

10 common GMP challenges facing Maintenance departments in pharmaceutical plants 10 common GMP challenges facing Maintenance departments in pharmaceutical plants This white paper lists the GMP compliance problems often seen within the maintenance departments of pharmaceutical operations.

More information

FMC Technologies Measurement Solutions Inc.

FMC Technologies Measurement Solutions Inc. Table of Contents 1 Revision History... 4 2 Company... 5 2.1 Introduction... 5 2.2 Quality Policy... 6 2.3 Quality Organization... 6 2.4 Company Processes... 7 3 Scope and Exclusions... 8 3.1 Scope...

More information

MONTGOMERY COLLEGE JOB CLASS SPECIFICATION

MONTGOMERY COLLEGE JOB CLASS SPECIFICATION MONTGOMERY COLLEGE JOB CLASS SPECIFICATION Title: Project Manager I (Facilities) Grade: J FLSA: Nonexempt Financial Disclosure: No Job Class Level: This includes performance level positions in the Project

More information

NABL NATIONAL ACCREDITATION

NABL NATIONAL ACCREDITATION NABL 160 NABL NATIONAL ACCREDITATION BOARD FOR TESTING AND CALIBRATION LABORATORIES GUIDE for PREPARING A QUALITY MANUAL ISSUE NO. : 05 AMENDMENT NO : 00 ISSUE DATE: 27.06.2012 AMENDMENT DATE: -- Amendment

More information

Professional Engineers Using Software-Based Engineering Tools

Professional Engineers Using Software-Based Engineering Tools GUIDELINE Professional Engineers Using Software-Based Engineering Tools CONTRIBUTORS Eric Brown, P. Eng. Colin Cantlie, P. Eng. Norm Fisher, P. Eng. Jeremy Jackson, P. Eng. Tibor Palinko, P. Eng. Daniel

More information

H.V.A.C. Design Plumbing Design

H.V.A.C. Design Plumbing Design H.V.A.C. Design H.V.A.C. Design Mira Costa College Arts Complex CP Upgrade 1. PART 1 GENERAL 1.1. DESCRIPTION SECTION 23 09 00 HVAC INSTRUMENTATION AND CONTROL 2. PART 2 - PRODUCTS 2.1. Materials

More information

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment

Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire

More information

PHARMACEUTICAL TRAINING GUIDELINE

PHARMACEUTICAL TRAINING GUIDELINE PHARMACEUTICAL TRAINING GUIDELINE 5850 Boymel Dr. Suite 1 Fairfield, OH 45014 Tel.: 513.860.3512 Fax: 513.860.3406 www.compliance-insight.com Reorder Item No. 20.020.2 PHARMACEUTICAL TRAINING GUIDELINE

More information

Project Management Guidelines

Project Management Guidelines Project Management Guidelines 1. INTRODUCTION. This Appendix (Project Management Guidelines) sets forth the detailed Project Management Guidelines. 2. PROJECT MANAGEMENT PLAN POLICY AND GUIDELINES OVERVIEW.

More information

1.0 INTRODUCTION 1.1 Overview

1.0 INTRODUCTION 1.1 Overview Guidance document for the writing of standard operating procedures (Taken from United States Environmental Protection Agency Guidance for Preparing Standard Operating Procedures (SOPs) EPA QA/G- 6 [EPA/600/B-

More information

WHEN YOU CONSULT A STATISTICIAN... WHAT TO EXPECT

WHEN YOU CONSULT A STATISTICIAN... WHAT TO EXPECT WHEN YOU CONSULT A STATISTICIAN... WHAT TO EXPECT SECTION ON STATISTICAL CONSULTING AMERICAN STATISTICAL ASSOCIATION 2003 When you consult a statistician, you enlist the help of a professional who is particularly

More information

CORPORATE QUALITY MANUAL

CORPORATE QUALITY MANUAL Corporate Quality Manual Preface The following Corporate Quality Manual is written within the framework of ISO 9001:2008 Quality System by the employees of CyberOptics. CyberOptics recognizes the importance

More information

GOOD DOCUMENTATION AND QUALITY MANAGEMENT PRINCIPLES. Vimal Sachdeva Technical Officer (Inspector), WHO Prequalification of Medicines Programme

GOOD DOCUMENTATION AND QUALITY MANAGEMENT PRINCIPLES. Vimal Sachdeva Technical Officer (Inspector), WHO Prequalification of Medicines Programme GOOD DOCUMENTATION AND QUALITY MANAGEMENT PRINCIPLES Vimal Sachdeva Technical Officer (Inspector), WHO Prequalification of Medicines Programme Contents 1. Why good documentation is essential? 2. What constitutes

More information

A Stability Program for the Distribution of Drug Products

A Stability Program for the Distribution of Drug Products A Stability Program for the Distribution of Drug Products Teresa I. Lucas*, Rafik H. Bishara, and Robert H. Seevers Drug products must be transported in a manner that ensures products will be maintained

More information

Selecting a Product Data Management System

Selecting a Product Data Management System Selecting a System "The product data management selection process requires planning, consideration, and commitment." Ed Miller, President of CIMdata, Inc. Software Do you know what it takes to select a

More information

CHAPTER 4 TYPES OF COST ESTIMATES

CHAPTER 4 TYPES OF COST ESTIMATES CHAPTER 4 TYPES OF COST ESTIMATES 1. INTRODUCTION All projects, both construction and environmental restoration, require cost estimates to plan and budget the project efficiently. Numerous estimates are

More information

Project Execution Planning: The Key to Successful Pharmaceutical Project Delivery

Project Execution Planning: The Key to Successful Pharmaceutical Project Delivery Reprinted from PHARMACEUTICAL ENGINEERING THE OFFICIAL TECHNICAL MAGAZINE OF ISPE MARCH/APRIL 2014, VOL 34, NO 2 Copyright ISPE 2014 www.pharmaceuticalengineering.org facilities and equipment : The Key

More information

Quality Management System Manual

Quality Management System Manual Quality Management System Manual This manual has been reviewed and approved for use by: Jack Zazulak President, Aurora Machine Limited March 07, 2011 Date - Copyright Notice - This document is the exclusive

More information

Using ISO 15489 as an Audit Tool

Using ISO 15489 as an Audit Tool Using ISO 15489 as an Audit Tool ISO 15489, the first international standard devoted to records management, provides a comprehensive and practical basis for auditing full and partial records management

More information

<name of project> Software Project Management Plan

<name of project> Software Project Management Plan The document in this file is adapted from the IEEE standards for Software Project Management Plans, 1058-1998, which conforms to the requirements of ISO standard 12207 Software Life Cycle Processes. Tailor

More information

Volume II- Project Development Processes

Volume II- Project Development Processes Volume II- Project Development Processes This section outlines the procedures that are expected of capital projects at The University of Chicago. These requirements supplement the planning procedures required

More information

FIX-RIGHT USER S GUIDE

FIX-RIGHT USER S GUIDE FIX-RIGHT FLAT RATE REPAIR PRICE BOOK FIX-RIGHT USER S GUIDE HELPING CONTRACTORS ACHIEVE SUCCESS AND PROFITABILITY! Since we began using flat rate pricing, no technician who worked with it wanted to go

More information

How To Use A Court Record Electronically In Idaho

How To Use A Court Record Electronically In Idaho Idaho Judicial Branch Scanning and Imaging Guidelines DRAFT - October 25, 2013 A. Introduction Many of Idaho s courts have considered or implemented the use of digital imaging systems to scan court documents

More information

DOCUMENT SCANNING SERVICES

DOCUMENT SCANNING SERVICES REQUEST FOR PROPOSAL FOR DOCUMENT SCANNING SERVICES ISSUING OFFICE RECORDS IMPROVEMENT COMMITTEE OF COUNTY OF FRANKLIN, PA RFP NUMBER 2015172-3 DATE OF ISSUANCE MARCH 23, 2015 CONTENTS I. INTRODUCTION

More information

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES

NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES NEBB STANDARDS SECTION-8 AIR SYSTEM TAB PROCEDURES 8.1 INTRODUCTION Testing, adjusting, and balancing of HVAC systems can best be accomplished by following a series of systematic procedures. The NEBB TAB

More information